development of eq-1a berth at …vizagport.com/tendersfiles/ppp progress/ppp29102014/vpt-eq-1a...

4
ID WBS Task Name Duration Start Finish 1 1 Development of Coal Terminal - EQ1A Berth Expansion at VPT 1643 days Fri 3/18/11 Wed 9/16/15 2 1.1 Concession Agreement 862 days Fri 3/18/11 Sat 7/27/13 16 1.2 Consultants & Contractors 1474 days Fri 3/18/11 Tue 3/31/15 31 1.3 Financial Closure 416 days Sat 2/4/12 Tue 3/26/13 37 1.4 EPC Preliminaries and Administrative Costs 1141 days Wed 8/1/12 Wed 9/16/15 38 1.4.1 EPC Management/Supervision Cost 1141 days Wed 8/1/12 Wed 9/16/15 39 1.4.2 Indirect Costs At Head Office 1141 days Wed 8/1/12 Wed 9/16/15 40 1.4.3 Progress Reports & Photographs 1141 days Wed 8/1/12 Wed 9/16/15 41 1.4.4 Transportation 1141 days Wed 8/1/12 Wed 9/16/15 42 1.4.5 LC Opening Charges for BMH Equipment 954 days Mon 2/4/13 Wed 9/16/15 43 1.5 Design & Engineering 1376 days Sat 7/9/11 Wed 4/15/15 44 1.5.1 Design & Engineering: Site Investigation 487 days Sat 7/9/11 Wed 11/7/12 71 1.5.2 Detailed Engineering: Civil 771 days Mon 10/1/12 Tue 11/11/14 72 1.5.2.1 DE Civil: Return End wall 72 days Mon 10/1/12 Wed 12/12/12 77 1.5.2.2 DE Civil: Berth 399 days Sat 12/1/12 Sat 1/4/14 82 1.5.2.3 DE Civil: Stacking Yard 405 days Sat 12/1/12 Fri 1/10/14 87 1.5.2.4 DE Civil: Transfer towers 697 days Sat 12/1/12 Wed 10/29/14 92 1.5.2.5 DE Civil: Building - Admin, Sub-Station 697 days Sat 12/1/12 Wed 10/29/14 97 1.5.2.6 DE Civil: Tippler station 696 days Sat 12/1/12 Tue 10/28/14 102 1.5.2.7 DE Civil: BOQ 710 days Sat 12/1/12 Tue 11/11/14 106 1.5.3 Detailed Engineering: Mechanical 928 days Wed 5/16/12 Sun 11/30/14 107 1.5.3.1 DE Mechanical: Ship loader 881 days Wed 5/16/12 Tue 10/14/14 112 1.5.3.2 DE Mechanical: Conveyor systems 730 days Mon 10/1/12 Wed 10/1/14 117 1.5.3.3 DE Mechanical: Wagon tippler 920 days Wed 5/16/12 Sat 11/22/14 122 1.5.3.4 DE Mechanical: Stacker Reclaimer 900 days Wed 5/16/12 Sun 11/2/14 127 1.5.3.5 DE Mechanical: Transfer towers 480 days Mon 7/1/13 Fri 10/24/14 132 1.5.3.6 DE Mechanical: Sprinkling system 500 days Tue 7/9/13 Fri 11/21/14 137 1.5.3.7 DE Mechanical: BOQ 734 days Mon 11/26/12 Sun 11/30/14 141 1.5.4 Detailed Engineering: Utilities 626 days Fri 3/8/13 Mon 11/24/14 142 1.5.4.1 DE Utilities: Fire fighting system 617 days Fri 3/8/13 Sat 11/15/14 146 1.5.4.2 DE Utilities: Electrical System(HT/LT/ELT) 600 days Fri 3/8/13 Wed 10/29/14 150 1.5.4.3 DE Utilities: Internal Roads 357 days Fri 3/8/13 Fri 2/28/14 154 1.5.4.4 DE Utilities: Drainage 297 days Fri 3/8/13 Mon 12/30/13 3/18 9/16 3/18 10/24 0 days 158 days 46 days 327 days 371 days 16 days 656 days 193 days 393 days 381 days 673 days 673 days 812 days 656 days 666 days 799 days 716 days 810 days 808 days 678 days 725 days 666 days 446 days 575 days 590 days 297 days 221 days H2 '10 H1 '11 H2 '11 H1 '12 H2 '12 H1 '13 H2 '13 H1 '14 H2 '14 H1 '15 H2 '15 H1 '16 2011 2012 2013 2014 2015 2016 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Baseline Baseline Milestone Baseline Summary Progress DEVELOPMENT OF EQ-1A BERTH AT VISAKHAPATNAM PORT Page 1 Project: Development of EQ-1A Berth at Visakhapatnam Port Date: 03/03/14

