dot hearings: pti and ptno application 10 september 2013
DESCRIPTION
DOT HEARINGS: PTI AND PTNO APPLICATION 10 SEPTEMBER 2013. PRESENTATION OVERVIEW. Executive Summary Polokwane IRPTS Current c ontext and r esponse Full network d esign Transit oriented land use Institutional arrangements with Province - PowerPoint PPT PresentationTRANSCRIPT
DOT HEARINGS: PTI AND PTNO APPLICATION10 SEPTEMBER 2013
PRESENTATION OVERVIEW1. Executive Summary 2. Polokwane IRPTS
• Current context and response• Full network design• Transit oriented land use• Institutional arrangements with Province• Management capacity, political support and
stakeholder buy-in
3. 2012/13 Progress and Spending• PTI allocations, rollover and spending
4. 2013/14 Progress and Spending• Current year progress on spending
5. Plans for 2014 MTEF• Worst-case scenario• Best case scenario
POLOKWANE: CITY OF THE STARS
THE DUAL APPROACH
Phase 1 &2 – Intervention Focus:• High quality public transport system facilitated by dedicated infrastructure• Regenerate the CBD • High density development• Promote spatial in-filling
Phase 2
Phase 1
Phase 3
Phase 4 Phase 3 & 4 – Intervention Focus• Build on current systems• Restructure Public Transport Operational Grant (PTOG) &
achieve industry transformation• Provide reliable, safe, scheduled, public transport• BUT not entrench current spatial and mobility patterns
BRT
High Quality PT
EXCITEMENT IS GROWING
PROJECT CHALLENGES
• More pictures
2010-2011 2011-2012 2012-2013 2013-2014R 0
R 50,000,000
R 100,000,000
R 150,000,000
R 200,000,000
R 250,000,000 Project expenditure
Increase in our institutional
capacity
Projected expenditure
WHY WE ARE HERE
R’m 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
PTI R 199 R456 R261 R211 R299 R171 R148
PTNO R0 R0 R44 R151 R148 R171 R202
TOTAL R199 R456 R301 R362 R447 R342 R350
MTEF
Current 1 2 3 4 5 6 Year
Phase 1: SeshegoPhase 2: Moletji
Phase 3: Mankweng Phase 4: North West/ Koloti
PIRPTS DESCRIPTION
POLOKWANE CURRENT CONTEXT
40km20km
Population: 630 000 Mean Monthly HH Income: R2000
Summary: Low income, mixed density, mixed urban - rural
Large number of rural remote settlements connected by subsidised buses & MBTs
Residential pop. concentration in NW (10km - 20km out)
Fast growing urban area with strong CBD
POLOKWANE CURRENT CONTEXT
Public transport provides an opportunity to address our urban and spatial planning
challenges
THE DUAL APPROACH
Phase 1 &2 – Intervention Focus:• High quality public transport system facilitated by
dedicated infrastructure• Regenerate the CBD • High density development• Promote spatial in-filling
Phase 2
Phase 1
Rapid Transit
THE DUAL APPROACH
Phase 3
Phase 4
Phase 3 & 4 – Intervention Focus• Build on current systems• Restructure Public Transport Operational Grant (PTOG) &
achieve industry transformation• Provide reliable, safe, scheduled, public transport• BUT not entrench current spatial and mobility patterns
Restructured Transit
TRANSIT ORIENTED LAND USE
The Dual Approach• Phase 1 & 2: Rapid transit system encourages spatial
infilling between Seshego & CBD• Phase 3: Establishes Mankweng as an economic hub,
while linking it with the CBD• Phase 4: Provides essential service to city
Infilling between Seshego and CBD
Development of stand alone urban hub
Essential services in rural areas
E
Phase 1Phase 2
PIRPTS System Description• Trunk & Trunk Extension Design• 80% of route residential, 54,000hh• 20,000 pax/peak period• 80% of hh within 500m of PIRTN• 4 million vehicle kms/year• 12.5 million passenger trips/year
PHASE 1 & 2 – SYSTEM DESCRIPTION
PIRPTS Vehicles• 151 x solo buses (65 capacity)• 35 x midi buses (25)Total: 186
E
Phase 1
Phase 2
PIRPTS Infrastructure• 12 km trunk lane• 6.6 km of trunk dedicated lane• 7 trunk extensions• 5 feeder routes• 6 trunk stations• Church Street pedestrianized &
dedicated to public transport• 2 Depots
PHASE 1 & 2 - INFRASTRUCTURE
E
B
C
Current Situation•Dual carriage way to CBD• Main access road with increasing congestion
Interventions Explored:• Mixed Traffic (no dedicated lane)• An Off-Peak Contra-Flow Lane• Single Median Bus Way• Two Dedicated Lanes (B to C)• Full trunk dedicated lanes• Full trunk, strengthened
dedicated lanes
Recommendation: Two Dedicated Lanes Travel time advantage A differentiated service Lower enforcement challenges Lower safety risks Lower costs
