development proposal & environmental management … city council... · 2015-11-27 · 6.3.15...
TRANSCRIPT
BURNIE WASTE MANAGEMENT CENTRE
STAGE 1 LANDFILL LEACHATE TREATMENT WETLAND
DEVELOPMENT PROPOSAL &
ENVIRONMENTAL MANAGEMENT PLAN
NOVEMBER 2015
Perth
12 Monger Street
PerthWA,Australia 6000
t +61[0]8 9227 9355
f +61[0]9 9227 5033
ABN : 39 092 638 410
Melbourne
2/26-36 High Street
Northcote VIC,Australia 3070
t +61[0]3 9481 6288
f +61[0]3 9481 6299
www.syrinx.net.au
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
This Development Proposal and Environmental Management Plan was prepared by:
Syrinx Environmental Pty Ltd
Head Office:
12 Monger Street, Perth 6000, WA
Contact Person: Dr Kathy Meney
Company Director | Principal Scientist
Telephone: 08 9227 9355
Email: [email protected]
For:
Burnie City Council
Registered office
PO Box 973, Burnie 7320
Contact Person: Mr Rowan Sharman
Manager Engineering Services
Telephone: 03 6430 5752
Email: [email protected]
Significant input regarding the landfill stability and potential associated risks was provided by
Tasman Geotechnics.
The DPEMP will be submitted to:
The Chairperson
Board of the Environment Protection Authority
GPO Box 1550, Hobart TAS 7001
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
PURPOSE OF REPORT
Syrinx Environmental Pty Ltd (‘Syrinx’) has prepared this document titled ‘Burnie Waste
Management Centre Stage 1 Landfill Leachate Treatment Wetland - Development Proposal &
Environmental Management Plan ’ (the ‘Report’) for the use of Burnie City Council (the
‘Client’).
LIMITATIONS OF REPORT
Syrinx Environmental PL has prepared this report as an environmental consultant provider. No
other warranty, expressed or implied, is made as to the professional advice included in this
report. This report has not been prepared for the use, perusal or otherwise, by parties other
than the Client, and their nominated consulting advisors without the consent of the Owner. No
further information can be added without the consent of the Client, nor does the report contain
sufficient information for purposes of other parties or for other uses. The information contained
in this report has been prepared in good faith, and accuracy of data at date of issue has been
compiled to the best of our knowledge. However, Syrinx Environmental PL is not responsible
for changes in conditions that may affect or alter information contained in this report before,
during or after the date of issue.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 i
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
TABLE OF CONTENTS
1.0 INTRODUCTION 1
1.1 TITLE OF THE PROPOSAL 1
1.2 PROPONENT DETAILS 1
1.2.1 Proponent Background 1
1.3 PROPOSAL SUMMARY 3
1.3.1 Proposal Background 3
1.3.2 Regional Context 6
1.4 LEGISLATIVE CONTEXT 7
1.4.1 Relevant Legislation, Regulations, Codes and Policies 7
1.4.2 Commonwealth Assessment Process 7
1.4.3 State Legislation & Assessment Process 8
1.4.4 Management Plan 10
1.4.5 Existing Permits & Manuals 10
2.0 PROPOSAL DESCRIPTION 11
2.1 PROJECT NEED 11
2.2 DETAILED PROJECT DESCRIPTION 12
2.2.1 General 12
2.2.2 Current Stage 1 Leachate Management 16
2.2.3 Proposed System Summary 19
2.2.4 System Components & Processes 20
2.2.5 Wetland Capacity and Performance 35
2.2.6 System Operation 38
2.2.7 Proposed Stormwater & Creek Enhancement Works 39
2.2.8 Construction 41
2.2.9 Commissioning 42
2.2.10 Precedent Projects 44
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 ii
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
3.0 PROJECT ALTERNATIVES 47
3.1 ON‐SITE TREATMENT VS DECOMMISSIONING & REMEDIATION VS
TRADE WASTE DISCHARGE 47
3.2 EVALUATION OF REUSE VS DISPOSAL OPTIONS 48
3.2.1 Reuse 48
3.2.2 Disposal 49
3.3 EVALUATION OF TREATMENT APPROACHES & TECHNOLOGIES 50
3.3.1 Evaluation of Leachate Management Approaches 50
3.3.2 Detailed Evaluation of Shortlisted Treatment Technologies 52
3.4 ASSESSMENT OF TREATMENT WETLAND LOCATIONS 53
4.0 PUBLIC CONSULTATION 56
4.1 STAKEHOLDER CONSULTATION 56
4.1.1 Community Consultation 56
4.1.2 Consultation with TasWater 59
4.2 REGULATORY CONSULTATION 60
5.0 THE EXISTING ENVIRONMENT 61
5.1 PLANNING ASPECTS 61
5.1.1 Land Tenure 61
5.1.2 Land Use & Planning History 62
5.1.3 Neighbouring Properties 62
5.2 ENVIRONMENTAL ASPECTS 63
5.2.1 Topography 63
5.2.2 Climate 63
5.2.3 Geology & Soils 64
5.2.4 Leachate (Current) 65
5.2.5 Leachate Seepage 78
5.2.6 Groundwater 81
5.2.7 Stormwater 88
5.2.8 Cooee Creek and its Tributary 92
5.2.9 Biodiversity & Conservation Significance 106
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 iii
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
5.2.10 Natural Events & Hazards 109
5.2.11 History of Waste Management 110
5.3 SOCIO-ECONOMIC ASPECTS 112
5.3.1 Project Socio-Economic Benefits 112
5.3.2 Heritage 113
6.0 POTENTIAL IMPACTS & THEIR MANAGEMENT 114
6.1 KEY ISSUES SPECIFIC TO THIS PROPOSAL 114
6.1.1 Potential Surface Water Quality and Hydrological Impacts 116
6.1.2 Summary of Potential Impacts to the Creek 125
6.1.3 Potential Groundwater and Geotechnical Impacts 127
6.2 HAZARD AND RISK ASSESSMENT OF KEY ISSUES 128
6.2.1 Risk Assessment Approach 128
6.2.2 Risk Identification 129
6.2.3 Risk Analysis 133
6.2.4 Proposed Management Measures 137
6.3 OTHER POTENTIAL IMPACTS AND MANAGEMENT RESPONSES 141
6.3.1 Air Quality 141
6.3.2 Noise Emissions 142
6.3.3 Waste Management 143
6.3.4 Dangerous Goods and Environmentally Hazardous Materials 143
6.3.5 Biodiversity and Natural Values 144
6.3.6 Pests, Weeds and Diseases 146
6.3.7 Dust 146
6.3.8 Sediment 147
6.3.9 Marine and Coastal 147
6.3.10 Greenhouse Gases and Ozone Depleting Substances 147
6.3.11 Heritage 148
6.3.12 Land Use & Development 149
6.3.13 Visual Impacts 149
6.3.14 Socio-Economic Issues 149
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 iv
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.3.15 Health & Safety Issues 149
6.3.16 Fire Risk 149
6.3.17 Infrastructure and Off-Site Ancillary Facilities 150
6.3.18 Environmental Management Systems 151
6.3.19 Cumulative and Interactive Impacts 151
6.3.20 Traffic Impacts 152
7.0 MONITORING & REVIEW 152
7.1 MONITORING PROGRAM 152
7.1.1 Sample Collection, Handling and Analysis 153
7.1.2 Sampling Locations 153
7.1.3 Sampling Frequency and Parameters 155
7.2 MANAGEMENT TRIGGERS 156
7.3 GEOTECHNICAL MONITORING 161
7.3.1 Construction Monitoring - Pre, During and Post Construction 161
7.3.2 Ongoing Settlement Monitoring 161
7.3.3 Wetland Liner Leakage Monitoring 161
7.4 MAINTENANCE & SYSTEM HEALTH MONITORING 162
7.4.1 Ongoing Maintenance Tasks 162
7.4.2 Scheduled Maintenance Tasks 163
7.5 REPORTING 164
8.0 DECOMMISSIONING & REHABILITATION 164
9.0 COMMITMENTS 164
10.0 CONCLUSION 164
REFERENCES 173
APPENDICES 176
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 v
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
LIST OF TABLES
Table 1. Wetland components and design details 36
Table 2. Estimated Performance of the Proposed Stage 1 Leachate Treatment System 37
Table 3. Preliminary construction timetable 41
Table 4. Estimates of raw materials and sources 42
Table 5. Wetland commissioning tasks and timing 44
Table 6. Broad leachate management approaches 50
Table 7. Outcomes of preliminary stage 1 leachate treatment options screening 51
Table 8. Summary of assessment of alternative wetland locations 54
Table 9. Frequency distribution of Stage 1 leachate flows 67
Table 10. Stage 1 leachate WQ – physical parameters 70
Table 11. Concentrations of nutrients in Stage 1 leachate 71
Table 12. Stage 1 leachate WQ – metals (total) 74
Table 13. Stage 1 leachate WQ – detected organics 77
Table 14. Mass loading of key pollutants to sewer 78
Table 15. Leachate seepage chemistry for the 3 sampling events in 2013 80
Table 16. Soil data from within the leachate seepage area (northern embankment of
Stage 1 landfill) 81
Table 17. Summary of groundwater quality data – pH, nutrients and dissolved metals 87
Table 18. Stormwater quality 91
Table 19. Estimated mass loading of key stormwater pollutants to the Creek from
Stage 2A stormwater flows 92
Table 20. Cooee Creek monitoring data - water quality results (April 2014) and
comparison with the Stage 1 leachate and site stormwater 97
Table 21. Sediment quality within Cooee Creek and unnamed tributary – April 2014 97
Table 22. EPA proposed water quality objectives for Cooee Creek 100
Table 23. Proposed water quality protection levels for discharge to the Cooee Creek
unnamed tributary 105
Table 24. Threatened species recorded (in bold) within 500m of stream reach and
those potentially present, by habitat type or survey evidence (NEST 2014) 107
Table 25. Pollutant concentrations in the Infiltration Wetland effluent 120
Table 26. Volumes estimated to be discharged directly to the Infiltration Wet Forest –
mean daily 120
Table 27. Annual discharge and mass loadings to the Infiltration Wet Forest 120
Table 28. Volumes estimated to be discharged directly to the Creek – mean daily 121
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 vi
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 29. Mass pollutant load to creek based on daily rainfall and flows 122
Table 30. Annual discharge and mass loadings to creek. 123
Table 31. Peak day mass load discharge to creek based on > 90% flows 124
Table 32. Summary of possible receptor/pathways interactions 132
Table 33. Proposed monitoring schedule for the treatment wetland 157
Table 34. Commitments table for the Burnie Treatment Wetlands proposal 165
Table 35. Summary of compliance with specific guidelines 167
LIST OF FIGURES
Figure 1. Location of the Burnie Waste Management Centre and the Stage 1 landfill 13
Figure 2. Land boundary, site layout and location points 14
Figure 3. Site Plan showing landfill stages 15
Figure 4. Burnie Waste Management Centre Site Plan 17
Figure 5. Process sketch showing existing leachate management (from BCC) 18
Figure 6. General site layout showing location of major components & access
points for construction and maintenance. 22
Figure 7. Process diagram showing proposed collection & conveyance
infrastructure works 23
Figure 8. Proposed modifications to the leachate collection and conveyance
infrastructure, and construction of emergency control infrastructure 26
Figure 9. Proposed alterations to MH1 (leachate) and MH3 (stormwater) 27
Figure 10. Typical section through surface flow wetland. 30
Figure 11. Long section showing proposed infiltration wet forest, stormwater swale
for treatment of low flows and modified creek discharge 32
Figure 12. Cross section showing proposed infiltration wet forest, stormwater swale
for treatment of low flows and modified creek discharge 33
Figure 13. Proposed nature & extent of creek enhancement works, and location of
new stormwater swale 40
Figure 14. Explanatory diagram of Lorong Halus Leachate Treatment Wetland 46
Figure 15. Rory Shaw Wetlands Park currently being constructed at a former landfill
site in California.. 46
Figure 16. Summary of leachate treatment technology evaluation 52
Figure 17. Mean climate data for Round Hill, Burnie 64
Figure 18. Average stage 1 leachate flows (March 2010-December 2014) 66
Figure 19. Frequency distribution graph of Stage 1 leachate flows 67
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 vii
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 20. Site current sampling locations 69
Figure 21. Seasonal changes in nutrients levels in Stage 1 leachate 72
Figure 22. Seasonal changes in Fe and Mn levels in Stage 1 leachate (median values) 75
Figure 23. Seasonal changes in Al concentrations in LO1 and SW1 (median values) 76
Figure 24. Seasonal changes in Zn levels in LO1 & stormwater (median values) 76
Figure 25. Seepage area showing ponding & low ‘sheen’ indicating metal precipitation 79
Figure 26. Extent of leachate seepage in August 2013 79
Figure 27. Standing water level data and cumulative deviation from mean annual
rainfall recorded for GW1 over the period 1991 to 2000. 83
Figure 28. Standing water level data and cumulative deviation from mean annual
rainfall recorded for GW2 over the period 1991 to 2006. 84
Figure 29. Conceptual site model – existing scenario 85
Figure 30. Stormwater network at BWM 89
Figure 31. Average (Stage 2) stormwater point discharge flows to Cooee Creek tributary 90
Figure 32. Cooee Creek catchment area. Burnie landfill site is up-gradient of CT-1 93
Figure 33. Conservation of Freshwater Ecosystem Values (CFEV) for the site. 94
Figure 34. Location of Water and Sediment samples undertaken as part of Cooee Creek
and Cooee Creek tributary background sampling 96
Figure 35. The outline of the 1000 year floodplain (blue hatched areas) 110
Figure 36. Conceptual site model – PROPOSED DEVELOPMENT SCENARIO 115
Figure 37. Proposed water circuit and water balance for normal (median) and high flows 118
Figure 38. Site layout showing borehole locations 119
Figure 39. Annual mass loading to the Infiltration Wet Forest 121
Figure 40. Annual mass loading to the Creek (based on daily rainfall and flows) 122
Figure 41. Proposed sampling locations. 154
LIST OF APPENDICES
APPENDIX 1. Burnie Waste Management Centre (BWMC) Stage 1 Landfill Leachate
Treatment Study – Option Development and Evaluation and Preferred
Option Concept Design (Syrinx Environmental PL, July 2014) 177
APPENDIX 2. Natural Values Assessment Report (NEST July 2014) 178
APPENDIX 3. EPBC Referral Decision 179
APPENDIX 4. Addendum to Stage 1 Landfill Leachate Treatment Study – Design Changes &
Alternative Wetland Option Assessment
(Syrinx Environmental PL May 2015) 180
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 viii
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 5. Assessment of Alternative Leachate Management Options
(BCC May 2015) 181
APPENDIX 6. Hydro‐geotechnical Investigation and Risk Assessment Version 2,
August 2015 (Tasman Geotechnics August 2015) 182
APPENDIX 7. Preliminary Treatment System And Associated Infrastructure Layout 183
APPENDIX 8. EPA Class Assessment Of The Project Proposal 184
APPENDIX 9. Proposed Wetland Species List 185
APPENDIX 10. Letters to Stakeholders 187
APPENDIX 11. Certificate of Title 188
APPENDIX 12. Chronology of the Waste Management Activities On Site 189
APPENDIX 13. CFEV Assessment Component Report. 190
APPENDIX 14. Risk Assessment Descriptors 191
APPENDIX 15. Risk Assessment Evaluation 193
LIST OF ABBREVIATIONS
Al Aluminium
ANZECCAustralian and New Zealand Environment and Conservation Council and Agriculture
and Resource Management Council of Australia and New Zealand
ARI Average Recurrence Interval
BCC Burnie City Council
bgl / m bgl Below ground level / meters below ground level
BOD Biochemical Oxygen Demand/Biological Oxygen Demand
BOM Bureau of Meteorology
BWMC Burnie Waste Management Centre
C Carbon
Chl-a Chlorophyll-a
CFEV Conservation of Freshwater Ecosystem Values
cfu Colony forming unit
COD Chemical Oxygen Demand
Cr Chromium
Cu Copper
d Day
dia Diameter
DO Dissolved Oxygen
DOC Dissolved Organic Carbon
DPEMP Development Proposal & Environmental Management Plan
DPIWE Department of Primary Industries, Parks, Water and Environment
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 9
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
EC Electrical Conductivity
E. coli Escherichia coli
EH&S Environmental Health & Safety
EMPC Environmental Management and Pollution Control
EPA Environmental Protection Authority
EPBC Environmental Protection and Biodiversity Conservation
EPN Environmental Protection Notice
EPP Environment Protection Policy
ET Evapotranspiration
EWR Environmental Water Requirement
Fe Iron
ha Hectare
GCL Geosynthetic Clay Liner
GHG Green House Gas
GIL Groundwater Investigation Level
GW Groundwater
HLR Hydraulic Loading Rate
HDPE High Density Polyethylene
Hr Hours
HRT Hydraulic Retention Time
kg Kilogram
kL Kiloliter
kW Kilowatt
kWhr Kilowatt hour
LLDPE Linear Low Density Polyethylene
LOD Limit of Detection
LOR Limit of Reporting
L/sec Litre per second
m Metre
MAH Monocyclic Aromatic Hydrocarbons
MBR Membrane Bioreactor
MH Manhole
MF Microfiltration
ML Megalitre
mm Millimetre
Mn Manganese
MRT Mineral Resources Tasmania
NEPM National Environment Protection Measure
NH4-N Ammonium Nitrogen
Ni Nickel
NOI Notice of Intent
NOx Oxidised Nitrogen (Nitrate & Nitrite)
NRM Natural Resources Management
NTU Nephelometric Turbidity Units
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 10
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
OC Organic Carbon
OC/OP Organochlorine / Organophosphate (pesticides)
Org N Organic Nitrogen
ORP Oxidation Reduction Potential
PAHs Polycyclic Aromatic Hydrocarbons
Pb Lead
PCB Polychlorinated biphenyl
PEVs Protected Environmental Values
pH Hydrogen Ion Concentration [Potential of Hydrogen]
Redox Reduction Oxidation Potential
RO Reverse Osmosis
SBR Sequencing Batch Reactor
SFW Surface Flow Wetland
SIDP Stormwater Infrastructure Development Project
SMD Slightly to Moderately Disturbed
SSFW Subsurface Flow Wetland
SW Stormwater
TDS Total Dissolved Solids
TEC Threatened Ecological Communities
TN Total Nitrogen
TP Total Phosphorus
UF Ultrafiltration
UTAS University of Tasmania
UV Ultraviolet
TALC Tasmanian Aboriginal Land Council
TSS Total Suspended Solids
WQ Water Quality
WQGs Water Quality Guidelines
WQO Water Quality Objective
WWTP Wastewater Treatment Plant
Zn Zinc
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 1
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
1.0 INTRODUCTION
1.1 TITLE OF THE PROPOSAL
Burnie Waste Management Centre Stage 1 Landfill Leachate Treatment Wetland.
1.2 PROPONENT DETAILS
The proponent of the landfill leachate treatment wetland is Burnie City Council.
Registered address: 80 Wilson Street, Burnie 7320, Tasmania
Postal address: PO Box 973, Burnie 7320, Tasmania
ABN number: 29 846 979 690
The relevant council contact officer and contact details are:
Mr Rowan Sharman
Manager Engineering Services
Burnie City Council
Ph. (03) 6430 5752
F: 1300 287 643
1.2.1 Proponent Background
Burnie City Council has a strong and successful record of delivering capital works projects and
has a strong engineering team in its Technical Services Department to provide support to the
project. Some recent large projects are provided below.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 2
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Project Project Cost Project Description
Coastal Pathway
and Waterfront
Boardwalk
$3,925,474 Completed in October 2010.
Three major elements were constructed to create a 5.5 km shared
walking and cycling pathway around Burnie’s foreshore as part of
the greater Cradle Coast Regional’s coastal pathways project. The
project comprises a concrete pathway, an elevated timber
boardwalk along West Beach and a rail overpass structure.
Waterfront
Development
$6,358,051 Completed in February 2012.
Comprises the redevelopment of the Burnie Waterfront Precinct
to include a new 280 m long terraced sea wall including lawn
events area, BBQ shelters, wet and dry play elements, lighting and
a pedestrian friendly street and parking arrangements that brings
the city to the sea. Many elements design and managed by
Council Technical Services.
Stormwater
Infrastructure
Development
Project
$4,250,000 Commenced in June 2012 – Ongoing.
The objective of this project is to reduce stormwater infiltrations
to the waste water network to provide capacity for economic
expansion opportunities in the region. Works include; identifying
sources of infiltration, installing stormwater mains and property
plumbing. The Stage 1 Leachate Treatment proposal is an element
of this project.
Waste Transfer
Facility
$1,461,005 Completed in November 2012.
This project included the construction of a waste transfer and
resource recovery facility at the Burnie Waste Management
Centre to offer a long term sustainable solution for the
management of waste, by maximising the recovery of resources
from the waste stream and avoiding their disposal to landfill.
Managed by Council Technical Services.
Stage 1 Landfill
Rehabilitation &
Stage 2A Landfill
$1,700,000 Completed July 2006.
This project comprised capping and rehabilitation of Stage 1
Landfill and development of Stage 2A landfill cell at the Burnie
Waste Management Centre. Managed by Council Technical
Services.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 3
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
1.3 PROPOSAL SUMMARY
1.3.1 Proposal Background
Project Overview
Burnie City Council is proposing to construct and operate an on-site wetland treatment and
disposal system for management of Stage 1 landfill leachate generated at the Burnie Waste
Management Centre (BWMC), Burnie, Tasmania (Figure 1).
The project is part of a federally funded Stormwater Infrastructure Development Project
(SIDP). The goal of this SIDP Project is to deliver a stormwater improvement program across
the Burnie City that will reduce discharge and infiltration to TasWater’s waste water network
by at least 1.9ML per day, within a total cost of $4.25 million. This project was due to be
completed by the end of June 2015. However, an extension of time has been granted to
complete the leachate treatment project by the end of June 2016.
The SIDP carries environmental and efficiency benefits, and ultimately it is a critical
investment in infrastructure-readiness to realise economic expansion opportunity for the
region. The leachate management project is critical to achieving the objectives of the SIDP
program, since it accounts for almost a third of the stormwater diversion target.
This proposal involves the design and construction of a treatment wetland system and
associated hydraulic and civil infrastructure at the BWMC to manage the Stage 1 Landfill
leachate. It also includes decommissioning of the current (Stage 1) leachate discharge system
to TasWater’s sewage network, and replacement of this with site infiltration (median flows) and
point discharge (large flows) of highly treated leachate into the un-named tributary of Cooee
Creek.
Unlike typical landfill leachate, the Stage 1 landfill leachate is low strength predominantly
comprising groundwater (>80-90%) due to compromises in the original construction and
landfilling practices resulting in the ingress of groundwater into the leachate collection system.
As such, the characteristics of the leachate stream are more akin to groundwater or
stormwater, than to leachate. The only contaminants exceeding the EPA Draf t Water Quality
targets for Cooee Creek are ammonium nitrogen and total nitrogen. There are occasional
exceedances of aluminium, chromium, copper, nickel and zinc.
Studies Completed and Current Project Status
A wide range of technical studies and reports have been completed as part of this project to
date, which form the basis of this DPEMP:
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 4
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Surface Water & Preliminary Soil and Sediment Investigation (and supporting sampling
quality plan) (an appendix in Syrinx Environmental PL, July 2014) – contained in
APPENDIX 1.
Burnie Waste Management Centre (BWMC) Stage 1 Landfill Leachate Treatment
Study – Option Development and Evaluation and Preferred Option Concept Design
(Syrinx Environmental PL, July 2014) – APPENDIX 1.
Natural Values Assessment Report (NEST July 2014) - APPENDIX 2.
EPBC Referral documentation (BCC Nov 2014) and EPBC assessment. The EPBC
assessment is contained in - APPENDIX 3.
Addendum to Stage 1 Landfill Leachate Treatment Study – Design Changes &
Alternative Wetland Option Assessment (Syrinx Environmental PL May 2015) –
APPENDIX 4.
Assessment of Alternative Leachate Management Options (BCC May 2015) -
APPENDIX 5.
Hydro‐geotechnical Investigation and Risk Assessment Version 2, August 2015
(Tasman Geotechnics August 2015) - APPENDIX 6.
BCC Mooreville Road Hydrological Runoff Assessment (Tasmanian Consulting
Service, April 2015, provided as an appendix in Tasman Geotechnics August 2015) –
APPENDIX 6.
These studies were provided to the EPA as part of the NOI submission in Sept 2015.
The proposal is currently in the design phase, with a view to construction in Feb – Jun 2016.
The project timelines are driven by the SIDP, which will require this project to be substantially
delivered by end June 2016, otherwise the funding will need to be returned or re -appropriated,
and this project will not proceed.
Physical Components of the Proposal
The key physical elements of the proposal are as follows:
Refurbishment of the main Stage 1 leachate pumping station to separate leachate from
site stormwater flows and incorporate a sedimentation trap. NOTE: stormwater is being
managed as a parallel project on site. This will incorporate capacity and treatment
improvements across the site.
Installation of new pumps, rising mains to the wetland and sediment traps to ensure
efficient and sufficient duty and standby capacity to convey large flow events (>50
year) and to ensure appropriate sediment controls are in place to prevent pump wear
and protect the capacity of the chamber.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 5
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Construction of an emergency leachate overflow storage tank to enable gravity
conveyance and storage of overflows due to pump failure, from the leachate manhole
chamber and gravity return to the leachate manhole chamber as levels subside.
Decommissioning of the existing TasWater sewer discharge point and construction of a
new gravity connection downgradient of the emergency storage tank, as a final
contingency against non‐compliant flows.
Construction of the treatment wetland itself on the Stage 1 landfill cap, comprised of
the following components:
o Inlet sedimentation/precipitation pond – for removal of iron, manganese and
other metals to prevent clogging of wetland. Limestone or limesand will be
incorporated in this pond to elevate pH.
o Surface flow (horizontal) wetland – multiple cells in parallel to allow draining,
maintenance and operation of each cell depending on flows.
o Subsurface flow (horizontal) biofilters (2 in parallel) to promote denitrification
primarily.
o Polishing wetland with adsorption media to allow further treatment and a
recirculation system to return water to the head of the system if non‐compliant.
Construction of an infiltration wetland within the northern boundary of the site to
enable infiltration of compliant treated water.
Construction of an overflow pipe and swale to discharge to the existing unnamed
tributary of Cooee Creek in large flow periods.
A preliminary site layout plan showing the major components is provided in APPENDIX 7.
Best Practice Management
The perceived best practice management of municipal solid waste and landfill leachate has
altered significantly over the past 50 years, moving from unlined landfills with leachate
discharge to surface waters and/or aquifers, to fully contained ‘dry’ landfills and disposal of
leachate predominantly to sewer, to ‘wet cell’ (bioreactor) landfills and on‐site treatment and
discharge of leachate. There is a growing number of projects globally that look to redevelop
existing landfills and post‐closure landfill redevelopment is becoming recognised as part of the
sustainable landfill management process.
These shifts reflect better controls on waste management and recycling, better understanding
of landfill processes, concerns around the long‐time scale required for management of dry
containment landfills since degradation processes are extremely slow, and an appreciation of
issues associated with discharging leachate to wastewater treatment plants. Hence,
enhancing the rate of degradation of landfill waste (wet landfills) and enabling leachate
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 6
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
treatment and discharge to the environment using ‘state‐of‐the‐art’ technologies and risk
assessment methods is becoming the new standard globally (see review in ARRPET 2007).
Discharge of landfill leachate to sewers is not considered best management practice due to
compromises in the WWTP associated with leachate composition and/or hydraulic loading,
and because this does not concur with sustainability principles and guidelines within Australia
and overseas that promote on‐site leachate management. Sewer discharge is discouraged in
some countries (e.g. Sweden) via legislative measures and stringent requirements of
wastewater treatment plants for acceptance of incoming industrial wastewater. Most Australian
mainland states (e.g. Queensland, WA) do not permit disposal of leachate to sewer unless a
strong case can be mounted to justify this approach. On‐site treatment and discharge of
leachate to the environment is becoming a preferred global approach. Treated leachate
discharge to fresh water ecosystems is currently practiced in South Africa (e.g. the
Buffelsdraai and Mariannhill landfill sites in Durban), Scandinavia, the US, UK and Australia.
The BWMC scenario is interesting in that the cell, while designed as a dry containment cell,
operates as a ‘wet’ cell in reverse; that is, whilst there is little infiltration of rainwater due to a
competent surface cap, there is upward migration of groundwater into the landfill cell due to
compromised groundwater drainage pipes. Hence, the Stage 1 landfill has operated
(unintentionally) as a modern upflow bioreactor cell. This accounts for the low strength ‘raw’
leachate quality (as indicated from leachate seepage data, Section 5.2.5).
Costs & Benefits
The capital cost of this project is approximately $2 mill. The proposal will not generate a direct
product however will provide important 1. environmental benefits - including reinstating
environmental flows to the Cooee Creek tributary (approximately 400 m3 day on average of
clean groundwater is currently mixed with leachate and diverted away from the catchment to
sewer); 2. community benefits - the wetland system is a community asset providing
educational and research values; 3. economic benefits – the system will free up capacity in
the TasWater sewer system which will enable expansion of key economic growth projects.
1.3.2 Regional Context
As described above, this project is part of a federally funded Stormwater Infrastructure
Development Project (SIDP) intended to deliver a stormwater improvement program across
the Burnie urban area. The direct result of this Stage 1 Landfill Leachate Treatment Project
will be to release significant capacity (up to 600kL/day) at the waste water treatment plant at
Round Hill and its associated pipe network and pump stations, to handle the forecast waste
water flows from the new Lion cheese processing plant, a lead enterprise for the expansion of
the dairy industry on the north-west coast of Tasmania and other similar enterprises.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 7
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
This project is being undertaken along with stormwater treatment and creek enhancement
works within the site (see Section 2.2.7). It is expected these works will occur concurrently
with this leachate treatment project.
1.4 LEGISLATIVE CONTEXT
1.4.1 Relevant Legislation, Regulations, Codes and Policies
Legislation, regulations, policies and guidelines that are relevant to the Burnie project include
the following:
Commonwealth
Environment Protection and Biodiversity Conservation Act 1999.
State
Environmental Management and Pollution Control Act 1994 (EMPCA) and associated
policies and Regulations.
State Policy on Water Quality Management (EPA 1997).
Water Management Act 1999 and associated Regulations.
Workplace Health and Safety Act 2012 and the Work Health and Safety Regulations
2012.
Environment Protection Policy (Air Quality) 2004.
Threatened Species Protection Act 1995.
Weed Management Act 1999 and the Weed Management Regulations 2000.
1.4.2 Commonwealth Assessment Process
Under the Commonwealth’s Environmental Protection and Biodiversity Conservat ion Act 1999
(EPBC Act) the proposed actions (‘the project’) cannot proceed if they have or a re likely to
have a significant impact on any of the matters of environmental significance without referral
to the Department of Sustainability, Environment, Water, Population and Communities, and
approval from the Australian Government environment minister.
A referral of the Burnie project was made under the EPBC Act on 12th November 2014. The
outcome of this referral was that the proposed project is not a controlled action. The EPBC
referral decision is included in APPENDIX 3.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 8
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
1.4.3 State Legislation & Assessment Process
The Environmental Management and Pollution Control Act 1994 (EMPC Act)
This is the primary environment protection and pollution control legislation in Tasmania.
Section 27B(2) of the EMPC Act states that a Notice of Intent (NOI) document may be
prepared and submitted the Board of the Environment Protection Authority (the Board) to
enable the Board to determine the class of assessment and to develop project-specific
guidelines for the case assessment.
In line with this, BCC submitted a NOI document (Notice of Intent – Construction of a Leachate
Treatment Wetland and Infiltration/Discharge of Treated Leachate to an Unnamed Tributary of
Cooee Creek, North West Tasmania) and all supporting documentation on the 7th
of
September 2015 .
The EPA undertook an assessment of the provided information and determined the proposal is
a ‘level 2 activity’, as defined in the EMPC Act, being a Wastewater Treatment Works (clause
3(a), schedule 2 of the EMPC). The class of assessment was determined to be 2B as the
project is not considered to be a small-scale project with minor, localised environmental
impacts that can be readily mitigated through appropriate management (EPA September
2015).
Project Specific Guidelines were prepared by the Board identifying the key issues that have
been considered and addressed in the preparation of this DPEMP document (shown in Section
10.0).
State Policy on Water Quality Management (EPA 1997)
Any discharges to Cooee Creek or its tributaries is regulated by the State Policy on Water
Quality Management and will require EPA Board approval. This states the following key
principles for setting emission limits for discharge to surface waters (Division 2B, Section
16.2):
(a) The discharge limits must be set at levels which will not prejudice the achievement of water
quality objectives; and
(b) Pollutant discharges to the environment should be reduced to the maximum extent that is
reasonable and practical having regard to best practice environmental management, and in
accordance with the following hierarchy of waste management, arranged in decreasing order
of desirability:
(1) waste avoidance;
(2) recycling/reclamation;
(3) waste re-use;
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 9
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
(4) waste treatment to reduce potentially degrading impacts; and
(5) waste disposal.
The approach taken in developing the discharge strategy for this project followed this
hierarchy.
Environment Protection Policy (Air Quality) 2004.
The Environment Protection Policy (Air Quality) 2004 (the Air Quality EPP), provides a
framework for the management and regulation of point and diffuse sources of emissions to air
for pollutants with the potential to cause environmental harm.
The key environmental values of relevance to Burnie project that require protection under this
Act are:
The life, health and well-being of humans (on-site workers, neighbours and general
public) at present and in the future; and
The integrity of ecosystems and ecological processes within the key receiving
environment, which is the unnamed tributary to Cooee Creek.
Potential impacts on these values arising from the proposed project are discussed in Section
6.
Threatened Species Protection Act 1995
This Act provides the statute relating to conservation of flora and fauna. The aim of the Act is
to provide for the protection and management of threatened native flora and fauna and to
enable and promote the conservation of native flora and fauna. The Threatened Species
Protection Act 1995 is administered by the Department of Primary Industries and Water
(DPIW) and operates within the Resource Management and Planning System for Tasmania.
Under the Act, threatened species are given a listing category (endangered, vulnerable or
rare) depending on the extinction risks the species face.
Potential impacts of the project on the threatened flora and/or fauna species are discussed in
Section 6.3.5.
Weed Management Act 1999
The Weed Management Act 1999 is the principal legislation concerned with the management
of declared weeds in Tasmania. The Act provides for the control and eradication of weeds
focusing on:
(a) minimising negative effects of weeds on the sustainability of Tasmania's productive
capacity and natural ecosystems; and
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 10
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
(b) promoting a strategic and sustainable approach to weed management; and
(c) encouraging community involvement in weed management; and
(d) promoting the sharing of responsibility for weed management between government,
natural resource managers, the community and industry in Tasmania.
Appropriate, sustainable management of weeds underpins the proposed wetland treatment
system design (Section 2.2) and the Environmental Risk Assessment (Section 6.3.6).
Numerous management actions are proposed and will be implemented during the system’s
construction and operation which focus on weed management (Section 6.2.4). These will
contribute to the overall enhancement of the creek and surrounding environment.
1.4.4 Management Plan
The following will be developed to ensure good environmental practices on site and to
minimise any risks associated with the system construction, commissioning and operations, as
delineated in the environmental risks assessment undertaken for the project (see Section ):
1. Operation and Maintenance Plans will be developed and will detail the required
maintenance activities and frequencies.
2. Existing risk management plans will be updated regularly, to include responses to
incidences potentially connected with the treatment system.
3. Appropriate training of staff responsible for system maintenance will be undertaken,
including preparation of user-friendly management and maintenance plans.
1.4.5 Existing Permits & Manuals
BCC has operated the Stage 1 landfill under a Permit to Operate Scheduled Premises
Conditions issued by Department of Primary Industries, Parks, Water and Environment
(DPIWE, formerly Department of Environmental and Land Management). In 2004 DPIWE
issued a new Environmental Protection Notice (EPN) for the site, and since then the Stage 2A
landfill has been operating in accordance with this EPN and two additional update EPNs as
follows:
EPN 7007/1 (issued on the 18th
November 2004), is the current main EPN for the site,
issued after the DPEMP for the Stage 2 landfil l area was approved.
EPN 7007/2 (issued on 7th
October 2005) amended the reporting cycle from a calendar
year arrangement to a financial year arrangement, as per the request of BCC.
EPN 7007/3 (issued on 20th
April 2006) stipulates that waste data must be reported
against processing routes, the primary source and secondary source (where possible).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 11
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
The BMWC landfill operations are managed in accordance with an environmental management
manual titled, Mooreville Road Landfill – Environmental Operations Manual (prepared by
Mienhardt Infrastructure and Environment, April 2005). BCC undertakes regular water quality
monitoring and reporting in accordance with EPN monitoring requirements. The monitoring
program includes sampling, testing and reporting of groundwater bore holes, surface water
locations and leachate flows. Sampling is undertaken on a quarterly basis and quarterly
monitoring reports as well as the annual reports are submitted to the EPA for review.
2.0 PROPOSAL DESCRIPTION
2.1 PROJECT NEED
Treatment and diversion of the mixed groundwater-leachate stream at the Burnie Waste
Management Centre is a critical component of the federally funded Stormwater Infrastructure
Development Project (SIDP) as described previously. This project accounts for almost a third
of the stormwater diversion target.
The core project drivers for this project and the SIDP program more broadly are:
1. Recurring environmental issues associated with the current leachate management,
including:
a. Occasional leachate overflows to the adjacent creek/stormwater system
(Cooee Creek unnamed tributary) in high rainfall events.
b. Leachate seepage episodes in very large rainfall events or extended rainfall
periods.
c. Groundwater incursion into the leachate collection system significantly
increasing the overall leachate volumes requiring treatment and management,
and causing a reduction in environmental flows to the receiving Cooee creek
unnamed tributary.
d. Capacity limitation of the existing sewer network, which currently results in raw
sewage and raw leachate overflows in events greater than the 1:10 year ARI
directly into Cooee Creek (TasWater pers. comm.).
e. Capacity limitation of the existing WWTP network. TasWater are strongly
supportive of the proposal to remove leachate from the daily Round Hill WWTP
load due to issues with hydraulic loading and other well established issues
associated with its composition. TasWater has advised they are working toward
strongly dis-incentivising disposal of landfill leachate and other trade waste to
sewer over the coming years.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 12
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
2. Economic issues including:
a. Long-term cost to maintain discharge to the TasWater sewer system
particularly in context of recent and anticipated future escalation of trade waste
charges implemented across Tasmania that will most certainly make leachate
disposal to sewer cost-prohibitive.
b. Issue of limiting TasWater from being able to take additional waste from the
Lion cheese factory and other enterprises due to capacity constraints of the
sewer and WWTP.
3. Potential community issues given that escalation in charges for sewer disposal will
flow on to the community via rates and also due to potential exposure to leachate (and
sewage) along the creek during storm events.
2.2 DETAILED PROJECT DESCRIPTION
2.2.1 General
The project essentially involves the use of constructed wetland technology to remove the low
level contaminants from the Stage 1 leachate, the use of an extensive infiltration ‘wet forest’
area for indirect discharge of treated water within the BWMC land, and the construction of an
overflow discharge point to the unnamed tributary of Cooee Creek, at the northern boundary of
the site, adjacent private land. Improvement works to the creek are also included.
This proposal is associated with an existing activity on site, which is the Burnie Waste
Management Centre (and former landfill site). It is currently regulated via existing
Environmental Protection Notices (EPNs) (see Section 1.4.5). This project is part of the overall
landfill closure planning for the site, focussed on leachate management for the Stage 1 landfill
cell, which was decommissioned in 2004/5.
Location Map & Site Plan
A general location map with site images is shown in Figure 1. The land boundary is shown in
Figure 2. Note the middle red line in Figure 2 indicates two separate titles. The land boundary
is the outer red line.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 13
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 1. Location of the Burnie Waste Management Centre and the Stage 1 landfill
Top of Stage 1 landfill looking east. Trees
mark property boundary/buffer
Stage 1 leachate pump station looking
north toward Cooee Creek tributary.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 14
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 2. Land boundary, site layout and location points
Site boundary
point Latitude Longitude
1 41° 04'51.26"S 145°52'35.89"E
2 41° 04'51.59"S 145°52'39.26"E
3 41° 04'49.61"S 145°52'39.73"E
4 41° 04'51.29"S 145°52'55.07"E
5 41° 05'00.91"S 145°52'52.94"E
6 41° 05'10.56"S 145°52'50.85"E
7 41° 05'08.78"S 145°52'36.36"E
8 41° 05'09.88"S 145°52'32.60"E
9 41° 05'07.99"S 145°52'29.82"E
10 41° 05'05.48"S 145°52'27.52"E
11 41° 05'01.37"S 145°52'32.58"E
12 41° 04'58.77"S 145°52'34.31"E
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 15
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 3. Site Plan showing landfill stages
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 16
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
2.2.2 Current Stage 1 Leachate Management
The existing layout of the site showing the current leachate collection and conveyance network
is shown in Figure 4, and leachate process sketch in Figure 5. Leachate generated in Stage 1
of the landfill is currently collected in the northern pump well (MH1) down gradient of the
landfill area and pumped into TasWater’s sewer reticulation system for treatment at the
Roundhill WWTP. This stream is a combined leachate and groundwater stream (refer Section
5.2.4).