Upload: doanliem

Post on 23-Apr-2018

218 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: DEVELOPMENT OF EQ-1A BERTH AT …vizagport.com/Tendersfiles/PPP Progress/PPP29102014/VPT-EQ-1A MS… · 1 1 Development of Coal Terminal - EQ1A Berth Expansion at VPT 1643 days Fri

ID WBS Task Name Duration Start Finish

1 1 Development of Coal Terminal - EQ1A Berth Expansion at VPT

1643 days Fri 3/18/11 Wed 9/16/15

2 1.1 Concession Agreement 862 days Fri 3/18/11 Sat 7/27/13

16 1.2 Consultants & Contractors 1474 days Fri 3/18/11 Tue 3/31/15

31 1.3 Financial Closure 416 days Sat 2/4/12 Tue 3/26/13

37 1.4 EPC Preliminaries and Administrative Costs

1141 days Wed 8/1/12 Wed 9/16/15

38 1.4.1 EPC Management/Supervision Cost 1141 days Wed 8/1/12 Wed 9/16/15

39 1.4.2 Indirect Costs At Head Office 1141 days Wed 8/1/12 Wed 9/16/15

40 1.4.3 Progress Reports & Photographs 1141 days Wed 8/1/12 Wed 9/16/15

41 1.4.4 Transportation 1141 days Wed 8/1/12 Wed 9/16/15

42 1.4.5 LC Opening Charges for BMH Equipment

954 days Mon 2/4/13 Wed 9/16/15

43 1.5 Design & Engineering 1376 days Sat 7/9/11 Wed 4/15/15

44 1.5.1 Design & Engineering: Site Investigation

487 days Sat 7/9/11 Wed 11/7/12

71 1.5.2 Detailed Engineering: Civil 771 days Mon 10/1/12 Tue 11/11/14

72 1.5.2.1 DE Civil: Return End wall 72 days Mon 10/1/12 Wed 12/12/12

77 1.5.2.2 DE Civil: Berth 399 days Sat 12/1/12 Sat 1/4/14

82 1.5.2.3 DE Civil: Stacking Yard 405 days Sat 12/1/12 Fri 1/10/14

87 1.5.2.4 DE Civil: Transfer towers 697 days Sat 12/1/12 Wed 10/29/14

92 1.5.2.5 DE Civil: Building - Admin, Sub-Station

697 days Sat 12/1/12 Wed 10/29/14

97 1.5.2.6 DE Civil: Tippler station 696 days Sat 12/1/12 Tue 10/28/14

102 1.5.2.7 DE Civil: BOQ 710 days Sat 12/1/12 Tue 11/11/14

106 1.5.3 Detailed Engineering: Mechanical 928 days Wed 5/16/12 Sun 11/30/14

107 1.5.3.1 DE Mechanical: Ship loader 881 days Wed 5/16/12 Tue 10/14/14

112 1.5.3.2 DE Mechanical: Conveyor systems

730 days Mon 10/1/12 Wed 10/1/14

117 1.5.3.3 DE Mechanical: Wagon tippler 920 days Wed 5/16/12 Sat 11/22/14

122 1.5.3.4 DE Mechanical: Stacker Reclaimer

900 days Wed 5/16/12 Sun 11/2/14

127 1.5.3.5 DE Mechanical: Transfer towers

480 days Mon 7/1/13 Fri 10/24/14

132 1.5.3.6 DE Mechanical: Sprinkling system

500 days Tue 7/9/13 Fri 11/21/14

137 1.5.3.7 DE Mechanical: BOQ 734 days Mon 11/26/12 Sun 11/30/14

141 1.5.4 Detailed Engineering: Utilities 626 days Fri 3/8/13 Mon 11/24/14

142 1.5.4.1 DE Utilities: Fire fighting system

617 days Fri 3/8/13 Sat 11/15/14

146 1.5.4.2 DE Utilities: Electrical System(HT/LT/ELT)

