re-signalling with the cbtc signalling system - irse.org cbtc... · re-signalling with the cbtc...

34
www.thalesgroup.com Re-signalling with the CBTC Signalling System SHANTILAL MORAR TECHNICAL DIRECTOR/PROJECT DESIGN AUTHORITY 1ST DECEMBER 2016

Upload: hoangkhuong

Post on 16-May-2018

277 views

Category:

Documents


9 download

TRANSCRIPT

Page 1: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

www.thalesgroup.com

Re-signalling with the CBTC Signalling System

SHANTILAL MORARTECHNICAL DIRECTOR/PROJECT DESIGN AUTHORITY

1ST DECEMBER 2016

Page 2: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

www.thalesgroup.com

This Presentation▌ Customer Needs and Challenges

▌ Re-signalling with CBTC

▌ Return on Investment

▌ Conclusion

Page 3: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

www.thalesgroup.com

Customer Needs&

Challenges

Page 4: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

4

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Customers Priority and Expectation from Re-signalling

▌ Keeps system in good repair and no degradation of public services due to aging equipment

▌ Provides Safety Assurance to meet Current Standards - Enhanced Safety

▌ Increase capacity to address growing ridership into the future ( another 20-25 years)

▌ Provide improved availability and reliability

▌ Takes advantage of new technology to :

• Bring in more and richer functionality• Provides better efficiency and operational flexibility for operators• Provides easier maintenance• Facilitate operation management • Improved Performance and Capacity with existing tracks

▌ Efficient use of site access

Page 5: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

5

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Challenges

▌Project ChallengeRe-signalling projects requirements are:

• Upgrade an aging infrastructure• Predicted increase in service demands based on population growth• Legacy systems beyond expected life• Significant maintenance costs• Poor reliability due to life expired infrastructure• Need for 24 hours operations• Limited access opportunities

Page 6: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

6

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Challenges

▌Brown Field ChallengeAny proven solution will require some specific interfaces with legacy systems

• Migrate from existing technical and operational systems• Limited time to install and test on operational railway• Restoration to normal operations each Working day• No impact to revenue services• Consideration for reuse of existing components• Mixed mode operation• Early demonstration of technical solution• Upgraded User Interface• Variety of Rolling Stock

Page 7: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

7

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Automatic Operation

▌Project ChallengeAutomatic operation seen as critical by Customers to achieve required performance

• Rapidly increasing passenger numbers• Shorter journey times • Higher throughput required• Better ability to recover from service disruption needed• Variability of driver operation • Decision making support• Service regulation

Page 8: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

www.thalesgroup.com

Re-SignallingWithCBTC

Page 9: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

9

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

First Re-signalling to CBTC project - London Dockland Light Rail Initial scope: Resignalling 13 km, 15 stationsFirst SelTrac Revenue: 1994Follow on Extensions

Beckton: 1995Lewisham: 1999London City Airport: 2005Woolwich Arsenal: 2009Canning Town – Stratford: 2011

Current DLR system 34 km; 45 Stations149 Trains

Main transit for the London Olympics

Page 10: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

10

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Case Study on LUL Jubilee and Northern Lines

JUBILEE LINE• 35 Km• 27 stations, • 63 trains, • 2 Depots• New Control Centre• ATO Operation• 3 Migration Areas

NORTHERN LINE• 58 Km• 50 stations, • 106 trains, • 5 Depots• 660,400 passengers per day• New Control Centre• ATO Operation• 6 Migration Areas

• A mature, complex operating railway

• Complex Operations and Timetable

• Complex Junctions• Access restrictions• Minimum Impact to

Passenger Service

Page 11: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

11

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Case Study on LUL Jubilee and Northern Lines

Page 12: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

12

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Northern Line Complexity

• 58 km of track, serving 50 stations• 252 Million passengers a year in 2011,

approaching a million on weekday.

High Barnet

BANK

Page 13: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

13

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Northern Line – Project Summary

Page 14: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

14

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

IMR SER

Fuse/MCB Bay

Existing Interlocking

Existing Signalling System

Page 15: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

15

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Passive Installation – Data

IMR SER CBTC SER

FID DCTF CCTF1 CCTF2

RLBCCTB

EAK EAK

Fuse/MCB Bay

Existing Interlocking

Page 16: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

16

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

COC

SCSRR

Passive Installation – Control

IMR SER CBTC SER

RLBEAK EAK CCTBCCTB

FID DCTF CCTF2

TCTFTCTF

TEMPORARYCABLING

MCB

Term.Fuse/MCB Bay

Existing Interlocking

Page 17: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

17

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Commission – Change Over Cubical

IMR SER CBTC SER

RLBEAK EAK

MCB

CCTB CCTB

FID DCTF CCTF2

TEMPORARYCABLING

COC

SCSRR

Term.

