dike decisions based on the a dvanced h ydrological p rediction s ervice (ahps) contact:lee...

40
Dike Decisions Based on the Advanced Hydrological Prediction Service (AHPS) Contact: Lee Anderson, Meteorologist in Charge National Weather Service Grand Forks, North Dakota Phone: (701) 772-0720 (ext 642) E-mail: [email protected] Author: John Erjavec, Professor & Chair Department of Chemical Engineering University of North Dakota Phone: (701) 777- 4244 E-mail: [email protected] River D ike ofH eightL 2 D ike ofH eightL 1 L 2 L 1

Upload: willis-garrison

Post on 22-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Dike Decisions Based on the

Advanced Hydrological Prediction

Service

(AHPS)

Contact: Lee Anderson, Meteorologist in Charge

National Weather ServiceGrand Forks, North Dakota

Phone: (701) 772-0720 (ext 642)E-mail: [email protected]

Author: John Erjavec, Professor & Chair Department of Chemical

Engineering University of North Dakota

Phone: (701) 777- 4244E-mail: [email protected]

River

Dike of Height L2

Dike of Height L1

L2L1

Introduction

The purpose of this material is to help city managers, city engineers, hydrologists and others to use the river crest predictions from the new Advanced Hydrological Prediction Service (AHPS).The methodology presented helps calculate the economic benefits from a dike that may prevent flooding of a city.Economics is only one factor in this decision making process, but it is clearly an important factor.

All river crest predictions, even those using the AHPS, are inherently uncertain.

CONCLUSION:

Dike decisions must take degree of certainty of predictions into account.

ISSUE:

Decision Making when dealing with

Uncertainty

Situation:Exact outcome is NOT knownPossible outcomes ARE knownThe probability that a particular outcome will occur is known or can be estimated for each outcomeEconomics is an important factor in the decision

making process

Example 1: Investment Opportunity

Investment (i.e. COST) is $10,000 Return is uncertain:

Return may be $100,000 There may be no return

Summary of 2 Alternatives: Alternative 1: Do not invest

Cost = $0, Benefits = $0 Alternative 2: Invest

Cost = $10k, Benefits = uncertain

Decision to be made: Should one invest?We Need a Decision Making Criterion

TYPICAL CRITERIA:

One Alternative :Benefit / Cost Ratio > 1

Multiple Alternatives:Incremental Benefit

Incremental Cost> 1

TYPICAL CRITERIA (continued):

PROBLEM:

Since the outcomes can not be predicted with certainty, the actual Benefits are unknown.

SOLUTION: Use EXPECTED benefits

(i.e., use average benefits)

DEFINITION

The Expected Benefit, E(B), for a course of action (alternative) is the weighted average of the benefits from the possible outcomes for that alternative. Each benefit value for a particular outcome is weighted by the probability of that outcome actually happening. Mathematically, if the outcomes are denoted by O1, O2, etc., then

E(B) = BenefitO1x P(O1) + BenefitO2 x P(O2) + … where BenefitO1 is the benefit of Outcome1 , etc. and P(O1) is the probability of Outcome1 , etc.

CRITERION*:

Examine ratio of Incremental Expected Benefit, E(B), to Incremental Cost, C

Is E(B) / C > 1 ?

If ratio is >1, choose higher cost alternative.If ratio is <1, choose lower cost alternative.

*Remember, our situation is that we have two alternatives.

Example 1 (Continued)

Summary of 2 Alternatives: Alternative 1: Do not invest

Cost = $0, Benefits = $0 Alternative 2: Invest

Cost = $10k, Benefits = uncertain

Outcomes for Alternative 2: Outcome A = Investment pays off

BenefitA = $100,000 P(A) = 0.05 (that is, 5 times out of 100 it pays off)

Outcome B = Investment does not pay off BenefitB = $0 P(B) = 0.95 (that is, 95 times out of 100 it does not pay

off) Expected Value of Benefits =

(0.05)x($100,0000) + (0.95)x($0) = $5,000

Example 1 (Continued)

Apply Criterion:Incremental Expected Benefit = $5,000 (On average, we would get $5k per investment.)Incremental Cost = $10,000Since: E (B) / C = $5k/$10k = 0.5 <1Do NOT Invest

Note: We would never actually get a $5,000 return;either we would get $100,000 or nothing.The expected benefit of $5,000 is the return that one would get “on average” from numerous $10,000 investments such as this.

