defects liability period - bk_australia_s_mar14

Upload: shahid-akram

Post on 26-Feb-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    1/21

    ConstructionAustralia

    Defects "Liability" PeriodsWhy they shouldn't be called that!

    March 2014

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    2/21

    www.bakermckenzie.com/australia | 2

    1. Defects Liability Periods

    1.1 A common feature of construction contracts is what is known as a defects liability

    period. The defects liability period is the period of time within which the contractor is

    contractually obliged to return to the construction site to repair defects which have

    appeared in the contractor's works. The defects liability period usually commences on

    practical or substantial completion and extends for a specified period, commonly

    12 months. It is not uncommon for a further defects liability period, often equal to the

    original period, to apply to repaired works.

    1.2 The major benefit to the client to be derived from a contractual defects liability period is

    that it provides a mechanism for the making good of defects which either do not need

    to be completed prior to practical completion or which become apparent after practical

    completion without the need for the parties to resort to dispute resolution.

    1.3 Additionally, it would make practical sense for a client to have the contractor who

    performed the original work in which a defect has appeared return to rectify that defect

    (at least for a reasonable period, when the contractor's workforce are likely to still be

    the people who did the work originally). It is likely that a contractor who is unfamiliar

    with the original work would incur greater cost rectifying the same defect than the

    original contractor.

    1.4 In addition to a contractor being contractually obliged to return to the construction site

    to repair defects which have become apparent during the defects liability period,

    depending on the wording of the relevant clause, the contractor may also have an

    exclusive right to repair defects during that period. From a contractor's perspective,

    such an exclusive right may be beneficial, as the cost of repairing defects with its own

    employees is likely to be less than the cost of the owner employing another contractor

    to repair the defects at the cost of the contractor. Where a contract confers an

    exclusive right to repair defects on the contractor, an owner who engages another

    contractor to repair defects, without first offering the contractor the opportunity to repair

    the defects, will be in breach of contract.

    1.5 Many industry standard contracts contain wording which gives the contractor an

    exclusive right to repair defects for a defined period. For example, StandardsAustralia's standard form of contracts such as AS2124, AS4000 AS4902, and other

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    3/21

    www.bakermckenzie.com/australia | 3

    similar contracts, provide an exclusive right for the period stated in the direction given

    under the contract identifying the defect(s) requiring rectification. Similarly, GC21

    requires the owner to nominate the period in which the contractor must rectify the

    identified defect(s). FIDIC contracts provide the contractor with an exclusive right to

    rectify defect(s) for a "reasonable period", after which the owner must fix the date by

    which the contractor must rectify the defect(s). In each case, where defects are not

    rectified by the contractor by the nominated date, the contractor loses their exclusive

    right to rectify defects and the owner is entitled to engage another contractor with costs

    incurred by the owner from the other contractor at the original contractor's account.

    2. The extent of a contractors legal liability for defects

    2.1 The end of the defects liability period is not, however, the end of the contractor's

    liability to their client for defects. It is merely the end of the period during which the

    contractor is contractuallyobliged to return to site and make good defects. Because of

    this fact, many contract draftsmen these days call the periods 'defects correction

    periods' instead of 'defects liability periods'.

    2.2 Owners have a common law right to sue the contractor for breaches of contract,

    relevantly here, for instances where the construction work does not meet the

    specification. The Owner as claimant is entitled to an award of damages to put them

    back in the same financial position they would have been in but for the breach. This

    common law right exists notwithstanding the parties have contractually agreed a

    defects liability (or correction) period.

    2.3 In certain circumstances, contractors have a legislative obligation to rectify defects.

    Section 72 of the Queensland Building and Services Authority Act 1991provides that

    the Queensland Building and Services Authority (the QBSA) may, if it is of the opinion

    that building work is defective, direct the person who has carried out the building work

    to rectify the defective building work within the period stated in the direction. A direction

    under section 72 of that Act can be given within the period that is 6 years and 3 months

    after the building work to which the direction relates was completed or, if not

    completed, left in an incomplete state. It is possible for the QBSA to apply to the

    Queensland Civil and Administrative Tribunal (QCAT) for the period in which a

    direction under section 72 can be given to be extended.

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    4/21

    www.bakermckenzie.com/australia | 4

    3. Limitation periods

    3.1 A statutory limitation period is procedural rather than substantive in that it bars a

    remedy but does not extinguish the claim itself.

    3.2 The limitation period for an action for breach of contract is 6 years (or 3 years in the

    Northern Territory) from the date on which the cause of action accrued1.

    3.3 The limitation period for an action for breach of a deed is 12 years (or 15 years in

    Victoria and South Australia) from the date on which the cause of action accrued2.

    3.4 Naturally, therefore, owners (and their financiers) will prefer the construction

    agreement to be in the form of a deed, while contractors will prefer it to be in the form

    of a simple contract!

    3.5 The longer period for an action for breach of a deed, however, may be reduced in

    certain circumstances by the legislative "long stop" provisions in various states which

    apply to building actions. Refer to5 below. These "long stop" provisions are an

    example of where the right to a claim itself is extinguished.

    3.6 In contract, the cause of action accrues upon breach, irrespective of whether or not

    damage has been suffered (Battley v Faulkner (1820) 106 ER 668; Sheldon v McBeath

    (1993) Aust Torts Reports 81-209).

    3.7 This is in contrast to actions in tort for negligence, where the usual date of accrual is

    when damage has been suffered. Exactly when the breach occurs depends on the

    nature of the breach and the terms of the contract.

