appendix a salem reservoir and pumping ... - city of barrie

76
APPENDIX A Salem Road Water Reservoir & Pumping Station Technical Memorandum

Upload: others

Post on 14-Mar-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

APPENDIX A

Salem Road Water Reservoir & Pumping Station

Technical Memorandum

Salem Road Water Reservoir & Pumping Station

City of Barrie

Technology and Alternative Site Assessment

December 2017 Technical Memorandum

TABLE OF CONTENTS

1.0 INTRODUCTION ................................................................................ 1

Background ............................................................................................................................. 1

Objective .................................................................................................................................. 1

Existing Zone 3S Major Infrastructure Systems ................................................................. 2

Water Storage .......................................................................................................... 2

Pumping Capacity .................................................................................................... 2

Water Distribution Zones 2S & 3S – Critical Infrastructure ..................................... 3

2.0 CONCEPT DESIGN BASIS ............................................................... 4

Reservoir Storage Volume .................................................................................................... 4

Maximum Daily Design Flow .................................................................................... 4

Fire Storage Requirements ...................................................................................... 4

Equalization and Emergency Storage Requirements .............................................. 4

Pressure Zone 3S – 2027 to 2031 Pumping Requirements ............................................... 5

Proposed Salem Pumping Station Design Capacity ............................................... 6

Reservoir and Pumping Station Site Alternatives .............................................................. 7

Site 1: North Side of Salem Road ............................................................................ 9

Site 2: South Side of Salem Road ........................................................................... 9

Reservoir System Alternatives ........................................................................................... 10

Cast-in-Place Concrete In-Ground Reservoir ........................................................ 12

Cylindrical At-Grade Water Storage Reservoirs .................................................... 13

3.0 TECHNOLOGY OPTIONS & SITE LOCATIONS ............................ 17

Salem Road Reservoir and Pumping Station Design Features ...................................... 17

Option 1A – In-Ground Reservoir & Pumping Station – Site 1: North Side Salem Road17

Option 1B – In-Ground Reservoir and Pumping Station – Site 2: South Side Salem Road18

Options 2A & 3A – At-Grade Reservoir and Pumping Station – Site 1: North Side Salem

Road 19

Options 2B & 3B – At-Grade Reservoir and Pumping Station – Site 2: South Side Salem

Road 20

4.0 COST ANALYSIS ............................................................................ 21

Approach ............................................................................................................................... 21

Estimated Capital Costs ...................................................................................................... 21

Maintenance/Refurbishment Costs .................................................................................... 21

Estimated Energy Cost ........................................................................................................ 22

Summary of Cost Analysis .................................................................................................. 24

5.0 EVALUATION PROCESS ............................................................... 26

Technology Evaluation ........................................................................................................ 26

Environmental Impact Evaluation ...................................................................................... 26

6.0 RECOMMENDATIONS .................................................................... 28

7.0 REFERENCES ................................................................................. 29

TABLE OF FIGURE

Figure 2-1 Salem Reservoir and Pumping Station – Site Selection Options ........................................... 8

Figure 3-1 Salem Reservoir and Pumping Station – Site 1, In-Ground Reservoir Option ..................... 18

Figure 3-2 Salem Reservoir and Pumping Station – Site 1, At-Grade Reservoir Option Plan .............. 19

Figure 3-3 Salem Reservoir and Pumping Station – Site 1, At-Grade Reservoir Option 3D Views ...... 20

TABLE OF TABLES

Table 1-1 Existing City of Barrie Water Distribution System Pressure Zones 2S and 3S – Critical

Elevations, Design Pump Heads, Capacities and Storage Volume(2) ...................................................... 3

Table 2-1 Total Storage Capacity Criteria for Salem Reservoir ............................................................ 4

Table 2-2 Pressure Zone 3S Required Pumping Capacity: 2027 - 2031 ............................................... 5

Table 2-3 Existing and Proposed City of Barrie Water Distribution System Pressure Zones 2S

and 3S – Critical Elevations, Design Pump Heads, Capacities and Storage Volume ........................... 6

Table 4-1 Comparison Estimated Construction Cost – Reservoir and Pumping Station Options 24

Table 4-2 Comparison Estimated Life Cycle Costs – Reservoir and Pumping Station Options ..... 24

Table 5-1 Technology Evaluation Matrix ................................................................................................ 27

APPENDICES

Appendix A – Drawings

Appendix B – Capital and Life Cycle Cost Estimates

Appendix C – Evaluation Matrices

1 | P a g e

1.0 INTRODUCTION

Background

The City of Barrie issued an Official Plan Amendment and Secondary Plan for the Annexed Area, south of

the pre-2010 City boundary on January 1, 2010 following the acquisition of 2,350 hectares of land from the

Town of Innisfil pursuant to the Barrie-Innisfil Boundary Adjustment Act, 2009. In determining the future land

use of the transferred lands (“Annexed Lands”), the associated infrastructure requirements and financial

implications, the City commenced a comprehensive Master Planning initiative.

The City of Barrie Drinking Water System 2010 Annual Report identified five major pressure zones

throughout the City consisting of: Zone 1, 2North (2N), 3North (3N), 2South (2S) and 3South (3S). These

primary zones are controlled by elevated tanks and reservoirs. Some zones also have locally reduced or

boosted secondary pressure areas. The Water Storage and Distribution Master Plan, 2013 and Class EA

for the Annexed Area and Intensification Areas within the pre-2010 City boundary, was completed to identify

and evaluate the water storage and distribution requirements of the Study Area for a period of 2011 to 2031

due to anticipated growth. Further, the Master Plan fulfills the requirements of Phases 1 and 2 of the

Municipal Class EA process, the Lake Simcoe Protection Plan process and the Safe Water Drinking Act,

2002 for the expansion of the water storage and distribution system.

The Master Plan concluded that no additional storage was required for pressure Zones 1, 2S and 3N for all

the phases however there was a deficit of storage in Zones 2N and 3S for all phases. To account for the

storage deficit, a new Zone 3S reservoir, Salem Road Reservoir and Pumping Station, was recommended

for implementation in years 2022 to 2026 with an ultimate storage capacity of 20ML before the end of the

20 year planning horizon.

Drawings G01 and G02 in Appendix A provide an overview of the City of Barrie Water Distribution System

Pressure Zones and the Salem and Lockhart Road Study Area covered by this TM.

Objective

The primary purpose of the proposed Salem Water Reservoir and Pumping Station is to provide sufficient

storage and pumping capacity to accommodate future growth in the pressure Zones 2S and 3S.

The objectives of this Technical Memorandum are to evaluate two alternative site locations as well as three

reservoir technology system alternatives taking into consideration of the following considerations:

• Hydraulics and topography

• Site development, drainage and access

• Operation and maintenance

• Capital and Life cycle costs

2 | P a g e

Existing Zone 3S Major Infrastructure Systems

Zone 3S is located on the southwestern boundary of the City of Barrie and is a combination of both pre-

2010 City boundary area as well as a portion of the Annexed Lands. The major existing infrastructure

systems include the Barrie Surface Water Treatment Plant, located in Zone 2S, the Harvie Road Reservoir

and Pumping Station located in Zone 3S, the Mapleview Elevated Tank located in Zone 3S, and the Big Bay

Point Road Pumping Station, located in Zone 3S.

Water Storage

The Mapleview Drive Elevated Tank is located in the Zone 3S boundary between Hwy 400 and Essa Road.

Mapleview Elevated Tank contains floating storage capacity for Zone 3S and is currently the only existing

dedicated reservoir in Zone 3S.

Summary of the Mapleview Elevated Tank is as follows:

• Elevated tank designed for fire storage, equalization storage and emergency storage.

• Total capacity = 5,455 m3 (Reference: City of Barrie, Water Supply Master Plan, Schedule A,

Mapleview Elevated Water Reservoir, Pg. 22)

• Bottom Water Level = 337.7 m (Reference: 2012 InfoWater model)

• Top Water Level = 350.2 m (Reference: 2012 InfoWater model)

Pumping Capacity

The existing pumping capacity available is in Zone 3S consists of two (2) pumping stations detailed below:

1. Harvie Road Pumping Station, which comprises of four (4) pumps each with an approximate

capacity of 133.3 L/s (11.5 MLD) at 47m with a firm capacity of approximately 400 L/s (34.5 MLD)

and a total capacity of approximately 533 L/s (46.1 MLD) (reference: 2012 InfoWater model).

2. Big Bay Point Road Pumping Station, which comprises of four (4) pumps each with an approximate

capacity of 135 L/s (11.5 MLD) at 47.3m with a firm capacity of approximately 405 L/s (35 MLD)

and a total capacity of approximately 540 L/s (46.7 MLD) (reference: 2012 InfoWater model).

3 | P a g e

Water Distribution Zones 2S & 3S – Critical Infrastructure

Refer to Table 1-1 below illustrating the critical elevations, design pump heads, capacities and storage

volume of the existing major infrastructure systems in Zone 2S and 3S.

Table 1-1 Existing City of Barrie Water Distribution System Pressure Zones 2S and 3S – Critical

Elevations, Design Pump Heads, Capacities and Storage Volume(2)

Location Description

Operating

Elevation

(m)

Design

Pump

Head (m)

Equipped

Capacity (L/s)

Firm Capacity

(L/s) (1)

Vol

(ML)

Barrie Surface

Water

Treatment

Plant –

Centreline of

Pump

Discharge

Pumps to

Harvie

Reservoir and

proposed

Salem

Reservoir

255.1 m 65.5 m 1255 L/s 920 L/s N/A(3)

Big Bay Point

Road Pumping

Station –

Centre Line of

Pump

Discharge

Pumps to the

Mapleview

Elevated Tank 281.3 m 47.3 m

Existing Design Cap:

500 L/s (2x100+

2x150 @ 47.3m

TDH)

Existing Firm Cap:

350 L/s (2x100+

1x150)

N/A

Harvie Road

Pumping

Station –

Centreline of

Pump

Discharge

Pumps to the

Mapleview

Elevated Tank 304.8 m 45.0 m

533 L/s (4 Duty

Pumps, at 133.3

L/s)

400 L/s (3 Duty

Pumps at

133.3 L/s)

N/A

Harvie Road

Reservoir –

Operating

Range

Provides

floating

storage at

Pressure Zone

2S and

pumped

storage to

Pressure Zone

3S

302 m –

308 m N/A N/A N/A

27.3

ML

Mapleview

Elevated Tank

– Operating

Range

Provides

floating

storage at

Pressure Zone

3S

337.7 m –

350.2 m N/A N/A N/A

5.4

ML

Notes:

1. Firm pumping capacity = equipped pumping capacity minus largest pump out of service.

2. Reference: 2012 InfoWater model.

3. N/A denotes not applicable.

4 | P a g e

2.0 CONCEPT DESIGN BASIS

Reservoir Storage Volume

The storage volume requirements need to provide for fire storage, maximum day equalization storage and

emergency storage for Zone 3S as per the MOECC Guidelines and the City’s Water Transmission and

Distribution Policies and Design Guidelines. Population growth in Zone 3S has been calculated to be an

equivalent population of 72,717 by 2031 (Water Storage and Distribution Master Plan – Appendix D – Phase

3: 2027 – 2031 Table). This equivalent population will require 20ML water storage volume to meet projected

demand. Refer to Table 2-1 for a detailed breakdown.

Table 2-1 Total Storage Capacity Criteria for Salem Reservoir

Component Criteria Water Storage and Distribution Master

Plan, October 2013

A: Fire Storage Largest expected fire volume

(378 L/s per 6 hours) 8165

B: Equalization Storage 25% of Maximum Day Demand 7881

C: Emergency Storage 25% of (A + B) 4011

Total A + B + C 20063

Notes:

1. Water Storage and Distribution Master Plan – Appendix D – Phase 3: 2027 – 2031 Table.

Maximum Daily Design Flow

The proposed conceptual design for the Salem Water Reservoir and Pumping Station are based on the City

of Barrie Water Storage and Distribution Master Plan – Appendix D – Phase 3: 2027 – 2031 Table, which is

consistent with the Water Transmission and Distribution Policies and Design Guidelines, 2015, as well as

the MOECC Criteria. Based on the Master Plan, the ultimate (2031) Maximum Day flow is 365 L/s (31.5

MLD).

Fire Storage Requirements

The City of Barrie’s Water Transmission and Distribution Policies and Design Guidelines, 2015, indicates

that watermain sizing shall be determined by fire flow plus maximum day use. The total equivalent population

for 2031 in Zone 3S is estimated to be 72,717. As the MOECC recommends a fire flow of 378 L/s for 6

hours, the calculated required volume of fire storage is 8165 m3. (Source: Water Storage and Distribution

Master Plan – Appendix D – Phase 3: 2027 – 2031).

Equalization and Emergency Storage Requirements

In accordance with MOECC Guidelines and the City’s standards, Equalization Storage is 25% of the

maximum day demand and Emergency Storage is 25% of the sum of Fire Storage and Equalization Storage.

5 | P a g e

The equalization storage requirements amounts to approximately 7.9 MLD and 4.0 MLD for emergency

storage.

Pressure Zone 3S – 2027 to 2031 Pumping Requirements

The required 2027 to 2031 required pumping capacity for Pressure Zone 3S has been estimated at

approximately 803 L/s, in accordance with the following design rationale:

• Water Storage and Distribution Master Plan – Appendix D – 2027 to 2031 Maximum Day Demand

(MDD) of 365 L/s.

• Peak Hour Demand of 550 L/s, calculated by multiplying the MDD by 1.5.

• Fire Flow of 378 L/s in accordance with MOECC guidelines and the Water Storage and Distribution

Master Plan – Appendix D – 2027 to 2031.

• Available Fire Flow protection from the existing Mapleview Elevated Tank of 125 L/s, calculated by

50% of the 5,400,000 L capacity of the tank, divided by a 6 hour fire flow.

• The required pumping capacity for Pressure Zone 3S – 2027 to 2031 was calculated by the addition

of the peak hour demand and the fire flow, less the available fire flow from the Mapleview Elevated

Tank to obtain 803 L/s.

Table 2-2 Pressure Zone 3S Required Pumping Capacity: 2027 - 2031

Location Description

Zone 3S

Max Day

Demand

(L/s)

Peak Hour

Demand

(L/s)

Fire Flow

(L/s)

Available

Fire Flow

from

Mapleview

Elevated

Tank (L/s)

Required

Pumping

Capacity

(L/s)

Pressure Zone

3S: Pumping

Stations

Capacity

Requirement:

Pumps to the

Mapleview

Elevated Tank and

Pressure Zone 3S

365 L/s (1) 550 L/s (2) 378 L/s (1) 125 L/s (3) 803 L/s (4,5)

Notes:

1. Water Storage and Distribution Master Plan – Appendix D – Phase 3: 2027 – 2031 Table.

2. Peak Hour Demand = Maximum Day Demand times 1.5.

3. Available fire flow is calculated by 50% of the available storage volume in the Mapleview

Elevated Tank (2,700,000 L) divided by 216,000 seconds (i.e., 6 hour fire duration in accordance

with MOECC Design Guidelines and the Water Storage and Distribution Master Plan).

4. Required pumping capacity is calculated based on Peak Hour demand plus Fire Flow, less the

available Fire Flow from the Mapleview Elevated Tank.

5. Required pumping capacity is based on a combination of two (2) of the three (3) Zone 3S

pumping stations in service (i.e., Big Bay Point Road Pumping Station, Harvie Road Pumping

Station, and the proposed Salem Road Pumping Station)

6 | P a g e

Proposed Salem Pumping Station Design Capacity

The planned 2027 – 2031 pumping capacity for Pressure Zone 3S has been calculated to be approximately

803 L/s. This pumping capacity is required to be achieved based on the City’s required pumping strategy:

Convey the planned pumping capacity via 2 of the 3 pumping stations which service Pressure Zone 3S).

The available firm pumping capacity from each of the existing Zone 3S Pumping Stations (i.e., Harvie Road

Pumping Station and the Big Bay Point Pumping Station) is approximately 400 L/s. With one of these

pumping stations out of service, the pump capacity deficit for Pressure Zone 3S is approximately 403 L/s.

Based on this pumping capacity deficit, it is recommended that three (3) duty pumps and (1) one standby

pump on VFD control are proposed to supply approximately 403 L/s, with the output capacity per pumps

estimated at 135 L/s. Addition design characteristics of the pumping station should include a common

suction header will draw from a depressed sump pit, piping configuration will allow water to bypass the

reservoir complete and be pumped immediately, bi-directional piping that will allow flow to be recirculated

into Zone 2S, as required.

Table 2-3 summarizes the existing and proposed critical elevations, design pump heads, capacities and

storage volumes for Pressure Zones 2S and 3S – 2027 – 2031 planning period.

Table 2-3 Existing and Proposed City of Barrie Water Distribution System Pressure Zones 2S

and 3S – Critical Elevations, Design Pump Heads, Capacities and Storage Volume

Location Description

Operating

Elevation

(m)

Design

Pump Head

(m)

Equipped

Capacity

(L/s)

Firm

Capacity

(L/s) (1)

Volume

(ML)

Barrie Surface

Water Treatment

Plant – Centreline

of Pump

Discharge

Pumps to Harvie

Reservoir and

proposed Salem

Reservoir

255.1 m 65.5 m 1255 L/s 920 L/s N/A3

Big Bay Point

Road Pumping

Station – Centre

Line of Pump

Discharge

Pumps to the

Mapleview

Elevated Tank

281.3 m 47.3 m

Existing

Design Cap:

500 L/s

(2x100+

2x150 @

47.3m TDH)

Proposed

Design Cap:

540 L/s

(4x135L/s @

47.3mTDH)

Existing

Firm Cap:

350 L/s

(2x100+

1x150)

Proposed

Firm Cap:

405 L/s

(3x135L/s

@ 47.3m

TDH)

N/A

Harvie Road

Pumping Station

– Centreline of

Pump Discharge

Pumps to the

Mapleview

Elevated Tank

304.8 m 45.0 m

533 L/s (4

Duty Pumps,

at 133.3 L/s)

400 L/s (3

Duty Pumps

at

133.3 L/s)

N/A

7 | P a g e

Location Description

Operating

Elevation

(m)

Design

Pump Head

(m)

Equipped

Capacity

(L/s)

Firm

Capacity

(L/s) (1)

Volume

(ML)

Harvie Road

Reservoir –

Operating Range

Provides floating

storage at

Pressure Zone 2S

and pumped

storage to

Pressure Zone 3S

302 m –

308 m N/A N/A N/A 27.3 ML

Mapleview

Elevated Tank –

Operating Range

Provides floating

storage at

Pressure Zone 3S 337.7 m –

350.2 m N/A N/A N/A 5.4 ML

Proposed Salem

Pumping Station

– Centreline of

Pump Discharge

Pumps to the

Mapleview

Elevated Tank

± 304.8 m (2) ± 45.0 m (2)

535 L/s

(3 Duty

Pumps, 1

Standby

Pump, each

rated at

±135 L/s)

405 L/s

(3 Duty

Pumps at

±135 L/s)

Proposed Salem

Reservoir –

Operating Range

Provides floating

storage at

Pressure Zone 2S

and pumped

storage to

Pressure Zone 3S

302 m –

308 m N/A N/A N/A 20 ML

Notes:

1. Firm pumping capacity = equipped pumping capacity minus largest pump out of service.

2. Estimated to be approximately equivalent to the existing Harvey Road Pumping Station for

conceptual design and preferred site selection analysis. The final elevation of the pump

discharge header and design pump head is required to be determine at the detailed design

stage.

3. N/A denotes not applicable.

Reservoir and Pumping Station Site Alternatives

Overview of Site Evaluation Process

The City’s Water Storage and Distribution Master Plan (2013) modeling assumed the proposed site for the

Salem Road Reservoir and Pumping station to be located just east of the Veterans Drive and Salem Road

intersection, just west of Highway 400. This is depicted in Drawing G02 in Appendix A. The area was

considered compatible for this infrastructure based on existing land use, topographic features and water

distribution system needs.

Based on the study area proposed in the City’s Water Storage and Distribution Master Plan, the following

site selection options are identified in order to proceed with the conceptual design of the proposed Salem

8 | P a g e

Reservoir and Pumping Station. This is also prerequisite to the City proceeding with land acquisition for the

proposed infrastructure:

1. Site 1 – Located north of Salem Road, west of the existing Galaxy Cinema, and east of Norris Drive

(4.05 ha)

2. Site 2 – Located south of Salem Road, west and north of the existing treed area, east of the existing

agricultural area (3.46 ha)

3. Site 3 – Located south of Lockhart Road, east of HWY400 (1.3 ha)

The overall study area and site locations are shown in Figure 2-1.

Figure 2-1 Salem Reservoir and Pumping Station – Site Selection Options

Sites 1 and 2 provide sufficient space for initial development and future expansion and are both considered

possible locations for the Salem Road Reservoir and Pumping Station. Site 1 has an average site elevation

of 304.0m – 305.0m, which is considered workable for either an in-ground cast-in-place reservoir, or an at-

grade reservoir structure and in-ground pumping station. A portion of Site 2 has a moderately higher average

site elevation up to 310m, which lends itself more to the in-ground cast-in-place reservoir design option.

Both Site 1 and 2 provide a suitable footprint for future expansion pending development within the City,

although Site 1 is closer to existing development.

One of the key considerations to site selection is evaluating the need to modify the site through excavation

and regrading. Nominal site elevations for the proposed reservoir need to be consistent with the low and

high operating elevations within Pressure Zone 2S ranging from 302.0m – 308.0m. All sites would require a

significant amount of site grading, and potential haulage of soils off-site, pending the results of a more

detailed geotechnical investigation.

9 | P a g e

Site 3 provides an appropriate area for the current proposed reservoir and pumping station site, however

offers limited future expansion opportunities due to its small footprint and adjacent constraints including

HWY400 and the Hydro corridor. The average grade of this site is approximately 298.0m which requires

considerable infill to raise the site to accommodate the minimum operating level of 302.0 m within Pressure

Zone 2S.

It is anticipated the development of any of the three (3) sites would not have significant negative impact to

the natural and social/cultural environment although some land use will be changed to suit the approved

zoning of these and adjacent lands as well as the proposed Salem Road redevelopment.

It should be noted that for the selected site and reservoir technology, the City’s hydraulic model and hydraulic

capacity of the Barrie SWTP would need to be reviewed to confirm the final reservoir design and pumping

station capacities for the Salem Reservoir and Pumping Station.

Site 1: North Side of Salem Road

Site 1 is located on a property approximately 293m long by 137m deep covering an area of approximately

4.05 ha, making it suitable for both the proposed reservoir and pumping station, as well as accommodating

future expansion. The southeastern-most quadrant consists of steep sloped terrain ranging in elevations

from 295m to 305m. The northern and southwestern sections are relatively flatter, but still have a notable

elevation variance of 4 meters from 305m to 309m. The site is generally undeveloped green land consisting

of small shrubbery plants over approximately half of the property and offers the greatest flexibility associated

with a future expansion compared to the other sites.

Bordering the site on the north and east side are existing commercial properties accessible from Commerce

Park Drive and consist of surface parking and low rise sprawling commercial plazas. Immediately to the west

and south of the site are mostly green fields and some rural single family dwellings.

The section of Salem Rd just south of the property is currently a dirt road which dead-ends just east of the

site before Highway 400. As noted above, this portion of Salem Rd is proposed for future road upgrade

which is projected to become a major transit corridor crossing over Highway 400 and extending to Lockhart

Rd.

Site 2: South Side of Salem Road

Site 2 is located on a moderately smaller, and narrower, land parcel which measures roughly 365m long by

125m deep covering an extended area of approximately 3.46 ha. The site slopes horizontally from the

northwestern corner to the southeastern corner with quite significant grade variance, generally rising up from

the western most portion at an elevation of approximately 310 m, and then sloping away to the south and

east.

Site 2 is generally undeveloped green land consisting of forested areas, especially within the eastern portion

which has suitable grades for both reservoir storage options. This site is narrower than the Site 1, and does

not offer as much flexibility associated with a future expansion compared to Site 1.

Lands adjacent to the Site 2 are currently undeveloped with nearby areas designated as neighbourhood

mixed use as part of the 2031 Salem Secondary Master Plan. Development beyond 2031 may continue to

increase neighbourhood mixed use lands which directly border this site.

10 | P a g e

Site 3: South Side of Lockhart Rd

Site 3 covers the smallest area of all 3 options, measuring approximately 115m by 115m and consisting of

a total of 1.31 ha. The site is relatively flat and has an average elevation of approximately 298 m. This site

would require some infilling to facilitate reservoir and pumping station construction to accommodate the low

operating level of 302m within Pressure Zone 2S. Given the existing grade, this site is most suitable for the

at-grade reservoir storage option.

Bordering the site, on the north side of Lockhart Rd, are existing low-rise commercial/industrial properties

with surface parking accessible from Lockhart Rd, Bayview Dr and Saunders Rd. Immediately to the west is

Highway 400 with predominantly green fields, forest and a golf course to the south. Passing adjacent and

to the east of the site running through the property in a north-south direction is a hydro corridor.

Lockhart Rd just north of the property currently dead-ends just west of the site before Highway 400. As noted

above, this portion of Lockhart Rd is proposed for future road upgrade which is projected to become a major

transit corridor crossing over Highway 400 and extending to Salem Rd. This development will significantly

limit access to the site.

One of the major contributors for the preferred site selection is the availability of land for future expansion.

Given the steep downward slopes associated with the east, west and south borders of Site 3, as well as the

proximity to the existing Hydro corridor, it is not practical to extend this site beyond the depicted boundaries.

Summary of Site Review

Based on the above evaluation and noting the required infrastructure and existing grading constraints, both

Site 1 and Site 2 are candidate sites worth further evaluation with Site 1 offering the best overall location

considering adjacent development, accessibility, environmental sensitivity and future expansion. However,

there is no significant additional space available on Site 3 to expand water storage capacity in the future

beyond 20ML, the site is sandwiched between Highway 400 and a Hydro Corridor and ultimately offers

limited access. Therefore, Site 3 is excluded from any further analysis.

Reservoir System Alternatives

As described below in more detail, there a variety of materials and technologies that may be employed to

provide potable water storage. For this analysis, the City has requested three alternative reservoir systems

be assessed for implementation; traditional in-ground or partially in-ground cast-in-place concrete structure,

at-grade cylindrical precast concrete, horizontally prestressed tank structure and at grade cylindrical glass-

fused-to-steel bolted steel tank structure. There are significant differences between these approaches which

dictate that a more detailed assessment of each alternative on each of the proposed sites, be completed as

part of this Technical Memorandum.

The large majority of reservoirs currently in use and being specified for new construction are based on steel,

glass-fused-to-steel and concrete materials and technologies. Reservoirs are generally considered to be

ground-supported, flat-bottom tanks with a tank shell height less than its nominal footprint or diameter. This

configuration is generally considered the most economical to construct and maintain.

11 | P a g e

Traditionally, large storage tanks have been either made from steel, which is welded together and finished

onsite, or concrete, which is poured in place onsite. Both types of tanks perform well, but have some distinct

disadvantages when compared to other available reservoir technologies:

• Cast-in-place concrete in-ground reservoirs are generally more complex and time consuming to

construct and require added time and special provisions to properly cure and test before being put

into service as compared to cylindrical steel or precast/prestressed concrete style at-grade

reservoirs.