During dry and moderate rainfall periods (low flows), leachate collected in the northern pump
station (MH1) is directed (pumped) into the adjacent 150 dia. gravity sewer pipe. The capacity
of the pump at MH1 from Stage 1 is around 17 L/sec. High level alarms are fitted to the pump
stations which are connected to Council’s telemetry alarm. However, during extended or
intense periods of wet weather when the combined leachate-groundwater flow is high, the 150
dia. gravity sewer pipe does not have sufficient capacity to convey the flow. To overcome the
150 dia. sewer pipe capacity limitations, flow is pumped from the northern pump well via an
overland 100 dia. PE rising main to the leachate pond located near Stage 2A cell. From there,
it is pumped via an 80 dia. uPVC rising main along Mooreville Road to discharge into
TasWater gravity system beyond the zone of pipe capacity limitation. The pump capacity of
the leachate pond is also 17 L/sec.
On two occasions in the last few years, leachate has almost overflowed from the leachate
pond into the adjacent creek/stormwater system.
There is a weir in the northern pump well to separate leachate from stormwater. If the power
fails or pump problems occur, leachate will overflow the weir and enter the stormwater/creek
system. If the 150 dia. gravity sewer pipe is overloaded, leachate (comb ined with sewage from
site amenities) may enter the stormwater system and flow into the creek.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 17
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 4. Burnie Waste Management Centre Site Plan
Stage 1 leachate pump station and
MH1 cover.
Stage 1 leachate/stormwater manhole
chamber (MH1) showing baffle
separator.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 18
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 5. Process sketch showing existing leachate management (from BCC)
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 19
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
2.2.3 Proposed System Summary
Design Objectives
The following have been set as design objectives for the proposed wetland and associated
infrastructure/works:
Separation of individual water streams generated within the landfill site (leachate,
stormwater and leachate seepages) to manage peak flows and minimise risks of direct
discharge of untreated flows to Cooee Creek tributary.
Incorporation of a gravity overflow pipe and emergency storage tank from the raw
leachate chamber that prevents raw leachate flows overflowing to Cooee Creek
tributary.
Provision of a multi-stage treatment system with excess capacity, operational flexibility
and multiple contingencies to optimise treatment performance and risk management.
Incorporation of design features that enable progressive adaption and responses to
changing water quality and volumes, resulting from climate change and changes in
landfill leachate characteristics.
Restoration of biodiversity values within the landfill site and the immediate discharge
environment.
Creation of a wetland attraction/feature within the site that could eventually be opened
to the public with educational, research and interpretative opportunities.
Design Criteria
The following criteria apply to the design of the proposed wetland, which reflect the
environmental, hydrological and geotechnical constraints associated with the project setting.
These are discussed in detail in Section 5.0.
Treatment of contaminants to the set Water Quality Targets for discharge to Cooee
Creek tributary, which are in line with the EPA Draft Water Quality Objectives for
Cooee Creek and ANZECC Water Quality Guidelines (2000) and incorporate findings
of the creek-specific water quality monitoring undertaken for this project (refer to
Section 5.2.7).
A requirement to use plant species endemic to the area and local to Tasmania to
prevent weed issues, species appropriate to the hydrological regime and water quality,
species that will enhance the biodiversity values of the site and wider area.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 20
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Ability to appropriately treat (i.e. to the set water quality standards) up to the 90
percentile flows (note, 90 percentile flows calculated on present flow data as 600
m3/day).
Provision of back-up contingencies in case of power failure, maintenance outages and
storm events, including emergency storage tank.
Ability to detain and treat the leachate flows generated in >50-year storm events by
providing sufficient capacity within the wetland and pump system to deliver and contain
3500 m3 for 24-hours of flows (>80-year event).
Capacity to intercept and treat leachate seepages generated in extreme rainfall events
to prevent direct discharge of untreated leachate to the creek.
Provision of sufficient contingencies to enable recycling of leachate if treatment
standard is non-compliant with discharge standards, and/or for leachate volumes
beyond the pump capacity of the main system (i.e. extreme events).
Sizing of the wetland freeboard and pipework infrastructure to contain the direct
volumes generated in a 1000 year ARI rainfall event to avoid overflows. Hydrological
modelling indicates that direct rainfall volumes generated in a 1000 year rain event
could be accommodated within the wetland system with a freeboard of 182 mm, hence
a minimum freeboard is set at 200 mm.
Height of wetland bunds to be no greater than 2 m to prevent potential excessive
settlement on the landfill cap.
For all wetland cells, allowance of a setback buffer of a minimum 10 m from the landfill
bund wall and central stormwater swale on top of the landfill cap, and 10 m from the
toe of the northern embankment, to ensure no compromise to landfill stability.
Design should accommodate settlement of the wetland over time in line with predicted
landfill settlement rates (see Section 6.1.2 and APPENDIX 6).
2.2.4 System Components & Processes
The proposed treatment wetland will be a combination of parallel components in series to
enable single operation in low flows and/or maintenance events. The components are as
follows:
1. Modified manhole and pump station for conveyance of flows to the wetland.
2. Pre-filter – iron/manganese drop out pond.
3. Vegetated surface flow wetland- aerobic system for promotion of nitrification and
precipitation of any residual metals.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 21
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
4. Vegetated subsurface flow wetland – anaerobic media filled beds, operating
intermittently to promote denitrification.
5. Polishing wetland (aerobic) with outlet monitoring point and recirculation pipe for non-
compliant water.
6. Infiltration ‘Wet Forest’ – to enable highly treated water to further attenuate residual
nutrients/contaminants through the soil profile and promote diffuse subsurface release
to the unnamed tributary to Cooee Creek.
7. Phytoremediation swale – to intercept and divert for treatment leachate seepage flows
that can occur at the bench on the northern embankment during extreme rain events.
The following physico-chemical and biological processes dominate the treatment sequence:
Aeration – reduces the COD/BOD demand, promoting oxidation of organics and
reduced forms of metals, metalloids.
Volatilisation – removes simple organics from the water matrix to the atmosphere.
Filtration (entrainment & settlement) – physically removes suspended solids and
pathogens from the leachate stream.
Passive chemical oxidation and precipitation – converts dissolved metals/metalloids
into particulate forms, which are then removed by filtration and precipitation. Metals
precipitate in the form of insoluble carbonates and hydroxides (in aerobic and
anaerobic conditions).
Attachment & adsorption – metals/metalloids, organics, pathogens and colloids adsorb
to media, biofilms and plant roots/rhizomes.
Ion exchange – the sediments of wetlands and high cation exchange media such as
volcanic and organic media act as ion exchange sites for metals.
Solar disinfection – destroys pathogens via UV radiation.
Biodegradation – converts organics and nutrients to inert forms, including to gaseous
phases or carbon sources for plants. Occurs on biofilms attached to media and plant
root/rhizomes. These processes are mediated by bacteria, fungi, yeast and algae.
Phytoremediation – reduces contaminants in the leachate stream via plant uptake and
accumulation of metals, nutrients, hydrocarbons and salts.
A general site arrangement is shown in Figure 6. A process schematic is provided in Figure 7.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 22
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 6. General site layout showing location of major components & access points
for construction and maintenance.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 23
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 7. Process diagram showing proposed collection & conveyance infrastructure works
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 24
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Construction Material Details
The general construction material components are as follows:
1. Liner: Existing landfill clay cap levelled and stripped of topsoil; 2 mm LLDPE (linear
low density polyethylene) liner.
2. External Bunds: Clay won on site 2 mm LLDPE liner.
3. Internal Bunds: Clay won on site. Note seepage through internal bunds is not an issue
since leachate is contained by the base liner and external bunds.
4. Media: The pre-treatment cell will contain 0.4m depth of limestone spalls (~10mm dia)
in the first half of the cell to increase alkalinity. The surface flow wetlands will only
contain topsoil over the liner (mainly won from site but some additional material may
need to be imported). The subsurface flow wetland is to contain 0.6m depth of clean
washed lightweight volcanic media (scoria or local alternative material). The polishing
wetland contains a small area of zeolite (0.2 m depth) and topsoil in the remainder.
5. Wetland Hydraulic Infrastructure: All major conveyance pipework will be constructed of
HDPE of appropriate size and class. Internal distribution pipework within cells will be
slotted PE or uPVC. Outlet controls will include adjustable weirs to allow variable
operating depths and siphon pipes to facilitate full drainage and control detention
periods. Adjustable weirs will be concrete with timber birdsmouth sheeting. Sufficient
grades will be provided for all pipe connections to allow for settlement of the landfill.
6. Plant Species: Species selection has been based on those species which have been
successfully used previously in constructed wetlands with similar hydraulic regimes
and compositions, and which occur locally in the area and hence are well adapted to
local conditions and do not pose weed issues to the surrounding creek and other
remnant vegetation areas. The species list includes rushes and sedges
(predominantly from the families Cyperaceae and Juncaceae) within the wetlands, a
range of local shrubs and herbs on the bunds, and a range of trees, shrubs,
sedges/rushes and trees within the infiltration area to maximise ET losses and
biodiversity benefits.
The infiltration ‘wet forest’ will use species typical of the Wet Sclerophyll Forest type
on lower slopes (dominated by stringybark eucalypts, Eucalyptus obliqua). This is
present as remnants within the local region and was present historically. Note, no trees
species will be used on top of the landfill cap.
The indicative species list has been derived from the Burnie Planting Guide, local
nursery lists, Tasmania Flora census lists and previous species lists used by Syrinx for
projects within Tasmania, and is contained in APPENDIX 9.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 25
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Detailed Components
A summary process description for each component provided below. Preliminary design
drawings are provided in APPENDIX 7.
Manhole Pump Station, Rising Main and Stormwater Modifications
This project will involve modifications and refurbishment to the existing raw leachate collection
and conveyance infrastructure as follows and as shown in Figure 7, Figure 8 and Figure 9:
Retain and refurbish the existing leachate pump station (MH1). Install a new sediment
chamber ahead of the manhole to facilitate sediment collection and removal.
Decommission the stormwater line between MH2 and MH1 and seal the pipe inlet to
the MH1 chamber.
Repurpose and modify the existing stormwater outlet pipe from MH1 to connect raw
leachate to the emergency leachate storage tank (activated at a set water level)
(Figure 9).
Install a new rising main (possibly two lines, one for average flows and one for peak
flows) from MH1 to the wetland inlet. The inlet will be a splitter box arrangement to
enable separation of high flows and average flows within the wetland feed system.
Install a new high efficiency duty duty pump optimised for average flow delivery (~5-
7L/sec) with peak pump capacity of 18L/sec, and maintain the existing pump (23L/sec)
as duty standby (in case of pump failure and for peak flows). The combined capacity
will be 43L/sec, or 3,542 kL/day.
Construct a new stormwater pipe connection from MH2 to MH3 (Figure 8, Figure 9).
Construct new pipe from MH3 to head of new stormwater treatment swale. Retain
existing 1050 dia pipe outlet to creek for high flow discharges. Stormwater
swale/wetland to extend between MH1 and the creek for treatment of average
stormwater flows (1 in 1 year).
Construct new MH4 with sediment capture and connect new 150 dia leachate line into
this chamber (Figure 8).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 26
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 8. Proposed modifications to the leachate collection and conveyance infrastructure, and construction of emergency control infrastructure
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 27
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 9. Proposed alterations to MH1 (leachate) and MH3 (stormwater)
The conveyance pumps are serviced by site power, however a back-up generator will be
installed to ensure continuous pumping during power outages. The variable speed
submersible pumps are 3.4 kW capacity with an estimated power draw of ~12,000 to 20,000
kWhrs per annum, inclusive of peaks. The recirculation pump to return non-compliant flows
from the polishing wetland back through the treatment circuit is a solar operated pump, hence
has no grid power draw and no emissions.
The operational life of the pumps is estimated at 15 years. The life of all other associated
infrastructure (pipes, manhole chambers etc) is 50 years or longer.
The rising main will be a single 200 mm HDPE line or dual 150 mm lines. This will be
determined based on the most efficient arrangement for the selected pumps (duty duty
20L/sec (average 8L/sec daily cycle) and duty standby 23 L/sec).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 28
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Pre-filter (Inlet) (Cell 1)
The Constructed Wetland comprises a range of different cells performing different functions in
a treatment train arrangement.
The Prefilter is the inlet pond to the wetland system designed to assist in the precipitation and
settling of low level metals (principally iron and manganese), as well as to dissipate flows and
equalise volumes to enable steady and distributed flows to the main wetland system. To
facilitate metal drop-out, the first part of the pond is to be filled to 0.3 – 0.5 m depth with local
limestone stones (10mm dia); the last half of the pond is to be kept clear of rocks to enable
sludge removal in time. This is not expected to occur more frequently than every 5-10 years
since the TSS of the leachate is low.
The inlet to the Pre-filter will receive pumped water from the manhole chamber (MH1), which
is to be distributed in a deep rock-lined distribution channel along the length of the pond and
approximately 1m wide, to dissipate flows. The deeper open water areas of the Pre -filter are to
allow for settling, flow equalisation and aeration, while the shallow thick vegetated areas
encourage plant and microbial filtration and pollutant uptake.
The pre-filter discharges to the surface flow wetland via a series of adjustable weirs, spaced
evenly to ensure even flow distribution.
Surface Flow Wetland (10 cells)
This component is designed to maximise the removal of ammonium nitrogen and is to be
aerobic. The surface flow wetland is configured so as to distribute flows into four pairs of cells
in series, with the system operable in four separate streams to facilitate flow control and
maintenance. Flow is horizontal in all cells, and is controlled by manual operated valves that
will be adjusted twice yearly as follows:
From June/July to Oct of each year – all cells on maximum flow. This corresponds with
the largest inflows to the system since groundwater contributions are highest during
this period.
From Nov to May of each year - cells cycled off in series to enable drawdown and
reoxygenation of sediments, any other maintenance, and then returned to low flow
conditions.
During very low flow periods (150 kL/day or less), only some cells will operate to prevent
stagnation and generation of organics. Other cells will receive intermittent flows to avoid
drying of sediments.
The total area of the 10 cells is approximately 1.1 ha and this component has an average
residence time of 10 days.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 29
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
The outlets of the surface flow wetland cells discharge to the subsurface flow wetland, with
sufficient hydraulic grade between weirs to facilitate gravity flow. A typical section through the
surface flow wetlands is shown in Figure 10.
Subsurface Flow Wetlands (3 cells)
This component is designed to maximise the removal of nitrate and is to be anaerobic. The
inlet to the subsurface flow wetlands (SSFW) is via four perforated distribution pipes set just
below the surface of the wetland. Flow is downward vertical. Multiple cells are required to
allow intermittent operation of each cell, to maximise nitrification-denitrification and facilitate
maintenance. The cells are to be 600mm depth and filled with scoria or similar volcanic media
with high cation exchange capacity and high surface area. The combined system is to be
approximately 2500 m2, 0.6m depth, fully vegetated, and allow an average detention of 2 days
to optimise denitrification. Beds would operate intermittently to optimise anaerobic conditions.
Treated leachate from these cells discharges into the polishing cell.
Polishing Surface Flow Wetland
This cell provides additional polishing of the leachate prior to discharge to the infiltration ‘Wet
Forest’. This cell would act as the performance monitoring point. The cell would be vegetated
except at the outlet weir which would be constructed as a deep open water zone to avoid
incursion of vegetation. This cell would incorporate zeolite and possibly other amendments to
polish residual ammonium via adsorption.
The discharge outlet structure for this cell would have a slow release pipe for average
treatment flows, while outflows above the normal discharge level/pipe capacity would rise and
be detained. Treated flows would then either discharge over a weir structure if water quality
compliance is maintained, or be recirculated back to the surface flow wetland if not complian t
(i.e. installed monitoring sensor triggers this requirement for indicator parameters (i.e. NH 4-N,
pH, conductivity). A recirculation pipe and pump will be installed to enable return of flows to
the treatment network if they are non-compliant.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 30
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 10. Typical section through surface flow wetland.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 31
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Infiltration ‘Wet Forest’
The northern area of the landfill site down-gradient of the Stage 1 landfill has been reserved
for infiltration/evapotranspiration, and would be revegetated as a ‘Wet Forest’, or infiltration
wetland (Figure 11 and Figure 12). This enables the recharge of treated leachate to the
aquifer and eventual discharge of these waters to the unnamed creek via subs urface flows.
There is approximately 6m separation distance between the base of the wetland and the
superficial aquifer, which is under artesian pressure at this location. Hence, further
attenuation of residual nutrients would occur through this process.
Using a conservative infiltration rate of 1*10^-6
(typical permeability point recorded in Coffey
shallow bores for sandy clay/silty clays, Coffey 2007) shows that >90% of summer‐autumn
flows and >75% of winter‐spring flows will be infiltrated within this zone and report as
subsurface discharge to the creek (which mimics the normal hydrological regime for this creek
and others in this region) (see also Section 5.2.6).
This wet forest area allows for further attenuation of contaminants through the soil and via
plant root activity, as well as a more natural subsurface recharge regime to the creek for the
majority of the time. To accommodate the grade changes, this area would be bunded and
terraced to reduce the slope and optimise vertical infiltration/ET losses. Flows in excess of the
infiltration capacity would discharge via a weir/cascade outflow to the creek.
Emergency Storage
Given the leachate will need to be pumped to the inlet of any treatment system (due to depth
of leachate collection pipes and height of available treatment area), some provision for peak
flows in excess of pump capacity is required. An emergency storage tank is therefore
incorporated downgradient of the raw leachate chamber to enable gravity overflow from the
manhole to this storage tank.
Raw leachate overflows from the MH1 which occur as a result of either extended duration non-
compliant flow, or dual pump failure (i.e. both duty and duty standby pump outage) are
proposed to be managed via a 150 kL partially buried emergency storage tank. Leachate
would rise within the current manhole and overflow to the tank. This tank provides 6 hrs
storage for the 90 percentile flows and ~10 hrs storage for average daily flows. This is
considered sufficient time to repair pumps or reinstate power or back-up power to the pumps
(if these have failed).
Flows from this tank would drain (via gravity) back to the MH1 pump station when the system
is repaired (see Figure 8).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 32
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 11. Long section showing proposed infiltration wet forest, stormwater swale for treatment of low flows and modified creek discharge
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 33
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 12. Cross section showing proposed infiltration wet forest, stormwater swale for treatment of low flows and modified creek discha rge
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 34
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Leachate Seepage Phytoremediation Swale
An interception swale planted with medium and deep rooted vegetation is proposed along the
northern containment bund where seepage events have occurred in very high, extended
rainfall events. This is intended to intercept subsurface flows continually, and to enable
capture and remediation of seepage expressions as they occur. This swale would be pervious
but part filled with limestone stones to provide an alkalinity buffer to seepage waters, and
prevent acidification of soils. Plant species with metal tolerant and uptake capabilities would
be preferenced as shallow rooted vegetation. Flows in excess of infiltration treatment capacity
will be discharged to the MH1 chamber. Species selected will be locally native and members
of Cyperaceae (sedges), Juncaceae (rushes) and Restionaceae (Southern Rushes) , proven in
phytoremediation.
Creek Discharge
Flows in excess of infiltration capacity will discharge via a new pipe discharge, embedded
within a rock cascade, to the unnamed creek tributary (Figure 11 and Figure 12). The
discharge works will be tied into the proposed creek restoration works, and will be positioned
within the BCC site boundary. An on-line ultrasonic clamp on flow meter (or similar) will be
installed to automatically monitor discharge flows and activate and alarm to trigger manual
sampling. The creek discharge will be the final compliance monitoring point.
Connection Infrastructure to Existing Taswater Sewer Network.
Currently, the Stage 1 leachate is discharged to the TasWater sewer network via a pump
located within the MH1 chamber, to an existing sewer manhole (MH) (Figure 5). A minor
leachate pipe (Ø150) discharges directly to the sewer MH. In large events, leachate is pumped
via a rising main to the main Stage 2 leachate storage pond, and is discharged to sewer from
this point.
This proposal will decommission the two existing Stage 1 discharge points (the leachate pond
and sewer connection will be maintained for Stage 2 leachate flows). A new gravity connection
point (new manhole) will be constructed immediately downgradient of the emergency storage
tank, which will be activated when levels within the emergency storage rise. The proposed
location of the new manhole MH5 is shown in Figure 8.
The requirements for discharge to sewer are as shown in Figure 8, and are limited to pump
failure, and wetland non-compliance. The pump and pipe network along with excess capacity
within the wetland and emergency storage can effectively detain leachate flows generated in a
>80 year peak event (the wetland has 3,600 - 5,500 m3 of freeboard capacity within the
system depending on seasonal adjustments to operating water levels). The 24 hr 100 year
storm event leachate flows have been estimated at ~3,600 m3/day (Syrinx 2014, APPENDIX
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 35
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
1). However the wetland may not effectively treat the leachate flows during a 24 hour >80 year
event, hence slow release discharge may occur on the days following the storm event.
Off-site infrastructure
No new off-site infrastructure or ancillary facilities are required to support this proposal.
2.2.5 Wetland Capacity and Performance
To size the wetland, detailed modelling was undertaken using average and median daily and
monthly flows for the period 2010-2014, mean monthly concentrations of leachate pollutants,
and temperature and rate constant factors adjusted for the climatic setting and from previous
relevant Syrinx performance data. Capacity sizing was undertaken also using the 90 percentile
wet year to ensure adequate storage and treatment in wet years. The model used was a
modified first-order kinetic, sequential model based on Kadlec and Wallace (2008). The model
was run for the limiting parameter (ammonium nitrogen) for initial sizing, and included all
nitrogen species, phosphorus, TSS, metals and COD for detailed sizing.
A specific daily water balance model was built to determine daily flows and to determine the
spill over of flows from cell to cell, using rainfall and run-off data for the period 1968-2010 for
the Burnie BOM station. The required treatment area, operating depth/volumes, hydraulic
loading rates and hydraulic retention times are shown for each component in Table 1.
The expected performance of the system for the key contaminants is shown in Table 2.
Modelled performance data is presented for the three wettest months of the year (August to
October), which are characterised by the highest loads of key pollutants (nutrients) in a typical
year (see Section 5.2.4).
Note, while progressive pollutant removal through the treatment system and performance
efficiency of each system component was modelled using the approach outlined in Section
6.1.1, a conservative approach was taken such that once the set target concentrations are
achieved in the system, no further reduction was considered (although in reality pollutants will
be further removed in subsequent components as demonstrated by specific modelling outputs
for individual cells). Consequently, in Table 2 specific modelled data was presented only for
those system components where levels are above the set targets; once these targets are met
it is assumed that pollutant concentration will stay below these target levels.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 36
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 1. Wetland components and design details
OFF
LANDFILL
CELL
CELL 1
CELL 2 - MAIN
SURFACE FLOW
WETLAND
CELL 3 - SUBSURFACE
FLOW BIOFILTER
CELL 4 -
POLISHING
WETLAND
CELL 5
Pretreatment for
metal removalCell SF2A Cell 3 SSFA Cell 4
Infiltration
wetland
Cell area (m2) 500 11,000 2,500 500 4,000
Total depth (substrate & water) (m) 0.9 0.6 - 0.8 0.6 0.8 0.1
Substrate typelocal limestone
(10 - 50 mm dia)sandy clay scoria sandy clay
sandy clays /
silty clays
Substrate depth (m) 0.3 0.3 0.6 0 - 0.3 -
e (void space as %) 0.0 0.0 0.45 0.0
Operating water depth (above
substrate) (m)0.6 0.3 -0.5 0.0 0.5 0 - 0.1
Operating volumetric capacity (kL) 300 3,300 675 250 400
Min freeboard height (to
accommodate 1:1000 yr event) (m)0.2 0.2 0.2 0.2 0.1
Freeboard capacity 100 2200 - 4400 500 100 400
Peak volumetric capacity (extreme
event) (kL)395 7,590 1,150 350 800
HLR (q) (M/yr) 1.07 - 0.54 0.05 - 0.02 0.22-0.1 1.1 - 0.5 0.1 - 0
Theoretical detention time (d) 1 - 0.5 11.21 - 7.6 2.61 - 1.22 0.9 - 0.4 4.4 - 0.9
WHOLE SYSTEM Area (m2) 18,500
Detention time (d) 11 - 20
ON LANDFILL STAGE 1 CELL
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 37
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 2. Estimated performance of the proposed Stage 1 leachate treatment system (median for wet months August to October)
OFF LANDFILL
CELL
RAW
LEACHATE
CELL 1 -
PREFILTER
CELL 2 - MAIN
SURFACE
FLOW
WETLAND
CELL 3 -
SUBSURFACE
FLOW
BIOFILTER
CELL 4 -
POLISHING
WETLAND
CELL 5 -
INFILTRATION 'WET
FOREST'
SET
TARGETS
FUNCTION
▪ Inlet pond to the
system; flow
dissipation &
volume
equalisation
▪ removal of
ammonium
nitrogen via
oxidation (& TN
removal)
▪ removal of nitrate
- dinitrification (&
TN removal)
▪ further polishing of
treated leachate
▪ precipitation &
settling of low level
metals (mainly Fe
& Mn)
▪ removal of TP
& BOD
▪ removal of TP ▪ attenuation of
contaminants through
the soil & via plant
root activity
▪ removal of
suspended solids
▪ metal
precipitation
▪ removal of
coliforms
▪ provision of
subsurface recharge
regime to the creek
▪ aeration ▪ removal of
coliforms
Total Suspended Solids (TSS) mg/L 18.9 5.66 <5 <5 <5 <5 -
Biochemical Oxygen Demand
(BOD)mg/L 10 9.07 <5 <5 <5 <5 -
Total Nitrogen (TN) mg/L 7.9 7.5 2.22 1.6 <1.45 <1.45 1.45
Ammonium Nitrogen mg/L 7.9 7.1 1.70 <1.6 <1.6 <1.6 1.61
Total Phosphorus (TP) mg/L 0.036 0.035 <0.03 <0.03 <0.03 <0.03 0.03
Total Iron (Fe) mg/L 9.36 2.3 0.5 0.4 <0.3 <0.3 0.30
Total Manganese (Mn) mg/L 2.043 1.9 <1.9 <1.9 <1.9 <1.9 1.90
Faecal coliformsCFU/
100 ml260 202 <100 <100 <100 <100 100
ON LANDFILL STAGE 1 CELL
▪ polishing of
nutrients & metals
prior to discharge
to the infiltration
‘Wet Forest'.
Pollutant Removal (effluent conc. - cell outlet) - median for August to October
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 38
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
2.2.6 System Operation
Hours of operation – System Life
The system will operate 24 hrs a day, every day for the forecast life of the leachate treatment
system (minimum 20-30 years). The pumps will operate between 8-24 hrs per day. This is
equivalent to the current leachate pump operation cycle.
Vehicle movements - Construction
All materials will be supplied locally and will be transported to site via trucks. Most topsoil and
clay for bund construction will be sourced from site.
Truck movements into the site will be required for the delivery of:
1. LLDPE liner materials – 2 container loads (est), ex Melbourne by ship.
2. Topsoil (max 1500 m3) – 95 truck loads at 22 m
3 per load.
3. Machinery for construction works (mobilisation and demobilisation) – approx 15
machines (including 4 heavy load vehicles) and light vehicles (3 excavators, 4 site
trucks, 2 bobcats, 1 trencher, 1 grader, 4 utes), ex Burnie, by road.
4. Pumps and pipework – 10 loads: flat tray truck. Pipe, local manufacture (ex Burnie or
Launceston), by road. Pumps Italian manufacture by road, ex Launceston. Pipe fittings
ex Melbourne by sea.
5. Volcanic rock media – 1 truck, ex Hobart by road.
6. Plants local – by road.
Hours of operation – Construction
Works will be completed according to the Hours of Use specified in the Environmental
Management and Pollution Control (Miscellaneous Noise) Regulations 2004 - SCHEDULE 7 -
Hours of Use:
Monday to Friday: 7.30am to 6pm inclusive.
Saturday: 8am to 6pm inclusive.
Sundays and Public Holidays: 10am to 6pm inclusive.
Vehicle movements - Commissioning
Only light vehicles (Council vehicles) will be used for commissioning and ongoing operations.
A sludge truck will be required infrequently (~5-10 yearly) to remove sediment in the pre-filter,
and annually to biannually to remove sediment from manhole chambers.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 39
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Operational Regime
The entire wetland system has individual inlet/outlet flow control valves to cells, which allows
for flexibility in operation design features to allow for draining, maintenance and variations in
flow. Cells will have siphon drainage pipes installed to provide a full drain option for re -
aeration of sediments and to prevent excessive detention of flows that could lead to stagnation
and mosquito/odour issues.
2.2.7 Proposed Stormwater & Creek Enhancement Works
Currently, the stormwater from the site discharges into the same manhole chamber as the
leachate, separated by a baffle (see Figure 5).
The current condition of the creek at the discharge point is degraded. There is limited
overstorey cover and the understorey is predominantly weeds (APPENDIX 2), including
glyceria, blackberry and hawthorn. The weeds, particularly glyceria (Glyceria maxima), are
choking the stream, reducing water quality and also reducing potential habitat for the
threatened Burnie burrowing crayfish and giant freshwater lobster.
BCC intends rehabilitating the creek within their site boundary (predominantly south of the
Stage 1 landfill as part of a parallel project. This will involve the clearing of weeds and
replanting with local native species. The works will involve battering some of the banks in
places to reduce erosion and improve the site for planting.
In addition to the site based works, BCC will undertake tie in works at the discharge point for
these current works, which similarly will include weed control, erosion control and revegetation
works. The extent of works will extend into the neighbouring downstream property, subject to
landholder permission/interest. The nominal extent of works is shown in Figure 13.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 40
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 13. Proposed nature & extent of creek enhancement works, and location of new stormwater swale
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 41
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
2.2.8 Construction
A preliminary timetable for major construction activities is shown in Table 3.
Table 3. Preliminary construction timetable
Note, measures for managing construction risks, including weed controls, pests and diseases,
sediment, dust etc are outlined in Section 6.0.
An estimate of the raw materials that will be required for the proposal is provided in Table 4.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 42
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 4. Estimates of raw materials and sources
2.2.9 Commissioning
For the correct function and operation of the passive leachate treatment system the correct
sequence and timing of events must be adhered to during wetland commissioning. Factors
such as water levels, plant height and health and leachate loading must be carefully managed
to ensure that the wetland design and plants are not compromised by initial and subsequent
water level increases.
Key commissioning items include:
Pumps, pipework and valves (as part of civil contract)
Telemetry system and flow/water quality meters (as part of civil contract)
Treatment wetland planting (as part of landscape contract)
Treatment wetland validation monitoring (separate specialist contract) .
The key wetland commissioning items are shown in Table 5, with the major items described
below. Note, discharge to TasWater is proposed to be maintained during the commissioning
phase, until such time that validation monitoring has demonstrated acceptable performance of
the system.
Water Levels
The water levels in the wetland cells must rise gradually (by no more than 100 mm per week)
to avoid plant stress and fully inundating plants. It is critical that the water level does not
exceed more than two thirds the heights of the plants. If this depth should be exceeded the
commissioning process should be halted until the plants have grown to above this nominal
level.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 43
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
The system should be commissioned using the minimum operating water depth until the
system is ‘full’. At this point, the weir boards should be raised in concert with plant growth to
the seasonal operating depth.
Leachate Loading
The wetland should be commissioned with the Stage 1 leachate, after planting is completed to
avoid human contact with the leachate and potential health risks during planting works.
Planting should occur after sufficient rain has fallen to ensure moist soil conditions. The
design of the wetland, including the type of species planted, and the diluted nature of the
leachate means that the leachate loading during the commissioning phase has an extremely
low risk of impacting on the wetland plants and is suitable without diluting with a clean water
source.
Timing of Commissioning
Commissioning of the wetland should occur over a period of three months after wetland plants
are established and after the wetland is sufficiently ‘full’ and discharging . Validation monitoring
should be undertaken over a six month period, after the completion of commissioning.
End of Commissioning
Commissioning will be considered completed after six months of validation monitoring has
demonstrated acceptable performance of the system. Acceptable performance will be defined
as the meeting of the water quality compliance targets (Table 23) and as outlined in the
expected performance targets provided in Table 2.
Table 5 below details the sequence of actions to be followed during commissioning of the
system.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 44
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 5. Wetland commissioning tasks and timing
2.2.10 Precedent Projects
Whilst the intended wetland system on top of the landfill does not represent a post -closure
land use, the intent is that the wetlands and infiltration ‘wet forest’ will be retai ned in the long
term as a biodiversity and educational area abutting the agricultural and nearby residential
areas.
There is a growing number of projects globally that look to redevelop existing landfills and
post-closure landfill redevelopment is becoming recognised as part of the sustainable landfill
management process. Bouzza and Kavazanjian (2001) discuss various aspects of
redevelopment associated with hard and soft uses. Hard uses include commercial/industrial
developments, shopping centres and highways, while soft uses include golf courses, leachate
storage and treatment infrastructure, public parks and recreational facilities.
Sequence
of EventsTask Timing Location Notes
Time
frame
1Check all pipew ork and pipe
connections.Pre leachate release.
Entire Wetland
System.
Visually inspect all pipew ork and pipe connections for
debris, blockages and cracks or other defects. Repair as
required.
1 day
2Check all manholes, pits and
headw alls.Pre leachate release.
Entire Wetland
System.
Visually inspect all pits and headw alls for debris,
blockages and cracks or other defects. Repair as
required.
1 day
3
Wet commission pumps and test all
electrical componenets (f low
meters, WQ probes)
Pre leachate release.Entire Wetland
System.Use clean w ater for commission testing. 1 day
4
Ensure w eirs w ithin the system are
set at the low est level, and that the
outlet to the leachate chamber is
active to prevent any leachate and
w ater release to infiltration
w etland/ creek.
Pre leachate release. Polishing WetlandWill be opened one system is commissioned and w ater
quality is monitored and performance is proven.1 day
5 Check inlet valves. Pre leachate release. Pre f ilter. Visually inspect. Repair and adjust as required. 1 day
6
Progressively f ill pre f ilter w ith
leachate until design w ater level is
reached.
At leachate release. Pre f ilter. Fill using leachate and let w ater overflow into SF1. 1 w eek
7
Progressively allow w etland cells
to f ill until all areas reach minimum
design w ater levels.
At leachate release.Entire Wetland
System.
* Fill using leachate.
* Ensure that at least one third of the average plant foliage
is above the top w ater level at all times.
2 w eeks
8
Check integrity of all liners and
inspect pipe connections and
headw alls for leaks.
At leachate release.Entire Wetland
System.
Monitor w ater levels w eekly to see if any leaks through
the liner or at pipe/headw all joints are occurring.
ongoing
for 4
w eeks
9
After checking leachate quality for
compliance, close outlet connection
to the leachate chamber and allow
leachate to discharge into
infiltration basins.
After monitoring of
leachate qualityInfiltration basins.
If leachate quality is non-complinant, maintain discharge to
leachate chamber.Week 3
10
As w ater levels are raised check
for plant health, short circuiting and
preferential f low paths.
At leachate release.Entire Wetland
System.
If plant health is poor contact Syrinx for plant trouble
shooting. If short-circuiting or preferential f low paths are
developing, monitor frequently. If problem still exists after
more w ater is released reduce f low s and undertake
remedial bio-engineering w orks to correct the problem.
2 months
11
Monitor the w etland w eekly for the
f irst month to ensure plant health is
acceptable, short-circuiting and
preferential f low paths do not
occur.
At design f lowEntire Wetland
System.
It is imperative that during the f irst month the w etland is
checked daily to ensure correct function and
performance.
1 month
12
It is essential that regular
maintenance checks are
undertaken.
Post leachate release.Entire Wetland
System.
A detailed maintenance checklist w ill be provided in the
O&M Manual, (pending)Ongoing
Leachate Treatment Wetland, BCC
Commissioning Schedule
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 45
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Waste settlement is an important factor in both hard and soft post-closure uses of landfills.
Both total and differential settlements are of engineering concern. For soft uses, settlement
may affect drainage grades and grade-sensitive uses.
Whilst many landfills are remediated and/or geotechnically engineered in order to support the
proposed end use, many ‘soft’ uses with re latively lightweight loads are constructed with
minimal or no geotechnical improvements. These include:
Woodland habitat restoration projects, wetlands and major landscape, sports field (e.g.
Sydney Olympic Park, and Churchill Park in Launceston);
Golf course developments (e.g. Burswood in Perth developed in the 1980s, and
Cannon Hill Community Links which is about to start in Brisbane). Golf courses
typically incorporate ponds, bunkers and vegetation screening, all of which apply
different loads to the landfill.
A directly similar project to the one proposed for Burnie was constructed for the City of
Lancaster in Ohio at the Stonewall Cemetery Road Landfill in 2006 (Burgess and
Niple, 2015). A series of leachate treatment wetland cells were constructed o n top of
the covered waste and down gradient of the landfill to maximise the available space,
and were lined with a double LLDPE synthetic liner.
Another similar project is the Lorong Halus landfill in Singapore which was closed in
1999. Part of the Lorong Halus landfill nearest the river was then turned into a
wetlands preserve (Eco Water Treatment Park) so that the leachate could be pumped
into the wetlands for treatment (Figure 14). The Lorong Halus Eco Water Treatment
Park was completed in 2010 and is not only a functioning organic water treatment
system and a test bed for new bio-engineering water treatments, but also serves as an
education centre and a nature park.
The Rory Shaw Wetland Park in LA, California has used a former landfill site and is
repurposing it to feature a green, native-habitat-rich treatment approach to stormwater
management (shown below). Environmental benefits of the project include stormwater
capture and pretreatment; stormwater detention; constructed t reatment wetlands; and
groundwater replenishment (Figure 15) (http://www.psomas.com/wetlands-park-
transforms-former-landfill-site-rory-shaw-wetland/#sthash.J0KqIUkp.dpuf).
Hence, the proposed concept for the Burnie treatment wetlands on top of the landfill cap is not
without precedent.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 46
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 14. Explanatory diagram of Lorong Halus Leachate Treatment Wetland (from
Singapore Public Utilities Board)
Figure 15. Rory Shaw Wetlands Park currently being constructed at a former landfill
site in California. Image sourced from Los Angeles County Department of Public
Works.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 47
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
3.0 PROJECT ALTERNATIVES
The project involved several levels of investigation regarding the feasibility of various options
for the Stage 1 leachate management, including:
Evaluation of an on‐site treatment system vs full decommissioning and remediation of
the Stage 1 landfill vs continuing with the trade waste discharge to sewer arrangement.
Evaluation of various on-site and off-site reuse and disposal options.
Evaluation of on-site treatment approaches and technologies, including risk and cost
analysis.
Alternative assessment of treatment wetland locations.
3.1 ON‐SITE TREATMENT VS DECOMMISSIONING & REMEDIATION VS TRADE WASTE
DISCHARGE
An assessment of alternate leachate management options was undertaken by BCC and Syrinx
in May 2015 in order to investigate and evaluate the potential risks associated with different
leachate management approaches, and to determine the best option in terms of environmental
outcomes and financial feasibility. The evaluation criteria used to access each option included:
Environmental Benefit/Impact, Risk, Economic Impact, and Community Impact/Sustainability.
The assessment process and final recommendations are contained within APPENDIX 5.
As a initial step, this assessment process evaluated the suitability of the following options:
Do nothing and continue to discharge to TasWater Sewerage System under a Trade
Waste Agreement (TWA) with TasWater (Base Case).
Remove waste from Stage 1 Landfill and develop and dispose to new waste cell on
site (Stage 2B/C).
Remove waste from Stage 1 Landfill, transport and dispose to an alternate landfill (e.g.
Port Latta or Dulverton).
On-site treatment.
The two options that considered site decommissioning and remediation of the Stage 1 landfill
with waste removal and disposal were found not to be environmentally or financially viable.
The costs to remove the waste body and dispose it to an alternate location were determined to
be extreme and prohibitive. The evaluation process also identified high risks associated with
both of these options in terms of environmental impacts during the construction and
rehabilitation phase.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 48
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
The option that considered the Do Nothing approach based on continuing with a Trade Waste
Agreement was also found to be cost prohibitive (especially in light of the highly likely increase
in disposal charges), with very poor environmental and community outcomes. This option was
not seen by Burnie City Council as feasible as it does not deal with the key pressing
environmental issues on site and does not represent a long-term sustainable solution for the
Council.
Furthermore, in dialogue with TasWater it became obvious that a “do nothing’ option would not
be seen favourably as there are continuous issues with regard to acceptance of trade waste to
the sewer system, given that the leachate stream is highly dilute and at times causes
biological performance issues for the WWTP. Also, the TasWater WWTP and sewer network
currently operates near capacity, and removing trade waste flows from the sewer would
reduce the number of non-compliant discharge events and is seen as critical to freeing up
capacity to accommodate the Lion development and other future waste streams. Furthermore,
the objectives of Council’s Stormwater Infrastructure Development Project would not be met
without a solution that removes leachate from the TasWater sewerage system.
On‐site treatment was assessed as the best sustainable economic, environmental and
social outcome in the long run.
3.2 EVALUATION OF REUSE vs DISPOSAL OPTIONS
In line with the State Water Policy, and in acknowledgment of the local receiving environme nt,
treated leachate reuse was considered ahead of a discharge consideration. The evaluation
process was undertaken in discussion with relevant stakeholders, e.g. TasWater, EPA and
adjacent landowners.
The approach and summary key findings arising from this evaluation process are out lined in
sections below. More details regarding this process can be found in APPENDIX 1 and
APPENDIX 4.
3.2.1 Reuse
Limited treated effluent reuse options were identified, namely reuse for off-site irrigation of
pasture.