    4. Head contract deed/subcontract simple contract

    4.1 There is little difference between a contract and a deed in terms of their construction,

    performance and enforcement. As noted above, there is however a very significant

    difference in the limitation periods under each, with parties to a contract having a

    1Limitation Act 1969(NSW), s 14(1)(a); Limitation of Actions Act 1958(Vic), s 5(1)(a); Limitation of Actions Act 1974(Qld),

    s10(1); Limitation Act 1985(ACT), s11;Limitation Act (NT), s12;Limitation of Actions Act 1936(SA), s 35;Limitation Act 1974

    (Tas), s4(1); Limitation Act 2005(WA), s 13.2

    Limitation Act 1969(NSW), s 16; Limitation of Actions Act 1958(Vic), s 5(3);Limitation of Actions Act 1974(Qld), s10(3);Limitation Act 1985(ACT), s13;Limitation Act (NT), s14(1);Limitation of Actions Act 1936(SA), s 34;Limitation Act 1974

    (Tas), s4(3); Limitation Act 2005(WA), s 18.

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    5/21

    www.bakermckenzie.com/australia | 5

    period of 6 years within which to commence an action for breach while parties to a

    deed have a period of 12 (or 15) years within which to commence an action for breach.

    4.2 Due to these different limitation periods, a contactor who is a party to a deed with his

    principal who enters downstream only a simple contract with a subcontractor in which

    they seek to pass on certain of their obligations would open themself to claims under

    their upstream deed which, in certain circumstances, they are not able to pass to their

    downstream subcontractor.

    4.3 To illustrate the point, consider the construction contractor who enters a deed with a

    principal pursuant to which they are to construct a building. The contractor then

    subcontracts specialist packages using simple contracts. Should any breach of the

    upstream deed come to light more than 6 years after completion which is attributable,

    either in whole or in part, to one of the subcontractors, the contractor could well find

    themselves liable upstream without recourse downstream.

    5. Legislative "long stop" provisions

    5.1 In NSW, section 109ZK of the Environmental Planning and Assessment Act 1979

    (NSW) (EPA Act) and its associated provisions commenced on 1 July 1998 and were

    introduced by the Environmental Planning and Assessment Amendment Act

    1997(NSW) (Amending Act). It is largely accepted that section 109ZK imposes a 10

    year limitation, "long stop", period for bringing any building action.3This is supported by

    the wording in subsection 109ZK(1) "Despite any Act or law to the contrary" and

    subsection 109ZK(2), which explicitly states that the provision does not operate to

    extend any period of limitation under the Limitation Act 1969 (NSW).4

    3"The purpose of a long-stop period is to fix a date on which an action will become statute-barred, irrespective of whether the

    date of discoverability has occurred. [] a claim will become statute-barred on the expiry of the limitation period or the long-

    stop period, whichever is the earlier", Panel for Review of the Law of Negligence, Review of the Law of Negligence: Final

    Report (2002), para. 6.32.4Cf. section 134 Building Act 1993 (VIC): "Despite any thing to the contrary in the Limitation of Actions Act 1958 or in any other

    Act or law, a building action cannot be brought more than 10 years after the date of issue of the occupancy permit in respect

    of the building work (whether or not the occupancy permit is subsequently cancelled or varied) or, if an occupancy permit is

    not issued, the date of issue under Part 4 of the certificate of final inspection of the building work", noting that there is no

    Victorian equivalent to subsection 109ZK(2) of the NSW Act. Consequently, the debate in Victoria has focused largely on

    whether section 134 Building Act 1993 (VIC) imposes a "long stop" period or replaces the ordinary 6 year limitation period

    provided under the Limitation of Actions Act 1958 (VIC); see e.g. Brirek Industries Pty Ltd v McKenzie GroupConsulting(Vic) Pty Ltd [2011] VCC 294, which adopts the "long stop" approach c.f.Thurston v Campbell [2007] VCAT 340, which

    adopts the "replacement" view; see alsoC. Harrison & J. Greentree, "Limitations periods - Building Act 1993 (Vic), s 134"(2006) 22 Building and Construction Law Journal 243.The decision in Brirek Industriesalso interestingly restricts section 134

    to building actions brought in negligence and excludes contractual claims. (Note that this case is currently being appealed).

    http://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toihttp://legalonline.thomson.com.au/jour/resultDetailed.jsp?curRequestedHref=journals&contentSourceHref=journals/BCL/volumes/22/parts/4/articles/243/fulltext&hitListPageContext=http://legalonline.thomson.com.au/jour/resultSummary.jsp?limit=20___showDropDown=true___asicDropDown=0___articleCitation=%282006%29%2022%20BCL%20243___product=BCL_BS%3A%3A%3ABCL&searchId=0&hit=1&hits=1&articleType=fulltext&freeText=&articleCitation=%282006%29%2022%20BCL%20243&product=BCL_BS%3A%3A%3ABCL&titleCode=Toi
  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    6/21

    www.bakermckenzie.com/australia | 6

    5.2 Indeed, the explanatory note to the Amending Act states that one of its objectives was

    to provide for "a maximum limitation period of 10 years, for actions relating to building

    work and subdivision".5The rationale for this 10 year limitation period is also dealt with

    in the explanatory note:

    The imposition of a limitation period of 10 years for any persons liability for

    damage arising from defective building work or subdivision work is designedto

    address the law concerning latent defects in which th e current l imitat ion

    period begins to run only wh en the defect becomes apparent. The approachtaken in the proposed provisions is to limit the period within which proceedings can

    be commenced to the period of 10 years running from the date on which the

    relevant occupation certificate or subdivision certificate is issued or, in the case of

    subdivision work that is carried out after a subdivision certificate is issued, from the

    date on which a compliance certificate is issued with respect to the completion of

    that work. The new rule will not extend any period of limitation under the Limitation

    Act 1969, so that the period during which proceedings may be brought may, under

    that Act, be shorter than the 10 years proposed. [Emphasis added].6

    5.3 Consistent with this, the Courts have interpreted section 109ZK as a 10 year long stop

    period. InOwners Strata Plan 56963 v Australand7(Australand) , McDougall J stated

    that "[t]he purpose of s 109ZK was to provide a 'drop dead' date after which actions

    might not be brought if they fell within the definition of 'building action' All that s

    109ZK(1) did was impose a time limit for the enforcement of those rights".8Similarly, in

    TheOwners Corporation of Strata Plan 61390 v Multiplex Corporate Agency Pty Ltd

    (No 1),9the Court held that "[s]ection 109ZK relevantly provides that a building action

    may not be brought in relation to any building work more than 10 years after the date

    on which the relevant final occupation certificate was issued".10Thus, it has been

    rather uncontroversial that section 109ZK imposes a 10 year long stop period for

    bringing building actions.

