don renewable energy programdon renewable energy...

11

Click here to load reader

Upload: lykhuong

Post on 26-Jul-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

DON Renewable Energy ProgramDON Renewable Energy Program

E.C. HoelzerNAVFAC Atlantic Renewable Energy

[email protected]

Page 2: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

Why Renewable Projects?

• Renewable Energy Mandates• SECNAV Goal: 50% renewable / alternative energy by 2020

SECNAV Goal: 50% net zero installations by 2020• SECNAV Goal: 50% net zero installations by 2020• 10 USC 2911(e): Produce or procure 25% of all DoD energy from renewable energy by 2025• EPACT 2005: Renewable energy – 3% by 2007, 5% by 2010, 7.5% 2013 and beyond• EISA 2007, EO 13423: Energy efficiency, energy intensity, biofuels, etc.• EO 13514: Carbon / Green House Gasses

–Energy Independence/Security • On-site generation and consumption• Reduced dependence on purchased power

• EO 13514: Carbon / Green House Gasses

–Rate Stability• Renewable power rates will be fixed and

lower than or equal to “brown power” • Reduce peak power demand save money• Reduce peak power demand – save money• Potential for revenue/in-kind consideration

(PPA/EJV/EUL contracts)

2

Page 3: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

Solar PV Projects in Norfolk Area (ARRA)

Location kW Mount

Willoughby Area , Naval Station 2100 Ground

THE SYSTEM WILL BE INTERCONNECTED TO AND WILL BE OPERATED IN PARALLEL WITH THE NAVAL STATION ELECTRIC GRID PER THE NEC

3

Page 4: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

Wind Energy Projects - Operational

• 3 8 MW NB Guantanamo Bay Cuba3.8 MW NB Guantanamo Bay, Cuba• 1.5 MW MCLB Barstow, CA• 0.7 MW at Navy Auxiliary Landing Field,

San Clemente Island, CA

4

Page 5: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

Wind Energy

5

Page 6: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

Landfill Gas ESPC at MCLB Albany Georgia

• Methane gas from nearby county landfill (LFG) to operate a 1.9 MW generator.

• Waste heat from the generator will be used to produce steam for process loads.

• Generator will supply power to a critical load during utility outages (Energy Security).

• Total project (includes lighting upgrades) will deliver 116,774 MMBTU/Yr. (19.3%)

• Construction underway, ECD Apr 11.

LFG Natural Gas 

Energy Offset by Renewables

Offset

LFG ElectricOffset

RENEWABLE ENERGY19.3% of Total Consumption

11%

41%8%

Electric

40%

6

Page 7: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

Initial Renewable RFI’s (Lant AOR)

RFI #1 - Newport

FEC Midwest

FEC Wash

FEC Midlant

RFI #2 Camp Lejeune/Cherry Points

FEC Southeast

RFI #2 – Camp Lejeune/Cherry Points

RFI #3 – Beaufort,Parris Island, Blount Island, Albany

RFI #4 – JAX, Mayport, Key West, , yp , y ,Guantanamo, Gulfport, Whiting Field, Kingsville, New Orleans, Panama City, Meridian, Pensacola, Corpus Christi, Fort Worth, King’s Bay

7

Page 8: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

Project Execution Vehicles

•Utility Energy Services Contract (UESC)

•Energy Savings Performance Contract (ESPC)

•Design/Build, Design/Bid/Buildg g

•Enhanced Use Lease

•Energy Joint Venture

•Power Purchase Agreementg

8

Page 9: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

Renewable Project Process – Step 1 (RFI)

Request For Information (or Interest)All t h l i id d–All technologies are considered

• However, unproven or experimental tech not desirable

–Power may be used by base sold to grid or combination of the–Power may be used by base, sold to grid or combination of the two

–Most favorable projects expected to be in the 1 – 5 MW range

–Power Purchase Agreement (PPA) enables 20 - 30 year contract

–Each RFI to be developed for specific FEC

9

Page 10: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

RFI (RPO East) Issued in FY2010

• RFI #1 (closed Apr 22)–Newport (Wind Energy)

• RFI #2 (closed Apr 23)–Camp Lejeune–Cherry Point

• RFI #3 (closed Apr 28)–Parris Island–Beaufort

Blount Island–Blount Island–Albany

• RFI #4 (closed 5 October)–JAX, Mayport, Whiting Field, Kings Bay, Key West, GTMO, Pensacola, Kingsville, Fort , yp , g , g y, y , , , g ,

Worth, Panama City

• Require minimal Site Data Packages

10

Page 11: DON Renewable Energy ProgramDON Renewable Energy Programsdi.odu.edu/ceevc/2010/fa201041/ceevc_Presentation 7 - NAVFAC... · DON Renewable Energy ProgramDON Renewable Energy Program

Renewable Project Process

• Establish installation requirements

Size (MWh) required–Size (MWh) required

–Unworkable technologies (Mission Collision)

• Examine RFI responses

–Specific Technologies

–Financial capacity

L i ti–Logistics

–Technically appropriate

• Feasibility Studies, Business Case Analyses, Fuel Studiesy y

• NEPA Studies, Site Approvals, FAA Approvals, etc.

• Request For Proposal

11