• Field-welded steel reservoirs generally require a high level of welding and erecting skill and can be

difficult to finish properly at the site. Welding must be thoroughly inspected during and after

completion to ensure that the steel structure will not fail, leak or corrode prematurely.

o Field erected welded steel reservoirs constructed to AWWA specifications provide zero

leakage tolerance and can be fabricated in virtually any size or with any dimensions, in

accordance with the AWWA D100 code basic design. Manual, semi-automatic and fully

automated field welding techniques and processes have constantly improved over the years

offering the potential of increased economy and strength.

o Welded steel reservoirs have minimum roof plate thickness of .1875", a minimum shell plate

thickness of .1875", and a minimum floor plate thickness of .2500".

o All the panel joints are welded, fusing the entire structure into one solid piece, thus making

it very sturdy and durable.

o The projected lifetime of a welded steel tank may be as much as 100 years depending on

operating conditions and normal maintenance.

o Welded steel tanks can be repainted and coating work can be done on-site for easy

inspection. NSF approved lining is provided in accordance with local potable water

standards and MOECC regulations.

o Decorative features are readily available, such as knuckles, pilasters, dome or umbrella

roofs, and special colours, lighting and signage.

In more recent years with the development of improved steel fabrication technologies, field-erected Epoxy

and Glass-Fused-to-Steel Bolted Reservoirs, which use laser or die-cut steel panels that are bolted into

place onsite, offer the strength of welded steel, high corrosion resistance and are comparatively easy to

maintain or repair.

In recent years, the majority of new glass-fused-to-steel bolted tank installations have been supplied by

Greatario Engineered Storage Systems, an authorized, independent dealer for CST Storage (Aquastore®)

and H2Flow Tanks and Systems Inc., a local distributor of Permastore® Tanks and Silos. Both manufacturers

have over 26 years of experience supplying, erecting and servicing glass-fused-to-steel tanks in the

industrial and municipal market place, many in Ontario, for potable water storage. These two manufacturers

directly service the Ontario market such that a competitive bid can be obtained.

In addition, similar improvements in precast concrete reservoir design technologies and construction

techniques offer the advantages of high-strength, abrasion and corrosion resistance concrete structures

utilizing field fabricated precast panels. Construction requires that following placement of the precast panels

and seals, the reservoir wall is circumferentially prestressed with continuous high strength steel wire.

Circumferential prestressing places the reservoir wall in permanent compression resulting in a high strength

and durable cylindrical structure. A high-pH shotcrete is applied over the exterior prestressing, which

passivates the steel, providing permanent bond and corrosion protection. DN Tanks, a firm with extensive

12 | P a g e

experience in the design and construction of AWWA D110 Type III reservoirs, have been consulted. DN

Tanks has built over 3,000 tanks over the past 80 years around the world including the 5 ML precast and

prestressed concrete tank located at the Glenway Reservoir facility in Town of Newmarket. Members of the

Project Team toured this facility September 28, 2016. These types of tanks offer the following benefits:

• The concrete interior of an AWWA D110 tank can eliminate the need for protective coatings which

may reduce downtime associated with periodic coating maintenance.

• Added flexibility in terms of the site development, e.g., they can be constructed at-grade, partially

buried, or fully buried.

• Architectural elements including painted logos, brick veneers, EIFS systems, or other aesthetic

enhancements can be included to compliment nearby buildings and structures.

• Be designed with insulation and heating systems to suit local climate, reducing concerns with

respect to freezing.

• Can accommodate mixing systems.

• The tank is constructed so that the floor and walls are structurally independent, which means that

the wall is permitted to expand and contract without placing excessive bending stressed on the wall

or floor.

• The tank walls are placed into compression by circumferential prestressing. Every prestress wire is

fully encased in shotcrete to provide long term corrosion protection. This ensures the tank walls will

remain in permanent compression, eliminating shrinkage cracks, stress cracks, seepage, and

deterioration.

• Speed of construction to reduce the overall schedule – The method of on-site precasting operation

permits simultaneous construction of the tank walls and floor; resulting in a fast and efficient tank

construction process.

Both glass-fused to steel and precast/prestressed reservoir structures are considered technically sound

choices for potable water storage especially when carefully manufactured, handled, installed and

maintained. Bolted steel reservoirs offer the quickest construction in the field and are the easiest to enlarge

by addition of new bolted panel sections.

Cast-in-Place Concrete In-Ground Reservoir

Cast-in-place concrete reservoir construction is a common approach to reservoir design and has been

employed by the City on previous builds including the Harvie and Sunnidale reservoirs. Design of reinforced

concrete reservoir structures must be carried out in accordance with the requirements of ACI 350R-89 –

Environmental Engineering Concrete Structures and CAN/CSA A23.3 Design of Concrete Structures, and

practical design considerations. The following are the applicable guidelines and standards that would be

used for design of this reservoir technology:

• American Concrete Institute (ACI 350R)

• AWWA Standards

• CSA A23.1, A23.2, A23.3 and A23.4

• Ministry of Environment and Climate Change (MOECC)

• Various codes; Building, Fire and Electrical, NFPA

In-ground or partially in-ground water storage offers the advantage of minimizing temperature loss, reduced

exposure to exterior weather freeze-thaw cycles, potentially more secure access and have footprint and

13 | P a g e

layout that offers space for alternative recreational activities. The following offers a summary of cast-in-place

concrete in-ground reservoir key features:

• No size or configuration restrictions; very flexible design alternatives;

• Cast-in-place concrete requires special design requirements and construction techniques to ensure

a high-performance and watertight containment structure;

• Suitable for site specific terrain, climate and site conditions

• In-ground installation allows for inconspicuous structures with engineered environmental and

landscape features that blend well with the nearby natural environs

• Ease of accessibility to the roof structure by at grade access for valves, gates, instrumentation and

other equipment.

The primary disadvantage to this approach is potential for undetected infiltration or exfiltration and differential

settlement due to the nature and stability of underlying soil and impact on structural cracking and leakage.

Based on our experience in other reservoir assessment and rehabilitation projects, the two main areas of

water loss from these types of reservoirs are from cracks (shrinkage and stress induced) and at expansion

joints. Therefore, the following are some suggested key design features for future consideration:

• Refinement of the Volume of Cement for the Concrete Mix

• Use of ‘slip sheet’ between the base slab and the soil

• Temperature Control during Concrete Curing

• Crack Control Design as per ACI 350R

• Refinement of Expansion Joints

Reservoirs will typically have large footprint with larger surface areas to be maintained and theoretically

higher potential for cracking and leakage than cylindrical reservoirs. Compartmentalization allows taking

various portions of the reservoir offline for maintenance, but requires more complex piping, valves and

controls. Measures to ensure dead zones are minimized and a consistent water age and quality is

maintained in the storage reservoir need to be developed and integrated into the design. Staging

construction for future expansion is considered more complex compared to the at-grade reservoir options.

Cylindrical At-Grade Water Storage Reservoirs

Cylindrical at-grade water storage reservoirs can be constructed employing a variety of techniques and

materials, configured in single or multi-tank arrangements and be designed to operate in our frigid winter

climate. The primary advantage of a cylindrical tank design is ability to store water over greater depth thereby

greatly reducing footprint, site requirements and related costs. The most economical structures are also

mostly above ground surface helping to reduce structural costs and providing ready access for routine

inspection.

There are generally no operating restrictions imposed, nor requirements for minimum turnover to prevent

ice damage notwithstanding active reservoir mixing helps to increase water turnover for improved water

quality maintenance. However, reduced turnover combined with inadequate mixing and extended low

temperature conditions can result in formation of an ice lens, which can become lodged against the reservoir

wall. When this occurs, combined with sudden higher flows such as a fire event and/or a water main failure,

the structure is at risk for extreme forces caused by eccentric loading due to failure of the ice lens. Therefore,

in designing at-grade cylindrical tanks for the City of Barrie, it will be necessary to evaluate the potential for

14 | P a g e

formation of an ice lens and designs for the resulting forces acting on the structure taking into consideration

potential effects of ice abrasion acting on the reservoir wall.

The following sections provide added details on the water storage reservoir technologies reviewed as part

of this TM.

2.4.2.1 Glass-Fused-to-Steel At-Grade Cylindrical Tank Reservoir

Factory coated bolted steel tanks and reservoirs were adapted in the late 1970’s for potable water storage

primarily through the release of Standard AWWA D103 which allows the use of lighter-gauge steel in the

production of tank sheets:

• Normally sold in standard sizes and dimensions employing uniform panel sizes which are readily

transported to and assemble at site.

• Capacity ranges up to approximately 23 ML.

• Shell stress can range up to 21,600 PSI with A36 steel in the AWWA D103 design code.

• Bolted steel reservoirs have a minimum roof plate thickness of .0700" (2 mm), a minimum shell plate

thickness of .0940" (2.5 mm), and a minimum floor plate thickness of .0940" (2.5 mm). In all cases,

thinner than the same requirements for welded steel tank structures

• Factory fused silica glass coating on interior and exterior of steel sections

• Coatings used to protect against weather and corrosion and create a glass shell

• Water-resistant interior and a graffiti-resistant exterior

• Steel sections and joints are lapped and bolted, with gasket material in between, bolted on site,

assembled from the top down with a jacking system that progressively elevates the structure. This

approach permits future addition of extra panels and rings to increase individual tank capacity

• Projected service life of factory coated bolted steel reservoirs to be 45-50 or greater with proper

preventative maintenance, controlled operating conditions and ongoing maintenance of cathodic

protection. As regular inspections indicate, it may be more practical to replace the bolted reservoir

assembly rather than recoat or repair leaks.

• Coatings must be done at remote factory and be NSF certified where required.

• Decorative features are usually not available. The numerous bolted joints discourage painting signs.

Reservoir colour may be limited to a standard manufacturer’s colour.

• Suitable for the local terrain, climate and site conditions

• Tank construction requires specialized construction teams

For example, the factory-applied glass-fused-to-steel coating forms a hard, inert barrier for both the interior

and exterior of surfaces of the tank. It protects the steel core against weather and corrosion. The fusion

process produces a barrier coating on the sheet edges, so that the entire steel panel is encapsulated in a

glass shell. The glass coating provides a water-resistant interior and a graffiti-resistant exterior, ideally suited

to municipal potable water storage applications.

Tank sheets are shipped on protective skids with crated hardware and accessories. At the jobsite, tanks are

installed using specialized equipment.

When choosing a Glass-Fused-to-Steel Storage Reservoir, it is important to take into consideration design

and manufacturing factors which may impact the operating life and associated life cycle costs of the

structure. For example coating thickness impacts the base metal’s mechanical properties, impacting the

15 | P a g e

hardness, flexibility, brittleness and chip resistance of each individual tank panel. Proper coating thickness

application is key to elasticity and longevity of the coating.

The use of proprietary high quality A36 carbon steel specifically manufactured for the fusion process should

also be taken into consideration. Sheet edges also should be properly coated with the same material in

order to avoid electrolysis of dissimilar metals, rust, wakening of the fusion bonding and allowing oxidation

by-products to leak through.

2.4.2.2 Precast/Prestressed Concrete At-Grade Cylindrical Tank Reservoir

In prestressed concrete reservoir construction, tanks consist of precast concrete walls, an embedded steel

diaphragm and wire-wound prestressing. Tank sizes can range significantly and can be constructed on

varying types of terrain and are suitable for cold-climate climates. The following is a summary of prestressed

concrete tank key features:

• Size range up to 75.7 ML

• The reservoir can be constructed with either a flat slab roof or a free standing, clear spanning dome

• The precast wall requires no through wall tie holes

• Precast concrete wall panels are horizontally cast and custom formed on-site to the full curvature

and full height of the tank ensuring proper forming, inspection and placement of concrete

• An embedded steel diaphragm is the full height of the tank and acts as a water barrier in the finished

tank to assure watertightness. It also acts as the bottom casting form for the wall panels.

• Wall panels are placed onto bearing pads outside of the encased waterstop. Set approximately 150

to 250 mm apart, the wall panels form a series of open slots, which are later closed

• Stress plates are used for large diameter wall openings putting the entire wall in permanent

compression

• Prestressing is completed on site using carefully controlled wire-winding encased in shotcrete by an

ACI certified nozzleman

• The solid, small diameter prestressing wire builds gradual compression, provides enhanced

redundancy, and eliminates the potential of corrosion

• External panel finishing consists of shotcrete and architectural concrete coating. Option to finish with

architectural treatment or natural finish

• Suitable for the local terrain, climate and site conditions

• Tank construction requires specialized construction teams

If approved by the City, additional detail design and construction requirements are normally required to

ensure quality is maintained in terms of precast panel design, joint interfaces, tensioning, stitch panel, etc.

Cylindrical tank shapes are relatively easy to fabricate by utilizing curved precast panels when compared to

cast-in-place construction. Therefore, less time and setup is generally required in construction for precast

concrete than cast-in-place, with the added benefit of lower construction cost.

Following tank concrete placement, the tank wall is circumferentially prestressed with continuous high

strength steel. Circumferential prestressing is key to ensuring the tank wall is in permanent compression

thus resulting in the most durable tank structure. Shotcrete is applied over the exterior prestressing,

providing permanent bond and corrosion protection.

16 | P a g e

From a concrete durability approach, the use of high-strength air entrained concrete with specific quality

control measures is generally recommended and would be consistent with appropriate design

methodologies for concrete based water holding structures including the requirements of AWWA D110 Type

III standard for horizontal prestressed concrete water storage tanks and ACI 372R. Concrete should be

plastic wrapped and water cured for 7 days.

There are a large number of established design-build firms including DN Tanks who have designed and

constructed various precast configurations and will work directly with the various equipment suppliers

(mixing systems, piping, etc.) and the City to optimize their design.

17 | P a g e

3.0 TECHNOLOGY OPTIONS & SITE LOCATIONS

Salem Road Reservoir and Pumping Station Design Features

The approximate conceptual design features of the proposed 20 ML Salem Road / 20 ML Reservoir are

summarized as follows:

• Grade Elevation (existing topography): +/- 298 – 307m (Site 1) | +/- 300 – 310m (Site 2) – as

previously noted, Site 3 is excluded from further analysis.

• Minimum Reservoir Operating Level in Pressure Zone 2S – 302.0 m.

• Maximum Reservoir Operating Level in Pressure Zone 2S – 308.0 m.

• Maximum Pumped Hydraulic Grade Line in Pressure Zone 3S - 350.15 m.

• Footprint: (approx.) 90m x 65m (in-ground) | 46m diameter x 2 tanks (cylindrical at-grade) +

pumphouse / valve chamber.

• Duo cell with baffle walls and/or other mixing provisions | dual cylindrical reservoir with active mixing

system.

• Combined valve chamber and pumping station | Separate valve chamber & pumphouse building

• 4 duty, 1 standby pumping system each preliminarily sized at 135 L/s. Final pump sizing is to be

completed at the detailed design stage in combination with verification of the City’s water model.

• Firm pumping capacity of 403 L/s.

• 600mm diameter bi-directional watermain connection from Salem Rd

• Overflow and drains diverted to de-chlorination chamber and stormwater management/overflow

pond on redeveloped property

• 1.8m chain-link fence around perimeter of site

The design of the reservoir, pumping station, watermains and associated infrastructure will comply with City

of Barrie Standards, Canadian Standards Association (CSA), American Water Works Association (AWWA)

standards and MOECC Design Guidelines for Drinking Water Systems

An optimization study can be done at the detailed design stage to determine an operating approach that

minimizes operating costs throughout the lifetime of the reservoir and pumping station as demand in the City

increases.

With exception of site specific access road requirements, specific elevations and overall site plan and layout,

the general arrangement of the in-ground cast-in-place reservoir and pumping station will be similar on either

Site 1 or Site 2. In the case of the at-grade cylindrical reservoir designs, the general arrangement for either

the glass-fused-to-steel bolted steel reservoir or the precast/prestressed reservoir are assumed to be

identical. Refer to the following sections for additional details.

Option 1A – In-Ground Reservoir & Pumping Station – Site 1: North Side Salem Road

A proposed conceptual general arrangement is shown on Drawing Figure 3-1, as well as on Drawings Fig-

2 and Fig-3 in Appendix A. The in-ground structural design is consistent with the existing Sunnidale Park

reservoir with a nominal water storage capacity of 2 x 10 ML (20 ML). The site development shows the

approximate location of the reservoir structure assuming an approximate balanced cut and fill on this site.

18 | P a g e

Based on this location, it is recommended the pumphouse building be located on the west side of the

reservoir structure due to proximity of Salem Rd and the provision of a mildly sloping access road (less than

2%), as shown in Figure 3-1. In this way, it is also possible to maintain a minimum buffer of over 33m from

reservoir to the nearest property line bordering the location of the adjacent Cinema.

Overall, pending suitable soil conditions, this site provides a suitable location for the staged construction of

an in-ground cast-in-place reinforced concrete reservoir and pumping station. Refer to Figure 3-1.

Figure 3-1 Salem Reservoir and Pumping Station – Site 1, In-Ground Reservoir Option

Option 1B – In-Ground Reservoir and Pumping Station – Site 2: South Side Salem Road

The general arrangement is presented at a conceptual level on the aerial site plan presented in Figure 2-1

and on Drawing Fig-1 in Appendix A. The in-ground structural design is identical to Option 1A with a nominal

water storage capacity of 2 x 10 ML (20 ML). The site development shows the approximate location of the

reservoir structure based on an approximate balanced cut and fill of the selected site. Based on this location,

it is recommended the pumphouse building be located on the east side of the reservoir structure. This allows

a mildly sloping access road. Through this conceptual plan, a 30m buffer is maintained around all sides of

the reservoir and pumping station, which is important given future anticipated neighbourhood mixed use

development, along with the planned Salem Road expansion project.

Pending suitable soils conditions, this site provides a suitable location for the staged construction of an in-

ground cast-in-place reinforced concrete reservoir and pumping station although related construction costs

are expected to be higher at Site 2 compared to Site 1 due primarily to existing site conditions.

19 | P a g e

Options 2A & 3A – At-Grade Reservoir and Pumping Station – Site 1: North Side Salem Road

The proposed general arrangement of an at-grade cylindrical reservoir (either as a glass-fused-to-steel or

precast/prestressed configuration) and pumping station design is shown in Figures 3-2 and 3-3, as well as

on Drawings Fig.-1, Fig.-4 and Fig.-5 in Appendix A. The reservoir design and layout is based on each tank

having a nominal diameter of 46m, side water depth (SWD) of 6m and overall effective reservoir depth of

6.5-7m. A separate structure housing a combination valve chamber and pumping station interconnected to

the storage reservoirs would also be provided.

Figure 3-2 Salem Reservoir and Pumping Station – Site 1, At-Grade Reservoir Option Plan

20 | P a g e

Figure 3-3 Salem Reservoir and Pumping Station – Site 1, At-Grade Reservoir Option 3D Views

Options 2B & 3B – At-Grade Reservoir and Pumping Station – Site 2: South Side Salem Road

The general arrangement is presented at a conceptual level on the aerial site plan presented in Figure 2-1

and Drawing Fig.-1 in Appendix A. The at-grade design is identical to Option 2A/2B with a nominal water

storage capacity of 20 ML, achieved in 2 – 46m diameter tanks, each having a side water SWD of 6m, and

an overall effective reservoir depth of 6.5-7m. The site development shows the approximate location of the

reservoir structure based on an approximate balanced cut and fill of the selected site. Based on this location,

it is recommended the pumphouse building be located on the south side of the reservoir structure. This

allows a mildly sloping access road. Through this conceptual plan, a 30m buffer is maintained around three

sides of the reservoir and pumping station, which is important given future anticipated neighbourhood mixed

use development, along with the planned Salem Road expansion project.

Pending suitable soils conditions, this site provides a suitable location for the staged construction of an at-

grade reservoir and pumping station although related construction costs are expected to be higher at Site 2

compared to Site 1 due primarily to existing site conditions.

21 | P a g e

4.0 COST ANALYSIS

Approach

In order to make a thorough comparison of the proposed technologies, a review and sensitivity analysis of

capital, operating and maintenance costs over a projected 50 year period was carried out. The future costs

are analysed on a yearly basis with estimated current-day construction and maintenance costs and

converted into present values. To further derive fully developed costs, financial assumptions were made as

follows:

• 5% Discount factor

• 3% inflation factor

• $1.00 cost of diesel fuel/litre

• $0.20/kWh cost of electricity

It may be prudent to consider raising the inflation factor, but even an increase of up to 5-8% would not affect

the ranking of cost of the options reviewed as part of this report.

Refer to Appendix B for the detailed cost analysis tables and worksheets adapted for this analysis.

Estimated Capital Costs

The conceptual design drawings presented in Appendix A, along with supplemental process definition

drawings linked to WSP BIM database, were used as a basis for generating construction unit values based

on a Division 1-16 approach. Assumed typical present-day construction costs were in some cases allocated

as unit rates to determine final capital cost estimates. General assumptions applied as part of the analysis

include:

• Reservoir sized at 20MLD, not phased (e.g., by not deferring work to the future even though

only half of ultimate storage may be initially constructed)

• Pumping station configuration is assumed generally consistent for all three reservoir technology

concepts

• Reservoir locations optimized and designed to minimize earthworks cut/fill

• Property acquisition costs are not included as part of this analysis

Maintenance/Refurbishment Costs

Reservoir and pumping station components from each Division 1-16 were further allocated maintenance

and refurbishment costs, as applicable, on a yearly basis. This generally covers inspections, cleaning,

painting and repairs to maintain serviceability. The specific assumptions made are stated in the Life Cycle

Cost Estimate spreadsheet presented in Appendix B. Major maintenance/refurbishment costs identified are

as follows:

• CCTV inspection/ cleaning cost of sewerage/watermain/storm lines

• Landscaping, site maintenance, building repair costs and general upkeep

• Major equipment maintenance costs and instrument calibration

• Equipment and instrumentation end of life replacement costs

The project service life of the cast-in-place in-ground and precast/prestressed reservoirs are expected to

exceed 50 years with appropriate preventative maintenance. The project service life of the glass-fused-to-

22 | P a g e

steel bolted tanks is projected to be 40-50 years and under this analysis the tank, dome and internals are

projected to be replaced in year 45 of this analysis.

Labour costs associated with inspection, operating and maintaining the various water storage reservoir

options reviewed in this TM are assumed to be equivalent would likely be subject to change following

evolving regulatory requirements and City mandated policies and therefore were not carried as part of this

analysis.

Like water quality monitoring, planned reservoir inspections provide information used to identify and evaluate

current and potential water quality problems that may be related to maintenance. Both interior and exterior

inspections are employed to assure the tank’s physical integrity, security, and high water quality. Inspection

type and frequency are driven by many factors specific to each storage facility, including its type (e.g.,

standpipe, reservoir, etc), vandalism potential, age, condition, cleaning program or maintenance history,

water quality history, funding, staffing, and other utility criteria. AWWA Manual M42, Steel Water Storage

Tanks provides information regarding inspection during tank construction and periodic operator inspection

of existing steel tanks.

Specific guidance on the inspection of concrete tanks was not found in the literature. However, the former

AWWA Standard D101 document may be used as a guide to inspect all appurtenances on concrete tanks.

Concrete condition assessments should be performed with guidance from the tank manufacturer.

Routine inspections typically monitor the exterior of the storage facility and grounds for evidence of intrusion,

vandalism, coating failures, security, and operational readiness. Based on a review of reference information,

routine inspections should be conducted on a daily to weekly basis. In jurisdictions where SCADA systems

include electronic surveillance systems are employed, alarm conditions may substitute for daily physical

inspection.

Periodic inspections are designed to review areas of the storage facility not normally accessible from the

ground and hence not evaluated by routine inspections. Based on a literature review and reviewed

references, periodic inspections are typically conducted every 1 to 4 months.

Finally, comprehensive inspections are performed to evaluate the current condition of storage facility

components and will usually require the reservoir be removed from service and drained unless robotic

devices or divers are used. AWWA Manual M42 recommends that tanks be drained and inspected at least

once every 3 years or as otherwise required. Best Industry practices suggest that comprehensive

inspections be conducted every 3 to 5 years for structural condition and possibly more often for water quality

purposes.

Based on utility surveys and industry best practises, it appears that most water utilities that have regular

reservoir cleaning programs employ a cleaning interval of 2 to 5 years and that most tanks are painted

(exterior coating) on an interval of 10 to 15 years.

Estimated Energy Cost

Reservoir and pumping station components from each Division 1-16 were further allocated energy cost, as

applicable, on a yearly basis. The specific assumptions made are identified in the Life Cycle Cost estimate

spreadsheet in Appendix B. Major energy cost items identified were pumps, the diesel engine generator

23 | P a g e

set and ventilation infrastructure. In determining future energy requirements for the pumps, the following

assumptions were made:

• 20MLD Reservoir, with average daily flow capacity of 31.5MLD

• 3 duty, 45KW pumps – estimated average rate of power consumption at +/- 93 kW

• Required annual power rate adjusted to accommodate phased flow (25% of energy required years

1-5, 50% of energy required years 6-10, 75% of energy required years 11-15, 100% of energy

required years 16-50), with a projected 10% additional pumping premium for the at-grade reservoirs

due to the taller tank height

In determining future energy requirements for the generator, the following assumptions were made:

• 250 kW diesel generator size.

• 6 hour / month estimated operational hours.

• 68 L/hr fuel consumption.

In determining future energy requirements for the ventilation infrastructure, the following assumptions were

made:

• Heating load of 20 kW, operating at 6 months / year.

• Ventilation load of 12-15 kW, operating at 9 months /year.

It is noted that in addition to the above, the at-grade circular tanks require some form of active and/or passive

mixing and therefore it is necessary to account for any related energy requirement. Mixing processes within

a water storage reservoir should be carefully designed and controlled to minimize water age and promote

complete mixing. A well-mixed tank achieves more uniform water quality, temperature and age and is easier

to manage. When mixing does not occur throughout the storage facility, stagnant zones can form where

water age will exceed the overall average water age in the facility. Therefore, mixed flow is preferable to

plug flow in distribution system storage.

Mixing can be encouraged through the development of a turbulent jet. Mixing a fluid requires a source of

energy input, and in a storage facility, this energy is normally introduced from the facility’s inflow.

Temperature differences between the inflow and the ambient water temperature within the storage facility

can also cause the water to form stratified layers that do not mix together. Stratification is more common in

tall tanks such as standpipes and tanks with large diameter inlets. It can be avoided by increasing the inflow

rate.

Local power rates are based largely when electricity is used, and therefore it may be cost-effective to control

pumping in an effort to reduce the maximum power demand. In effect, the part-time use of more or larger

pumps and higher efficient motors may be more cost-effective than using constant-rate pumping over the

typical operating day. In other words, to get the best electric power rates, pumping (or power-demand load)

must be reduced during the periods when the maximum electrical demand occurs. A simple way to reduce

rates is to pump more water into storage during off-peak hours when electrical power demand and unit costs

are lowest and to reduce pumping during periods when both demand and power costs are highest. The

tradeoff is this technique generally requires marginally increased storage capacity.

24 | P a g e

Summary of Cost Analysis

The results of this analysis, expressed in Canadian dollars (CAD), are summarized in the following Tables.

Table 4-1 Comparison Estimated Construction Cost – Reservoir and Pumping Station Options

Table 4-2 Comparison Estimated Life Cycle Costs – Reservoir and Pumping Station Options

ITEM DESCRIPTION

Option 1A:

CIP Concrete In-

ground Reservoir

& PS

-

Site 1

North Side Salem

Road

Option 1B:

CIP Concrete In-

ground Reservoir

& PS

-

Site 2

South Side

Salem Road

Option 2A:

Glass Fused to

Steel At-Grade

Reservoir & PS

-

Site 1

North Side Salem

Road

Option 2B:

Glass Fused to

Steel At-Grade

Reservoir & PS

-

Site 2

South Side

Salem Rd

Option 3.A:

Precast,

prestressed

Concrete At-

Grade Reservoir

& PS

-

Site 1

North Side Salem

Rd

Option 3. B:

Precast,

prestressed

Concrete At-

Grade Reservoir

& PS

-

Site 2

South Side

Salem Rd

A.