PHASE 1 & 2 – DEDICATED LANE ASSESSMENT
Design:• Feeders to centralised
Mankweng interchange• Trunk route running to
CBD
PHASE 3 – MANKWENG DESIGN
17
MANKWENG CENTRAL NODE
Focus:• Formalise and integrate
current Mini-Bus Taxi (MBT) & Bus Services
• Use existing vehicles • Offering operational
efficiencies• Improve connectivity,
peak & off-peak availability
• Safe and reliable• Restructuring current
PTOG contracts• Integrated Fare
Management
60 Standard Buses providing 15 000 pax trips per day on Polokwane to Mankweng trunk route.
Design:• Feeders to Koloti Interchange or to
edge of Perskebuilt • Trunk route through running to CBD
To Moletjie
PHASE 4 - NW/KOLOTI DESIGN
Focus:• Formalise and integrate
current Mini-Bus Taxi (MBT) & Bus Services
• Use existing vehicles • Offering operational
efficiencies• Improve connectivity,
peak & off-peak availability
• Safe and reliable• Restructuring current
PTOG contracts• Integrated Fare
Management
Restructure existing 25 Buses + 35 MTB’s to feed into transfer terminal of PIRPTS at Moletjie. Approx. 4500 pax trips per day.
CITY WIDE NMT
Cycle and Pedestrian Networks
Urban Greening
ACCESS DESIGN
• The initial draft Universal Design Access Plan will be available at the end of September.
• Thereafter, a Universal Design Workshop will be held for all team members and stakeholders to introduce the concepts of Universal Design and Accessibility.
• Engagement of local organisations and groups of Passengers with Categories of Special Needs is being planned.
13/14 14/15 15/16 16/17 17/18 18/19 19/20Year 1 2 3 4 5 6 7
IMPLEMENTATION
PIRPTS Full Network
2
Moletjie- CBD3 000 vehicle seats
21 000 pax/day4
North West – CBD5 000 vehicle seats
20 000 pax/day
F
Public Transport Restructuring Stream
Phase 1: Seshego - CBD6 000 vehicle seats
42 000 pax/day
1
3Mankweng - CBD
5 000 vehicle seats 20 000 pax /day
Rapid Transit Stream
13/14 14/15 15/16 16/17 17/18 18/19 19/20Year 1 2 3 4 5 6 7
IMPLEMENTATION
PIRPTS Full Network
2
Moletjie- CBD3 000 vehicle seats
21 000 pax/day4
North West – CBD5 000 vehicle seats
20 000 pax/day
F
Public Transport Restructuring Stream
Phase 1: Seshego - CBD6 000 vehicle seats
42 000 pax/day
1
3
Mankweng - CBD5 000 vehicle seats
20 000 pax /day
Rapid Transit Stream
Dual rollout approach sees parallel implementation of the Rapid Transit system
and the Restructured Public Transport system
13/14 14/15 15/16 16/17 17/18 18/19 19/20Year 1 2 3 4 5 6 7
IMPLEMENTATION
PIRPTS Full Network
2
Moletjie- CBD3 000 vehicle seats
21 000 pax/day4
North West – CBD5 000 vehicle seats
20 000 pax/day
F
Public Transport Restructuring Stream
Phase 1: Seshego - CBD6 000 vehicle seats
42 000 pax/day
1
3
Mankweng - CBD5 000 vehicle seats
20 000 pax /day
Rapid Transit Stream
• Allows for the establishment of the full network, over a relatively short period
• Supports rapid service improvement and delivery to the public
• Facilitates a smooth transformation and transition process with the industry
INSTITUTIONAL ARRANGEMENTS WITH PROVINCE
• Partnership with Provincial government– Agreement on responsibilities for the PIRPTS– To lead to possible Inter-Government
Agreement (IGA)• Significant effects on Great North
Transport (GNT)– Requires restructuring following
introduction of the PIRPTS• Phase 3 and 4 affects 2 private bus
operators contracted to Province (under PTOG subsidy)– The contracts will need to be devolved to
Municipality and restructured• Cooperation around operating licenses
MANAGEMENT CAPACITY AND SUPPORT• PIRPTS Management Unit has been established
