documenting major projects – some wildcard issues · documenting major projects – some wildcard...
TRANSCRIPT
1
Documenting Major Projects –Some Wildcard Issues
Stephen Webb, Dan Brown and Kate PapailiouThursday 7 March 2013
WIN: What in-house lawyers need
Knowledge, support and networkingfor the in-house lawyer community
www.dlapiperwin.com
2DOCUMENTING MAJOR PROJECTS 7 March 2013
2
Agenda
3
Governing law and dispute forum
'Innocuous' boilerplate clauses
Force majeure
Liability regimes
Default and termination
DOCUMENTING MAJOR PROJECTS 7 March 2013
Governing law and dispute forum
4
Tactics in contract negotiation phase
English v. New York v. Australian v. local law
Foreign enforceability of arbitration awards v. court
judgments (New York Convention v. Hague Convention)
Chinese contractors / suppliers and PRC or Hong Kong
law performance bonds
Joinder of disputes in connected contracts
DOCUMENTING MAJOR PROJECTS 7 March 2013
3
Boilerplate - good faith
Scenario
MoUs to establish framework for negotiation and definitive agreements
Essentially non-binding except for good faith obligation
Issues
Delay, uncertainty and loss of momentum
Approach
Consider whether to include or not in MoUs / Heads of Agreement
Exclude – either expressly or by reserving complete discretion
Define or identify things which not bad faith (particularly long-term contracts)
UK governing law – express obligation to negotiate in good faith unenforceable;limited duty re exercise of powers (not objective reasonableness)
7 March 2013DOCUMENTING MAJOR PROJECTS 5
Boilerplate - conditions precedent
Scenario
Various CPs to financial close / completion
Each party to use reasonable endeavours to satisfy
CPs include approvals, FIRB, feasibility studies, signing other agreements
Issues
Reservation of discretion within CPs
Reasonable endeavours obligation to satisfy
For whose benefit and who has to satisfy
Approach
Consider need for absolute discretion
Define limits of reasonable endeavours:
not applicable to discretional CPs
must a party agree to conditions or assume obligations / liability?
Identify for whose benefit
7 March 2013DOCUMENTING MAJOR PROJECTS 6
4
Force Majeure
Scenario
Power Project
Fuel Supply Agreement
Issues
Dealing with aftermath of FM
Substitute performance / solesource
Impact of commercial decisions/ curtailment
7 March 2013DOCUMENTING MAJOR PROJECTS 7
Force Majeure
7 March 2013DOCUMENTING MAJOR PROJECTS 8
Issue Owner Approach
Dealing with aftermath of FM • Ensure that FM provisions deal with aftermath of event• If you require supplier to make up for failure to supply during
FM – ensure Contract says so• If you do not want to accept supply when your operations are
affected by FM – ensure Contract says so• If you do address aftermath – is this consistent with other
mechanisms
Substitute performance / solesourcing
• Counterparties should not be excused from performancebecause subcontractor / supplier suffers FM
• Reasonable endeavours to comply with affected obligation• Source from third parties (where commercially reasonable)
Impact of commercial decisions /curtailment
• Allocation of partial supply - pro-rata, chronologically or inaccordance with industry practices
• Contract must be clear about process in these circumstances
Consistency of FM regimes acrossProject documents
• Ensure FM arrangements are consistent• Narrower relief through downstream documents• Express right to FM relief if FM occurs under upstream
documents
5
Liability
Scenario
Power Project
EPC Contract
Issues
Consequential loss
Gross negligence
7 March 2013DOCUMENTING MAJOR PROJECTS 9
Liability
Issue Owner Approach
Consequential loss exclusion • Consequential loss has quite a broad definition inAustralia – everything that is not the "normalmeasure"
• Prudent to expressly agree what losses are notconsequential losses
• Include all loss / liability expressly set out inContract (ie: loss arising from damage caused bydefects)
• Include all loss / liability arising under other Projectdocuments due to contractor's act, omission,breach or default
Liability for gross negligence • Common law meaning not clear – so define it• Ideally – low threshold (ie: close to negligence)• Seeing more disputes based on Contractor's
alleged gross negligence
7 March 2013DOCUMENTING MAJOR PROJECTS 10
6
Default and termination
11DOCUMENTING MAJOR PROJECTS 7 March 2013
Issue Owner Approach
Events of default Whether to codify termination regime Ability to terminate where LD or liability cap reached Deemed repudiation - protect loss of bargain damages
Termination forconvenience
Preserve absolute discretion and without liability Ensure triggered for ineffective termination for cause Payment – work to date and reasonable direct costs Termination payment is sole remedy Include power to de-scope or move work elsewhere
Financiers' rights Obligation to enter into financier tripartite
Consequences Rights to set-off and call on security Transition arrangements (training / spares / cooperation) Rights to IP Novation of key subcontracts Payment of termination compensation
Other topics?
Balance sheet and credit agency treatment of counterpartydebt e.g. PPAs and GSAs
Prevention principle under (usually) construction contracts -the ease of invalidating LDs
Joinder of disputes across multiple or interlinked contracts
Tax splitting of construction and supply contracts
Change of control
12DOCUMENTING MAJOR PROJECTS 7 March 2013
7
Questions?
13DOCUMENTING MAJOR PROJECTS 7 March 2013