dead run stream restoration segment 2 – 3
TRANSCRIPT
A Fairfax County, VA, publication
Department of Public Works and Environmental ServicesWorking for You!
Dead Run Segment 2/3 Stream RestorationMcLean Central Park and Dead Run Stream Valley Park
December 7, 2017
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Community Meeting: Pardon our Dust
• Project Background
– Background
– Major Project Elements
• Construction Timeline Summary
• Project Schedule/Phasing, Site Access, Construction Equipment
• Example photos from Dead Run Segment 1 project – (designed by Stantec and constructed by Meadville Land Services, Inc.)
• Safety During Construction
• Q&A
2
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Project Background
• Fall 2013: Project initiated
• Winter 2013: Surveys and assessment completed
• April 2014: Pre-concepts submitted
• April 23, 2014: First public meeting
• April 2014 – March 2016: Stakeholder/community coordination and design refinement
• April 2016: Revised final concept design completed
• November 2, 2016: Final community task force meeting
• September 2017: Final design completed
• October 2017: Advertised for bid to six pre-qualified contractors
• November 21, 2017: Bid opening
4
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Items of Work
Restoration of approximately 2,800 linear feet of the section of Dead Run that flows through McLean Central Park, Dead Run Stream Valley Park, and adjacent private properties and its tributaries using Natural Channel Design techniques
Restoration of tributary near the tennis courts to stabilize large, unsafe headcut
Replace one pedestrian trail bridge over the tributary which parallels Churchill Drive
Control invasive plants and replant the riparian corridor in excess of Chesapeake Bay Preservation Ordinance requirements
5
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration
Restoration Renderings
7
Online Story Maps with Photographs - Virtual Stream Walk: • Existing conditions map link: (please cut and paste or type these links into your
browser) http://fairfaxcountygis.maps.arcgis.com/apps/MapTour/index.html?appid=c1cada0ba98c4434bfcfab759301602f#
• Proposed renderings map link: http://fairfaxcountygis.maps.arcgis.com/apps/MapTour/index.html?appid=077a029f66b849afae46189ee6da1916#
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration
Restoration Renderings
8
Existing Conditions: Recent tree fall above pedestrian bridge in Segment 2
Dead Run Segment 2/3 Stream Restoration
12
Pedestrian Bridge Replacement
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration
14
Replanting the Riparian Corridor
Stormwater Planning Division
Stormwater Planning Division
Dead Run Segment 2/3 Stream Restoration
Planting Outside Project Limits
15
Total 2/3 of an acre outside of LOD being planted
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Summary of Construction Timeline
• Notice to proceed expected to be issued to Meadville Land Services, Inc. in February 2018
• Project duration: 410 calendar days (<14 months)
• Special project phasing (next slide)
• 2 year 85% care and replacement warranty on all trees and shrubs effective from date of plant installation
16
https://www.meadvillelandservice.com/
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Phasing Requirements
• Project is broken into 3 sections with the intent of limiting overall disturbance at any given time
• Contractor may only begin work in a section (including vegetation clearing and access road setup) upon approval from the County
• Approval to begin a new section will be based on a dedicated construction crew being assigned to complete that section
• Trail management plan required to be submitted by the contractor and approved by the County prior to any work
17
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Proposed Schedule
• Example construction schedule above
• Contractor will submit final schedule for approval– Restoration section schedules can overlap with multiple crews
• Permit required stream restoration monitoring by County: 3 Years
• Vegetation Monitoring and Maintenance by County: 3 Years
18
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Notice to Proceed
Project Start Up and Site Preparation
Restoration Section 1
Restoration Section 2
Restoration Section 3
Site Restoration and Planting
Project Completion
Construction Warranty 12 Months
Vegetation Warranty 24 Months
MonthActivity Comments
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Construction – Meadville Land Service, Inc.
• Project Schedule:1. Install erosion and
sedimentation controls and tree protection measures
2. Clearing and grubbing3. Construct stream
restoration in segments from upstream to downstream
4. Stabilize each segment as it is completed
5. Final planting of trees and shrubs to occur during the planting window following construction completion
• Site Access• Construction Equipment
19
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Dead Run at Dominican Retreat (Segment 1) Timeline
• 1,940 linear feet of restoration with a contract duration of 365 days
• October 10, 2016: Notice to proceed issued
• October 10, 2016 – November, 2016: material submittals, contractor mobilization, erosion and sediment controls installation, access road installation, tree removal
• December 2016 – June 27, 2017: In stream work, site stabilization
• June 27, 2017: Substantial completion awarded to contractor (75 days ahead of schedule)
• July 2017: Demobilization and final site cleanup
• October, 2017: Tree and shrub installation during the fall planting window
20
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Dead Run Segment 1 Photos
21
Access road and tree protection area
Stockpile area
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Dead Run Segment 1 Photos
22
Track truckExcavator
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Dead Run Segment 1 Photos
Before
23
After Grading (before tree and shrub planting)
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Dead Run Segment 1 Photos
24
Before After
Dead Run Segment 2/3 Stream Restoration
Stormwater Planning Division
Dead Run Segment 1 Photos
Planting
25
Dead Run Segment 1 Stream Restoration
26
Safety During Construction
• Contractor is required to comply with Fairfax County’s Construction Safety Resolution.
• For all residents, keeping safe means following two simple rules:
1. Please stay outside the construction limits at all times!
2. Observe construction activities from a safe distance.
Stormwater Planning Division
Dead Run Segment 1 Stream Restoration
27
Contact information
Construction related issues:Utilities Design and Construction Division703-324-5111, TTY 711 or by email:Janet Grubb-Webber: [email protected]
Questions on design:
Stormwater Planning Division 703-324-5500, TTY 711 or by email: Joe Riley-Ryan: [email protected]
Project Web Site: https://www.fairfaxcounty.gov/dpwes/stormwater/#projects
Stormwater Planning Division