Transcript
Page 1: Belfast Hotel Project

Belfast Hotel Project

• 141 Bedrooms

• 15 VRF 3-Pipe Systems

• 151 Indoor Units

• Total Installed Capacity – 398 kW

• Site time – 16 Weeks

Page 2: Belfast Hotel Project

Design Stage• Design Calculations - Cymap• Indoor Unit Type• System Capacities• Pipe runs and piping restrictions

Page 3: Belfast Hotel Project

Site Drawings

Page 4: Belfast Hotel Project
Page 5: Belfast Hotel Project

5-Year Peace of Mind Warranty

• Design criteria met with regard to horizontal and vertical pipe runs

• Validated pressure tests and evacuation procedures

• Calculated refrigerant added to system

• Detailed commissioning reports by certified engineer returned to Toshiba

• Maintenance contract in place with an Accredited Installer

• 5-Year parts and labour warranty with manufacturer not contractor

Page 6: Belfast Hotel Project

Manufacturers Warranty


Top Related