600 days Fri 3/8/13 Wed 10/29/14

150 1.5.4.3 DE Utilities: Internal Roads 357 days Fri 3/8/13 Fri 2/28/14

154 1.5.4.4 DE Utilities: Drainage 297 days Fri 3/8/13 Mon 12/30/13

3/18 9/163/18 10/24

0 days

158 days

46 days

327 days

371 days

16 days

656 days

193 days

393 days

381 days

673 days

673 days

812 days

656 days

666 days

799 days

716 days

810 days

808 days

678 days

725 days

666 days

446 days

575 days

590 days

297 days

221 days

H2 '10 H1 '11 H2 '11 H1 '12 H2 '12 H1 '13 H2 '13 H1 '14 H2 '14 H1 '15 H2 '15 H1 '16 H2 '162010 2011 2012 2013 2014 2015 2016

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Critical

Critical Split

Baseline

Baseline Milestone

Baseline Summary

Progress

DEVELOPMENT OF EQ-1A BERTH AT VISAKHAPATNAM PORT

Page 1

Project: Development of EQ-1A Berth at Visakhapatnam PortDate: 03/03/14

Page 2: DEVELOPMENT OF EQ-1A BERTH AT …vizagport.com/Tendersfiles/PPP Progress/PPP29102014/VPT-EQ-1A MS… · 1 1 Development of Coal Terminal - EQ1A Berth Expansion at VPT 1643 days Fri