TCTFTCTF

Existing Interlocking

Fuse/MCB Bay

Page 18: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

18

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

CBTC Commissioned

IMR SER CBTC SER

FID DCTF CCTF2

COC

SCSRR

RLBEAK EAK CCTB CCTB

TEMPORARYCABLING TCTFTCTF

Existing Interlocking

Fuse/MCB Bay

Page 19: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

www.thalesgroup.com

ReturnOn

Investment

Page 20: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

20

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Jubilee Line and Northern Line Re-signalling Return of Investment

CBTC

Operation and Maintenance

E & M Equipment

Civil Construction

Land

ReturnInvestm

ent

• Capacity increase:Jubilee Line 33% , Northern Line 20%

• Journey times Reduction:Jubilee Line 22% , Northern Line 18%

Page 21: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

21

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Case Study Lessons Learnt

▌ Lessons learntFrom a complex Brown Field Re-signalling

• One can never spend too much time with Operators and Maintainers when developing and agreeing requirements

• Demonstration of reliability prior to commissioning is essential• Prove as much as possible ‘off site’• Complex interfaces require real attention to detail • The whole railway system must be considered• Collaboration will resolve problems• Always consider the whole life of the system• Dependencies are key

Page 22: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

22

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Collaborative Working

▌Optimising relationshipsThe importance of a collaborative relationship

• Consider the team in the widest possible sense• Problems are resolved by discussion• Co-location has many benefits• Always ask which party is best placed to deliver• There is a solution to every challenge• Celebrate success• Have a contract to ‘enable collaboration’

Page 23: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

23

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

New Challenges

▌Ever strengthening relationshipsIn July 2015 Thales were awarded the re-signalling of 4 additional lines (Metropolitan, District, Circle and Hammersmith and City) by London Underground, known as the 4LM project.

- Solution based upon proven Jubilee and Northern Line Solution- Enhanced to meet latest requirements e.g. radio- Continued collaborative working approach- Minimise disruption to passengers- 320 route kilometres of track - 191 trains (S7 & S8 – Stock), 52 Engineers Vehicles- 16 existing control locations rationalised to one new OCC- Long term partnerships

Page 24: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

24

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Automating the most Complex Metro in the World

• ATO enables the upgrade benefits • Huge increase in capacity ML 27%/DL 24%/C&H L 65% • 32TPH in central section (27TPH now)

• > 1M Passenger• 26% of LU Total • Makes 40% of LU Network

• Padding – Farringdon is World Oldest Underground Railway (1863)

• Trains up to 50 years old• Some parts of Signalling from 1920s

Page 25: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

25

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

DistrictLine

Metropolitan Line

Hammersmith & City Line

Circle Line

4LM Migration Strategy

Project Complexity and Size330Km Route Tracks

Trains191 New S-Stock Trains (ML, DL, CL + H&C Line)2 S Stock Type S7 (133) and S8 (58)5 Types of Engineering Trains

Depots4 Major Depots2 Major Sidings4 Other Sidings

• Position based Transponders• Radio Communication• Mixed Train Operations (CBTC and Non-CBTC)• Both Moving Block and Fix Block Signalling• Inter-Lines Stock Move Interfaces• 16 existing control locations rationalised to one new OCC

4LM Migration Areas

Page 26: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

26

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Hong Kong 7 Lines Re-signalling Project Overview

1

2

3

45

• All 7 lines will be converted to Thales SelTrac® CBTC solution with moving block technology, 2.4 Ghz Software Defined Radio (SDR) communication with fallback to LTE.

• Integrated interlocking• Triple redundancy

Work scope covers :• 5 separate CBTC systems.

• One each CBTC for first 4 Lines

• One CBTC for remaining 3 Lines

• 7 lines ~ 120 km double track and 73 stations

• 7 types of veh, (158) • 3 types loco/engineering

trains (48)• 5 depots with test track• 1 OCC with 5 separate ATS

Page 27: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

27

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Hong Kong 7 Lines Re-signalling Project Overview

Page 28: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

28

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Hong Kong 7 Lines Re-signalling Project Overview

▌Both Customer and Suppliers fully acknowledge:Importance of partnership and have a “Partnering Agreement” in placeImplementation Lessons Learnt at each key milestone

▌Customer takes proactive approach and gets involved at early stage

▌Customer Engineering and Operators gets involved at early stage

Page 29: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

www.thalesgroup.com

Conclusion

Page 30: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

30

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

More Capacity & Reduced journey times

15.4 min

13.8 min

Pre-upgrade Post-upgrade

Average journey timeNorthern Line

Replaced signalling to reduce the average journey

time by 1 min 37 sec.