SUBTOTAL - Div 1-16 $25,967,000 $28,066,000 $17,687,000 $18,145,000 $20,850,000 $21,175,000

B.

ALLOWANCE @ 20% $5,193,400 $5,613,200 $3,537,400 $3,629,000 $4,170,000 $4,235,000

C. $31,160,400 $33,679,200 $21,224,400 $21,774,000 $25,020,000 $25,410,000

ALL COSTS LESS HST

ESTIMATED TOTAL

CONSTRUCTION COSTS

ESTIMATED

CONTINGENCY COSTS

ESTIMATED

CONSTRUCTION COSTS

TECHNOLOGY DESCRIPTION

COMPARISON OF ESTIMATED CONSTRUCTION COSTS

SALEM ROAD RESERVOIR AND PUMPING STATION CONCEPTUAL DESIGN - TECHNOLOGY ASSESSMENT

ITEM DESCRIPTION

Option 1A:

CIP Concrete

In-ground

Reservoir & PS

-

Site 1

North Side

Salem Rd

Option 1B:

CIP Concrete

In-ground

Reservoir & PS

-

Site 2:

South Side

Salem Rd

Option 2A:

Glass Fused

Steel At-Grade

Reservoir & PS

-

Site 1

North Side

Salem Rd

Option 2B:

Glass Fused

Steel At-Grade

Reservoir & PS

-

Site 2

South Side

Salem Rd

Option 3A:

Precast

prestressed At-

Grade

Reservoir & PS

-

Site 1

North Side

Salem Rd

Option 3B:

Precast

prestressed At-

Grade

Reservoir & PS

-

Site 2

South Side

Salem Rd

A.

ESTIMATED 50 YR

OPERATIONS &

MAINTENANCE

COSTS - PRESENT

VALUE

$5,460,000 $5,460,000 $8,644,000 $8,644,000 $6,334,000 $6,334,000

B.

ESTIMATED

CONSTRUCTION

COSTS - PRESENT

VALUE

$31,161,400 $33,679,200 $21,224,400 $21,774,000 $25,020,000 $25,410,000

C.ESTIMATED LIFE

CYCLE COSTS$36,621,400 $39,139,200 $29,868,400 $30,418,000 $31,354,000 $31,744,000

ALL COSTS LESS HST

TECHNOLOGY DESCRIPTION

COMPARISON OF ESTIMATED LIFE CYCLE COSTS

SALEM ROAD RESERVOIR & PUMPING STATION CONCEPTUAL DESIGN - TECHNOLOGY ASSESSMENT

25 | P a g e

The cost analysis indicates the At-Grade Reservoir and Pumping Station options are significantly less costly

to implement than the In-Ground cast-in-place concrete reservoir options. The analysis also shows that site

development costs on Site 1 are projected to be less than Site 2 assuming soil conditions are comparable.

Overall, Option 2A, the bolted cylindrical glass-fused-to-steel reservoir and pumping station located on Site

1 is the least costly to implement over the projected 50-year life cycle cost basis used for this analysis,

followed by Option 3A. As previously noted, the actual service life of the 20 ML storage reservoir and

pumping station will depend on the noted O&M factors and the level of preventative maintenace provided.

Estimated total construction cost including engineering and contingency of the full build of Option 1B is

estimated to be $33.7M CAD, the highest of the six alternatives evaluated. The higher cost compared to

Option 1A is due largely to projected higher site development costs at Site 2.

Estimated construction cost and 50-year life cycle cost of the full build of Option 2A is estimated to be $21.2M

CAD and $29.9M CAD, respectively, the lowest of the alternatives.

Estimated construction cost and 50-year life cycle cost of the full build of Option 3A is estimated to be $25.0M

CAD and $31.3M CAD, respectively, marginally higher than Option 2A.

Based on our preliminary cost review, Option 2A, at-grade glass-fused-to-steel bolted steel reservoir

structure located on Site 1 north of Salem Road, west of Hwy 400 is projected to be the least costly to

construct, operate and maintain. However, when compared to Option 1A, in-ground cast-in-place reinforced

concrete reservoir structure, the cylindrical at-grade reservoirs will be highly visible and therefore strategies

to mitigate and enhance the visual aesthetics should be developed

26 | P a g e

5.0 EVALUATION PROCESS

Technology Evaluation

In order to complete a thorough and defendable evaluation of the technology options for the Salem Road reservoir and pumping station options reviewed in this Technical Memorandum, an evaluation matrix to score the relative attributes of the proposed infrastructure assets was developed. The primary evaluation criteria specific to the different reservoir technologies is organized according to Construction, Financial and Technical attributes with each having the following considerations:

• Construction related evaluation criteria has been assigned a 20/100 (20%) relative importance weighting.This criteria takes into consideration the complexity of design and construction, the ease at which the facility can be expanded beyond 20 ML and the time and relative effort to complete the design, tendering and construction process. Each of the above noted criteria is assigned a relative weighting and then for each technology option ranked 1-3, with 1 being the best and 3 being the worse. When tota

• Financial related evaluation criteria has been assigned a 30/100 (30%) relative importance

weighting. This criteria takes into consideration projected costs associated with Engineering, Construction, Contingencies, Operations and Maintenance Costs and overall Life Cycle Costs as detailed in the previous section of the Technical Memorandum. Each of the above noted criteria is assigned a relative weighting and then for each technology option ranked 1-3 as above.

• Technical related evaluation criteria is considered the most important and has been assigned a

50/100 (50%) relative importance weighting. Technical criteria takes into consideration Occupational Health and Safety factors impacting operations and maintenance staff, Water System Security, Ease of Maintenance, potential for Temperature, Ice and Freeze issues, possibility of Leakage Failure, the relative Complexity of Repairs and Water Quality. As above, each of the noted criteria is assigned a relative weighting and then each technology option ranked 1-3.

The Technology Evaluation matrix with a summary of the scoring and Reservoir Technology weightings and rankings is given in the following Table 5-1 and in Appendix C. Based on the above weighting and ranking methodology, the lowest overall score is considered the optimal (best) Reservoir Technology. Overall, Options 3.A/3.B, precast/prestressed Concrete At-Grade Reservoir & Pumping Station has the lowest score and therefore highest ranking of the technology options reviewed in this Technical Memorandum.

Environmental Impact Evaluation

To complement the Technology Evaluation, a separate tabulation of Environmental Impact criteria and qualitative evaluations and scoring is tabulated and presented in Appendix C. The table itemizes Natural Environment and Socio-Cultural Environment criteria organized by Technology Option and by Site. For the selected Technology Options and Sites 1 and 2, the general conclusion is the CIP in-ground reservoir and pumping station on Site 1 is ranked as having the least environmental impact, whereas both at-grade cylindrical reservoirs on Site 2 are ranked as having the greatest environmental impacts. In all cases, it would be necessary to mitigate and manage the noted environmental impacts through the implementation phase of the project.

27 | P a g e

Table 5-1 Technology Evaluation Matrix

28 | P a g e

6.0 RECOMMENDATIONS

This Technical Memorandum has reviewed the feasibility of implementing three different reservoir

technologies on three separate sites. Summaries of the cost analyses and evaluation matrices are tabulated

in Appendix B and Appendix C, respectively. Some relevant points to highlight:

• All water storage reservoir technologies reviewed in the preparation of this document are equally

suitable for implementation by the City taking into consideration the technology specific design and

construction requirements as well as site specific requirements applicable to either Site 1 or Site 2.

• Site 3 was eliminated from the detailed analysis due to the limited property size and constrained

location.

• The use of an in-ground cast-in-place concrete reservoir is considered a technically viable

alternative at either of the two viable locations although Site 1 is recommended over Site 2. This

acknowledges that both sites can be redeveloped to meet the water system HGL requirements.

However, the topography of both sites have some challenges, drainage will require special attention

and soil conditions are unknown. A geotechnical investigation was not carried out in support of this

analysis.

• The major environmental impact of the reservoir itself is its appearance

o Construction of an in-ground cast-in-place concrete reservoir at either site is considered to

be the least visually disruptive and distractive solution compared to either circular at-grade

reservoir options.

o The visual impact of constructing a highly visible at-grade cylindrical water storage reservoir

can be mitigated by using aesthetically appealing tank designs and exterior coat systems

that either blend the reservoir into the surrounding terrain or promote a theme or other

municipal initiative

• Projected total annual life cycle costs for the two at-grade reservoir options are significantly lower

than the projected costs for the in-ground cast-in-place technology, regardless of which site is

considered.

• Site 1 appears to be more adaptable given the large property size, general condition and topography

of the land and adjacent commercial/industrial development.

• Both sites can be readily linked into the existing water distribution network with no apparent or

significant differences between the two sites.

• There is relatively no difference in the impact on adjacent development during or after construction

when comparing the two evaluated sites.

• Estimated construction costs and present value annualized life cycle cost (LCC) for Option 2A –

Glass-Fused-to-Steel Bolted Steel Reservoir, are projected to be the lowest at $23.6M CAD

On the strength of this analysis and evaluation of related Natural Environment, Socio-Cultural Environment,

Construction, Financial and Technical considerations, site flexibility, mitigatable impacts and highest

Technology Evaluation Score, Option 3A – Precast/Prestressed Concrete Cylindrical Reservoir and

Pumping Station on Site 1, north of Salem Road, west of Highway 400, is recommended.

29 | P a g e

7.0 REFERENCES

In preparation of the conceptual design and recommendations for the Salem Water Reservoir and Pumping

Station, WSP has reviewed the following documents:

• City of Barrie Official Plan, June 2009

• Water Transmission and Distribution Policies and Design Guidelines, City of Barrie, May 25, 2015

• Places to Grown Act, 2005

• Ministry of the Environment Design Guidelines for Drinking Water Systems, 2008

• InfoWater Water, 2013 • Water Storage and Distribution Master Plan, 2013 • Harvie Road Reservoir and Pumping Station Drawings dated March 2008. • Sunnidale Park Reservoir and Pumping Station Drawings dated March 2014.

AWWA Storage Standards applicable to this TM include the following:

• D100-11 Welded Carbon Steel Tanks for Water Storage

• D102-14 Coating Steel Water-Storage Tanks

• D103-09 Factory-Coated Bolted Carbon Steel Tanks for Water Storage

• D103-97 Factory-Coated Bolted Steel Tanks for Water Storage

• D104-11 Automatically Controlled, Impressed-Current Cathodic Protection for the Interior

Submerged Surfaces of Steel Water Storage Tanks

• D106-16 Sacrificial Anode Cathodic Protection Systems for the Interior Submerged Surfaces of

Steel Water Storage Tanks

• D108-10 Aluminum Dome Roofs for Water Storage Facilities

• D110-13 Wire- and Strand-Wound, Circular, Prestressed Concrete Water Tanks

• D115-06 Tendon-Prestressed Concrete Water Tanks

APPENDIX A

DRAWINGS

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

T

T

T

T

T

T

T

T

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

10T

H S

ID

ER

O

AD

10TH LINE

5T

H S

ID

ER

O

AD

10TH LINE

E

S

S

A

R

O

A

D

LOCKHART ROAD

LOCKHART ROAD

HU

RO

NIA

R

OA

D

SAUNDERS ROAD

BA

YV

IE

W

D

RIV

E

SA

UN

DE

RS

R

OA

D

VE

TE

RA

N'S

D

RIV

E

MAPLEVIEW DRIVE EASTMAPLEVIEW DRIVE WEST

E

S

S

A

R

O

A

D

VE

TE

RA

N'S

LN

HARVIE ROAD

BIG BAY POINT ROAD

W

E

L

H

A

M

R

O

A

D

BA

YV

IE

W

D

RIV

E

YO

NG

E S

TR

EE

T

CR

ES

CE

NT

S

T

.

P

A

U

L

'

S

Y

O

N

G

E

S

T

R

E

E

T

ARDAGH ROAD

M

A

P

L

E

T

O

N

TO

W

N LIN

E R

OA

D

C

O

U

N

TY

R

O

A

D

N

o. 27

LITTLE AVENUE

ARDAGH ROAD

TIFFIN STREETTIFFIN STREETCOUNTY ROAD No. 90

LA

K

E

S

H

O

R

E

D

R

IV

E

IN

NIS

FIL S

TR

EE

T

M

IL

L

E

R

D

R

IV

E

M

IL

L

E

R

D

R

IV

E

E

D

G

E

H

IL

L

DRIVE

F

E

R

N

D

A

L

E

D

R

I

V

E

N

O

R

T

H

F

E

R

N

D

A

L

E

D

R

N

O

R

T

H

D

U

N

L

O

P

S

T

R

E

E

T

W

E

S

T

F

E

R

N

D

A

L

E

D

R

IV

E

S

O

U

TH

A

N

N

E

S

T

R

E

E

T

S

O

U

T

H

S

A

N

F

O

R

D

S

T

R

E

E

T

A

N

N

E

S

T

R

E

E

T

N

O

R

T

H

R

O

S

S

S

T

.

C

O

L

L

IE

R

S

T

R

E

E

T

S

U

N

N

I

D

A

L

E

R

O

A

D

L

E

A

C

O

C

K

D

R

C

U

N

D

L

E

S

R

O

A

D

W

E

S

T

S

U

N

N

I

D

A

L

E

R

O

A

D

W

E

L

L

IN

G

T

O

N

S

T

R

E

E

T

W

E

S

T

H

I

G

H

W

A

Y

N

o

.

4

0

0

K

E

M

P

E

N

FELTD

R

IV

E

B

LA

K

E

S

TR

E

E

T

B

L

A

K

E

S

T

R

E

E

T

A

R

R

O

W

R

O

A

D

P

E

N

E

T

A

N

G

U

I

S

H

E

N

E

R

O

A

D

G

E

O

R

G

I

A

N

D

R

I

V

E

G

E

O

R

G

I

A

N

DRIVE

L

I

T

T

L

E

L

A

K

E

D

R

I

V

E

W

E

L

L

IN

G

T

O

N

S

T

R

E

E

T

G

R

O

V

E

S

T

R

E

E

T

E

A

S

T

V

IN

C

E

N

T

S

T

R

E

E

T

D

U

C

K

W

O

R

T

H

S

T

R

E

E

T

S

T

E

E

L

S

T

R

E

E

T

S

T

E

E

L

S

T

R

E

E

T

G

R

O

V

E

S

T

R

E

E

T

E

A

S

T

J

O

H

N

S

O

N

S

T

.

H

IG

H

W

A

Y

N

o

. 4

0

0

H

IG

H

W

A

Y

N

o

. 4

0

0

B

A

Y

F

IE

L

D

S

T

R

E

E

T

P

E

R

E

G

R

IN

E

S

T

L

IV

IN

G

S

T

O

N

E

S

T

. E

A

S

T

L

IV

IN

G

S

T

O

N

E

S

T

R

E

E

T

W

E

S

T

A

V

E

NORTH

PRESSURE ZONES

ZONE 3

SOUTH

ZONE 2

SOUTH

ZONE 3 SOUTH

REDUCED

ZONE 1

CHIEFTAIN

INCREASED

PRESS.

ZONE 3

NORTH

ZONE 2

NORTH

ZONE 2 NORTH

REDUCED

ZONE 3 NORTH

REDUCED

DWG. No.DATE:SCALE:

OCT 2017N.T.S.

CLIENT:

STUDY

AREA

G01

4

0

0

.0

0

400.00400.00

400.00

4

0

0

.

0

0

500.00

400.00

500.00

500.00

400.00400.00

500.00

4

0

0

.

0

0

400.00

400.00

500.00

500.00

500.00

5

0

0

.0

0

600.00

400.00

4

0

0

.0

0

4

0

0

.

0

0

600.00

400.00

600.00

400.00

400.00

400.00

600.00

400.00

400.00

400.00

4

0

0

.0

0

400.00

400.00

4

0

0

.

0

0

6

0

0

.

0

0

4

0

0

.

0

0

4

0

0

.

0

0

400.00

500.00

400.00

400.00

500.00

400.00

400.00

400.00400.00 400.00

400.00 400.00

400.00

5

0

0

.0

0

4

0

0

.0

0

500.00

4

0

0

.0

0

400.00

400.00400.00 400.00 400.00400.00

400.00

500.00

5

0

0

.0

0

400.00

400.00

400.00

400.00

400.00

400.00

400.00

500.00

500.00

500.00

400.00

400.00

500.00

500.00

500.00

500.00

400.00

400.00

500.00500.00

500.00

6

0

0

.

0

0

900.00

600.00

500.00

500.00

400.00

400.00

600.00

500.00

500.00

40

0.0

0

750.00

900.00

900.00

400.00

4

0

0

.

0

0

500.00

600.00

400.00

5

0

0

.0

0

400.00

5

0

0

.

0

0

500.00

5

0

0

.

0

0

4

0

0

.

0

0

750.00

400.00

4

0

0

.

0

0

400.00

400.00400.00

400.00

4

0

0

.

0

0

900.00

500.00

600.00

600.00

6

0

0

.

0

0

6

0

0

.

0

0

6

0

0

.0

0

6

0

0

.0

0

6

0

0

.

0

0

6

0

0

.

0

0

6

0

0

.

0

0

6

0

0

.

0

0

600.00

600.00

6

0

0

.

0

0

6

0

0

.

0

0

6

0

0

.

0

0

6

0

0

.

0

0

6

0

0

.

0

0

6

0

0

.

0

0

750.00

6

0

0

.

0

0

750.00

1200.00

1200.00

1200.00

1200.00

1200.00

600.00

1200.00

1050.00

1

2

0

0

.0

0

400.00

400.00

500.00

400.00

500.00

500.00

4

0

0

.

0

0

4

0

0

.

0

0

400.00400.00

4

0

0

.

0

0

400.00

400.00

400.00

4

0

0

.

0

0

500.00

500.00

400.00

6

0

0

.0

0

750.00

60

0.0

0

600.00

7

5

0

.0

0

7

5

0

.

0

0

600.00

60

0.0

0

600.00

750.00

750.00

500.00

400.00

400.00

400.00

4

0

0

.

0

0

4

0

0

.

0

0

400.00

400.00

400.00

R

R

R

R

R

R

R

R

R

T

T

T

T

P

P

P

P

P

P

P

P

P

10T

H S

ID

ER

O

AD

10TH LINE

5T

H S

ID

ER

OA

D

10TH LINE

E

S

S

A

R

O

A

D

LOCKHART ROAD

LOCKHART ROAD

HU

RO

NIA

R

OA

D

SAUNDERS ROAD

BA

YV

IE

W

D

RIV

E

SA

UN

DE

RS

R

OA

D

VE

TE

RA

N'S

D

RIV

E

MAPLEVIEW DRIVE EASTMAPLEVIEW DRIVE WEST

E

S

S

A

R

O

A

D

VE

TE

RA

N'S

LN

HARVIE ROAD

BIG BAY POINT ROAD

W

E

L

H

A

M

R

O

A

D

BA

YV

IE

W

D

RIV

E

YO

NG

E S

TR

EE

T

CR

ES

CE

NT

S

T

.

P

A

U

L

'

S

Y

O

N

G

E

S

T

R

E

E

T

ARDAGH ROAD

M

A

P

L

E

T

O

N

TO

W

N LIN

E R

OA

D

C

O

U

N

TY

R

O

A

D

N

o. 27

LITTLE AVENUE

ARDAGH ROAD

IN

NIS

FIL S

TR

EE

T

F

E

R

N

D

A

L

E

D

R

IV

E

S

O

U

T

H

A

V

E

S

T

A

N

D

A

R

D

S

C

IT

Y

B

A

R

R

IE

STUDY AREA AND PRESSURE ZONE 2S - 3S

NORTH

EX. HARVIE RD RESERVOIR

AND PUMPING STATION

CAPACITY = 27.7 ML

BOT. ELEV. = 301.90

TOP ELEV. = 352.90

EX. BARRIE SWTP

EX. MAPLEVIEW DR RESERVOIR

CAPACITY = 4.5 ML

BOT. ELEV. = 337.65

TOP ELEV. = 350.15

STUDY AREA

PROP. SALEM RD. RESERVOIR

AND PUMPING STATION

CAPACITY = 20 ML

TOP ELEV. = 308.0

BOT. ELEV. = 302.0 (IN GROUND / ON GROUND)

DWG. No.DATE:SCALE:

OCT 2017N.T.S.

CLIENT:

G02

ASSUMED LOCATION OF

SALEM RD FACILITY PER

WATER SYSTEM MODELING

BIG BAY POINT ROAD

PUMPING STATION

2 PUMPS x 100 l/s @47m

2 PUMPS x 150 l/s @47m

PREFERRED SITE 1

294 292

290

288

297

298

298

308

296

296

304 305

306

303 300

290

307

306

305

300

310

285

300

300

300

295

290

310

305

295

309

299

295

297

290

311

311

311

313

312

312

311

312

310

308

297

305

307

306

305

300

295

280 285

290

295

300

275

280

310

306

307

308

309

309

312

311

310

309

307 305

285

290

295

299

277

298

298

295

300

309 308

301 300 303

301

307

305

297

300

304

307

309

COMMERCE PARK DR

HW

Y 4

00

GALAXY

CINEMA

HY

DR

O C

OR

RID

OR

SALEM RD

LOCKHART RD

SITE - 1

VE

TE

RA

NS

DR

NO

RR

IS D

R

SITE - 3

SITE - 2

1A

2A / 3A

2B / 3B

1B

100m 75m 50m 25m 0 100m

DATE:SCALE:

OCT 2017

THE CITY OF BARRIE

SALEM RESERVOIR AND PUMPING STATION

100 Commerce Valley Drive West, Thornhill, ON, Canada L3T 0A1Tel: (905) 822-1100 Fax: (905) 822-0055 www.wsp.com

CLIENT:

23/1

0/2

017 2

:24:4

1 P

MX

:\D

IV10\3

2-1

5075 -

Sale

m R

eserv

oir &

PS

\MU

N\R

eserv

oir &

Pum

pin

g S

tation\0

0 -

BIM

\Pro

c\F

IG 1

- O

VE

RV

IEW

OF

LO

CA

L S

TU

DY

AR

EA

_R

15.r

vt

OVERALL SITE PLANFIG.-1 OVERVIEW OF LOCAL STUDY AREA

308

310

296

304

305 306

307

308

307

303

300

290

285

300

300

303

301

307

306 3

05

304

SALEM RD

COMMERCE PARK DR

HW

Y 4

00

RESERVOIRTOP.EL. 308.5

PUMPING STATIONF.F.EL. 309.0

PROPERTY LINE

PR

OP

ER

TY

LINE

PR

OP

ER

TY

LINE

GALAXY

CINEMA

1

FIG-04

CAPACITY10ML

FUTURECAPACITY

10ML

OVERFLOW PIPE

305.0 m

30.0 m

30.0 m

40.0 m

DATE:SCALE:

OCT 2017

THE CITY OF BARRIESALEM RESERVOIR AND PUMPING STATION (SITE-1)

100 Commerce Valley Drive West, Thornhill, ON, Canada L3T 0A1Tel: (905) 822-1100 Fax: (905) 822-0055 www.wsp.com

CLIENT:

23/1

0/2

017 2

:44:1

6 P

MX

:\D

IV10\3

2-1

5075 -

Sale

m R

eserv

oir &

PS

\MU

N\R

eserv

oir &

Pum

pin

g S

tation\0

0 -

BIM

\Pro

c\F

IG 2

- S

ITE

PLA

N O

PT

ION

S 1

A_R

15.r

vt

SITE PLAN - OPTION 1AFIG.- 2: SITE-1 PLAN OPTIONS 1A

PR

OP

ER

TY

LIN

E

PR

OP

ER

TY

LIN

E

SALEM RD.

GRADE EL. 309.0 m ±

RD. EL. 296.0 m

RESERVOIRCAPACITY 10ML + 10ML (FUTURE)

RESERVOIRTOP EL. 308.5

H.W.L. 308.0 m

L.W.L. 302.0 m

DATE:SCALE:

OCT 2017

THE CITY OF BARRIESALEM RESERVOIR AND PUMPING STATION (SITE-1)

100 Commerce Valley Drive West, Thornhill, ON, Canada L3T 0A1Tel: (905) 822-1100 Fax: (905) 822-0055 www.wsp.com

CLIENT:

23/1

0/2

017 2

:59:5

6 P

MX

:\D

IV10\3

2-1

5075 -

Sale

m R

eserv

oir &

PS

\MU

N\R

eserv

oir &

Pum

pin

g S

tation\0

0 -

BIM

\Pro

c\F

IG 2

- S

ITE

PLA

N O

PT

ION

S 1

A_R

15.r

vt

SECTION & 3D VIEW - OPTION -1A

3D VIEW FROM EAST

3D VIEW FROM WEST

SECTION

FIG.- 3: SITE-1 OPTION 1A RENDERINGS

294 292

290

288

297

298

298

308

303 300

290

306

300

285

300

300

300

295

290

310

305

295

299

295

297

290

311

311

311

313

312

312

311

312

310

308

297

305

307

306

305

300

295

280 285

290

295

300

275

280

310

306

307

308

309

312

311

310

309

307 305

285

290

295

299

277

298

298

295

300

309 308

301 300 303

301

309

305

COMMERCE PARK DR

HW

Y 4

00

GALAXY

CINEMA

HY

DR

O C

OR

RID

OR

SALEM RD

LOCKHART RD

1

FIG-2

SITE - 1

(30 Salem Road)

VE

TE

RA

NS

DR

NO

RR

IS D

R

PROPOSED RESERVOIRAND BOOSTER PUMPINGSTATION

100m 75m 50m 25m 0 100m

DATE:SCALE:

OCT 2017

THE CITY OF BARRIESALEM RESERVOIR AND PUMPING STATION (SITE-1)

100 Commerce Valley Drive West, Thornhill, ON, Canada L3T 0A1Tel: (905) 822-1100 Fax: (905) 822-0055 www.wsp.com

CLIENT:

23/1

0/2

017 2

:39:4

4 P

MX

:\D

IV10\3

2-1

5075 -

Sale

m R

eserv

oir &

PS

\MU

N\R

eserv

oir &

Pum

pin

g S

tation\0

0 -

BIM

\Pro

c\F

IG 4

- S

ITE

PLA

N O

PT

ION

S 2

A &

3A

_R

15.r

vt

SITE PLAN OPTIONS 2A & 3AFIG.- 4: SITE-1 PLAN OPTIONS 2A & 3A

High Water Level

308 m

F. F. Level

302 m

PR

OP

ER

TY

LIN

E

RESERVOIRCAPACITY 10ML + 10ML (FUTURE)

PR

OP

ER

TY

LIN

E

SALEM ROAD

ROAD EL. 296.0 m

PUMPING STATIONF.F. EL. 302.0

DATE:SCALE:

OCT 2017

THE CITY OF BARRIESALEM RESERVOIR AND PUMPING STATION (SITE-1)

100 Commerce Valley Drive West, Thornhill, ON, Canada L3T 0A1Tel: (905) 822-1100 Fax: (905) 822-0055 www.wsp.com

CLIENT:

23/1

0/2

017 3

:02:2

4 P

MX

:\D

IV10\3

2-1

5075 -

Sale

m R

eserv

oir &

PS

\MU

N\R

eserv

oir &

Pum

pin

g S

tation\0

0 -

BIM

\Pro

c\F

IG 4

- S

ITE

PLA

N O

PT

ION

S 2

A &

3A

_R

15.r

vt

SECTION AND 3D VIEWS OPTIONS 2A & 3A

3D VIEW FROM WEST

3D VIEW FROM EAST

SECTION

N.T.S.