On-site reuse opportunities identified included irrigation of capped landfill areas and
surrounding grassed buffers for which demand is very low (calculated to be <4 ML/annum) and
seasonal. Hence, given the high annual volumes of treated leachate (90% of daily volumes are
at or below 600 kL/day meaning that annually more than 20 ML of leachate is generated), on
site reuse was found to be unfeasible as it would require a major winter storage (>90 ML,
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 49
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
assuming 6 months storage) which is prohibitive in terms of the space requirement within the
landfill site boundary. Hence, on-site reuse was determined not to be a realistic reuse option
on its own, as it cannot deal with full volume of treated leachate over a full ye ar.
Off-site reuse opportunities were also found to be limited and unfeasible because of good
rainfall and the availability of high quality groundwater in the region, and absence of industrial
or other high volume users within feasible proximity. Furthermore, immediate reuse demands
from surrounding neighbours for dam storages would require major pumping and infrastructure
and would only address a small portion of the excess supply.
3.2.2 Disposal
In addition to the discharge to the TasWater sewer option (Do Nothing) considered in Section
3.1 above, two other discharge options were considered and evaluated:
Discharge within the site or above the landfill site.
Off site discharge to the downstream unnamed tributary of Cooee Creek.
Infiltration of leachate into the landfill body was not found to be feasible given the high rainfall
in the area, as it would create a re-circulation loop for leachate with only minimal potential for
a reduction in the quantity of leachate requiring disposal. Similarly, infiltration in areas located
above the landfill site were also found to be unfeasible given this scenario would require
significant pumping costs, has high groundwater tables within a recharge area, and therefore
could result in a localised recharge of the groundwater with contaminated water which adds to
the leachate/groundwater volumes reporting to the Stage 1 collection system.
Infiltration within the site was found to be feasible along the northern site boundary (area
approximately 0.4 ha with optimal soil infiltration characteristics. Using a conservative
infiltration rate of 1*10^-6
m/s(typical permeability for this part of the site) shows that most of
the treated leachate will infiltrate in this zone and report as subsurface discharge to the creek
(which mimics the normal hydrological regime for this creek and others in this region).
Consequently, the optimal strategy was determined to be:
1. Indirect discharge of the treated leachate onsite via infiltration in a ‘wet forest’
wetland zone,
2. Direct discharge of large treated leachate flows that exceed the infiltration capacity to
the unnamed tributary of the Cooee Creek.
Further evaluation of the potential impacts to groundwater and the creek is covere d in Section
6.0.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 50
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
3.3 EVALUATION OF TREATMENT APPROACHES & TECHNOLOGIES
A range of leachate management approaches and technologies commonly applied on landfill
sites was assessed in terms of their appropriateness for the Stage 1 landfill leachate in the
Syrinx Options Study (APPENDIX 1).
3.3.1 Evaluation of Leachate Management Approaches
The broad methods commonly applied to leachate management are summarised in Table 6.
Table 6. Broad leachate management approaches
These methods were assessed against a range of preliminary screening criteria developed
specifically for the project. These criteria, as well as the outcomes of the preliminary
evaluation of possible treatment technologies for the Stage 1 leachate, are shown in Table 7.
Based on the requirement that the standard of treatment of the leachate is met consistently,
as well as on other environmental impacts and site suitability, the best performing
technologies were found to be: reverse osmosis (RO), membrane bioreactor (MBR), and
constructed wetlands. These three shortlisted technologies were further subjected to detailed
evaluation in order to determine a preferred treatment solution for the Stage 1 leachate.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 51
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 7. Outcomes of preliminary stage 1 leachate treatment options screening
+ Meets criterion
± Partially meets criterion or meets criterion but
requires more effort / investment.
- Does not meet criterion
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 52
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
3.3.2 Detailed Evaluation of Shortlisted Treatment Technologies
The three shortlisted technologies were evaluated against each other and against the “do
nothing” (Base Case) option (continuation of discharge to sewer). The evaluation was done
using a custom built Sustainable Infrastructure Decision Model (SIDM©) which contains a
number of criteria grouped in the following risk-based evaluation categories:
Local environment & Public health protection;
Design;
Costs; and
Planning & Management
The overall performance of the shortlisted technologies against the evaluation criteria can be
seen in Figure 16.
Figure 16. Summary of leachate treatment technology evaluation
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 53
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
In summary, the constructed wetland system scored the highest and outperformed MBR
and RO technologies across all evaluation categories, primarily due to the following
characteristics:
▪ passive sustainable nature;
▪ low reliance on energy & low/no chemical requirements;
▪ built resilience to deal with changes in flows and leachate quality;
▪ simplicity of operation and a significantly lower operating cost; and
▪ a range of value adds, such as biodiversity enhancement.
Consequently, the treatment wetland system was found to be the preferred
technological solution for dealing with the Stage 1 landfill leachate, and was further
progressed in terms of design and risk management.
3.4 ASSESSMENT OF TREATMENT WETLAND LOCATIONS
The following assessment step investigated the feasibility of alternative locations for the
construction of the proposed the on-site treatment wetland system. This process is outlined in
further detail in APPENDIX 4.
The following alternative wetland locations were evaluated:
1. Treatment wetland located south of Stage 1 adjacent to the creek system.
2. Treatment wetland located down gradient of the pump station (on Bartlett’s property).
3. Treatment wetland located north of the Stage 1 Landfill, within the existing Council
boundary.
These options were then compared with the “preferred option” of locating the treatment
wetland on top of the Stage 1 Landfill as proposed in the original system design (APPENDIX
1) and as proposed in this current Development Proposal. The landfill cap has a large
relatively flat land area available, meaning the full treatment system can be constructed within
the site boundaries with adequate buffer zones. The system involves pumping leachate to the
head of the wetland and gravity flow of treated effluent to an Infiltration Wet Forest; flows in
excess of infiltration capacity discharge to the creek.
All of the above described location options (the three alternative and the preferred options)
were assessed against five (5) criteria (Table 8):
Available area and compliance with discharge criteria.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 54
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Availability and timely acquisition of land (including rezoning).
Clearance of established vegetation buffers.
Proximity to residential areas.
Avoidance of 1:1000 year flood plain.
Cost.
Table 8. Summary of assessment of alternative wetland locations
Of the three alternative locations, Option 3C (located north of the Stage 1 Landfill) was found
to be the most favourable alternate site option to compare with the preferred location for a
wetlands development (Table 8). This option would be fully contained within the site and no
additional purchase of land would be required. Similar to locating the treatment system on the
Stage 1 Landfill, this option involves pumping leachate to the head of the wetland and gravity
flow of the treated effluent to the infiltration wetland and the creek. The terrain available for
this option is very steep and would require significant earthworks, estimated to cost
approximately $1.5M more than the preferred location.
Locating the wetland to the north of the Stage 1 Landfill would involve a much greater
pumping head compared with locating the wetland on top of Stage 1 Landfill (preferred
option). Furthermore, there would be very limited potential for infiltration of treated leachate
within the site boundary due to less available land, hence the majority of treated leachate
would be discharged directly to the creek.
In contrast, a wetland located on top of the Stage 1 Landfill requires only minor top soil
stripping / earthworks as the terrain is ideally suited to a wetland, and has a lower pumping
head which enables recirculation between system components with minor grade changes.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 55
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Further, this option allows for the majority of the land along the northern boundary to be used
for infiltration of treated leachate (Wet Forest), minimising direct discharge to the creek and
providing further water treatment.
The geotechnical report (Tasman Geotechnics August 2015) which evaluated the potential
hydrogeotechnical risks of each location concluded that the hazards associated with loc ating
and operating a wetland on top of the Stage 1 Landfill presents a Low to Very Low risk,
provided the following aspects are incorporated into the design and operation of the wetland
as follows:
Regular maintenance checks on pump and equipment are undertaken to minimise
blockages and overtopping.
Wetland is designed for sufficient freeboard to cope with anticipated rainfall events.
Wetland is located at least 10m from the crest of the landfill containment bund.
Incorporating a geosynthetic or LLDPE liner in the floor of the wetland is not essential;
however it would reduce the risk profile associated with seepage into the landfill to Very Low.
Based on the above evaluation, a wetland system constructed on top of the Stage 1
Landfill scored highest against the assessment criteria and remains Council’s preferred
option for the management of the Stage 1 Landfill leachate.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 56
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
4.0 PUBLIC CONSULTATION
In order to develop an appropriate treatment and disposal/reuse option, a collaborative
engagement process was undertaken with the stakeholders and the EPA, as key regulators.
This consultation and engagement process that has been undertaken thus far and is being
developed for the next project stages is in line with the aims, principles and approaches
outlined in A Tasmanian Government Framework for Community Engagement (Tasmania
Government, December 2013). The overall objective of the consultation process is to provide
an engagement continuum (i.e. a continuum of engagement practices, coordination and
information sharing) that facilitates decision-making and provides positive and mutually agreed
outcomes for the community, the Government and the Council.
4.1 STAKEHOLDER CONSULTATION
Key stakeholders in this project include Burnie City Council, TasWater, the general Burnie
community, adjacent neighbours, downstream landowners (residents living along the Creek),
TAFE Farm, Schools, UTAS, and Cradle Coast Authority NRM.
4.1.1 Community Consultation
Initial Engagement
BCC and Syrinx met initially with the immediate neighbours (adjacent landowners)
downstream of the landfill site in late April 2014 to brief them on the project, hear any
concerns and gauge interest in potential reuse of treated wastewater.
Downstream landowner’s permission was also sought for the background Cooee Creek
sampling program undertaken as part of this study (April 2014), and these downstream users
were briefed on the sampling project by Syrinx staff. A letter regarding the overall project and
sampling program was distributed by the BCC to seven immediate landowners in March 2014
(see APPENDIX 10 for the letter and list of contacted landowners).
Additional communication (via phone and in person) was held with relevant neighbours and
downstream landowners.
A summary of the information provided by Syrinx and BCC to private stakeholders included
the following:
Overview of leachate treatment study.
Scope of works for sampling event.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 57
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Brief summary of environmental issues and reasoning for undertaking this sampling
project.
Environmental, social and economic considerations associated with the project, project
approach, timelines and likely preferred approach.
During this initial public consultation, no objections to the proposed project were received.
Feedback from conversations with landowners was generally positive and indicated their
desire to be kept progressively informed during the project.
Follow On Consultation
Stakeholder consultation was again undertaken in July 2015. A letter advising all landholders
downstream and adjacent to the unnamed tributary and Cooee Creek (original landowners
contacted plus additional seven landowners) was issued, advising them of the NOI submission
and providing an update regarding the project status, additional stud ies undertaken in 2015
and the status of the approvals process. This letter also included a plan showing the location
of the proposed system, and a concept layout of the treatment cells.
From this correspondence, three landowners, which are also creek water users, requested
further project information. These stakeholders were individually visited in early September
2015 by BCC and Syrinx, and briefed in detail. In summary, the main initial concerns were
primarily related to the potential impact of leachate discharge (both treated lea chate and non-
treated in peak storm events or events of system failure) on the creek water quality and
subsequently on crops/vegetable irrigation and livestock drinking.
However, after Syrinx /BCC provided additional information regarding the additional studies
undertaken to ‘proof up’ the proposed system, the ‘safety nets’ put in place for the project, and
in particular after communicating and explaining the current sewer capacity issues and the re-
occurring spillage incidents, the landholders appeared reassured that the system would be
safe and that it provides an overall beneficial outcome for the environment and the local
community. One landholder stated his philosophical opposition to the removal of leachate from
sewer since he saw this as a breach of an agreement.
This landholder meeting also clearly demonstrated the absolute need for continuity of
community consultation that would be responsive to differences between the key landholders
and perceived key issues. The concern that all of the landholders expressed for the ecosystem
health of the Creek system also paralleled their willingness for more meaningful engagement
in next project stages, especially in those restorative elements related to
protection/enhancement of the creek.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 58
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Consultation Alignment with Framework for Community Engagement
As stated in the Tasmanian Government Framework for Community Engagement , a successful
community engagement process should include the following steps:
Inform – this is a one-way communication process mostly based on the information
provision to public.
Consult – this is a two-way communication and sharing process.
Involve, collaborate/ partner - working with communities through partnerships.
Empower - community empowerment.
The public consultation process undertaken thus far for the Burnie project follows this staged
engagement approach, and up to this point in the project it has successfully delivered the two
first steps, information sharing and a two-way communication which was used to gather
feedback on the key public issues associated with the proposed works and to ‘test’ the
proposed system in terms of public acceptance.
This engagement process was undertaken in a timely and honest fashion, with straightforward
account of all project benefits, risks and risk management measures. The consultation process
was also respectful of different people’s agendas and views, and was done with an aim to
enable community inputs.
In terms of future public engagement, the focus will be on continuing with the progressive
information sharing and on meaningful community involvement and collaboration .
BCC will continue to communicate with stakeholders through the following mechanisms:
Provision of copies of this DPEMP to, and discussion with, key stakeholders.
Provision of additional information that would increase community awareness
regarding the creek’s values, key existing threats, and positive impacts of the project
on the creek’s ecosystem health and visual values.
A special community information session days will be scheduled in the Council building and
at the waste centre site, with Council and Syrinx representatives that will enable all
interested community members to seek additional information regarding the project and
express (voice) their concerns, opinions and suggestions. To facilitate this process, visual
panels containing the most relevant project information presented in an appropriate (user-
friendly) form will be prepared for this community session and displayed in the Council
building foyer. Open day panels will remain displayed in the Council building and comments
will be sought for any further inputs. This will allow residents to have a progressive input into
the project (post information sessions) and will also enable those residents that couldn’t
attend the information sessions to ‘have their say’. Panels accompanied with the key project
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 59
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
information will also be uploaded on the Council’ website and residents will be able to leave
on-line comments and inputs specific to the project.
Provision of opportunities for community and other stakeholders to be directly involved in the
project.
The project includes intensive creek restoration efforts and wetland planting. These actions
are planned to be undertaken in close collaboration with the community, school and NRM.
This involvement is expected to assist in raising community understanding of the project
drivers and benefits leading to a greater project appreciation and ownership.
Maintaining a line of communication with the key stakeholders.
Regular updates will be provided to all stakeholders regarding the project’s progress,
environmental achievements (including water monitoring data) and creek rehabilitation plans.
This will be done through written communication (newsletters to community), on-line
information (on Council’s website) and via annual reports.
Provision of additional opportunities for community education, engagement and
ownership through interaction with improved visual amenities of the project area.
The project will significantly improve aesthetic values of the site via creek restoration
efforts, an appropriate landscape design of the wetland system and provision of
educational/recreational opportunities and interpretative signage. Together, this will
make the site ‘appealing’ to community. Due to its educational and research values it
is expected that the site will be also frequently visited by school students. Schools and
the NRM will be involved in the wetland planting works.
Providing opportunities for community to comment on and provide inputs regarding the
project after the system commissioning.
Post commissioning residents will be able to express their opinions (positive and
negative) and raise any concerns regarding the system performance, site aesthetics or
any other issues. This will be facilitated on-line (comments on the dedicated forums on
Council’s website) and via comment forms collected in the Council building.
4.1.2 Consultation with TasWater
The engagement process with TasWater included progressive information sharing and regular
meetings aimed at understanding the key issues with regard to acceptance of trade waste to
the sewer system and potential barriers for continual discharge of Stage 1 leachate to sewer.
The initial meeting with TasWater was held on 23rd
of April 2014. During this meeting
TasWater stressed that the current WWTP is at capacity, and removing trade waste flows from
the sewer would reduce the number of non‐compliance events and free up capacity to deal
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 60
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
with other waste streams not currently serviced by the WWTP. In terms of the Stage 1
leachate specifically, this stream is dilute and causes issues in terms of the biological
performance of the WWTP, and overflows along the existing creek in peak storm events.
Therefore, TasWater was of an opinion that there was a broader environmental benefit of on-
site leachate management and disposal. During this initial engagement, they acknowledged
that this BCC Stage 1 leachate project could be a demonstration site that would demonstrate
sustainable management of industrial wastewater, and would encourage research into onsite
treatment options for other landfill areas across the State that would potentially result in a
reduction in industrial waste disposal to their sewer systems more broadly.
A follow up meeting was held with TasWater on September 4th
2015, which focused on
discussions regarding the formal approval for maintaining an emergency connection to sewer.
TasWater advised that this was acceptable and will issue a letter of agreement, following
receipt of design flow requirements from BCC. TasWater has provided preliminary comments
to the EPA, which indicate they are supportive of the project.
Syrinx and BCC are in the process of collating and providing additional information to
TasWater regarding the frequency and volumes of leachate expected to be discharged to
sewer. The two scenarios where sewer discharge is expected are in the unlikely event of
pump failure, and in periods of non-compliant treated water discharge (see Figure 8). There is
a lag in peak flows into the leachate collection system after rain events since flows must first
recharge and then discharge from the aquifer (see Section 5.2.4 and APPENDIX 1), and there
is significant buffering and storage capacity within the wetland system. However, some
volumes may be subsequently released to sewer if the wetland cannot treat these flows
adequately. This means any discharge to sewer, if required at all, will be activated on the
second or third day following the storm event after the peak capacity of the sewer is restored.
4.2 REGULATORY CONSULTATION
BCC and Syrinx have maintained an ongoing consultative relationship wi th the EPA on this
project. Engagement with the EPA began immediately on project inception (March 2014) and
has included comprehensive and ongoing communication with both the local regulatory officer
and various experts in the Hobart office. The EPA have progressively provided advice and
informal review of studies/reports undertaken and have assisted in guiding the approvals
process thus far.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 61
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
5.0 THE EXISTING ENVIRONMENT
5.1 PLANNING ASPECTS
5.1.1 Land Tenure
The Burnie Waste Management Centre (BWMC) is located within the Burnie City Council Local
Government area and is operated by Burnie City Council. The subject site includes two lots:
Lot description
City of Burnie
Lot 1 on Plan 145841
Derivation: Part of 50,000 acres granted to the Van Diemans Land Company
Derived from A19301
City of Burnie
Lot 2 on Sealed plan 27996
Derivation: Part of Section 133, 50,000 acres granted to the Van Diemans Land Company
Prior CT 4261/55
The existing site Certificate of Title, is shown in APPENDIX 11.
The tenure is freehold and is owned by Burnie City Council. Under the Town Planning
Scheme, the site is included in “Community Purposes”. The planning scheme specifies the
zone is primarily intended to ensure that locations are available for specific public uses such
as disposal areas, cemeteries, crematoria, schools and council depose. Within the
“Community Purpose” zone, the landfill site is zoned “Utilities” which is primarily intended: i)
“To provide land for major utilities installations and corridors ”and ii) “To provide for other
compatible uses where they do not adversely impact on the utility”.
The proposed project site is located within the BWMC boundary, as shown in Figure 2.
The land surrounding the BWMC to the west and south of the site is mainly agricultural (zoned
Rural Resource), while the area to the north and east is zoned as General Residential.
The proposed leachate wetland treatment project does not conflict with any other known
developments within the BWMC site or surrounding land.
There are no easements on the property.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 62
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
5.1.2 Land Use & Planning History
The BWMC includes a landfill site (Stage 1 and Stage 2A), new Waste Transfer and Resource
Recovery Facility (WTRRF), Recycle/Recovery Loops and associated infrastructure (toll booth,
amenities building, tip shop, leachate ponds and pump stations) (see Figure 4). The total area
of the BWMC site is ~ 28 ha. The total landfill area is ~14 ha, comprising of ~8.3 ha for the
Stage 1 and ~5.8 ha for the Stage 2A.
The entire BWMC site has been used for waste management since it was opened as a formal
landfill site in 1987. Prior to this the land was used solely for agricultural purposes (livestock
grazing) and comprised of open pasture with remnant bush along the creeks.
A brief chronology of the landfill site is given in APPENDIX 12.
Currently the BMWC landfill site operates as a Waste Transfer and Resource Recovery
Facility, with putrescible waste being transferred to another landfill site (Dulverton Landfill).
The resource recovery facility includes a recycle loop, and tip shop, while concrete, masonry
and timber is stockpiled for reuse processing.
Green waste is handled on a green waste hardstand area, located on part of the old Stage 1B
landfill area.
5.1.3 Neighbouring Properties
There are three neighbouring properties located mainly adjacent to the north -east and
northern boundary of the site (visible on Figure 1). These are:
Land immediately downstream land (incorporating the unnamed tributary which is the
current BCC discharge point).
Land to the south of the landfill site.
Land adjacent to the waste centre eastern boundary (upgradient of Stage 1).
The nearest residential subdivision is currently on Three Mile Lane Road, approximately 200m
away (visible on Figure 1).
The TAFE agricultural farm site is located > 1 km north-west of the project site. Farmland
occurs to the west of Mooreville Rd.
There are no other land uses within the 500 m of the proposal site.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 63
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
5.2 ENVIRONMENTAL ASPECTS
A detailed description of the physical environment within project site and its immediate
surrounding is provided in various sections of APPENDIX 1 and APPENDIX 6.
Below is the synthesis of key characteristics of the physical environment.
5.2.1 Topography
The BWMC site comprises about 28 ha of moderate sloping ground. The natural ground
elevation is approximately 165 mAHD at the southern end of the site to 139 mAHD at the
outlet to Cooee Creek tributary. The location of the proposed leachate treatment system is on
top of the Stage 1 landfill (see Figure 6) to take advantage of the available space and to
maximise gravity flow of treated leachate through the treatment cells (note, the leachate will
be pumped to the head of the wetland system). The top of the Stage 1 landfill cap is at ~162
mAHD at the peak, as surveyed in April 2013.
5.2.2 Climate
The Bureau of Meteorology (BOM) station closest to the project site is at Round Hill Burnie
(operational since 1944), and data from this station has been used to determine the local
climatic conditions. The key characteristics are as follows:
Burnie exhibits a temperate, maritime climate with mild summers and relatively cold
winters.
The warmest months are January (21.1°C) and February (21.3°C), while July is the
coldest (12.8°C).
Significant temperature variations exist on site - In summer temperatures can rise to
35C° while from March to November they fall below zero. Significant temperature shifts
are also recorded for individual months where temperature can vary by up to ~20-
30°C.
The average annual rainfall is 945.9 mm with a low of 402.5 mm/year and high of
1488.4 mm/year. For the seven months during the year (April to October), average
daily rainfall exceeds evaporation.
Analysis of leachate flow data (APPENDIX 1) revealed that the leachate flows were
found not to show a correlation with individual rainfall events (although do with
seasonal rainfall) however these high rainfall events greatly impact on the overall
water behaviour on site (stormwater generation, groundwater levels, seepage) and
contribute to the overall leachate-associated issues on site.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 64
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Wind is predominantly westerly or southwesterly (especially during the afternoon). The
months with the highest wind speed are October, November and December (14.1-14.9
km/hr at 9 am and 18.4-19.1 km/hr at 3 pm).
Mean rainfall, evaporation and temperature data is summarised in Figure 17.
Figure 17. Mean climate data for Round Hill, Burnie
5.2.3 Geology & Soils
The natural geology of the site and region generally are Tertiary volcanic basalts, which are
highly weathered (Mineral Resources Tasmania (MRT) Digital Geological Atlas, 1:25,000
Series, Burnie sheet). Although grouped as basalt soils, they typically comprise a sequence of
layers or flows. Creeklines and valleys within the region also contain Quaternary quartz
sediments and river silts and gravels, with Precambrian dolerites underlying the basalts or
outcropping in some areas.
The Stage 1 landfill pre-development site lies within a valley tract, and was constructed over
two spring-fed gullies and a swamp which together with two other spring-fed gullies on the site
form the head of the unnamed tributary to Cooee Creek.
There are no features of geoconservation significance within the project area.
Soils for the area are classed as Tertiary basalt ferrosols within the Lapoinya Association.
Within the site, the landfill overlays the semi confined basalt aquifer, with riverine creek fill
0
5
10
15
20
25
0
20
40
60
80
100
120
140
160
Tem
pe
ratu
re (°
C)
Rai
nfa
ll /
Evap
ora
tio
n (
mm
)
Mean rainfall (mm) for years 1944 to 2015
Mean monthly evaporation (mm) for years 1965 to 1982 (calculated from daily)
Mean maximum temperature (Degrees C) for years 1944 to 2015
Mean minimum temperature (Degrees C) for years 1944 to 2015
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 65
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
materials and swampy deposits associated with now piped/drained spring expressions. Soils
are indicated as mainly brown to orange clays and silts of low to medium plasticity, associated
with weathering of the basalts (APPENDIX 6).
The site is not within an acid sulphate soil risk area (LIST Tasmania).
5.2.4 Leachate (Current)
Quantity (Flows)
Detailed analysis of leachate flows (current and historic) and flow distributions & patterns was
undertaken as a part of the initial Syrinx study (APPENDIX 1). This section summarises the
key points.
Analysis Approach
Currently, leachate flows are not directly monitored and are derived from pump data from the
MH1 chamber. The ‘capture rate’ of leachate flows is limited by the pumping capacity of the
system, which is ~ 40L/sec, or 3,456 kL/day, which can accommodate at least the 80 year ARI
event.
Because the leachate stream is around 80-90% groundwater, Stage 1 leachate flows
historically have been highly variable, influenced by seasonal rainfall patterns and
consequently variable groundwater inflows to the leachate drainage system. Further, annual
variations are or have been influenced by direct rainfall infiltration (in years prior t o capping in
2005), as well as a range of site works in more recent years associated with the development
and recent capping of the Stage 2 landfill and improvements to stormwater collection and
diversion on-site (which has reduced the incidence of mixing with leachate in MH1).
Due to these effects, the dataset used to characterise the existing leachate conditions on -site
is for the period March 2010 to December 2014 (current BCC dataset). This appears to be the
earliest stable trending dataset, and mainly reflects the completion of stormwater collection
and diversion works within Stage 2 and the waste facility area. Data points that reflected no
pumping or maintenance days were removed from the dataset.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 66
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Current Flows
Stage 1 flows for the period March 2010 to December 2014, are given in Figure 18.
This dataset shows an average flow of 350 kL/day and a median value of 311 kL/day. Peak
pumped flow for this period was 1,449 kL/day recorded in August 2012, which appears from
the data to be due to a result of groundwater level rise after continuous rainfall, rather than a
singular rain event. The highest overall flows were recorded in spring 2013 .
Figure 18. Average stage 1 leachate flows (March 2010-December 2014)
0
100
200
300
400
500
600
700
800
900
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec
2010 2011
2012 2013
2014
AVERAGE STAGE 1 FLOWS (kL/day)
kL/day 2010 2011 2012 2013 2014
OVERALL
AVERAGE
2010-2014
(kL/day)
se
Jan 456.0 287.6 272.4 339.8 339.0 8.22
Feb 448.1 251.2 265.3 306.0 310.3 8.80
Mar 207.3 365.1 250.7 230.5 278.4 265.3 5.54
Apr 214.2 347.5 297.3 204.7 279.8 268.2 7.73
May 194.4 282.3 471.9 203.3 266.5 283.7 8.82
June 206.1 267.2 477.4 198.4 265.2 282.9 9.36
July 242.8 288.4 280.3 258.6 284.3 271.1 4.33
Aug 286.3 338.3 763.3 502.8 343.8 446.9 20.10
Sep 395.8 383.5 806.1 661.1 340.2 517.3 17.33
Oct 390.9 381.6 585.5 675.2 332.0 473.0 15.36
Nov 361.1 364.7 379.4 538.6 306.0 389.9 7.40
Dec 377.4 344.8 341.9 424.4 285.6 354.9 7.55
350.2TOTAL AVERAGE
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 67
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Flow Distribution
A frequency graph was generated in order to assess the distribution of Stage 1 discharge
flows that will require treatment in the proposed system (Figure 19). Table 9 shows the
percentile rankings, which indicate that around 70% of flows are below 400 kL/day, 80% below
500 kL/day, 90% at or below 600 kL/day, and 95% 700 kL/day or below.
Figure 19. Frequency distribution graph of Stage 1 leachate flows
Table 9. Frequency distribution of Stage 1 leachate flows
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
40.0%
45.0%
100 200 300 400 500 600 700 800 900 1100 1200 1300 1400 1500
Fre
qu
en
cy
Range (daily flows kL/day)
Stage 1 Daily Flow Distribution for Feb 2010 - May 2014
95 percentile90 percentile
Flow Range
(kL/day)
Number of
Occurrences
Percentage
Frequency
Cumulative
Frequency %
100 3 0.2% 0.2%
200 193 12.6% 12.7%
300 357 23.2% 35.9%
400 587 38.2% 74.0%
500 208 13.5% 87.5%
600 44 2.9% 90.4%
700 75 4.9% 95.3%
800 36 2.3% 97.6%
900 10 0.7% 98.2%
1100 16 1.0% 99.3%
1200 4 0.3% 99.5%
1300 3 0.2% 99.7%
1400 3 0.2% 99.9%
1500 1 0.1% 100.0%
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 68
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Quality
As with leachate flow, a detailed analysis of leachate quality in terms of contaminant
composition, concentration and variability was done as a part of the initial Syrinx study
(APPENDIX 1). The section below summarises the key points.
Analysis Approach
The BCC have been undertaking monthly, quarterly and annual monitoring of various leachate
parameters to meet EPN compliance requirements. This comprehensive data set (from
January 2005 to November 2013) was used as the basis of Stage 1 leachate (LO1) quality
assessment. In line with the monitoring requirements, four LO1 samples are collected each
year from the MH1 chamber (except for the first monitoring year when only two samples were
collected), meaning that data from 33 sampling events was used in this analysis (Figure 20).
Stage 1 leachate (LO1) samples were analysed for a range of physico-chemical characteristic
as follows:
Physical characteristics, nutrients, most metals, and major anions/cations (quarterly).
Organic pollutants (insecticides/ pesticides and petroleum hydrocarbons) (tested
annually as they are generally found to be below the Level of Reporting (i.e. are not
detected in LO1 samples).
Under the existing scenario, leachate does not discharge to the Creek. However, the proposal
will result in highly treated leachate discharges in high rainfall events. As such, and in line with
the existing monitoring & reporting program and the Landfill Sustainability Guide (DPIWE
2004), the leachate water quality (WQ) data was assessed against the Australian Water
Quality Guideline for Aquatic Ecosystems (ANZECC, 2000) trigger values.
Trigger values are pollutant concentrations that, if exceeded, would indicate a potential
environmental problem, and would hence ‘trigger’ a management response, e.g. further
investigation and subsequent refinement of the guidelines according to local conditions. If the
trigger value is not exceeded, the risk of an impact is low and no further action is required.
Note, the aquatic ecosystem guideline trigger values for toxicants (e.g. metals) are risk-based
in the sense that they are calculated to protect a predetermined percentage of species with a
specified level of confidence (i.e. 99%, 95%, 90% and 80% protection level signifies the
percentage of particular species expected to be protected).
The WQ trigger values considered appropriate for the site are for the Ecosystem Condition 2
(level of protection 95% species) trigger values applying to lowland streams. This reflects the
agricultural land use surrounding the landfill site and the activities associated with landfill
operations and development within the site.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 69
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Note, the ANZECC trigger value used for ammonia is corrected for the pH of the leachate, in
accordance with Table 8.3.7 of the guidelines - a trigger value specific for pH 7.5 (1.61 mg/L)
was used to analyse ammonia data and establish ammonia-specific treatment requirements.
Figure 20. Site current sampling locations
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 70
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Physical Characteristics
A summary of the Stage 1 leachate physical characteristics is given in Table 10. The key
findings are as follows:
pH is within the circum-neutral range, averaging 6.8. pH values were found to be
slightly below the lower limit set by ANZECC guidelines on five occasions since
monitoring began (16% trigger breach).
Table 10. Stage 1 leachate WQ – physical parameters
Redox potential is positive indicating well oxygenated conditions . Note, a positive
oxidation-reduction potential and the presence of oxygen are common for mature
leachates, which have undergone the final maturation stage of waste degradation
(ARRPET, 2004), hence even disregarding the influence of groundwater incursion, the
leachate itself is expected to be well oxygenated.
Most solids are being reported as dissolved (TDS, soluble fraction) while only a small
fraction is present in particulate suspended form (TSS).
Commonly, under positive redox (oxidising conditions) and with a neutral pH (pH
greater than 5.5), redox-sensitive metals (Cu, Cr, Mn and Fe) react with water to form
relatively insoluble hydroxides and oxides. However, most of the Stage 1 leachate
contaminants are in soluble form and no correlation was found between either pH or
redox values with TSS and TDS. This indicates the leachate chemistry is complex and
simple patterns are overprinted by other factors that impact on these metal
concentrations (and probably concentrations of other pollutants). The key factor is
clearly the ingression of groundwater and the consequent dilution effect.
The conductivity of the leachate is primarily influenced by alkalinity which, for the pH
range, is dominated by bicarbonate ions. The balance of salts is comprised of sodium,
chloride and sulphate, which are at low levels within the leachate, with median values
recorded as follows: chloride – 53.5 mg/L; sodium - 36.6 mg/L; magnesium - 20.6
Physical Characteristics Range Average MedianANZECC (2000)
Aquatic ecosystem
pH 6.1 - 8 6.8 6.8 6.5 - 8.0
Alkalinity total mg CaCO3/L 30 - 271 172.9 179.6
Total Suspended Solids (TSS) mg/L 7 - 72.8 25.4 18.9
Total Dissolved Solids (TDS) mg/L 92.8 - 373 272.3 276.4
ORP (redox potential) Eh mV 276 - 663 470.2 434.0
Conductivity µS/cm 157 - 795 540.3 557.0
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 71
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
mg/L; sulfate - 11.3 mg/L; and potassium - 6.9 mg/L. Metals and ammonia comprise
the balance of electrical conductivity.
Nutrients
Nutrients (nitrogen species and phosphorus) are the key contaminants of concern for the
Stage 1 leachate, with a very high frequency of trigger exceedances (Table 11), meaning
these will need to be reduced within the proposed treatment system prior to any discharge to
creek.
Table 11. Concentrations of nutrients in Stage 1 leachate
Total nitrogen (TN) concentrations have exceeded trigger values at every sampling
event since the start of the monitoring program, with a median value of 7.9 mg/L. Most
of the total nitrogen reports as ammonia, while NOx species (nitrate and nitrite)
represent only a small portion of TN (6%).
Concentrations of ammonia in Stage 1 leachate exceed the set trigger value almost all
of the time (95% exceedances). Whilst elevated, ammonia concentrations in the
leachate are significantly lower compared to typical leachate, where ammonia often
exceeds 400 mg/L. This possibly reflects the significant dilution of leachate stream
with groundwater/stormwater, but also the waste composition.
Most of NOx species are present as nitrate (97%), typical of streams with positive
redox.
Phosphorus levels are low, with both average and median values well below ANZECC
trigger values. Detected TP values exceeded trigger values 25% of the time. Only
>20% of total P is in dissolved form.
Note, although phosphorus levels are relatively low in the Stage 1 leachate, they are
within the range that enables effective growth of wetland vegetation. Generally,
phosphorus is considered to be inefficient to support biological processes in
constructed wetlands if the N to P ratio is greater than 500 (Maehlum, T. 1999) , which
Nutrients Range Average Median
ANZECC (2000)
Aquatic
ecosystem
% exceed.
TN mg/L 1.1 - 15 8.1 7.9 0.5 100%
Ammonia total mg/L 0.07 - 14 7.8 7.9 1.61 97%
Nitrate mg/L 0.034 - 1.71 0.48 0.39 0.7 9%
Nitrite mg/L 0.004 - 0.03 0.01 0.01
TP mg/L 0.002 - 0.093 0.036 0.025 0.1 26%
Dissolved reactive P mg/L 0.002 - 0.044 0.006 0.004 0.02 0%
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 72
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
is not the case; the proposed wetland system has an N:P ratio of ~300. In terms of the
potential effect of low phosphorus concentrations on the efficiency of nitrogen removal
in the wetland treatment system, the key biological processes involved in removal of N
species (ammonification and nitrification) are primarily influenced by the N:C ratio, and
less so by the N:P ratio. Consequently, despite the relatively low TP levels in the
Stage 1 leachate, no addition of fertilisers is expected to be required either during
periods of wetland establishment nor during the normal system operation.
The existing data indicates seasonal patterns in terms of nutrient levels. As seen in Figure 21,
concentrations of TN, ammonia and TP appear to be the lowest in winter months (May to Aug),
with relative peaks in March and September. March peaks probably reflect a typical ‘first flush’
response at the onset of rainfall and initial recharge of the groundwater from agricultural
areas. The winter lows coincide with dilution as a result of higher rainfall and flows. Spring
peaks coincide with the highest leachate-groundwater flows in a typical year. It is unclear why
these presumably more dilute rain-dominated flows also have the highest nutrient
concentrations, however it may be associated with the rising leachate levels within the landfill
cell causing ‘scouring’ of higher layers within the leachate landfill in a rise and fall fashion
(APPENDIX 6), that means more concentrated nutrients become entrained in the discharge
flows. Pastures in the region are fertilised in winter and spring and it is also possible that low
uptake of N-fertilisers in winter when temperatures are low may increase this load to
groundwater and surface waters, however there is no evidence of similar spring peaks in
stormwater concentration up-gradient of the landfill (SW2).
Figure 21. Seasonal changes in nutrients levels in Stage 1 leachate (median values)
(data set 2005 – 2013)
0.00
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.08
0
2
4
6
8
10
12
Jan Feb Mar Apr May Jul Aug Sep Oct Nov Dec
TN ammonia TP
TP (
mg/
L)
Nit
roge
n (
mg/
L)
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 73
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
It should be noted that the ANZECC trigger value used for ammonia is corrected for the pH of
the leachate, in accordance with Table 8.3.7 of the ANZECC guide lines.
The freshwater high reliability trigger value for ammonia is 0.9 mg/L in Table 8.3.7 of the
ANZECC guidelines, and BCC has used this trigger value in their WQ monitoring and reporting
program. This trigger value has been derived from figures corrected as total ammonia at a
fixed pH of 8.0, which is not the pH characteristic of the leachate and results in an
overconservative trigger value.
Importantly, the toxicity of ammonia is primarily attributed to the un-ionised NH3 (not total
ammonia), and is highly influenced by pH (as well as temperature and ionic composition of
water). In general, at higher pH values (>8) ammonia predominantly exists in a more un -
ionised (more toxic) form, while at lower pH values, the un-ionised (ammonium) form is
dominant; hence the overall toxicity is greater at a higher pH. As outlined in the ANZECC
guidelines, trigger values for ammonia at pH conditions other than 8 should be calculated
using equations provided in these guidelines, or adopting pH-corrected values provided in
table 8.3.7 of the guidelines.
The average and median pH values of the Stage 1 leachate are 6.8 (Table 10), and since the
start of the monitoring program a pH greater than 7.5 was recorded only once while most of
the time (~65%) the pH was below 7. Furthermore, recent monitoring of water quality of the
unnamed tributary to Cooee Creek (March 2014), which is the key sensitive receiving
environment showed that the average pH is 7.4 with the maximum recorded value 7.5.
Therefore, to appropriately reflect the reduced ammonia toxicity at reported pH values
(leachate and creek), a trigger value specific for pH 7.5 (1.61 mg/L) was used to analyse
ammonia data and establish ammonia-specific treatment requirements.
Metals
In general, concentrations of heavy metals in Stage 1 leachate can be characterised as low to
very low, which is a characteristic of mature leachate that has undergone the fermentation
stage of waste degradation during which soluble metals are mostly bound in a metal sulphides
form. In terms of the total concentrations, two dominant metals are iron and manganese.
Other key metals that were found to at least one occasion during the monitoring period exceed
relevant ANZECC trigger values (95% protection) are aluminium, chromium, copper, nickel
and zinc (Table 12).
All of these metals are typical of municipal landfills and reflect the mixed nature of the waste
being disposed at the landfill (municipal, commercial and mixed indust rial waste). Other
monitored metals (As, Cd, Hg, Pb) were never found to exceed trigger values and were
predominantly below the level of detection, and hence were not included in Table 12.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 74
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 12. Stage 1 leachate WQ – metals (total)
In terms of individual metals, the Stage 1 leachate is characterised by the following:
Manganese (Mn) - is the key metal of concern in terms of compliance with the
ANZECC protection levels, as both the average and median values exceed 95% trigger
values. While frequent (64% of time), these exceedances are relatively minor (~7%
above trigger values). Manganese (and iron) are also signatures of the basalt geology,
hence elevated Mn could reflect the groundwater intrusion into the leachate system as
well as landfill chemistry. This is difficult to verify since there is no total metal data
available for groundwater. Mn levels in stormwater samples (SW1) are much lower
compared to leachate (see Section 5.2.7).
Reported Mn levels in leachate reflect total metal concentrations which includes the
concentration of metals in both dissolved and particular form. Dissolved metals are
generally considered more mobile, biologically available and potentially toxic. Under
aerobic conditions typical of the Stage 1 leachate stream, the solubility of Mn is
generally low as it forms a stable oxidized form (generally as MnO 2), which is highly
insoluble. Thus, most of the Mn reported in the Stage 1 leachate is expected to be in
particulate form.
Iron (Fe) - Higher Mn concentrations co-occur with elevated levels of iron (Fe) in the
leachate, as a result of their similar chemistry and responses to redox and pH (i.e. for
Mn to precipitate, the water must be well oxygenated to the extent that essentially all
Fe is insoluble, and pH should be near neutral or above). Given the local geology is
dominated by iron-rich volcanic basalt, high concentrations of iron are expected in the
local soils which were also used in landfill construction materials. This may have
added to the Fe load within the landfill waste and relatively high Fe levels in the
leachate stream. While not causing significant negative environmental impacts, high
Fe concentrations together with Mn do pose practical challenges for leachate
Range Average Median
ANZECC (2000)
Aquatic
ecosystem - 95%
protection
% exceed.