– Significant capacity created– Diverse skills sets and background– Supported by strong and capacitated municipal administration
• Strong political buy-in and support– Dedicated political structures – MMC is the IRPTN political champion – Personal attention and priority of Executive Mayor
• Extensive industry engagement – Frequent industry engagements (monthly with each
association)– Provincial leadership structures engaged (ITEEC)– Successful study tour– Industry strongly informed and involved
• A dual approach of technical and institutional -transformation rollout– Lessons from elsewhere in SA that institutional /
transformation issues delay successful rollout
2013/14
2014/15
2015/16
2016/17
2017/18
2018/19
2019/20
2020/21
2021/22
2022/23
2023/24
2024/25
2025/26
R -
R 50,000,000
R 100,000,000
R 150,000,000
R 200,000,000
R 250,000,000
R 300,000,000
R 350,000,000
R 400,000,000
R 450,000,000
R 500,000,000
Municipal Financial Year
CAPITAL COST SUMMARYBus purchases will be financed through debt and repaid with PTI over 5 years
Phase 1 : Seshego Infrastructure build
Phase 2: Moletji Infrastructure build
Phase 3 : Mankweng Infrastructure build
Phase 4: NW Infrastructure build
Vehicle Repayments for Seshego buses & Moletji buses
PIRPTS PROGRESS 2012/13
2011 - 2013 FINANCIAL YEARChallenges» Internal Capacity, Procurement Delays & Late
Appointments, Limited Contract Periods, Project Communications, Under-Expenditure.
» Alignment of Workstreams, Extension of Contracts, Project Office, Under-Expenditure, Terms of Reference limitations.
Resolutions» Establishment of Transportation Directorate, Clear
Project Structure, Project Office, Internal Capacity Building, Contract Extensions,
» Procurement Priority Appointment of Panel of Experts over 5 year period, Annual Performance Review of every Workstreams and annual setting of scope of works, Full commitment of funds.
CHALLENGES & RESOLUTIONS
Workstream Description Progress
Systems & Operational Planning
Technical Operational Plan
Phase 1 & 2 detailed plan Phase 3 & 4 concept plan
Business & Financial Planning
Business and Financial Plan
Detailed full financial model Costs and revenues over 12 years Business structures and contractual arrangements Organizational, capacity and governance requirement
Marketing & Communications
Integrated Marketing and Communications Strategy
Project Brand complete to be approved by Council in June Website and other key branding material
Industry Transition & Engagement
Industry Transformation and Engagement Process
Extensive engagement over past 12 months (local and provincial level)
MOU signed between Municipality and Taxi Associations Highly successful study tour to JHB, NM and CPT completed Bi-Monthly Progress Meeting with General Membership of
the Taxi Industry
InstitutionalEstablishment of the Transportation Directorate
Directorate established and staffed Council approval of TOP and IMCS s33 process completed, s78 Investigation underway Appointment of all required service providers completed
PROJECT TECHNICAL PROGRESS 2012/13
2012/13 PIRPTS FINANCIALS
FINANCE DETAILS 2012/13 R (million)
TOTAL PTI transferred to July 2012 49.070
TOTAL Expenditure to July 2012 14.792
Expenditure % to July 2012 30
2012/13
Rollover requested to 2012/13 34.276
PTI transferred in 2012/13 48.703
TOTAL PTI in 2012/13 82.979TOTAL Expenditure in 2012/13 (incl. commitments) 81.029
Expenditure % in 2012/13 98
2013/14
Rollover requested to 2013/14 40.546
2012/13 PIRPTS FINANCIALS
FINANCE DETAILS 2012/13 R (million)
TOTAL PTI transferred to July 2012 49.070
