delay analysis of raw water reservoir and pumping station

43
DELAY ANALYSIS OF RAW WATER RESERVOIR AND PUMPING STATION By Ch. Bala Krishna Assistant Professor Department of Civil Engineering

Upload: chetlapally-balakrishna

Post on 20-Mar-2017

60 views

Category:

Engineering


5 download

TRANSCRIPT

Page 1: Delay analysis of raw water reservoir and pumping Station

DELAY ANALYSIS OF RAW WATER RESERVOIR AND PUMPING STATION

ByCh. Bala Krishna

Assistant Professor

Department of Civil Engineering

Page 2: Delay analysis of raw water reservoir and pumping Station

Outline of the Presentation

• Introduction

• Need of the Study

• Objectives of the Study

• Literature Review

• Methodology

• Case Study Descriptions

• Results and Discussions

• Summary and Conclusions

Page 3: Delay analysis of raw water reservoir and pumping Station

Introduction

Page 4: Delay analysis of raw water reservoir and pumping Station

Introduction

• Delay means a time overrun either beyond the contract date or

beyond the date that the parties have agreed upon for the delivery of

the project.

• Delay is an interruption in the planned sequence or flow of work. It

can occur during the work or it can effect the over all project, so

completion of project may be extended.

• Delay Analysis is used to find the delays and its effects on the

project schedule and factors affecting the project.

Page 5: Delay analysis of raw water reservoir and pumping Station

Need of the Study

• This study concentrates on the work sequence, planning and

scheduling of the project.

• This study helps to identify the critical paths of the Reservoir and

pumping station construction work sequence.

• This study dwells on the importance of construction schedules in

achieving the aim of producing good quality construction work within

the specified time.

• This study also helps the project manager and concerned professionals

to produce good planning and scheduling for the project.

Page 6: Delay analysis of raw water reservoir and pumping Station

Objectives of the Study

To understand and identify the major types of construction

delays and causes in the construction project.

To estimate the amount of resources involved in the project,

during planning and construction stage.

To make a realistic and achievable schedule using Primavera.

To measure the impacts of construction delays of schedule

project.

Page 7: Delay analysis of raw water reservoir and pumping Station

Literature Review

Page 8: Delay analysis of raw water reservoir and pumping Station

• Trying to anticipate what will happen and devising ways of

achieving the set of objectives and targets”.

• The process of selecting one method and order of work to be

used on a project among all the various methods and

sequences in which it could be done.

• The process of determining the actual time periods during

which the activities are planned to take place.

• Scheduling is used for measuring delay and time extensions.

• Delay is an event that causes extended time to complete all or

part of the project

Page 9: Delay analysis of raw water reservoir and pumping Station

Parties Responsible for Delay

Owner

Contractor

Sub-contractor

Suppliers

Labor Unions

Nature

Page 10: Delay analysis of raw water reservoir and pumping Station

Most Common Causes

Differing site conditions

Change in requirements or design

Inclement weather

Shortage of labor, material and equipment

Defective plans or specifications

Page 11: Delay analysis of raw water reservoir and pumping Station

Construction Delay Types

Excusable Delay:

o Compensable Delay

o Non - Compensable Delay

Non Excusable Delay

Page 12: Delay analysis of raw water reservoir and pumping Station

Non Excusable Delays• Contractor problem result in schedule impacts.

• Contractor not entitled to either time extension or

compensation.

• Examples:

• Late submittals

• Late material delivery

• Insufficient manpower

Page 13: Delay analysis of raw water reservoir and pumping Station

Conti…

• Contractor gets NO additional TIME

• Contractor gets NO additional MONEY

Page 14: Delay analysis of raw water reservoir and pumping Station

Excusable But Non Compensable

• Delay event:

Not controlled by the contractor

Not controlled by the owner

• Depends on contract, but typically

Acts of God

Union strikes

Local disputes

Page 15: Delay analysis of raw water reservoir and pumping Station

• Granted additional TIME

• NO additional MONEY

Owner Caused Delay:

• Defective designs

• Slow return of shop drawings

• Change order

• Defective supplied equipments

Conti…

Page 16: Delay analysis of raw water reservoir and pumping Station

Critical and Non Critical Delays

• Delays that result in extended project completion are

known as “Critical delays” and

• Delay that do not extend the project completion date are

known as Non Critical delays.