Al µg/L 2.5 - 705 44.8 13.4 55.0 16%
Cr µg/L 0.5 - 3 0.74 0.5 1.0 12%
Cu µg/L 0.4 - 2.98 0.71 0.50 1.4 6%
Fe µg/L 1,887 - 34,500 12,930 9,358
Mn µg/L 142 - 3,960 2,159 2,043 1,900 64%
Ni µg/L 2.4 - 15.8 10.2 10.1 11 30%
Se µg/L 5 - 26 8.5 5.0 5 3%
Zn µg/L 0.5 - 39 7.3 6 8 27%
denotes trigger value exceedances
Metals (total)
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 75
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
collection and treatment. They contribute to the hardness of the leachate, and can
precipitate within the leachate distribution systems causing a reduction of pipe
diameters and eventually clogging, as well as the loss of pressure in pumps and pipes.
Seasonal variations in Fe and Mn concentrations in the leachate show a strong
correlation (Figure 22), and are similar to seasonal patterns observed for nutrients
(nitrogen, ammonia, phosphorus, Figure 21). Furthermore, they show reasonable
similarity with the seasonal patterns in Fe and Mn concentrations in stormwater (see
Section 5.2.7). As with nutrients, concentrations are at a peak in spring when
groundwater has recharged and the interaction between groundwater and leachate
waste materials are at their highest.
Figure 22. Seasonal changes in Fe and Mn levels in Stage 1 leachate (median values)
Aluminium (Al) - At times Al concentrations in the Stage 1 leachate were found to
significantly exceed ANZECC 95% trigger values, the average and median
concentrations are below this trigger values.
Seasonal variations in Al concentrations in the Stage 1 leachate and SW1 stormwater
showed very similar patterns, indicating interaction and mixing between these two
streams (Figure 23). Al levels in SW1 stormwater are higher compared to LO1
leachate (as well as the SW2 stormwater entering the landfill site) suggesting that
these high Al levels may originate from other activities beyond the Stage 1 landfill.
High natural background levels of aluminium (Sharman 2002) could also be one of the
contributors.
0
500
1,000
1,500
2,000
2,500
3,000
3,500
0
5,000
10,000
15,000
20,000
25,000
30,000
Jan Feb Mar Apr May Jul Aug Sep Oct Nov Dec
Fe Mn
Fe (
ug/m
l)
Mn (ug/m
l)
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 76
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 23. Seasonal changes in Al concentrations in LO1 and SW1 (median values)
Zinc (Zn) & Nickel (Ni) - Both Zn and Ni exceed relevant ANZECC guidelines ~30% of
the time, although their median and average concentrations are below relevant trigger
values.
Relative similarity in seasonal patterns in Zn levels in leachate and SW1 stormwater
indicate mixing of these streams. Similarly to Al, during certain months Zn levels were
higher in the SW1 stormwater samples compared to the leachate stream, indicating
that other activities other than the Stage 1 landfill contribute to stormwater
contamination with Zn (Figure 24). As for aluminium, high background levels of zinc
(Sharman 2002) could also be contributing to this observed Zn levels in stormwater.
Figure 24. Seasonal changes in Zn levels in LO1 & stormwater (median values)
0
100
200
300
400
500
600
700
800
900
1000
0
5
10
15
20
25
30
35
40
Jan Feb Mar Apr May Aug Sep Oct Nov Dec
LO1 SW1
Leachate
(ug/m
l)
sto
rmw
ate
r (u
g/m
L)
0
2
4
6
8
10
12
14
16
18
Jan Feb Mar Apr May Aug Sep Oct Nov Dec
SW2 LO1 SW1
Zn
con
cen
tra
tio
ns
(µg/
mL)
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 77
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Organics & Other Chemicals
The Stage 1 leachate is characterised by a very low presence of organics as demonstrated by
i) the low COD which is found to be below LOR throughout the sampling events, and ii)
absence (concentrations below LOD) of most organic pollutants tested as a part of the regular
monitoring program. Out of more than 50 different organic contaminants tested on an annual
basis only four polycyclic aromatic hydrocarbons (PAHs) have been detected in the Stage 1
leachate stream (Table 13). These four PAHs were found to be only occasionally present in
LO1 (≤50% of time), and at very low levels. The ANZECC trigger values are set for
naphthalene only, and this PAH is well below the 95% protection level.
Such a low level of organics in leachate is typical of mature landfill sites that have undergone
degradation and volatilization of aromatic hydrocarbons which are the most organic
compounds reported in landfill leachate. As a result, only small amounts of refractory organic
carbon usually remain in old landfilled wastes, and report to their leachate streams.
Table 13. Stage 1 leachate WQ – detected organics
Cyanide was detected in the Stage 1 leachate during a single monitoring event only
(14/02/2006) when it was above the guideline limits, and hence is not considered to be a
major contaminant of concern.
Thus, based on the available leachate data, organics are not considered to be major
contaminants of concern in terms of environmental impacts associated with the discharge of
treated leachate to the creek. If anything, the very low presence of organics may slow down
biological treatment processes within the wetland system, most notably dentitrification
processes in the subsurface (anaerobic) system component. Further data is being gathered to
assess the BOD:COD ratio and determine if supplementary carbon will be required. Carbon
additions can be accommodated within ether the Cell 1 pre-treatment cell (e.g. by adding
slowly degrading carbon materials such as woodchips), or as liquid or granular humates within
any system component. When the system reaches maturation, the wetland cycle of plant and
microbe growth, death, atmospheric fixation and partial decomposition etc will likely provide a
sufficient carbon source.
Organics Range Average Median % detected
ANZECC (2000)
Aquatic
ecosystem
Acenaphthene µg/L <0.5 - 1.39 0.82 0.62 50% -
Naphthalene µg/L <0.5 - 0.54 0.51 0.50 17% 16
Benzo(k)fluoranthene µg/L <0.5 - 0.6 0.52 0.50 17% -
Fluorene µg/L <0.5 - 0.7 0.55 0.50 33% -
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 78
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Pathogens
The presence of pathogens (E. coli) in Stage 1 leachate is monitored annually. Since the
beginning of the monitoring program, E. coli was always found to be below the level of
detection in the leachate stream.
Discharge (Mass Loads) to Sewer
Mass loadings (average daily and average annual) of key contaminants present in Stage 1
leachate to TasWater sewer were calculated using the median pollutant concentrations
available for the period 2005-2013 and average annual leachate flows calculated using
available leachate flow data for the period 2010-2014. This data is presented in Table 14.
Table 14. Mass loading of key pollutants to sewer
5.2.5 Leachate Seepage
There have only been two seepage events on site which occurred in 2007 and 2013 along the
northern containment bund, both after extreme (>80 year ARI) or extended rainfall periods. In
both cases, leachate seepages expressed as localised ponding which eventually infiltrated
(Figure 25), and there was no discharge to the creek, however in both cases flows were within
20 m of the creek discharge point (Figure 26).
Leachate seepages caused localised mineral salt scalding and plant death.
Throughout the record August/September 2013 rainfall, small volumes of landfill leachate
seeped from Stage 1 landfill containment bund over a length of approximately 20 m. This
AVERAGE
ANNUAL FLOWS
(2010-2014)
(kL/annum)
127,890
ANNUAL MASS
LOADING TO SEWER
(kg per annum)
TSS 2,417
TN 1,010
Ammonia 1,009
TP 3.2
Al 1.7
Cr 0.06
Cu 0.06
Fe 1197
Mn 261
Ni 1.3
Se 0.6
Zn 0.7
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 79
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
seepage ponded in an area adjacent to the northern boundary (Figure 26). The issue was
identified on 13/9/13 and the EPA was advised the same day, who requested BCC to
undertake sampling. Two samples were taken at Site 1 and 2 on the 17/9/13 down gradient of
the seepage source, and two further sampling events were conducted in December 2013.
Flows were too small to estimate volumes, however given the area impacted it is estimated to
be <50 m3.
Figure 25. Seepage area showing ponding & low ‘sheen’ indicating metal precipitation
Figure 26. Extent of leachate seepage in August 2013
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 80
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
The composition of leachate water sampled within ponded areas of the site over the three
sample periods indicated a highly diluted flow (Table 15), supporting the view that this
seepage is most likely to have come from lateral flow out of the landfill cap intermediate batter
into the drainage trench that is around the east and north sides of the scrap metal storage
compound area. It is likely that this flow has seeped through the landfill containment bund to
present as ponds on the mid level bench of the containment bund. A similar seepage along
the west side of the scrap metal area in 2007 was controlled by the installation of a drainage
blanket and subsoil drain directed to the leachate pond.
Table 15. Leachate seepage chemistry for the 3 sampling events in 2013
The chemistry of the seepage is more or less the same as in the LO1 (Stage 1 leachate) for
Mn, Fe, Ni and Zn sampled at a similar time (Sept 2013). However, Al concentrations are
extremely elevated – 4,210 ug/L compared with 54 ug/L in the LO1 leachate flows - this may
indicate a point source within the landfill itself. Cu and Cr are also elevated compared with
LO1 leachate.
Interestingly, organics (COD) are detectable, and within the typical mature leachate range.
COD is always below the level of reporting in the Stage 1 leachate samples, since it is highly
diluted by groundwater mixing.
In April 2014, Syrinx undertook additional investigations of soils within the leachate seepage
area, to assess the extent of contamination, if any, and possible requirements as part of the
overall leachate treatment design options. Soil data (Table 16) indicates that there is no
contamination of soils (using NEPM guidelines for industrial sites). While this is not therefore
of immediate concern (since contaminants did not discharge off-site), given seepage events
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 81
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
have occurred more than once on-site at this location, the seepage zone as such has been
incorporated into the overall treatment system by creating a phytoremediation swale to collect
the seepage and direct it to the leachate treatment system. Furthermore, soils, while below
the relevant guidelines, still contain elevated metals (copper, chromium III, nickel and zinc) .
Hence, these soils will be stripped and disposed of or only used within embankment fill
material or for site levelling material under liners.
Table 16. Soil data from within the leachate seepage area (northern embankment of
Stage 1 landfill)
5.2.6 Groundwater
Hydrogeological Context
The regional catchment hydrogeology has been well characterised (Martin and Currie 2008 ‐
Conceptual model report for Cam‐Emu‐Blyth), the subregional (Cooee Creek) catchment
hydrology modelled as part of flood risk assessments (Entura 2011), and the local site
catchment hydrogeology (including the installation and monitoring of a large number of bores)
studied as part of baseline land capability assessments and specific landfill design studies
(Sloane 2000, Coffey 2004, 2007, 2008, SKM 2007, Tasman Geotechnics 2015).
A continuous water level record exists for the Burnie wells for the period December 2003 to
March 2006 and is reported on in the state (Mineral Resources Tasmania) groundwater data
collection program. Manual water level readings have been recorded since 1991.
These studies and investigations demonstrate that the entire landfill operation is confined
within a natural Tertiary basalt valley. The site acts as a significant groundwater discharge
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 82
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
zone with spring expressions along the valley slopes and floor and discharge of all
groundwater to the two creeks on‐site.
The Stage 1 subcatchment discharges to the northern ‘unnamed tributary’. The long term
hydrographs for the site (Figure 27 and Figure 28) and the groundwater contour levels (which
are above the creek invert level) support a “fill and spill’ groundwater model for the shallower
sub‐regional flow systems; i.e. rapid infiltration of rainfall recharge occurs to a maximum level
(sustained through capillary rise) at which point any subsequent infiltration is lost as discharge
to the surrounding rivers and streams.
The unnamed creek is a minor part of the overall Cooee Creek catchment (<5% of the
catchment area), and constitutes less than 1.5% of the total Cooee Creek flows (Entura 2011).
A conceptual site model illustrating the interactions between groundwater with leachate and
surface flows is shown in Figure 29.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 83
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 27. Standing water level data and cumulative deviation from mean annual rainfall recorded for GW1 (Burnie Tip site 1, ID 17778) o ver
the period 1991 to 2000. From Martin and Currie 2008
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 84
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 28. Standing water level data and cumulative deviation from mean annual rainfall recorded for GW2 (Burnie Tip site 4, ID (ID 1778 0)
over the period 1991 to 2006. From Martin and Currie 2008
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 85
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 29. Conceptual site model – existing scenario
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 86
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Groundwater Quality
Groundwater quality monitoring has been undertaken across the site since 1991 as part of the
original site permit conditions and subsequently as part of the s tate (Mineral Resources
Tasmania) groundwater data collection program. Quarterly groundwater monitoring of one
upstream (GW3) and two downstream bores (GW2, GW 1) is undertaken by the BCC.
Historical data for GW1 and GW2 is contained in periodic MRT reports.
Groundwater monitoring bores (located on Figure 20) are as follows:
GW3 – located upgradient of the landfill along the southern boundary of the site.
GW2 - located near the entrance at the northwestern end of site down gradient of the
Stage 2A landfill, and the western section of the Stage 1 landfill.
GW1 - located along the northern boundary downstream of the Stage 1 landfill.
The key water quality data for the three monitoring bores (Table 17) shows groundwater is
characterised by a slightly acidic to neutral pH, with elevated nutrients (mainly nitrogen) and
some metals. Similar to stormwater, the dominating nitrogen form is nitrate while ammonia
represents only a small fraction of TN. Total N and nitrate values appear to be higher in the
bore up-gradient of the landfill (GW3), compared to the downstream bores, suggesting that
agricultural activities may be the dominant source of nutrients in GW. Dissolved metals
including Cr, Ni and Zn are present in GW3 and GW2, but are low in GW1. It is difficult to
determine the source of these low level metals, since they are typical of both agricultural
fertilisers and herbicides, and of the leachate waste. Organic pollutants, which are monitored
annually, were not detected in any of the GW samples.
The springhead dam on private land above the GW3 bore and SW2 stormwater monitoring
point has been filled with unapproved materials in the past, including tyres, which may have
contributed to elevated chromium and metals in groundwater.
In comparing the long term water quality data for groundwater bores with other regional bores
from the MRT program indicates there is no difference between the Burnie bores and other
regional rural bores in terms of quality. Importantly, groundwater recharge zones are located
above the Stage 1 and Stage 2 landfill operations, with these and the majority of the site
within a groundwater discharge zone, hence all site runoff reports to Cooee Creek as surface
or subsurface discharge and the potential for groundwater contamination is remote. All bores
are similar in chemistry and contaminants measured all are within groundwater drinking level
criteria (NEPM GIL criteria).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 87
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 17. Summary of groundwater quality data – pH, nutrients and dissolved metals
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 88
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
5.2.7 Stormwater
Stormwater Flows
Stormwater at the BWMC site is managed by a network of open channel, cut-off swale drains
and pipe conveyance infrastructure. The stormwater network is indicated in Figure 5 , Figure 8
and Figure 30.
The capacity of the stormwater network was assessed as part of this proposal by Tasmanian
Consulting Service (2015) using a DRAINS model, which in particular focussed on the risk of
flooding to the proposed wetland under extreme rain events (APPENDIX 6). This study
concluded that the site stormwater infrastructure can adequately handle flows from rainfall
events to up and including 20 Year ARI without any overland flows or upwelling. During 100
year ARI events, some overspilling was modelled to occur adjacent the 900 DIA RCP culvert
under 3 Mile Line Road, however this does not result in overland flow over the roadway since
the Northern Waterway/Creek (Cooee Creek unnamed tributary) would simply swell and flood
the adjacent grass paddocks. Detailed flood modelling undertaken by Entura (2011) showed
the same result. The addition of treated leachate flows to the creek is minor and therefore
highly unlikely to increase the risk of flooding along this section of the creek.
Direct (point source) stormwater discharge to Cooee Creek tributary occurs via a pipe and
pump connection that links Stage 2A stormwater flows to the MH1 chamber. Flow data is
estimated using pump records (period 2010-2014, Figure 31). Stormwater from Stage 2A is
pumped to MH1 at a maximum 10L/sec flow rate and this flow reports to the MH1 chamber
and from here discharges via a pipe to the creek.
The dataset indicates there is a constant baseflow of ~ 2.5 -3 L/sec, and in winter/spring flows
are ~4-5L/sec. These average flows are used below to estimate the current mass load to the
creek from point stormwater discharges from Stage 2A only. Note, this is clearly an
underestimation of total site stormwater flows.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 89
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 30. Stormwater network at BWMC (from Tasmanian Consulting Service 2015 report)
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 90
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 31. Average (Stage 2) stormwater point discharge flows to Cooee Creek tributary
Stormwater Quality
Stormwater quality is monitored quarterly by the BCC as part of the EPN conditions. Similar to
groundwater, there are upstream (SW2) and downstream monitoring points (SW3 is in the
Stage 2 landfill area and SW1 downgradient of the Stage 1 landfill, Figure 20).
Stormwater quality data is shown in Table 18.
Stormwater entering the site (SW2) contains elevated levels of nutrients with both median TN
and TP values exceeding ANZECC standards, most likely as a result of fertiliser use on the
upstream farm properties. In contrast to the leachate stream, stormwater TN is dominated by
inorganic forms, with nitrate dominating and ammonia representing only a small fraction of the
total nitrogen (up to 10%).
Metal characteristics are similar to Stage 1 leachate, with stormwater entering the site (SW2)
containing notable levels of metals which occasionally exceed ANZECC guidelines for the
protection of aquatic ecosystems. This most likely reflects an agricultural source.
When comparing the water quality at SW1 (downstream) with the two monitoring points
upstream of the site (SW3 and SW2), it can be noted that most of the detected metals are
0
100
200
300
400
500
600
700
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec
AVERAGE STORMWATER DISCHARGE TO CREEK kL/day (2010-2014)
2010-2014 kL/day
median 252.00
average 286.49
max 5040.00
min 0.00
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 91
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
present in higher concentrations and are characterised by a higher frequency of guideline
exceedances. This is particularly the case for Al, Fe, Mn, Ni and Zn (Table 18), which
suggests interaction/mixing between these streams.
While the higher concentrations of Fe, Mn and Ni in SW1 may originate from the ingression of
leachate into the stormwater system, the same is not the case for some other metals including
Al, Zn, Cr and Cu. As discussed previously in the leachate WQ section, levels of Al and Zn in
SW1 are higher compared to LO1 samples, suggesting the influence of some other activities
on stormwater quality.
Stormwater flows across the landfill site generally do not show organic contamination as
indicated by the very low COD (below LOR), relatively low DOC and general absence of
analysed organic pollutants in SW samples.
A key risk response included in the proposed project includes the separation of the current
stormwater discharge infrastructure from the leachate collection and treatment system to avoid
untreated leachate discharge via the stormwater system.
Table 18. Stormwater quality
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 92
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Estimated Current Stormwater Mass Loads to Creek
There is insufficient flow data to generate a mass load balance for the site. As an estimate,
the pump flow data from Stage 2 that reports to MH1 and directly discharges as point source
to the creek, is shown in Table 19. This is clearly only a portion of the total flows.
Table 19. Estimated mass loading of key stormwater pollutants to the Creek from
Stage 2A stormwater flows
5.2.8 Cooee Creek and its Tributary
The Burnie Landfill operations are within the immediate water catchment of Cooee Creek. The
Stage 1 landfill pre-development site lies within a valley tract, and was constructed over two
spring-fed gullies, and a sumpland (swamp) along a major creekline (Cooee Creek unnamed
tributary). These were infilled and drained as part of the development works, and the majority
of the creek tributary infilled, diverted and/or modified for both Stage 1 and Stage 2 landfill
activities.
Under the current landfill operational regime, this creek receives all flows from the site not
managed within the leachate recovery and disposal system (i.e. stormwater plus groundwater
flows that bypass the leachate collection system). This means that this unnamed tributary is
the immediate off-site receiving environment. In addition to this site discharge, this tributary
receives groundwater discharge and surface runoff from neighbouring farms (this includes
agricultural pollutants).
The unnamed tributary has its origin 100 m upstream of the landfill area, and rises as springs
mostly within the landfill site and connects to the Cooee Creek watercourse approximately 3.0
km north-west of the landfill site. The Cooee Creek catchment starts near West Ridgley and
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 93
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
flows into the Bass Strait, dropping around 300 m over its 13 km length. The total catchment
area is 102 km2, and the catchment area of the unnamed tributary is 5.2 km
2 or 5% of the
catchment (Entura, 2011). Martin and Currie (2008) analysed data (stream heights, DEM,
groundwater elevations) for the catchment and concluded that rivers and creeks in the vicinity
of the site are gaining creeks (i.e. groundwater discharge zones), and do not recharge the
groundwater except at local higher catchment creeks where the invert of the creek bed may be
seasonally at least above the groundwater level. This latter pattern was shown for the creek in
the Stage 2 Development Approvals reporting for the site (Coffey, 2004).
Cooee Creek is within the broader Cam River Surface Water Catchment (DPIPWE, 2014),
although functions within its own hydrological boundary (Cooee Creek Catchment). The Cam
River is very well protected in terms of its Protected Environmental Values (PEVs) as it is very
intensively used for recreation, and the EPA have used the Cam River data in developing Draft
Water Quality objectives for Cooee Creek. PEV’s have not been formally identified for the
Cooee Creek catchment or the unnamed tributary on the landfill site.
Figure 32. Cooee Creek catchment area. Burnie landfill site is up-gradient of CT-1
Creek Ecology
The two natural values assessments undertaken for the project site (NEST 2013 & APPENDIX
2) concluded that the Cooee Creek unnamed tributary is already significantly impacted as it
flows through a highly modified environment. The section of the unnamed tributary close to the
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 94
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
BWMC and neighbouring agricultural land were found to be generally degraded and in poor
condition, infested with weeds (APPENDIX 2). Visual assessment of Creek’s condition
undertaken by Syrinx in April 2014 (APPENDIX 1) also confirmed that the unnamed tributary is
fairly degraded, with evidence of erosion, high weed extent, stock impacts and limited riparian
vegetation. Parts of the creek have been piped (through the residential area downstream of
Three Mile Rd) and dammed in some sections ( the TAFE property is the first main dam
feature).
Approximately 3 km downstream of the BWMC (APPENDIX 2) the unnamed tributary passes
through remnant vegetation, with steep forested gullies of mixed eucalypt over a wet
understorey that provides high quality habitat for creek fauna.
According to the Conservation of Freshwater Ecosystem Values (CFEV) database (WIST,
DPIWE), the creek above the Stage 1 landfill site is identified as of moderate conservation
management priority, however the tributary downstream of the Stage 1 landfill (within and off -
site including piped sections) is shown as having high conservation management priority
(APPENDIX 13).
Figure 33. Conservation of Freshwater Ecosystem Values (CFEV) for the site.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 95
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
While not mapped formally on the Groundwater Dependent Ecosystems Atlas (Bureau of
Meteorology, Australian Government), Cooee Creek is known to be groundwater recharged
and hence should be classed as a groundwater dependent creek system. As such the
vegetation and fauna supported by the creek system relies on groundwater discharge to
maintain environmental flows and permanent pool habitats.
Water Abstraction
There are fifteen known water licence holders (21 water licence numbers and 65 abstraction
points) along Cooee Creek and its tributary with this water used for irrigation purposes (Water
Information System of Tasmania, accessed November 2015). Water use is primarily during
summer months for irrigation of vegetable crops and pasture. Water is stored in dams over the
winter period and then used in summer. Direct take allocation allow a water user to take water
directly from the flow of the creek during the summer months.
Properties that are riparian to a stream have an automatic water right for stock and domestic
purposes, such as watering livestock, home gardens and even dwellings.
Water Quality
Water quality and sediment sampling and analysis of Cooee Creek and its unnamed tributary
were undertaken as part of this leachate treatment project (APPENDIX 1) to determine
baseline conditions of these key surface water receiving environments.
Water samples were collected during two sampling events at four locations along the tributary
and four locations (upstream and downstream from the unnamed tributary) (Figure 34).
Sediment samples were collected from four locations across the creek system. All samples
were analysed for a broad range of physico-chemical stressors and toxicants (Table 20 and
Table 21).
The water quality data of Cooee Creek and its tributary indicates that this creek system is
already impacted upon and receives discharge from the landfill site, as a result of groundwater
and stormwater discharge (which is to be expected given the local hydrology and the loc ation
of the landfill in a valley). Consequently, the system can be classified as slightly or moderately
disturbed (condition 2 ecosystems) based on the ANZECC (2000). This classification has been
adopted by the EPA in the Draft Proposed Water Quality Objectives for Cooee Creek.
The key concerns in terms of creek water quality are nutrients (total nitrogen, nitrate and total
phosphorus) and some metals (aluminium, copper, lead and manganese).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 96
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 34. Location of Water and Sediment samples undertaken as part of Cooee Creek and Cooee Creek tributary background sampling (Syrinx,
APPENDIX 1)
Cooee Creek
Cooee Creek
Cooee Creek
Unnamed tributary
Unnamed tributary
BWMC
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 97
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 20. Cooee Creek monitoring data - water quality results (April 2014) and
comparison with the Stage 1 leachate and site stormwater
Table 21. Sediment quality within Cooee Creek and unnamed tributary – April 2014
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 98
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Importantly, levels of key pollutants (nutrients and metals) and their distribution both upstream
and downstream of the landfill site suggest that groundwater/surface water discharge from the
landfill site is not the only source impacting on creek health. Rather, this creek system
receives inputs from other sources such surface runoff or groundwater discharge from nearby
properties (with a strong signature of fertiliser practices) as well as downstream properties.
For example, the presence of copper at very high concentrations along the length of the
tributary and Cooee Creek, is a strong signature of fertiliser use. Furthermore, a dominance of
organic N in sediment suggests other inputs apart from landfill leachate, given leachate is
dominated by ammonia.
Protected Environmental Values (PEVs)
PEVs have not been specified for Cooee Creek however the Environmental Management
Goals for the North-Central Coast Catchments do recommend suitable PEVs based on the
origin of the creek and the nature of the landscape through which it flows. For this project the
following PEVs were proposed as a minimum to ensure protection of Cooee Creek and its
unammed tributary:
Protection of aquatic ecosystems - (ANZECC Water Quality Guidelines (2000))
Recreational water use; and
Agricultural water use.
Given the current degraded nature the unnamed tributary (i.e. erosion, relatively poor water
quality, highly impacted by the extensive urban and agricultural land use in the catchment, it is
anticipated that the unnamed tributary would be rarely (if ever) used for recreational purposes
and most likely this would include secondary recreational activities only (e.g. less body contact
such as fishing). The recreational (primary and/or secondary) users of Cooee Creek were not
considered to be a key human receptor group given that any flows discharged to the unnamed
tributary would be significantly diluted before they reach Cooee Creek. Hence, protection levels for
secondary recreational contact were adopted.
EPA Draft Water Quality Objectives for Cooee Creek
A snap shot water quality monitoring event undertaken in Cooee Creek and its tributary in
April 2014 (APPENDIX 1), together with visual assessments of ecosystem health (APPENDIX
1 and APPENDIX 2), suggests that this system is already impacted upon and hence can be
classified as slightly or moderately disturbed (condition 2 ecosystems) based on the ANZECC
(2000).
In line with this, the Tasmanian EPA has prepared Draft Water Quality Objectives for Cooee
Creek as part of the Water Quality Guidelines (WQGs) for Cam Catchment in which Cooee
Creek is classified as a Slightly to Moderately disturbed (SMD) ecosystem. The 80th
and/or
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 99
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
20th
percentile trigger values were determined using the creek-specific data obtained during
the 30/11/2004 to 04/10/2007 monitoring period (Table 22). For physical parameters, triggers
were derived from 30-31 analysed samples, while for nutrients only 4 samples were used in
determining the trigger values. There is no ammonia specific data for Cooee Creek, and hence
the use of SMD WQOs for the Cam catchment is recommended.
Given the relatively small number of samples (especially for nutrients), this EPA Draft Water
Quality Objectives report is an evolving document, and the EPA have indicated they are
interested in obtaining creek-specific data to finalise the draft.
To this end, the Cooee Creek water quality data gathered in April 2014 by Syrinx as a part of
this BCC project could be included in the overall data set for refinement of the 20th
/80th
percentile trigger values. When this data (i.e. for Cooee Creek and its unnamed tributary) is
compared with the data used to derive the EPA trigger values, the following can be observed:
Median values for DO and the conductivity are very similar to the EPA median levels.
pH levels of Cooee Creek and its tributary measured in April 2014, while within circum -
neutral range, appear to be somewhat higher (more alkaline) compared to the previous
results.
Nutrients (and in particular TN) were found to be elevated compared to the EPA data.
TN concentrations in the six (6) analysed Cooee Creek samples from the three
sampling locations were in the range 0.5 – 2 mg/L, with a median of 1.3 mg/L which is
significantly higher compared to the EPA median of 0.68 mg/L. While nitrate levels are
comparable between the EPA and Syrinx data, this difference in the TN concentrations
is most likely due to the relatively high ammonia levels in the Syrinx April 20014 data.
However, as the EPA data set does not include ammonia levels, this cannot be
confirmed.
Ammonia levels in the Syrinx 2014 sampling of the Cooee Creek and its tributary were
similar to the Cam Catchment WQGs.
TP levels in the Cooee Creek and in particular the unnamed tributary were found to be
higher compared to the EPA data.
Turbidity, temperature and Chlorophyll-a were not included in the April 2014
monitoring program, so no comparison can be made with the EPA data set.
Note, the EPA data does not cover the limits for metals and other chemical contaminants (e.g.
organics, cyanide). Hence, the WQ protection trigger values adopted here for these chemical
toxicants are the default values (95% level of protection) provided in the ANZECC Guidelines.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 100
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 22. EPA proposed water quality objectives for Cooee Creek
EPA - Proposed Annual Water Quality Objectives (Shaded)
Percentile 5th 10th 20th Median 80th 90th 95thSample
Number
ANZECC
(2000)#
Unnamed
tributary
(median
values )
Cooee
Creek
(median
values)
Dissolved Oxygen mg/L 8.3 8.7 9 9.8 11.2 11.5 11.6 30 9.85 10.2
Dissolved Oxygen %
SaturationND ND
Field Cond @ TRef25 µS/cm 94 100.6 115.1 151.4 205 215.8 276.5 31 150.5 143.5
pH field - sensor TC 6.7 6.7 6.9 7.2 7.3 7.5 7.7 31 6.5-8.0 7.4 7.6
Turbidity NTU 2.6 3.9 4.3 5.1 7.8 12.8 18 31
Temperature (Celsius) 7.3 8.1 10.1 13 16.7 17.6 18.5 31
Ammonia as N mg/l ND 1.61* 0.05 0.03
Nitrate as N mg/l~ 0.427 0.432 0.441 0.47 0.498 0.508 0.512 2 0.7 0.625 0.435
Nitrite as N mg/l ND
Total Nitrogen as N mg/l ~ 0.155 0.17 0.2 0.438 0.681 0.715 0.732 4 0.5 1.8 1.25
Phosphorus, Dissolved
Reactive as P mg/lND
Total Phosphorus as P mg/l ~ 0.011 0.012 0.015 0.021 0.025 0.028 0.029 4 0.05 0.045 0.030
Total Suspended Solids
(1.5µm)mg/lND <5 <5
Total Suspended Solids
(0.45µm) mg/LND
ND= No data, ~ = Insufficient data for generation of WQOs (va lues included for information purposes only)
* ANZECC 2000 guidel ines - Trigger va lues for toxicants . 95% protection level adjusted for pH
Syrinx data (April
2014)
# ANZECC water qual i ty guidel ines (2000) - Default trigger va lues for phys ica l and chemical s tressors for south-east Austra l ia for s l ightly dis turbed ecosystems
total
ammonia
nitrogen
as N^
(mg/L)
Annual 0.051
Summer 0.048~
Autumn 0.070~
Winter 0.055~
Spring 0.043~
CAM CATCHMENT
WQGs
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 101
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
While the EPA data and the derived protection limits provide an important understanding of
the ecosystem health of the Cooee Creek, using these values as the water quality protection
trigger values for discharging treated leachate (and stormwater) into the creek system, poses
the following concerns, especially in terms of nutrient targets:
None of the nutrient data collected by the EPA included the unnamed tributary of
Cooee Creek, which is the proposed receiving environment for the treated leachate.
This is particularly the case for ammonia for which the data was adopted from the Cam
Catchment data set. As discussed above, the Cooee Creek unnamed tributary is
already a highly disturbed system. This relatively high level of disturbance is evident in
the recent (April 2014) WQ and sediment data for this tributary, compared to the
Cooee Creek itself (see section above) In contrast, Cooee Creek and the Cam
Catchment as larger scale systems, are far less disturbed, and predominantly limited
to agricultural influences. Such a marked difference between the ecosystem conditions
questions the appropriateness of using the Cam Catchment / Cooee Creek data for
setting the discharge levels for the unnamed tributary.
Nutrient protection levels (TN, TP, nitrate) were derived from only 2 to 4 sampling
events, the last one being in 2007. Such a small number of samples is generally not
sufficient to derive a statistically significant local reference system (as acknowledged
by the EPA in this project). The April 2014 sampling events, if included in the overall
data set would inevitably increase the median, and hence the 80th
percentile trigger
values for TN and TP.
The ammonia trigger values set by EPA (for the Cam Catchment) reflect the levels of
ammonia as a chemical stressor, not as a toxicant.
Based on the ANZECC 2000 Guidelines, nutrients (TN and TP) are generally
considered to be non-toxic direct-effect stressors, meaning that they do not have a
toxic effect but rather that elevated levels result in adverse changes to the ecosystem
as a result of nuisance growth of aquatic plants (eutrophication), excessive algal
growth and cyanobacterial blooms. Ammonia and nitrate, on the other hand, are also
toxicants; that is stressors that are directly toxic to biota.
Protection levels for the key stressors such as TN and TP are derived from relevant
reference systems, either from the same or local ecosystems, or from regional
reference ecosystems. The trigger values of toxic stressors such as ammonia and
nitrate are generally determined from laboratory ecotoxicity tests conducted on a range
of sensitive aquatic plant and animal species. These trigger values are outlined in
Table 3.4.1 of the ANZECC Guidelines. In other words, the non-toxic effect of
ammonia is generally ‘managed’ via setting TN protection levels, while its toxicity is
regulated by the set default values outlined in the ANZECC Guidelines.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 102
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Therefore, in terms of appropriate ammonia and nitrate protection levels for discharge to the
unnamed tributary, both ammonia and nitrate should be considered as toxicants and the 95%
protection levels outlined in the ANZECC Guidelines applied (Table 3.4.1 in Guidelines). Given
the pH-dependence of ammonia toxicity, this ammonia protection value should be pH
corrected, resulting in a trigger value of 1.6 mg/L (see Table 23).
Proposed Water Quality Targets for Discharge to Cooee Creek Tributary
As discussed above, the EPA proposed water quality objectives for Cooee Creek were derived
from a relatively small data set which mostly did not include samples from the unnamed
tributary of Cooee Creek and are considered a draft set intended to be progressively updated
as more specific data becomes available. These values are based on the least impacted sites
within the SMD (Slightly to Moderately disturbed ecosystem) and are considered to represent
aspirational Water Quality Targets. If the Creek-specific water quality data gathered as a part
of this project (April 2014) is included in the overall data set this would alter the 20th
/80th
percentile trigger values, especially for nutrients and pH.
Hence, for the purpose of setting up specific creek water quality protection levels that would
adequately reflect both the specific creek data and the objectives set by the EPA, two types of
targets were developed:
1. Interim targets – that fully reflect creek-specific conditions; they were derived using the
monitoring data from April 2014. These targets are intended to be immediately adopted
and implemented.
2. Aspirational targets – derived by inclusion of creek-specific data into the EPA data set.
These targets are intended to replace the interim targets when the EPA dataset is
statistically robust and trigger values set as final, and after the performance of the
treatment system has been validated over several years .
These two target types apply for nutrients and pH only; the targets for other stressors
(physical) adopt the EPA set values, while targets for toxicants and other pollutants were
derived from relevant ANZECC guidelines.
Therefore, the following water quality protection levels are proposed to be used to manage
discharge of the treated leachate into the Cooee Creek unnamed tributary (Table 23):
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 103
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Temperature, conductivity, turbidity & Chlorophyll-a – targets as outlined by EPA.
pH and DO
a) Aspirational Targets: Targets determined by including the most recent April
2014 WQ data into the EPA data set and recalculating the 20th
/80th
percentile
trigger value.
b) Interim Target: Target derived as the median values from Cooee Creek and the
unnamed tributary from April 2014 monitoring data (current baseline).
TN & TP
a) Aspirational Targets: Targets determined by including the most recent April
2014 WQ data into the EPA data set and recalculating the 80th
percentile
trigger value.
b) Interim Target: Target derived as the median values from Cooee Creek and the
unnamed tributary from April 2014 monitoring data (current baseline) .
Ammonia – ANZECC 95% trigger values for freshwater ecosystems corrected for pH
(toxicants, Table 3.4.1).
Nitrate and Metals - ANZECC 95% trigger values for freshwater ecosystems
(toxicants).
Fe – EPA advice on soluble iron (target 0.3 mg/L) was adopted together with the
relevant trigger values for total metals as outlined in the ANZECC Primary Industry
Guidelines (2000).
Other chemical pollutants - ANZECC 95% trigger values for freshwater ecosystems.
Faecal coliforms / E. coli – Currently, the creek water is primarily used for irrigation
of pasture and fodder for dairy animals and as a drinking supply for dairy animals. The
use of this water for garden irrigation cannot be excluded although the exact type of
vegetables being irrigated (e.g. salad vegetables or vegetables requiring peeling or
cooking), the extent of any garden areas and frequency of irrigation, as well as the
irrigation methods (via spray or trickle irrigation) is not known.
In terms of potential recreational use, given the current degraded nature of the
unnamed tributary (i.e. erosion, relatively poor water quality, highly impacted by the
extensive urban and agricultural land use in the catchment) this creek is rarely if ever
used for recreational purposes and is most likely used for secondary recreational
activities only, which include activities with less body contact such as fishing.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 104
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
In light of this, the following guidelines and trigger values were considered appropriate
for setting the protection levels for coliforms:
o The ANZECC Guidelines for recreational water quality and aesthetics (2000):
the secondary level recreational contact - the median value in fresh and marine
waters not to exceed 1,000 faecal coliform organisms/100 mL or 230
enterococci organisms/100 mL.
o The ANZECC Guidelines for Primary Industry (2000): drinking water for
livestock – the median value not to exceed 100 faecal (thermotolerant)
coliforms per 100 mL (median value).
o The ANZECC Guidelines for Primary Industry (2000): irrigation waters for
pasture and fodder (for grazing animals except pigs and dairy animals) - the
median value not to exceed 100 faecal (thermotolerant) coliforms per 1,000 mL
(median value).
Escherichia coli is a more sensitive indicator of faecal pollution of source water than
thermotolerant coliforms, and are already monitored as part of the routine BCC
leachate monitoring program. Consequently, E.coli and enterococci have been
adopted as the key indicators of microbiological contamination of creek water with
human (and to a lesser degree, animal) faeces. In line with the ANZECC guidelines
outlined above, the protection levels were set to be <230 organisms/100 mL for
enterococci and <100 cfu/100 ml for E.coli.
Note, this protection level is above the trigger values set for irrigation of vegetable
crops that are directly eaten (e.g. lettuce) which is <10 cfu/100 ml. Given the
uncertainties regarding the use of creek water for this particular purpose, and more
importantly, considering the multiple inputs to the creek from nearby residential
properties and farms which include pathogen contaminated agricultural surface run off,
it is questionable if such a pristine water quality (in terms of pathogen) can be
achieved at all.
Surface run-off from agricultural land or irrigated pasture runoff is known to contain a
major numbers of faecal organisms with levels being as high as 40,000 cfu /100 ml
(Carey et al, 2004). Furthermore, the levels of E.coli in Shorewell Creek passing
through the residential areas of Burnie were detected to be ~2,000 cfu/100 ml
(Sharman, R (2002). Consequently, setting up a very stringent pathogen protection
level of <10 cfu/100 mL was considered impracticable and not critical for the protection
of public and animal health, and a more appropriate, less stringent value of <100
cfu/100 ml was hence adopted.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 105
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 23. Proposed water quality protection levels for discharge to the Cooee Creek
unnamed tributary
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 106
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
5.2.9 Biodiversity & Conservation Significance
There are no national parks, nature reserves or wetlands of national significance (RAMSAR) in
the vicinity of the project site (10 km). The site also does not contain outstanding natural
features.
This proposal was referred to the EPBC in November 2014, and was determined as not a
controlled action (APPENDIX 3).
Listed threatened species and ecological communities
Two natural values assessments of the landfill site for BCC have been undertaken in recent
years – one as part of the Stage 2 landfill rehabilitation planning (NEST 2013) and most
recently one as part of the Landfill Stage 1 leachate management project ( APPENDIX 2).
These studies found that there are several species listed under the Environment Protection
and Biodiversity Conservation Act 1999 (EPBC Act) recorded within 500m of the Burnie Waste
Management Centre and along the un-named tributary flowing from the Centre. Several
species are also listed under the Tasmanian Threatened Species Protection Act 1995.
The threatened species listed under the EPBC Act and recorded within 500 m and 1 km of the
un-named tributary or are likely to occur here, based on habitat, are listed in Table 24. The
section of the creek that flows through the BWMC and the unnamed creek itself were found to
be a suitable habitat for the Burnie burrowing crayfish. This was the only species confirmed
within 1 km of the project site. The Green and gold frog and Eastern barred bandicoot could
potentially inhabit this zone (APPENDIX 2), however the survey did not identify individuals or
evidence of their activity. The only evidence of activity for these two species was found in the
creek section 4 kms downstream of the project site. No impacts to the Eastern barred
bandicoot are likely given the key threats to this species are feral animals and remnant
vegetation disturbance.