FIG.- 5: SITE-1 OPTIONS 2A & 3A RENDERINGS

APPENDIX B

CAPITAL AND LIFE CYCLE COST ESTIMATES

ITEM DESCRIPTION

Option 1A:

CIP Concrete In-

ground Reservoir

& PS

-

Site 1

North Side Salem

Road

Option 1B:

CIP Concrete In-

ground Reservoir

& PS

-

Site 2

South Side

Salem Road

Option 2A:

Glass Fused to

Steel At-Grade

Reservoir & PS

-

Site 1

North Side Salem

Road

Option 2B:

Glass Fused to

Steel At-Grade

Reservoir & PS

-

Site 2

South Side

Salem Rd

Option 3.A:

Precast,

prestressed

Concrete At-

Grade Reservoir

& PS

-

Site 1

North Side Salem

Rd

Option 3. B:

Precast,

prestressed

Concrete At-

Grade Reservoir

& PS

-

Site 2

South Side

Salem Rd

A.

SUBTOTAL - Div 1-16 $25,967,000 $28,066,000 $17,687,000 $18,145,000 $20,850,000 $21,175,000

B.

ALLOWANCE @ 20% $5,193,400 $5,613,200 $3,537,400 $3,629,000 $4,170,000 $4,235,000

C. $31,160,400 $33,679,200 $21,224,400 $21,774,000 $25,020,000 $25,410,000

ALL COSTS LESS HST

ESTIMATED TOTAL

CONSTRUCTION COSTS

ESTIMATED

CONTINGENCY COSTS

ESTIMATED

CONSTRUCTION COSTS

TECHNOLOGY DESCRIPTION

COMPARISON OF ESTIMATED CONSTRUCTION COSTSSALEM ROAD RESERVOIR AND PUMPING STATION CONCEPTUAL DESIGN - TECHNOLOGY ASSESSMENT

Summary m:\2017\salem reservoir and pumping station - august 2017\final_appendices\appendix_b\ref\salem_reservoir_ps_cost_estimate_comparison_technology assessment_mep_dec06_2017.xls

OPTION 1A : In-ground Cast-in-Place Concrete Reservoir - Site 1, North of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

1. 1 Lump Sum 2,360,703.60$ Incl. in Unit Price Incl. in Unit Price 2,360,703.60$ 2,360,703.60$

2. 8,898,496.00$

1 Lump Sum 386,156.00$ Incl. in Unit Price Incl. in Unit Price 386,156.00$

1 Lump Sum 75,000.00$ Incl. in Unit Price Incl. in Unit Price 75,000.00$

3040 m2 1,200.00$ Incl. in Unit Price Incl. in Unit Price 3,648,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

19000 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 950,000.00$

30201 m3 100.00$ Incl. in Unit Price Incl. in Unit Price 3,020,120.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

100 m 1,100.00$ 50% $ 550.00 165,000.00$

48 m 1,500.00$ 50% $ 750.00 108,000.00$

49 m 450.00$ 50% $ 225.00 33,140.00$

135 m 500.00$ 50% $ 250.00 101,480.00$

40 m 500.00$ 50% $ 250.00 30,000.00$

14 m 500.00$ 50% $ 250.00 10,500.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

1 Lump Sum 8,000.00$ Incl. in Unit Price Incl. in Unit Price 8,000.00$

1 Lump Sum 6,000.00$ Incl. in Unit Price Incl. in Unit Price 6,000.00$

120 m3 500.00$ 50% $ 250.00 90,000.00$

553 m 40.00$ Incl. in Unit Price Incl. in Unit Price 22,100.00$

19000 m2 5.00$ Incl. in Unit Price Incl. in Unit Price 95,000.00$

1 Lump Sum 100,000.00$ Incl. in Unit Price Incl. in Unit Price 100,000.00$

3. 9,767,710.00$

11,468 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 2,866,930.00$

1 Lump Sum -$ Incl. in Unit Price Incl. in Unit Price -$

4897 m3 1,400.00$ Incl. in Unit Price Incl. in Unit Price 6,855,780.00$

1 Lump Sum 25,000.00$ Incl. in Unit Price Incl. in Unit Price 25,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

4. 156,660.00$

298 m2 25.00$ Incl. in Unit Price Incl. in Unit Price 7,460.00$

298 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 14,920.00$

298 m2 200.00$ Incl. in Unit Price Incl. in Unit Price 59,680.00$

298 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 74,600.00$

5. 250,860.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

4 ea 100.00$ 33% $ 33.00 530.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

4 ea 15,000.00$ 33% $ 4,950.00 79,800.00$

1 ea 15,000.00$ 33% $ 4,950.00 19,950.00$

2 ea 15,000.00$ 33% $ 4,950.00 39,900.00$

8 m2 600.00$ 33% $ 198.00 6,480.00$

55 m 200.00$ 33% $ 66.00 14,710.00$

17 m 200.00$ 33% $ 66.00 4,500.00$

9 ea 1,500.00$ 33% $ 495.00 17,960.00$

21 m 150.00$ 33% $ 49.50 4,130.00$

5 m2 500.00$ 33% $ 165.00 3,050.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

6. Includes Div6+7+8+9+10 163,740.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

7.

364 m2 5.00$ 33% $ 1.65 2,420.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 30,000.00$ 33% $ 9,900.00 39,900.00$

8.

Total Cost Estimate

02380 Erosion and Sediment Control

All Wood and Plastics Items

Watertight Drainage Hatch (1219x1219mm) - 2

Roof Access Hatch (1000 x 1000mm) - 1

3200 Concrete Reinforcement

Division 4 - Masonry

4080 Mansonry Reinforcement and Connectors

5501 Metal Fabrications - Architectural

5502 Metal Fabrications - Structural

Steel Bollards

All Other Metal Items

2140 Dewatering

Division 5 - Metals

2701 Aggregates

2511 Watermains

5310 Specialty Items

4200 Unit Masonry

4090 Masonry Accessories

3345 Concrete Curing and Finishing

2311 Site Grading

(i) Pumping Station

3100 Concrete Forms and Accessories

3300 Cast in Place Concrete

(ii) Reservoir

(iii) Retention Chamber

3375 Concrete Floor Toppings

Division 3 - Concrete

Division 8 - Metal Doors and Frames

Division 7 - Building Specialties

Division 6 - Carpentry

3372 Non-shrink Grout

(i) Pumping Station

(ii) Reservoir

(iii) Retention Chamber

2100 General Allowances (5%)

Description

2936 Landscaping

2911 Topsoil and Finish Grading

2821 Chain Link Fences and Gates

2723 Granular Sub-Base

2315 Excavation, Trenching and Backfill (& Disposal)

Division 1 - General Requirements (10%)

2721 Granular Base

Division 2 - Site Work

4060 Mortar and Masonry Grout

FRP Platform

FRP Handrail (Retention+Reservoir)

FRP Ladder

Aluminum Handrail (Staircase)

2150 Shoring Systems

5000 Metals General Requirements

02530 Sewerage Gravity Sanitary Sewer

2741 Asphalt Paving

2200 Site Preparation

02362 Dust Control

02630 Storm Sewers

STM - Landscaping Drainage 450 mm

STM - Overflow Outlet 600 mm

STM - 200 mm

WM - 600mm, steel casing

WM - 500mm

07610 Preformed Metal Standing Seam Roofing System

7200 Insulation

7130 Membrane Waterproofing

Access Hatch (914 x 914 mm) - 4

Staircase (Pumping Station)

Aluminum Handrail (Mezz+Basem't+Bldg)

Aluminum Grating (Pumping Station)

Option 1A - CIP Concrete m:\2017\salem reservoir and pumping station - august 2017\appendices\appendix_b\salem_reservoir_ps_cost_estimate_comparison_technology assessment_mep_oct25_2017.xls

OPTION 1A : In-ground Cast-in-Place Concrete Reservoir - Site 1, North of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

Total Cost EstimateDescription

8 ea 3,000.00$ 25% $ 750.00 30,000.00$

1 Lump Sum 3,000.00$ Incl. in Unit Price Incl. in Unit Price 3,000.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

9.

298 m2 25.00$ 25% $ 6.25 9,320.00$

1 Lump Sum 2,000.00$ 25% $ 500.00 2,500.00$

10.

1 Lump Sum 20,000.00$ 50% $ 10,000.00 30,000.00$

11.

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1,000,850.00$

4 Each 85,000.00$ 33% $ 28,050.00 452,200.00$

3 Each 60,000.00$ 33% $ 19,800.00 239,400.00$

3 Each 75,000.00$ 33% $ 24,750.00 299,250.00$

2 Each 35,000.00$ 75% $ 26,250.00 122,500.00$ 122,500.00$

26,600.00$ 106,400.00$

1 Each 20,000.00$ 33% $ 6,600.00 39,900.00$

1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

1 Each 30,000.00$ 33% $ 9,900.00 169,570.00$

12. 5,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 21,950.00$

3 Each 5,500.00$ 33% $ 1,815.00 11,170.00$

14 Each 600.00$ 33% $ 198.00 15,960.00$

2 Each 6,000.00$ 33% $ 1,980.00 2,390.00$

6 Each 300.00$ 33% $ 99.00 26,600.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 66,500.00$

1 Each 50,000.00$ 33% $ 16,500.00 15,000.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price

13. 75,000.00$

1 Lump Sum 50,000.00$ 50% $ 25,000.00 incl Div14+15 2,082,400.00$

14. 15,000.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 19,950.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 26,600.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00

20 m 300.00$ 33% $ 99.00 13,300.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 19,950.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 6,650.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 19,950.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00

3 Each 8,000.00$ 33% $ 2,640.00 7,980.00$

1 Lump Sum 6,000.00$ 33% $ 1,980.00 6,650.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 239,400.00$

9 Each 20,000.00$ 33% $ 6,600.00 13,300.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 66,500.00$

1 Lump Sum 50,000.00$ 33% $ 16,500.00 33,250.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 93,100.00$

1 Lump Sum 70,000.00$ 33% $ 23,100.00 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 887,850.00$

16. 30,000.00$

1 Lump Sum 30,000.00$ Incl. in Unit Price Incl. in Unit Price 6,650.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 199,500.00$

1 Each 150,000.00$ 33% $ 49,500.00 133,000.00$

1 Each 100,000.00$ 33% $ 33,000.00 26,600.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 79,800.00$

4 Each 15,000.00$ 33% $ 4,950.00 66,500.00$

2 Each 25,000.00$ 33% $ 8,250.00 212,800.00$

8 Each 20,000.00$ 33% $ 6,600.00 133,000.00$

1 Lump Sum 100,000.00$ 33% $ 33,000.00

Div 2-16 23,607,036$ 23,607,036$ Total 25,967,740$ 25,967,740$

11260 Chemical Storage and Feed Equipment

Solonoid Valve - 19mm

15204 Process Piping Specialties

All Other Doors and Windows Items

Bi-directional Magnetic Flowmeter - 300mm

Magnetic Flowmeter - 300mm

Magnetic Flowmeter - 200mm

Centrifuge Pumps

Submersible Sump Pump

Vertical Turbine Pump

08710 Door Hardware

09900 Painting and Protective Coatings

Division 11 - Equipment

Division 10 - Miscellaneous Specialties

Division 9 - Dry Wall and Painting

11000 Equipment General Requirements

15060 Pipe Fittings

15010 Mechanical General Requirements

13305 Field Wiring

13141 Pressure Gauge

16461 Dry Type Transformers

16820 Motor Control Centre

16816 Variable Frequency Drives

16811 Motor Starters

16627 Automatic Transfer Switches

16556 Diesel Engine Generator Set

16818 Soft Starter Drives

16560 Emergency Chlorine Scrubber

Division 16 - Electrical

11560 Flowmeter

15100 Plumbing Piping

16000 Electrical General Works

15955 Piping Leakage Testing

15950 HVAC Systems Testing, Adjusting, and Balancing

15900 HVAC Controls

15830 Fans

15810 Metal Ductwork and Accessories

15802 Fiberglass Reinforced Plastic Ductwork

15760 Electric Unit Heaters

15440 Plumbing Equipment

15410 Plumbing Fixtures

11215 Pumps

13140 Pressure Transmitter

15202 Vibration and Noise Control

15201 Piping Support Systems

15200-14 Copper Tubing and Fittings

Division 13 - Instrumentation and Control

150mm dia. Pipe

Division 15 - Mechanical

All Other Finishes Items

10200 Louvres and Vents

Division 14 - Monorail and Hoist

14620 Monorail and Hoist

13130 Float Switch

13110 Ultrasonic Level Transmitter

13105 General Instrumentation Requirements

13010 Process Control - General Requirements

13480 SCADA System Integrator

13400 Programmable Logic Controller

08110 Steel Door Frames

Option 1A - CIP Concrete m:\2017\salem reservoir and pumping station - august 2017\appendices\appendix_b\salem_reservoir_ps_cost_estimate_comparison_technology assessment_mep_oct25_2017.xls

OPTION 1.B: In-ground Cast-in-Place Concrete Reservoir - Site 2, South of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

1. 1 Lump Sum 2,551,459.45$ Incl. in Unit Price Incl. in Unit Price 2,551,459.45$ 2,551,459.45$

2. 10,806,054.50$

1 Lump Sum 482,134.50$ Incl. in Unit Price Incl. in Unit Price 482,134.50$

1 Lump Sum 90,000.00$ Incl. in Unit Price Incl. in Unit Price 90,000.00$

3040 m2 1,200.00$ Incl. in Unit Price Incl. in Unit Price 3,648,000.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

25000 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 1,250,000.00$

46047 m3 100.00$ Incl. in Unit Price Incl. in Unit Price 4,604,690.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 25,000.00$ Incl. in Unit Price Incl. in Unit Price 25,000.00$

80 m 1,100.00$ 50% $ 550.00 132,000.00$

48 m 1,500.00$ 50% $ 750.00 108,000.00$

55 m 450.00$ 50% $ 225.00 37,130.00$

100 m 500.00$ 50% $ 250.00 75,000.00$

20 m 500.00$ 50% $ 250.00 15,000.00$

14 m 500.00$ 50% $ 250.00 10,500.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

1 Lump Sum 8,000.00$ Incl. in Unit Price Incl. in Unit Price 8,000.00$

1 Lump Sum 6,000.00$ Incl. in Unit Price Incl. in Unit Price 6,000.00$

80 m3 500.00$ 50% $ 250.00 60,000.00$

553 m 40.00$ Incl. in Unit Price Incl. in Unit Price 22,100.00$

17500 m2 5.00$ Incl. in Unit Price Incl. in Unit Price 87,500.00$

1 Lump Sum 100,000.00$ Incl. in Unit Price Incl. in Unit Price 100,000.00$

3. 9,767,710.00$

11,468 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 2,866,930.00$

1 Lump Sum -$ Incl. in Unit Price Incl. in Unit Price -$

4897 m3 1,400.00$ Incl. in Unit Price Incl. in Unit Price 6,855,780.00$

1 Lump Sum 25,000.00$ Incl. in Unit Price Incl. in Unit Price 25,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

4. 156,660.00$

298 m2 25.00$ Incl. in Unit Price Incl. in Unit Price 7,460.00$

298 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 14,920.00$

298 m2 200.00$ Incl. in Unit Price Incl. in Unit Price 59,680.00$

298 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 74,600.00$

5. 250,860.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

4 ea 100.00$ 33% $ 33.00 530.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

4 ea 15,000.00$ 33% $ 4,950.00 79,800.00$

1 ea 15,000.00$ 33% $ 4,950.00 19,950.00$

2 ea 15,000.00$ 33% $ 4,950.00 39,900.00$

8 m2 600.00$ 33% $ 198.00 6,480.00$

Aluminum Handrail (Mezz+Basem't+Bldg) 55 m 200.00$ 33% $ 66.00 14,710.00$

17 m 200.00$ 33% $ 66.00 4,500.00$

9 ea 1,500.00$ 33% $ 495.00 17,960.00$

21 m 150.00$ 33% $ 49.50 4,130.00$

5 m2 500.00$ 33% $ 165.00 3,050.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

6. Includes Div6+7+8+9+10 163,740.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

7.

364 m2 5.00$ 33% $ 1.65 2,420.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 30,000.00$ 33% $ 9,900.00 39,900.00$

8.

8 ea 3,000.00$ 25% $ 750.00 30,000.00$

1 Lump Sum 3,000.00$ Incl. in Unit Price Incl. in Unit Price 3,000.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

9.

298 m2 25.00$ 25% $ 6.25 9,320.00$

Total Cost Estimate

Aluminum Handrail (Staircase)

All Wood and Plastics Items

All Other Doors and Windows Items

Watertight Drainage Hatch (1219x1219mm) - 2

Roof Access Hatch (1000 x 1000mm) - 1

Access Hatch (914 x 914 mm) - 4

Staircase (Pumping Station)

Steel Bollards

5501 Metal Fabrications - Architectural

5502 Metal Fabrications - Structural

07610 Preformed Metal Standing Seam Roofing System

Division 8 - Metal Doors and Frames

08110 Steel Door Frames

08710 Door Hardware

Division 9 - Dry Wall and Painting

09900 Painting and Protective Coatings

Division 6 - Carpentry

Division 7 - Building Specialties

7130 Membrane Waterproofing

7200 Insulation

All Other Metal Items

FRP Platform

4060 Mortar and Masonry Grout

FRP Handrail (Retention+Reservoir)

FRP Ladder

Aluminum Grating (Pumping Station)

4080 Mansonry Reinforcement and Connectors

4090 Masonry Accessories

4200 Unit Masonry

Division 5 - Metals

5000 Metals General Requirements

5310 Specialty Items

(ii) Reservoir

(iii) Retention Chamber

3345 Concrete Curing and Finishing

3372 Non-shrink Grout

3375 Concrete Floor Toppings

Division 4 - Masonry

(i) Pumping Station

(ii) Reservoir

(iii) Retention Chamber

3200 Concrete Reinforcement

3300 Cast in Place Concrete

(i) Pumping Station

2821 Chain Link Fences and Gates

2911 Topsoil and Finish Grading

2936 Landscaping

Division 3 - Concrete

3100 Concrete Forms and Accessories

2701 Aggregates

2721 Granular Base

2723 Granular Sub-Base

2741 Asphalt Paving

STM - Landscaping Drainage 450 mm

STM - Overflow Outlet 600 mm

02530 Sewerage Gravity Sanitary Sewer

WM - 600mm, steel casing

WM - 500mm

02380 Erosion and Sediment Control

STM - 200 mm

02630 Storm Sewers

2200 Site Preparation

2311 Site Grading

2315 Excavation, Trenching and Backfill (& Disposal)

02362 Dust Control

2511 Watermains

Description

Division 1 - General Requirements (10%)

Division 2 - Site Work

2100 General Allowances (5%)

2140 Dewatering

2150 Shoring Systems

Option 1B - CIP Concrete \\thfiler1.mmm.ca\wpdocs$\2017\salem reservoir and pumping station - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment_mep_oct20_2017.xls

OPTION 1.B: In-ground Cast-in-Place Concrete Reservoir - Site 2, South of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

Total Cost EstimateDescription

1 Lump Sum 2,000.00$ 25% $ 500.00 2,500.00$

10.

1 Lump Sum 20,000.00$ 50% $ 10,000.00 30,000.00$

11.

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1,000,850.00$

4 Each 85,000.00$ 33% $ 28,050.00 452,200.00$

3 Each 60,000.00$ 33% $ 19,800.00 239,400.00$

3 Each 75,000.00$ 33% $ 24,750.00 299,250.00$

2 Each 35,000.00$ 75% $ 26,250.00 122,500.00$ 122,500.00$

106,400.00$

1 Each 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

Bi-directional Magnetic Flowmeter - 300mm 1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

12. 169,570.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

3 Each 5,500.00$ 33% $ 1,815.00 21,950.00$

14 Each 600.00$ 33% $ 198.00 11,170.00$

2 Each 6,000.00$ 33% $ 1,980.00 15,960.00$

6 Each 300.00$ 33% $ 99.00 2,390.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

13.

1 Lump Sum 50,000.00$ 50% $ 25,000.00 75,000.00$

14. 2,082,400.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 6,000.00$ 33% $ 1,980.00 7,980.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

9 Each 20,000.00$ 33% $ 6,600.00 239,400.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

1 Lump Sum 70,000.00$ 33% $ 23,100.00 93,100.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

16. 887,850.00$

1 Lump Sum 30,000.00$ Incl. in Unit Price Incl. in Unit Price 30,000.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Each 150,000.00$ 33% $ 49,500.00 199,500.00$

1 Each 100,000.00$ 33% $ 33,000.00 133,000.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

4 Each 15,000.00$ 33% $ 4,950.00 79,800.00$

2 Each 25,000.00$ 33% $ 8,250.00 66,500.00$

8 Each 20,000.00$ 33% $ 6,600.00 212,800.00$

1 Lump Sum 100,000.00$ 33% $ 33,000.00 133,000.00$

Div 2-16 25,514,594.50$ 25,514,595$ Total 28,066,053.95$ 28,066,054$

11260 Chemical Storage and Feed Equipment

Magnetic Flowmeter - 300mm

Magnetic Flowmeter - 200mm

Centrifuge Pumps

Submersible Sump Pump

Vertical Turbine Pump

11560 Flowmeters

11215 Pumps

16560 Emergency Chlorine Scrubber

16627 Automatic Transfer Switches

16811 Motor Starters

16816 Variable Frequency Drives

16818 Soft Starter Drives

16820 Motor Control Centre

15950 HVAC Systems Testing, Adjusting, and Balancing

15955 Piping Leakage Testing

Division 16 - Electrical

16000 Electrical General Works

16461 Dry Type Transformers

16556 Diesel Engine Generator Set

15440 Plumbing Equipment

15760 Electric Unit Heaters

15802 Fiberglass Reinforced Plastic Ductwork

15810 Metal Ductwork and Accessories

15830 Fans

15900 HVAC Controls

15200-14 Copper Tubing and Fittings

15201 Piping Support Systems

15202 Vibration and Noise Control

15204 Process Piping Specialties

15205 Process Valves and Operators

15410 Plumbing Fixtures

14620 Monorail and Hoist

Division 15 - Mechanical

15010 Mechanical General Requirements

15060 Pipe Fittings

15100 Plumbing Piping

15200 Process Piping and Fittings

13140 Pressure Transmitter

13141 Pressure Gauge

13305 Field Wiring

13400 Programmable Logic Controller

13480 SCADA System Integrator

Division 14 - Monorail and Hoist

Division 13 - Instrumentation and Control

13010 Process Control - General Requirements

13105 General Instrumentation Requirements

13110 Ultrasonic Level Transmitter

13130 Float Switch

All Other Finishes Items

Division 10 - Miscellaneous Specialties

10200 Louvres and Vents

Division 11 - Equipment

11000 Equipment General Requirements

Option 1B - CIP Concrete \\thfiler1.mmm.ca\wpdocs$\2017\salem reservoir and pumping station - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment_mep_oct20_2017.xls

OPTION 2A : At-ground Glass Fused to Steel Reservoir & PS - Site 1, North of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

1. 1 Lump Sum 1,607,997.15$ Incl. in Unit Price Incl. in Unit Price 1,607,997.15$ 1,607,997.15$

2. 2,740,171.50$

1 Lump Sum 91,021.50$ Incl. in Unit Price Incl. in Unit Price 91,021.50$

1 Lump Sum 50,000.00$ Incl. in Unit Price Incl. in Unit Price 50,000.00$

485 m2 1,200.00$ Incl. in Unit Price Incl. in Unit Price 581,510.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

19000 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 950,000.00$

2089 m3 100.00$ Incl. in Unit Price Incl. in Unit Price 208,920.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

150 m 1,100.00$ 50% $ 550.00 247,500.00$

60 m 1,500.00$ 50% $ 750.00 135,000.00$

49 m 450.00$ 50% $ 225.00 33,140.00$

135 m 500.00$ 50% $ 250.00 101,480.00$

40 m 500.00$ 50% $ 250.00 30,000.00$

14 m 500.00$ 50% $ 250.00 10,500.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

1 Lump Sum 8,000.00$ Incl. in Unit Price Incl. in Unit Price 8,000.00$

1 Lump Sum 6,000.00$ Incl. in Unit Price Incl. in Unit Price 6,000.00$

120 m3 500.00$ 50% $ 250.00 90,000.00$

553 m 40.00$ Incl. in Unit Price Incl. in Unit Price 22,100.00$

19000 m2 5.00$ Incl. in Unit Price Incl. in Unit Price 95,000.00$

1 Lump Sum 30,000.00$ Incl. in Unit Price Incl. in Unit Price 30,000.00$

3. 2,504,590.00$

1,810 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 452,590.00$

1 Lump Sum -$ Incl. in Unit Price Incl. in Unit Price -$

1673 m3 1,200.00$ Incl. in Unit Price Incl. in Unit Price 2,007,000.00$

1 Lump Sum 25,000.00$ Incl. in Unit Price Incl. in Unit Price 25,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

4. 156,660.00$

298 m2 25.00$ Incl. in Unit Price Incl. in Unit Price 7,460.00$

298 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 14,920.00$

298 m2 200.00$ Incl. in Unit Price Incl. in Unit Price 59,680.00$

298 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 74,600.00$

5. 134,690.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

4 ea 100.00$ 33% $ 33.00 530.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

2 ea 15,000.00$ 33% $ 4,950.00 39,900.00$

1 ea 15,000.00$ 33% $ 4,950.00 19,950.00$

8 m2 600.00$ 33% $ 198.00 6,480.00$

20 m 200.00$ 33% $ 66.00 5,320.00$

10 m 200.00$ 33% $ 66.00 2,660.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

6. Includes Div6+7+8+9+10 6,041,290.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

7.

277 m2 5.00$ 33% $ 1.65 1,840.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 30,000.00$ 33% $ 9,900.00 39,900.00$

20000 m3 165.00$ 50% $ 82.50 4,950,000.00$

1 Lump Sum 742,500.00$ 25% $ 185,625.00 928,130.00$

8.

8 ea 3,000.00$ 25% $ 750.00 30,000.00$

1 Lump Sum 3,000.00$ Incl. in Unit Price Incl. in Unit Price 3,000.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

9.

298 m2 25.00$ 25% $ 6.25 9,320.00$

1 Lump Sum 2,000.00$ 25% $ 500.00 2,500.00$

10.

1 Lump Sum 20,000.00$ 50% $ 10,000.00 30,000.00$

11.