    5Explanatory Note accompanying the Environmental Planning and Assessment Amendment Bill 1997 at p. 2.

    6Explanatory Note at p. 11.

    7[2011] NSWSC 710.

    8[2011] NSWSC 710 at [18].

    9[2012] NSWSC 298.

    10[2012] NSWSC 298 at [3] (Pembroke J).

    http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?freeText=109ZK___caseUpdates=0___limit=20___showDropDown=true___asicDropDown=0___legislationConsidered=%22environmental%20planning%20and%20assessment%20act%22___product=abstract&freeText=109ZK&caseUpdates=0&limit=20&showDropDown=true&asicDropDown=0&legislationConsidered=%22environmental%20planning%20and%20assessment%20act%22&product=abstract&hits=1&hit=1&contentSourceHref=cases/ujs/court/NSWSC/year/2011/number/710http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?freeText=109ZK___caseUpdates=0___limit=20___showDropDown=true___asicDropDown=0___legislationConsidered=%22environmental%20planning%20and%20assessment%20act%22___product=abstract&freeText=109ZK&caseUpdates=0&limit=20&showDropDown=true&asicDropDown=0&legislationConsidered=%22environmental%20planning%20and%20assessment%20act%22&product=abstract&hits=1&hit=1&contentSourceHref=cases/ujs/court/NSWSC/year/2011/number/710http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?freeText=109ZK___caseUpdates=0___limit=20___showDropDown=true___asicDropDown=0___legislationConsidered=%22environmental%20planning%20and%20assessment%20act%22___product=abstract&freeText=109ZK&caseUpdates=0&limit=20&showDropDown=true&asicDropDown=0&legislationConsidered=%22environmental%20planning%20and%20assessment%20act%22&product=abstract&hits=1&hit=1&contentSourceHref=cases/ujs/court/NSWSC/year/2011/number/710http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?caseUpdates=0___limit=20___showDropDown=true___caseName=Owners%20Corporation%20of%20Strata%20Plan%2061390%20v%20Multiplex%20Corporate%20Agency%20Pty%20Ltd%20(No%201)___asicDropDown=0___product=abstract&caseUpdates=0&limit=20&showDropDown=true&caseName=Owners%20Corporation%20of%20Strata%20Plan%2061390%20v%20Multiplex%20Corporate%20Agency%20Pty%20Ltd%20(No%201)&asicDropDown=0&product=abstract&hits=1&hit=1&contentSourceHref=cases/ujs/court/NSWSC/year/2012/number/298http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?caseUpdates=0___limit=20___showDropDown=true___caseName=Owners%20Corporation%20of%20Strata%20Plan%2061390%20v%20Multiplex%20Corporate%20Agency%20Pty%20Ltd%20(No%201)___asicDropDown=0___product=abstract&caseUpdates=0&limit=20&showDropDown=true&caseName=Owners%20Corporation%20of%20Strata%20Plan%2061390%20v%20Multiplex%20Corporate%20Agency%20Pty%20Ltd%20(No%201)&asicDropDown=0&product=abstract&hits=1&hit=1&contentSourceHref=cases/ujs/court/NSWSC/year/2012/number/298http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?caseUpdates=0___limit=20___showDropDown=true___caseName=Owners%20Corporation%20of%20Strata%20Plan%2061390%20v%20Multiplex%20Corporate%20Agency%20Pty%20Ltd%20(No%201)___asicDropDown=0___product=abstract&caseUpdates=0&limit=20&showDropDown=true&caseName=Owners%20Corporation%20of%20Strata%20Plan%2061390%20v%20Multiplex%20Corporate%20Agency%20Pty%20Ltd%20(No%201)&asicDropDown=0&product=abstract&hits=1&hit=1&contentSourceHref=cases/ujs/court/NSWSC/year/2012/number/298http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?caseUpdates=0___limit=20___showDropDown=true___caseName=Owners%20Corporation%20of%20Strata%20Plan%2061390%20v%20Multiplex%20Corporate%20Agency%20Pty%20Ltd%20(No%201)___asicDropDown=0___product=abstract&caseUpdates=0&limit=20&showDropDown=true&caseName=Owners%20Corporation%20of%20Strata%20Plan%2061390%20v%20Multiplex%20Corporate%20Agency%20Pty%20Ltd%20(No%201)&asicDropDown=0&product=abstract&hits=1&hit=1&contentSourceHref=cases/ujs/court/NSWSC/year/2012/number/298http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?freeText=109ZK___caseUpdates=0___limit=20___showDropDown=true___asicDropDown=0___legislationConsidered=%22environmental%20planning%20and%20assessment%20act%22___product=abstract&freeText=109ZK&caseUpdates=0&limit=20&showDropDown=true&asicDropDown=0&legislationConsidered=%22environmental%20planning%20and%20assessment%20act%22&product=abstract&hits=1&hit=1&contentSourceHref=cases/ujs/court/NSWSC/year/2011/number/710
  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    7/21

    www.bakermckenzie.com/australia | 7

    5.4 It is relevant to note that in all jurisdictions other than Queensland and Western

    Australia, there are equivalent 10 year limitation periods for actions for damages

    arising from building work. Notably, the definition of "building work" varies across

    jurisdictions. Some jurisdictions have confined the definition to the more "physical"

    aspects, while other jurisdictions have adopted a broader definition similar to that in

    NSW.11A table summarising these differences is provided below:

    Table of 'long stop' provisions across Australian jurisdictions

    Equivalentprovision 10 years runs from: "building work"includes design?

