Belfast Hotel Project
• 141 Bedrooms
• 15 VRF 3-Pipe Systems
• 151 Indoor Units
• Total Installed Capacity – 398 kW
• Site time – 16 Weeks
Design Stage• Design Calculations - Cymap• Indoor Unit Type• System Capacities• Pipe runs and piping restrictions
Site Drawings
5-Year Peace of Mind Warranty
• Design criteria met with regard to horizontal and vertical pipe runs
• Validated pressure tests and evacuation procedures
• Calculated refrigerant added to system
• Detailed commissioning reports by certified engineer returned to Toshiba
• Maintenance contract in place with an Accredited Installer
• 5-Year parts and labour warranty with manufacturer not contractor
Manufacturers Warranty