Page 17: Delay analysis of raw water reservoir and pumping Station

Methodology

Page 18: Delay analysis of raw water reservoir and pumping Station

• Initiation

• Planning

• Execution

• Monitoring / Controlling

• Closing

Project Planning Management

Page 19: Delay analysis of raw water reservoir and pumping Station

Advantages:

Central database, Primavera P6 enables project managers to

access project data any where and at any time.

This single data base increases

• Efficiency

• Consistency and repeatability

• Saving organization’s time and money

Page 20: Delay analysis of raw water reservoir and pumping Station

CASE STUDY

Page 21: Delay analysis of raw water reservoir and pumping Station

Project Attributes

Project Data:

• The project “Raw Water Reservoir and Pumping Station” is

located at Bomakkal village in Karimnagar (District).

• This project is constructed under Godavari Drinking Water

Supply Project Phase-1 and named as Maulana Abdul Kalam

Hyderabad Srujala Sravanthi Scheme.

Page 22: Delay analysis of raw water reservoir and pumping Station

Study Area

Name of the project : Raw Water Reservoir and Pumping

station

Name of the company : Nagarjunga construction company

Built up Area : 18420.86 Sqm

Total project duration : 24 Months

Total project cost : 15.84 Crores

Page 23: Delay analysis of raw water reservoir and pumping Station

• Hyderabad Metropolitan Water Supply and Sewerage Board and

AP Transco officials are involved in their respective works. The

drinking water project aims to bring 172 Million Gallons per

day (MGD) from Yellampally barrage in karimnagar (District).

• The scheme envisaged to bring 10 TMC of water from river

Godavari to Hyderabad city. The total project cost Rs. 3375

Crores is estimated.

Page 24: Delay analysis of raw water reservoir and pumping Station

Project Schedule

• The total project duration was 713 days. The actual planned

schedule contains all types of activities with different duration

based upon the nature of work.

• The actual planned schedule also contains work breakdown

structure where the activities are categorized under their

specific work and explains the resources, roles assigned to the

activities.

Page 25: Delay analysis of raw water reservoir and pumping Station

Updated Proposed Schedule

• The updated proposed schedule was 683 days. The updated

proposed schedule is prepared by an general survey regarding

the duration of the project.

• The survey is conducted to find out whether the planned

schedule can be decreased by adding more resources.

Page 26: Delay analysis of raw water reservoir and pumping Station

Duration Analysis

• The duration analysis is to compare the actual planned

schedule duration and updated proposed schedule duration.

• The duration of the activities are taken into account to show

the difference between the two schedules.

• The duration of the activities are compared to find out the

delays in both schedules.

Page 27: Delay analysis of raw water reservoir and pumping Station

Results and Discussions

Page 28: Delay analysis of raw water reservoir and pumping Station

Activity wise Delay Analysis

Earthwork

Excav

tion Reservo

ir

Foundati

on

Raft Fo

oting

Retaining w

all Belo

w GL

Columns and Grad

e Slab

Retaining w

all Above

GL

Beams a

nd Roof Slab

Launder

Wall

Mechan

ical W

ork

Archite

ctural

Work

Electr

ical Fi

ttings

Earthwork

Excav

tion Pumping Stati

on

Foundati

on

Raft Fo

oting

Columns

Beams a

nd Ground Le

vel Sla

b

Retaining W

alls

Columns Above

Ground Le

vel Sl

ab

Beams a

nd Roof Slab

Mechan

ical W

ork

Archite

ctural

Work

Electr

ical Fi

ttings0

20406080

100120140160180

Raw water Reservoir and Pumping Station

Del

ay(d

ays)

Activities

Page 29: Delay analysis of raw water reservoir and pumping Station

Earthwork

Excav

tion Reservo

ir

Foundati

on

Raft Fo

oting

Retaining w

all Belo

w GL

Columns and Grad

e Slab

Retaining w

all Above

GL

Beams a

nd Roof Slab

Launder

Wall

Mechan

ical W

ork

Archite

ctural

Work

Electr

ical Fi

ttings

Earthwork

Excav

tion Pumping Stati

on

Foundati

on

Raft Fo

oting

Columns

Beams a

nd Ground Le

vel Sla

b

Retaining W

alls

Columns Above

Ground Le

vel Sl

ab

Beams a

nd Roof Slab

Mechan

ical W

ork

Archite

ctural

Work

Electr

ical Fi

ttings0

20

40

60

80

100

120

140

160

Raw water Reservoir and Pumping Station

Del

ay(d

ays)

Activities

Conti..