    NSW Section 109ZKEnvironmentalPlanning andAssessment Act1979

    See below table Yes

    See below table

    ACT Section 142Building Act 2004

    date certificate of completion given, orif no certificate, date of last inspectionon completion, or if no inspection, dateof first occupation);

    No

    See section 6

    NT Sections 159, 160Building Act 1993

    date of issue of occupancy permit inrespect of the work, or if an occupancypermit is not issued, on the date offirst occupation of the building aftercompletion of the work

    Possible

    "building work"means work for or inconnection with theconstruction,demolition orremoval of a buildingor plumbing ordrainage services

    Seesection 4

    SA Section 73Development Act1993

    date of completion of the building work No

    Seesection 4

    TAS Sections 255, 266Building Act 2000

    date certificate of occupancy issued,or if no certificate, date of firstoccupation, or if not occupied, twoyears after issue of building permit

    Possible

    "building work"means work relatingto - erecting, re-

    11

    See e.g. section 4 of the EPA Act (NSW): "building work" includes the design, inspection and issuing of a Part 4A certificate or

    complying development certificate in respect of building work.; section 3 Building Act 2000 (Tas): "building work" means "(a)

    erecting, re-erecting, constructing, altering, repairing, underpinning, demolishing or removing a building; or (b) adding to a

    building; or (c) excavating or filling incidental to an activity referred to in paragraph (a) or (b); or (d) any other prescribedwork"; cf. section 129 Building Act 1993 (Vic): "building work includes the design, inspection and issuing of a permit in respect

    of building work".

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    8/21

    www.bakermckenzie.com/australia | 8

    Equivalentprovision

    10 years runs from: "building work"includes design?

    erecting,constructing, altering,repairing,underpinning,demolishing orremoving a buildingor adding to abuilding orexcavating or filling

    incidental to anactivity referred toabove

    See section 3

    VIC Section 134Building Act 1993

    date of issue of occupancy permit, or ifpermit not issued, date of issue ofcertificate of final inspection

    Yes

    See section 129

    QLD Not applicable

    WA Not applicable

    5.5 Section 109ZK appears in Division 2 of Part 4C entitled "Liability" and provides:

    (1) Despite any Act o r law to the contr ary, abui lding act ionmay not be brought in

    relation to any bui ld ing work:

    (a) more than 10 years after the date on which the relevant final occupation

    certificate is issued, or

    (b) in a case where no final occupation certificate is issued, more than 10 years

    after:

    (i) the last date on which the building work was inspected by a certifying

    authority, or

    (ii) if no such inspection has been conducted, the date on which that part of

    the building in relation to which the building work was carried out is first

    occupied or used.

    5.6 Section 109ZI provides the relevant definitions:

    In this Part:

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    9/21

    www.bakermckenzie.com/australia | 9

    "bui ld ing act ion" means an action (including a counter-claim) for loss or damage

    arising out of or concerning defect ive bui lding wo rk.

    "bui ld ing work"includesthe design, inspection and issuing of a Part 4A

    certificate or complying development certificate in respect of building work.

    [Emphasis added].

    5.7 This should be read together with section 4 of the EPA Act dealing with definitions of

    the EPA Act generally:

    "bui ld ing work" means any physical activity involved in the erection of a building.

    "bui ld ing" includes part of a building, and also includes any structure or part of a

    structure (including any temporary structure or part of a temporary structure), but

    does not include a manufactured home, moveable dwelling or associated structure

    or part of a manufactured home, moveable dwelling or associated structure.

    6. Actions for damages arising from defective design

    6.1 Generally, a proprietor who suffers loss as a result of defective design may recover

    damages from the designer for breach of contract or negligence.12Under the EPA Act,

    the 10 year limitation period is applicable only to actions relating to "building work" and

    section 109ZI expands the general definition of "building work" provided in section 4 of

    the EPA Act to explicitly include "design".13Therefore, an action claiming defective

    design is likely to fall within the ambit of section 109ZK.

    6.2 Indeed, inAustraland, the NSW Supreme Court held that section 109ZK did apply to

    an action arising out of defective design. The Court inAustraland dealt with a

    negligence claim in respect of the waterproofing of a roof:

    The question is therefore whether this is a building action. On and from

    1 July 1998, the combined effect of the definition of buildingwork in s 4(1) of the

    EPA Act and the definition of building work in s 109ZI is, I think, that bui ld ing

    wo rk means any physical act iv i ty involved in the erect ion of a bui lding and

    12Voli v Inglewood Shire Council(1963) 110 CLR 74; Halsbury's Laws of Australia, Building and Construction,"Breach of

    Contract by Designer or Consultant" at [65-2140].13

    Lym International Pty Ltd v Marcolongo[2011] NSWCA 303at [18] (Campbell JA): "[b]ecause the definition of "building work" ins 109ZI was an inclusive one, it had the effect of expanding, for the purposes of Part 4C, the definition contained in s 4 EPA

    Act".

