![Page 1: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/1.jpg)
Global solutions are our strength. l Emch+Berger AG BernSchlösslistrasse 23 l PO Box 6025 l CH-3001 Bern l Phone +41 31 385 61 11 l [email protected] l www.emchberger.ch
Patrick Almy, Weisskopf Engineering AG
SWISSED15 Conference - 8. September 2015
Denmarks New Railway Signalling System
![Page 2: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/2.jpg)
2008 Track Slot Demand
2
![Page 3: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/3.jpg)
Expected Train Path Demand
3
![Page 4: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/4.jpg)
TMvS
TMvS
TMvS
New TrackSignalling ProgrammeTraffic Management CenterElectrificationSpeed IncreaseClose to stable CapacityHigh PerformanceTraffic Management
Answer the challenge
4
Rapidly growing demand on the railway network
operated by
BDK chose to answer the challenge by building a
powerful automated traffic management solution
![Page 5: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/5.jpg)
Transforming Traffic Management
5
PROJECT
DELIVERABLES
DRIVER
VISION
BLUEPRINT
BUSINESS
CHANGES
REALISATION
![Page 6: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/6.jpg)
Apologise or Anticipate?
6
Sorry
![Page 7: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/7.jpg)
Anticipation is the Driver
The more automated a rail system,
the higher the customer‘s need
for individual attention in case of disruptions
Anticipate, adapt and communicate
7
DRIVER
![Page 8: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/8.jpg)
Run a train
8
View of Service
Provider
Planned Service
Service Provided
Punctuality
Customer View
Service
Expectation
Perception of
Service Quality
Customer
Satisfaction
Quality Circle(EN 13816 – Service Quality in Public Transportation)
Deliver a service
![Page 9: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/9.jpg)
Formalize how passengers perceive the railway services
SERVICE INTENTIONS9
![Page 10: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/10.jpg)
Managing Service Intentions is the Vision
10
VISION
Service Intention Examples:
• Transport Service within a time frame
• Transfer Connection to another transport service
• Service Quality, such as ...
• bicycle wagon
• guided children wagon
t
s
![Page 11: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/11.jpg)
Managing Service Intentions is the Vision
11
Customer‘s Service Expectations are satisfiedeven under Disruptions
VISION
Precondition:Production must permanently be under tight control
![Page 12: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/12.jpg)
Production under Control
Inner Control Loop: Tasks
12
BLUEPRINT (1)
![Page 13: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/13.jpg)
Outer Control Loop:
13
· -
BLUEPRINT (2)
Production under Control
![Page 14: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/14.jpg)
14
BLUEPRINT (2)
Reduced computational complexity
Using formalized service intentions allows massive
Reduction of computational complexity
Basic concept:
• Separation in two levels: Macroscopic and microscopic level
• Relaxing the problem definition by using service intentions opens
the solution space and reduces complexity
• Focus on solving local problems in hot spots (stations with high
utilisation) and then fill in the blanks in-between
Formalized in
«Algorithmic decision support for train scheduling in a large and highly
utilized railway network» PhD Thesis from Gabrio Curzio Caimi
Allows to reschedule at the whole Danish railway network at least every 6 seconds
![Page 15: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/15.jpg)
Legacy: Systems in Denmark anno 2013
15
Decisions
Decisions
Decisions
PassengerInformation
PassengerInformation
Decisions
Line Side Signals
Fallback
Block Section
Interlocking
Route Storage
Route Setting
Automated
Route Setting
Waiting
Criteria
Annual
Timetable
Timetable
Daily
Decisions
![Page 16: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/16.jpg)
The radical step: Throw it all out
16
Decisions
Decisions
Decisions
Decisions
PassengerInformation
PassengerInformation
Decisions
Line Side Signals
Fallback
Block Section
Interlocking
Route Storage
Route Setting
Automated
Route Setting
Waiting
Criteria
Annual
Timetable
Timetable
Daily
![Page 17: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/17.jpg)
Signalling Programme
Background
– Punctuality decreasing while
maintenance costs increasing
– 50% of today's train delays
are due to signalling failures
– Systems from 1930 still in use
17
Processes and ways of
working are unsuitable
![Page 18: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/18.jpg)
The Unique Chance
1 Total replacement of the Signalling System
in one Project
2 Transform Traffic Management
by Capitalising
on Opportunities presented by current IT
18
![Page 19: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/19.jpg)
Signalling Programme
Total Replacement of the
Signalling System
in one Project
– A Euro 3.2 billion replacement
programme of renewing all Danish
railway signalling together between
2009 and 2022
19
– Moving from track side signalling
to in-cab signalling
– Advanced Traffic Management
System
![Page 20: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/20.jpg)
Signalling Programme
Transform Traffic Management
by capitalising on
opportunities presented by current IT
Introducing ERTMS Level2
New Operational Rules
New processes for
Traffic Management
Maintenance
20
![Page 21: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/21.jpg)
The legacy System
21
Decisions
Decisions
Decisions
Decisions
PassengerInformation
PassengerInformation
Decisions
Line Side Signals
Fallback
Block Sections
Interlocking
Route Storage
Route Setting
Automated
Route Setting
Waiting
Criteria
Annual
Timetable
Timetable
Daily
![Page 22: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/22.jpg)
Cab Signals
Interlocking
The BANEDANMARK System
22
Block Sections
Interlocking
Automated
Route SettingDecisions
PassengerInformationProduction Plan
Service
Intentions
Automated Route Setting
PROJECT
DELIVERABLES
Block Sections
![Page 23: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/23.jpg)
Managing the Business Change
23
BUSINESS
CHANGES
Changing Culture
as premise for Benefit Realisation:
From Production to Service Culture
We chose to include Culture
to capture current Deficiencies at the Root
![Page 24: Denmarks New Railway Signalling System - SSSEssse.ch/sites/default/files/page_images/SWISSED15 - Almy - Denmarks... · Signalling System in one Project –A Euro 3.2 billion replacement](https://reader031.vdocuments.site/reader031/viewer/2022020204/5a7fcd217f8b9a682c8bc940/html5/thumbnails/24.jpg)
Arriving at ease / Felix Laube / DD.MM.YYYY 24
REALISATION
A railway the delivers
high quality services to
well informed passengers
even during disruptions