Arab Brothers Ltd. Creativity Beyond Expectationswww.a-brothers.com
15
The Construction of YATTA Reservoir 2004/2005
Yatta City/ Hebron/West Bank/Palestine. Location
Construction of Main Pipeline and RC reservoir for Yatta Project
ARD/USAID Client
Arab Brothers Company Contractor
2004 Start Date
2005 Completion Date
580,000 USD Value of ProjectCircular Reservoir Reservoir Shape2000 M3 Reservoir SizeSub Contractor Role in Contract
The Construction of DURA Reservoir 2006/2007
Dura City/ Hebron/West Bank/Palestine. Location
Construction of Halhul Dura Yatta Water System Project
El Concorde, WBWD, AFD Client
Arab Brothers Company Contractor
2006 Start Date
2007 Completion Date
700,000 Euro Value of ProjectRectangular Reservoir Reservoir Shape5000 M3 Reservoir SizeSub Contractor Role in Contract
The Construction of KHARAS Reservoir 2006/2007
Kharas/ Hebron/West Bank/Palestine. Location
Kharas Water System Project Project
Palestine Water Authority, World Bank Client
Arab Brothers Company Contractor
2006 Start Date
2007 Completion Date
265000 USD Value of ProjectCircular Reservoir Reservoir Shape1000 M3 Reservoir SizeMain Contractor Role in Contract
The Construction of AQRABA/Majdal Reservoirs 2009
Aqraba & Majdal City/ Nablus/West Bank/Palestine. Location
Construction of Aqraba & Majdal Reservoirs Project
Palestine Water Authority Client
Arab Brothers Company Contractor
2009 Start Date
2009 Completion Date
975,000 USD Value of Project
Both of them Circular Reservoirs Reservoir Shape
Aqraba is 2000 M3 & Majdal is 1500 M3 Reservoir Size
Main Contractor Role in Contract
The Construction of Bureen Reservoir & Bureen Pump Reservoir 2009
Bureen/ Nablus/West Bank/Palestine. Location
INPI-USAID: Burin Water System Project
CDM, USAID, Palestine Water Authority Client
Arab Brothers Company Contractor
2009 Start Date
2009 Completion Date
2,985,000 USD Value of ProjectCircular Reservoirs Reservoir Shape
500 M3 Bureen Reservoir & 300 M3 Bureen Pump Reservoir SizeSubContractor Role in Contract
RESERVOIRS PROJECT (T.O#30)
The project were consist of (6 concrete reservoirs and water transmission systems in west bank) :• Reference No: (No. 294-1-30-08-00221-00)• Funded By:USAID.• Consultant: MWH.• Employer: APCO ARCON.• Owner: Palestine Water Authority.• Contractor: Arab Brothers Company.
Where the Reservoirs as the following:
The Construction of YATTA Reservoir 2010
Yatta/ Hebron/West Bank/Palestine. Location
INPI: USAID: Task Order 30-Reservoirs Project
APCO ARCON, USAID Client
Arab Brothers Company Contractor
2010 Start Date
2011 Completion Date
1,845,000 $ Value of Project
Circular Reservoirs Reservoir Shape
4000 M3 Reservoir Size
Sub Contractor Role in Contract
The Construction of ABU HILAL Reservoir 2010
Dura/ Hebron/West Bank/Palestine. Location
INPI: USAID: Task Order 30-Reservoirs Project
APCO ARCON, USAID Client
Arab Brothers Company Contractor2010 Start Date2010 Completion Date
1,189,000 $ Value of ProjectRectangular Reservoir Reservoir Shape
2000 M3 Reservoir SizeSub Contractor Role in Contract
The Construction of SINJER Reservoir 2010
Singer/ Hebron/West Bank/Palestine. Location
INPI: USAID: Task Order 30-Reservoirs ProjectAPCO ARCON, USAID ClientArab Brothers Company Contractor2010 Start Date2011 Completion Date558,966 $ Value of ProjectRectangular Elevated Reservoirs Reservoir Shape500 M3 Reservoir Size
Sub Contractor Role in Contract
The Construction of EIN SINYA Reservoir 2010
Ein Sinya/ Ramallah/West Bank/Palestine. Location
INPI: USAID: Task Order 30-Reservoirs Project
APCO ARCON, USAID Client
Arab Brothers Company Contractor2010 Start Date2010 Completion Date
616,233 $ Value of ProjectRectangular Reservoir Reservoir Shape
1000 M3 Reservoir SizeSub Contractor Role in Contract
The Construction of ZITA Reservoir 2010
Zeita/ Tulkarem/West Bank/Palestine. Location
INPI: USAID: Task Order 30-Reservoirs ProjectAPCO ARCON, USAID ClientArab Brothers Company Contractor2010 Start Date2011 Completion Date467,277 $ Value of ProjectRectangular Elevated Reservoirs Reservoir Shape500 M3 Reservoir Size
Sub Contractor Role in Contract
The Construction of ALUBAN Reservoir 2010
Alluban/ Nablus/West Bank/Palestine. Location
INPI: USAID: Task Order 30-Reservoirs Sector
APCO ARCON, USAID Project
Arab Brothers Company Contractor2010 Start Date2010 Completion Date
629,083 $ Value of ProjectRectangular Elevated Reservoir Reservoir Shape
500 M3 Reservoir SizeSub Contractor Role in Contract
The Construction of DIER SAMIT Reservoir 2010 /T.O#24
Dier Samit/ Dura/West Bank/Palestine. Location
INPI: USAID: Task Order 30-Reservoirs ProjectAPCO ARCON, USAID ClientArab Brothers Company Contractor2010 Start Date2011 Completion Date447,101 $ Value of ProjectCircular Reservoirs Reservoir Shape2000 M3 Reservoir Size
Sub Contractor Role in Contract
The Construction of SURIF Reservoir 2012
Surif/ Hebron/West Bank/Palestine. Location
Construction of water system, and RC reservoir Project
Palestine water Authority Client
Arab Brothers Company Contractor2012 Start Date2012 Completion Date
1,500,350 € Value of ProjectCircular Reservoir Reservoir Shape
2000 M3 Reservoir SizeMain Contractor Role in Contract