ID WBS Task Name Duration Start Finish

158 1.5.4.5 DE Utilities: Water System 617 days Fri 3/8/13 Sat 11/15/14

162 1.5.4.6 DE Utilities: Land scaping/Green belt

357 days Fri 3/8/13 Fri 2/28/14

166 1.5.4.7 DE Utilities: BOQ 596 days Sun 4/7/13 Mon 11/24/14

170 1.5.5 Detailed Engineering: Railways 590 days Sat 3/2/13 Mon 10/13/14

171 1.5.5.1 DE Railways: Alignment 363 days Sat 3/2/13 Fri 2/28/14

175 1.5.5.2 DE Railways: Turn out Scheme 363 days Sat 3/2/13 Fri 2/28/14

179 1.5.5.3 DE Railways: Layout 363 days Sat 3/2/13 Fri 2/28/14

183 1.5.5.4 DE Railways: Tracks 363 days Sat 3/2/13 Fri 2/28/14

187 1.5.5.5 DE Railways: S & T 363 days Sat 3/2/13 Fri 2/28/14

191 1.5.5.6 DE Railways: Approvals 580 days Sat 3/2/13 Fri 10/3/14

195 1.5.5.7 DE Railways: BOQ 580 days Tue 3/12/13 Mon 10/13/14

199 1.5.6 Approvals & Clearances 1261 days Tue 11/1/11 Wed 4/15/15

200 1.5.6.1 CFE (APPCB) 163 days Tue 11/1/11 Thu 4/12/12

205 1.5.6.2 Port Estate Plan Approval 124 days Thu 5/17/12 Tue 9/18/12

209 1.5.6.3 AP Transco 59 days Sun 2/15/15 Wed 4/15/15

213 1.5.6.4 GVMC - Water Supply 75 days Sun 8/17/14 Fri 10/31/14

217 1.5.6.5 Fire Safety 88 days Sun 8/17/14 Thu 11/13/14

221 1.5.6.6 Marine clearance 60 days Thu 12/13/12 Mon 2/11/13

226 1.6 Procurement: Material Handling Systems

1009 days Tue 8/14/12 Wed 5/20/15

227 1.6.1 Procure: Mechanical Systems 804 days Tue 8/14/12 Mon 10/27/14

234 1.6.2 Procure: Electrical Systems 561 days Tue 3/26/13 Wed 10/8/14

242 1.6.3 Procure: Fire Fighting 178 days Thu 7/31/14 Sun 1/25/15

249 1.6.4 Procure: Railways 234 days Sun 9/28/14 Wed 5/20/15

257 1.6.5 Procure: Berth fixtures 403.3 daysSun 12/1/13 Thu 1/8/15

265 1.7 Construction 1140 days Thu 8/2/12 Wed 9/16/15

266 1.7.1 EPC Preliminaries and Administrative Costs

1110 days Sat 9/1/12 Wed 9/16/15

267 1.7.1.1 Guest House Accommodaion 1110 days Sat 9/1/12 Wed 9/16/15

268 1.7.1.2 Vehicles, Transportation etc 1110 days Sat 9/1/12 Wed 9/16/15

269 1.7.1.3 Progress Reports & Photographs 1110 days Sat 9/1/12 Wed 9/16/15

270 1.7.1.4 Ward and Watch 1110 days Sat 9/1/12 Wed 9/16/15

271 1.7.1.5 Safey and Training 1110 days Sat 9/1/12 Wed 9/16/15

272 1.7.1.6 Tools, Equipment and Machinery 1110 days Sat 9/1/12 Wed 9/16/15

273 1.7.1.7 Site Office Maintenance 1110 days Sat 9/1/12 Wed 9/16/15

274 1.7.2 Establishment of Site Office, P&MYard, Lab, Sores, PC Yard, Utilities

406 days Thu 8/2/12 Thu 9/12/13

275 1.7.2.1 Establishment of Site Offices 406 days Thu 8/2/12 Thu 9/12/13

282 1.7.2.2 Establishment of P&M yard 41 days Wed 9/5/12 Tue 10/16/12

290 1.7.2.3 Establishment of Laboratory 26 days Sat 12/15/12 Thu 1/10/13

296 1.7.2.4 Establishment of Stores 84 days Thu 8/2/12 Thu 10/25/12

541 days

316 days

446 days

377 days

305 days

267 days

328 days

293 days

220 days

493 days

377 days

634 days

-47 days

0 days

698 days

468 days

486 days

0 days

406 days

280 days

310 days

436 days

406 days

612.3 days

327 days

327 days

0 days

0 days

-3 days

-37 days

29 days

H2 '10 H1 '11 H2 '11 H1 '12 H2 '12 H1 '13 H2 '13 H1 '14 H2 '14 H1 '15 H2 '15 H1 '16 H2 '162010 2011 2012 2013 2014 2015 2016

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Critical

Critical Split

Baseline

Baseline Milestone

Baseline Summary

Progress

DEVELOPMENT OF EQ-1A BERTH AT VISAKHAPATNAM PORT

Page 2

Project: Development of EQ-1A Berth at Visakhapatnam PortDate: 03/03/14

Page 3: DEVELOPMENT OF EQ-1A BERTH AT …vizagport.com/Tendersfiles/PPP Progress/PPP29102014/VPT-EQ-1A MS… · 1 1 Development of Coal Terminal - EQ1A Berth Expansion at VPT 1643 days Fri