    http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?caseUpdates=0___limit=20___showDropDown=true___caseName=Lym%20International%20Pty%20Ltd%20v%20Marcolongo___asicDropDown=0___product=abstract&caseUpdates=0&limit=20&showDropDown=true&caseName=Lym%20International%20Pty%20Ltd%20v%20Marcolongo&asicDropDown=0&product=abstract&hits=2&hit=1&contentSourceHref=cases/ujs/court/NSWCA/year/2011/number/303http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?caseUpdates=0___limit=20___showDropDown=true___caseName=Lym%20International%20Pty%20Ltd%20v%20Marcolongo___asicDropDown=0___product=abstract&caseUpdates=0&limit=20&showDropDown=true&caseName=Lym%20International%20Pty%20Ltd%20v%20Marcolongo&asicDropDown=0&product=abstract&hits=2&hit=1&contentSourceHref=cases/ujs/court/NSWCA/year/2011/number/303http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?caseUpdates=0___limit=20___showDropDown=true___caseName=Lym%20International%20Pty%20Ltd%20v%20Marcolongo___asicDropDown=0___product=abstract&caseUpdates=0&limit=20&showDropDown=true&caseName=Lym%20International%20Pty%20Ltd%20v%20Marcolongo&asicDropDown=0&product=abstract&hits=2&hit=1&contentSourceHref=cases/ujs/court/NSWCA/year/2011/number/303http://legalonline.thomson.com.au/cases/resultDetailed.jsp?curRequestedHref=cases&hitListPageContext=http://legalonline.thomson.com.au/cases/resultSummary.jsp?caseUpdates=0___limit=20___showDropDown=true___caseName=Lym%20International%20Pty%20Ltd%20v%20Marcolongo___asicDropDown=0___product=abstract&caseUpdates=0&limit=20&showDropDown=true&caseName=Lym%20International%20Pty%20Ltd%20v%20Marcolongo&asicDropDown=0&product=abstract&hits=2&hit=1&contentSourceHref=cases/ujs/court/NSWCA/year/2011/number/303
  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    10/21

    www.bakermckenzie.com/australia | 10

    includ es the design of that bui ld ing, and the other matters referred to in t he

    extended defini t ion in s 109ZI. That is to say, it includes the design in

    respect of bui ld ing work" .

    It seems to me to follow that the subject matter of the claim against Australand, at

    least insofar as it relates to the design and construction of the building, is building

    work. As to construction: it is obviously enough physical activity involved in the

    erection of the building. It is thus within the definition in s 4(1) of the EPA Act.

    As to design: i t is within the extended defini t ion of bui ldin g wor k in s 109ZI,

    being design in respect of the bui lding wo rk that was subsequently carried

    out .[Emphasis added].14

    7. Actions for damages arising from breach of "design life" warranties

    7.1 An example of a contractual design life warranty is as follows:

    "The minimum design life of the Tunnel shall be:-

    (i) for the structure, 100 years;

    (ii) for major mechanical & electrical items, pavement (except as noted

    below) and tunnel finishes, 20 years;

    (iii) road surface, 10 years

    All renewable items will be required to have a reasonable life at the time of expiry

    of the Lease. A schedule of such items, with life at handover, is to be agreed with

    the owner."

    7.2 It is not clear from the explanatory note or drafting history of the provisions detailed in

    Section5 above whether the legislature had in mind how section 109ZK would affect

    "design life" or "fitness for purpose" warranties in building contracts. If actions arising

    from breach of "design life" warranties were captured by section 109ZK, it would render

    "design life" warranties effectively meaningless to the extent that they provide

    warranties for a period greater than 10 years from the date a final occupation certificate

    is issued, such as in the example clause given in7.1 above. Rather, they would simply

    be providing an unenforceable right. To date, there does not appear to be any case law

    on this specific point.

    14Australandat [16]-[17] (McDougall J).

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    11/21

    www.bakermckenzie.com/australia | 11

    7.3 However, guidance can be drawn from a South Australian case dealing with a breach

    of contractual warranty as to approvals and consents. In Huepauff & Ors v Inter-

    Continental Travels P/L No. SCCIV-01-70,15the Supreme Court of South Australia

    rejected the application of the 10 year limitation period to an action for breach of

    contractual warranty. In Huepauff, the Plaintiff had purchased a house from the

    Defendants. Following the discovery of defective plumbing work, the Plaintiff sued for

    damages based on an alleged breach of warranty in the contract for sale. The relevant

    warranty stated:

    "The Vendor warrants that to the Vendor's knowledge, no building work has been

    carried out on the Land without all necessary consents and approvals having been

    obtained, except as set out in Item R of the Schedule".

    Item R of the Schedule stated "nil".

    7.4 At first instance, the Magistrate found in favour of the Plaintiff. On appeal, the

    Defendants claimed that the action was statute barred by the operation of section 73

    Development Act 1993 (SA) (the South Australian equivalent of section 109ZK). The

    question for the Court was whether section 73 Development Act 1993 (SA) applied to a

    claim for damages resulting from a breach of contractual warranty as to approvals:

    [quoting Perry J on this issue from earlier proceedings] "If a warranty had been

    given which expressly referred to the soundness of a building, in my opinion the

    section is hardly likely to apply so as to put a plaintiff out of court, even if the

    alleged breach of warranty is as a result of defective building work which had been

    completed more than ten years before the action was brought.

    To give the sect ion such a con struct io n wou ld result in quite bizarre

    consequences. It would mean on Mr Manetta's argument that if an express

    warranty was given as to the soundness of a building as part of a contract of sale,

    the warranty could not be relied upon as a basis for the award of damages, if the

    unsoundness was as a result of building work which was more than ten years old.

    In my opinio n, mu ch clearer word s in the sect ion wo uld be necessary before

    i t could h ave such a strange result."

    15[2001] SASC 119.

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    12/21

    www.bakermckenzie.com/australia | 12

    I agree. I also agree that s 73 operates to bar the remedy, but not the right.