The nearest State listed Threatened ecological community is an undefined wetland, which is
listed as vulnerable under State legislation (Nature Conservation Act 2002), and occurs ~2
kms downstream of the project site (LIST Database). It is not listed as being of National
significance.
This community was not identified within the NEST (2014) report, however it was noted that
this area is highly impacted from weeds and cattle impacts. Eucalyptus viminalis wet forest,
which is listed as endangered occurs in uplands around the forested Cam River catchment,
however is not within the area of impact.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 107
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 24. Threatened species recorded (in bold) within 500m of stream reach and
those potentially present, by habitat type or survey evidence (NEST 2014)
Listed migratory species
Field surveys conducted in July 2014 (NEST 2014) observed only one migratory species with
the potential to inhabit the area is, Lathamus discolour (Swift Parrot) which is an endangered
species.
Vegetation & Flora
Native vegetation of the areas surrounding the project site is reflective of the diverse
topography of the region, as well as localised hydrological and geological influences. Much of
the privately-owned land in the region has been cleared for agriculture, which has impacted on
the water quality of the creeks and groundwater.
The natural vegetation of the region is Eucalyptus obliqua wet forest with broad leaf shrubs
growing on the lower slopes, with white gum wet forest (Eucalyptus viminalis wet forest)
occurring on the upper slopes and outside of the project area of influence. The wet obliqua
forest dominates the Cooee Creek environment. This community is dominated by stringybark
eucalypts (Eucalyptus obliqua) with a mixture of broadleaf species such as blackwood (Acacia
melanoxylon), dogwood (Pomaderris apetela), and an understorey including forest daisybush
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 108
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
(Olearia lirata), stinkwood, (Zieria arborescens), satinwood (Nematolepis squamea) and
treeferns (Dicksonia antarctica) (APPENDIX 2).
A total of 29 plant species were identified during the site survey in 2014 over a distance of
approximately 4 km, including the project site. None of the identified species are threatened
flora, i.e. they are not present on the list of Ihreatened plants within the Burnie Local
Government Area (Department of Primary Industries, Parks, Water and Environment,
Threatened Species Section (DPIPWE), site accessed November 2015).
Seventeen weeds/exotic species were also identified. Of these, four species (gorse,
blackberry, Cortaderia species and Elisha's tears) are on the list of Declared Agricultural and
Environmental Weeds in Tasmania (DPIPWE Tasmania, site accessed November 2015).
These declared weeds were primarily identified in creek sections surrounded by agricultural
land.
The section of the creek that flows through the BWMC was found to be highly impacted, with
heavy weed infestations. The dominant weed species in areas close to the BWMC is the
invasive riparian weed, Glyceria, which is classified as a Non-declared Agricultural and
Environmental Weeds in Tasmania (DPIPWE). This weed was considered to be the highest
risk weed to the natural values of the creek (APPENDIX 2).
Fauna
The NEST (2014) assessment of natural values of the Cooee Creek un-named tributary
included an assessment of fauna (APPENDIX 2). This survey was done over the entire 4 kms
from the Waste Management Centre to the confluence with Cooee Creek.
This study found that the section of the creek that flows through the BWMC is suitable habita t
for the Burnie burrowing crayfish. The Spotted tailed quoll, Green and gold frog and Eastern
barred bandicoot could potentially also inhabit this zone.
Downstream of the BWMC, creek sections either passing through areas of native vegetation or
areas that have had work undertaken to improve the riparian zones showed evidence of
burrowing crayfish activity consistent with the presence of the Burnie burrowing crayfish.
Cooee Creek approximately 3 kms from the BWMC provides a well-shaded stream with pools
suitable for presence of the Giant freshwater crayfish.
The green and gold frog was considered potentially occurring in the creek areas in the vicinity
of the project site (unnamed tributary). Signs of habitation by pademelons (Thylogale
billardierii) and Tasmanian Native-hen (Tribonyx mortierii) were also noted.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 109
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Riparian areas in proximity of the project site that are well connected to larger patches of
bushland, are expected to be used as hunting territories by the Tasmanian devil and spotted -
tailed quoll.
A Masked owl (Tyto novaehollandiae) was also sighted during the survey. Signs of bandicoot
activity were also found but it could not be determined whether it was from the Southern brown
bandicoot (Isoodon obesulus) or Eastern barred bandicoot (Perameles gunnii).
As expected, sighting of fauna was dependent on the level of creek degradation and
vegetation cover.
5.2.10 Natural Events & Hazards
Fire
Currently, the risk of fire at the BWMC is relatively low due to the operations being now limited
to waste recovery, and due to existing procedures covered by the existing EPN and
management plan for the site (Mooreville Rd Landfill Environmental Operations Manual,
Meinhardt Infrastructure and Environment Pty Ltd, April 2005). Strict management procedures
apply that include the following:
Strict control of accepted waste types (no explosives).
Site supervision during hours of operations and presence of a Caretakers’ residence
on the site perimeter.
No permission for open fires on the site; only regulated gas flames are us ed.
Appropriate training of operators for fire fighting.
Provision of fire breaks.
Provision of vehicular access on site to all fire fighting equipment.
Provision of appropriate signage.
Appropriate and regular maintenance of all fire fighting equipment.
Restricted site access.
Flooding
The 1000 year ARI flood line is assumed to be up to ~1.0 to 1.5 m above existing surface
above the current creek waterway (top of bank). The outline of the 1000 year floodplain is
shown in Figure 35. The treatment wetland will be located well above this line. The pump
station, emergency storages and infiltration swale will be located within this zone (since this is
the current status).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 110
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 35. The outline of the 1000 year floodplain (blue hatched areas)
Natural Hazards
No active or recent landslides have occurred on the site or have been mapped historically
(MRT Burnie Landslide Inventory Map, Stevenson et al 2010).
5.2.11 History of Waste Management
A summary of historical waste management activities on site that may affect the proposal is
summarised below. In the main, this information is relevant to understanding the nature of the
leachate chemistry (due to mixing with groundwater as discussed in Section 5.2.4), and the
geotechnical assessment of locating a wetland treatment system on top of the landfill cap (see
6.1.2).
Prior to development, the site contained springheads and shallow gullies and a large
swamp at the confluence of the creeks. “Stormwater” pipes were installed in the base
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 111
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
of the landfill cell to collect the spring flow and surrounding groundwater seepage. The
pipes were rubber ring joined concrete pipe. Strictly speaking, the pipes form a
groundwater drainage system.
The groundwater drainage system under Stage 1 Landfill was compromised many
years ago during landfill operations. Recent (August 2015) photographic evidence
confirms that:
o For some of the manholes, holes were punched into the concrete manhole
sections to allow surface runoff to drain from the operating landfill surface,
o Some manhole shaft joints were not properly sealed, allowing leachate to seep
into the manholes.
o Manhole E shows that the liners are mis-aligned allowing seepage into the
manhole. There are also several holes in the liners.
Stage 1 Landfill was filled between 1987 and 2004, and capped in 2004/2005. Survey
data confirms the base of the manholes is about 10 m below the landfill cap. Anecdotal
commentary from the BCC Waste Team Leader at the time was that filling started
against the northern containment bund wall and progressed in a southerly and easterly
direction. When filled, a temporary cap was put on the landfill. Approval was then
obtained from the licensing authority to place a 2nd lift (3 m of waste) on Stage 1. The
2nd lift was achieved by constructing a bund wall along the northern edge of Stage 1
and filling in the same manner as the first lift: in a southerly and easterly direction
(verified by the cross section presented in Figure 4 of the Tasman Geotechnical report,
APPENDIX 6). There was no separation of waste during filling of Stage 1 (eg greens,
paper and metals) and car bodies were squashed and included in the waste.
Spreading and compaction of the waste was achieved with a 14t drott, an earthmoving
machine similar to a bulldozer, but with a front bucket. However, the degree of
compaction of the waste was minimal. The use of a compactor at the site did not
commence until close to the end of Stage 1. Hence, compaction of the waste is likely
to be poor.
Assuming poor compaction of the waste, the bulk density may be as low as 0.6 t/m3.
However, considering the inclusion of day and intermediate cover, some compaction
from the drott and the fact that Stage 1 was capped at least 10 years ago, it can be
argued that the waste density is higher. A value of 0.8 t/m3 is deemed appropriate to
assess the long term stability of the landfill.
The Stage 1 Landfill comprises two capping designs – the northern part has a rock
aggregate drainage layer while the southern part contains a Geosynthetic Clay Liner
(GCL) (visible on Figure 35 and APPENDIX 7).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 112
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Between 2007 and 2015, the site was accepting select clay material, which was
progressively placed and stockpiled on the western side of the Stage 1 cap. Stage 2A
landfill was capped in March 2015 with the clay stockpiled on Stage 1.
5.3 SOCIO-ECONOMIC ASPECTS
As previously discussed under the Public Consultation Section (Section 4.0), the key
stakeholders that will potentially be impacted by or have an interest in the proposed project
include immediate neighbours, downstream landowners, the broader Burnie Community, the
TAFE Farm, Schools, UTAS, Cradle Coast Authority, NRM and Burnie City Council.
5.3.1 Project Socio-Economic Benefits
In addition to environmental gains, the project is expected to provide a range of social as well
as economic benefits to these key stakeholder groups.
Social Benefits
At the present, the landfill site has no broader social benefits to the local and regional
community, outside of the waste management function. The Stage 1 site is fully fenced and is
not accessible to the public. The site has a very limited biodiversity and aesthetic values, and
is not visually connected to its surroundings.
The proposed wetland system is expected to greatly enhance the aesthetic and biodiversity
values of the landfill and enable better integration of the site with its surrounding environment.
The constructed wetland system will provide an opportunity for installation of boardwalks and
other interpretative signage, and for ongoing teaching and research opportunities with lnks to
the UTAS Cradle Coast Campus and schools. This is expected to increase community
appreciation of the site and site usage, and it is anticipated that over the time (especially after
the wetland system achieves maturation) the site will be frequently utilised by the local
community.
Planting of the wetland will be undertaken with community involvement including local schools,
interested local community members and the NRM group.
Economic Benefits
The project is expected to provide several direct and indirect economic benefits on both a
local and regional scale. These include:
Freeing up capacity in the Round Hill WWTP via removal of leachate from the sewage
system for other industries. A key immediate development demand in this regard is
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 113
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
expansion of the cheese processing plant by Lion, which is a lead enterprise for the
expansion of the dairy industry in the north-west coast of Tasmania.
The proposal will not have a negative effect on surrounding land values. On the
contrary, the planned the wetland and associated creek restoration and stormwater
works will enhance the values of the site and surrounding land.
Increases in environmental flows will potentially increase the irrigation capacity of the
creek system further benefiting downstream agricultural users.
Provision of employment opportunities during the system construction for the local and
wider regional community.
5.3.2 Heritage
Aboriginal Heritage
Aboriginal people are known to have lived in the region. It is recognised that all registered and
unregistered Tasmanian Aboriginal sites are protected by the State Aboriginal Relics Act 1975
and the Commonwealth Aboriginal and Torres Strait Islander Heritage Protection Act 1984.
A review of the Tasmanian Aboriginal Land Council (TALC) site register indicated an absence
of Aboriginal sites and/or artefact areas within a 2.5 km radius of the landfill site. An aboriginal
cultural heritage assessment of the area confirmed there are no aboriginal artefacts on the
landfill site (SEMF, 2002).
The landscape of the landfill site has been significantly modified by the historic agricultural
and grazing activities and more recently activities associated with landfill operations. As such
there are no Aboriginal landscape values remaining within the project area, in the form of
significant native vegetation with traditional cultural associations. The project area is assessed
as being of low archaeological sensitivity (SEMF, 2002).
European Heritage
The project must comply with the Historic Cultural Heritage Act 1995.
However, there are no listed heritage properties and/or values as no places or sites exist in
the project area that are listed on the National Heritage List, Register of the National Estate,
Tasmanian Heritage Register or the Tasmanian Historic Places Inventory.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 114
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.0 POTENTIAL IMPACTS & THEIR MANAGEMENT
6.1 KEY ISSUES SPECIFIC TO THIS PROPOSAL
The key issues identified as specific to this proposal are:
Potential surface water hydrology and water quality impacts.
Potential groundwater impacts and geotechnical issues.
The background to these issues is covered in Section 5.0. This section uses a risk based
assessment method to identify the potential impacts, receptors, pathways and
mitigation/management measures required (or already incorporated into the design), to
manage these risks. To assist in the assessment of surface water quality impacts, the mass
pollutant loads expected to be discharged to the infiltration Wet Forest (on site) and to the
unnamed Cooee Creek tributary, is provided, as well as a summary of geotechnical issues
pertinent to the risk profile. The hydrogeotechnical report is provided as APPENDIX 6.
The proposal is not expected to have any impacts on the groundwater aquifer, since the
proposal sits within a groundwater discharge zone with all groundwater within Stage 1
discharging via surface flows or subsurface seepage to the unnamed Cooee Creek tributary.
This has been discussed throughout the document and in detail in Section 5.2.6, and is
illustrated in the current conceptual site model (Figure 29) and the conceptual model showing
the proposed development (Figure 36).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 115
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 36. Conceptual site model – PROPOSED DEVELOPMENT SCENARIO
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 116
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.1.1 Potential Surface Water Quality and Hydrological Impacts
The proposed design of the leachate wetland system aims to minimise direct discharge of the
treated leachate to the unnamed tributary of Cooee Creek by maximising on-site infiltration
within the last component of the system (Infiltration Wet Forest). Hence, most of the treated
leachate will discharge indirectly via subsurface infiltration to the Creek , with only flows in
excess of the infiltration capacity of the Wet Forest overflowing directly to the Creek via a
weir/cascade (i.e. during high or prolonged seasonal rainfall events).
This proposal will result in three key changes:
1. Treatment of the Stage 1 leachate to ANZECC aquatic ecosystem protection standards
prior to discharge.
2. Indirect discharge on site of highly treated leachate via infiltration in low and average
flows (<360 m3/day).
3. Direct discharge to the creek in high seasonal flows, prolonged rainfall periods which
generate above average leachate flows, and peak flows), rather than to sewer.
The proposed routing of flows and water balance is indicated in Figure 37.
Of note, the Stage 1 leachate chemistry is below the EU Landfill Directive Annex II criteria for
inert waste, meaning this would be allowable for direct release to the environment in EU
countries (see discussion in regard to this in Valencia et al 2009). This is not obviously
proposed here however provides some context as to the highly risk averse approach taken to
the treatment and discharge design.
To inform the risk assessment, an assessment of treated leachate flows and pollutant mass
loads to the infiltration forest and to the creek is provided below. Note, actual daily rainfall and
leachate data for the period 2010 – 2014 was used to generate the daily mass balance. This
dataset includes peak rainfall events. The daily mass balance assumes that once the soil
profile is saturated, all further inputs will report via overland flow to the discharge point, and
via the stormwater swale to the Cooee Creek discharge point as shown in Figure 11 and
Figure 12.
Mass load calculations were undertaken using the following inputs and assumptions:
Area of the Infiltration Wet Forest of 4,000 m2, with a 100 mm operating water depth
and additional 100 mm freeboard activated in large flow periods.
Actual (empirical) daily rainfall data and daily leachate flows for the period 2010-2014.
It is important to note that these flow data incorporate peak rainfall events that
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 117
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
occurred within the 2010-2014 period, including the extreme (>80 year) 2011 summer
rain events and includes both wet years (2012, 2013) and a dry year (2014).
A conservative infiltration rate of 1*10^-6
m/s. Previous borelogs around the site (Coffey
2004, 2007 and APPENDIX 6) indicates the soils in the proposed infiltration area are
sandy clays and silty clays. The recent bore (BH26, Figure 38, drilled as part of the
geotechnical risk assessment indicated soils were silty clays near the toe of the Stage
1 northern embankment (APPENDIX 6). Weathered basalt in BH26 was encountered
at 2.5m bgl. Previous descriptions of a bore near to the Stage 1 pump station (MH1)
indicate deeper profiles with groundwater observed at ~4.5m bgl (Coffey 2007).
For nutrients, iron, manganese and zinc - concentration in the Infiltration Wetland
effluent were modelled based on the approach outlined in Kadlec & Wallace 2008 and
using mean monthly concentrations, temperature adjustments and pollutant specific
removal rate coefficients (Table 25).
For other contaminants of concern, final effluent concentrations were ass umed to have
met the set WQ targets at the outlet of the polishing wetland as outlined in Table 23
(Table 25).
Indirect Discharge Occurrences - Estimated Mass Loadings to Wet Forest
The infiltration ‘Wet Forest’ is designed as a large riparian buffer which will further attenuate
the volume of treated leachate and mass of residual nutrients and trace metals on -site, via the
following processes:
1. Infiltration and storage of water within the soil pore spaces (infiltration rate assumed at
1*10^-6,
which was recorded in bores within the proposed area).
2. Complexation of minerals with clay particles and organics .
3. Plant uptake of water and nutrients.
Treated leachate infiltrated within the site not taken up in soil storage and evapotranspiration,
will eventually join the groundwater throughflow at the contact zone of the basalt, and migrate
via subsurface flows to the creek. The model indicates that subsurface flows will be minimal
(limited to spring/winter). Due to the attenuation within the vertical soil profile (~2.5 – 4.5 m
depth) and the long lateral flow path (>100 m), the concentration of pollutants is expected to
be >90% attenuated (typical of riparian buffers), hence any subsurface discharges will be very
minor in terms of mass load.
For the purpose of this mass balance, all water in excess of ET and soil storages is assumed
to discharge via surface flows to the creek, with indirect discharges ignored at this stage. The
mass loads to the infiltration wetland are shown in Table 26, Table 27 and Figure 39.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 118
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 37. Proposed water circuit and water balance for normal (median) and high flows
MH1
ORANGE: All internal flows through wetland
YELLOW: High flows, 23L/sec max flow rate engaged when median flows exceed 20L/sec. Max 1989 m3/day
HIGH FLOW SPLITTER
BOX & SEDIMENT
DROP OUT CHAMBER
HEADER TANK/SPLITTER
LIGHT BLUE: Median flows, 20L/sec max flow rate max 1728 m3/day
DARK BLUE: All raw leachate flows to max 3600 m3/day or 43 L/sec
RED: All dilute flood flows >3600 m3/day (>80 year event) from emergency storage to swale and creek (>43 L/sec) – flows will be mixed & diluted with on-site stormwater and creek flood flows.
MH1
EMERGENCY STORAGE
GREEN: All treated flows plus rainfall via outlet pipe to infiltration wetland - max 5500 m3/day . Flows in excess of infiltration capacity overflow to max swale and creek - ~35 ML per year .INFLUENT
SAMPLE LOCATION (INF)
EFFLUENT
SAMPLE
LOCATION (EFF 1)
PURPLE: Recirculation of non-compliant flows (max 4 L/sec 350 m3/day.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 119
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 38. Site layout showing borehole locations (from Tasman Geotechnics report,
August 2015). Note BH26 is within natural ground. MW bores are monitoring
wells
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 120
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 25. Pollutant concentrations in the Infiltration Wetland effluent
Table 26. Volumes estimated to be discharged directly to the Infiltration Wet Forest –
mean daily
Table 27. Annual discharge and mass loadings to the Infiltration Wet Forest
Pollutant
concentrations
(mg/L)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
TSS 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31
TN 0.3296 0.2625 0.2072 0.2113 0.4015 0.4064 0.4338 0.8906 1.0028 0.7631 0.4307 0.3626
Ammonium N 0.2707 0.2102 0.1584 0.1626 0.3295 0.3341 0.3543 0.7789 0.8877 0.6712 0.3671 0.3030
Organic N 0.0418 0.0416 0.0403 0.0408 0.0398 0.0397 0.0390 0.0391 0.0390 0.0403 0.0418 0.0418
Nitrate N 0.0170 0.0108 0.0085 0.0078 0.0323 0.0326 0.0405 0.0726 0.0762 0.0516 0.0217 0.0178
TP 0.0107 0.0098 0.0082 0.0083 0.0088 0.0088 0.0082 0.0134 0.0151 0.0142 0.0121 0.0111
Fe 0.0368 0.0277 0.0164 0.0243 0.0357 0.0387 0.0345 0.0790 0.1044 0.0776 0.0685 0.0339
Mn 0.1156 0.0906 0.0547 0.0647 0.0829 0.0848 0.0721 0.2714 0.3431 0.2848 0.1752 0.1355
Zn 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0004 0.0006 0.0005 0.0002 0.0002
Al 0.0550
Cr 0.0010
Cu 0.0014
Ni 0.0110
Sn 0.0050
modelled pollutant concentrations
assumed requred conc target will be achieved for these pollutants as outlined in WQ Target table
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
discharge
(m3/day)255.4 225.3 264.5 264.5 312.6 322.7 327.3 526.2 556.8 482.1 383.9 314.5
VOLUMES DISCHARGED TO INFILTRATION WET FOREST (average daily for period March 10-Dec 14)
Pollutants Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecANNUAL
(kg)
TSS 2.45 1.96 2.54 2.46 3.00 3.00 3.15 5.06 5.18 4.63 3.57 3.02 40.02
TN 2.61 1.66 1.70 1.68 3.89 3.93 4.40 14.53 16.75 11.40 4.96 3.54 71.05
NH4- N 2.14 1.33 1.30 1.29 3.19 3.23 3.59 12.71 14.83 10.03 4.23 2.95 60.83
Org N 0.33 0.26 0.33 0.32 0.39 0.38 0.40 0.64 0.65 0.60 0.48 0.41 5.20
Nitrate N 0.13 0.07 0.07 0.06 0.31 0.32 0.41 1.18 1.27 0.77 0.25 0.17 5.03
TP 0.06 0.04 0.05 0.05 0.06 0.06 0.06 0.15 0.18 0.15 0.10 0.08 1.02
Fe 1.28 0.75 0.55 0.79 1.45 1.57 1.44 6.07 8.42 5.51 3.59 1.47 32.90
Mn 0.92 0.57 0.45 0.51 0.80 0.82 0.73 4.43 5.73 4.26 2.02 1.32 22.56
Zn 0.0012 0.0007 0.0005 0.0006 0.0009 0.0010 0.0008 0.0071 0.0098 0.0069 0.0029 0.0017 0.03
Al 0.436 0.347 0.451 0.436 0.533 0.533 0.558 0.897 0.919 0.822 0.633 0.536 7.10
Cr 0.0079 0.0063 0.0082 0.0079 0.0097 0.0097 0.0101 0.0163 0.0167 0.0149 0.0115 0.0098 0.13
Cu 0.0111 0.0088 0.0115 0.0111 0.0136 0.0136 0.0142 0.0228 0.0234 0.0209 0.0161 0.0137 0.18
Ni 0.087 0.069 0.090 0.087 0.107 0.107 0.112 0.179 0.184 0.164 0.127 0.107 1.42
Sn 0.040 0.032 0.041 0.040 0.048 0.048 0.051 0.082 0.084 0.075 0.058 0.049 0.65
MONTHLY MASS LOAD TO CREEK (kg)
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 121
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 39. Annual mass loading to the Infiltration Wet Forest (based on actual daily
rainfall and leachate flows)
Direct Discharge Occurrences - Estimated Mass Loadings to Creek
The creek volumetric discharges and mass load discharges in each month and annual mass
load discharges for select pollutants, are shown in Table 28, Table 29 and Figure 40.
Table 28. Volumes estimated to be discharged directly to the Creek – mean daily
0
10
20
30
40
50
60
70
80
TSS TN NH4-N
Org N Nitrate N
TP Fe Mn Zn Al Cr Cu Ni Sn
pollutants 40.02 71.05 60.83 5.20 5.03 1.02 32.90 22.56 0.03 7.10 0.13 0.18 1.42 0.65
kg
annual mass loading (kg)
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 122
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 29. Mass pollutant load to creek based on daily rainfall and flows
Figure 40. Annual mass loading to the Creek (based on daily rainfall and flows)
Pollutants Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecANNUAL
(kg)
TSS 0.34 0.14 0.23 0.16 0.35 0.38 0.37 1.71 1.74 1.19 0.46 0.24 7.3
TN 0.36 0.12 0.16 0.11 0.45 0.50 0.51 4.90 5.63 2.92 0.64 0.28 16.6
NH4- N 0.30 0.09 0.12 0.09 0.37 0.41 0.42 4.29 4.98 2.57 0.55 0.23 14.4
Org N 0.05 0.02 0.03 0.02 0.04 0.05 0.05 0.22 0.22 0.15 0.06 0.03 0.9
Nitrate N 0.02 0.00 0.01 0.00 0.04 0.04 0.05 0.40 0.43 0.20 0.03 0.01 1.2
TP 0.01 0.00 0.00 0.00 0.01 0.01 0.01 0.05 0.06 0.04 0.01 0.01 0.2
Fe 0.18 0.05 0.05 0.05 0.17 0.20 0.17 2.05 2.83 1.41 0.47 0.11 7.7
Mn 0.13 0.04 0.04 0.03 0.09 0.10 0.09 1.49 1.93 1.09 0.26 0.10 5.4
Zn 0.0002 0.0000 0.0000 0.0000 0.0001 0.0001 0.0001 0.0024 0.0033 0.0018 0.0004 0.0001 0.0
Al 0.060 0.024 0.042 0.029 0.062 0.068 0.065 0.303 0.309 0.210 0.082 0.042 1.3
Cr 0.0011 0.0004 0.0008 0.0005 0.0011 0.0012 0.0012 0.0055 0.0056 0.0038 0.0015 0.0008 0.0
Cu 0.0015 0.0006 0.0011 0.0007 0.0016 0.0017 0.0017 0.0077 0.0079 0.0054 0.0021 0.0011 0.0
Ni 0.012 0.005 0.008 0.006 0.012 0.014 0.013 0.061 0.062 0.042 0.016 0.008 0.3
Sn 0.005 0.002 0.004 0.003 0.006 0.006 0.006 0.028 0.028 0.019 0.007 0.004 0.1
MONTHLY MASS LOAD TO CREEK (kg)
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 123
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
The comparison of total annual discharge to the Creek in a dry year (2014) and wet years
(2012, 2013) and corresponding mass loadings of key pollutants is presented in Table 30.
Table 30. Annual discharge and mass loadings to creek.
In a dry year the discharge to the Creek and the mass loads of key pollutants is 70 -80% lower
compared to the average discharge. In wet years (such as 2012), discharge and mass loading
is approximately 1.5x higher compared to the average scenario.
Peak per day mass loading of key pollutants for 90% rainfall and flows through the system
(peak loading) was calculated using the average daily flows for the top 10% of monthly flows
for the period 2010-2014, and concentrations of pollutants as discussed above.
These peak per day mass loads to the Creek are presented in Table 31. On those peak days
loads to the Creek are ~4 times higher compared to average daily flows. However, it is
important to note that these peak loading days occur on average 2-3 times per month, or only
7-10% of the time within the year.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 124
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 31. Peak day mass load discharge to creek based on > 90% flows
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 125
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.1.2 Summary of Potential Impacts to the Creek
Based on the empirical rainfall and leachate data analysed for the period 2010 to 2014, >90%
of summer‐autumn flows and >75% of winter‐spring flows will be infiltrated within the
‘Infiltration Wet Forest’ along the northern boundary of the site, with only flows in excess of the
infiltration capacity directly discharged to the creek. Hence, on most days there will be no
direct discharges to the creek, and infiltrated flows will be expressed as subsurface seepages
along the banks and base of the unnamed creek tributary. These flows will help to restore the
riparian vegetation and muddy creek conditions favourable to the Burnie burrowing crayfish
and other fauna.
In terms of mass pollutant loads, this proposal will divert minor (predominantly nutrient) loads
to the creek which otherwise would have reported to the sewer system. However, the current
pollutant loads which discharge to the creek via untreated stormwater flows (Table 19) is
significantly higher (more than 11 times the mass of nitrogen for example) than what will be
contributed via treated leachate flows. Since part of the Stage 1 leachate project is to
undertake stormwater improvement works, a percentage of the annual (1 year ARI and less)
mass loads will be retained and treated within the proposed stormwater swale and will no
longer discharge to the creek. The modelling and sizing of the stormwater system is currently
underway, however it is expected that the stormwater swale will remove as a minimum 30% of
the total nitrogen and total phosphorus loads to the creek, and more than 80% of the metal
load. If this is achieved, total nitrogen (key nutrient of concern), would reduce from 178
kg/annum minimum mass load to 124 kg/annum, which means 53.4 kg would no longer report
to the creek. Hence, whilst the treated leachate discharge will result in on average 16
kg/TN/annum being discharged to the creek, more than 3 times this amount will be removed
as a result of stormwater treatment, hence the net effect will be a reduction in pollutant loads
discharged to the creek.
During large storm events, stormwater will discharge as normal to the creek hence there will
be little change to mass loads, however high flows will be conveyed via a rock cascade
structure which will remove sediment even in these larger events. There will be a higher
discharge of treated leachate to the creek in these events since the infiltration capacity of the
Wet Forest will be exceeded. This results in a higher mass load discharge as indicated in
Table 31, however the affect is small on an annual basis (less than 1.5 times average mass
loads) since these are short term events. Furthermore, during these events the broader
catchment effects of dilution and peak run-off will dominate and largely mask these events, as
now typically occurs for this creek. Further, during peak storm events, the tributary upgradient
of Three Mile Road is expected to cause flows to back up and spread broadly within the
floodplain (Tasmanian Consulting Services (appendix report within APPENDIX 6), hence
depositing most of the sediment and pollutant loads as a result along this localised section of
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 126
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
the creek. The hydrological modelling undertaken by Tasmanian Consulting Services indicated
that the tributary (referred to as the Northern Waterway/Creek in their report) would flood the
adjacent grass paddocks as follows:
In a 50 Year ARI the flooding is relatively minor and is localised to the area
immediately adjacent the road culvert at Three Mile Road,
For a 100 Year event the flooding extends to approximately half of its chainage.
During a 1000 Year event flooding extends to the entire chainage (with flooding at the
landfill boundary relatively minor).
In summary, the mass pollutant loads expected to be discharged to the creek in higher
seasonal rainfall periods and/or in prolonged rainfall events that result in the infiltration
capacity of the system being exceeded, are considered small considering the current
discharges to the Creek from the landfill site and neighbouring agricultural and residential
properties. They are significantly lower than what occurs typically at the site, both as a result
of discharges directly to the Creek when flows exceed the 20 year ARI capacity of the pipe,
pump and pit infrastructure, and in average stormwater discharge events.
On an annual basis, the nitrogen load exiting the site from treated leachate for example is
<10% of that discharge from the Stage 2A stormwater system through the existing piped
network (Table 19) (16 kg/annum, compared with 178 kg/annum).
As a part of this project, at least 30% of the annual mass pollutant loads due to stormwater will
be removed within swales and sediment drop out structures. In peak storm events, the creek is
expected to back up and engage the wider floodplain such that any sediment and entrained
pollutants (from either leachate or stormwater) are likely to be deposited within the floodplain,
rather than being conveyed further downstream. Hence, the overall Stage 1 leachate project
and associated stormwater improvement works combined will lead to a reduction in the overall
mass pollutant loads discharged to the creek.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 127
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.1.3 Potential Groundwater and Geotechnical Impacts
A hydrogeotechnical investigation and geotechnical model has been undertaken as part of this
project and is contained in APPENDIX 6.
The following potential hazards were identified and addressed in this study:
Wetland leakage – potential to saturate the landfill cell and resultant impact on the
containment bund.
Wetland mass load – potential for landfill cap settlement and risk to overall stability as
a result of the added mass load on the cell.
Water table rise/flood – potential for the inflowing groundwater table to rise within the
waste cell and/or flood from an extreme rainfall event.
Ahead of undertaking the hydrogeotechnical risk assessment a geotechnical model was
developed to provide a robust basis for the assessment. The model was informed by both
previous investigations, additional investigations undertaken as part of this study and revi ew
of published data.
A summary of the hydro-geotechnical model is as follows:
The Stage 1 Landfill is constructed on natural clay that forms the base of the landfill.
The landfill containment bund comprises the northern face of the Stage 1 landfill, and
includes both an excavated portion and constructed embankment.
The landfill is capped with 1 m to 2 m of compacted clay and a growing medium (at
least 0.5 m thick). The cap in the southern section of the landfill contains a GCL layer,
while the cap in the northern section of the landfill contains an aggregate rock layer for
lateral drainage. The cap effectively prevents seepage of runoff into the landfill cell.
The landfill cap is currently experiencing settlement of less than 2 mm/yr.
A section of the cap was surcharged by stockpiling soil. The settlement at the base of
that stockpile was measured to be 50 to 600 mm over a 7 year period. Removal of the
stockpile means that the waste has been pre-consolidated in this area.
Based on review of typical parameters, consolidation, or long-term, settlement is likely
to be completed within 2 years of placing a structure, such as the proposed wetland
cells.
The regional groundwater is recharged upstream of the landfill from rainfall and seeps
into the landfill cell through springs that were present before development of the site.
Groundwater collection pipes were installed on the floor of the landfill, however at least
one of the inspection manholes allows leachate into the groundwater collection pipes
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 128
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
and the pipes themselves were compromised, allowing leachate to enter. Excavation of
natural clay for construction purposes may have created new seepage zones.
There are several types of openings through which the leachate is drained from the
landfill: broken pipes and holes in manhole shafts. There are fewer openings near the
landfill containment bund than below the centre of the landfill. Therefore, the rate of
outflow near the containment bund may not be sufficient to discharge the groundwater
inflows after an intense rain period. Thus, the leachate level behind the landfill
containment bund increased in early August 2015, as the leachate is temporarily
“stored”.
6.2 HAZARD AND RISK ASSESSMENT OF KEY ISSUES
6.2.1 Risk Assessment Approach
A detailed risk assessment was undertaken using the approach outlined in the Principles and
Guidelines (Standards Australia, 2009), and the supporting document HB 203:2006
Environmental Risk Management – Principles and Process (Standards Australia, 2006). This
approach is based on the consideration of the likelihood and consequences of a hazard event
occurring, in the context of the environment and proposed design (i.e. key environmental
sensitivities and receptors, existing site conditions, design measures etc). It distinguishes the
inherent and residual risk of hazard incidents. Inherent risk represents the risk of
environmental harm occurring from a hazard if there were no mitigation controls in place.
Residual risk measures the likelihood and consequences of environmental harm taking
account of controls.
The inherent risk was analysed under two scenarios:
After acute problems such as significant incidences on site .
During chronic problems such as when a treatment system is performing poorly (e.g.
due to lack of maintenance).
Note, for this risk assessment it has been assumed that all the elements and contingency
measures included in the treatment system design are fully implemented, so the risks
assessed are those that can potentially arise from hazardous events / incidents outside of
normal system operation. In addition, the normal operation of the proposed Burnie leachate
treatment system, under which highly treated effluent is discharged to the unnamed tributary,
was also analysed in terms of any negative/positive impacts on the receiving environment and
any other relevant receptors (environmental and human).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 129
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.2.2 Risk Identification
The first step of the Burnie Risk Assessment process was the identification of potential risks.
This step included:
Identification of source of risk.
Identification of potential impacts.
Source of risk identification involved recognition of key hazards relevant to the site and
project, key hazardous events and environmental aspects (i.e. receptors and pathways). In
other words this first step is about developing a hazard−pathway−receptor model which
identifies and describes the nature of a risk and how environmental harm may result from it.
This is critical for undertaking risk analysis and developing an effective risk treatment.
To guide the risk assessment, a conceptual site model of the proposed development scenario
(Figure 36) was developed to identify the relevant receptors and pathways.
Identification of Receptors
A receptor is a specific ‘component’ of the environmental that could potentially be impacted by
the hazardous events associated with the project. A receptor could be biological (e.g. flora,
fauna species, habitats or entire ecosystems, biodiversity) or physical (e.g. groundwater,
surface water, land form, etc).
The receptor analysis for the Burnie project site (landfill), was done in the context of its
immediate and broader environmental setting, and using the findings from two natural values
assessments of the landfill site that have been undertaken in recent years (NEST 2013,
APPENDIX 2). Also, water quality and creek sediment baseline investigations undertaken for
this study were used to inform this process (Section 5.2.8).
Groundwater is not considered a receptor on site since the underlying hydrogeology confines
the aquifers with all superficial groundwater flows discharging directly to the creek (Section
5.2.6). Downstream groundwater users are also, by extens ion, not considered to be receptors
since there is no pathway. Groundwater springs that are collected in the groundwater drainage
system that was compromised during construction, does mix with leachate however is
collected within the leachate system and reports to the treatment system.
The following key receptors have been identified with summary descriptions provided.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 130
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Ecological Receptors
1. Unnamed tributary to Cooee Creek
o The unnamed tributary is a very minor part of the Cooee Creek system (5% of
catchment).
o There are no significant flora or fauna receptors within this creek tributary.
o The ecological and landscape values are low due to the extent of degradation and
reduced flows
o Restoring environmental flows to the creek is considered a positive environmental
benefit in terms of ecological values and recovery of significant species habitat.
Detailed information on this receptor is provided in Section 5.2.8.
2. Cooee Creek
o Cooee Creek receives a range of discharges from the surrounding agricultural and
residential land uses, and is not pristine. The Syrinx baseline studies indicate the
Creek system is equivalent to ANZECC Ecosystem Condition 2: Slightly to
moderately disturbed systems
o The key concerns are nutrients (total nitrogen, nitrate and total phosphorus) and
some metals (aluminium, copper, lead and manganese).
o Threatened and listed migratory species - the only potential matter of
environmental significance identified in the proximity of the landfill site is the
Burnie burrowing crayfish (listed as 'Vulnerable' under Schedule 4 of the
Tasmanian Threatened Species Protection Act (1995) and is listed as Vulnerable
under the EPBC Act 1999.).
Detailed information on this receptor is provided in Section 5.2.8.
3. Livestock
o The unnamed tributary and Cooee Creek are used for livestock drinking/stock
watering on properties along these creeks. Consequently, creek contamination as
a result of hazardous events occurring on the landfill site would potentially impact
on livestock.
4. Irrigation pasture
o Creek water is used primarily during summer months for irrigation of vegetable
crops and pasture, and this use could be jeopardised in the event of creek water
contamination.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 131
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Human receptors
1. Recreational users
o Humans could potentially be impacted by contamination originating from the landfill
site and leachate treatment system through recreational use of the unnamed
tributary and/or Cooee Creek.
o Considering the current degraded nature of the unnamed tributary (i.e. erosion,
relatively poor water quality, highly impacted by the extensive urban and
agricultural land use in the catchment) this creek is rarely if ever used for
recreational purposes and is most likely used for secondary recreational activities
only, which include activities with less body contact such as fishing.
2. On site workers & general public
o This group of human receptors include BCC employees and contractors that work
at the landfill site and the general public (mainly immediate neighbours) who can
potentially be exposed to hazardous events occurring within the site. The landfill
has been non-operational since 2012 (stopped taking waste) and is currently
operating as a Waste Transfer and Resource Recovery Facility. Hence, on site
personnel are limited. The site does not permit unauthorised access.
Possible Pathways
The pathway is the route via which a hazard can impact on the identified receptor(s) (note that
for one hazard there may be multiple pathways, receptors and mechanisms of harm). For
exposure to occur, a complete pathway must exist between the source of contamination and
the receptor. Where the exposure pathway is incomplete, there is no exposure and hence no
risk via that pathway.
Considering that the main identified receptors for the Burnie project site include two key
surface water features in the vicinity of the project site (unnamed tributary to Cooee Creek and
Cooee Creek itself) especially in terms of the possible impacts on the Burnie burrowing
crayfish, the main pathway identified for the project is via discharge of pollutants to the
unnamed tributary (Table 32). This can occur as a result of: i) direct discharge of untreated
leachate, and ii) direct discharge of partially treated leachate.
For human receptors, the main exposure pathway is direct contact with contaminants and
intake via solid waste and / or leachate ingestion and dermal contact with waste and/or
leachate (Table 32).
Contaminant pathway via atmospheric depositions (air-borne dust) has not been included in
the exposure pathways, as it can be expected that any air -borne contamination will present a
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 132
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
minimal risk to the human and surface waters compared with the risk of harm posed by direct
discharge and direct contact. Noise emission was also not considered to be a significant
exposure pathway. Both of these are addressed in later sections however.
Table 32. Summary of possible receptor/pathways interactions
Hazard / Hazardous Event Identification
A hazard is a source of potential harm or adverse impacts to the receptor; a hazardous event
is an event that results in the occurrence of negative impacts associated with the hazard.
The hazard/hazardous event identification process was based on an analysis of all activities
and processes associated with the operation and maintenance of the proposed leachate
treatment system, in the context of the local setting and current and future landfill activities.
This process resulted in short listing of the following hazardous events (incidences), which are
grouped based on their potential consequences:
Hazardous event/incidents resulting in the release of raw leachate and/or solid waste to
creek, and/or ponding of raw leachate on site
1. Sliding failure of landfill containment bund caused by:
a. Wetland mass/location compromises structural integrity of landfill bund.
b. Rising leachate levels within landfill causing saturation and weakening of
containment bund.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 133
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
2. Pump / electrical failure – caused by:
a. Power outage (weather, fire, explosion etc)
b. Pump clogging due to lack of / poor maintenance
Hazardous event/incidents resulting in the release of partially treated leachate to creek,
or ponding on site
1. Leakage of the proposed wetland treatment system leading to either seepage of
leachate through the clay liner base into the existing clay capping and lateral seepage
of leachate through the landfill containment bund. This could be caused by differential
settlement of the landfill cap potentially impacting liner integrity.