TOTAL Expenditure to July 2012 14.792
Expenditure % to July 2012 30
2012/13
Rollover requested to 2012/13 34.276
PTI transferred in 2012/13 48.703
TOTAL PTI in 2012/13 82.979TOTAL Expenditure in 2012/13 (incl. commitments) 81.029
Expenditure % in 2012/13 98
2013/14
Rollover requested to 2013/14 40.546
Poor expenditure to July 2012, for various reasons
related to slow start-up on the project
2012/13 PIRPTS FINANCIALS
FINANCE DETAILS 2012/13 R (million)
TOTAL PTI transferred to July 2012 49.070
TOTAL Expenditure to July 2012 14.792
Expenditure % to July 2012 30
2012/13
Rollover requested to 2012/13 34.276
PTI transferred in 2012/13 48.703
TOTAL PTI in 2012/13 82.979TOTAL Expenditure in 2012/13 (incl. commitments) 81.029
Expenditure % in 2012/13 98
2013/14
Rollover requested to 2013/14 40.546
PTI allocation in 2012/13 was R 99m. Municipality requested this allocation be reduced by R 50m to reflect ability to spend
2012/13 PIRPTS FINANCIALS
FINANCE DETAILS 2012/13 R (million)
TOTAL PTI transferred to July 2012 49.070
TOTAL Expenditure to July 2012 14.792
Expenditure % to July 2012 30
2012/13
Rollover requested to 2012/13 34.276
PTI transferred in 2012/13 48.703
TOTAL PTI in 2012/13 82.979TOTAL Expenditure in 2012/13 (incl. commitments) 81.029
Expenditure % in 2012/13 98
2013/14
Rollover requested to 2013/14 40.546
Includes R 40.546m committed funds, to be spent by October 2013
2012/13 PIRPTS FINANCIALS
FINANCE DETAILS 2012/13 R (million)
TOTAL PTI transferred to July 2012 49.070
TOTAL Expenditure to July 2012 14.792
Expenditure % to July 2012 30
2012/13
Rollover requested to 2012/13 34.276
PTI transferred in 2012/13 48.703
TOTAL PTI in 2012/13 82.979TOTAL Expenditure in 2012/13 (incl. commitments) 81.029
Expenditure % in 2012/13 98
2013/14
Rollover requested to 2013/14 40.546
Dramatic improvement in expenditure in 2012/13,
reflecting pro-active steps taken by the municipality
2012/13 PIRPTS FINANCIALS
FINANCE DETAILS 2012/13 R (million)
TOTAL PTI transferred to July 2012 49.070
TOTAL Expenditure to July 2012 14.792
Expenditure % to July 2012 30
2012/13
Rollover requested to 2012/13 34.276
PTI transferred in 2012/13 48.703
TOTAL PTI in 2012/13 82.979TOTAL Expenditure in 2012/13 (incl. commitments) 81.029
Expenditure % in 2012/13 98
2013/14
Rollover requested to 2013/14 40.546
Rollover of committed funds from 2012/13, to be
spent by October 2013.
PIRPTS PROGRESS 2013/14
MILESTONES 2013/14
Designs for the full Ph 1 & 2 be completed by Jan 2014 and the tender for construction be awarded by Mar 2014
ITS, Control Centre & Vehicle Specifications completed by March 2014
Technical Specifications
Full network Business & Financial Plan to be completed by June 2014
Full Network Business Plan
Industry transition engagements across all phases with minibus and bus
industry, negotiations begin June 2014
Negotiations Begin
The PIRTN brand is finalised by June 2014 and official brand launch
Brand Finalization
Designs for Mandela Drive dedicated lane (B to C) to be completed in Nov 2013 and
construction to begin in Mar 2013Mandela Drive
Designs for full Trunk
STAKEHOLDER ENGAGEMENT
EXPENDITURE 2013/14Expenditure item Amount
(R‘m)% of Total Funds
receivedTotal expected expenditure to end June 2014 R 199m 100%
Planning costs R 50m 25%
Detailed Design & Construction R126m 63%
Stakeholder and industry engagement R 23m 12%
EXPENDITURE 2013/14Expenditure item Amount
(R‘m)% of Total Funds
receivedTotal expected expenditure to end June 2014 R 199m 100%
Planning costs R 50m 25%
Detailed Design & Construction R126m 63%
Stakeholder and industry engagement R 23m 12%