ID WBS Task Name Duration Start Finish

300 1.7.2.5 Establishment of precast Yard 35 days Tue 12/18/12 Tue 1/22/13

305 1.7.2.6 Establishment of utilities 133 days Tue 10/16/12 Tue 2/26/13

313 1.7.2.7 Site Safey: Sign Board, Safey Board & Hording, etc

367 days Sat 9/8/12 Tue 9/10/13

315 1.7.3 Site Development Activities 337.04 days

Sat 9/1/12 Sun 8/4/13

316 1.7.3.1 Site Grading 45 days Sat 9/1/12 Tue 10/16/12

322 1.7.3.2 Area Fencing & Lighting 280.04 days

Sun 10/28/12 Sun 8/4/13

327 1.7.3.3 Traffic Diversions 32 days Thu 11/1/12 Mon 12/3/12

330 1.7.4 Selective Demolition 817 days Sun 11/25/12 Fri 2/20/15

331 1.7.4.1 Demo: Boat Basin Jetty 194 days Sun 11/25/12 Fri 6/7/13

338 1.7.4.2 Demo: Tug tie-up Jetty 173 days Sun 8/31/14 Fri 2/20/15

345 1.7.4.3 Demo: Old M F jetty 109 days Mon 9/1/14 Fri 12/19/14

352 1.7.4.4 Demo: NEW M F Jetty 109 days Sat 11/1/14 Wed 2/18/15

359 1.7.4.5 Demo: Lunch&Store room 73 days Mon 12/17/12 Thu 2/28/13

366 1.7.4.6 Demo: Scooter shed 64 days Mon 12/17/12 Tue 2/19/13

373 1.7.4.7 Demo: SMS (OH) office & buildings, sheds etc

64 days Sat 4/27/13 Sun 6/30/13

380 1.7.5 Civil Structures 1002 days Thu 11/1/12 Fri 7/31/15

381 1.7.5.1 Return end wall 348 days Thu 11/1/12 Tue 10/15/13

390 1.7.5.2 Berth with diaphragm wall 821 days Wed 5/1/13 Fri 7/31/15

398 1.7.5.3 Ground improvement at stock yard

812 days Wed 1/23/13 Wed 4/15/15

403 1.7.5.4 Stacker reclaimer foundation 692 days Thu 5/9/13 Wed 4/1/15

412 1.7.5.5 Wagon tippler house 556 days Fri 8/16/13 Mon 2/23/15

426 1.7.5.6 Transfer tower houses 138 days Wed 10/29/14 Mon 3/16/15

434 1.7.5.7 Dump ponds 467 days Thu 10/24/13 Tue 2/3/15

441 1.7.5.8 Sub station 166 days Mon 9/15/14 Sat 2/28/15

450 1.7.5.9 Conveyor foundations 92 days Mon 11/17/14 Tue 2/17/15

457 1.7.5.10 MCC building 202 days Mon 9/15/14 Sun 4/5/15

466 1.7.5.11 Administrative Building Construcion

202 days Mon 9/15/14 Sun 4/5/15

468 1.7.5.12 Maintenance Yard Construction 202 days Mon 9/15/14 Sun 4/5/15

470 1.7.6 Mechanical Structures 372 days Fri 8/15/14 Sat 8/22/15

471 1.7.6.1 Ship loader fabrication 273 days Fri 8/15/14 Fri 5/15/15

476 1.7.6.2 Ship loader erection 222 days Mon 1/12/15 Sat 8/22/15

480 1.7.6.3 Stacker reclaimer fabrication 180 days Wed 9/3/14 Mon 3/2/15

484 1.7.6.4 Stacker reclaimer erection 236 days Tue 12/2/14 Sun 7/26/15

489 1.7.6.5 Conveyer structural steel fabrication

141 days Wed 10/1/14 Thu 2/19/15

493 1.7.6.6 Conveyer structural steel erection

165 days Sun 2/1/15 Thu 7/16/15

-37 days

-37 days

0 days

-9.96 days

-10 days

-9.96 days

-10 days

496 days

16 days

496 days

522 days

583 days

-37 days

-37 days

-37 days

387 days

155 days

387 days

560 days

424 days

369 days

502 days

325 days

443 days

538 days

516 days

467 days

467 days

400 days

625 days

487 days

289 days

401 days

544 days

667 days

H2 '10 H1 '11 H2 '11 H1 '12 H2 '12 H1 '13 H2 '13 H1 '14 H2 '14 H1 '15 H2 '15 H1 '16 H2 '162010 2011 2012 2013 2014 2015 2016

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Critical

Critical Split

Baseline

Baseline Milestone

Baseline Summary

Progress

DEVELOPMENT OF EQ-1A BERTH AT VISAKHAPATNAM PORT

Page 3

Project: Development of EQ-1A Berth at Visakhapatnam PortDate: 03/03/14

Page 4: DEVELOPMENT OF EQ-1A BERTH AT …vizagport.com/Tendersfiles/PPP Progress/PPP29102014/VPT-EQ-1A MS… · 1 1 Development of Coal Terminal - EQ1A Berth Expansion at VPT 1643 days Fri