2. Failure of wetland embankment caused by differential settlement of landfill
leading to localised subsidence of wetland cell bunds, overtopping of leachate from
wetland bunds and exposure of partially treated leachate to receptors.
3. Failure or impeded performance of wetland cell(s) caused by:
a. Compromised system construction (system not built to design).
b. Cold weather that compromises biological system performance.
c. Change in leachate chemistry beyond design ranges for prolonged per iod of
time.
d. Contamination via pesticides, herbicides etc from neighbouring farm properties
that can cause plant/microbial death, and consequently reduced system
performance.
e. Poor system maintenance.
4. Increase in volumes of groundwater-leachate beyond treatment system capacity
in events of extreme & prolonged rainfall.
5. Damages to the treatment system caused by flooding from property upgradient
(east) in extreme rain potentially coupled with excessive irrigation.
6. Fire induced damages of the treatment system caused by vandalism, lightening
and/or electrical faults.
6.2.3 Risk Analysis
The risk analysis was carried out following the principles of the Australian Standard for risk
management to identify ‘priority risks’. Risk analysis included the following two steps: i) risk
evaluation and ii) preparation of risk treatment measures. A separate landfill risk assessment
was also undertaken as part of the Geotechnical Study (Tasman Geotechnics), based on the
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 134
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
risk matrix published by the Australian Geomechanics Society (AGS, 2007). This was also
used to inform the environmental risk assessment.
Environmental Risk Evaluation
In this step risks were determined using the likelihood and consequence approach, which then
enabled identification of management measures for individual determined risks.
Likelihood refers to the possibility or frequency of an environmental impact. The categories of
likelihood, consequence and risk used in the Burnie risk assessment is shown in APPENDIX
14.
In terms of risk evaluation for the Burnie leachate treatment system, the key concerns are any
implications of potential discharge of either raw or inadequately treated leachate to the
unnamed tributary, and the negative impacts of the discharge on the key iden tified
environmental and/or human receptors. Hence, the risk analysis was done for these two
concerns to develop an understanding of the severity of any risks (inherent risks) as well as
the management measures/strategies that are either already planned to be implemented or
need to be considered in order to reduce residual risks. As stated previously, in addition to
the key hazardous events, risk analysis was also undertaken for the normal system operation
which includes release of fully treated leachate to the unnamed tributary.
The risk evaluation is presented in APPENDIX 15.
In summary, there are no inherent risks that are considered unacceptable in any
circumstances and that are not possible to manage/mitigate.
The great majority of identified risks to the key environmental and human receptors from either
hazardous events or normal operations are inherently low (i.e. of an acceptable level). There
were only two risks characterised as medium and both of them are due to potential system
failure or impeded performance of wetland cell(s) that result in non-compliant quality of
leachate outflow. They are caused either by a) the system being inadequately built (not in full
compliance with the design) or b) poor maintenance. Both of these events are assumed to
occur occasionally (every 5-20 years) and the consequence of possible impacts arising from
these events are considered to be moderate given that discharge of non-compliant leachate
would potentially cause only short to medium term localised impacts.
Normal operation of the treatment system with discharge of highly treated effluent to the
unnamed creek was found to carry only low inherent risk. This is to be expected given that
potential impacts of the effluent discharge to the creek were analysed during the initial system
development and an array of measures were implemented in the system design to address
any of these potential impacts. The key arguments supporting the very low inherent risk of
normal system operation are:
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 135
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Very high quality of treated effluent – in line with EPA Draft Water Quality Objectives
for Cooee Creek and relevant ANZECC (2000) trigger values.
Discharge approach that minimise direct discharge of the treated leachate to the
unnamed tributary by maximising on-site infiltration within the last system component
(Infiltration Wetland / Wet Forest). This reduces the mass load of pollutants discharged
to the creek and enables further attenuation of infiltrated effluent.
The fact that the water quality within the unnamed tributary and Cooee Creek is
already relatively poor and both creeks are considered degraded due to historic and
current impacts from neighbouring land users. Consequently, these surface waters are
not used for swimming (or other primary recreational uses) and this is unlikely to
change in the future given declining water levels and many alternative locations.
Discharge of treated effluent (in terms of flows, pollutant concentration and mass
loads) is not considered to negatively impact on the unnamed tributary and Cooee
Creek, key creek biota, or any downstream users of these creeks.
Furthermore, discharge to the creek would help re-establish pre-development flows, since at
present a substantial proportion of leachate and groundwater (entrained within the leachate)
flows is diverted to sewer. Hence, increasing the environmental flows, particularly given
climate predictions of declining rainfall, would be a beneficial outcome of the proposed
treatment system. Restoration of environmental flows (together with the proposed creek
enhancement) would have positive impacts on the Burnie burrowing crayfish, which is the key
species of concern (the only threatened species) in this project.
Geotechnical Risk Evaluation
This quantitative geotechnical risk assessment undertaken by Tasman Geotechnics
(APPENDIX 6) and the associated hydrological stormwater runoff assessment undertaken by
Tasmanian Consulting Services (appendix to APPENDIX 6), concluded that the proposed
wetland system posed a low to very low risk.
The key findings and implications are:
Stage 1 landfill is set into the valley tract and as such the landfill is largely contained
within the natural topography.
The landfill is relatively shallow depth (10 m) and has been closed for over 10 years
(ceased receiving waste in 2004 and was capped in 2005), and has already completed
primary consolidation. The landfill cap is currently experiencing less than 2 mm/yr
settlement. The estimated weight of the proposed wetland system is ~17 kPa, which is
considered to be a minor load. Consolidation settlement of the landfill cap under the
wetland mass load is predicted to be 230 mm. Based on review of typical parameters,
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 136
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
consolidation settlement is likely to be completed within 2 years of placing a load. Long
term settlement as a result of biodegradation of the landfill is estimated at 2 mm/year.
This is within the adaptive design capability of the system. Note, the stockpile of clay
materials placed on top of the landfill provides empirical data for calculating the likely
settlement of the wetlands on top of the landfill cap. The stockpile height varied from
about 3.5 m to 6 m, and by 2013 achieved a footprint of about 6000 m2 (190 m long by
between 20 m and 60 m wide) and had an estimated pressure of 52 kPa. This
compares with 24 kPa for the wetland bunds and 17 kPa for the wetland cells. Survey
data for the landfill cap was available for two dates: 04/05/2006 (before soil
stockpiling) and 05/04/2013 (before Stage 2 capping commenced, when the stockpile
was at maximum height), almost a 7 year time interval. This empirical data was used to
derive the predictive settlement model for the wetland. These have been accounted for
in the wetland freeboard design.
The surface flow wetlands will be constructed with an LLDPE liner on top of the Stage
1 landfill cap, with only shallow operating water depths, such that the bund heights will
be limited to 1.2 to 1.5 m to accommodate liner, substrate, water and freeboard for
extreme storm events. A slightly higher bund (0.1 m) will be incorporated to
accommodate long‐term settlement. The overall bund height will be less than 2 m to
avoid the potential for excessive settlement.
Leachate levels rise and fall within the landfill in response to rainfall and imply that
there is upward flow into the landfill. The flows are likely to originate at the springs, but
could also be in other areas where there has been excavations to borrow clay to create
floor of the landfill. The upward flow prevents leachate from leaking into the natural
aquifers. The landfill does have a standing leachate level within the cell, however there
is no evidence that this has an impact on the cell or containment bund.
The wetland will have minor leakage risk since it will be a LLDPE liner over existing
natural clay topsoil capping of very low permeability, and in part over a GCL liner with
very low permeability.
The proposed wetland may result in tensile strains in the capping clay (and in the
wetland structure itself) that are at the lower limit of the failure limits. This means that
the probability of either the wetland or the landfill cap being compromised is very low.
Based on Factor of Safety analysis, the current landfill containment bund has a very
low probability of failure, including when modelled with saturated waste. The presence
of the wetland (modelled as a 17kPa pressure) has a small impact on the calculated
FOS.
Placing the wetlands at least 10m from the crest will not adversely impact on the
stability of the containment bund wall.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 137
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
The preferred wetlands location on the top half of the eastern cell was assessed as
being at minimal risk of inundation from overland flows from catchments to the east of
the site or from flooding of the existing site stormwater infrastructure during extreme
1000 Year ARI events (Tasmanian Consulting Services report contained in APPENDIX
6). Quantitative modelling in this same report concluded that inundation of the
proposed wetlands located on the top third of the eastern landfill cell was not
considered to be a realistic possibility, even for extreme rainfall events.
Therefore, construction of a wetland on top of the landfill cap at least 10 m from the landfill
crest has a Low to Very Low risk profile for the hazards associated with settlement of the
landfill cap and the wetland, possible failure of the landfill containment bund, and extreme
rainfall events. Overtopping of the wetland presents a moderate risk profile if the infrastructure
at the wetland is not adequately managed.
6.2.4 Proposed Management Measures
This step in the risk assessment is about establishing the additional risk treatment measures
needed to be implemented such that those inherent risks which are above acceptable levels,
can be reduced to acceptable levels (i.e. Low).
Theoretically, risk can be treated in two ways—by reducing the likelihood or reducing
consequence. Operationally, risk treatment options can also be categorised into changes
and/or additions to the infrastructure (in the case of this proposal this would include
changes/additions to the treatment system or other infrastructure elements associated with the
treatment system) or processes.
The following measures are proposed to ensure protection of the environment, protection of
human health, compliance with the relevant legislation, and to maximise positive project
benefits.
POTENTIAL WETLAND SYSTEM FAILURE OR IMPEDED PERFORMANCE
Design
Separation of the current stormwater discharge infrastructure and the leachate
collection and treatment system to avoid untreated leachate discharge via the
stormwater system.
Conservative sizing of the treatment system to treat the 90 percentile flows and, if
required, to enable leachate recirculation and further treatment prior to discharge.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 138
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
In built storage capacity to accept and dampen variable flow volumes, including peak
storm event flows (the pump and storage capacity will accommodate >80-year event).
Multiple component system design with a sequential treatment train to ensure a
continuously high standard of treatment.
Discharge of average flow treated leachate via an on site infiltration Wet Forest to
reduce direct discharge to the creek and enable further attenuation of residual
nutrients through the soil profile.
Use of an open swale as the ultimate discharge pathway to the existing unnamed
tributary Cooee Creek for flows in excess of infiltration capacity.
Connection to sewer maintained in case of non-compliance, as final contingency.
Collection of extreme storm event leachate seepages that may occur along the
northern embankment within a phytoremediation swale.
Construction
Placement of the wetland system limited to at least 10m from the landfill crest.
Height of bunds limited to 2m.
Use of a LLDPE liner to reduce wetland seepage risks.
Construction of an emergency storage tank, recirculation system for non-compliant
water, and a connection to the TasWater sewer, as a final contingency measures.
The wetland designer will be retained during construction / contract management and
commissioning phases to ensure that all system components (e.g. liner, hydraulics,
planting, etc) and safeguard management elements are constructed as per design.
Commissioning and Operation
Performance monitoring will be conducted through the system to enable adaptive
response and to trigger emergency recirculation or disposal to sewer.
An appropriate annual maintenance budget will be included for the life of the wetland
to ensure that all required maintenance activities are done appropriately and with the
required frequency.
Operation and Maintenance Plans will be developed and will detail the required
maintenance activities and frequencies.
Appropriate equipment checks and maintenance regimes will be implemented.
Existing risk management plans will be updated to include responses to incidences
potentially connected with the treatment system. This will include incidence response
for any on site ponding and mosquito management.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 139
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Appropriate training of staff responsible for system maintenance will be undertaken,
including preparation of user-friendly management and maintenance plans.
MANAGEMENT MEASURES TO MINIMISE/ MANAGE RISKS ASSOCIATED WITH
LANDFILL SETTLEMENT
Design
Appropriate freeboard capacity will be incorporated to accommodate the direct rainfall
volumes generated in a 1000 year rainfall event (182 mm) and to accommoda te
leachate volumes generated in an 80-year event.
Bund heights will be limited to 2m to limit settlement effects.
Construction
Heavy machinery use will be avoided along the top of the northern containment bund
Accurate surveys of base levels will be undertaken, before wetland placement.
A minimum of four (4) survey markers will be installed and fortnightly monitoring of
settlement levels undertaken across the landfill pre-during and post construction for
several months.
Operation
Annual monitoring of settlement levels across the landfill will be undertaken.
Annual assessment of the integrity of wetland cells and associated infrastructure
located on top of the landfill cap (bunds, liners, pipework, weirs etc), will be
undertaken.
Quarterly checks of wetland perimeter bunds to ensure the minimum freeboard depth
is maintained and that any localised areas that may have settled below this minimum
(200 mm) level are repaired promptly.
Any repair work required due to settlement effects (Section 6.2.3) will be undertaken,
to maintain system integrity and performance.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 140
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
MANAGEMENT MEASURES TO MINIMISE/ MANAGE RISKS ASSOCIATED WITH
PROTECTION/ENHANCEMENT OF THE CREEK ECOSYSTEM
Design
The design will accommodate flow controls (rocks, swales) to dampen velocity,
encourage sediment drop out and reduce sediment transport to the creek.
Bioengineering measures (vegetated brushmatressing, rock stabilisation) will be
incorporated to stabilise embankments and facilitate re-establishment of native
species.
A meandering swale/cascade at the discharge point will be incorporated to slow flow
velocity prior to creek discharge (for stormwater average flows and peak treated
flows).
Construction
No clearing of native vegetation will be undertaken.
Sediment controls (traps, sediment curtains) will be installed during creek
enhancement works, and sediment reused within the landfill area.
Locally native species will be used in the treatment system to avoid invasive species
entering the creek and to enhance biodiversity.
Key species will be incorporated within the wetlands to enhance the habitat value and
water quality of the creek (e.g. shade species, nesting trees, protective understorey for
avoiding predators etc).
Enhancement of the northern boundary of the site will be undertaken by replacing
grassland and weeds with dense native vegetation (Wet Forest) to reduce the risk of
weeds to the creek, provide shading, assist in phytoremediation and
evapotranspiration.
Restoration works will be undertaken in the immediate unnamed creek discharge area
to reduce weeds, enhance riparian vegetation, improve habitat and reduce erosion.
Operation
An ongoing weed management program within the wetland system and creek
discharge areas will be implemented.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 141
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
MANAGEMENT MEASURES TO MINIMISE VISUAL IMPACTS AND ENHANCE VISUAL
AMENITY AND COMMUNITY USE
No native vegetation clearing will be undertaken.
Each component of the wetland system will be appropriately landscaped in order to
visually integrate with each other and within the site.
Locally indigenous, shrubby vegetation and trees (Wet Forest) will be planted along
the northern boundary of the site within the infiltration area and swale.
BCC will provide controlled site access and interpretative walks/signage to enable
community use of the proposed system for education and research.
6.3 OTHER POTENTIAL IMPACTS AND MANAGEMENT RESPONSES
6.3.1 Air Quality
Dominant winds at the site are south westerly (most dominant) and west/north westerly. The
nearest sensitive receptors to the site are the immediate neighbouring farm properties and a
residential subdivision on Three Mile Lane Road, approximately 200m north of the site. The
surrounding site is rural.
The proposal will not generate point source odour emissions, with the potential for air quality
impacts limited to the wetland anoxia and dust during construction works. The leachate itself
has no odour since it is dominated by groundwater (>80-90%), hence the concentrations of
pollutants are very low and odours are not detectable. There is a potential for odours within
the wetland if the system is allowed to become anoxic, which would cause the build up and
release of H2S and/or methane gases. This is unlikely since the system is designed to be
shallow and aerobic, and has an operational regime that incorporates routine drawdown of
wetland cells to maintain oxygenation of the wetland sediments and to ensure aerobic
degradation of organics. These risks will be managed by a detailed operational plan and via
the existing day-to-day personnel on-site.
The subsurface component is anaerobic, but since this system is subsurface and receives
highly treated water through previous treatment steps, odours are unlikely. There is a
potential for localised odours if/when raw leachate seepages occur along the northern
embankment, however these are very small in volume and will be intercepted and treated
subsurface.
Finally, the system does not incorporate chemical dosing, and pumps are operated by existing
site power or solar, with diesel only used as backup in case of power failure. The previous use
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 142
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
of the site for landfilling and the current use for waste sorting creates more odours than the
proposed project.
The following is the history of complaints regarding odours for the existing site ( documented in
the annual reporting since 2004).
No complaints have been received since cessation of sludge disposal to landfill in mid -2007.
Dust emissions may arise from loading, unloading and transport, and will be managed via
appropriate dust management practices. These will be outlined in the Contractors Construction
Management Plan, but will likely include the provision of watering trucks during construction
works.
Air quality risks and odour issues are considered to be a minor issue for this proposal.
6.3.2 Noise Emissions
There will be no noise emissions during operation above existing operations. Noise emissions
are limited to the raw leachate submersible pump. Noise during construction will be managed
in accordance with the existing EPN requirements and Mooreville Rd Management Plan, and
in accordance with an approved Construction Plan to be provided by the appointed Contractor.
Noise will be managed by restricting construction activities to daylight hours in accordance
with the Hours of Use specified in the Environmental Management and Pollution Control
(Miscellaneous Noise) Regulations 2004 - SCHEDULE 7 - Hours of Use:
Monday to Friday 7.30am to 6pm inclusive.
Saturday 8am to 6pm inclusive.
Sundays and Public Holidays 10am to 6pm inclusive.
06-07 Odour complaints from employees and public relating to disposal of new
Burnie Waste water Treatment Plant sludge. This issue was managed using odour suppression sprays and operational changes
07-08 An odour complaint relating to disposal of the new Burnie Waste Water Treatment Plant sludge. A Tip Shop Contractor employee submitted a
workers compensation claim to Workplace Standards Tasmania relating to sludge disposal. Disposal of sludge to landfill ceased on 30 June 2007.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 143
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.3.3 Waste Management
Potential Impacts
Minimal waste will be generated as a result of this proposal, and is limited to the generation of
sediment sludge within leachate sediment chambers and the wetland pre -filter.
The leachate contains very low levels of TSS and organics, and the system does not
incorporate any chemical dosing to aid precipitation/coagulation. Hence, it is expected to
generate very low levels of sediment/sludge (calculated at < 1 tonne per annum). The pre-filter
is designed to promote the precipitation of low level metals within this zone (with carbonates)
and this will form the main management zone, in addition to the sediment chamber within the
leachate manhole. The sediment is likely to contain high concentrations of metals and will
need to be managed as a Controlled Waste as defined by and in accordance with the EMPC
Act.
Management Responses
Accumulated sediment will be removed periodically within the deep zone of the pre -filter and
from the manhole sediment chambers using a vacuum (sucker) truck with material disposed to
an active landfill facility. Provision for mechanical access will be included in the detailed
design. Sediment removal within the sediment chambers will be undertaken annually and from
the pre-filter as required.
6.3.4 Dangerous Goods and Environmentally Hazardous Materials
The construction of the treatment system will involve the use of some combustible materials,
such as fuels for construction equipment. These materials will be used, stored and transported
in accordance with the Dangerous Substances (Safe Handling) Act 2005 and Dangerous
Substances (Safe Handling) Regulations 2009. No dangerous goods or hazardous materials
are required for wetland operation. A diesel back up generator will be installed at the raw
leachate manhole chamber (MH1) to ensure continuous pump operation in times of power
failure, however no diesel will be stored on site. The generator will be checked and refuelled
as part of weekly scheduled maintenance activities.
Contractors will be required to address the management of dangerous substances within a
Construction Management Plan.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 144
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.3.5 Biodiversity and Natural Values
Potential Impacts
Potential risks to threatened species in the receiving creek environment were identified during
the study undertaken by NEST in 2014. Risk factors that were noted during the survey
included: soil erosion, stock access to streams, farm/fertiliser run-off, the presence of invasive
weeds, livestock access, feral cats, rubbish, and in-stream sedimentation. Most of these risks
were associated with existing landuses (landfill, agricultural, urban etc) and associated
activities.
The natural value assessment study did not consider discharge of the treated leachate as
having a negative impact in terms of water quality; in the contrary they indicated this project
would have a positive impact. Furthermore, construction of the treatment system was also
considered to have minimal impacts assuming appropriate management plans are put in
place.
Restoration of environmental flows (together with the proposed creek enhancement) would
have positive impacts on the Burnie burrowing crayfish (Engaeus yabbimunna), which is the
key species of concern (the only threatened species) in this project. The greatest threats to
this species are water pollution, water diversion and habitat removal (Burrowing Crayfish
Group Recovery Plan 2001-2005). A major cause of decline of this species locally is the
sedimentation of creeks due to loss of riparian vegetation, and the consequent loss of in-
stream pools and muddy zones that are essential habitat characteristics (NEST 2014). The
core objectives identified for recovery of these species are as follows:
Maintain or improve water availability (especially in seepages).
Maintain or improve water quality (against pollutants, pesticides).
Maintain or improve habitat (native riparian vegetation and soil integrity).
Exclude disruptive processes from sensitive areas (seepages/marshes/streamside
areas).
Increase the reservation/protection of these species on Crown and private land .
Increase public awareness and appreciation of, and involvement in, threatened
species protection.
The reduction of siltation characteristics and enhancement of seepages is a key priority
identified for the Burnie burrowing crayfish, since the drying of sites is a major threat. The
NEST report notes that sedimentation from other neighbouring landuses and activities is a key
existing issue which has already impacted on some of the threatened species within 4 kms of
the site (Burnie burrowing crayfish, Giant freshwater lobster, Green and gold frog).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 145
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Whilst no specific environmental water requirements (EWRs) have been set for this species,
recommendations for maintenance of habitats for these species is provided in related reports,
including the Emu River Environmental Water Requirements report, which indicated for that
river a minimum flow of 0.8 m3/sec (DPIPWE 2001).
No threatened ecological communities (TECs) that are likely to be impacted by the proposed
project as no TECs were identified within 500 m of the project site. The nearest TEC is a
wetland 2kms downstream. This wetland is hydrologically connected to the unnamed
tributary, is degraded (due to siltation and weed invasion) and is likely to either be unaffected
by the proposal or will slightly benefit from the enhanced environmental flows. Furthermore,
the project will not result in the clearing or indirect disturbance of native vegetation within or
outside of the project site, and in contrast will result in an additional 2 ha of native vegetation
and wetland habitat areas.
Swift Parrots require old eucalypts of more than one hundred years of age to provide the tree
hollows they require for breeding. The proposed project does not include any vegetation
clearing or tree removal. Quite the contrary, construction of the treatment wetland system
within the BCC landfill site and additional creek restoration efforts will result in creation of
habitats and food provision areas for avifauna.
Consequently, the project is not expected to negatively affect the visitation rates and
behaviours of migratory species in the region.
Management Responses
The proposed project will involve direct improvement works to the creek via removal of weeds,
revegetation and sediment controls but will also result in a higher volume of water discharging
to the creek bed, predominantly via subsurface discharges from the Infiltration Forest. These
flows (which will supplement current seepages by approximately 4 m3/sec on an annual
average basis), will help to prevent stagnation of the creek , drying of seepage zones and
subsequent loss of riparian vegetation, and will support the creation and maintenance of
muddy substrates and seasonal pools.
Sediment controls will be implemented for creek enhancement works and construction
activities near to the creek, including stormwater/leachate collection and conveyanc e
refurbishment works, construction of the infiltration wetland, and creek discharge works. Silt
curtains and sediment ponds are likely to be required to minimise sediment run-off to the creek
and transport of sediments downstream.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 146
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.3.6 Pests, Weeds and Diseases
Potential Impacts
Potential impacts due to pests, weeds and diseases is considered low since the proposed
treatment system will only use locally native species and weed control works will be
undertaken as part of construction works and on an ongoing basis to minimise impacts to
wetland vegetation. During construction works, the site will be managed so as to limit the
introduction and spread of introduced plant species, weeds, pests and diseases (including
Dieback Phytophthora cinnamomi), using all practical and operational means.
Management Responses
Management practices to prevent the spread of pests, weeds and diseases into uninfected
areas will include strict hygiene measures such as:
Dieback free construction materials will be used.
All imported soils will be certified and purchased from accredited suppliers only.
Equipment, machinery and vehicle inspection, washdown and disinfection procedures
will be implemented and enforced prior to site entry and departure
Weed control will be undertaken prior to clear and grub works.
Ongoing weed control and disease management will be undertaken in accordance with
an Operational and Maintenance Plan to be developed.
6.3.7 Dust
Potential Impacts
Dust due to construction activities will be managed during construction works to avoid impacts
to workers, neighbouring properties and the natural environment.
Management Responses
Dust control will be implemented during construction works in order to minimise export off site.
Water tankers will be utilised to prevent dust emissions if soil moisture is low and wind velocity
is high.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 147
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.3.8 Sediment
Potential Impacts
Sediment can cause impacts to the creek by reducing open water habitat and through
entrained pollutants. Sediment has caused issues within the creek system in the past , and will
need to be carefully managed during wetland construction works and creek enhancement
works.
Management Responses
Sediment control structures will be installed prior to commencement of work in order to negate
or minimise sediment export off site. Sediment traps and temporary lined stormwater bunds to
400mm height will be constructed to manage surface water flows during the construction
period. Silt curtains will be installed within the creek during construction of the infiltration wet
forest, stormwater swale, manhole refurbishment works and creek enhancement works.
6.3.9 Marine and Coastal
The site is not within a marine or coastal area.
6.3.10 Greenhouse Gases and Ozone Depleting Substances
Potential Impacts
The proposed leachate treatment system is not expected to significantly increase the level of
GHG emissions currently being emitted from the landfill site. This is predominantly due to the
following:
The proposed system is predominantly a passive wetland system that relies on
naturally occurring physico/chemical and biological processes to achieve pollutant
removal. As such, they have a minimal reliance on mechanical components and have
very low energy demands, and consequently operation of such systems results i n
generation of low GHG emissions.
Emissions will mostly result from construction machinery and any associated transport
to and from the site, and from pumping requirements to the wetland system, which are
equivalent to the current scenario (leachate will be pumped to the wetland instead of to
the sewer network). Pumping (electrical) requirements are relatively small and
calculated to generate approximately 10-17 t/year of CO2 emissions per year.
Given aerobic (oxidised) conditions are dominant in the proposed system, methane is
not anticipated to be produced (methane is typically produced in anoxic soils and
sediments).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 148
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Vegetation within the proposed system will serve as a carbon sink thereby further
reducing emissions and acting as a positive GHG offset within the site.
Construction and operation of the proposed leachate treatment system will not involve
the generation or use of any ozone depleting substances.
Management Responses
The recirculation pump required to enable return of non-compliant leachate from the
polishing wetland back through the treatment system (contingency measure) will be
solar powered with battery storage.
A new high efficiency pump will be installed as the duty pump to minimise electrical
use and emissions (compliant with best practice standards for submersible pumps).
All equipment, machinery and vehicles used during the system construction and
operation will be well maintained in order to minimise the generation of greenhouse
gases.
Reuse of material present on site will be maximised to reduce GHG emission from
transport of off-site material.
6.3.11 Heritage
Potential Impacts
It is highly unlikely that Aboriginal artefacts will be uncovered during the treatment system
construction, since the majority of works will be on top of the landfill cap and because
excavation is limited to topsoil stripping and levelling (top 300mm only) . Furthermore, there
will be no impact on heritage buildings and/or associated historical structures arising from the
systems construction and operation.
Hence, there are no site specific heritage constraints or requirements for the project .
Management Responses
Given lack of impacts, no specific mitigation measures are proposed.
In the unlikely event that any artefacts or sites are discovered during system construction
/operation, all activities will cease immediately until a proper assessment is undertaken. The
appropriate personnel at the Aboriginal Heritage Tasmania (division of the Department of
Primary Industries, Parks, Water and Environment) will be contacted to assess the situation
and agree upon the appropriate management measures.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 149
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.3.12 Land Use & Development
The proposal does not alter the current constraints for future land use and development in
place at present, since the site is a designated landfill (Resource Recovery) facility.
6.3.13 Visual Impacts
This project will improve the visual amenity of the site and surrounding areas through the
reinstatement of significant areas of natural vegetation (~2 ha) and creek improvement works.
Visual impressions of the wetland have been provided in earlier sections (Figure 10, Figure
11, Figure 12 and Figure 13.
6.3.14 Socio-Economic Issues
The estimated capital spend on this project is ~$2 mill, with annual opex of ~$80k. Most of this
will be expended in Tasmania, except where local materials cannot be sourced (refer Table 4).
Local contractors will be used for construction works, and training opportunities provided to
BCC staff and NRM groups during the construction and commissioning stages.
The broader economic impact of this project has been discussed in previous sections and in
APPENDIX 5.
As previously discussed, this project is funded by a federal grant as part of the Stormwater
Infrastructure Development Program, with funds contingent on substantial completion of works
by June 2106.
6.3.15 Health & Safety Issues
An OH&S plan will be required to be provided by the Contractor as part of the tender
documentation, and will be compliant with the WorkHealth and Safety Act 2012 and the Work
Health and Safety Regulations 2012 and in accordance with existing BCC policies and
standards that apply to the site. This will describe the health and safety management
systems to be used during construction and operational phases.
6.3.16 Fire Risk
Potential Impacts
As discussed in Section 5.2.10, the risk of fire at the landfill site is relatively low due to the
safety procedures in place and restricted access. Construction of the proposed leachate
treatment system is not expected to significantly increase this existing low risk. The only
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 150
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
additional wetland-associated factors that might contribute to fire occurrence and/or impact
extent are:
Electrical connections to pumps required for system operation.
Vegetation cover (i.e. presence of plants in surface and subsurface system
components and the phytoremediation swale) which might serve as an additional fuel
load increasing the spread and fire intensity – note this is not considered to pose a
major threat given plants will be within the wetland system (partially submerged in free
standing water or within damp ground). Most of the wetland plants are resistant to fire
hence if a fire does occur this will not impair treatment function (and is often used as a
management method to enhance wetland performance/health) .
Management Responses
An existing Fire Management (Action) Plan will be updated prior to the treatment
system commissioning and operation, to include any additional risks arising from the
treatment system and procedures required for their management. All employees and
contractors will be briefed during inductions on wetland-specific fire risks and
appropriate management responses.
All pumps servicing the treatment system will have lightening / short circuiting/
electrical protection installed.
Access to the system will be controlled (no unauthorised access allowed).
The construction of the treatment system will involve the use of some combustible
materials, such as fuels for construction equipment. These materials will be used,
stored and transported in accordance with the Dangerous Substances (Safe Handling)
Act 2005 and Dangerous Substances (Safe Handling) Regulations 2009.
All electrical infrastructures associated with the treatment system operations will be
constructed in compliance with the Tasmanian Electricity Code to minimise risk of
electrical faults that may act as ignition sources.
All site access roads and tracks will be maintained to acceptable fire fighting standard.
6.3.17 Infrastructure and Off-Site Ancillary Facilities
The proposed system will not have any significant negative impacts on the existing on site
and/or off-site infrastructure (e.g. roads, rail, etc).
No roads upgrade and no significant off-site infrastructure changes/upgrades will be required
to service the proposed treatment system.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 151
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
The proposed project will utilise the existing infrastructure on site, including manhole
chambers, existing pump, existing sewer network and existing internal network of roads and
access points. The main Stage 1 leachate pumping station will be refurbished to separate
leachate from site stormwater flows and will incorporate a sediment trap. The existing
connection to the TasWater sewer network will be modified to enable contingency discharge
only. Specific access paths point will be constructed to enable treatment system monitoring
and maintenance.
The construction phase will require the initial delivery of materials and construction equipment,
however this process will be managed and is not expected to pose any adverse infrastructure
impacts.
6.3.18 Environmental Management Systems
Operation of the proposed leachate treatment system will be undertaken in accordance with
the operational requirements outlined in a new EPN for the site, which will accord generally
with the existing EPN and management plan for the site (Mooreville Rd Landfill Environmental
Operations Manual, Meinhardt Infrastructure and Environment Pty Ltd, April 2005).
During the construction phase, all contractors will be properly inducted to ensure all
appropriate environmental management expectations are communicated prior to commencing
work. Contractors will need to address environmental management within an approved
Construction Management Plan, prior to commencement of works.
Appropriate training of all on site personnel will be undertaken focusing on procedures and
measures for minimising any environmental impacts possibly associated with the system’s
operation. User friendly user-friendly management and maintenance plans, and safety plans
will be prepared to ensure continuous awareness and education of all relevant employees
regarding the system operation and the responses to operational environmental concerns.
6.3.19 Cumulative and Interactive Impacts
The proposed leachate treatment system will be located on the Stage 1 landfill cap, and will
provide a positive environmental outcome when compared with the existing site context.
Construction of the system is also not expected to pose any significant negative impacts given
that the additional traffic on local and regional roads associated with the required construction
activities and the material will only be minimal. There will be no negative visual impacts, and in
contrast the project is expected to increase the visual, biodiversity and land use value of the
site itself and neighbouring properties. Hence, the proposed system is not foreseen to pose
any significant cumulative or interactive negative environmental and human health impacts.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 152
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
6.3.20 Traffic Impacts
It is expected that there will be only minor increases in traffic on local roads associated with
the construction of the proposed system (e.g. for delivery of import material and o ther
construction-associated vehicular traffic).
This temporary additional traffic is not expected to create any operational and/or safety issues
either to on-site workers or local residents.
7.0 MONITORING & REVIEW
7.1 MONITORING PROGRAM
The following objectives have been identified for the water quality and quantity monitoring
program:
1. Influent and effluent quality (physico-chemical parameters)
o To ensure that influent water quality is within the system’s treatment capacity
and that the effluent meets the required quality criteria (which will be regulated
via a new EPN/Licence).
2. Influent and effluent quantity (flows) and groundwater levels in infiltration area
o To ensure that water flows are within the wetland operational capacity and that
discharges to the infiltration forest do not negatively impact groundwater levels
and flows.
3. Vegetation and sediment quality (system health check)
o To ensure that contaminant accumulation and cycling patterns within the
wetland are understood and potentially quantified.
4. Database maintenance (quality assurance and reporting)
o To ensure maintenance of the database of all data collected is sufficient to
satisfy the abovementioned objectives, provide ease of reporting and enable
performance assessment and design/operation of future systems.
Apart from the ongoing monitoring schedule which covers influent and effluent quantity and
quality, during the first year of operation, additional monitoring locations within the treatment
train and a higher sampling and analysis frequency will be undertaken to allow fine tuning of
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 153
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
operating parameters (e.g. flow and operating depths) and to optimise the performance of the
wetland system. This monitoring is important as it will ensure that the different wetland
components, such as pre-treatment, surface and subsurface flow wetlands and infiltration
forest function within their operational capacities and that any potential issues are detected at
an early stage.
The wetland monitoring program will be complemented by ongoing visual checks of vegetation
health, inspection of hydraulic components such as pipes, pits and headwalls and preventative
maintenance of mechanical components such as pumps and valves as described in an
Operational and Maintenance Plan to be developed for the site.
7.1.1 Sample Collection, Handling and Analysis
Water collection will be undertaken in a manner consistent with the relevant ‘AS/NZS 5667
Water Quality - Sampling’ Series and water samples submitted to a laboratory with current
NATA accreditation for the analysis specified. All samples will be analysed in accordance with
the current “Standard Methods for Examination of Water and Wastewater – APHA –AWWA-
WEF” or equivalent method recognised by the EPA.
7.1.2 Sampling Locations
The proposed sampling locations are shown in Figure 41.
The current monitoring schedule for groundwater locations upgradient of the proposed wetland
system (i.e. locations G2 and G3) will remain unchanged as they will not be impacted by the
proposal. Proposed sampling sites relevant to the treatment system include ongoing
monitoring points, where flows and water quality will be recorded for the life of the treatment
wetland, and additional water quality monitoring points within the treatment train, where grab
samples will be collected during the first year of operation to gauge performance and fine tune
operation.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 154
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Figure 41. Proposed sampling locations.
Briefly, the monitoring sites are:
1. Ongoing monitoring locations (flow meter, grab samples and continuous in -situ
monitoring)
a. INF - Influent leachate, sampled at manhole 1 (MH1). This is equivalent to the
existing location (L1). A flow meter will be present at the rising main.
b. EFF 1 - Treated leachate, sampled at the outlet of the Polishing Wetland. A
flow meter and in situ pH, electrical conductivity and ammonia (ion selective)
probe will be present at this location.
c. EFF2 - Treated leachate discharge point sampled at the outlet of the Infiltration
Forest (when discharging to unnamed tributary). A level sensor and flow meter
will be present at this location.
2. GW1 - Existing groundwater monitoring location at the Infiltration Forest to be
maintained - sampling frequency will be intensified to monitor indirect discharges to the
creek.
INF
EFF 1
EFF 2 GW 1
PRE
SSF
SSF
SSFSF
SF
SF
SF
SF
SF
SF
SF
SF
SF
PF
PW
SF
SSF
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 155
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
3. Additional year 1 monitoring locations (grab samples)
a. PRE - Pre-Treatment effluent, sampled at the outlet of the Pre-Treatment cell
to gauge metal removal (Fe/Mn) performance
b. SF - Surface Flow Wetland effluent, sampled at the manhole downstream of
SF6 to gauge the performance of the surface f low wetland cells
c. SSF - Sub-Surface Flow Wetland effluent, sampled at the outlet of the
subsurface flow wetlands.
7.1.3 Sampling Frequency and Parameters
The proposed frequency of monitoring and parameters to be analysed for the ongoing
monitoring program have been based on the existing EPN schedule and the proposed Water
Quality Protection levels as shown in Table 23.
In general, the same physico-chemical parameters and frequency prescribed in the current
EPN for the site have been maintained as they are considered applicable for both influent and
effluent leachate and groundwater at the infiltration area. Dissolved oxygen (DO) has been
added to the list of parameters as it provides valuable information to process control. In
addition to routine analytical parameters and grab samples continuous online flow monitoring
with flow meters at INF, EFF 1 and EFF 2 has also been included. Continuous online
(telemetry) monitoring of pH, electrical conductivity (EC) and ammonia is also proposed at
EFF 1 (Table 33) so that the operator can be notified when these parameters are outside of
their target range and take remedial action (e.g. activate recycle mechanism). During the first
year of operation, the monitoring of physical parameters and nutrients is increased to monthly
at all locations and the monitoring of metals increased to every two months at INF, PRE, EFF
1 and GW1 (Table 33). Frequency of other parameters such as cations, anions, pesticides,
hydrocarbons and E. coli in the first year will remain as per the ongoing (year 2 onwards)
schedule (Table 33).
Groundwater parameters at G1 will be reviewed on an annual basis and compared against
historical quality and water level data, rainfall data and flow rates through the wetlands.
Should no appreciable change in levels or quality occur in the first year, monitoring frequency
of physical parameters, nutrients and metals could be reduced to quarterly as per current EPN
prescription.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 156
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
7.2 MANAGEMENT TRIGGERS
Certain sample points will be installed and monitored for the purpose of preventing non -
compliant events to occur, and to trigger the appropriate management responses. This will be
detailed in a separate monitoring and maintenance manual so is only indicatively outlined
here. Preventative monitoring includes general maintenance of the wetland system, plant
health checks, geotechnical checks etc (see Sections below). In addition, specific monitoring
and management response triggers are proposed as follows:
TRIGGER 1: Trigger to activate recirculation through the treatment system.
The first trigger will be activated via an automated flow controller set to trigger recirculation
either:
1. When the infiltration wetland is at capacity and no attenuation of additional flows is
possible (i.e. there is active discharge to the creek) – measured by continuous flow
meter, AND EITHER:
a) When flows into the wetland exceed the maximum treatable design flows (1500
m3/day) – triggered by flow levels in the pump and pit infrastructure, OR
b) When one or more on-line parameters (ammonia, pH, conductivity) exceed a
specified maximum trigger value. Note, these values will be refined during the
commissioning phase once the system performance is proofed. Initially, these
will be equivalent to the compliance monitoring targets (Water Quality
Protection Levels for creek discharge) as shown in Table 23.