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1,000,850.00$

4 Each 85,000.00$ 33% $ 28,050.00 452,200.00$

3 Each 60,000.00$ 33% $ 19,800.00 239,400.00$

3 Each 75,000.00$ 33% $ 24,750.00 299,250.00$

Total Cost Estimate

(ii) Reservoir

(iii) Retention Chamber

(ii) Reservoir

(iii) Retention Chamber

11000 Equipment General Requirements

11215 Pumps

Vertical Turbine Pump

Submersible Sump Pump

Centrifuge Pumps

Division 9 - Dry Wall and Painting

09900 Painting and Protective Coatings

All Other Finishes Items

Division 10 - Miscellaneous Specialties

10200 Louvres and Vents

Division 11 - Equipment

Glass-Fused Geodoesic Dome (10 000 m3 x 2)

Accessories and Appurtenances

Division 8 - Metal Doors and Frames

08110 Steel Door Frames

08710 Door Hardware

All Other Doors and Windows Items

All Wood and Plastics Items

Division 7 - Building Specialties

7130 Membrane Waterproofing

7200 Insulation

07610 Preformed Metal Standing Seam Roofing System

7150 Glass-Fused Steel Reservoir (10 000 m3 x 2)

Roof Access Hatch (1000 x 1000mm) - 1

Aluminum Grating (Pumping Station)

Aluminum Handrail (Mezz+Basem't+Bldg)

Aluminum Handrail (Staircase)

All Other Metal Items

Division 6 - Carpentry

5310 Specialty Items

5501 Metal Fabrications - Architectural

Steel Bollards

Staircase (Pumping Station)

5502 Metal Fabrications - Structural

Access Hatch (914 x 914 mm) - 2

4060 Mortar and Masonry Grout

4080 Mansonry Reinforcement and Connectors

4090 Masonry Accessories

4200 Unit Masonry

Division 5 - Metals

5000 Metals General Requirements

3300 Cast in Place Concrete

(i) Pumping Station

3345 Concrete Curing and Finishing

3372 Non-shrink Grout

3375 Concrete Floor Toppings

Division 4 - Masonry

2911 Topsoil and Finish Grading

2936 Landscaping

Division 3 - Concrete

3100 Concrete Forms and Accessories

(i) Pumping Station

3200 Concrete Reinforcement

STM - Landscaping Drainage 450 mm

2701 Aggregates

2721 Granular Base

2723 Granular Sub-Base

2741 Asphalt Paving

2821 Chain Link Fences and Gates

WM - 500mm

WM - 600mm, steel casing

02530 Sewerage Gravity Sanitary Sewer

02630 Storm Sewers

STM - 200 mm

STM - Overflow Outlet 600 mm

2200 Site Preparation

2311 Site Grading

2315 Excavation, Trenching and Backfill (& Disposal)

02362 Dust Control

02380 Erosion and Sediment Control

2511 Watermains

Description

Division 1 - General Requirements (10%)

Division 2 - Site Work

2100 General Allowances (5%)

2140 Dewatering

2150 Shoring Systems

Option 2A - Glass Fused Steel \\thfiler1.mmm.ca\wpdocs$\2017\salem reservoir and pumping station - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment_mep_oct20_2017.xls

OPTION 2A : At-ground Glass Fused to Steel Reservoir & PS - Site 1, North of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

Total Cost EstimateDescription

2 Each 35,000.00$ 75% $ 26,250.00 122,500.00$ 122,500.00$

239,400.00$

1 Each 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

Bi-directional Magnetic Flowmeter - 300mm 1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

2 Each 50,000.00$ 33% $ 16,500.00 133,000.00$

12. 169,570.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

3 Each 5,500.00$ 33% $ 1,815.00 21,950.00$

14 Each 600.00$ 33% $ 198.00 11,170.00$

2 Each 6,000.00$ 33% $ 1,980.00 15,960.00$

6 Each 300.00$ 33% $ 99.00 2,390.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

13.

1 Lump Sum 50,000.00$ 50% $ 25,000.00 75,000.00$

14. 2,082,400.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 6,000.00$ 33% $ 1,980.00 7,980.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

9 Each 20,000.00$ 33% $ 6,600.00 239,400.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

1 Lump Sum 70,000.00$ 33% $ 23,100.00 93,100.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

16. 887,850.00$

1 Lump Sum 30,000.00$ Incl. in Unit Price Incl. in Unit Price 30,000.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Each 150,000.00$ 33% $ 49,500.00 199,500.00$

1 Each 100,000.00$ 33% $ 33,000.00 133,000.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

4 Each 15,000.00$ 33% $ 4,950.00 79,800.00$

2 Each 25,000.00$ 33% $ 8,250.00 66,500.00$

8 Each 20,000.00$ 33% $ 6,600.00 212,800.00$

1 Lump Sum 100,000.00$ 33% $ 33,000.00 133,000.00$

Div 2-16 16,079,971.50$ 16,079,971.50$

Total 17,687,968.65$ 17,687,968.65$

11260 Chemical Storage and Feed Equipment

16627 Automatic Transfer Switches

16811 Motor Starters

16816 Variable Frequency Drives

16818 Soft Starter Drives

16820 Motor Control Centre

15955 Piping Leakage Testing

Division 16 - Electrical

16000 Electrical General Works

16461 Dry Type Transformers

16556 Diesel Engine Generator Set

16560 Emergency Chlorine Scrubber

15760 Electric Unit Heaters

15802 Fiberglass Reinforced Plastic Ductwork

15810 Metal Ductwork and Accessories

15830 Fans

15900 HVAC Controls

15950 HVAC Systems Testing, Adjusting, and Balancing

15410 Plumbing Fixtures

15440 Plumbing Equipment

15204 Process Piping Specialties

15205 Process Valves and Operators

15200-14 Copper Tubing and Fittings

15201 Piping Support Systems

15202 Vibration and Noise Control

15100 Plumbing Piping

15200 Process Piping and Fittings

13480 SCADA System Integrator

Division 14 - Monorail and Hoist

14620 Monorail and Hoist

Division 15 - Mechanical

15010 Mechanical General Requirements

15060 Pipe Fittings

13110 Ultrasonic Level Transmitter

13130 Float Switch

13140 Pressure Transmitter

13141 Pressure Gauge

13305 Field Wiring

13400 Programmable Logic Controller

Magnetic Flowmeter - 200mm

Magnetic Flowmeter - 300mm

11700 Mixer

Division 13 - Instrumentation and Control

13010 Process Control - General Requirements

13105 General Instrumentation Requirements

11560 Flowmeter

Option 2A - Glass Fused Steel \\thfiler1.mmm.ca\wpdocs$\2017\salem reservoir and pumping station - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment_mep_oct20_2017.xls

OPTION 2B : At-ground Glass Fused to Steel Reservoir & PS - Site 2, South of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

1. 1 Lump Sum 1,649,582.15$ Incl. in Unit Price Incl. in Unit Price 1,649,582.15$ 1,649,582.15$

2. 2,959,171.50$

1 Lump Sum 104,521.50$ Incl. in Unit Price Incl. in Unit Price 104,521.50$

1 Lump Sum 50,000.00$ Incl. in Unit Price Incl. in Unit Price 50,000.00$

485 m2 1,200.00$ Incl. in Unit Price Incl. in Unit Price 581,510.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

25000 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 1,250,000.00$

1589 m3 100.00$ Incl. in Unit Price Incl. in Unit Price 158,920.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 25,000.00$ Incl. in Unit Price Incl. in Unit Price 25,000.00$

100 m 1,100.00$ 50% $ 550.00 165,000.00$

48 m 1,500.00$ 50% $ 750.00 108,000.00$

49 m 450.00$ 50% $ 225.00 33,140.00$

135 m 500.00$ 50% $ 250.00 101,480.00$

40 m 500.00$ 50% $ 250.00 30,000.00$

14 m 500.00$ 50% $ 250.00 10,500.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

1 Lump Sum 8,000.00$ Incl. in Unit Price Incl. in Unit Price 8,000.00$

1 Lump Sum 6,000.00$ Incl. in Unit Price Incl. in Unit Price 6,000.00$

80 m3 500.00$ 50% $ 250.00 60,000.00$

553 m 40.00$ Incl. in Unit Price Incl. in Unit Price 22,100.00$

25000 m2 5.00$ Incl. in Unit Price Incl. in Unit Price 125,000.00$

1 Lump Sum 75,000.00$ Incl. in Unit Price Incl. in Unit Price 75,000.00$

3. 2,504,590.00$

1,810 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 452,590.00$

1 Lump Sum -$ Incl. in Unit Price Incl. in Unit Price -$

1673 m3 1,200.00$ Incl. in Unit Price Incl. in Unit Price 2,007,000.00$

1 Lump Sum 25,000.00$ Incl. in Unit Price Incl. in Unit Price 25,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

4. 156,660.00$

298 m2 25.00$ Incl. in Unit Price Incl. in Unit Price 7,460.00$

298 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 14,920.00$

298 m2 200.00$ Incl. in Unit Price Incl. in Unit Price 59,680.00$

298 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 74,600.00$

5. 145,920.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

4 ea 100.00$ 33% $ 33.00 530.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

2 ea 15,000.00$ 33% $ 4,950.00 39,900.00$

1 ea 15,000.00$ 33% $ 4,950.00 19,950.00$

8 m2 600.00$ 33% $ 198.00 6,480.00$

55 m 200.00$ 33% $ 66.00 14,710.00$

17 m 200.00$ 33% $ 66.00 4,500.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

6. 6,226,910.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

7.

277 m2 5.00$ 33% $ 1.65 1,840.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 30,000.00$ 33% $ 9,900.00 39,900.00$

20000 m3 165.00$ 50% $ 82.50 4,950,000.00$

1 Lump Sum 742,500.00$ 50% $ 371,250.00 1,113,750.00$

8.

8 ea 3,000.00$ 25% $ 750.00 30,000.00$

1 Lump Sum 3,000.00$ Incl. in Unit Price Incl. in Unit Price 3,000.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

9.

298 m2 25.00$ 25% $ 6.25 9,320.00$

1 Lump Sum 2,000.00$ 25% $ 500.00 2,500.00$

(ii) Reservoir

(iii) Retention Chamber

(ii) Reservoir

(iii) Retention Chamber

Total Cost Estimate

WM - 600mm, steel casing

WM - 500mm

All Wood and Plastics Items

All Other Metal Items

Aluminum Handrail (Staircase)

Aluminum Handrail (Mezz+Basem't+Bldg)

Aluminum Grating (Pumping Station)

Roof Access Hatch (1000 x 1000mm) - 1

Access Hatch (914 x 914 mm) - 2

5000 Metals General Requirements

5310 Specialty Items

5501 Metal Fabrications - Architectural

5502 Metal Fabrications - Structural

STM - Landscaping Drainage 450 mm

STM - Overflow Outlet 600 mm

08710 Door Hardware

Division 9 - Dry Wall and Painting

09900 Painting and Protective Coatings

All Other Finishes Items

All Other Doors and Windows Items

7130 Membrane Waterproofing

7200 Insulation

07610 Preformed Metal Standing Seam Roofing System

7150 Glass-Fused Steel Reservoir (10 000 m3 x 2)

Division 8 - Metal Doors and Frames

08110 Steel Door Frames

Accessories and Appurtenances

Glass-Fused + Geodoesic Dome (10 000 m3 x 2)

Division 6 - Carpentry

Division 7 - Building Specialties

Steel Bollards

Staircase (Pumping Station)

Division 4 - Masonry

4060 Mortar and Masonry Grout

4080 Mansonry Reinforcement and Connectors

4090 Masonry Accessories

4200 Unit Masonry

Division 5 - Metals

3200 Concrete Reinforcement

3300 Cast in Place Concrete

(i) Pumping Station

3345 Concrete Curing and Finishing

3372 Non-shrink Grout

3375 Concrete Floor Toppings

2821 Chain Link Fences and Gates

2911 Topsoil and Finish Grading

2936 Landscaping

Division 3 - Concrete

3100 Concrete Forms and Accessories

(i) Pumping Station

02530 Sewerage Gravity Sanitary Sewer

02630 Storm Sewers

2701 Aggregates

2721 Granular Base

2723 Granular Sub-Base

2741 Asphalt Paving

STM - 200 mm

2200 Site Preparation

2311 Site Grading

2315 Excavation, Trenching and Backfill (& Disposal)

02362 Dust Control

2511 Watermains

02380 Erosion and Sediment Control

Description

Division 1 - General Requirements (10%)

Division 2 - Site Work

2100 General Allowances (5%)

2140 Dewatering

2150 Shoring Systems

Option 2B - Glass Fused Steel c:\users\whittakerd\documents\projects\salem reservoir and pumping station\revisions - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment.xls

OPTION 2B : At-ground Glass Fused to Steel Reservoir & PS - Site 2, South of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

Total Cost EstimateDescription

10.

1 Lump Sum 20,000.00$ 50% $ 10,000.00 30,000.00$

11.

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1,000,850.00$

4 Each 85,000.00$ 33% $ 28,050.00 452,200.00$

3 Each 60,000.00$ 33% $ 19,800.00 239,400.00$

3 Each 75,000.00$ 33% $ 24,750.00 299,250.00$

2 Each 35,000.00$ 75% $ 26,250.00 122,500.00$ 122,500.00$

239,400.00$

1 Each 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

Bi-directional Magnetic Flowmeter - 300mm 1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

2 Each 50,000.00$ 33% $ 16,500.00 133,000.00$

12. 169,570.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

3 Each 5,500.00$ 33% $ 1,815.00 21,950.00$

14 Each 600.00$ 33% $ 198.00 11,170.00$

2 Each 6,000.00$ 33% $ 1,980.00 15,960.00$

6 Each 300.00$ 33% $ 99.00 2,390.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

13.

1 Lump Sum 50,000.00$ 50% $ 25,000.00 75,000.00$

14. 2,082,400.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 6,000.00$ 33% $ 1,980.00 7,980.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

9 Each 20,000.00$ 33% $ 6,600.00 239,400.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

1 Lump Sum 70,000.00$ 33% $ 23,100.00 93,100.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

16. 887,850.00$

1 Lump Sum 30,000.00$ Incl. in Unit Price Incl. in Unit Price 30,000.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Each 150,000.00$ 33% $ 49,500.00 199,500.00$

1 Each 100,000.00$ 33% $ 33,000.00 133,000.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

4 Each 15,000.00$ 33% $ 4,950.00 79,800.00$

2 Each 25,000.00$ 33% $ 8,250.00 66,500.00$

8 Each 20,000.00$ 33% $ 6,600.00 212,800.00$

1 Lump Sum 100,000.00$ 33% $ 33,000.00 133,000.00$

Div 2-16 16,495,821.50$ 16,495,821.50$

Total 18,145,403.65$ 18,145,403.65$

11260 Chemical Storage and Feed Equipment

16816 Variable Frequency Drives

16818 Soft Starter Drives

16820 Motor Control Centre

16461 Dry Type Transformers

16556 Diesel Engine Generator Set

16560 Emergency Chlorine Scrubber

16627 Automatic Transfer Switches

Magnetic Flowmeter - 300mm

Magnetic Flowmeter - 200mm

16000 Electrical General Works

15204 Process Piping Specialties

15205 Process Valves and Operators

15410 Plumbing Fixtures

15440 Plumbing Equipment

16811 Motor Starters

15810 Metal Ductwork and Accessories

15830 Fans

15900 HVAC Controls

15950 HVAC Systems Testing, Adjusting, and Balancing

15955 Piping Leakage Testing

Division 16 - Electrical

15760 Electric Unit Heaters

15802 Fiberglass Reinforced Plastic Ductwork

15060 Pipe Fittings

15100 Plumbing Piping

15200 Process Piping and Fittings

15200-14 Copper Tubing and Fittings

15201 Piping Support Systems

15202 Vibration and Noise Control

13400 Programmable Logic Controller

13480 SCADA System Integrator

Division 14 - Monorail and Hoist

14620 Monorail and Hoist

Division 15 - Mechanical

15010 Mechanical General Requirements

13105 General Instrumentation Requirements

13110 Ultrasonic Level Transmitter

13130 Float Switch

13140 Pressure Transmitter

13141 Pressure Gauge

13305 Field Wiring

Division 11 - Equipment

11000 Equipment General Requirements

11215 Pumps

11560 Flowmeter

Division 13 - Instrumentation and Control

13010 Process Control - General Requirements

Centrifuge Pumps

Submersible Sump Pump

Vertical Turbine Pump

11700 Mixer

Division 10 - Miscellaneous Specialties

10200 Louvres and Vents

Option 2B - Glass Fused Steel c:\users\whittakerd\documents\projects\salem reservoir and pumping station\revisions - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment.xls

OPTION 3A: At-ground Pre-Cast/Pre-Stressed Concrete Reservoir & PS - Site 1, North of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

1. 1 Lump Sum 1,895,507.15$ Incl. in Unit Price Incl. in Unit Price 1,895,507.15$ 1,895,507.15$

2. 2,658,421.50$

1 Lump Sum 88,521.50$ Incl. in Unit Price Incl. in Unit Price 88,521.50$

1 Lump Sum 50,000.00$ Incl. in Unit Price Incl. in Unit Price 50,000.00$

485 m2 1,200.00$ Incl. in Unit Price Incl. in Unit Price 581,510.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

19000 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 950,000.00$

1589 m3 100.00$ Incl. in Unit Price Incl. in Unit Price 158,920.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

150 m 1,100.00$ 50% $ 550.00 247,500.00$

60 m 1,500.00$ 50% $ 750.00 135,000.00$

49 m 450.00$ 50% $ 225.00 33,140.00$

135 m 500.00$ 50% $ 250.00 101,480.00$

40 m 500.00$ 50% $ 250.00 30,000.00$

14 m 500.00$ 50% $ 250.00 10,500.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

1 Lump Sum 8,000.00$ Incl. in Unit Price Incl. in Unit Price 8,000.00$

1 Lump Sum 6,000.00$ Incl. in Unit Price Incl. in Unit Price 6,000.00$

81 m3 500.00$ 50% $ 250.00 60,750.00$

553 m 40.00$ Incl. in Unit Price Incl. in Unit Price 22,100.00$

19000 m2 5.00$ Incl. in Unit Price Incl. in Unit Price 95,000.00$

1 Lump Sum 30,000.00$ Incl. in Unit Price Incl. in Unit Price 30,000.00$

3. 2,839,090.00$

1,810 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 452,590.00$

1 Lump Sum -$ Incl. in Unit Price Incl. in Unit Price -$

1673 m3 1,400.00$ Incl. in Unit Price Incl. in Unit Price 2,341,500.00$

1 Lump Sum 25,000.00$ Incl. in Unit Price Incl. in Unit Price 25,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

8,489,250.00$

1 Lump Sum 3,920,000.00$ 65% $ 2,548,000.00 6,468,000.00$

1 Lump Sum 1,617,000.00$ 25% $ 404,250.00 2,021,250.00$

4. 156,660.00$

298 m2 25.00$ Incl. in Unit Price Incl. in Unit Price 7,460.00$

298 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 14,920.00$

298 m2 200.00$ Incl. in Unit Price Incl. in Unit Price 59,680.00$

298 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 74,600.00$

5. 145,920.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

4 ea 100.00$ 33% $ 33.00 530.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

2 ea 15,000.00$ 33% $ 4,950.00 39,900.00$

1 ea 15,000.00$ 33% $ 4,950.00 19,950.00$

8 m2 600.00$ 33% $ 198.00 6,480.00$

55 m 200.00$ 33% $ 66.00 14,710.00$

17 m 200.00$ 33% $ 66.00 4,500.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

6. Includes Div6+7+8+9+10 163,160.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

7.

277 m2 5.00$ 33% $ 1.65 1,840.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 30,000.00$ 33% $ 9,900.00 39,900.00$

8.

8 ea 3,000.00$ 25% $ 750.00 30,000.00$

1 Lump Sum 3,000.00$ Incl. in Unit Price Incl. in Unit Price 3,000.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

9.

298 m2 25.00$ 25% $ 6.25 9,320.00$

1 Lump Sum 2,000.00$ 25% $ 500.00 2,500.00$

Total Cost Estimate

Division 9 - Dry Wall and Painting

09900 Painting and Protective Coatings

All Other Finishes Items

7200 Insulation

07610 Preformed Metal Standing Seam Roofing System

Division 8 - Metal Doors and Frames

08110 Steel Door Frames

08710 Door Hardware

All Other Doors and Windows Items

Aluminum Handrail (Staircase)

All Other Metal Items

Division 6 - Carpentry

All Wood and Plastics Items

Division 7 - Building Specialties

7130 Membrane Waterproofing

Staircase (Pumping Station)

5502 Metal Fabrications - Structural

Access Hatch (914 x 914 mm) - 2

Roof Access Hatch (1000 x 1000mm) - 1

Aluminum Grating (Pumping Station)

Aluminum Handrail (Mezz+Basem't+Bldg)

4200 Unit Masonry

Division 5 - Metals

5000 Metals General Requirements

5310 Specialty Items

5501 Metal Fabrications - Architectural

Steel Bollards

10ML x 2 Pre-Stressed Conc. Reservoir

Accessories and Appurtenances

Division 4 - Masonry

4060 Mortar and Masonry Grout

4080 Mansonry Reinforcement and Connectors

4090 Masonry Accessories

3300 Cast in Place Concrete

(i) Pumping Station

3345 Concrete Curing and Finishing

3372 Non-shrink Grout

3375 Concrete Floor Toppings

3380 Pre-Stressed Conc. Reservoir (34m x 11m)

(ii) Reservoir

(iii) Retention Chamber

2911 Topsoil and Finish Grading

2936 Landscaping

Division 3 - Concrete

3100 Concrete Forms and Accessories

(i) Pumping Station

3200 Concrete Reinforcement

(ii) Reservoir

(iii) Retention Chamber

STM - Landscaping Drainage 450 mm

2701 Aggregates

2721 Granular Base

2723 Granular Sub-Base

2741 Asphalt Paving

2821 Chain Link Fences and Gates

WM - 500mm

WM - 600mm, steel casing

02530 Sewerage Gravity Sanitary Sewer

02630 Storm Sewers

STM - 200 mm

STM - Overflow Outlet 600 mm

2200 Site Preparation

2311 Site Grading

2315 Excavation, Trenching and Backfill (& Disposal)

02362 Dust Control

02380 Erosion and Sediment Control

2511 Watermains

Description

Division 1 - General Requirements (10%)

Division 2 - Site Work

2100 General Allowances (5%)

2140 Dewatering

2150 Shoring Systems

Option 3A - Pre-Stressed Conc c:\users\whittakerd\documents\projects\salem reservoir and pumping station\revisions - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment.xls

OPTION 3A: At-ground Pre-Cast/Pre-Stressed Concrete Reservoir & PS - Site 1, North of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

Total Cost EstimateDescription

10.

1 Lump Sum 20,000.00$ 50% $ 10,000.00 30,000.00$

11.

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1,000,850.00$

4 Each 85,000.00$ 33% $ 28,050.00 452,200.00$

3 Each 60,000.00$ 33% $ 19,800.00 239,400.00$

3 Each 75,000.00$ 33% $ 24,750.00 299,250.00$

2 Each 35,000.00$ 75% $ 26,250.00 122,500.00$ 122,500.00$

239,400.00$

1 Each 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

Bi-directional Magnetic Flowmeter - 300mm 1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

2 Each 50,000.00$ 33% $ 16,500.00 133,000.00$

12. 169,570.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

3 Each 5,500.00$ 33% $ 1,815.00 21,950.00$

14 Each 600.00$ 33% $ 198.00 11,170.00$

2 Each 6,000.00$ 33% $ 1,980.00 15,960.00$

6 Each 300.00$ 33% $ 99.00 2,390.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

13.

1 Lump Sum 50,000.00$ 50% $ 25,000.00 75,000.00$

14. 2,082,400.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 6,000.00$ 33% $ 1,980.00 7,980.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

9 Each 20,000.00$ 33% $ 6,600.00 239,400.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

1 Lump Sum 70,000.00$ 33% $ 23,100.00 93,100.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

16. 887,850.00$

1 Lump Sum 30,000.00$ Incl. in Unit Price Incl. in Unit Price 30,000.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Each 150,000.00$ 33% $ 49,500.00 199,500.00$

1 Each 100,000.00$ 33% $ 33,000.00 133,000.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

4 Each 15,000.00$ 33% $ 4,950.00 79,800.00$

2 Each 25,000.00$ 33% $ 8,250.00 66,500.00$

8 Each 20,000.00$ 33% $ 6,600.00 212,800.00$

1 Lump Sum 100,000.00$ 33% $ 33,000.00 133,000.00$

Div 2-16 18,955,071.50$ 18,955,071.50$

Total 20,850,578.65$ 20,850,578.65$

16627 Automatic Transfer Switches

16811 Motor Starters

16816 Variable Frequency Drives

16818 Soft Starter Drives

16820 Motor Control Centre

15955 Piping Leakage Testing

Division 16 - Electrical

16000 Electrical General Works

16461 Dry Type Transformers

16556 Diesel Engine Generator Set

16560 Emergency Chlorine Scrubber

15760 Electric Unit Heaters

15802 Fiberglass Reinforced Plastic Ductwork

15810 Metal Ductwork and Accessories

15830 Fans

15900 HVAC Controls

15950 HVAC Systems Testing, Adjusting, and Balancing

15410 Plumbing Fixtures

15440 Plumbing Equipment

15204 Process Piping Specialties

15205 Process Valves and Operators

15200-14 Copper Tubing and Fittings

15201 Piping Support Systems

15202 Vibration and Noise Control

15100 Plumbing Piping

15200 Process Piping and Fittings

13480 SCADA System Integrator

Division 14 - Monorail and Hoist

14620 Monorail and Hoist

Division 15 - Mechanical

15010 Mechanical General Requirements

15060 Pipe Fittings

13110 Ultrasonic Level Transmitter

13130 Float Switch

13140 Pressure Transmitter

13141 Pressure Gauge

13305 Field Wiring

13400 Programmable Logic Controller

Magnetic Flowmeter - 200mm

Magnetic Flowmeter - 300mm

11700 Mixer

Division 13 - Instrumentation and Control

13010 Process Control - General Requirements

13105 General Instrumentation Requirements

11000 Equipment General Requirements

11215 Pumps

Vertical Turbine Pump

Submersible Sump Pump

Centrifuge Pumps

11560 Flowmeter

11260 Chemical Storage and Feed Equipment

Division 10 - Miscellaneous Specialties

10200 Louvres and Vents

Division 11 - Equipment

Option 3A - Pre-Stressed Conc c:\users\whittakerd\documents\projects\salem reservoir and pumping station\revisions - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment.xls

OPTION 3B: At-ground Pre-Cast/Pre-Stressed Concrete Reservoir & PS - Site 2, South of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

1. 1 Lump Sum 1,925,057.15$ Incl. in Unit Price Incl. in Unit Price 1,925,057.15$ 1,925,057.15$

2. 2,953,921.50$

1 Lump Sum 104,271.50$ Incl. in Unit Price Incl. in Unit Price 104,271.50$

1 Lump Sum 50,000.00$ Incl. in Unit Price Incl. in Unit Price 50,000.00$

485 m2 1,200.00$ Incl. in Unit Price Incl. in Unit Price 581,510.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

25000 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 1,250,000.00$

1589 m3 100.00$ Incl. in Unit Price Incl. in Unit Price 158,920.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 25,000.00$ Incl. in Unit Price Incl. in Unit Price 25,000.00$

100 m 1,100.00$ 50% $ 550.00 165,000.00$

48 m 1,500.00$ 50% $ 750.00 108,000.00$

49 m 450.00$ 50% $ 225.00 33,140.00$

135 m 500.00$ 50% $ 250.00 101,480.00$

40 m 500.00$ 50% $ 250.00 30,000.00$

14 m 500.00$ 50% $ 250.00 10,500.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

1 Lump Sum 8,000.00$ Incl. in Unit Price Incl. in Unit Price 8,000.00$

1 Lump Sum 6,000.00$ Incl. in Unit Price Incl. in Unit Price 6,000.00$

80 m3 500.00$ 50% $ 250.00 60,000.00$

553 m 40.00$ Incl. in Unit Price Incl. in Unit Price 22,100.00$

25000 m2 5.00$ Incl. in Unit Price Incl. in Unit Price 125,000.00$

1 Lump Sum 75,000.00$ Incl. in Unit Price Incl. in Unit Price 75,000.00$

3. 2,839,090.00$

1,810 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 452,590.00$

1 Lump Sum -$ Incl. in Unit Price Incl. in Unit Price -$

1673 m3 1,400.00$ Incl. in Unit Price Incl. in Unit Price 2,341,500.00$

1 Lump Sum 25,000.00$ Incl. in Unit Price Incl. in Unit Price 25,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

8,489,250.00$

1 Lump Sum 3,920,000.00$ 65% $ 2,548,000.00 6,468,000.00$

1 Lump Sum 1,617,000.00$ 25% $ 404,250.00 2,021,250.00$

4. 156,660.00$

298 m2 25.00$ Incl. in Unit Price Incl. in Unit Price 7,460.00$

298 m2 50.00$ Incl. in Unit Price Incl. in Unit Price 14,920.00$

298 m2 200.00$ Incl. in Unit Price Incl. in Unit Price 59,680.00$

298 m2 250.00$ Incl. in Unit Price Incl. in Unit Price 74,600.00$

5. 145,920.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

4 ea 100.00$ 33% $ 33.00 530.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

2 ea 15,000.00$ 33% $ 4,950.00 39,900.00$

1 ea 15,000.00$ 33% $ 4,950.00 19,950.00$

8 m2 600.00$ 33% $ 198.00 6,480.00$

55 m 200.00$ 33% $ 66.00 14,710.00$

17 m 200.00$ 33% $ 66.00 4,500.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

6. 163,160.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

7.