ID WBS Task Name Duration Start Finish

497 1.7.6.7 Transfer tower struct. Fabrication

141 days Fri 10/24/14 Sat 3/14/15

501 1.7.6.8 Transfer tower struct. Erection 159 days Thu 1/15/15 Tue 6/23/15

505 1.7.6.9 Wagon tippler fabrication 213 days Tue 9/23/14 Fri 4/24/15

509 1.7.6.10 Wagon tippler erection 207 days Mon 12/22/14 Fri 7/17/15

513 1.7.7 Railway Network 180 days Sun 1/11/15 Fri 7/10/15

514 1.7.7.1 Civil works - Area Grading & Ballast Laying

150 days Sun 1/11/15 Wed 6/10/15

515 1.7.7.2 Track laying 150 days Tue 2/10/15 Fri 7/10/15

516 1.7.8 Electrical Works 266 days Sun 12/14/14 Sun 9/6/15

517 1.7.8.1 Electrical Works: For Conveyors 65 days Sun 4/19/15 Tue 6/23/15

518 1.7.8.2 Electrical Works: For Stacker / Reclaimer

123 days Thu 2/5/15 Mon 6/8/15

519 1.7.8.3 Electrical Works: For Wagon Tippler Station

127 days Sat 12/27/14 Sun 5/3/15

520 1.7.8.4 Electrical Works: For Shiploader 110 days Wed 2/18/15 Mon 6/8/15

521 1.7.8.5 Electrical Works: Control and Communication

266 days Sun 12/14/14 Sun 9/6/15

522 1.7.9 Construction Utilities 310 days Wed 8/27/14 Fri 7/3/15

523 1.7.9.1 Fire fighting system 57 days Mon 12/15/14 Tue 2/10/15

526 1.7.9.2 Electrical System(HT/LT/ELT) 150 days Tue 2/3/15 Fri 7/3/15

527 1.7.9.2.1 Substation 116 days Tue 2/3/15 Sat 5/30/15

530 1.7.9.2.2 DG Sets 39 days Tue 2/24/15 Sat 4/4/15

533 1.7.9.2.3 MCC panels 122 days Tue 3/3/15 Fri 7/3/15

536 1.7.9.2.4 HT/LT Cabling 112 days Tue 2/3/15 Tue 5/26/15

539 1.7.9.2.5 Earthing 88 days Fri 2/13/15 Tue 5/12/15

542 1.7.9.2.6 Lighting 81 days Tue 2/3/15 Sat 4/25/15

545 1.7.9.2.7 Data / Controls Network 119 days Tue 3/3/15 Tue 6/30/15

548 1.7.9.3 Internal Roads 136 days Wed 8/27/14 Sat 1/10/15

554 1.7.9.4 Drainage 129 days Fri 8/29/14 Mon 1/5/15

559 1.7.9.5 Water System 133 days Fri 8/29/14 Fri 1/9/15

566 1.7.9.6 Land scaping/Green belt 133 days Tue 9/2/14 Tue 1/13/15

571 1.7.9.7 Dust Suppression System 51 days Mon 1/5/15 Wed 2/25/15

573 1.8 Testing & Commissionning 86 days Fri 6/12/15 Sun 9/6/15

574 1.8.1 Testing & Comm.: Ship Loaders 50 days Sat 7/18/15 Sun 9/6/15

575 1.8.2 Testing & Comm.: Stacker reclaimer 50 days Fri 7/3/15 Sat 8/22/15

576 1.8.3 Testing & Comm.: Conveyer & Transfer Towers

50 days Sat 7/18/15 Sun 9/6/15

577 1.8.4 Testing & Comm.: Wagon tippler 50 days Fri 6/12/15 Sat 8/1/15

578 1.9 Project Completion 10 days Sun 9/6/15 Wed 9/16/15

579 1.9.1 Snags and Punch list 5 days Sun 9/6/15 Fri 9/11/15

580 1.9.2 Project Completion 5 days Fri 9/11/15 Wed 9/16/15

581 1.9.3 Project Finish 0 days Wed 9/16/15 Wed 9/16/15

511 days

493 days

634 days

364 days

495 days

414 days

437 days

424 days

499 days

465 days

634 days

592 days

587 days

465 days

684 days

712 days

414 days

447 days

433 days

266 days

423 days

409 days

327 days

9/16

H2 '10 H1 '11 H2 '11 H1 '12 H2 '12 H1 '13 H2 '13 H1 '14 H2 '14 H1 '15 H2 '15 H1 '16 H2 '162010 2011 2012 2013 2014 2015 2016

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Critical

Critical Split

Baseline

Baseline Milestone

Baseline Summary

Progress

DEVELOPMENT OF EQ-1A BERTH AT VISAKHAPATNAM PORT

Page 4

Project: Development of EQ-1A Berth at Visakhapatnam PortDate: 03/03/14