    Section 73 has no application to a claim for damages resulting from a breach of a

    contractual warranty as to approvals and consents or for damages for

    misrepresentation as to approvals and consents." [Emphasis added]16

    Accordingly, the Court held the action was not statute barred and the appeal was

    dismissed.

    7.5 Although Hueppauffdeals with a warranty as to consents and approvals and in the

    context of a contract for the sale of land rather than building and construction, similar

    arguments by analogy could be made for NSW. The reasoning in Hueppauff draws

    attention to a possible distinction which could be raised in NSW to bring an action

    outside the scope of section 109ZK. Arguably, an action for damages arising from a

    breach of warranty of design life or fitness for purpose could be distinguished from an

    action for damages for "defective design". By characterising the claim as one for

    "breach of warranty" rather than "defective design", the claim would not be caught by

    the definition of "building action" and thus fall outside the scope of section 109ZK. Yet,

    depending on the facts of the situation, it could be that there would actually be no

    substantive difference in a claim for damage arising out of a "breach of warranty" as

    opposed to "defective design" and a Court may reject such a superficial delineation.

    7.6 The argument would be that the contractor has contractually promised, on a continual

    or repeating basis, that the warranted works will remain fit for their intended purpose

    for a period of, say, 100 years and that breach of that promise occurs only when there

    is knowledge of a failure of such structures to survive for the contracted design life, as

    distinct from when the (inadequate) design is prepared. The argument would then bethat having provided the contractual promise of a 100 year life, it would be unlawful for

    legislation to override the contractual promise by restricting the promisees right to rely

    on that contractual promise to 6 / 12 years from the time of design as this would

    effectively mean that all such contractual design life provisions are not worth the

    paper on which they are written.

    7.7 Any argument that upon completion of the works the contractor handed over control for

    the protection, use and maintenance of the works would be countered by alleging that

    16Hueppauff & Ors v Inter-Continental Travels P/L No. SCCIV-01-70[2001] SASC 119 per Martin J at 37.

    http://www.austlii.edu.au/cgi-bin/sinodisp/au/cases/sa/SASC/2001/119.html?stem=0&synonyms=0&query=title(Hueppauffhttp://www.austlii.edu.au/cgi-bin/sinodisp/au/cases/sa/SASC/2001/119.html?stem=0&synonyms=0&query=title(Hueppauffhttp://www.austlii.edu.au/cgi-bin/sinodisp/au/cases/sa/SASC/2001/119.html?stem=0&synonyms=0&query=title(Hueppauffhttp://www.austlii.edu.au/cgi-bin/sinodisp/au/cases/sa/SASC/2001/119.html?stem=0&synonyms=0&query=title(Hueppauff
  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    13/21

    www.bakermckenzie.com/australia | 13

    there would be a reduction or extinguishment of the design life promise only where the

    failure of the works to survive is due to an external event (or the plaintiff's own actions)

    as opposed to inherent failure.

    7.8 In the context of a breach of warranty, to ascertain when the limitation period begins to

    run, it is necessary to consider whether the warranty gives rise to a continuing

    obligation. The distinction between two types of contractual promises was discussed by

    Dixon J in Larking v Great Western (Nepean) Gravel Ltd (1940) 64 CLR 221, 236-8.

    Dixon J observed:

    If a covenantor undertakes that he will do a definite act and omits to do it within the

    time allowed for the purpose, he has broken his covenant finally and his continued

    failure to do the act is nothing but a failure to remedy his past breach and not the

    commission of any further breach of his covenant. His duty is not considered as

    persisting and, so to speak, being forever renewed until he actually does that

    which he promised. On the other hand if his covenant is to maintain a state or

    condition of affairs, as, for instance maintaining a building in repair, then a

    further breach arises in every successive moment of time during which the state or

    condition is not as promised If the covenant names a time for the doing or

    completion of a definite act, it is clear that failure to do the act within the time

    involves a breach once and for all the same conclusion will follow where no time

    is limited but a specified thing is to be done and a reasonable time elapses for the

    performance of the covenant.

    7.9 This distinction is relevant when considering the types of warranties which are often

    provided. For example, in Swan Pools Ltd v Baker (1980) 25 SASR 103, the defendant

    agreed to supply and install a fibre glass swimming pool for the plaintiff and warranted

    that it would rectify and make good any defect caused by faulty workmanship or

    materials, which should appear in the fibre glass tank within three years of the

    commencement of filtration. The pool was installed in late 1971, and defects were first

    notified to the defendant by the plaintiff in 1972. Proceedings against the defendant

    were brought in August 1978. The defendant claimed that the breach of warranty

    occurred on the date of delivery of the defective tank in 1971, and therefore the claim

    was statute-barred. The Court rejected this argument, holding that the obligation was of

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    14/21

    www.bakermckenzie.com/australia | 14

    the latter kind as described by Dixon J in Larking (Mitchell J, at 108). Mitchell J

    (Walters J agreeing), held that the breach of warranty occurred when the reasonable

    time [to rectify the damage] expired (Mitchell J, at 108). Cox J held that it is implicit in

    the warranty that the [defendant] would not be in breach of it, in the event of any such

    defect occurring, before it had been notified of the defect and a reasonable time for

    doing the repairs had elapsed (at 110). On the facts, the majority held that the

    reasonable time to rectify the defects elapsed at the beginning of 1978, and so that

    was the relevant date from which the limitation period would begin to run (at 108).

    Cox J held that the reasonable time for rectification elapsed in September 1972,

    though even on this earlier date, the action was still brought within time (at 111).

    7.10 To contrast, where a warranty is given simply that a product will be free from defects

    for a stated period of time, and defective goods have been supplied, it appears that the

    warranty does not impose a continuing obligation for the period of warranty (see

    VAI Industries (UK) Ltd v Bostock & Bramley [2003] EWCA Civ 1069; Tranquility Pools

    v Huntsman Chemical Co Australia Pty Ltd [2011] NSWSC 75). Rather, where

    defective goods are supplied, the date of breach is taken to occur on the date ofsupply, and that is the relevant date of accrual for the purposes of the limitation period.