277 m2 5.00$ 33% $ 1.65 1,840.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 30,000.00$ 33% $ 9,900.00 39,900.00$

8.

8 ea 3,000.00$ 25% $ 750.00 30,000.00$

1 Lump Sum 3,000.00$ Incl. in Unit Price Incl. in Unit Price 3,000.00$

1 Lump Sum 20,000.00$ Incl. in Unit Price Incl. in Unit Price 20,000.00$

9.

298 m2 25.00$ 25% $ 6.25 9,320.00$

1 Lump Sum 2,000.00$ 25% $ 500.00 2,500.00$

Total Cost Estimate

08110 Steel Door Frames

08710 Door Hardware

All Other Doors and Windows Items

Division 9 - Dry Wall and Painting

09900 Painting and Protective Coatings

All Other Finishes Items

All Wood and Plastics Items

Division 7 - Building Specialties

7130 Membrane Waterproofing

7200 Insulation

07610 Preformed Metal Standing Seam Roofing System

Division 8 - Metal Doors and Frames

Roof Access Hatch (1000 x 1000mm) - 1

Aluminum Grating (Pumping Station)

Aluminum Handrail (Mezz+Basem't+Bldg)

Aluminum Handrail (Staircase)

All Other Metal Items

Division 6 - Carpentry

5310 Specialty Items

5501 Metal Fabrications - Architectural

Steel Bollards

Staircase (Pumping Station)

5502 Metal Fabrications - Structural

Access Hatch (914 x 914 mm) - 2

4060 Mortar and Masonry Grout

4080 Mansonry Reinforcement and Connectors

4090 Masonry Accessories

4200 Unit Masonry

Division 5 - Metals

5000 Metals General Requirements

(i) Pumping Station

3345 Concrete Curing and Finishing

3372 Non-shrink Grout

3375 Concrete Floor Toppings

3380 Pre-Stressed Conc. Reservoir (34m x 11m)

Division 4 - Masonry

10ML x 2 Pre-Stressed Conc. Reservoir

Accessories and Appurtenances

(ii) Reservoir

(iii) Retention Chamber

2936 Landscaping

Division 3 - Concrete

3100 Concrete Forms and Accessories

(i) Pumping Station

3200 Concrete Reinforcement

3300 Cast in Place Concrete

(ii) Reservoir

(iii) Retention Chamber

2701 Aggregates

2721 Granular Base

2723 Granular Sub-Base

2741 Asphalt Paving

2821 Chain Link Fences and Gates

2911 Topsoil and Finish Grading

WM - 600mm, steel casing

02530 Sewerage Gravity Sanitary Sewer

02630 Storm Sewers

STM - 200 mm

STM - Overflow Outlet 600 mm

STM - Landscaping Drainage 450 mm

2311 Site Grading

2315 Excavation, Trenching and Backfill (& Disposal)

02362 Dust Control

02380 Erosion and Sediment Control

2511 Watermains

WM - 500mm

2200 Site Preparation

Description

Division 1 - General Requirements (10%)

Division 2 - Site Work

2100 General Allowances (5%)

2140 Dewatering

2150 Shoring Systems

Option 3B - Pre-Stressed Conc c:\users\whittakerd\documents\projects\salem reservoir and pumping station\revisions - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment.xls

OPTION 3B: At-ground Pre-Cast/Pre-Stressed Concrete Reservoir & PS - Site 2, South of Salem Rd, West of Hwy 400

Item Estimated Unit Unit Estimate Installation Factor Price per Unit of Qty ($) % ($) ($) ($)

Total Cost EstimateDescription

10.

1 Lump Sum 20,000.00$ 50% $ 10,000.00 30,000.00$

11.

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1,000,850.00$

4 Each 85,000.00$ 33% $ 28,050.00 452,200.00$

3 Each 60,000.00$ 33% $ 19,800.00 239,400.00$

3 Each 75,000.00$ 33% $ 24,750.00 299,250.00$

2 Each 35,000.00$ 75% $ 26,250.00 122,500.00$ 122,500.00$

239,400.00$

1 Each 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

Bi-directional Magnetic Flowmeter - 300mm 1 Each 30,000.00$ 33% $ 9,900.00 39,900.00$

2 Each 50,000.00$ 33% $ 16,500.00 133,000.00$

12. 169,570.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

3 Each 5,500.00$ 33% $ 1,815.00 21,950.00$

14 Each 600.00$ 33% $ 198.00 11,170.00$

2 Each 6,000.00$ 33% $ 1,980.00 15,960.00$

6 Each 300.00$ 33% $ 99.00 2,390.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Each 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

13.

1 Lump Sum 50,000.00$ 50% $ 25,000.00 75,000.00$

14. 2,082,400.00$

1 Lump Sum 15,000.00$ Incl. in Unit Price Incl. in Unit Price 15,000.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Lump Sum 15,000.00$ 33% $ 4,950.00 19,950.00$

1 Lump Sum 6,000.00$ 33% $ 1,980.00 7,980.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

9 Each 20,000.00$ 33% $ 6,600.00 239,400.00$

1 Lump Sum 10,000.00$ 33% $ 3,300.00 13,300.00$

1 Lump Sum 50,000.00$ 33% $ 16,500.00 66,500.00$

1 Lump Sum 25,000.00$ 33% $ 8,250.00 33,250.00$

1 Lump Sum 70,000.00$ 33% $ 23,100.00 93,100.00$

1 Lump Sum 10,000.00$ Incl. in Unit Price Incl. in Unit Price 10,000.00$

1 Lump Sum 5,000.00$ Incl. in Unit Price Incl. in Unit Price 5,000.00$

16. 887,850.00$

1 Lump Sum 30,000.00$ Incl. in Unit Price Incl. in Unit Price 30,000.00$

1 Lump Sum 5,000.00$ 33% $ 1,650.00 6,650.00$

1 Each 150,000.00$ 33% $ 49,500.00 199,500.00$

1 Each 100,000.00$ 33% $ 33,000.00 133,000.00$

1 Lump Sum 20,000.00$ 33% $ 6,600.00 26,600.00$

4 Each 15,000.00$ 33% $ 4,950.00 79,800.00$

2 Each 25,000.00$ 33% $ 8,250.00 66,500.00$

8 Each 20,000.00$ 33% $ 6,600.00 212,800.00$

1 Lump Sum 100,000.00$ 33% $ 33,000.00 133,000.00$

Div 2-16 19,250,571.50$ 19,250,571.50$

Total 21,175,628.65$ 21,175,628.65$

16820 Motor Control Centre

16461 Dry Type Transformers

16556 Diesel Engine Generator Set

16560 Emergency Chlorine Scrubber

16627 Automatic Transfer Switches

16811 Motor Starters

16816 Variable Frequency Drives

15900 HVAC Controls

15950 HVAC Systems Testing, Adjusting, and Balancing

15955 Piping Leakage Testing

Division 16 - Electrical

16000 Electrical General Works

16818 Soft Starter Drives

15410 Plumbing Fixtures

15440 Plumbing Equipment

15760 Electric Unit Heaters

15802 Fiberglass Reinforced Plastic Ductwork

15810 Metal Ductwork and Accessories

15830 Fans

15201 Piping Support Systems

15202 Vibration and Noise Control

15204 Process Piping Specialties

15205 Process Valves and Operators

15200-14 Copper Tubing and Fittings

15010 Mechanical General Requirements

15060 Pipe Fittings

15100 Plumbing Piping

15200 Process Piping and Fittings

13305 Field Wiring

13400 Programmable Logic Controller

13480 SCADA System Integrator

Division 14 - Monorail and Hoist

14620 Monorail and Hoist

Division 15 - Mechanical

13010 Process Control - General Requirements

13105 General Instrumentation Requirements

13110 Ultrasonic Level Transmitter

13130 Float Switch

13140 Pressure Transmitter

13141 Pressure Gauge

Submersible Sump Pump

Centrifuge Pumps

11560 Flowmeter

Magnetic Flowmeter - 200mm

Magnetic Flowmeter - 300mm

Division 13 - Instrumentation and Control

11700 Mixer

11260 Chemical Storage and Feed Equipment

Division 10 - Miscellaneous Specialties

10200 Louvres and Vents

Division 11 - Equipment

11000 Equipment General Requirements

11215 Pumps

Vertical Turbine Pump

Option 3B - Pre-Stressed Conc c:\users\whittakerd\documents\projects\salem reservoir and pumping station\revisions - august 2017\2017-08-22 salem reservoir_cost estimate comparison_technology assessment.xls

ITEM DESCRIPTION

Option 1A:

CIP Concrete In-

ground

Reservoir & PS

-

Site 1

North Side

Salem Rd

Option 1B:

CIP Concrete In-

ground

Reservoir & PS

-

Site 2:

South Side

Salem Rd

Option 2A:

Glass Fused

Steel At-Grade

Reservoir & PS

-

Site 1

North Side

Salem Rd

Option 2B:

Glass Fused

Steel At-Grade

Reservoir & PS

-

Site 2

South Side

Salem Rd

Option 3A:

Precast

prestressed At-

Grade Reservoir

& PS

-

Site 1

North Side

Salem Rd

Option 3B:

Precast

prestressed At-

Grade Reservoir

& PS

-

Site 2

South Side

Salem Rd

A.

ESTIMATED 50 YR

OPERATIONS &

MAINTENANCE

COSTS - PRESENT

VALUE

$5,460,000 $5,460,000 $8,644,000 $8,644,000 $6,334,000 $6,334,000

B.

ESTIMATED

CONSTRUCTION

COSTS - PRESENT

VALUE

$31,161,400 $33,679,200 $21,224,400 $21,774,000 $25,020,000 $25,410,000

C.ESTIMATED LIFE

CYCLE COSTS$36,621,400 $39,139,200 $29,868,400 $30,418,000 $31,354,000 $31,744,000

ALL COSTS LESS HST

TECHNOLOGY DESCRIPTION

COMPARISON OF ESTIMATED LIFE CYCLE COSTS

SALEM ROAD RESERVOIR & PUMPING STATION CONCEPTUAL DESIGN - TECHNOLOGY ASSESSMENT

Location: North of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PS Reservoir Type: CIP Concrete, In-Ground, 20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 15

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity

(L/s)403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 48,600

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Power per Year at Ultimate Flowrate

(kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Estimated Operational Hours per Month (hrs) 6

Estimated Realization of Ultimate Flowrate Estimated Operation per Year (hours) 72

Years 1 - 5 25% Estimated Annual Fuel Consumption (L)/yr 4,905

Years 6 - 10 50%

Years 11 - 15 75%

Years 16 - 50 100%

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of $10,000 for

CCTV inspection and cleaning/ flushing costs.

1. Not applicable

- - - - - - - - - - - - - - - - - - 10,000$ -

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable. 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ -

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at $5/m3 of CIP

concrete. Total estimated concrete volume is 4,897 m3. Costs

estimated every 10 years for crack repair and resurfacing..

1. Not applicable.

- - - - - - - - - - - - - - - - - 24,485$ -

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable. - - - - - - - - - - - - - - - - - - - -

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.- - - - - - - - - - - - - - - - - - - -

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated at

$10,000.

1. Not applicable.- - - - - - - - - - - - - - - - - - - -

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - - -

Div 11 Equipment

11000

11215

11560

Pumps

1. Estimated annual maintenance costs - $1,500 per pump. Total of

4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per pump.

1. Refer to pump electricity cost

calcuations, above.

6,000$ 32,000$ 6,000$ 32,000$ 6,000$ 32,000$ 6,000$ 32,000$ 6,000$ 32,000$ 6,000$ 64,000$ 6,000$ 64,000$ 6,000$ 64,000$ 6,000$ 64,000$ 6,000$ 64,000$

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable. 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at $2,500.

15 year instrumentation replacement and refurbishment costs

estimated at $50,000.

2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ -

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment - $1,500. 1. Not applicable/

- - - - - - - - 1,500$ - - - - - - - - - 1,500$ -

Div 15 Mechanical15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

- - - - - - - - - - - - - - - - - - 5,000$ -

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - - -

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - -

15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations, above.- 18,000$ - 18,000$ - 18,000$ - 18,000$ 18,000$ - 18,000$ - 18,000$ - 18,000$ - 18,000$ 5,000$ 18,000$

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five year

refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption costs

calculation, above.2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 5,000$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 5,000$ 5,000$

16820 MCC and associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - 10,000$ -

16xxx Cathodic Protection 1. Not applicable.

55,000$ 55,000$ 55,000$ 55,000$ 55,000$ 87,000$ 87,000$ 87,000$ 87,000$ 87,000$

Note: O&M costs are assumed to be the same between Site 1 and Site 2 56,650$ 58,350$ 60,100$ 61,903$ 63,760$ 103,883$ 106,999$ 110,209$ 113,515$ 116,921$

54,000$ 53,000$ 52,000$ 51,000$ 50,000$ 78,000$ 76,000$ 75,000$ 73,000$ 72,000$

36,000$ 36,000$ 36,000$ 36,000$ 40,000$ 36,000$ 36,000$ 36,000$ 36,000$ 94,485$

37,080$ 38,192$ 39,338$ 40,518$ 46,371$ 42,986$ 44,275$ 45,604$ 46,972$ 126,980$

35,000$ 35,000$ 34,000$ 33,000$ 36,000$ 32,000$ 31,000$ 31,000$ 30,000$ 78,000$

5,460,000$

31,161,400$ *obtained from Capital Cost Estimate Spreadsheet

36,621,400$

Sub-Total - Estimated Construction Cost - Present Value

5 7 8

Grand Total - Estimated 50 Yr Life Cycle Cost - Present Value

110,000$ 86,000$ 84,000$ 86,000$ 107,000$ 89,000$ 88,000$

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount Factor

621

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for Discount Factor

106,000$

Pump Electricity Cost Calculation, Assumptions:

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

9

150,000$ 103,000$

Design Alternative No. 1A

3 4 10

Page 1 of 5

Location: North of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PS Reservoir Type: CIP Concrete, In-Ground, 20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 15

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity

(L/s)403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 48,600

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Power per Year at Ultimate Flowrate

(kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Estimated Operational Hours per Month (hrs) 6

Estimated Realization of Ultimate Flowrate Estimated Operation per Year (hours) 72

Years 1 - 5 25% Estimated Annual Fuel Consumption (L)/yr 4,905

Years 6 - 10 50%

Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of $10,000 for

CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at $5/m3 of CIP

concrete. Total estimated concrete volume is 4,897 m3. Costs

estimated every 10 years for crack repair and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated at

$10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

Pumps

1. Estimated annual maintenance costs - $1,500 per pump. Total of

4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at $2,500.

15 year instrumentation replacement and refurbishment costs

estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment - $1,500. 1. Not applicable/

Div 15 Mechanical15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations, above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five year

refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption costs

calculation, above.

16820 MCC and associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Sub-Total - Estimated Construction Cost - Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - Present Value

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount Factor

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for Discount Factor

Pump Electricity Cost Calculation, Assumptions:

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Design Alternative No. 1A

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

- - - - - - - - - - - - - - - - - - 10,000$ -

5,000$ - 5,000$ - 5,000$ - 5,000$ - 15,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 10,000$ -

- - - - - - - - - - - - - - - - - 24,485$ -

- - - - - - - - - - - - - - - - - - 20,000$ -

- - - - - - - - - - - - - - - - - - 5,000$ -

- - - - - - - - - - - - - - - - - - 10,000$ -

- - - - - - - - - - - - - - - - - - 10,000$ -

6,000$ 96,000$ 6,000$ 96,000$ 6,000$ 96,000$ 6,000$ 96,000$ 6,000$ 96,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 40,000$ 128,000$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

2,500$ - 2,500$ - 2,500$ - 2,500$ - 50,000$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ -

- - - - - - - - 1,500$ - - - - - - - - - 1,500$ -

- - - - - - - - - - - - - - - - - - 5,000$ -

- - - - - - - - - - - - - - - - - - 15,000$ -

- - - - - - - - - - - - - - - - - - 15,000$ -

- 18,000$ - 18,000$ - 18,000$ - 18,000$ 18,000$ - 18,000$ - 18,000$ - 18,000$ - 18,000$ 5,000$ 18,000$

2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 5,000$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 5,000$ 5,000$

- - - - - - - - - - - - - - - - - - 10,000$ -

119,000$ 119,000$ 119,000$ 119,000$ 119,000$ 151,000$ 151,000$ 151,000$ 151,000$ 151,000$

164,724$ 169,666$ 174,756$ 179,998$ 185,398$ 242,311$ 249,580$ 257,067$ 264,779$ 272,723$

96,000$ 94,000$ 93,000$ 91,000$ 89,000$ 111,000$ 109,000$ 107,000$ 105,000$ 103,000$

36,000$ 36,000$ 36,000$ 36,000$ 97,500$ 36,000$ 36,000$ 36,000$ 36,000$ 208,485$

49,832$ 51,327$ 52,867$ 54,453$ 151,902$ 57,769$ 59,503$ 61,288$ 63,126$ 376,547$

29,000$ 29,000$ 28,000$ 28,000$ 73,000$ 26,000$ 26,000$ 25,000$ 25,000$ 142,000$

130,000$ 245,000$ 119,000$ 162,000$ 137,000$ 135,000$ 132,000$

141312 15

121,000$ 123,000$

11

125,000$

2019181716

Page 2 of 5

Location: North of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PS Reservoir Type: CIP Concrete, In-Ground, 20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 15

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity

(L/s)403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 48,600

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Power per Year at Ultimate Flowrate

(kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Estimated Operational Hours per Month (hrs) 6

Estimated Realization of Ultimate Flowrate Estimated Operation per Year (hours) 72

Years 1 - 5 25% Estimated Annual Fuel Consumption (L)/yr 4,905

Years 6 - 10 50%

Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of $10,000 for

CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at $5/m3 of CIP

concrete. Total estimated concrete volume is 4,897 m3. Costs

estimated every 10 years for crack repair and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated at

$10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

Pumps

1. Estimated annual maintenance costs - $1,500 per pump. Total of

4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at $2,500.

15 year instrumentation replacement and refurbishment costs

estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment - $1,500. 1. Not applicable/

Div 15 Mechanical15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations, above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five year

refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption costs

calculation, above.

16820 MCC and associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Sub-Total - Estimated Construction Cost - Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - Present Value

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount Factor

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for Discount Factor

Pump Electricity Cost Calculation, Assumptions:

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Design Alternative No. 1A

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

- - - - - - - - - - - - - - - - - - 10,000$ -

5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 15,000$ -

- - - - - - - - - - - - - - - - - 24,485$ -

- - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - -

6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 50,000$ -

- - - - - - - - 1,500$ - - - - - - - - - 1,500$ -

- - - - - - - - - - - - - - - - - - 5,000$ -

- - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - -

- 18,000$ - 18,000$ - 18,000$ - 18,000$ 18,000$ - 18,000$ - 18,000$ - 18,000$ - 18,000$ 5,000$ 18,000$

2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 5,000$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 5,000$ 5,000$

- - - - - - - - - - - - - - - - - - 10,000$ -

151,000$ 151,000$ 151,000$ 151,000$ 151,000$ 151,000$ 151,000$ 151,000$ 151,000$ 151,000$

280,904$ 289,332$ 298,012$ 306,952$ 316,160$ 325,645$ 335,415$ 345,477$ 355,841$ 366,517$

101,000$ 99,000$ 97,000$ 95,000$ 93,000$ 92,000$ 90,000$ 88,000$ 86,000$ 85,000$

36,000$ 36,000$ 36,000$ 36,000$ 40,000$ 36,000$ 36,000$ 36,000$ 36,000$ 151,985$

66,971$ 68,980$ 71,049$ 73,181$ 83,751$ 77,637$ 79,966$ 82,365$ 84,836$ 368,907$

24,000$ 24,000$ 23,000$ 23,000$ 25,000$ 22,000$ 21,000$ 21,000$ 21,000$ 85,000$

125,000$ 123,000$ 120,000$ 118,000$ 170,000$ 118,000$ 114,000$ 111,000$ 109,000$ 107,000$

30292825 26 2721 22 23 24

Page 3 of 5

Location: North of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PS Reservoir Type: CIP Concrete, In-Ground, 20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 15

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity

(L/s)403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 48,600

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Power per Year at Ultimate Flowrate

(kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Estimated Operational Hours per Month (hrs) 6

Estimated Realization of Ultimate Flowrate Estimated Operation per Year (hours) 72

Years 1 - 5 25% Estimated Annual Fuel Consumption (L)/yr 4,905

Years 6 - 10 50%

Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of $10,000 for

CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at $5/m3 of CIP

concrete. Total estimated concrete volume is 4,897 m3. Costs

estimated every 10 years for crack repair and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated at

$10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

Pumps

1. Estimated annual maintenance costs - $1,500 per pump. Total of

4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at $2,500.

15 year instrumentation replacement and refurbishment costs

estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment - $1,500. 1. Not applicable/

Div 15 Mechanical15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations, above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five year

refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption costs

calculation, above.

16820 MCC and associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Sub-Total - Estimated Construction Cost - Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - Present Value

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount Factor

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for Discount Factor

Pump Electricity Cost Calculation, Assumptions:

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Design Alternative No. 1A

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

- - - - - - - - - - - - - - - - - 10,000$ -

5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 10,000$ -

- - - - - - - - - - - - - - - - - 24,485$ -

- - - - - - - - - - - - - - - - - 20,000$ -

- - - - - - - - - - - - - - - - - 5,000$ -

- - - - - - - - - - - - - - - - - 10,000$ -

- - - - - - - - - - - - - - - - - 10,000$ -

6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 40,000$ 128,000$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ -

- - - - - - - - 1,500$ - - - - - - - - - 1,500$ -

- - - - - - - - - - - - - - - - - 5,000$ -

- - - - - - - - - - - - - - - - - 15,000$ -

- - - - - - - - - - - - - - - - - 15,000$ -

- 18,000$ - 18,000$ - 18,000$ - 18,000$ 18,000$ - 18,000$ - 18,000$ - 18,000$ - 18,000$ 5,000$ 18,000$

2,500$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 5,000$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 5,000$ -$

- - - - - - - - - - - - - - - - - 10,000$ -

146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$

365,012$ 375,962$ 387,241$ 398,858$ 410,824$ 423,149$ 435,843$ 448,918$ 462,386$ 476,258$

80,000$ 79,000$ 77,000$ 76,000$ 74,000$ 73,000$ 72,000$ 70,000$ 69,000$ 68,000$

36,000$ 36,000$ 36,000$ 36,000$ 40,000$ 36,000$ 36,000$ 36,000$ 36,000$ 208,485$

90,003$ 92,703$ 95,484$ 98,349$ 112,554$ 104,338$ 107,468$ 110,692$ 114,013$ 680,086$

20,000$ 19,000$ 19,000$ 19,000$ 20,000$ 18,000$ 18,000$ 17,000$ 17,000$ 97,000$

36 37 38 39 4031 32 33 34 35

100,000$ 98,000$ 96,000$ 95,000$ 94,000$ 91,000$ 90,000$ 87,000$ 86,000$ 165,000$

Page 4 of 5

Location: North of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PS Reservoir Type: CIP Concrete, In-Ground, 20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 15

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity

(L/s)403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 48,600

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Power per Year at Ultimate Flowrate

(kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Estimated Operational Hours per Month (hrs) 6

Estimated Realization of Ultimate Flowrate Estimated Operation per Year (hours) 72

Years 1 - 5 25% Estimated Annual Fuel Consumption (L)/yr 4,905

Years 6 - 10 50%

Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of $10,000 for

CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at $5/m3 of CIP

concrete. Total estimated concrete volume is 4,897 m3. Costs

estimated every 10 years for crack repair and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated at

$10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

Pumps

1. Estimated annual maintenance costs - $1,500 per pump. Total of

4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at $2,500.

15 year instrumentation replacement and refurbishment costs

estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment - $1,500. 1. Not applicable/

Div 15 Mechanical15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations, above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five year

refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption costs

calculation, above.

16820 MCC and associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Sub-Total - Estimated Construction Cost - Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - Present Value

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount Factor

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for Discount Factor

Pump Electricity Cost Calculation, Assumptions:

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Design Alternative No. 1A

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

- - - - - - - - - - - - - - - - - 10,000$ -

5,000$ - 5,000$ - 5,000$ - 5,000$ - 15,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ -

- - - - - - - - - - - - - - - - - 24,485$ -

- - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - -

6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$ 6,000$ 128,000$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

2,500$ - 2,500$ - 2,500$ - 2,500$ - 50,000$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ -

- - - - - - - - 1,500$ - - - - - - - - - 1,500$ -

- - - - - - - - - - - - - - - - - 5,000$ -

- - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - -

- 18,000$ - 18,000$ - 18,000$ - 18,000$ 18,000$ - 18,000$ - 18,000$ - 18,000$ - 18,000$ 18,000$

2,500$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 5,000$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 5,000$ -$

- - - - - - - - - - - - - - - - - 10,000$ -

146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$ 146,000$

490,545$ 505,262$ 520,419$ 536,032$ 552,113$ 568,676$ 585,737$ 603,309$ 621,408$ 640,050$

66,000$ 65,000$ 64,000$ 63,000$ 61,000$ 60,000$ 59,000$ 58,000$ 57,000$ 56,000$

36,000$ 36,000$ 36,000$ 36,000$ 97,500$ 36,000$ 36,000$ 36,000$ 36,000$ 89,485$

120,956$ 124,585$ 128,323$ 132,172$ 368,706$ 140,222$ 144,428$ 148,761$ 153,224$ 392,294$

16,000$ 16,000$ 16,000$ 15,000$ 41,000$ 15,000$ 15,000$ 14,000$ 14,000$ 34,000$

46 47 48 49 5041 42 43 44 45

71,000$ 90,000$ 82,000$ 81,000$ 80,000$ 78,000$ 102,000$ 75,000$ 74,000$ 72,000$

Page 5 of 5

Location: North or South of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PSReservoir Type:

Glass-Fused-to-Steel Reservoir, At-Grade,

20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 12

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity (L/s) 403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 38,880

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Pump Power per Year at Ultimate

Flowrate (kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Total No. of Mixer Operating Hours per Year @

50% for 6 months and 25% for 6 months

(hr/year)

19710 Estimated Operational Hours per Month (Hrs) 6

Pump Power (KW) 2.5 Estimated Operation per Year (Hours) 72

No. of Mixers 2 Estimated Annual Fuel Consumption (L)/yr 4,905

Required Mixer Power per Year at Ultimate

Flowrate (kW-h/year)98,550

Estimated Realization of Ultimate Flowrate

Years 1 - 5 25%

Years 6 - 10 50%

i Years 11 - 15 75%

Years 16 - 50 100%

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works

2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of

$10,000 for CCTV inspection and cleaning/ flushing costs.