Page 30: Delay analysis of raw water reservoir and pumping Station

• After comparing both the durations of activities, the updated

proposed schedule is reduced by 30 days.

• The schedule duration is decreased by assigning more resources

(manpower, equipments).

Conti..

Page 31: Delay analysis of raw water reservoir and pumping Station

Resource Analysis

• The resource analysis is to compare the resources used in

actual planned schedule and updated proposed schedule. The

resources assigned for actual planned schedule takes the

project to complete in 713 days.

• The updated proposed schedule takes 683 days to complete the

project. By assigning more resources the duration is decreased

by 30 days.

Page 32: Delay analysis of raw water reservoir and pumping Station

Actual Schedule Versus Proposed Schedule

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 260

5

10

15

20

25

30

35

Actual ScheduleProposed scheduleSc

hedu

le

Resources

Page 33: Delay analysis of raw water reservoir and pumping Station

Determination of Causes and Types of Delays

• In this case study project, there are total of 20 delay events

including both critical and non-critical delays. Critical 11of

them are occurred as critical activities while 9 occurred as

non-critical activities.

Page 34: Delay analysis of raw water reservoir and pumping Station

Delay Activities

No Delay Description Impacted Activity

Name

Impacted Activity

Code

1 Delay occurred due to unforeseeable

weather conditions

Earthwork excavation P 1040

2 Delay in supply of steel for Raft

Footings occurred due to transportation

Raft Footing/

Reinforcement

P 1110

3 Delay in Reinforcement of Retaining

walls occurred due to corrections in

drawing

Retaining walls P 1170

4 Delay in backfilling compaction for

Retaining walls due to failure of

equipment

Backfilling

compaction

P 1240

Page 35: Delay analysis of raw water reservoir and pumping Station

5 Delay in cut and bend of steel in

Columns and Grade slab

Reinforcement

Columns & Grade slab P 1250

6 Delay in formwork for Columns &

Grade slab

Columns & Grade slab P 1270

7 Delay in Earthwork Excavation

occurred due to predecessor activity

Excavation P 1770

8 Delay in compaction of CNS soils

occurred due to unforeseeable

whether conditions

CNS soil compaction P 1800

Conti..

Page 36: Delay analysis of raw water reservoir and pumping Station

9 Delay in PCC compaction occurred due

to equipment failure

PCC compaction P 1820

10 Delay in marking for Raft Footings

occurred due to corrections in drawings

Raft Footings marking P 1830

11 Delay in supply of steel for Raft

Footings occurred due to transportation

Raft Footing

Reinforcement

P 1840

Conti..

Page 37: Delay analysis of raw water reservoir and pumping Station

Types of Delays

Impacted Activity Earthwork Excavation

Start 01-04-2013

Finish 10-06-2013

Duration 61 days

Delay type Excusable delay

Delay description Delay occurred due to unforeseeable whether

conditions

Page 38: Delay analysis of raw water reservoir and pumping Station

Impacted Activity Raft Footing Reinforcement

Start 28-06-2013

Finish 09-07-2013

Duration 10 days

Delay type Non-Excusable delay

Delay description Delay in supply due to transportation

Conti..

Page 39: Delay analysis of raw water reservoir and pumping Station

Impacted Activity Raft Footing Marking

Start 26-08-2013

Finish 11-09-2013

Duration 18 days

Delay type Non-Excusable

Delay description Delay in marking for Raft Footing occurred due

to corrections in drawings

Conti..

Page 40: Delay analysis of raw water reservoir and pumping Station

Impacted Activity Raft Footing Reinforcement

Start 26-09-2013

Finish 11-10-2013

Duration 26 days

Delay type Non-Excusable

Delay description Delay in supply occurred due to transportation

Conti..

Page 41: Delay analysis of raw water reservoir and pumping Station

Summary and conclusions

Page 42: Delay analysis of raw water reservoir and pumping Station

Conclusion • It is observed from delay analysis that, the total 20 parameters

were identified and analyzed.

• From these 20 parameters, 11 parameters are the sensitive

parameters that effect the overall duration of the construction

project.

• It is observed that the updated proposed schedule decreased, by

increasing the resources and the cost of the project increased.

• After the updated proposed schedule, the complete project was

reduced by 30 days.

Page 43: Delay analysis of raw water reservoir and pumping Station

Thank you