    8. VAI Indu str ies (UK) Ltd v B ostoc k & B ramley [2003]EWCA Civ 1069

    8.1 In the English case, VAI Industries (UK) Ltd v Bostock & Bramley [2003] EWCA Civ

    1069, the plaintiff entered into an agreement for the supply of equipment from the

    defendant. The contract provided a warranty that:-

    All equipment is to be warranted as free from defects in Design Materials andWorkmanship and must conform to the specification and drawings.

    The warranty period is for no longer than 24 months from F.O.B provided that

    delay in equipment acceptance is not attributable to equipment of your supply.

    8.2 On the facts, the delivery FOB took place on 28 July 1995, and accordingly, the

    24 month warranty period expired on 28 July 1997 ([7]). On 31 August 1998, the

    equipment failed as a result of a defect. Proceedings were brought on

    1 February 2002. The defendant pleaded that the allegation of breach relating to defect

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    15/21

    www.bakermckenzie.com/australia | 15

    in design occurred on the date of delivery, 28 July 1995, and hence the limitation

    period expired on 27 July 2001 (s 5 Limitation Act 1980 (UK) providing a 6 year

    limitation period for action in simple contract), and the plaintiffs action was statute

    barred. The trial Judge held in favour of the defendant.

    8.3 On appeal, the plaintiff submitted that the warranty imposed on the defendant a

    continuous obligation to have the equipment free from defect throughout every day of

    the twenty-four month period, so that the failure to do so was a breach which occurred

    on each day, including the last day. Thus, time should run from the date of the lastbreach, that is, 28 July 1997, allowing the plaintiff to bring a claim within 6 years of that

    date, expiring 27 July 2003. The majority of the Court of Appeal rejected the plaintiffs

    submission.

    8.4 Carnwath LJ considered the warranty did not provide an ongoing obligation that the

    equipment would be free from defects, but rather placed a limitation on the extent of

    the suppliers obligation. [49]

    8.5 Carnwarth LJ stated:

    a clause of this kind is generally to be interpreted as giving rise to a single breach

    at the time of delivery, even though the obligation at that point is to ensure that the

    goods are in a condition which will remain fit for the purpose for a reasonable time

    thereafter I believe that clearer words would be needed, certainly in a form of

    contract provided by the purchaser, to create a continuing obligation such as relied

    on the appellant. ([51])

    8.6 Similarly, Newman J held that the warranty amounted to a promise that at the date ofdelivery the equipment would be free from defects and would conform to the

    specifications, and that it was not a promise that went to the future performance of the

    equipment but to its condition and state at the date of delivery.

    8.7 Ward LJ, dissenting, considered that the words of the warranty were those of a

    promissory warranty that each day for up to 24 months the equipment would be free

    from defects in design and in conformity with the specification ([48]). Ward LJ found

    that:

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    16/21

    www.bakermckenzie.com/australia | 16

    If the warranty continues for two years it seems to me inevitable that it is a promise

    that for each day of the two year period the equipment will be free from defect. For

    every day it continues to have a defect there is a breach ([35])

    and thus concluded that the claimants could rely on a breach of warranty up to

    27 July 1997, and the claim would not be statute barred.

    8.8 In reaching the above conclusion, Ward LJ determined that there were three possible

    interpretations of the warranty in this case:

    1. as concluded above, that the warranty is a promissory warranty that each day the

    equipment would be free from defects in design and be in conformation with the

    specification;

    2. that, as argued by the defence, the equipment is warranted free from defects in

    design and in conformation with the specification at the time of delivery and that

    the reasonable period during which the equipment would remain so was the

    period of "up to 24 months"; or

    3. that the stated time period of 24 months was the period in which the parties had

    contractually agreed the purchaser of the equipment was required to make its

    claim under the warranty.

    8.9 Carnworth LJ, with whom Newman J concurred, held that the words "The warranty

    period is for no longer than 24 months" could not "change the nature of the warranty,

    nor in particular extend the obligations imposed on the supplier. In context, as I read

    it, it is intended to place a limitation on the extent of the supplier's obligations." [49]

    8.10 Such a conclusion may seem possible in light of the warranty considered in this case

    (24 months, clearly less than the statutory limit on a claim for breach of contract) but it

    would not seem logical had the warranty under consideration have been a 100 year

    design life. Could the Court have held that 100 years "place[d] a limitation on the extent

    of the supplier's obligations"? It seems that the opposite is the only possible

    interpretation and that the parties' agreement is not an attempt to fix the period of time

    within which a claim can be made but rather an agreement of the type at 1 above.

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    17/21

    www.bakermckenzie.com/australia | 17

    9. Tranqui l i ty Pools & Spas Pty Ltd v Hun tsman Chemic al Co Au stral ia Pty Ltd[2011]NSWSC 75

    9.1 VAI Industrieswas considered by the NSW Supreme Court in Tranquility Pools & Spas

    Pty Ltd v Huntsman Chemical Co Australia Pty Ltd [2011] NSWSC 75. There,

    Einstein J agreed with the majority in VAI Industries.

    9.2 The plaintiffs manufactured pools using a product supplied by the defendant and then

    sold those pools to customers. The plaintiffs claimed that the defendants product was

    defective which resulted in blistering and black spots in the pools. The plaintiffs brought

    an action for breach of contract on the basis the product was not of merchantable

    quality and was in contravention of ss 52 and 53 Trade Practices Act. It should be

    noted that the issue of limitation periods was raised, not as a defence by the

    defendant, but being relevant to assess damages and the extent of the plaintiffs

    liability to its customers as a result of the fault of the defendant.