1. Not applicable

- - - - - - - - - - - - - - - - - - 10,000$ - - - - - - -

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable. 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ -

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at

$5/m3 of CIP concrete. Total estimated concrete volume is

1,735 m3. Costs estimated every 15 years for crack repair

and resurfacing..

1. Not applicable.

- - - - - - - - - - - - - - - - - - - - - - - -

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable. - - - - - - - - - - - - - - - - - - - - - - - - - -

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.- - - - - - - - - - - - - - - - - - - - - - - - - -

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated

at $10,000.

1. Not applicable.- - - - - - - - - - - - - - - - - - - - - - - - - -

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - - - - - - - - -

Div 11 Equipment

11000

11215

11560

11700

Pumps and Mixers

1. Estimated annual maintenance costs - $1,500 per pump.

Total of 4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per

pump.

1. Refer to pump electricity cost

calcuations, above.

6,000$ 55,200$ 6,000$ 55,200$ 6,000$ 55,200$ 6,000$ 55,200$ 6,000$ 55,200$ 6,000$ 90,400$ 6,000$ 90,400$ 6,000$ 90,400$ 6,000$ 90,400$ 6,000$ 90,400$ 6,000$ 125,600$ 6,000$ 125,600$ 6,000$ 125,600$

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable. 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

11xxx Glass-fused-Steel Bolted Tank and Cover Estimated bolted tank replacement at yr 45 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at

$2,500. 15 year instrumentation replacement and

refurbishment costs estimated at $50,000.

2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ -

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment -

$1,500.

1. Not applicable/- - - - - - - - 1,500$ - - - - - - - - - 1,500$ - - - - - - -

Div 15 Mechanical

15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

- - - - - - - - - - - - - - - - - - 5,000$ - - - - - - -

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - - - - - - - - -

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - - - - - - - -

15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations,

above.- 16,000$ - 16,000$ - 16,000$ - 16,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$ 5,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five

year refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption

costs calculation, above.2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$

16820 MCC and associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - 10,000$ - - - - - - -

16xxx Cathodic Protection 1. 10 year sacraficial anode replacement at $10,000. 1. Not applicable. 10,000$

76,000$ 76,000$ 76,000$ 76,000$ 76,000$ 111,000$ 111,000$ 111,000$ 111,000$ 111,000$ 147,000$ 147,000$ 147,000$

Note: O&M costs are assumed to be the same between Site 1 and Site 2 78,280$ 80,628$ 83,047$ 85,539$ 88,105$ 132,540$ 136,516$ 140,611$ 144,830$ 149,175$ 203,482$ 209,587$ 215,874$

75,000$ 73,000$ 72,000$ 70,000$ 69,000$ 99,000$ 97,000$ 95,000$ 93,000$ 92,000$ 119,000$ 117,000$ 114,000$

36,000$ 36,000$ 36,000$ 36,000$ 42,500$ 36,000$ 36,000$ 36,000$ 36,000$ 82,500$ 36,000$ 36,000$ 36,000$

37,080$ 38,192$ 39,338$ 40,518$ 49,269$ 42,986$ 44,275$ 45,604$ 46,972$ 110,873$ 49,832$ 51,327$ 52,867$

35,000$ 35,000$ 34,000$ 33,000$ 39,000$ 32,000$ 31,000$ 31,000$ 30,000$ 68,000$ 29,000$ 29,000$ 28,000$

8,644,000$

21,224,400$ *obtained from Capital Cost Estimate Spreadsheet

29,868,400$

21,774,000$

30,418,000$

2 3 4 5

Design Alternatives No. 2A & 2B

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Pump & Mixer Electricity Cost Calculation, Assumptions: Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

12 13

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount

Factor

Sub-Total - Estimated Annual O&M Cost - Present Value 110,000$ 108,000$

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for

Discount Factor

6 7 8 9 10 111

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Grand Total - Estimated 50 Yr Life Cycle Cost - 2B Present Value

160,000$ 148,000$ 146,000$ 142,000$

Sub-Total - Estimated Construction Cost - 2B Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - 2A Present Value

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Construction Cost - 2A Present Value

103,000$ 108,000$ 131,000$ 128,000$ 126,000$ 123,000$ 106,000$

Page 1 of 4

Location: North or South of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PSReservoir Type:

Glass-Fused-to-Steel Reservoir, At-Grade,

20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 12

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity (L/s) 403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 38,880

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Pump Power per Year at Ultimate

Flowrate (kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Total No. of Mixer Operating Hours per Year @

50% for 6 months and 25% for 6 months

(hr/year)

19710 Estimated Operational Hours per Month (Hrs) 6

Pump Power (KW) 2.5 Estimated Operation per Year (Hours) 72

No. of Mixers 2 Estimated Annual Fuel Consumption (L)/yr 4,905

Required Mixer Power per Year at Ultimate

Flowrate (kW-h/year)98,550

Estimated Realization of Ultimate Flowrate

Years 1 - 5 25%

Years 6 - 10 50%

i Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works

2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of

$10,000 for CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at

$5/m3 of CIP concrete. Total estimated concrete volume is

1,735 m3. Costs estimated every 15 years for crack repair

and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated

at $10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

11700

Pumps and Mixers

1. Estimated annual maintenance costs - $1,500 per pump.

Total of 4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per

pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

11xxx Glass-fused-Steel Bolted Tank and Cover Estimated bolted tank replacement at yr 45 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at

$2,500. 15 year instrumentation replacement and

refurbishment costs estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment -

$1,500.

1. Not applicable/

Div 15 Mechanical

15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations,

above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five

year refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption

costs calculation, above.

16820 MCC and associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. 10 year sacraficial anode replacement at $10,000. 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Design Alternatives No. 2A & 2B

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Pump & Mixer Electricity Cost Calculation, Assumptions: Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount

Factor

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for

Discount Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Grand Total - Estimated 50 Yr Life Cycle Cost - 2B Present Value

Sub-Total - Estimated Construction Cost - 2B Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - 2A Present Value

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Construction Cost - 2A Present Value

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

- - - - - - - - - - - - 10,000$ - - - - - - - - - - - - -

5,000$ - 15,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 10,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ -

- - 8,750$ - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - 20,000$ - - - - - - - - - - - - -

- - - - - - - - - - - - 5,000$ - - - - - - - - - - - - -

- - - - - - - - - - - - 10,000$ - - - - - - - - - - - - -

- - - - - - - - - - - - 10,000$ - - - - - - - - - - - - -

6,000$ 125,600$ 6,000$ 125,600$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 40,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

2,500$ - 50,000$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ -

- - 1,500$ - - - - - - - - - 1,500$ - - - - - - - - - 1,500$ - - -

- - - - - - - - - - - - 5,000$ - - - - - - - - - - - - -

- - - - - - - - - - - - 15,000$ - - - - - - - - - - - - -

- - - - - - - - - - - - 15,000$ - - - - - - - - - - - - -

- 16,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$ 5,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$ 16,000$ - 16,000$

2,500$ 5,000$ 7,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 2,500$ 5,000$

- - - - - - - - - - - - 10,000$ - - - - - - - - - - - - -

10,000$

147,000$ 147,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$

222,351$ 229,021$ 292,057$ 300,818$ 309,843$ 319,138$ 328,712$ 338,574$ 348,731$ 359,193$ 369,969$ 381,068$ 392,500$

112,000$ 110,000$ 134,000$ 131,000$ 129,000$ 126,000$ 124,000$ 122,000$ 119,000$ 117,000$ 115,000$ 113,000$ 110,000$

36,000$ 108,750$ 36,000$ 36,000$ 36,000$ 36,000$ 196,500$ 36,000$ 36,000$ 36,000$ 36,000$ 42,500$ 36,000$

54,453$ 169,429$ 57,769$ 59,503$ 61,288$ 63,126$ 354,901$ 66,971$ 68,980$ 71,049$ 73,181$ 88,986$ 77,637$

28,000$ 81,000$ 26,000$ 26,000$ 25,000$ 25,000$ 134,000$ 24,000$ 24,000$ 23,000$ 23,000$ 26,000$ 22,000$

2618 19 20 21 22 2314 15 16 17 24 25

143,000$ 140,000$ 138,000$ 140,000$ 160,000$ 157,000$ 154,000$ 151,000$ 258,000$ 146,000$ 132,000$ 191,000$ 139,000$

Page 2 of 4

Location: North or South of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PSReservoir Type:

Glass-Fused-to-Steel Reservoir, At-Grade,

20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 12

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity (L/s) 403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 38,880

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Pump Power per Year at Ultimate

Flowrate (kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Total No. of Mixer Operating Hours per Year @

50% for 6 months and 25% for 6 months

(hr/year)

19710 Estimated Operational Hours per Month (Hrs) 6

Pump Power (KW) 2.5 Estimated Operation per Year (Hours) 72

No. of Mixers 2 Estimated Annual Fuel Consumption (L)/yr 4,905

Required Mixer Power per Year at Ultimate

Flowrate (kW-h/year)98,550

Estimated Realization of Ultimate Flowrate

Years 1 - 5 25%

Years 6 - 10 50%

i Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works

2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of

$10,000 for CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at

$5/m3 of CIP concrete. Total estimated concrete volume is

1,735 m3. Costs estimated every 15 years for crack repair

and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated

at $10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

11700

Pumps and Mixers

1. Estimated annual maintenance costs - $1,500 per pump.

Total of 4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per

pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

11xxx Glass-fused-Steel Bolted Tank and Cover Estimated bolted tank replacement at yr 45 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at

$2,500. 15 year instrumentation replacement and

refurbishment costs estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment -

$1,500.

1. Not applicable/

Div 15 Mechanical

15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations,

above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five

year refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption

costs calculation, above.

16820 MCC and associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. 10 year sacraficial anode replacement at $10,000. 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Design Alternatives No. 2A & 2B

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Pump & Mixer Electricity Cost Calculation, Assumptions: Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount

Factor

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for

Discount Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Grand Total - Estimated 50 Yr Life Cycle Cost - 2B Present Value

Sub-Total - Estimated Construction Cost - 2B Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - 2A Present Value

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Construction Cost - 2A Present Value

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

- - - - - - 10,000$ - - - - - - - - - - - - - - - - -

5,000$ - 5,000$ - 5,000$ - 15,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ 5,000$ - 5,000$ - 5,000$ - 5,000$ -

- - - - - - 8,750$ - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - - -

6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

2,500$ - 2,500$ - 2,500$ - 50,000$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ 2,500$ - 2,500$ - 2,500$ - 2,500$ -

- - - - - - 1,500$ - - - - - - - - - 1,500$ - - - - - - - -

- - - - - - 5,000$ - - - - - - ` - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - -

- 16,000$ - 16,000$ - 16,000$ 5,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$

2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 7,500$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$

- - - - - - 10,000$ - - - - - - - - - - - - - - - - -

10,000$

182,000$ 182,000$ 182,000$ 182,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$

404,275$ 416,403$ 428,895$ 441,762$ 442,514$ 455,790$ 469,463$ 483,547$ 498,054$ 512,995$ 528,385$ 544,237$ 560,564$

108,000$ 106,000$ 104,000$ 102,000$ 98,000$ 96,000$ 94,000$ 92,000$ 90,000$ 89,000$ 87,000$ 85,000$ 84,000$

36,000$ 36,000$ 36,000$ 148,750$ 36,000$ 36,000$ 36,000$ 36,000$ 42,500$ 36,000$ 36,000$ 36,000$ 36,000$

79,966$ 82,365$ 84,836$ 361,055$ 90,003$ 92,703$ 95,484$ 98,349$ 119,589$ 104,338$ 107,468$ 110,692$ 114,013$

21,000$ 21,000$ 21,000$ 84,000$ 20,000$ 19,000$ 19,000$ 19,000$ 22,000$ 18,000$ 18,000$ 17,000$ 17,000$

27 3028 29

127,000$ 125,000$ 186,000$ 129,000$

36 37 38 3931 32 33 34 35

107,000$ 105,000$ 102,000$ 101,000$ 118,000$ 115,000$ 113,000$ 111,000$ 112,000$

Page 3 of 4

Location: North or South of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PSReservoir Type:

Glass-Fused-to-Steel Reservoir, At-Grade,

20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 12

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity (L/s) 403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 38,880

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Pump Power per Year at Ultimate

Flowrate (kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Total No. of Mixer Operating Hours per Year @

50% for 6 months and 25% for 6 months

(hr/year)

19710 Estimated Operational Hours per Month (Hrs) 6

Pump Power (KW) 2.5 Estimated Operation per Year (Hours) 72

No. of Mixers 2 Estimated Annual Fuel Consumption (L)/yr 4,905

Required Mixer Power per Year at Ultimate

Flowrate (kW-h/year)98,550

Estimated Realization of Ultimate Flowrate

Years 1 - 5 25%

Years 6 - 10 50%

i Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works

2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of

$10,000 for CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at

$5/m3 of CIP concrete. Total estimated concrete volume is

1,735 m3. Costs estimated every 15 years for crack repair

and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated

at $10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

11700

Pumps and Mixers

1. Estimated annual maintenance costs - $1,500 per pump.

Total of 4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per

pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

11xxx Glass-fused-Steel Bolted Tank and Cover Estimated bolted tank replacement at yr 45 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at

$2,500. 15 year instrumentation replacement and

refurbishment costs estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment -

$1,500.

1. Not applicable/

Div 15 Mechanical

15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations,

above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five

year refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption

costs calculation, above.

16820 MCC and associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. 10 year sacraficial anode replacement at $10,000. 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Design Alternatives No. 2A & 2B

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Pump & Mixer Electricity Cost Calculation, Assumptions: Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount

Factor

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for

Discount Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Grand Total - Estimated 50 Yr Life Cycle Cost - 2B Present Value

Sub-Total - Estimated Construction Cost - 2B Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - 2A Present Value

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Construction Cost - 2A Present Value

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

10,000$ - - - - - - - - - - - - - - - - 10,000$

10,000$ 5,000$ - 5,000$ - 5,000$ - 5,000$ - 15,000$ 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$

- - - - - - - - 8,750$ - - - - - - - -

20,000$ - - - - - - - - - - - - - - - -

5,000$ - - - - - - - - - - - - - - - -

10,000$ - - - - - - - - - - - - - - - -

10,000$ - - - - - - - - - - - - - - - -

40,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

5,500,000$

2,500$ 2,500$ - 2,500$ - 2,500$ - 2,500$ - 50,000$ 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$

1,500$ - - - - - - - - 1,500$ - - - - - - - - 1,500$

5,000$ - - - - - - - - - - - - - - - - 5,000$

15,000$ - - - - - - - - - - - - - - - -

15,000$ - - - - - - - - - - - - - - - -

5,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$ 5,000$ 16,000$

7,500$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 7,500$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 2,500$ -$ 7,500$

10,000$ - - - - - - - - - - - - - - - - 10,000$

10,000$ 10,000$

177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$

577,381$ 594,702$ 612,543$ 630,919$ 649,847$ 669,342$ 689,423$ 710,105$ 731,409$ 753,351$ 775,951$

82,000$ 80,000$ 79,000$ 77,000$ 76,000$ 74,000$ 73,000$ 72,000$ 70,000$ 69,000$ 68,000$

176,500$ 36,000$ 36,000$ 36,000$ 36,000$ 5,582,750$ 36,000$ 36,000$ 36,000$ 36,000$ 82,500$

575,750$ 120,956$ 124,585$ 128,323$ 132,172$ 21,111,704$ 140,222$ 144,428$ 148,761$ 153,224$ 361,672$

82,000$ 16,000$ 16,000$ 16,000$ 15,000$ 2,350,000$ 15,000$ 15,000$ 14,000$ 14,000$ 32,000$

40 46 47 48 49 5041 42 43 44 45

164,000$ 88,000$ 87,000$ 84,000$ 83,000$ 100,000$ 96,000$ 95,000$ 93,000$ 91,000$ 2,424,000$

Page 4 of 4

Location: North or South of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PSReservoir Type:

Precast/Prestressed Concrete, At-Grade,

20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 12

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity

(L/s)403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 38,880

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Power per Year at Ultimate

Flowrate (kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Estimated Operational Hours per Month (Hrs) 6

Total No. of Mixer Operating Hours per Year @

50% for 6 months and 25% for 6 months

(hr/year)

19710 Estimated Operation per Year (Hours) 72

Pump Power (KW) 2.5 Estimated Annual Fuel Consumption (L)/yr 4,905

No. of Mixers 2

Required Power per Year at Ultimate

Flowrate (kW-h/year)98,550

Estimated Realization of Ultimate Flowrate

Years 1 - 5 25%

Years 6 - 10 50%

Years 11 - 15 75%

Years 16 - 50 100%

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish't

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works

2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of

$10,000 for CCTV inspection and cleaning/ flushing costs.

1. Not applicable

- - - - - - - - - - - - - - - - - - 10,000$ - - - - - -

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable. 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at

$10/m3 of CIP concrete. Total estimated concrete volume

is 3,346 m3. Costs estimated every 15 years for crack

repair and resurfacing..

1. Not applicable.

- - - - - - - - - - - - - - - - - - - - - - -

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable. - - - - - - - - - - - - - - - - - - - - - - - - -

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.- - - - - - - - - - - - - - - - - - - - - - - - -

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated

at $10,000.

1. Not applicable.- - - - - - - - - - - - - - - - - - - - - - - - -

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - - - - - - - -

Div 11 Equipment

11000

11215

11560

11700

Pumps and Mixers

1. Estimated annual maintenance costs - $1,500 per pump.

Total of 4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per

pump.

1. Refer to pump electricity cost

calcuations, above.

6,000$ 55,200$ 6,000$ 55,200$ 6,000$ 55,200$ 6,000$ 55,200$ 6,000$ 55,200$ 6,000$ 90,400$ 6,000$ 90,400$ 6,000$ 90,400$ 6,000$ 90,400$ 6,000$ 90,400$ 6,000$ 125,600$ 6,000$ 125,600$ 6,000$

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable. 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at

$2,500. 15 year instrumentation replacement and

refurbishment costs estimated at $50,000.

2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment -

$1,500.

1. Not applicable/- - - - - - - - 1,500$ - - - - - - - - - 1,500$ - - - - - -

Div 15 Mechanical

15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

- - - - - - - - - - - - - - - - - - 5,000$ - - - - - -

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - - - - - - - -

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - - - - - - -

15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations,

above.- 16,000$ - 16,000$ - 16,000$ - 16,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$ 5,000$ 16,000$ - 16,000$ - 16,000$ -

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five

year refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption

costs calculation, above.2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$

16820 MCC & associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable. - - - - - - - - - - - - - - - - - - 10,000$ - - - - - -

16xxx Cathodic Protection 1. Not applicable.

76,000$ 76,000$ 76,000$ 76,000$ 76,000$ 111,000$ 111,000$ 111,000$ 111,000$ 111,000$ 147,000$ 147,000$

Note: O&M costs are assumed to be the same between Site 1 and Site 2 78,280$ 80,628$ 83,047$ 85,539$ 88,105$ 132,540$ 136,516$ 140,611$ 144,830$ 149,175$ 203,482$ 209,587$

75,000$ 73,000$ 72,000$ 70,000$ 69,000$ 99,000$ 97,000$ 95,000$ 93,000$ 92,000$ 119,000$ 117,000$

36,000$ 36,000$ 36,000$ 36,000$ 42,500$ 36,000$ 36,000$ 36,000$ 36,000$ 72,500$ 36,000$ 36,000$ 36,000$

37,080$ 38,192$ 39,338$ 40,518$ 49,269$ 42,986$ 44,275$ 45,604$ 46,972$ 97,434$ 49,832$ 51,327$ 52,867$

35,000$ 35,000$ 34,000$ 33,000$ 39,000$ 32,000$ 31,000$ 31,000$ 30,000$ 60,000$ 29,000$ 29,000$ 28,000$

6,334,000$

25,020,000$ *obtained from Capital Cost Estimate Spreadsheet

31,354,000$

25,410,000$

31,354,000$

2 3 4 5

Design Alternatives No. 3A & 3B

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Pump Electricity Cost Calculation, Assumptions: Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

12 13

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount

Factor

Sub-Total - Estimated Annual O&M Cost - Present Value 110,000$ 108,000$

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for

Discount Factor

6 7 8 9 10 111

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Grand Total - Estimated 50 Yr Life Cycle Cost - 3B Present Value

152,000$ 148,000$ 146,000$ $

Grand Total - Estimated 50 Yr Life Cycle Cost - 3A Present Value

Sub-Total - Estimated Construction Cost - 3B Present Value

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Construction Cost - 3A Present Value

103,000$ 108,000$ 131,000$ 128,000$ 126,000$ 123,000$ 106,000$

Page 1 of 4

Location: North or South of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PSReservoir Type:

Precast/Prestressed Concrete, At-Grade,

20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 12

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity

(L/s)403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 38,880

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Power per Year at Ultimate

Flowrate (kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Estimated Operational Hours per Month (Hrs) 6

Total No. of Mixer Operating Hours per Year @

50% for 6 months and 25% for 6 months

(hr/year)

19710 Estimated Operation per Year (Hours) 72

Pump Power (KW) 2.5 Estimated Annual Fuel Consumption (L)/yr 4,905

No. of Mixers 2

Required Power per Year at Ultimate

Flowrate (kW-h/year)98,550

Estimated Realization of Ultimate Flowrate

Years 1 - 5 25%

Years 6 - 10 50%

Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works

2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of

$10,000 for CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at

$10/m3 of CIP concrete. Total estimated concrete volume

is 3,346 m3. Costs estimated every 15 years for crack

repair and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated

at $10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

11700

Pumps and Mixers

1. Estimated annual maintenance costs - $1,500 per pump.

Total of 4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per

pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at

$2,500. 15 year instrumentation replacement and

refurbishment costs estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment -

$1,500.

1. Not applicable/

Div 15 Mechanical

15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations,

above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five

year refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption

costs calculation, above.

16820 MCC & associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Design Alternatives No. 3A & 3B

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Pump Electricity Cost Calculation, Assumptions: Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount

Factor

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for

Discount Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Grand Total - Estimated 50 Yr Life Cycle Cost - 3B Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - 3A Present Value

Sub-Total - Estimated Construction Cost - 3B Present Value

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Construction Cost - 3A Present Value

Energy CostsMaintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

- - - - - - - - - - - - - 10,000$ - - - - - - - - - - -

- 5,000$ - 15,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 15,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ - 15,000$ -

- - - 33,460$ - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - 20,000$ - - - - - - - - - - -

- - - - - - - - - - - - - 5,000$ - - - - - - - - - - -

- - - - - - - - - - - - - 10,000$ - - - - - - - - - - -

- - - - - - - - - - - - - 10,000$ - - - - - - - - - - -

125,600$ 6,000$ 125,600$ 6,000$ 125,600$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 40,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

- 2,500$ - 50,000$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ -

- - - 1,500$ - - - - - - - - - 1,500$ - - - - - - - - - 1,500$ -

- - - - - - - - - - - - - 5,000$ - - - - - - - - - - -

- - - - - - - - - - - - 15,000$ - - - - - - - - - - -

- - - - - - - - - - - - 15,000$ - - - - - - - - - - -

16,000$ - 16,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$ 5,000$ 16,000$ - 16,000$ - 16,000$ - 16,000$ - 16,000$ 16,000$

5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$

- - - - - - - - - - - - - 10,000$ - - - - - - - - - - -

147,000$ 147,000$ 147,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 182,000$

215,874$ 222,351$ 229,021$ 292,057$ 300,818$ 309,843$ 319,138$ 328,712$ 338,574$ 348,731$ 359,193$ 369,969$ 381,068$

114,000$ 112,000$ 110,000$ 134,000$ 131,000$ 129,000$ 126,000$ 124,000$ 122,000$ 119,000$ 117,000$ 115,000$ 113,000$

36,000$ 133,460$ 36,000$ 36,000$ 36,000$ 36,000$ 191,500$ 36,000$ 36,000$ 36,000$ 36,000$ 52,500$

54,453$ 207,926$ 57,769$ 59,503$ 61,288$ 63,126$ 345,870$ 66,971$ 68,980$ 71,049$ 73,181$ 109,923$

28,000$ 100,000$ 26,000$ 26,000$ 25,000$ 25,000$ 130,000$ 24,000$ 24,000$ 23,000$ 23,000$ 32,000$

18 19 20 21 22 2313 14 15 16 17 24 25

143,000$ 140,000$ 138,000$ 142,000$ 140,000$ 160,000$ 157,000$ 154,000$ 151,000$ 254,000$ 146,000$ 210,000$ 145,000$

Page 2 of 4

Location: North or South of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PSReservoir Type:

Precast/Prestressed Concrete, At-Grade,

20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 12

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity

(L/s)403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 38,880

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Power per Year at Ultimate

Flowrate (kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Estimated Operational Hours per Month (Hrs) 6

Total No. of Mixer Operating Hours per Year @

50% for 6 months and 25% for 6 months

(hr/year)

19710 Estimated Operation per Year (Hours) 72

Pump Power (KW) 2.5 Estimated Annual Fuel Consumption (L)/yr 4,905

No. of Mixers 2

Required Power per Year at Ultimate

Flowrate (kW-h/year)98,550

Estimated Realization of Ultimate Flowrate

Years 1 - 5 25%

Years 6 - 10 50%

Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works

2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of

$10,000 for CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at

$10/m3 of CIP concrete. Total estimated concrete volume

is 3,346 m3. Costs estimated every 15 years for crack

repair and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated

at $10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

11700

Pumps and Mixers

1. Estimated annual maintenance costs - $1,500 per pump.

Total of 4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per

pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at

$2,500. 15 year instrumentation replacement and

refurbishment costs estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment -

$1,500.

1. Not applicable/

Div 15 Mechanical

15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations,

above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five

year refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption

costs calculation, above.