TRIGGER 2: Trigger to activate discharge to sewer
Flows to the TasWater sewer system are only envisaged when raw leachate cannot be
delivered to the wetland system due to pump failure (power outages plus generator failure),
which will be unlikely and infrequent (refer Section ). This will be triggered by rising water
levels in the manhole chamber (MH1) which will activate a gravity flow to the emergency
storage tank. Flows will only discharge to sewer if the capacity in the manhole chamber is not
reinstated within 24 hours (low flow events) or 6 hours (high flow events). This is activated
also by water levels rising in the tank and overflowing by gravity to the sewer network.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 157
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 33. Proposed monitoring schedule for the treatment wetland
GROUNDWATER
YEAR 1 YEAR 2 ONWARDS YEAR 1 ONWARDS *
ANALYTICAL PARAMETERS UNIT
MONITORING FREQUENCY AT
PROPOSED SAMPLING LOCATIONS
INF (L1), PRE, SF, SSF, EFF1 & EFF 2
MONITORING FREQUENCY AT
PROPOSED SAMPLING LOCATIONS
INF (L1), EFF1 & EFF 2
MONITORING FREQUENCY AT
PROPOSED SAMPLING
LOCATION G1 (INFILTRATION
FOREST
PHYSICAL
Water Level m AHD - - monthly
Flow m³
INF - continuous online monitoring (flow meter at
MH1)
EFF 1 - continuous online monitoring (flow meter
at SF7 polishing wetland outlet - performance
monitoring)
EFF 2 - online monitoring (flow sensor and meter
at creek discharge point)
INF - continuous online monitoring (flow meter at
MH1)
EFF 1 - continuous online monitoring (flow meter
at SF7 polishing wetland outlet - performance
monitoring)
EFF 2 - online monitoring (flow sensor and meter
at creek discharge point)
-
Temperature °C monthly quarterly monthly
Alkalinity Total mg CaCO3/L monthly quarterly monthly
Conductivity µS/cmEFF 1 - continuous online monitoring
Other locations - monthly
EFF 1 - continuous online monitoring
Other locations - quarterly monthly
pH EFF 1 - continuous online monitoring
Other locations - monthly
EFF 1 - continuous online monitoring
Other locations - quarterlymonthly
Dissolved Oxygen (DO) mg/L monthly quarterly monthly
Oxidation Reduction Potential Eh mV Eh mV monthly quarterly monthly
Total Dissolved Solids (TDS) mg/L monthly quarterly monthly
Total Suspended Solids (TSS) mg/L monthly quarterly monthly
SURFACE WATER AND LEACHATE
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 158
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
GROUNDWATER
YEAR 1 YEAR 2 ONWARDS YEAR 1 ONWARDS *
ANALYTICAL PARAMETERS UNIT
MONITORING FREQUENCY AT
PROPOSED SAMPLING LOCATIONS
INF (L1), PRE, SF, SSF, EFF1 & EFF 2
MONITORING FREQUENCY AT
PROPOSED SAMPLING LOCATIONS
INF (L1), EFF1 & EFF 2
MONITORING FREQUENCY AT
PROPOSED SAMPLING
LOCATION G1 (INFILTRATION
FOREST
CHEMICAL
Chemical oxygen demand (COD) ** mg/L quarterly quarterly quarterly
DOC mg/L mg/L quarterly quarterly quarterly
Nutrients
Ammonia mg/LEFF 1 - continuous online monitoring
Other locations - monthly
EFF 1 - continuous online monitoring
Other locations - quarterlymonthly
Nitrate mg/L monthly quarterly monthly
Nitrite mg/L monthly quarterly monthly
Total Nitrogen (TN) mg/L monthly quarterly monthly
Phosphorus Dissolved Reactive mg/L monthly quarterly monthly
Total Phosphorus (TP) mg/L monthly quarterly monthly
Major Anions
Chloride mg/L quarterly quarterly monthly
Sulphate mg/L quarterly quarterly monthly
Major Cations
Mg mg/L quarterly quarterly monthly
K mg/L quarterly quarterly monthly
Na mg/L quarterly quarterly monthly
Metals (total)
Al mg/L quarterly
As mg/L annually
Cd mg/L quarterly
Cr mg/L quarterly
Cu mg/L quarterly
Fe mg/L quarterly All monthly
Hg mg/L annually
Mn mg/L quarterly
Ni mg/L quarterly
Pb mg/L quarterly
Se mg/L annually
Zn mg/L quarterly
All every 2 months
at INF, PRE and EFF 1
SURFACE WATER AND LEACHATE
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 159
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
GROUNDWATER
YEAR 1 YEAR 2 ONWARDS YEAR 1 ONWARDS *
ANALYTICAL PARAMETERS UNIT
MONITORING FREQUENCY AT
PROPOSED SAMPLING LOCATIONS
INF (L1), PRE, SF, SSF, EFF1 & EFF 2
MONITORING FREQUENCY AT
PROPOSED SAMPLING LOCATIONS
INF (L1), EFF1 & EFF 2
MONITORING FREQUENCY AT
PROPOSED SAMPLING
LOCATION G1 (INFILTRATION
FOREST
CHEMICAL
OC/OP Pesticides
a-BHC µg/L
Aldrin µg/L
b-BHC µg/L µg/L
Chlordane µg/L µg/L
Chlorpyrifos µg/L µg/L
d-BHC µg/L µg/L
Diazinon µg/L µg/L
Dieldrin µg/L µg/L
Dimethoate µg/L µg/L
Disulfoton µg/L µg/L
Endosulfan I µg/L µg/L
Endosulfan II µg/L µg/L
Endosulfan sulphate µg/L µg/L
Endrin µg/L µg/L
Endrinaldehyde µg/L µg/L
Ethylparathion µg/L µg/L
Famphur µg/L µg/L
g-BHC µg/L µg/L
Heptachlor µg/L µg/L
Heptachlor epoxide µg/L µg/L
Hexachlorobenzene µg/L µg/L
Malathion µg/L µg/L
Methyl parathion µg/L µg/L
Phorate µg/L µg/L
pp'-DDD µg/L µg/L
pp'-DDE µg/L µg/L
pp'-DDT µg/L µg/L
Sulfotep µg/L µg/L
Thionazin µg/L µg/L
All annually at INF, EFF 1 and EFF 2 All annually at INF and EFF 1
SURFACE WATER AND LEACHATE
All monthly
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 160
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
GROUNDWATER
YEAR 1 YEAR 2 ONWARDS YEAR 1 ONWARDS *
ANALYTICAL PARAMETERS UNIT
MONITORING FREQUENCY AT
PROPOSED SAMPLING LOCATIONS
INF (L1), PRE, SF, SSF, EFF1 & EFF 2
MONITORING FREQUENCY AT
PROPOSED SAMPLING LOCATIONS
INF (L1), EFF1 & EFF 2
MONITORING FREQUENCY AT
PROPOSED SAMPLING
LOCATION G1 (INFILTRATION
FOREST
CHEMICAL
Polycyclic aromatic hydrocarbon
(PAH)
Acenaphthene µg/L µg/L
Acenaphthylene µg/L µg/L
Anthracene µg/L µg/L
Benzene µg/L µg/L
Benzo[a]anthracene µg/L µg/L
Benzo[a]pyrene µg/L µg/L
Benzo[b&k]fluoranthene µg/L µg/L
Benzo[ghi]perylene µg/L µg/L
Chrysene µg/L µg/L
Dibenzo[ah]anthracene µg/L µg/L
Fluoranthrene µg/L µg/L
Fluorene µg/L µg/L
Indeno[123-cd]pyrene µg/L µg/L
Naphthalene µg/L µg/L
Phenanthrene µg/L µg/L
Pyrene µg/L µg/L
Monocyclic aromatic hydrocarbon
(MAHs)
Ethylbenzene µg/L µg/L
om&p Xylene µg/L µg/L
Toluene µg/L µg/L
Total BTEX µg/L µg/L
Other
Cyanide total µg/L quarterly quarterly quarterly
PCB µg/L µg/L annually annually annually
MICROBIOLOGICAL
E.coli org /100 mls quarterly quarterly quarterly
Notes
** COD test method detection limit to be lowered to reflect range of values for leachate INF and EFF.
All annually at INF, EFF 1 and EFF 2 All annually at INF and EFF 1
All annually at INF, EFF 1 and EFF 2 All annually at INF and EFF 1
* Frequency and parameters to be reviewed following the results of the first year of operation with a view to decrease/increase sampling frequency and potentially delete unecessary parameters.
SURFACE WATER AND LEACHATE
All monthly
All monthly
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 161
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
7.3 GEOTECHNICAL MONITORING
7.3.1 Construction Monitoring - Pre, During and Post Construction
General settlement of the Stage 1 landfill area will be monitored via the installation of (semi)
permanent topographical survey markers within the extent of the proposed wetlands and
beyond. These markers will be checked by a certified surveyor pre (two weeks prior to works),
during works, and post construction works (for two months) on a weekly basis. The exact
number and location of markers will be established during detailed design. Nominally at least
eight markers covering the wetland extent are envisaged to cover surface flow wetland,
subsurface flow wetland, outer perimeter buns and potentially pipe and pit infrastructure .
7.3.2 Ongoing Settlement Monitoring
In order to monitor potential settlement and changes to design levels in the wetland area, a
minimum of four (4) (semi) permanent topographical survey points will be set on the wetland
bunds to the north, east, west and south of the wetlands and monitored monthly by a certified
surveyor for the initial 6 months. After six months and provided that negligible settlement has
occurred, monitoring can be reduced to annually. The northern geotechnical monitoring point
will be located on the containment bund adjacent to the site boundary. The exact coordinates
of the points will be determined during the detailed design stage.
7.3.3 Wetland Liner Leakage Monitoring
Any leakages in the wetland liner and Stage 1 landfill cap will simply be collected by the
leachate system at the base of the waste. Contiguous flow monitoring at the wetland influent
(INF) and wetland effluent (EFF1) will allow for a water balance to be carried out for the
wetland and determine whether water losses (beyond evapo-transpiration) are occurring.
Where a gravel drainage layer above the clay capping is present, such as the northern part of
Stage 1, any leakage through the wetland would flow laterally through this gravel layer and
directed to the phytoremediation swale. After heavy rainfall events, visual checks of flows in
the infiltration swale are to be undertaken and if abnormal flows are present beyond those
expected from rainfall, further investigation will be required to ascertain the origin of flows, and
would include testing the water in the phytoremediation swale.
The existing piezometers installed along the landfill cap for monitoring of leachate standing
levels will also be retained where possible and will continue to be monitored to assist in
assessing potential wetland leakages.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 162
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
7.4 MAINTENANCE & SYSTEM HEALTH MONITORING
7.4.1 Ongoing Maintenance Tasks
Ongoing maintenance tasks refer to those tasks which will be undertaken on a regular
(weekly, monthly or quarterly) basis. The ongoing maintenance tasks will be fully identified in
a Operating and Maintenance Manual to be done at a later stage, however as a minimum
these will include:
Maintenance Tasks for Infrastructure:
o Equipment (e.g. pumps, manholes, liner, concrete structures) – will be
inspected and maintained as per manufacturer’s specifications, and as part of
routine maintenance quarterly or biannually and after peak rainfall events.
o Operators Inspection Checklist (to be prepared as part of the Operating
Manual) – will be completed after each maintenance activity and any issues
recorded and actioned.
o Sediment levels – will be monitored quarterly and removed from sediment
chambers and pre-filter as required.
o Pipe work and weirs – will be checked for leaks and blockages weekly or
monthly and following peak events. Pipes will be cleaned periodically to ensure
they are free of any obstructions which have the potential to cause clogging.
o Manholes and valves – will be inspected to ensure function is correct and to
ensure accessibility.
o Access track and embankments –will be inspected for damage, erosion, and
weeds. Tracks will be maintained as required to ensure they remain clear and
accessible.
o Site Fencing – will be inspected quarterly to ensure public safety.
o Rock-lined distribution zones – will be inspected and cleaned as required.
Maintenance Tasks for Wetland Vegetation:
o Weed control activities – will be undertaken on a quarterly or bi-annual basis
throughout the wetland.
o Plant health, density and diversity – will be monitored on a bi-annual basis
throughout the wetland and appropriate management measures undertaken to
replace plants, undertake weed control works or apply conditioners etc if
required.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 163
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Maintenance Tasks for Potential Wetland Leakage:
o After heavy rainfall events, visual checks of flows in the infiltration swale will be
undertaken. If abnormal flows are present beyond those expected from rainfall,
further investigation will be undertaken to ascertain the origin of flows.
o The existing piezometers installed along the landfill cap for monitoring of
leachate standing levels will also be retained (where possible) and will
continue to be monitored to assist in assessing potential wetland leakages.
o If leakages due to issues of liner integrity are identified, the relevant section of
the wetland will be taken off-line and repaired.
Condition Assessments of the Creek Tributary - BCC, with the consent of the
neighbouring property owner, will undertake annual condition assessments of the
creek tributary from the treated leachate discharge point to Three Mile Road for the
first 3 years after construction of the treatment system. This will be to ensure the
anticipated positive creek benefits associated with improved environmental flows and
biodiversity improvement works are realised.
7.4.2 Scheduled Maintenance Tasks
Scheduled maintenance tasks are those tasks which will be scheduled annually or 3 to 5
yearly. The scheduled maintenance tasks will be fully identified in an Operating and
Maintenance Manual to be done at a later stage, however as a minimum these will include:
Maintenance Tasks for Wetland Vegetation.
o Sediment – will be removed and disposed of from pre-filter and manhole
chambers;
o Biomass thinning – will be undertaken on a 3 to 5 year harvesting plan; and
o Supplementary planting – will be undertaken in bare areas if required.
Maintenance Tasks for Landfill Settlement
o If required, repairs to wetland bund heights will be undertaken to maintain
flows and freeboard capacity. This will be achieved by adding fill material and
potentially extending the liner along any sections of the wetland bunds that
have settled below the critical 200 mm freeboard level. Weirs/pipes may
require adjustments (e.g. alter weir board positions) however this is not
envisaged as likely.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 164
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
7.5 REPORTING
In line with the current EPN prescription, a report with the results of the water monit oring,
including sampling locations, sampling methods, chain of custody documentation and
comparison of results against the site specific treatment criteria and the Australian Water
Quality Guideline for Aquatic Ecosystems (ANZECC, 2000) Ecosystem Condition 2 (level of
protection 95% species) trigger values applying to lowland streams will be prepared and
submitted to the EPA on a quarterly basis. The results of the geotechnical monitoring will also
be submitted to the EPA within the same report.
8.0 DECOMMISSIONING & REHABILITATION
The Burnie Waste Management Centre is expected to have a long life span as a waste
recovery centre (more than 20 years), hence the wetland itself will continue to be managed as
part of the site alongside this. At some point, the data on water quality discharge from the site
may indicate that the raw leachate is acceptable for direct infiltration on-site.
In the longer term at site closure, the wetland could be repurposed as a stormwater treatment
system, eventually opened to the public as a recreational biodiversity reserve.
9.0 COMMITMENTS
A consolidated set of commitments is provided in Table 34.
10.0 CONCLUSION
This DPEMP has complied with all the requirements of the project specific guidelines. The
relevant sections are summarised in Table 35.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 165
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 34. Commitments table for the Burnie Treatment Wetlands proposal
Design &
ApprovalsConstruction Operation
1 Undertake works to separate the stormwater from the MH1 leachate chamber BCC
2 Limit the placement of the wetland system to at least 10 m from the landfill crest. BCC
3 Ensure appropriate freeboard to accommodate the 1000 year rainfall event (182 mm) BCC
4 Limit the height of bunds to <2 m to prevent excessive settlement BCC
5 Use a LLDPE liner to reduce wetland seepage risks BCC
6 Construction of an emergency storage tank and recirculation system and operate for non-compliant water BCC
7 Construct a new connection to sewer maintained in case of non-compliance, as final contingency. BCC / TASWATER
8Retain wetland designer during construction / contract management phases to ensure quality control of all system
components (e.g. liner, hydraulics, planting, etc) and safeguard management elements are constructed as per design.BCC
9Ensure interception and treatment of extreme storm event leachate seepages that may occur along the northern
embankment, within a phytoremediation swale.BCC
10Establish a new compliance monitoring point at the creek discharge point and monitor flows (continuous, on-line) and
pollutants as shown in Table 31, when discharge events occur.BCC
11Establish a performance monitoring point at the polishing wetland outlet and install on-line flow and monitoring sufficient
to determine recirculation requirements (as shown in Table 33).BCC
12 Undertake sampling in accordance with the proposed monitoring schedule shown in Table 33. BCC
13Set aside an appropriate maintenance budget to be include in OPEX for the life of the wetland, to ensure that all required
maintenance activities are done appropriately and with the required frequency.BCC
14Develop Operation and Maintenance Plans which detail the required maintenance activities and frequencies and ensure
their appropriate implementation.BCC
NO. COMMITMENT
TIMING PHASE
RESPONSIBILITY
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 166
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 34 (cont.). Commitments table for the Burnie Treatment Wetlands proposal
Design &
ApprovalsConstruction Operation
15Ensure Construction Mangement Plans contain practices for managing environmental risks and safety risks during
construction works.BCC
16 Ensure Construction Management Plans comply with specifications and policies and sign off accordingly. BCC
17Update existing risk management plans to include responses to incidences potentially connected with the treatment
system. This will include incidence response for any on site ponding and mosquito management.BCC
18 Install 4 survey markers and undertake forthnightly monitoring of settlement levels across the landfill pre-during and post
construction for several months.BCC
19 No clearing of native vegetation. BCC
20Use of sediment controls (traps, sediment curtains) during creek enhancement works, and reuse of sediment within
landfill area.BCC
21Use of locally native species in the treatment system to avoid invasive species entering the creek and to enhance
biodiversity.BCC
22Undertake restoration works in the immediate unnamed creek discharge area to reduce weeds, enhance riparian
vegetation, improve habitat and reduce erosion.BCC
23 Undertake an annual condition assessment of the unnamed tributary to Three Mile Rd. BCC
24 Implement an ongoing weed management program within the wetland system and creek discharge areas. BCC
25Provide controlled site access and interpretative walks/signage to enable community use of the proposed system for
education and research.BCC
26 Undertake annual monitoring of settlement levels across the landfill. BCC
27Undertake appropriate training of staff responsible for system monitoring & maintenance, including preparation of user-
friendly management and maintenance plans.BCC
NO. COMMITMENT
TIMING PHASE
RESPONSIBILITY
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 167
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Table 35. Summary of compliance with specific guidelines
No. Summary of response
2.2.3 Proposed System Summary Includes summary of design objectives and criteria.
2.2.4 System Components & Processes
Includes detailed description of system components and processess, including
descriptin of creek discharge regime, connection infrastructure to existing
TasWater sewer network and construction material details.
2.2.6 System OperationHours of system operation, vehicualr movements during construction &
commisioning, and operational regime.
2.2.4 System Components & Processes Provides detailed description of system components.
2.2.5 Wetland Sizing/Capacity
Provides information regarding the required treatment area, operating
depth/volumes, hydraulic loading rates and hydraulic retention times are shown
for each component (Table 1).
3 2.2.7Proposed Stormwater & Creek
Enhancement Works
Provides a brief description of proposed stormwater and creek enhancement
works expected to tie in with the proposed leachate treatment works (Figures
11, 12).
4 2.2.10 Precedent ProjectsGlobal examples of landfill remediation projects for various 'soft' uses (i.e. with
relatively lightweight loads) with minimal or no geotechnical improvements.
5 2.2.3 Proposed System Summary Includes summary of design objectives and criteria.
6 6.3.6 Pests, weeds and diseasesProvides summary of weed/pest management responses during the system
construction and operation.
7 2.2.8 Construction Provides an estimate of the raw materials that will be required for the proposed
system and likely material sources (Table 4).
6.2.4Proposed Management
Measures
6.38 Sediment
REQUIREMENTS RESPONSE
Brief description of the proposed stormwater and creek enhancement works at the BWMC
site, with particular reference to the separation of site stormwater from the
leachate/groundwater system.
Section
2.2 Construction
Measures designed to prevent the introduction or spread of introduced plant species,
weeds, pests and diseases (such as phytophthora cinnamomi ) during construction works.
2.1 Proposal description - General
Detailed description of the wetland treatment system and associated infrastructure,
including size, volume, and design criteria of the wetland ponds, wetland liner, media
and species of flora, leachate collection and transfer infrastructure, overflow storage
ponds, infiltration area and discharge swale/outlets, and connection infrastructure to
existing TasWater sewer network.
1
Description of Specific Requirements
Description of treatment process and treatment capacity (i.e. kL per day), including
residence time required for removal of contaminates and design features to allow for
draining, maintenance and variations in flow.
2
Description of precedent projects, i.e. on‐site wetland leachate treatment facilities on
top of landfills. Where information is available, provide a summary of the issues’ and
success’ of these projects.
Design criteria for the proposed infrastructure in relation to flood risk, e.g. 1 in 100 year
event.
Estimates of the quantities of major raw materials required for construction activities
(e.g. clay, sand, aggregate) and their likely sources.
Details of management practices for areas disturbed during the construction phase to
prevent sediment movement into watercourses. 8
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 168
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
9 2.2.9 Commissioning Provides a list of key commissioning items , and detail regarding the timing and
end of commissioning period (Table 5).
10 2.2.1 General Figure 2. Land boundary, site layout and location points
11 2.2.1 General Figure 3. Site Plan showing landfill stages.
12 3.1
On‐Site Treatment vs
Decommissioning & Remediation
vs Trade Waste Discharge
Summary of the assessment process that focused on the suitability of the
following options:
1) Do nothing and continue to discharge to TasWater Sewerage System under a
Trade Waste Agreement (TWA) with TasWater (Base Case).
2) Remove waste from Stage 1 Landfill and develop and dispose to new waste
cell on site (Stage 2B/C).
3) Remove waste from Stage 1 Landfill, transport and dispose to an alternate
landfill (e.g. Port Latta or Dulverton).
4) On-site treatment.
3.2Evaluation of Reuse vs Disposal
Options
Summary of the assessment process that focused on the suitability of the
following options: 1) On-site reuse , 2) Discharge within the site or above the
landfill site, and 3)Off site discharge to the downstream unnamed tributary of
Cooee Creek.
3.3Evaluation of Treatment
Approaches & Technologies
Summary of the assessment process that focused on a suitability of leachate
management approaches and technologies commonly applied on landfill sites
(e.g. physico-chemical, advanced filtration and biological systems), including
detailed evaluation of three shortlisted technologies (RO, MBR, constructed
wetlands).
14 3.4Assessment of Treatment
Wetland Locations
Summary of the assessment process that focused on the he feasibility of four
alternative locations for the construction of the proposed the on-site treatment
wetland system
5.1.2 Land Use & Planning History
5.2.11 History of Waste ManagementA summary of historical waste management activities on site that may affect the
proposal.
Appendix 13.Chronology of the Waste
Management Activities On Site
2.3 Commissioning
A description of the commissioning of the wetland treatment facility and associated
infrastructure.
2.3 Site plan
A map delineating the boundary of the Land on which the activity will take place.
A site plan showing historical landfill, e.g. stages 1A, 1B, 1C and 2A, extents and
features.
3 Project Alternatives
A discussion of the alternatives for leachate management (e.g. treatment / full
decommissioning and remediation of the landfill / continuing with the trade waste
discharge to sewer, etc).
An assessment of the options for onsite leachate treatment, with reasons for the
preferred treatment system (e.g. physic-chemical systems, filtration, biological
treatment, etc).
13
An assessment of the options for wetland treatment location, with reasons for the
preferred location.
5.2 Existing environment – Environmental aspects
History of waste management activities on site, e.g. stages 1A, 1B, 1C and 2A, including a
description of all elements of the landfill that may affect the proposal. 15
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 169
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
16 5.2.6 Groundwater
Provides detail regarding the existing hydrogeological context and groundwater
quality. Includes summary of groundwater quality data and a conceptual site
model illustrating the interactions between groundwater with leachate and
surface flows .
17 5.2.4 Leachate (Current)Provides detail regarding the leachate flows, leachate quality, and calculations
on discharge (mass loads) of key pollutants to TasWater sewer (Table 14).
18
Provides detail regarding the nature and location of the leachate seepage
including data on leachate seepage chemistry for the 3 sampling events in 2013
(Table 15).
19
Provides summary of findings of soils investigation within the leachate seepage
undertaken in April 2014 (Table 16) and the extent of leachate seepage that
occurred in August 2013.
20 5.2.7 StormwaterProvides the estimates regarding the current stormwater mass loads to the
Creek (point source discharge) (Table 19).
21
Provides detail regarding the current Protected Environmental Values (PEVs) ,
EPA Draft Water Quality Objectives for Cooee Creek and proposed Water Quality
Targets for discharge to Cooee Creek tributary (Table 23).
22Provides information regarding the known abstraction points along Cooee Creek
.
23
24
25
26
27
This section: 1) Provides details regarding the nearest sensitive receptors to the
site; 2) Explains why the proposed wetland treatment system will not generate
point source odour emissions ; 3) Summarises the history of complaints
regarding odours for the existing site (documented in the annual reporting since
2004.
6.3.1 Air Quality
Results of ambient groundwater survey and modelling to define the local groundwater
environment, including groundwater quality and description of the interaction between
groundwater, leachate and surface water. The description must include concentrations of
key groundwater quality parameters.
Description of leachate quality and quantity currently discharged to TasWater’s sewage
network, including mass loadings of key effluent parameters.
Description of leachate seepage, including the mechanisms driving the seepage, and
seepage quantity and quality, including mass loadings of key water quality parameters.
Delineation and characterisation of the leachate seepage area and extent of any soil
contamination.
5.2.5 Leachate Seepage
Identification of current Protected Environmental Values (PEVs) at the proposed
discharge location and within the expected zone of impact, including Cooee Creek. Water
Quality Objectives (WQO’s) should be proposed in relation to all identified PEVs.
Details of the water use within the catchment of the receiving environment (i.e. the
unnamed creek and Cooee Creek).
5.2.8 Cooee Creek and its Tributary
Results of the ambient water quality survey, including mass loadings of key water quality
parameters across a range of flow conditions.
6.1 Air Quality
Provide a map of the area showing the existing and proposed facility and any sensitive
receptors that could be affected by odour emissions from the proposed facility.
Describe and mark the locations (on a site map) of all potential sources of odour
emissions (i.e. wetland ponds (types), infiltration areas etc), and under what conditions
emissions may occur, e.g. commissioning, normal operation, during maintenance etc.
Discuss the potential for odour emissions from the wetland treatment facility to cause
environmental nuisance, including under worst case or upset conditions.
Identify and discuss measures to be implemented (as appropriate) to mitigate any
impacts that may cause environmental nuisance.
Provide a history of odour complaints received in relation to the existing site and the
likely causes.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 170
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
28
29
30
31 6.2Hazard and Risk Assessment of
Key Issues
This section provides an assessment of potential environmental risks associated
with potential discharge of leachate (un-treated or partially treated leachate) to
the creek, or ponding on site, and impacts on the key relevant receptors,
including downstream water users.
32 5.2.8 Cooee Creek and its TributaryProvides detail regarding the proposed Water Quality Targets for discharge to
Cooee Creek tributary (Table 22).
33 5.2.8 Cooee Creek and its TributaryProvides detail regarding the proposed Water Quality Targets for discharge to
Cooee Creek tributary (Table 23).
34 8.0Decommissioning &
Rehabilitation
35 4.1.2 Consultation with TasWaterTaswater will undertake this assessment. They have indicated that this is
unlikely to be an issue.
This section contains the findings of an assessment of flows and pollutant mass
loads to the infiltration forest and to the creek, and includes: 1) Identification of
discharge pathways and occurrence of discharge events, 2) Indirect discharge
occurrences - Estimated mass loadings of key pollutants to wet forest; 3) Direct
discharge occurrences - Estimated Mass Loadings to Creek (i.e. creek volumetric
discharges and mass load discharges in each month and annual mass load
discharges for select pollutants); 4) Comparison of total annual discharge to the
Creek in a dry year (2014) and wet years (2012, 2013) and corresponding mass
loadings of key pollutants (Table 29 and Table 30).
Surface Water 6.1.1
Provide an assessment of the capacity of the sewerage system to receive the leachate
discharge, as part of contingencies measures.
Demonstrate that the proposed discharge(s) will satisfy the requirements of the State
Policy on Water Quality Management 1997, including compliance with any relevant
emission limit guidelines.
Recommend emission limits and trigger levels. These should be based on the character of
the receiving environment (e.g. water quality, proposed WQOs, seasonal flow).
Provide an estimate of the required life of the water treatment system (based on the
breakdown processes within the landfill), and the water quality criteria that need to be
met before the wetland system can be considered redundant (which may be based on the
quality of receiving environment, ratified WQOs, mass-loads of key contaminants etc).
6.2 Surface Water
Water balance for the site, detailing estimates of seasonal discharge to the receiving
environment, incorporating seasonal infiltration capacity and high flow/stormflow
management regimes
Identification of the discharge point from the activity to the surface water receiving
environment.
Expected quality of discharge to the surface water receiving environment (i.e. unnamed
creek), including annual mass loadings, and with comparison to ambient water quality.
The likely occurrence of discharge events to the surface environment should be clearly
understood from the water balance.
Discussion of the potential for the discharge to cause environmental impact. This should
include consideration of typical and plausible worst case situations, seasonal variations,
and potential for impact to downstream water users.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 171
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
5.2.6 GroundwaterMass loads to the infiltration wetland are shown in Table 26. Note, this DOES
NOT report to groundwater but discharges to the Creek via sub-surface flows.
6.1.1Potential Surface Water
Impacts
5.2.5 Leachate Seepage Describes the quality and estimate of volumes
2.2.4System Components &
Processes
Describes the phytoremediation swale proposed to intercept ad treat leachate
seepage events.
38 5.2.6 GroundwaterThere is no potential given it is a groundwater discharge zone. All flows
eventually report to the Creek (conceptual site model - Figure 28).
2.2.4 System Components &
Processes
6.2Hazard and Risk Assessment of
Key Issues
40 6.1.3 Potential Geotechnical Impacts Results and relevant information summarised in these two sections.
6.2Hazard and Risk Assessment of
Key Issues
Appendix 6 Hydro-geotechnical report (Tasman Geotechnics, August 2015)
41 7.3 Geotechnical Monitoring
Discussion of the potential for the treated discharge to the groundwater environment,
including the leachate seepage, to cause an environmental impact. This should include
consideration of typical and plausible worst case situations, and potential for impact to
the surface water and downstream water users.
A groundwater monitoring and reporting program must be developed, incorporating
appropriate mechanisms to monitor for wetland leakage, landfill cap settlement and loss
of landfill integrity.
Contingency measures to ensure protection of the receiving environment (i.e. the
groundwater, surface water and downstream water users) should treated leachate
exceed proposed trigger levels (see section 6.2) (e.g. collection and re-circulation of
treated leachate through wetland facility).
The expected quality and quantity of leachate seepage, and measures to manage the
seepage.
Characteristics of the effluent following treatment, including mass loadings of key
pollutants and the expected quality and quantity discharged to the groundwater
environment via the infiltration areas.
6.3 Groundwater & geotechnical issues
36
37
39
Results of the geotechnical investigations and modelling, incorporating a discussion(s) of
the potential for wetland leakage, landfill cap settlement and loss of landfill integrity
(including containment bund), their likely impact on the receiving environment, and
details of management strategies/contingency measures to mitigate the potential impact
(as appropriate).
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 172
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
42 6.3.3 Waste Management
43
44
45 Appendix 2NEST Natural Values
Assessment Report, 2014
Not quantitatively assessed but commented on in this Section and NEST report .
Increased flows are expected to improve habitat quality for the key fauna.
46 7.0 Monitoring & Review
47
48 7.3Maintenance and system health
monitoring
Monitoring programs to ensure the proper functioning of the wetland and infiltration
system and protection of the environment on an ongoing basis.
Details of the monitoring programs
Description of maintenance regimes to ensure the proper functioning of the wetland and
infiltration system on an ongoing basis.
Description of the potential changes to the flow regime of the unnamed creek and Cooee
creek, with particular regard to water levels, and the potential impact on Burnie
Burrowing Crayfish (Engaeus yabbimunna ) populations downstream of the development.
5.2.8 and
Appendix 14.Cooee Creek and its Tributary
7.0 Monitoring and maintenance
6.5 Waste Management
Description of the management of wetland sludge/bio-solids generated on site.
6.7 Biodiversity and nature conservation values
Results of surveys for any rare, threatened, endangered and locally endemic species that
will potentially be impacted by the proposal.
Identify any freshwater ecosystems of high conservation management priority using the
Conservation of Freshwater Ecosystem Values (CFEV) database (accessible on the internet
under water.dpiw.tas.gov.au/wist/). The scope of investigation should encompass the
vicinity of the proposed development where there is likelihood of alteration to the
existing environment. The specific CFEV information used for DPEMPs should be
Conservation Management Priority Potential which is appropriate for Development
Proposals.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 173
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
REFERENCES
Asian Regional Research Programme on Environmental Technology (ARRPET) (2004). State
of the Art Review Landfill Leachate Treatment. Asian Institute of Techno logy, Thailand and
Tongji University, China.
Australian and New Zealand Environment and Conservat ion Council and Agriculture and
Resource Management Council of Australia and New Zealand (ANZECC, 2000) National
Water Quality Management Strategy No. 4: Australian and New Zealand Guidelines for Fresh
and Marine Water Quality (October 2000).
Bouazza A and Kavazanjian E (2001). Construction on former landfills. Proceedings 2nd ANZ
Conference on Environmental Geotechnics, Newcastle, 467-482.
Carey, P.L., Drewry, J.J. Muirhead, R.W. & Monaghan, R.M. (2004). Potential for nutrient and
faecal bacteria losses from a dairy pasture under border-dyke irrigation: a case study.
Proceedings of the New Zealand Grassland Association 66: 141–149.
Coffey Geosciences (2004). Mooreville Road Landfill Stage 2: Hydrogeological Investigation
for Landfill Liner. Report HO2019/1-AB. Prepared for Burnie City Council, 20 January 2004.
Coffey Geotechnics (2008). Mooreville Road Landfill, Hydrogeology and Sub-liner Drainage.
Report GEOTPVAL307AA-AC. Prepared for Burnie City Council. 7 March 2008.
DPIWE (2001). Environmental Water Requirements for the Emu River. Report Series WRA
01/07 December, 2001.
DPIWE (2004). Landfill Sustainability Guide. Department of Primary Industries, Water and
Environment, 2004.
Entura (2011). Cooee Creek Flood Study. Prepared for Burnie City Council, September 2011.
EPA (1997). State Policy on Water Quality Management.
EPA (2010). Review of the State Policy on Water Quality Management 1997. Response to
Public Submissions and Preferred Options. EPA Division, Department of Primary Industries,
Parks, Water and Environment, 2010.
EPA (2015). Stage 1 Landfill Treatment, Burnie Waste Management Centre, Burnie.
Determination on Class of Assessment. Sept 10th
2015.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 174
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Ezzy A. R. and Latinovic M. (2004). MRT statewide groundwater monitoring network: Data
collection — September 2004 Mineral Resources Tasmania Tasmanian Geolog ical Survey
Record 2005/01.
Kadlec, R.H. and Wallace, S.D. (2008). Treatment Wetlands, 2nd ed.; CRC Press: Boca
Raton, FL, USA, 2008.
Maehlum, T. (1999). Wetlands for treatment of landfill leachates in cold climates. In: G.
Mulamootil, E.A. McBean, and F. Rovers (eds.) Con- structed wetlands for the treatment of
landfill leachate. Boca Raton, FL:Lewis Publishers, pp. 47-56.
Martin R and Currie D (2008). Development of Models for Tasmanian Groundwater
Resources. Conceptual Model Report for Cam-Emu-Blyth. Prepared for DPIW Tasmania,
November 2008.
Mienhardt Infrastructure and Environment, (April 2005). Mooreville Road Landfill –
Environmental Operations Manual.
NEST (2013). Burnie Waste Management Rehabilitation Program. Prepared for Burnie City
Council.
Sharman, R (2002). BEng Hons Thesis. Deakin University.
SKM (2007). Moreland Road Landfill, Environmental Review of Landfill. Prepared for Burnie
City Council. 14 March 2007.
Standards Australia (2006). HB 203:2006 Environmental risk management - Principles and
process.
Standards Australia (2009). AS/NZS ISO 31000:2009 Risk management - Principles and
guidelines.
Stevenson, M.D. and Mazengarb, C. 2010: Map 1, Burnie ‐ Landslide Inventory. Tasmanian
Landslide Map Series. Mineral Resources Tasmania, Department of Infrastructure Energy and
Resources, Hobart.).
Syrinx Environmental PL (2015). Water quality clarifications. Syrinx Memo report, Prepared for
burnie City council, July 2015.
Taylor, R. and A. Allen (2006). Waste Disposal and Landfill: Potential Hazards and Information
Needs, in O. Schmoll, G. Howard, J. Chilton and I. Chorus (eds) Protecting Guidelines for
Design and Operation of Municipal Solid Waste Landfills in Tropical Climates, 2013 Page 29.
Groundwater for Health: Managing the Quality of Drinking‐water Sources, IWA Publishing.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 175
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
Valencia, R, van der zon, W, Woelders, H. Lubberding, H.J. and Gizjen, H. (2009). Achieving
“Final Storage Quality” of municipal solid waste in pilot scale bioreac tor landfills. Waste
Management 29(1):78‐85 ∙ January 2009.
van Zomeren, A., H.A. van der Sloot, J.C.L. Meeussen, J. Jacobs, H. Scharff (2005),
Prediction of long term leachate behaviour of a sustainable landfill containing predominantly
inorganic waste. 10th
International Waste management and Landfill Symposium, October
2005, Sardinia). EU Council Directive 1999/31/EC of 26 April 1999 on the landfill of waste.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 176
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDICES
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 177
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 1. Burnie Waste Management Centre (BWMC) Stage 1 Landfill
Leachate Treatment Study – Option Development and Evaluation
and Preferred Option Concept Design (Syrinx Environmental PL,
July 2014).
ATTACHED SEPARATELY
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 178
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 2. Natural Values Assessment Report (NEST July 2014)
ATTACHED SEPARATELY
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 179
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 3. EPBC Referral Decision
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 180
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 4. Addendum to Stage 1 Landfill Leachate Treatment Study –
Design Changes & Alternative Wetland Option Assessment
(Syrinx Environmental PL May 2015).
ATTACHED SEPARATELY
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 181
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 5. Assessment of Alternative Leachate Management Options (BCC
May 2015).
ATTACHED SEPARATELY
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 182
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 6. Hydro‐geotechnical Investigation and Risk Assessment Version
2, August 2015 (Tasman Geotechnics August 2015)
ATTACHED SEPARATELY
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 183
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 7. Preliminary Treatment System and Associated Infrastructure
Layout
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 184
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 8. EPA Class Assessment of The Project Proposal
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 185
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 9. Proposed Wetland Species List
PLANT SPECIESDESCRIPTION
SURFACE FLOW/SUBSURFACE FLOW WETLANDS
Rushes and Sedges
Baloskion australis 'Southern Cordrush' Almost leafless rush to 0.5 metres. Flowering stems dark red-brown. Flowers reddish in spring/summer.
Baloskion tetraphyllum ' Tassel Cordrush' Soft foliaged clump-forming rush to 1.7 metres. Foliage soft green, flower spikes red-brown in spring/summer.
Baumea juncea 'Twine Sedge' Perennial emergent aquatic, creeping rhizomes, 0.5-1m. Culms blue-green.
Baumea rubiginosa Perennial emergent aquatic, creeping rhizomes, 0.5-1m. Culms dark green.
Carex apressa ' Tall Sedge'Erect clump forming perennial sedge 0.5-1.2m height. Width 1.0m. Evergreen with fast growth rate Suits most soils.
Flowering in Spring and Summer.
Carex fascicularis ' Tassel Sedge'Erect clump forming perennial sedge 0.5-1.0m height. Width 1.0m. Evergreen. Evergreen with fast growth rate Suits most
soils. Full sun to part shade. Flowering in Spring and Summer.
Carex longebrachiata 'Drooping Sedge' Tussock forming sedge to 0.6 metres with long arching flower stems.
Carex tasmanica 'Curly SedgeErect clump formimg perennial sedge 0.4m height. Width 0.4m. Evergreen. Evergreen with fast growth rate Suits most
soils. Flowering in Spring and Summer. Tasmanian threatened species.
Carex tereticaulis ' Hollow Sedge'Erect clump forming perennial sedge 1.0-1.8m height. Width 1.0m+. Evergreen. Evergreen with fast growth rate. Prefers
clay soils . Flowering in Spring and Summer.
Chorizandra enodis Perennial sedge 0.5- 1m. Very narrow blue-grey to dull green cylindrical culms. Small black flowerball seedheads.
Cyperus gunnii ' Flecked Flatsedge' Tall, tufted perennial sedge to 150cm, with short thick rhizome. Culms trigonous to terete.
Cyperus lucidus ' Candelabra Sedge'Robust perennial sedge up to 1.3 m. The leaves are thick and glossy. The flowers form an umbrella-l ike head which is
bright red when young, turning red-brown as it matures.
Eleocharis sphacelatus ' Tall Spike Rush' Perennial aquatic with stout rhizome. Culms terete to 5 m high. Permanent water.
Gahnia filum 'Chaffy Saw Sedge' Dense tufted perennial to 1.2 metres. Flowers in spring/summer. Tasmanian Bush Tucker.
Gahnia grandis 'Cutting Grass'Large tussock with plume-like flowering heads to 3.5 metres. Grass-like leaves, cutting edges. Flowers in spring/summer.
Isolepis fluitans ' Floating Clubsedge'Slender, aquatic or dry land perennial up to 15cm height.Erect and tufted, spreading or submerged. Use for ponds, wet
areas and water courses. Semi shade. Pale green or straw coloured flowers in spring/summer.
Isolepis inundata ' Swamp Clubsedge'Tufted perennial rush with stiffly erect or arching stems. Deep glossy green foliage. Purple-brown flowerheads
spring/summer. Most soil types and condition.
Isolepis stellata Tufted annual, grass-like or herb (sedge), 0.02-0.1 m high, spikelets 3-8, in a dense globular cluster; Flowers yellow-
green, Sep to Dec or Jan. Grey, black peaty or orange clayey sand, loam, sandy clay.
Juncus amabilis 'Hollow Rush'Densely tufted perennial rush 0.2-1.2m height. Width 0.2 -0.5m. Spreading from underground stems. Green flowers in
Summer. Best in seasonally moist to inundated soils.
Juncus astreptus ' Rigid Rush'Rhizomatous perennial forming tight clumps 0.6-1.0m height. Brownish green flowers in Summer. Most soils -well
drained or waterlogged.
Juncus bassianus ' Forest Rush' Rhizomatous perennial forming large clumps 0.5-1.0m height. Moist soils.