Example 2 (Fire Insurance for $250k House)

Outcomes (from fire rating bureau): O1 : No fire loss P(O1) = 0.985 O2 : $15k fire loss P(O2) = 0.010 O3 : $50k fire loss P(O3) = 0.004 O4 : $200k fire loss P(O4) = 0.001

Expected value of fire loss in any year: Expected Loss = ($0)(0.985) + ($15k)(0.010) + ($50k)(0.004) + ($200k)(0.001) = $550

Example 2 (Continued)

Expected Value of fire loss = $550/yrFire insurance (no deductible) = $750/yrSummary of Costs and Expected Benefits: Alt 1, No Insurance:

Cost = $0/yr, Expected “Benefits” = -$550/yr (fire loss) Alt 2, Buy Insurance:

Cost = $750/yr, Expected “Benefits” = $0/yr (No fire loss) Incremental Benefits = $0/yr – (-$550/yr) = $550/yr Incremental Costs = $750/yr - $0/yr = $750/yr

Example 2 (Continued)

Apply Criterion: E (B) / C = $550/$750 = 0.73 <1

Conclusion: The insurance is more costly (on average) than a fire.

(This is the expected result, since we know that insurance companies make money).

Decision: Should you buy insurance? Our criterion says that the less expensive alternative (no insurance) is the one that is the best.But we probably ought to buy the insurance anyway (assuming it is affordable), because being self-insured only makes sense if the worst outcome is not catastrophic.

General Approach

List all reasonable alternative courses of action. “Do nothing” is usually included on

the list.Determine the cost (investment) of each alternative on your list.List all outcomes for each alternative Determine the probability of each outcome Assign a value (benefit, which may be negative if it is

a loss) to each outcome.

Determine the Expected Value of the benefits for each alternative (course of action).

Example 3 Why Use Incremental Approach? (Why Not Maximize Benefit/Cost Ratio?)

Alt. Cost Benefit B/C

0 $0 $0 --- 1 $100 $200 2.00 2 $200 $350 1.75 3 $300 $475 1.58 4 $400 $575 1.42 5 $500 $650 1.30

• All alternatives are good. They all have B/C ratios > 1• Alternative 1 has the highest B/C ratio, but it is not the best.• Alternative 3 is the best. It keeps returning more in extra (incremental) benefits than the extra (incremental) costs.

Increment C B B/C

> Alt.1-Alt.0 $100 $200 2.00> Alt.2-Alt.1 $100 $150 1.50> Alt.3-Alt.2 $100 $125 1.25> Alt.4-Alt.3 $100 $100 1.00> Alt.5-Alt.4 $100 $75 0.75

General Approach (Continued)

Order the alternatives from least expensive to most expensive.Compare the alternatives pair-wise, starting with the least expensive, examining incremental benefits and incremental costs

If B/C > 1, keep the more expensive alternative In this case, the increased benefits outweigh the

increased costs of the more expensive alternative. If B/C < 1, keep the less expensive alternative

The alternative that is kept is compared to the next alternative on the list, and the procedure is repeated until all alternatives have been examined, and only one remains.

That alternative is the “winner” (final decision). Review the decision to make sure that the risk is not too great. (Being self insured only makes sense if the worst outcome(s) is not catastrophic.)

General Approach Applied to Dike Decisions

List all reasonable alternative dike levels. Start with the existing permanent dike level and end with the highest dike that could be built in the time allowed.Determine the cost of each dike level on your list.

By difference, calculate the incremental cost of adding to the dike to get to the next level of protection.Determine the loss which would be incurred to the city if a

river crest exceeded the level of the dike (by half of the interval between dike heights) for each dike height on your list.From AHPS, determine the probability of the river crest exceeding each dike height on your list.Determine the probability that the river crest will fall in each dike level range on your list by difference.

General Approach Applied to Dike Decisions (Continued)

Determine the Expected Loss for each increment of the dike, by multiplying the Loss to the city for flooding in a specific range times the probability that the river crest will fall in that range.Calculate the Incremental Expected Benefit / Incremental Cost ratio for each extra dike level under consideration. This is done by dividing the Expected Loss of Flooding which will be avoided by adding to the dike, by the incremental cost of building the dike higher (to the next level).If the ratio, E(B) / C, is greater than 1, the increment is worth adding.If the ratio, E(B) / C, is less than 1, the increment is not worth adding.Review the decision to make sure that the risk is not too great. (Being self insured only makes sense if the worst outcome(s) is not catastrophic.)

General Approach Applied to Dike Decisions (Continued)

Suggestions: Determine the cost of each dike level that is being

evaluated. By difference, calculate the cost of adding to the dike

to bring it to the next higher level, and put the information in a spreadsheet

Determine the damage to the city that would be incurred if the city were not protected by a dike and the river crest hit a level halfway between the dike levels being considered. Include that information in the spreadsheet.