    9.3 The plaintiffs had provided customers with warranties that:-

    the pool shell had been fabricated to the highest standards of manufacture andraw materials; and

    the pool shell was to be free from defects caused by workmanship or raw

    materials used in the fabrication process for ten years from the date the pool

    shell is first filled with water. [467]

    9.4 The plaintiffs claimed that pool owners would have a 16 year maximum claims period.

    The plaintiffs relied on reasoning similar to Ward LJs reasoning in VAI Industries. The

    plaintiffs claimed that the warranty constituted a promise that pools would be free from

    defects for the whole of the 10 years, and that if a breach of that warranty manifested

    on the last day in the tenth year, the normal 6 year limitation period would begin to run

    from that date, thus producing a 16 year maximum claims period ([579], [586]).

    9.5 Einstein J rejected this submission, and held:

    [588] In my view, the proper interpretation is that if a pool was supplied with a

    latent defect, such that it would eventually develop osmosis, the express warranty

    would be breached upon supply, since the shell would not be free of defectscaused by workmanship and/or raw materials. That is at the time of delivery the

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    18/21

    www.bakermckenzie.com/australia | 18

    customers cause of action for breach of the express warranty would have

    accrued. In my view, the words for 10 years when the Shell is first filled with

    water, define the period in which a claim for breach of the express warranty,

    based on the fact that defects had become manifest, could be made against

    Tranquility.

    9.6 These cases illustrate how the wording and nature of a warranty will dictate when a

    breach is taken to have occurred, and accordingly, the date of accrual for the purposes

    of the limitation period. Generally, where there is a warranty to rectify a defect, so longas the defect has been notified within the warranty period, then the date of breach will

    occur upon the expiration of the reasonable time to rectify the defect. Therefore,

    depending on the facts and the reasonable time to rectify a defect, the expiry of the

    limitation period may be well outside the warranty period, as seen in Swan Pools.

    10. Summary

    10.1 The principle remains that the date of accrual for a cause of action in contract is the

    date of breach. The date of breach does very much depend on the nature of thewarranty provided and the factual scenario. The results in both VAI Industriesand

    Tranquility Pools, that the date of supply was considered the date of breach of

    warranty, turn particularly on the facts and the wording of the warranties given. Notably

    in those cases, the equipment was defective from the very start.

    10.2 On the face of it, these cases do seem to create a strange situation, where a claim for

    a breach of warranty that equipment will be free of defects for a particular period of

    time (say 15 years) can only be brought within the first 6 years, and so where a defect

    manifests afterthe sixth year, a claimant will be statute barred, despite having paid for

    a longer period of warranty. Applying this reasoning, warranty periods for longer than 6

    years would be meaningless and a waste of money if a premium had been paid for the

    longer warranty period. Such a scenario was not raised before the courts in either VAI

    Industries or Tranquility Pools. However, the dissenting judgment of Ward LJ in VAI

    Industriesmakes a very persuasive argument in favour of such warranties being read

    as a continuing promise to have the equipment free from defect for every day of the

    warranty period; and that there is a breach of that warranty every day the equipment is

    defective. This reading would resolve the strange consequence noted above.

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    19/21

    www.bakermckenzie.com/australia | 19

    10.3 Moreover, there is little case law on this particular issue, as the majority of cases have

    been brought as actions in tort or under the Trade Practices Act (now theAustralian

    Consumer Law). Given that Tranquility Poolsdid not deal with the limitation issue as a

    defence, but as a subsidiary issue on the liability of the Plaintiff to its customers, and

    there is a strong dissenting judgment in VAI Industries, it may be likely that if such a

    question was brought before a Court today, it would be decided along the lines of

    Ward LJs judgment. Thus, it would be not be advisable to proceed on the basis that a

    warranty against defects would only be enforceable for the first 6 years of the warranty

    period.

  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    20/21

    www.bakermckenzie.com/australia | 20

    For further information

    Geoff WoodPartner

    Baker & McKenzie

    Level 27, AMP Centre

    50 Bridge Street

    Sydney NSW 2000

    Tel: +61 2 8922 5123

    Fax: +61 2 9225 7595

    [email protected]

    Fiona ElliotSenior Associate

    Baker & McKenzie

    Level 27, AMP Centre

    50 Bridge Street

    Sydney NSW 2000

    Tel: + 61 2 8922 5156

    Fax: +61 2 9225 7595

    [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]://www.bakermckenzie.com/FionaElliot/http://www.bakermckenzie.com/GeoffWood/mailto:[email protected]:[email protected]
  • 7/25/2019 Defects Liability Period - BK_Australia_s_Mar14

    21/21

    www.bakermckenzie.com/australia

    Baker & McKenzie has been global since ourinception. It is part of our DNA.

    Our difference is the way we think, work and behavewe combine an

    instinctively global perspective with a genuinely multicultural approach, enabledby collaborative relationships and yielding practical, innovative advice. With morethan 4,000 lawyers in 47 countries, we have a deep understanding of the cultureof business the world over and are able to bring the talent and experience neededto navigate complexity across practices and borders with ease.

    Baker & McKenzie, an Australian Partnership, is a member firm of Baker & McKenzie International, a Swiss Verein with member law firms around the world.

    In accordance with the common terminology used in professional service organisations, reference to a "partner" means a person who is a partner, or

    equivalent, in such a law firm. Similarly, reference to an "office" means an office of any such law firm.

    Baker & McKenzieABN 32 266 778 912

    AMP CentreLevel 2750 Bridge Street

    Sydney NSW 2000Australia

    P.O. Box R126Royal Exchange NSW 1223Australia

    Tel: +61 2 9225 0200Fax: +61 2 9225 1595DX: 218 SYDNEY

    www.bakermckenzie.com