This saves the average commuter 12.2 hours

travelling time per year

Replaced signalling to reduce the average journey

time by 1 min 49 sec.

This saves the average commuter 13.7 hours

travelling time per year

13.4 min 11.5

min

Pre-upgrade Post-upgrade

Average journey timeJubilee Line

Page 31: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

31

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

SelTrac™ Re-signalling Projects P

roje

ct

Con

trac

t Aw

ard

Ope

ratin

g M

ode

Inte

rlock

ing

Kilo

met

ers

1980

1981

1982

1983

1984

1985

1986

1987

1988

1989

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

Hong Kong DUAT - AT&D 2015 GOA3 I 70 Hong Kong DUAT - AT&D4LM District Line 2015 GOA2 I 188 4LM District Line4LM Metropolitan Line 2015 GOA2 I 67 4LM Metropolitan Line4LM - Hammersmith & City Line 2015 GOA2 I 27 4LM - Hammersmith & City LineHong Kong DUAT - TKL 2015 GOA3 I 14 Hong Kong DUAT - TKLHong Kong DUAT - KTL 2015 GOA3 I 18 Hong Kong DUAT - KTLJRE Joban 2014 GOA4 I 30 JRE JobanHong Kong DUAT - ISL 2015 GOA4 I 16 Hong Kong DUAT - ISLHong Kong DUAT - TWL 2015 GOA4 I 17 Hong Kong DUAT - TWLWest Virginia University 2014 GOA4 I 8 West Virginia UniversitySingapore EWL & TWE 2012 GOA4 E 57 Singapore EWL & TWEKuala Lumpur Ampang Line 2012 GOA4 I 45 Kuala Lumpur Ampang LineOrlando Disney World APM 2012 GOA4 I 22 Orlando Disney World APMSingapore NSL 2012 GOA4 E 46 Singapore NSLNew York Culver 2011 GOA2 E 8 New York CulverNew York Flushing Line 2010 GOA2 E 15 New York Flushing LineHong Kong APM 2011 GOA4 I 4 Hong Kong APMEdmonton North LRT 2011 GOA3 I 12 Edmonton North LRTParis RATP Line 13 2006 GOA2 E 23 Paris RATP Line 13London Tube Lines - Northern 2003 GOA2 I 58 London Tube Lines - NorthernLondon Tube Lines - Jubilee 2003 GOA2 I 37 London Tube Lines - JubileeBundang Commuter 2003 GOA2 E 6 Bundang CommuterSan Francisco MUNI 1992 GOA3 I 11 San Francisco MUNILondon DLR 1990 GOA3 I 38 London DLR

EI

Extension(s)

Loop CommunicationRadio Communication

Automatic Operation with Attendant in the CabAutomatic Operation with Attendant on TrainAutomatic Operation without a Driver

External InterlockingIntegrated InterlockingGOA3

GOA4

GOA2

Page 32: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

32

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Conclusions

▌ Focus On Risk• Understand Baseline Features and “Delta Functions” • Hardware and Software Complexity• Migration Sequence and Interfaces to Existing

Signalling• Make Difficult Decisions Upfront• Manage Parallel Design/Development Streams• Watch out for Overload – Both on Customer and

Suppliers• Areas that no-one wants to talk about!

• Hold Open Discussions

Page 33: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

33

© 2

016

Tha

les C

ana

da,

Tra

nsp

orta

tion

Solu

tions

.A

ll rig

hts r

eser

ved

.Pa

ssin

g on

or c

opyi

ng o

f thi

s doc

umen

t, us

e or

com

mun

ica

tion

of it

s con

tent

in w

hole

or i

n p

art

is no

t per

mitt

ed w

ithou

t Tha

les’

exp

ress

prio

r writ

ten

aut

horiz

atio

n..

Conclusions

▌Collaboration breeds successKey to successful brown field re-signalling includes:• Excellent communication in a collaborative

manner• Robust technical problem solving• Mature system architecture• Celebrate success• Consideration of whole life support• Learn lessons and continually improve.• A good contract will enable collaboration• The most important is ONE TEAM

UK National Rail Awards, Outstanding Teamwork Award

Page 34: Re-signalling with the CBTC Signalling System - irse.org CBTC... · Re-signalling with the CBTC Signalling System ... • Limited time to install and test on operational railway

www.thalesgroup.com

Thank youFor

Listening