COMMITTED FUNDS TO DATE R 198m 99%
Municipality has already committed the full PTI allocation for 2013/14
Achievements in 2013/14
Since July 2013– SLAs signed and funds committed– Technical design underway – Phase 1
& 2– Household survey almost complete– Conceptual design of Phase 3 & 4– Launch of PIRPTS completed– Extensive Industry capacitation
programme in place– Market survey in implementation– Engagements with Province and Bus
companies
PIRPTS PLAN FOR 2014 - 2016 MTEF
WORST CASE SCENARIO
• Worst case scenario = ZERO allocations in 2014/15 and 2015/16
• Unlikely that the project can continue– if outer year funding not secured to keep progress going– Extent of funding received can vary, but PIRPTS is not
viable if zero allocation remains
R’m 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
PTI R 199 R396 R218 R208 R299 R160 R135
PTNO R0 R0 R27 R117 R108 R118 R142
TOTAL R199 R396 R245 R325 R407 R278 R277
BEST CASE SCENARIO: PTI AND PTNOGMTEF
Current 1 2 3 4 5 6 Year
Phase 1: SeshegoPhase 2: Moletji
Phase 3: Mankweng Phase 4: North West/ Koloti
R’m 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
PTI R 199 R396 R218 R208 R299 R160 R135
PTNO R0 R0 R27 R117 R108 R118 R142
TOTAL R199 R396 R245 R325 R407 R278 R277
BEST CASE SCENARIO: PTI AND PTNOGMTEF
Current 1 2 3 4 5 6 Year
Phase 1: SeshegoPhase 2: Moletji
Phase 3: Mankweng Phase 4: North West/ Koloti
Phase 1Trunk, extension and feeder roadway works
Stations and stopsDepots
Control centre
R’m 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
PTI R 199 R396 R218 R208 R299 R160 R135
PTNO R0 R0 R27 R117 R108 R118 R142
TOTAL R199 R396 R245 R325 R407 R278 R277
BEST CASE SCENARIO: PTI AND PTNOGMTEF
Current 1 2 3 4 5 6 Year
Phase 1: SeshegoPhase 2: Moletji
Phase 3: Mankweng Phase 4: North West/ Koloti
Phase 1No PTNO requirements in 2014/15
R’m 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
PTI R 199 R396 R218 R208 R299 R160 R135
PTNO R0 R0 R27 R117 R108 R118 R142
TOTAL R199 R396 R245 R325 R407 R278 R277
BEST CASE SCENARIO: PTI AND PTNOGMTEF
Current 1 2 3 4 5 6 Year
Phase 1: SeshegoPhase 2: Moletji
Phase 3: Mankweng Phase 4: North West/ Koloti
Phase 1Trunk, extension and feeder roadway works
Stations and stopsDepots
Control centreIFM, ITS and Security equipment
R’m 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
PTI R 199 R396 R218 R208 R299 R160 R135
PTNO R0 R0 R27 R117 R108 R118 R142
TOTAL R199 R396 R245 R325 R407 R278 R277
BEST CASE SCENARIO: PTI AND PTNOGMTEF
Current 1 2 3 4 5 6 Year
Phase 1: SeshegoPhase 2: Moletji
Phase 3: Mankweng Phase 4: North West/ Koloti
Phase 1Industry compensation
Entity establishmentVOC establishment
Auxiliary contracts (ITS, IFM)
R’m 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
PTI R 199 R396 R218 R208 R299 R160 R135
PTNO R0 R0 R27 R117 R108 R118 R142
TOTAL R199 R396 R245 R325 R407 R278 R277
BEST CASE SCENARIO: PTI AND PTNOGMTEF
Current 1 2 3 4 5 6 Year
Phase 1: SeshegoPhase 2: Moletji
Phase 3: Mankweng Phase 4: North West/ Koloti
Phase 2Trunk, extension and feeder roadway works
Stations and stopsPhase 1
Principle debt on vehicle fleet
BEST CASE SCENARIO: PTI AND PTNOG
R’m 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
PTI R 199 R396 R218 R208 R299 R160 R135
PTNO R0 R0 R27 R117 R108 R118 R142
TOTAL R199 R396 R245 R325 R407 R278 R277
MTEF
Current 1 2 3 4 5 6 Year
Phase 1: SeshegoPhase 2: Moletji
Phase 3: Mankweng Phase 4: North West/ Koloti
Phase 1Interest on vehicle purchase
Industry compensationEntity establishmentVOC establishment
Auxiliary contracts (ITS, IFM)