Add the AHPS probability data to the spreadsheet (as per Examples 4-7).

Calculate Expected benefits and Incremental E(B)/C ratios for each dike level. Use ratios to help guide dike level decision.

Examples 4-7 (GF/EGF Flood Control)

Alternatives to Consider: 1: Do Nothing 2: 49’ Dike 3: 51’ Dike 4: 53’ Dike 5: 55’ Dike 6: 57’ Dike

Examine incremental benefit / incremental cost Note: Incremental benefit is the EXPECTED flood loss which is avoided by building the dike higher.

Benefits = Probability of flooding x Cost of Flood Damage

Incremental cost is the cost of adding to the dike to make it higher (see figure on next slide).

Dikes of Heights L1 and L2:

River

Dike of Height L2

Dike of Height L1

L2L1

River Property Dike Dike IncrementalHeight, Damage, Height Cost Dike Cost

ft $M $M $M

> 46 $0 46 $0.0046 to 49 $10.0 49 $0.30 $0.3049 to 51 $31.5 51 $1.00 $0.7051 to 53 $100 53 $2.40 $1.4053 to 55 $315 55 $4.20 $1.8055 to 57 $1,000 57 $6.50 $2.30

Basic Cost Data*

Flood Damage Dike Construction

Examples 4-7 (GF/EGF Flood Control)

*This data only needs to be collected once, and updated whenever it is deemed to be necessary.

Example 4:

Very High Crest Predicted(Most likely crest of 43

feet)

Example 4 AHPS Output (Actual Probabilistic Outlook for Red River at East Grand Forks, MN – 2001)

Example 4 (Continued)AHPS

River Probability River Crest ProbabilityCrest of Range, of Crest feet Exceeding feet in Range*

46 20.00% < 46 80.00%49 6.00% 46 to 49 14.00%51 4.00% 49 to 51 2.00%53 2.40% 51 to 53 1.60%55 0.81% ** 53 to 55 1.59%57 0.25% ** 55 to 57 0.56%

* These values were obtained by difference (see next slide)

** These values had to be obtained by extrapolation(see slide after next)

Probability of Crest Between L1 and L2

Probability of Probability of Probability of River Cresting = River Cresting - River CrestingBetween L1 & L2 Higher than L1 Higher than L2

AHPS Exceedance Probabilities

L1 L2 L1 L2

= -

Extrapolating AHPS Probabilities

L 0.025

Assume predictions follow aNormal Distribution

• Mean, L 0.50 = Level for 50% Exceedance Probability• Standard Deviation, s ~ (L 0.025 - L 0.50 )/2

where L 0.025 is the level which has a 2.5% chanceof being exceeded.

To find the probability of exceeding a level, L

• Calculate standard Normal deviate, z , which corresponds tohow many standard deviations L is from the mean:

z = (L – L 0.50)/s• Look up probability for z using statistical tables of the Normal Dist.

or use a spreadsheet (e.g. Excel NORMDIST function)

L 0.50

s

Extrapolating AHPS Probabilities (For Example 4, Case: L = 55 ft)

L0.025 = 53 ft

To find the probability of exceeding level, L = 55 ft

• Assume predictions follow a Normal Distribution• Mean = L 0.50 (obtained from AHPS Output)

= 43 ft for this example• L 0.025 (also from AHPS Output) used to get s

= 53 ft for this example• Standard Deviation, s = (L 0.025 - L 0.50 )/2 = (53-43)/2 = 5.0• Calculate standard Normal deviate, z:

z = (L – L 0.50)/s = (55-43)/5.0 = 2.4• Look up probability for z:

Prob(L > 55 ft) = Prob(z > 2.4) = 0.0081= 0.81%

Mean = 43 ft

s

L = 55 ft

Incremental IncrementalRiver Property Probability EXPECTED Dike ExpectedCrest Damage, of Crest Damage Cost Benefit/feet $M in Range $M $M Cost

(Benefit) Ratio> 46 $0 80.00% $0

46 to 49 $10 14.00% $1.40 $0.30 4.6749 to 51 $31.5 2.00% $0.63 $0.70 0.9051 to 53 $100 1.60% $1.60 $1.40 1.1453 to 55 $315 1.59% $5.01 $1.80 2.7855 to 57 $1,000 0.56% $5.60 $2.30 2.43

Note: Check increment 46-51 ft.Conclusion: Build dike to 57 feet

Economic Use of Predictions

Example 4 (Continued)

Example 5:

High Crest Predicted(Most likely crest of 40

feet)

Example 5 (Continued)

AHPS*River Probability River Crest ProbabilityCrest of Range, of Crest feet Exceeding feet in Range

46 12.00% < 46 88.00%49 3.80% 46 to 49 8.20%51 1.40% 49 to 51 2.40%53 0.50% 51 to 53 0.90%55 0.14% 53 to 55 0.36%57 0.04% 55 to 57 0.10%

AHPS Predictions

* These probabilities were simulated assuming a Normal-distribution with a mean (L50%) = 40 ft, and a standard deviation, s = 5 ft.