16820 MCC & associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Design Alternatives No. 3A & 3B

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Pump Electricity Cost Calculation, Assumptions: Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount

Factor

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for

Discount Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Grand Total - Estimated 50 Yr Life Cycle Cost - 3B Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - 3A Present Value

Sub-Total - Estimated Construction Cost - 3B Present Value

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Construction Cost - 3A Present Value

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish't

- - - - - - - - 10,000$ -

5,000$ - 5,000$ - 5,000$ - 5,000$ - 15,000$ - 5,000$ - 5,000$ - 5,000$ - 5,000$ 5,000$ 5,000$ - 5,000$ - 5,000$

- - - - - - - - 33,460$ -

- - - - - - - - - -

- - - - - - - - -

- - - - - - - - - -

- - - - - - - - - -

6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

2,500$ - 2,500$ - 2,500$ - 2,500$ - 50,000$ - 2,500$ - 2,500$ - 2,500$ - 2,500$ 2,500$ 2,500$ - 2,500$ - 2,500$

- - - - - - - - 1,500$ - 1,500$

- - - - - - - - 5,000$ -

- - - - - - - - - -

- - - - - - - - -

- 16,000$ - 16,000$ - 16,000$ - 16,000$ 5,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$

2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 2,500$ 5,000$ 7,500$ 5,000$ 7,500$

- - - - - - - - 10,000$ -

182,000$ 182,000$ 182,000$ 182,000$ 182,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$

392,500$ 404,275$ 416,403$ 428,895$ 441,762$ 442,514$ 455,790$ 469,463$ 483,547$ 498,054$ 512,995$ 528,385$

110,000$ 108,000$ 106,000$ 104,000$ 102,000$ 98,000$ 96,000$ 94,000$ 92,000$ 90,000$ 89,000$ 87,000$

36,000$ 36,000$ 36,000$ 36,000$ 163,460$ 33,500$ 33,500$ 33,500$ 33,500$ 42,500$ 33,500$ 33,500$ 33,500$

77,637$ 79,966$ 82,365$ 84,836$ 396,760$ 83,753$ 86,265$ 88,853$ 91,519$ 119,589$ 97,092$ 100,005$ 103,005$

22,000$ 21,000$ 21,000$ 21,000$ 92,000$ 18,000$ 18,000$ 18,000$ 17,000$ 22,000$ 17,000$ 16,000$ 16,000$

26 27 3028 29

127,000$ 125,000$ 194,000$ 132,000$ 129,000$

36 37 3831 32 33 34 35

106,000$ 103,000$ $ 116,000$ 114,000$ 112,000$ 109,000$ 112,000$

Page 3 of 4

Location: North or South of Salem, West of Hwy 400

Capital and Life Cycle Cost AnalysisPumping Station:

CIP Concrete, 4 pumps

(133L/s@60m, each)

Salem Rd Reservoir and PSReservoir Type:

Precast/Prestressed Concrete, At-Grade,

20MLD

Discount Factor 5.0% Heating Load - Estimated kW 20

Inflation Factor 3.0% Estimated Operation (Months) 6

Study Period 50 Estimated Operation (Days) 180

Estimated Cost of Diesel Fuel per Litre1.00$

Estimated Operation in Hours (50% On/Off

Cycle)2,160

Estimated Electricity Cost $ per kWh 0.20$ Estimated Operation in kWh/yr 43,200

Reservoir Capacity (ML) 20 Ventilation Load - Estimated kW 12

Average Daily Flow Capacity (L/s):

Zone 3 Max Day Demand / Max Day Peaking

Factor - 1.75 / 2 (i.e., No. of Duty Pumping

Stations)

104.3 Estimated Operation (Months) 9

Total Firm Pumping Capacity

(L/s)403 Estimated Operation (Days) 270

Annual Station Flow (m3/year) 3,288,754

Estimated Operation in Hours

(50% On/Off Cycle)3,240

Pump Operating Flow - per Pump (L/s) 133 Estimated Operation in kWh/yr 38,880

No. of Duty Pumps 3

Total No. of Pump Operating Hours per Year

(hr/year)6869

Pump Power (KW) 93 Diesel Generator Size (Prime) - kW 250

Required Power per Year at Ultimate

Flowrate (kW-h/year)638,793

Fuel Consumption - L/hr

(dieselserviceandsupply.com)68

Estimated Operational Hours per Month (Hrs) 6

Total No. of Mixer Operating Hours per Year @

50% for 6 months and 25% for 6 months

(hr/year)

19710 Estimated Operation per Year (Hours) 72

Pump Power (KW) 2.5 Estimated Annual Fuel Consumption (L)/yr 4,905

No. of Mixers 2

Required Power per Year at Ultimate

Flowrate (kW-h/year)98,550

Estimated Realization of Ultimate Flowrate

Years 1 - 5 25%

Years 6 - 10 50%

Years 11 - 15 75%

Years 16 - 50 100%

Specification No. Specification / Asset Description Maintenance Cost Rationale Energy Cost Rationale

Div 2 Site Works

2315

2511

2530

2630

Sewerage, Watermain, Storm

1. 10 year maintenance costs including allowance of

$10,000 for CCTV inspection and cleaning/ flushing costs.

1. Not applicable

2741

2821

2911

2936

Asphalt, Fences, Finish Grading, Landscaping

1. 15 year maintenance cost of asphalt - $10,000.

2. 20 Year fence maintenance costs - $5,000.

3. Annual landscaping/snow cost estimate - $5,000.1. Not applicable.

Div 3 Concrete Works

3200

3300Cast-In-Place Concrete

1. Concrete repair and resurfacing work estimated at

$10/m3 of CIP concrete. Total estimated concrete volume

is 3,346 m3. Costs estimated every 15 years for crack

repair and resurfacing..

1. Not applicable.

Div 7 Building Specialties

7000 Membrane Waterproofing 1. 20 year refurbishment costs estimated at $20,000 1. Not applicable.

Div 8 Metal Doors and Frames

8110

8710All Doors and Window Items

1. 20 year refurbishment costs of $5,000 1. Not applicable.

Div 9 Dry Wall and Painting

9900 All Finishing Items1. 20 Year Painting and wall refurbishment costs estimated

at $10,000.

1. Not applicable.

Div 10 Miscellaneous Specialties

10200 Louvres and Vents 1. 20 Year refurbishment costs estimated at $10,000. 1. Not applicable.

Div 11 Equipment

11000

11215

11560

11700

Pumps and Mixers

1. Estimated annual maintenance costs - $1,500 per pump.

Total of 4 pumps.

2. Estimated 20 year refurbishment costs - $10,000 per

pump.

1. Refer to pump electricity cost

calcuations, above.

11260 Chemical Storage and Feed Equipment Estimated annual costs at $20,000 1. Not applicable.

Div 13 Insrumentation and Control

13000 Instrumentation and Control Infrastructure

1. Annual instrumentation calibration costs estimated at

$2,500. 15 year instrumentation replacement and

refurbishment costs estimated at $50,000.

Div 14 Monorail

14620 Metal Fabrication General1. 5 year maintenance check-up and refurbishment -

$1,500.

1. Not applicable/

Div 15 Mechanical

15200

15200-14

15201

15202

15204

Process Piping and Fittings

1. 10 year cleaning and labelling costs at $5,000. 1. Not applicable.

15205 Valves 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15760 Unit Heaters 1. 20 year refurbishment costs estimated at $15,000. 1. Not applicable.

15830

15900

15950

15955

Ventilation Infrastructure

10 year refurbishment costs - $5,000. 1. Refer to heating and ventilation

consumption costs calculations,

above.

Div 16 Electrical

16556 Diesel Engine Generator Set1. Annual maintenance costs estimated at $2,500. Five

year refurbishment costs estimated at $5,000.

1. Refer to diesel fuel consumption

costs calculation, above.

16820 MCC & associated Infrastructure 1. 10 year maintenance costs estimated at $10,000. 1. Not applicable.

16xxx Cathodic Protection 1. Not applicable.

Note: O&M costs are assumed to be the same between Site 1 and Site 2

Design Alternatives No. 3A & 3B

Financial Calculation Assumptions: Heating Cost Calculation, Assumptions:

Pump Electricity Cost Calculation, Assumptions: Ventilation Cost Calculation, Assumptions:

Diesel Fuel Cost Calculation, Assumptions:

Sub-Total - Estimated Annual M/R Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual M/R Cost - Present Value - Adjusted Annually for Discount

Factor

Sub-Total - Estimated Annual O&M Cost - Present Value

Sub-Total - Estimated Energy Cost Annual - Simple Cost

Sub-Total - Estimated Annual Energy Cost - Adjusted Annually for Inflation Factor

Sub-Total - Estimated Annual Energy Cost - Present Value - Adjusted Annually for

Discount Factor

Sub-Total - Estimated Annual Maintenance / Refurbishment Cost - Simple Cost

Grand Total - Estimated 50 Yr Life Cycle Cost - 3B Present Value

Grand Total - Estimated 50 Yr Life Cycle Cost - 3A Present Value

Sub-Total - Estimated Construction Cost - 3B Present Value

Sub-Total - Estimated 50 Yr O&M Costs - Present Value

Sub-Total - Estimated Construction Cost - 3A Present Value

Energy CostsMaintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

Maintenance/

Refurbish'tEnergy Costs

10,000$ 10,000$

- 5,000$ 10,000$ 5,000$ - 5,000$ - 5,000$ - 5,000$ 15,000$ 5,000$ - 5,000$ - 5,000$ - 5,000$ 5,000$

33,460$

20,000$

5,000$

10,000$

10,000$

160,800$ 6,000$ 160,800$ 40,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$ 6,000$ 160,800$

20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$ 20,000$

- 2,500$ 2,500$ 2,500$ - 2,500$ - 2,500$ - 2,500$ 50,000$ 2,500$ - 2,500$ - 2,500$ - 2,500$ 2,500$

1,500$ 1,500$ 1,500$

5,000$ 5,000$

15,000$

15,000$

16,000$ 16,000$ 5,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$ 16,000$

7,500$ 7,500$ 7,500$

10,000$ 10,000$

177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$ 177,000$

544,237$ 560,564$ 577,381$ 594,702$ 612,543$ 630,919$ 649,847$ 669,342$ 689,423$ 710,105$ 731,409$ 753,351$ 775,951$

85,000$ 84,000$ 82,000$ 80,000$ 79,000$ 77,000$ 76,000$ 74,000$ 73,000$ 72,000$ 70,000$ 69,000$ 68,000$

33,500$ 186,500$ 33,500$ 33,500$ 33,500$ 33,500$ 113,460$ 33,500$ 33,500$ 33,500$ 33,500$ 47,500$

106,095$ 608,370$ 112,557$ 115,933$ 119,411$ 122,994$ 429,060$ 130,484$ 134,398$ 138,430$ 142,583$ 208,236$

16,000$ 86,000$ 15,000$ 15,000$ 15,000$ 14,000$ 48,000$ 14,000$ 14,000$ 13,000$ 13,000$ 18,000$

38 39 40 46 47 48 49 5041 42 43 44 45

101,000$ 100,000$ 168,000$ 87,000$ 86,000$ 83,000$ 82,000$ 86,000$ 95,000$ 94,000$ 92,000$ 90,000$ 122,000$

Page 4 of 4

APPENDIX C

EVALUATION MATRICES

Evaluation Criteria

Relative

Importance

By Criteria Overall

Construction 20%

Relative Complexity 30% 6% 3 0.18 1 0.06 1 0.06

Expandability 60% 12% 3 0.36 1 0.12 1 0.12

Implementation Schedule 10% 2% 3 0.06 1 0.02 1 0.02

100% 20% 0.60 0.20 0.20

Financial 30%

Engineering+Construction+Contingencies 60% 18% 3 0.54 1 0.18 2 0.36

Operations & Maintenance Costs 20% 6% 1 0.06 3 0.18 2 0.12

Life Cycle Costs 20% 6% 1 0.06 3 0.18 2 0.12

100% 30% 0.66 0.54 0.60

Technical 50%

Occupational Health and Safety 20% 10% 3 0.30 1 0.10 1 0.10

Water System Security 20% 10% 1 0.10 3 0.30 2 0.20

Ease of maintenance 15% 8% 3 0.23 2 0.15 1 0.08

Ice/Freeze Issues 10% 5% 1 0.05 3 0.15 2 0.10

Leakage Failure 10% 5% 3 0.15 2 0.10 1 0.05

Complexity of Repairs 10% 5% 3 0.15 1 0.05 2 0.10

Demonstrated technology in colder climates 5% 3% 1 0.03 3 0.08 2 0.05

Water Quality 10% 5% 1 0.05 3 0.15 2 0.10

100% 50% 1.05 1.08 0.78

TOTALS 100% 100% 3.57 2.56 2.38

Relative Rankings: 1,2,3 with 1 best, 3 worse. Lowest score has highest ranking.

In-Ground Cast-in-Place Glass-Fused-to-SteelPrecast-Prestressed

Concrete

SALEM ROAD RESERVOIR AND PUMPNG STATION CONCEPTUAL DESIGN - TECHNOLOGY EVALUATION MATRIX

Reservoir Technology Ranking and ScoreRelative Weighting

m:\2017\salem reservoir and pumping station - august 2017\final_appendices\appendix_b\ref\salem reservoir_cost_final_ranking_comparison_technology assessment_dw_mep_dec05_2017.xls

Salem Road Reservoir & Pumping Station Environmental Evaluation Matrix Page 1 of 4

Do Nothing Option 1

Cast-in-Place Concrete In-Ground Reservoir

Option 2

Glass-Fused-to-Steel At-Grade Reservoir

Option 3

Precast/prestressed Concrete At-Grade Reservoir

No servicing to support future

development

1A

Site 1

North side Salem Rd, West of Hwy 400

1B

Site 2

South side Salem Rd, West of Hwy 400

2A

Site 1

North side Salem Rd, West of Hwy 400

2B

Site 2

South side Salem Rd, West of Hwy 400

3A

Site 1

North side Salem Rd, West of Hwy 400

3B

Site 2

South side Salem Rd, West of Hwy 400

(Most to Least Preferred)

Natural Environment

Impact on designated natural areas (e.g. ESPAs and PSWs)

During

construction

N/A

No designated natural areas in the vicinity,

therefore minimum impacts anticipated.

Lover’s Creek Swamp PSW and a Core Area

that is part of the City of Barrie’s Natural

Heritage System are located to the south of

this area. Potential for sediment release to

adjacent features during construction.

No designated natural areas in the vicinity,

therefore minimum impacts anticipated.

Lover’s Creek Swamp PSW and a Core Area

that is part of the City of Barrie’s Natural

Heritage System are located to the south

of this area. Potential for sediment release

to adjacent features during construction.

No designated natural areas in the vicinity,

therefore minimum impacts anticipated.

Lover’s Creek Swamp PSW and a Core Area

that is part of the City of Barrie’s Natural

Heritage System are located to the south

of this area. Potential for sediment

release to adjacent features during

construction.

During

operation

N/A

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

Impact on natural heritage features (e.g. wetlands, woodlands, valleylands, wildlife and wildlife habitat)

During

construction

N/A

Construction of the reservoir will remove a

portion of a cultural vegetation mosaic (cultural

meadow / plantation / woodland) that likely

supports a typical suite of wildlife. No wetland

impacts.

Construction of the reservoir will remove a

portion of a cultural vegetation mosaic

(cultural meadow / woodland) as well as the

edge of a deciduous forest. Vegetation

communities likely support a typical suite of

wildlife. No direct wetland impacts

anticipated.

Construction of the reservoir will remove a

portion of a cultural vegetation mosaic

(cultural meadow / plantation / woodland)

that likely supports a typical suite of

wildlife. No wetland impacts.

Construction of the reservoir will remove a

portion of a cultural vegetation mosaic

(cultural meadow / woodland) as well as

the edge of a deciduous forest. Vegetation

communities likely support a typical suite

of wildlife. No direct wetland impacts

anticipated.

Construction of the reservoir will remove a

portion of a cultural vegetation mosaic

(cultural meadow / plantation / woodland)

that likely supports a typical suite of

wildlife. No wetland impacts.

Construction of the reservoir will remove

a portion of a cultural vegetation mosaic

(cultural meadow / woodland) as well as

the edge of a deciduous forest.

Vegetation communities likely support a

typical suite of wildlife. No direct wetland

impacts anticipated.

During

operation

N/A

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

Impact on fisheries and aquatic habitat

During

construction

N/A

No watercourses in the vicinity of Option A

therefore no impacts anticipated.

Lover’s Creek is located to the south of this

area. No impacts during construction are

anticipated.

No watercourses in the vicinity of Option A

therefore no impacts anticipated.

Lover’s Creek is located to the south of this

area. No impacts during construction are

anticipated.

No watercourses in the vicinity of Option A

therefore no impacts anticipated.

Lover’s Creek is located to the south of

this area. No impacts during construction

are anticipated.

During

operation

N/A

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

Impact on Species at Risk (SAR) or SAR habitat

During

construction

Salem Road Reservoir & Pumping Station Environmental Evaluation Matrix Page 2 of 4

Do Nothing Option 1

Cast-in-Place Concrete In-Ground Reservoir

Option 2

Glass-Fused-to-Steel At-Grade Reservoir

Option 3

Precast/prestressed Concrete At-Grade Reservoir

No servicing to support future

development

1A

Site 1

North side Salem Rd, West of Hwy 400

1B

Site 2

South side Salem Rd, West of Hwy 400

2A

Site 1

North side Salem Rd, West of Hwy 400

2B

Site 2

South side Salem Rd, West of Hwy 400

3A

Site 1

North side Salem Rd, West of Hwy 400

3B

Site 2

South side Salem Rd, West of Hwy 400

(Most to Least Preferred)

N/A SAR habitat potential is considered low-moderate

based on fall field review.

Low potential for SAR bats in cultural plantation

(cavity trees).

Low-moderate potential for two SAR birds (Whip-

poor-will [Threatened] and Common Nighthawk

[Threatened]). Follow-up surveys are

recommended.

Low potential for Eastern Hog-nosed Snake

(Threatened).

SAR habitat potential is considered low-

moderate based on fall field review.

Low potential for SAR bats in cultural

plantation / deciduous forest (cavity trees).

Low-moderate potential for two SAR birds

(Whip-poor-will [Threatened] and Common

Nighthawk [Threatened]). Follow-up surveys

are recommended.

Low potential for Eastern Hog-nosed Snake

(Threatened).

SAR habitat potential is considered low-

moderate based on fall field review.

Low potential for SAR bats in cultural

plantation (cavity trees).

Low-moderate potential for two SAR birds

(Whip-poor-will [Threatened] and Common

Nighthawk [Threatened]). Follow-up

surveys are recommended.

Low potential for Eastern Hog-nosed Snake

(Threatened).

SAR habitat potential is considered low-

moderate based on fall field review.

Low potential for SAR bats in cultural

plantation / deciduous forest (cavity trees).

Low-moderate potential for two SAR birds

(Whip-poor-will [Threatened] and

Common Nighthawk [Threatened]). Follow-

up surveys are recommended.

Low potential for Eastern Hog-nosed Snake

(Threatened).

SAR habitat potential is considered low-

moderate based on fall field review.

Low potential for SAR bats in cultural

plantation (cavity trees).

Low-moderate potential for two SAR birds

(Whip-poor-will [Threatened] and Common

Nighthawk [Threatened]). Follow-up

surveys are recommended.

Low potential for Eastern Hog-nosed Snake

(Threatened).

SAR habitat potential is considered low-

moderate based on fall field review.

Low potential for SAR bats in cultural

plantation / deciduous forest (cavity

trees).

Low-moderate potential for two SAR birds

(Whip-poor-will [Threatened] and

Common Nighthawk [Threatened]).

Follow-up surveys are recommended.

Low potential for Eastern Hog-nosed

Snake (Threatened).

During

operation

N/A

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

No impacts during regular operation are

anticipated.

Overall ability

to meet

regulatory

constraints

No works therefore no impacts to

natural environment features.

All works appear to be outside of LSRCA regulation

limits – confirmed with LSRCA. SAR potential

needs to be addressed.

All works appear to be outside of LSRCA

regulation limits – confirmed with LSRCA. SAR

potential needs to be addressed.

All works appear to be outside of LSRCA

regulation limits – confirmed with LSRCA.

SAR potential needs to be addressed.

All works appear to be outside of LSRCA

regulation limits – confirmed with LSRCA.

SAR potential needs to be addressed.

All works appear to be outside of LSRCA

regulation limits – confirmed with LSRCA.

SAR potential needs to be addressed.

All works appear to be outside of LSRCA

regulation limits – confirmed with LSRCA.

SAR potential needs to be addressed.

Socio-Cultural Environment

Effectiveness

and reliability

in achieving EA

objectives

Does not achieve study objectives

Meets study objectives

Meets study objectives

Meets study objectives

Meets study objectives

Meets study objectives

Meets study objectives

Potential for disruption / inconvenience to adjacent properties and buildings

During

construction

N/A

Limited low potential for minor/temporary

disruption to adjacent properties

Limited low potential for minor/temporary

disruption to adjacent properties

Limited low potential for minor/temporary

disruption to adjacent properties

Limited low potential for minor/temporary

disruption to adjacent properties

Limited low potential for minor/temporary

disruption to adjacent properties

Limited low potential for minor/

temporary disruption to adjacent

properties

Impact on

existing utilities

and services

(e.g. mains

sewers, gas,

electric etc.)

N/A

Salem Rd will be reconstructed as part of works.

No significant constraints identified.

Lockhart Rd will be reconstructed as part of

works. No significant constraints identified.

Salem Rd will be reconstructed as part of

works No significant constraints identified.

Lockhart Rd will be reconstructed as part

of works. No significant constraints

identified.

Salem Rd will be reconstructed as part of

works. No significant constraints identified.

Lockhart Rd will be reconstructed as part

of works. No significant constraints

identified.

Access to site;

present and

future

N/A

Access available from Salem Rd.

Access available from Salem Rd.

Access available from Salem Rd.

Access available from Selem Rd.

Access available from Salem Rd.

Access available from Salem Rd.

Salem Road Reservoir & Pumping Station Environmental Evaluation Matrix Page 3 of 4

Do Nothing Option 1

Cast-in-Place Concrete In-Ground Reservoir

Option 2

Glass-Fused-to-Steel At-Grade Reservoir

Option 3

Precast/prestressed Concrete At-Grade Reservoir

No servicing to support future

development

1A

Site 1

North side Salem Rd, West of Hwy 400

1B

Site 2

South side Salem Rd, West of Hwy 400

2A

Site 1

North side Salem Rd, West of Hwy 400

2B

Site 2

South side Salem Rd, West of Hwy 400

3A

Site 1

North side Salem Rd, West of Hwy 400

3B

Site 2

South side Salem Rd, West of Hwy 400

(Most to Least Preferred)

During

operation

N/A

No disruption/inconvenience to adjacent

properties during regular operation

No disruption/inconvenience to adjacent

properties during regular operation

No disruption/inconvenience to adjacent

properties during regular operation

No disruption/inconvenience to adjacent

properties during regular operation

No disruption/inconvenience to adjacent

properties during regular operation

No disruption/inconvenience to adjacent

properties during regular operation

Impact on local businesses

During

construction

N/A

No impact on local businesses during construction

– area is primarily industrial / commercial

No impact on local businesses during

construction – area is primarily industrial /

commercial

No impact on local businesses during

construction – area is primarily industrial /

commercial

No impact on local businesses during

construction – area is primarily industrial /

commercial

No impact on local businesses during

construction – area is primarily industrial /

commercial

No impact on local businesses during

construction – area is primarily industrial /

commercial

During

operation

N/A

No impact on local businesses during regular

operation

No impact on local businesses during regular

operation

No impact on local businesses during

regular operation

No impact on local businesses during

regular operation

No impact on local businesses during

regular operation

No impact on local businesses during

regular operation

Potential for loss or disruption to community / recreational features

During

construction

N/A

No disruption to community/recreational features

during construction

No disruption to community/recreational

features during construction

No disruption to community/recreational

features during construction

No disruption to community/recreational

features during construction

No disruption to community/recreational

features during construction

No disruption to community/recreational

features during construction

During

operation

N/A

No permanent loss of community features

No permanent loss of community features

No permanent loss of community features

No permanent loss of community features

No permanent loss of community features

No permanent loss of community features

Impact on

adjacent

development

N/A

No impacts on adjacent industrial/commercial

development.

No adjacent development

No impacts on adjacent

industrial/commercial development.

No adjacent development

No impacts on adjacent

industrial/commercial development.

No adjacent development

Change in

community

character

N/A

No change in community character

No change in community character

No change in community character

No change in community character

No change in community character

No change in community character

Consistency

with current

land use

designations,

policies and

development

plans

Existing land use is maintained –

however does not support growth

objectives and is not consistent

with OP policy

Consistent with land use designations and

supports growth objectives

Consistent with future land use designations,

existing surrounding land use and supports

growth objectives

Consistent with land use designations and

supports growth objectives

Consistent with future land use

designations, existing surrounding land use

and supports growth objectives

Consistent with land use designations and

supports growth objectives

Consistent with future land use

designations, existing surrounding land

use and supports growth objectives

growth objectives

Site Aesthetics

& Ability to

blend into

surrounding

landscape

N/A

Sub-grade reservoir will have minor visual impact

Sub-grade reservoir will have minor visual

impact

Above-grade reservoir will have minor

visual impact but can be designed to blend

into nearby land use.

Above-grade reservoir will have minor

visual impact but can be designed to blend

into nearby land use.

Above-grade reservoir will have minor

visual impact but can be designed to blend

into nearby land use.

Above-grade reservoir will have minor

visual impact but can be designed to blend

into nearby land use.

Salem Road Reservoir & Pumping Station Environmental Evaluation Matrix Page 4 of 4

Do Nothing Option 1

Cast-in-Place Concrete In-Ground Reservoir

Option 2

Glass-Fused-to-Steel At-Grade Reservoir

Option 3

Precast/prestressed Concrete At-Grade Reservoir

No servicing to support future

development

1A

Site 1

North side Salem Rd, West of Hwy 400

1B

Site 2

South side Salem Rd, West of Hwy 400

2A

Site 1

North side Salem Rd, West of Hwy 400

2B

Site 2

South side Salem Rd, West of Hwy 400

3A

Site 1

North side Salem Rd, West of Hwy 400

3B

Site 2

South side Salem Rd, West of Hwy 400

(Most to Least Preferred)

Potential for

disruption to

local traffic

during

construction

N/A

Site near industrial area and minimal local traffic.

Site near industrial area and minimal local

traffic.

Site near industrial area and minimal local

traffic.

Site near industrial area and minimal local

traffic.

Site near industrial area and minimal local

traffic.

Site near industrial area and minimal local

traffic.

Potential for

noise, dust and

vibration

during

construction

N/A

Hwy 400 in near proximity of property. No

significant issues identified.

Hwy 400 in near proximity of property. No

significant issues identified.

Hwy 400 in near proximity of property. No

significant issues identified.

Hwy 400 in near proximity of property. No

significant issues identified.

Hwy 400 in near proximity of property. No

significant issues identified.

Hwy 400 in near proximity of property. No

significant issues identified.

Impact on heritage resources (e.g. archaeological, built heritage and cultural heritage landscapes)

During

construction

N/A

No impacts to built heritage resources. A Stage 1 –

2 Archaeological Assessment required.

No impacts to built heritage resources. Stage

1 – 2 Archaeological Assessment required.

No impacts to built heritage resources.

Stage 1 – 2 Archaeological Assessment

required.

No impacts to built heritage resources.

Stage 1 – 2 Archaeological Assessment

required.

No impacts to built heritage resources.

Stage 1 – 2 Archaeological Assessment

required.

No impacts to built heritage resources.

Stage 1 – 2 Archaeological Assessment

required.

During

operation

N/A

No impacts, provided archaeological clearance is

obtained prior to construction.

No impacts, provided archaeological

clearance is obtained prior to construction.

No impacts, provided archaeological

clearance is obtained prior to construction.

No impacts, provided archaeological

clearance is obtained prior to construction.

No impacts, provided archaeological

clearance is obtained prior to construction.

No impacts, provided archaeological

clearance is obtained.

Impact on agricultural and rural areas

During

construction

N/A

N/A – area designated as General Industrial

Area is currently designated Rural Area. It is

not under agricultural production. The area is

designated Industrial Business Park in the

Ultimate Land Use Concept Plan.

N/A – area designated as General Industrial

Area is currently designated Rural Area. It

is not under agricultural production. The

area is designated Industrial Business Park

in the Ultimate Land Use Concept Plan.

N/A – area designated as General Industrial

Area is currently designated Rural Area. It

is not under agricultural production. The

area is designated Industrial Business Park

in the Ultimate Land Use Concept Plan.

During

operation

N/A

N/A – area designated as General Industrial

Area is currently designated Rural Area. It is

not under agricultural production. The area is

designated Industrial Business Park in the

Ultimate Land Use Concept Plan.

N/A – area designated as General Industrial

Area is currently designated Rural Area. It

is not under agricultural production. The

area is designated Industrial Business Park

in the Ultimate Land Use Concept Plan.

N/A – area designated as General Industrial

Area is currently designated Rural Area. It

is not under agricultural production. The

area is designated Industrial Business Park

in the Ultimate Land Use Concept Plan.

OVERALL

Does not provide the required

servicing infrastructure to meet

growth objectives

Ranked to have lowest environmental impact

Ranked to have the fourth lowest

environmental impact

Ranked as the second lowest

environmental impact

Considered to have greatest environmental

impact

Ranked to have the third lowest

environmental impact

Considered to have greatest

environmental impact