Juncus filicaulis ' Thread Rush'Densely tufted perennial rush 15-45cm height. 30-50cm width. Spreading from underground stems. Straw coloured
flowers in Summer.
Juncus gregiflorus 'Green Rush'Densely tufted perennial rush 0.4-1.7m height. Width 0.6-1.5m. Spreading from underground stems. Straw coloured
flowers in Summer.
Juncus pauciflorus 'Loose Flower Rush' Rhizomatous, colonial perennial, herb, 0.3-1 m high. Fl. Sep to Oct. Clay.
Juncus pallidus 'Pale Rush' Tall robust rush to 2.0 metres. Vigorous coloniser of poorly drained areas.
Juncus procerus ' Tall Rush'Dense robust tufted perennial rush 1.2-1.5m height. Width 0.6-1.5m. Spreads from underground stems. Straw coloured
flowers in Summer.
Juncus sarophorus ' Broom Rush'Tufted perennial rush 0.7-2.0m height. Width 0.5-1.0m. Spreads from underground stems. Straw coloured flowers in
Summer.
Schoenoplectus tabernaemontani ' River Club Rush' Creeping rhizomatous perennial sedge, 1-3.0 m height. Straw coloured flowers in Summer.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 186
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
INFILTRATION 'WET FOREST' & WETLAND BUNDS
Rushes and Sedges
Eleocharis acuta ' Common Spike Rush' Perennial sedge with creeping rhizome. Culms terete. 0.3 - 0.5m high. Seasonal wetlands.
Gahnia grandis 'Cutting Grass' Large tussock with plume-like flowering heads to 3.5 metres. Grass-like leaves, cutting edges. Flowers in spring/summer.
Gymnoschoenus sphaerocephalus ' Button Grass'This species is the dominant species of most lowland sedgelands on wet peat in Tasmania. It forms large, dense clumps
of long, narrow, yellow-brown leaves with long, cylindrical stems, each bearing a spherical terminal head of flowers.
Isolepis stellata Tufted annual, grass-like or herb (sedge), 0.02-0.1 m high, spikelets 3-8, in a dense globular cluster; Flowers yellow-
green, Sep to Dec or Jan. Grey, black peaty or orange clayey sand, loam, sandy clay.
Poa labillardierei ' Tussock Grass'Dense perennial tussock grass, common in open forests particularly in moister areas on southern slopes or in gullies
and along watercourses, on loamy soils. Suitable to clay soils. Si lver.
Xyris muelleri 'Yellow-eyed Grass'Leaves more or less spirall ing. Flowers yellow, lasting more than one day, early summer. Tasmania, in moist soil at
margins of streams and ponds.
Herbs
Billardiera longiflora 'Climbing Blue Berry'
(Climber)
Ornamental twiner grows to ~3m tall. Partial or full shade. Flowers spring and summer, producing creamy green bell-
shaped flowers that are tinged with purple. Suitable to clay soils.
Chrysocephalum apiculatum Varies considerably in form, 0.2 - 1 m in height, Suitable in clay soils. Yellow flowers.
Austrodanthonia pilosa ' Velvert Wallaby Grass' Perennial grass. Whispy white tips.
Dichondra repens 'Kidneyweed' Fast-growing groundcover. Leaves are small and kidney shaped. This plant has a creeping habit and forms a thick mat.
Diplarrena moraea 'White Flag Iris' Perennial small herb which forms thick clumps with long narrow leaves and white flowers at the ends of slender stems.
Helichrysum scorpioides Everlasting. Yellow flowers / grey foliage (daisy l ike).
Patersonia fragilis ' Short Purple Iris' Tufted glabrous herb to c. 50 cm high with purple flowers.
Triglochin procera 'Ribbon weed' Aquatic perennial. Permanent water.
Shrubs
Acacia myrtifolia 'Red-stemmed wattle'Shrub 1 - 2 m tall by 1-2 m wide. The phyllodes are ell iptic and usually slightly curved. The cream flower clusters are
globular in shape and occur on short racemes from the leaf axils in spring. Suitable to clay soils.
Acacia mucronata ' Narrow-leaved wattle' Shrub 1 - 2 m tall. Yellow flowers. 1-15m.
Acacia verticillata 'Prickly Moses'Variable height; generally rounded shrub. Phyllodes are dark green, spine-like, to 2 cm, in whorls around the stem. Pale
yellow flowers in short spikes. Yellow flowers. 5-10m. Suitable to clay soils.
Banksia marginata ' Silver Banksia'Medium shrub to 2 m tall. Leaf upper surface dark green with the lower surface white and hairy. Flowers pale yellow,
densely packed in cylindrical spikes up to 100 mm long. Suitable to clay soils.
Bauera rubioides ' Dog Rose' Scrambling shrub to 2 m high, stems extensively branched. Pink flowers. 0.3-1.5m.
Bursaria spinosa ' Prickly Box' Evergreen shrub <2 m tall, shrub or small tree <5 m tall or tree 5-10 m tall. Suitable to clay soils.
Bossiaea prostrata 'Creeping Bossiaea' Small (0.5m) prostrate shrub with yellow flowers.
Correa alba 'White Correa' Small shrub with grey foliage and white flowers. Grows to 1.5m.
Correa lawrencianaGrows to between 0.6- 9m in height, and has leaves with a shiny, dark-green upper surface. Flowers winter- spring,
typically yellow-green. Suitable to clay soils.
Daviesia latifolia ' Hop Bitter-pea' Shrub 1- 3 m with large leaves and clusters of yellow and brown pea flowers produced between Sept-Dec.
Daviesia ulicifolia Grows to 2m with yellow / red pea flowers.
Dillwynia cinerascens ' Parrot Pea' Compact shrub to 0.3-1.5m. Masses of yellow & red flowers (appearing orange)in spring.
Dillwynia glaberrima Small shrub ~1.5 metres high by 1m wide. Yellow / red flowers forming in spring.
Epacris impressa Shrub to 1-1.5m with stiff branches. Pink / red bell shaped flowers.
Hibbertia procumbens A prostrate and spreading shrub, with yellow flowers.
Leptospermum lanigerum ' Woolly Tea-Tree' Large, spreading or erect shrub, Flowers are white and appear in early summer. Suitable to clay soils.
Leptospermum scoparium Compact shrubup to 2 m tall. Leaves are variable in shape and size. White flowers, occasionally tinged with pink and
rarely red, 1 cm in diameter, occur in spring and early summer.
Leucopogon parviflorus 'Currant Bush' Erect shrub or small tree, 120–500 cm high; branchlets finely pubescent. White flowers. Suitable to clay soils.
Lomatia tinctori Small shrub to 2 m, spreading through suckers. Cream or white flowers in summer. Suitable to clay soils.
Olearia lirata 'Daisybush' Shrub to 4 m high with greyish-white branchlets and white flowers.
Oxylobium ellipticum 'Golden Rosemary' Erect to procumbent shrub to ≥ 2 m high. Yellow flowers spears. Suitable to clay soils.
Pimelea linifolia Small, erect shrub to 0.5-1.5m, with l inear leaves. Flowers usually white or very pale pink he species occurs on a range
of soils from sands to clays.
Tasmannia lanceolata 'Mountain Pepper'Tall evergreen shrub to small tree up to 10 m high. The trunk is straight, with many branches arising at acute angles.
Suitable to clay soils.
Tetratheca pilosa 'Hairy Pink Bells' Erect or spreading shrub with branches up to 1 m high, arising from stout root stock, mauve flowers.
Tall Shrubs / Small Trees (swamp) (no trees on landfill cap)
Acacia dealbata 'Si lver Wattle' Large shrub or medium‐sized tree with an erect main stem 6–15 m tall. Suitable to clay soils.
Acacia melanoxylon 'Blackwood' Medium-sized to tall tree. Suitable to clay soils.
Eucalyptus amygdalina ' Black Peppermint'
Tree to 30 m tall. Forming a l ignotuber. Bark rough on part or all of trunk and to base of large branches, finely fibrous
peppermint type, dark grey to grey-brown, smooth bark white to grey, or brownish, sometimes with ribbons of
decorticated bark in the upper branches. Suitable to clay soils.
Eucalyptus gunnii 'Cider Gum'
Small- to medium-sized evergreen tree. The bark is often persistent for several metres as a thin, grey stocking, or
shedding all over to leave a smooth, yellowish, patchy surface, weathering to white-, green- or pink-grey. Leaves are
stalked, ell iptical to ovate, to 8 cm long and 3 cm broad, concolorous, grey-green and thick. White flowers are produced
in midsummer. Grey / silver. Suitable to clay soils.
Eucalyptus obliqua ' Stringybark'
Tree to 90 m tall, or sometimes a mallee. Forming a l ignotuber. Bark rough to small branches or sometimes branches < 8
cm diameter smooth; rough bark stringy or fibrous, brown to grey-brown, longitudinally furrowed; smooth bark green or
grey. Suitable to clay soils.
Eucalyptus ovata ' Swamp Gum'Usually a medium-sized tree, but can grow up to 30 m tall. This tree is often found in swampy areas and in this
environment the tree is usually smaller in size. Suitable to clay soils.
Eucalytpus viminalis ' White Gum'Tree to 30 m high ; bark smooth or persistent on lower trunk, grey to grey-black, shortly fibrous, hard, platy, smooth
above, white, grey or yellow, shedding in long ribbons. Suitable to clay soils.
Melaleuca ericifolia 'Swamp Paperbark' Shrub or small tree to 8 m high with corky bark. Suitable to clay soils.
Melaleuca squarrosa Shrub or small tree to 12 m high with papery bark.
Nematolepis squamea 'Satinwood'Large shrub or small tree up to ~ 10m. The leaves are ell iptical , glossy green above and silvery below. Flowering
usually occurs in spring; flowers white. Suitable to clay soils.
Pomaderris apetala ' Dogwood'Widespread and abundant tree or large shrub species. One of the main components in the canopy of wet sclerophyll
forests. It has large leaves, which have irregular margins and irregularly lumpy surface. Suitable to clay soils.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 187
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 10. Letters to Stakeholders
ATTACHED SEPARATELY
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 188
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 11. Certificate of Title
SEARCH DATE : 23-Jul-2014SEARCH TIME : 07.43 AM
DESCRIPTION OF LAND City of BURNIE Lot 1 on Plan 145841 Derivation : Part of 50000 acres granted to The Van Diemans Land Company Derived from A19301
SCHEDULE 1 BURNIE CITY COUNCIL
SCHEDULE 2 Reservations and conditions in the Crown Grant if any CONVEYANCE Made Subject to Exceptions And Reservations in favour of The V.D.L. Co.
UNREGISTERED DEALINGS AND NOTATIONS No unregistered dealings or other notations
SEARCH OF TORRENS TITLE
VOLUME
145841FOLIO
1
EDITION
1DATE OF ISSUE
22-Mar-2007
RESULT OF SEARCHRECORDER OF TITLES
Issued Pursuant to the Land Titles Act 1980
Department of Primary Industries, Parks, Water and Environment www.thelist.tas.gov.auPage 1 of 1
SEARCH DATE : 23-Jul-2014SEARCH TIME : 07.44 AM
DESCRIPTION OF LAND City of BURNIE Lot 2 on Sealed Plan 27996 Derivation : Part of Section 133, 50,000 Acres Granted to The Van Diemens Land Company Prior CT 4261/55
SCHEDULE 1 BURNIE CITY COUNCIL
SCHEDULE 2 Reservations and conditions in the Crown Grant if any SP 27996 EASEMENTS in Schedule of Easements CONVEYANCE Made Subject to Exceptions And Reservations in favour of The V.D.L. Co. created by a more fully set forth in Conveyance No. 14/322 14/322 CONVEYANCE Made Subject to Fencing Condition
UNREGISTERED DEALINGS AND NOTATIONS No unregistered dealings or other notations
SEARCH OF TORRENS TITLE
VOLUME
27996FOLIO
2
EDITION
1DATE OF ISSUE
16-May-1994
RESULT OF SEARCHRECORDER OF TITLES
Issued Pursuant to the Land Titles Act 1980
Department of Primary Industries, Parks, Water and Environment www.thelist.tas.gov.auPage 1 of 1
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 189
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 12. Chronology of the Waste Management Activities On Site
Stage 1 - Landfill Stages 1A, 1B and 1C were developed in the period from 1987 to 2004. The
Stage 1 landfill operations ceased in around 2004, with Stage 1A, 1B and 1C areas being
progressively capped between 2004 and 2005. A leachate rising main and second pump was
installed in late Feb 2009 to carry flows in excess of the main pump capacity (Pump 1) to the
Stage 2 Leachate Pond.
Stage 2 - Development of Stage 2A – Cell 1 and Cell 2 occurred in the period from 2004 to
2005. The life of Stage 2A was ~ 8.2 years, and was capped (interim cover) in March 2013.
Waste Facility - Construction of the Waste Transfer and Resource Recovery facility began in
April 2012 and was commissioned in Nov 2012. Pre-development it was the greenwaste
stockpile/chipping pad and runoff from the area went to stormwater to the west (minor) and
rest to the leachate pond from the eastern and southern areas.
A review of the BMWC landfill site was undertaken between 2006 and 2011, to assess the
long term needs of the Burnie Municipality, and the financial and environmental risks and
benefits of developing the remaining Stage 2B and Stage 2C areas. As a result of this review
it was proposed that a new Waste Transfer Station (WTS) be developed, and the Stage 2
landfill site would be closed and not further developed. Following the start of the WTS
operation in November 2012, the Stage 2A landfill site ceased to take waste. Since 2013 the
Stage 2A landfill Area has been capped with an interim final cover and is currently being
rehabilitated.
Pre 1987: Push pit
1987 to 2004: Development of Stages 1A, 1B and 1C
2004: Development of Stage 2A – Cell 1 and capping Stage 1B.
2005: Development of Stage 2A – Cell 2 and capping of Stage 1A & 1C.
2006: Development of Resource Recovery Area (Recycle Loop)
2012: Completion of Waste Transfer and Resource Recovery Facility and ceased
operation of Stage 2A landfill
2013: Interim cap of Stage 2A, rehabilitation.
2014: Initiation of Stage 1 leachate wetland treatment project
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 190
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 13. CFEV Assessment Component Report.
This document has been produced by The Department of Primary Industries, Parks, Water and Environment.
Questions concerning its content may be directed by email to [email protected]
The URL for this page is: http://wrt.tas.gov.au/wist/
Page 1 - CFEV Assessment Component Report
Important biophysical class (as predicted under pristine conditions) Biophysical Class Type: Tree assemblage Class Description: A mosaic of damp sclerophyll, wet eucalypt forest andrainforest extending from coastal north-western Tasmania, through Quamby to thenorth-eastern highlands in the north in the mid reaches of the Derwent and thelower Huon River in the south. Similar tree composition to assemblage 18. Species Composition: Acacia dealbata, Acacia melanoxylon, Allocasuarinalittoralis, Atherosperma moschatum, Banksia marginata, Bursaria spinosa,Eucalyptus amygdalina, Eucalyptus obliqua, Eucalyptus ovata Eucalyptus regnans,Eucalyptus viminalis, Exocarpos cupressiformis, Leptospermum lanigerum,Leptospermum scoparium var., Melaleuca squarrosa, Monotoca glauca, Notelaealigustrina, Nothofagus cunninghamii, Olearia argophylla, Phebalium squameum,Phyllocladus aspleniifolius, Pittosporum bicolor, Pomaderris apetala, Pomaderriselliptica, Pomaderris pilifera, Tasmannia lanceolata, Zieria arborescens Integrated Conservation Value Ranking: High Description: High Integrated Conservation Value (ICV). ICV integrates theRepresentative Conservation Value with known Special Values (eg. threatened andpriority species and communities, and priority sites). Special Values
River Report
ID: 179764
Easting: 405763
Northing: 5451938
Conservation Management Priority
Priority: Very High
Description: Very High Conservation Management Priority (CMP). The river sectionis part of a river cluster for which the conservation management is a very highpriority when development is proposed or occurs. This applies in the situationwhere further development occurs within the catchment which may contribute to achange in aquatic ecological condition or status. This CMP was derived byconsidering both its Integrated Conservation Value and land management security(by tenure).
Representative Conservation Value
Ranking: B
Description: B class Representative Conservation Value (RCV). This river sectionis within the second group of sites selected for rivers. Selection is based onrepresentativeness, rarity of classification units and naturalness.
This document has been produced by The Department of Primary Industries, Parks, Water and Environment.
Questions concerning its content may be directed by email to [email protected]
The URL for this page is: http://wrt.tas.gov.au/wist/
Page 2 - CFEV Assessment Component Report
Land Tenure Security Value: Low Description: This river section lies within a catchment that has predominantly lowsecurity of land tenure. There are no formal or mandatory restrictions in placeto ensure that the land within this catchment is managed to conserve or protectthe landscape from potential negative impacts. This includes areas of privateland, unallocated crown land, Commonwealth land, Hydro managed land and areasmanaged by other water authorities.
Name Scientific Name Type Status
burrowingcrayfish(Burnie)
Engaeusyabbimunna
ThreatenedFauna Species
Undifferentiated
platypus Ornithorynchusanatinus
Phylogenetically DistinctFauna Species
Non-outstanding
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 191
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
APPENDIX 14. Risk Assessment Descriptors
Qualitative criteria for likelihood
Qualitative criteria for consequence
The level of risk caused by the previously identified hazard/hazardous events was determined
by combining likelihood and consequence in a matrix as presented below. Risk is calculated
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 192
BURNIE LEACHATE TREATMENT WETLAND
DPEMP
as the product of the likelihood of an event and the consequences of the event if it did occur:
RISK = LIKELIHOOD x CONSEQUENCE.
Risk matrix
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 193
APPENDIX 15. Risk Assessment Evaluation
RISK EVALUATION 1 - discharge of raw leachate
Potential Impact
Hazard / Event Caused By Results In Likelihood Consequence Comments Risk MitigationResidual
Risk
RARE MODERATE LOW ▪ Continual monitoring of leachate levels in
select bores
LOW
Rising leachate levels within
landfill causing saturation and
weakening of containment bund.
Consequence: Consequences of potential impacts to receptors are considered to be moderate , as they are reversible, short to
medium term since only a portion of stored leachate would likely reach the unnamed tributary, and the capacity of the unnamed
tributry (from site boundary to Three Mile Rd) is and as a result of downstream dilution.
▪ Dilution of leachate will occur within the unnamed tributary from continuous groundwater discharge and surface runoff from
neighbouring properties. This creek is already degraded- water quality is relatively poor and the creek is eroded, with limited
riparian vegetation and weeds infestation. Consequently, discharge of leachate in the event of sliding failure of the landfill
embankment is unlikely to cause major additional degradation of the creek ecosystem and/or landscape values.
▪ Confluence of unnamed tributary into Cooee Creek is approximately 4km downstream of landfill. The 'unnamed creek' is one
of many tributaries with a catchment area of only 5.2 km2 (or 5% of the Cooee Creek catchment). Consequently, discharge of
leachate to the unnamed tributary is not expected to cause major impacts on Cooee Creek , key protected species (crayfish),
livestock or recreational users.
RARE MINOR LOW
Exposed solid waste and ponding of
raw leachate on site (impacts on on-
site workers). Potential mosquito risk.
RARE INSIGNIFICANT ▪ Only a very small number of council workers are present on-site. Risk management procedures already exist on site. LOW ▪ Existing risk management plan will be
updated to include responses to incidences
potentially connected with the treatment
system. This will include incidence
response for any on site ponding and
mosquito management. Appropriate training
of all on site personnel will be undertaken.
LOW
2 Raw leachate pump failure Power outage (weather, fire,
explosion etc)
Raw leachate overflow from pump
chamber and discharge into the
unnamed creek
UNLIKELY MINOR LOW ▪ Implement apprpriate equipment checks
and maintenance regimes.
LOW
Pump clogging due to lack of /
poor maintenance
Consequence: The consequence is considered to be minor as only a relatively small volume of raw leachate would potentially
reach the creek (most would likely infiltrate) . The flows that potentially do reach the creek would be further diluted which would
significantly reduce the severity of any environmental impact as discussed under Risk 1 above.
Ponding of raw leachate on site UNLIKELY INSIGNIFICANT As explained for Risk 1, only a very small number of Council workers are present on-site. Risk management procedures already
exist on site and these will be updated to reflect the risks associated with the leachate treatment wetland.
LOW LOW
1 Sliding failure of landfill
containment bund
leading to release of: 1) raw leachate
stored within the landfill cell, 2) raw
and partially treated leachate within
the wetland or 3) solid waste to
ajacent properties.
Wetland mass/location
compromises structural integrity
of landfill bund.
▪ Deterioration of creek water quality, major mass loads of pollutants, major sediment loads, altered creek hydrology.
POTENTIAL RISKS ASSOCIATED WITH THE RELEASE OF RAW LEACHATE AND/OR SOLID WASTE TO CREEK
▪ Negative health impacts on secondary recreational users of the Creek via high level of pathogenic microorganisms, elevated concentrations of metals and organic pollutants
▪ Potential risk of vectors (bird & mosquitoes) infecting livestock and humans with pathogens
Ecological
▪ General public
Human
LOW
Key receptors
▪ Unnamed tributary / Cooee Creek - water quality, ecosystem and landscape
values.
▪ Creek biota incl potential lsited species (Burnie Burrowing crayfish)
▪ Downstream creek water users (livestock, irrigation)
▪ Negative impacts on crayfish habitat in Cooee Creek as a result of poor WQ and increased sedimentation.
▪ Recreational users, irrigation users
▪ On site workers
▪ The Stage 1 landfill potentially has up to 100ML of stored leachate/groundwater below the cap while the wetland contains ~ 9ML
of partially treated leachate in total. In the event of landfill sliding failure, only the portion of raw and treated leachate contained
above the natural valley slope and subject to the lateral failure extent could be 'released' (assuming 1 ha of affected area this
would be ~0.5 ML of wetland partially treated leachate and ~5ML of stored raw leachate). The release will not be instantaneous
(it will be seep from the solid waste and clays) and will mainly be contained on site. Any seepage or leachate overflows will be
captured frst in the phytoremediation swale, which directs leachate in excess of the swale capacity to the emergency storage
where it can be pumped direct to sewer. Any flows not captured could discharge into the creek however there is significant
capacity (~2.5 ML storage from unnamed tributary to the Three Mile Rd culvert, Entura 2011), and there would be more than
sufficient time to temporarily dam this section of the creek and pump to waste.
Likelihood: It is assumed that issues with pump failure may occur from time to time due to power failure or inappropriate pump
maintenance, however there are sufficient contingencies in place to limit discharge to the creek. This includes a duty and standby
pump with generator back-up, gravity emergency storage system (6-10 hrs) which should enable adequate response time, and a
connection to sewer if this storage reaches capacity. A breach could only occur if the fleachate flow rates exceeded sewer
capacity (e.g. extreme rain events). Note, the proposed treatment system will not increase the inherent risk profile (will be reduced
due to gravitational emergency storage and sewer connection structures).
▪ Degradation of ecosystem and landscape values within the Unnamed Creek and/or Cooee Creek; erosion, weed infestation, .
▪ Potentially negative health impacts on livestock, poor WQ prohibits pasture irrigation
▪ Potential direct exposure of on-site workers to contaminants in exposed solid waste and/or raw leachate
▪ The site topography and available areas indicate that solid waste would be predominantly contained within the site. Given the
very localised nature of potential environmental impacts (immediate neighbouring properties only) the consequence was
considered to be minor.
Likelihood: Based on the Geotechnical Study , the likelihood of sliding failure of the landfill containment bund is very rare given
the Factor of Safety (FOS) for a non-leaking wetland is higher than 4, while the FOS for the present landfill containment bund is
assessed to be at least 4.5 (recommended FOS is 1.5). Based on the calculated FOS, placing the wetlands at least 10m from
the crest will not adversely impact on the stability of the containment bund wall.
Solid landfill waste spills to adjacent
propert/ies
Raw leachate discharging to the
unnamed tributary and possibly Cooee
Creek
Further erosion of landfill embankment
due to water spillages potentially
creating channels over embankment
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 194
RISK EVALUATION 2 - discharge of partially treated leachate
Potential Impact
Hazard / Event Causes Result Likelihood Consequence Comments Risk MitigationResidual
Risk
1 Leakage of the wetland treatment
system
UNLIKELY MINOR Likelihood: It is considered unlikely that wetland seepage will not cause impacts given the following: LOW LOW
▪ Any localised seepage through the wetland liner and leachate migration through landfill would be retarded by the existing
underlying GCM or compacted clay liner.
Impairment of wetland performance due
to need for repairs.
▪ Wetland liners (GCL and HDPE) can accommodate large settlement. Liner (HDPE) accommodates a tensile strain of 1-10%,
hence can tolerate differential settlements of at least 450mm without breakage. Bunds have sufficient freeboard t accomodate
settlement.
Consequence: The consequence of any potential impacts are considered minor given the following:
▪ Seepage rate through compacted landfill clay cap is about 1% of typical daily flow rate from groundwater drainage system, so
additional flows due to seepage would be minimal . Due to these low flows, lateral seepage would be mostly contained on site
as a wet spot around the wetland. All ponded leachate would be partially treated further reducing the severity of any impacts to
on-site workers.
▪ System has a phytoremediation swale along the northern embankment which intercepts and treats seepage events if they
occur.
▪ Wetland cells can be individually isolated/bypassed for repair if required, without impacting performance of rest of wetland
▪ Any localised breakages in the wetland liner &/or bund settlements are easily repaired.
Likelihood: It is considered rare for this event to occur because settlement is unlikely to cause more than a localised effect and
because wetland volumes are small and if spill over the landfill banks will be contained within the phytoremediation swale and
emergency storage.
LOW ▪ Annual surveys of wetland bunds to track
changes.
LOW
Consequence: Considered to be minor since:
Ponding of the leachate on site,
potential direct exposure of on site
workers and potential mosquito issues.
▪ Released leachate will be partially (e.g. ammonia) or fully (metals and organics) treated for key pollutants.
▪ Spills will be intercepted by the phytoremediation swale along the northern embankment with excess captured within the
infiltration wetland.
▪ Treated leachate that does discharge into the unnamed tributary will be diluted as a result of continuous groundwater and
surface water discharge to creek.
▪ Any on site ponding of treated leachate will be localised, short term and appropriately managed under normal management
regimes on site. Given the relatively good quality of treated leachate , any direct exposure of on site workers is not expected to
cause any significant issues.
▪ Recreational users, irrigation users
b) Lateral seepage through the
wetland bund onto the clay capping.
▪ Creek biota incl potential lsited species (Burnie Burrowing crayfish)
2 Failure of wetland embankments Differential settlement of landfill
leading to localised subsidence
of wetland cell bunds and
overtopping of leachate.
▪ General public
▪ On site workers
Differential settlement of landfill
cap potentially impacting liner
integrity and/or overtopping from
wetland bunds. a) Seepage through the clay liner
base into the existing clay capping
POTENTIAL RISKS ASSOCIATED WITH THE RELEASE OF PARTIALLY AND/OR INADEQUATELY TREATED LEACHATE TO CREEK
Key receptors
▪ Unnamed tributary / Cooee Creek - water quality, ecosystem and landscape
values. ▪ Deterioration of creek water quality, increase in pollutants mass loading, sediment loads, altered creek hydrology.
Ecological
▪ Negative impacts on crayfish population in Cooee Creek as a result of poor WQ and increased sedimentation.
▪ Downstream creek water users (livestock, irrigation) ▪Impacts on the ecosystem and landscape values within the Unnamed Creek and/or Cooee Creek; erosion.
Human ▪ Potentially negative health impacts of minor WQ deterioration on livestock and pasture irrigation
▪ Potential risk of vectors (bird & mosquitoes) infecting livestock and humans with pathogens
▪ Potential direct exposure of on-site workers to contaminants in partially treated leachate
▪ Negative health impacts on secondary recreational users of the Creek via increased level of pathogenic microorganisms, elevated concentrations of metals and organic pollutants
Lateral seepage through landfill
containment bund resulting in
discharge of leachate to the
environment
▪ Existing risk management procedures will
be amended to include management of this
risk.
MINOR
▪ Only a small volume of leachate will potentially be discharged to the creek. Wetland volumetric capacity is approximately 9ML
, and in a case of embankment failure only a very small portion of this volume (depending on the scale of failure across the
system) will be released over the containment bund (likely <1 ML)
Partially treated leachate being
discharged directly over landfill
containment bund and disharging to
the creek.▪ Existing risk management plan will be
updated to include responses to incidences
potentially connected with the treatment
system. This will include incidence
response for any on site ponding and
mosquito management. Appropriate training
of all on site personnel will be undertaken.
RARE
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 195
RISK EVALUATION 2 - discharge of partially treated leachate cont.
Potential Impact
Hazard / Event Causes Result Likelihood Consequence Comments Risk MitigationResidual
Risk
1. Not built to design Quality of the final effluent non-
compliant with set performance
targets.
POSSIBLE MODERATE ▪ Any deviation to design will be corrected before practical completion and commissioning of the system. MEDIUM LOW
Discharge of effluent of inadequate
quality to the creek.
Ponding of partially treated effluent on
site.
▪ Performance monitoring will be conducted
through the system to enable adaptive
response and to trigger emergency
recirculation or disposal to sewer
2. Cold weather (biological
performance compromised)
UNLIKELY MINOR ▪ System has been conservatively designed and modelled using site specific temperature data and conservative removal
coefficients for various pollutants. Many contingencies are included within the system design to accommodate reduced
performance without impacting on the quality of the final effluent.
LOW LOW
3. Change in leachate chemistry
beyond design ranges for
prolonged period of time
UNLIKELY MINOR ▪ Leachate is already in maturation phase so large fluctutaions extremely unlikely. Conservative wetland sizing has been
considered in the design.
▪ Wetland design is based on 5 years of site specific leachate quality data which shows stable conditions and on well
established leachate treatment wetland performance data (international literature).
LOW LOW
4. Contaminated via pesticides,
herbicides etc (weed
management - neighbouring
farms) that can cause
plant/microbial death, and
consequently reduced system
performance
UNLIKELY MINOR ▪ Wetlands are known to deal well with and degrade most of the currently used pesticides (Kadlec & Wallace, 2008).
Herbicide damage likely to be minor - wetland plants have high resilience and recover well from spray drift.
LOW LOW
5. Poor maintenance LIKELY MODERATE ▪ Wetlands are robust systems. Each wetland cells can be isolated/ bypassed for repair if needed, without impacting others. MEDIUM ▪ Appropriate maintenance budget will be
include in OPEX for the life of the wetland.
LOW
▪ Performance monitoring/maintenance
activities will be conducted through the
system to enable adaptive response and to
trigger emergency recirculation or disposal
to sewer.
▪ Appropriate training of staff responsible for
system maintenance will be undertaken,
including preparation of user-friendly
management and maintenance plans.
4 Extreme, prolonged rainfall
events
Discharge of inadequately treated
leachate to the Creek.
UNLIKELY MINOR Likelihood: It is considered unlikely that this event will occur and cause impact on key receptors given the following: LOW LOW
▪ Conservative sizing of system to accommodate the 90 percentile flows in the treatment process, ability to contain and enable
treatment via recirculation of up to 1500kL/day (20-year event peak flows), and ability to discharge to sewer.
▪ Project improves the current risk profile by separation of stormwater and leachate.
▪ Treatment system is operated on a maximum inflow rate ensurig consistency of treatment performance - flows in excess of this
are contained in the emergency overflow tank flow and in worst case discharged to sewer.
Consequence: Given all the safeguards in place, if this event does occur it would involve a discharge of only very small volumes
of partially treated leachate from the system. This is considered to potentially create only minor issues due to a major dilution
within the unnamed tributary (which would be especially high in those prolonged high rain event) and the fact that effects would
not be long term.
3 Failure or impeded performance
of wetland compromising the quality
of leachate outflow
▪ Recreational users, irrigation users
▪ Creek biota incl potential lsited species (Burnie Burrowing crayfish)
▪ General public
▪ On site workers
POTENTIAL RISKS ASSOCIATED WITH THE RELEASE OF PARTIALLY AND/OR INADEQUATELY TREATED LEACHATE TO CREEK
Key receptors
Volumes of groundwater-leachate
cannot be accommodated in the
collection/conveyance
network, or treatment system.
▪ Unnamed tributary / Cooee Creek - water quality, ecosystem and landscape
values. ▪ Deterioration of creek water quality, increase in pollutants mass loading, sediment loads, altered creek hydrology.
Ecological
▪ Negative impacts on crayfish population in Cooee Creek as a result of poor WQ and increased sedimentation.
▪ Downstream creek water users (livestock, irrigation) ▪Impacts on the ecosystem and landscape values within the Unnamed Creek and/or Cooee Creek; erosion.
Human ▪ Potentially negative health impacts of minor WQ deterioration on livestock and pasture irrigation
▪ Potential risk of vectors (bird & mosquitoes) infecting livestock and humans with pathogens
▪ Potential direct exposure of on-site workers to contaminants in partially treated leachate
▪ Negative health impacts on secondary recreational users of the Creek via increased level of pathogenic microorganisms, elevated concentrations of metals and organic pollutants
▪ The proposed system includes two safe guards to prevent discharge of inadequately treated final effluent: a) A recirculation line
that ensures non-compliant effluent is recycled through the treatment train before discharge; b) A contingency connection to
sewer.
▪ Design approach based on the sequential treatment train, multiple treatment cells, and conservative removal coefficients ensure
that any temporary failure of individual cells to perform properly will be compensated by the rest of the system without jeopardising
the overall system performance.
▪ Performance monitoring will be conducted
through the system to enable adaptive
response and to trigger emergency
recirculation or disposal to sewer
▪ Wetland designer will be retained during
construction / contract management
phases (e.g. superintendency) to ensure
that all system components and safeguard
management elements are constructed as
per design.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 196
RISK EVALUATION 2 - discharge of partially treated leachate cont.
Potential Impact
Hazard / Event Causes Result Likelihood Consequence Comments Risk MitigationResidual
Risk
5 RARE MINOR Likelihood: The hydrological study (Tasman Geotechnics Aug 2015) indicated that a rain event causing erosion and landslide
would be extremely rare (>1,000 years). While inappropriate irrigation activities could somewhat impact on this, the event would
still be classified as rare.
LOW LOW
Consequence: The consequence of this event is considered minor given the multiple contingencies in place and that this would
be localised to only a portion of the wetland system.
6 Vandalism 1. Exposed pipework connecting and
within wetland cells destroyed resulting
in leachate leakage.
UNLIKELY MINOR ▪ Most pipes will be buried and hence will not be damaged by fire. Exposed pipes if destroyed will not cause wetland operation to
cease. Any leakage (or any damage) can be easily and quickly localised and cells by passed. Site is fenced with access controls
in place to prevent unauthorside access.
LOW Unauthorised access control to wetland area LOW
Lightening 2. Plants burnt impacting system
performance.
POSSIBLE INSIGNIFICANT ▪ Most wetland plants are resistant to fire and will regrow rapidly after fire. Burning will not impact on the key removal
mechanisms by rhizosphere/soil microorganisms. Plant regrowth will enhance pollutant removal (a high rate of nutrient uptake
occurs after burning).
LOW Install lightening / short circuiting/ electrical
protection to pumps.
LOW
Electrical faults 3.Wetland bund liner melted causing
leachate leakage.
UNLIKELY MINOR ▪ Impervious HDPE liners will be buried and hence will not be exposed to above ground fire. LOW LOW
Fire within wetland system causing
physical damage to the system and
its components
▪ Recreational users, irrigation users
▪ Creek biota incl potential lsited species (Burnie Burrowing crayfish)
▪ General public
▪ On site workers
POTENTIAL RISKS ASSOCIATED WITH THE RELEASE OF PARTIALLY AND/OR INADEQUATELY TREATED LEACHATE TO CREEK
Key receptors
▪ Unnamed tributary / Cooee Creek - water quality, ecosystem and landscape
values. ▪ Deterioration of creek water quality, increase in pollutants mass loading, sediment loads, altered creek hydrology.
Ecological
▪ Negative impacts on crayfish population in Cooee Creek as a result of poor WQ and increased sedimentation.
▪ Downstream creek water users (livestock, irrigation) ▪Impacts on the ecosystem and landscape values within the Unnamed Creek and/or Cooee Creek; erosion.
Human ▪ Potentially negative health impacts of minor WQ deterioration on livestock and pasture irrigation
▪ Potential risk of vectors (bird & mosquitoes) infecting livestock and humans with pathogens
▪ Potential direct exposure of on-site workers to contaminants in partially treated leachate
▪ Negative health impacts on secondary recreational users of the Creek via increased level of pathogenic microorganisms, elevated concentrations of metals and organic pollutants
Flooding from adjacent property
upgradient (east) of landfill land and
material transport directly onto the
wetlands system.
Extreme weather and flooding
exacerbated by excessive
irrigation, soil creep, and farming
activities.
Physical damage of the treatment
system, compromised structures, and
reduced treatment performance
resulting in discharge of effluent of
inadequate quality.
BWMC Stage 1 Leachate Treatment System DPEMP November 2015 197
RISK EVALUATION 3 - normal operation
Potential Impact
Hazard / Event Causes Result Likelihood Consequence Comments Risk Mitigation MeasuresResidual
Risk
1 Normal operation of the proposed
on site treatment system
UNLIKELY INSIGNIFICANT It is considered unlikely that discharge of appropriately treated effluent from the treatment wetland will cause any significant
detrimental impacts on the receiving creek(s) and downstream users given the following:
LOW LOW
▪ Very high quality of treated effluent: Final effluent will be treated to a high standard prior to any discharge - water quality targets
for key contaminants of concern are in line with EPA Draft Water Quality Objectives for Cooee Creek and ANZECC (2000)
Aquatic Ecosystems - 95% level of protection, ANZECC (2000) recreational - secondary contact & ANZECC(2000) Primary
industry - short term irrigation and livestock drinking.
▪ Direct discharge of treated leachate (and mass loading to the creek) will be minimised through maximising on-site infiltration
within the last system’s cell (Cell 5 – Infiltration Wetland / Wet Forest). It is expected that most of the treated leachate ( 91% of
summer-autumn flows, and 78% of winter-spring flows) will discharge indirectly via subsurface infiltration to the Creek, utilising
land along the northern embankment within the landfill site boundary. Only during high rainfall events, flows in excess of the
infiltration capacity of the Infiltration Wetland would overflow directly to the Creek via a weir/cascade.
▪ Relatively poor condition of the unnamed tributary and Cooee Creek due to historic and current impacts from the landfill and
adjacent rural properties and residential developments. The unnamed tributary (for up to 3 km downstream of the landfill site) is
considered to be degraded, with relatively poor water quality and evidence of erosion, high weed extent, stock impacts and
limited riparian vegetation. In terms of water quality the Creek system is classed as ANZECC Ecosystem Condition 2: Slightly to
moderately disturbed systems and Ecosystem Condition 3: Highly disturbed system. based on the ANZECC (2000).
Consequently, discharge of highly treated effluent that is of much better quality than either of the creeks is unlikely to jeopardise
the quality of these surface waters. In terms of pollutant load, calculated annual loads of pollutants likely to be directly discharged
to the creek in storm events are relatively low - TSS<4 kg, TN, 17 kg, TP , 0.2 kg, Fe, 8 kg, Mn,5.4 kg. These mass loads are
considered small overall and lower than what probably occurs typically at the site, both as a result of discharges directly to the
Creek when flows exceed the 20 year ARI capacity of the pipe, pump and pit infrastructure, and also due to short duration storm
events which exceed the pump capacity and result in overflows from the MH1 chamber to the Creek. The potential impacts of
these pollutant loads are considered even less significant considering continual inputs from neighbouring properties.
▪ Discharge to the creek would help re-establish pre-development flows, since at present a substantial proportion of leachate
and groundwater (entrained within the leachate) flows is diverted to sewer. Hence, increasing the environmental flows, particularly
given climate predictions of declining rainfall, would be a beneficial outcome of the proposed treatment system.
▪ Unnamed creek is not used for recreation and this is unlikely to change in the future given declining water levels and many
alternative locations.
▪ Creek biota incl potential lsited species (Burnie Burrowing crayfish) ▪ Negative impacts on crayfish population in Cooee Creek as a result of lower WQ and increased sedimentation.
▪ Downstream creek water users (livestock, irrigation)
POTENTIAL RISKS ASSOCIATED WITH THE RELEASE OF FULLY TREATED LEACHATE TO THE CREEK
Key receptors
Ecological
▪ Unnamed tributary / Cooee Creek - water quality, ecosystem and landscape
values. ▪ Deterioration of creek water quality, increase in pollutant mass loadings, creek sedimentation , changes in creek hydrology.
▪ Degradation of ecosystem and landscape values within the Unnamed Creek and/or Cooee Creek; erosion, weed infestation, .
Discharge of treated effluent causing
1) degradation of the unnamed tributary
and Cooee Creek (WQ, ecosystem &
landscape values), and/or 2. negative
impacts on creek recreational users
and/or other downstream users
(irrigation, livestock drinking)
Human ▪ Potentially negative health impacts on livestock and negative impacts on pasture irrigation
▪ Recreational users, irrigation users ▪ Negative health impacts on secondary recreational users of the Creek via high level of pathogenic microorganisms, elevated concentrations of metals and organic pollutants
▪ General public ▪ Potential risk of vectors (bird & mosquitoes) infecting livestock and humans with pathogens
Discharge of treated effluent from the
on site treatment wetland compliant
with current discharge standards
(ANZECC etc)
▪ On site workers ▪ Potential direct exposure of on-site workers to treated leachate.