Example 5 (Continued)

Incremental IncrementalRiver Property Probability EXPECTED Dike ExpectedCrest Damage, of Crest Damage Cost Benefit/feet $M in Range $M $M Cost

(Benefit) Ratio> 46 $0.0 88.00% $0.00

46 to 49 $10.0 8.20% $0.82 $0.30 2.7349 to 51 $31.5 2.40% $0.76 $0.70 1.0851 to 53 $100.0 0.90% $0.90 $1.40 0.6453 to 55 $315.0 0.36% $1.13 $1.80 0.6355 to 57 $1,000.0 0.10% $1.00 $2.30 0.43

Conclusion: Build dike to 51 feet

Economic Use of Predictions

Example 6:

Medium Crest Predicted(Most likely crest of 38

feet)

Example 6 (Continued)

AHPS*River Probability River Crest ProbabilityCrest of Range, of Crest feet Exceeding feet in Range

46 6.00% < 46 94.00%49 1.40% 46 to 49 4.60%51 0.50% 49 to 51 0.90%53 0.14% 51 to 53 0.36%55 0.040% 53 to 55 0.10%57 0.007% 55 to 57 0.03%

AHPS Predictions

* These probabilities were simulated assuming a Normal-distribution with a mean (L50%) = 38 ft, and a standard deviation, s = 5 ft.

Example 6 (Continued)

Incremental IncrementalRiver Property Probability EXPECTED Dike ExpectedCrest Damage, of Crest Damage Cost Benefit/feet $M in Range $M $M Cost

(Benefit) Ratio> 46 $0.0 94.00% $0.00

46 to 49 $10.0 4.60% $0.46 $0.30 1.5349 to 51 $31.5 0.90% $0.28 $0.70 0.4151 to 53 $100.0 0.36% $0.36 $1.40 0.2653 to 55 $315.0 0.10% $0.32 $1.80 0.1855 to 57 $1,000.0 0.03% $0.33 $2.30 0.14

Conclusion: Build dike to 49 feet

Economic Use of Predictions

Example 7:

Low Crest Predicted(Most likely crest of 36

feet)

Example 7 (Continued)

AHPS*River Probability River Crest ProbabilityCrest of Range, of Crest feet Exceeding feet in Range

46 2.30% < 46 97.70%49 0.500% 46 to 49 1.80%51 0.140% 49 to 51 0.36%53 0.034% 51 to 53 0.11%55 0.007% 53 to 55 0.03%57 0.001% 55 to 57 0.01%

AHPS Predictions

* These probabilities were simulated assuming a Normal-distribution with a mean (L50%) = 38 ft, and a standard deviation, s = 5 ft.

Example 7 (Continued)

Incremental IncrementalRiver Property Probability EXPECTED Dike ExpectedCrest Damage, of Crest Damage Cost Benefit/feet $M in Range $M $M Cost

(Benefit) Ratio> 46 $0.0 97.70% $0.000

46 to 49 $10.0 1.80% $0.180 $0.30 0.6049 to 51 $31.5 0.36% $0.113 $0.70 0.1651 to 53 $100.0 0.11% $0.106 $1.40 0.0853 to 55 $315.0 0.03% $0.085 $1.80 0.0555 to 57 $1,000.0 0.01% $0.060 $2.30 0.03

Conclusion: Build no dike

Economic Use of Predictions

SUMMARYThe uncertainty of river level predictions is a key factor that must be taken into account in any dike decisions.The relative costs of building a dike versus the costs incurred by flood damage are also key factors in dike decisions.The appropriate economic criterion to use as part of the decision making process is the ratio of the incremental expected benefit (by avoiding flood damage) to the incremental cost of adding to the dike height.Even when the probability of a crest exceeding a high level is low (less than 1%, as in Example 3), it may still be worth building a dike to that level when the costs of damage are very high. This is true because the expected benefits are calculated as the (probability) x (potential damage).