daily work plan

198
DAILY WORK PLAN section date 01.04.2015 02.04.2015 03.04.2015 section 4 : pesocani- trebenista from km 0+000 to 12+698.72 Public holiday.There is no activities today preparatory works for the camp in the village of Meseista preparatory works for the camp in the village of Meseista section 5: trebenista- podmolje-ohrid from km 0+000 do km 10+263.26 Public holiday.There is no activities today

Upload: dusko-blagica-cocoroski

Post on 12-Jan-2016

213 views

Category:

Documents


0 download

DESCRIPTION

Daily Work Plan

TRANSCRIPT

Page 1: Daily Work Plan

DAILY WORK PLAN

sectiondate

01.04.2015 02.04.2015 03.04.2015 04.04.2015

section 4 : pesocani-

trebenista from km 0+000 to 12+698.72

Public holiday.There is no activities today

preparatory works for the camp in the village of Meseista

preparatory works for the camp in the village of Meseista

preparatory works for the camp in the village of Meseista

section 5: trebenista-

podmolje-ohrid from km 0+000 do

km 10+263.26

Public holiday.There is no activities today

Page 2: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 29.04.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Reinforcing and formwork bracing on the I part of the laid joist of pillar S2 left. request for inspection

5 Earth works km 4+011 Excavation of the foundations of pillar S1.

6 Earth works Excavation with crushing of stone material.

7 Earth works km 5+094 Excavation of the foundations of pillar S1 and S5 right.

8 Concrete works km 5+094 requests for inspection

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Concrete works request for inspection

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+800~km 4+920

Formwork bracing on the II part pillar S3 left; Reinforcing, formwork bracing and concreting of the II campade of the foundation of pillar S2 left; Reinforcing the I part of pillar S5 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150 Reinforcing of the second height of ZV.2; Concreting of the foundation of ZXII.1.

Page 3: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 28.04.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Earth works km 5+094 Excavation of the foundations of pillar S1 and S5 right.

7 Concrete works km 5+094

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Blasting

Formwork removing of the parapet of wing K1' and wing K2' of abutment S4; Reinforcing of the laid joist of pillar S2 left; Formwork removing of the laid joist of pillar S3 right.

km 4+800~km 4+920

Formwork removing of the I part pillar S3 left; Reinforcing and formwork bracing on the II part pillar S3 left; Formwork removing of the I campade of the foundation of pillar S2 left; Reinforcing, formwork bracing on the II campade of the foundation of pillar S2 left; Digging in of the foundation of pillar S5 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700; Blasting

km 7+800~km 8+150Formwork removing of the first height of ZV.2; Reinforcing of the foundation of ZXII.1.

Page 4: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 27.04.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 requests for inspection

5 Earth works Excavation with crushing of stone material.

6 Earth works km 5+094 Excavation of the foundations of pillar S1 and S5.

7 Concrete works km 5+094 requests for inspection

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works requests for inspection

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Blasting

Formwork removing of the I and II camapde of pillar S1; Reinforcing and formwork bracing of the laid joist of pillar S2 right; Formwork removing of the laid joist of pillar S3 right.

km 4+800~km 4+920

Reinforcing and formwork bracing on the I part pillar S3 left; Reinforcing the first height of pillar S5 left; Reinforcing the first part of pillar S5 left; Reinforcing, formwork bracing and concreting of the I campade of the foundation of pillar S2 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150Formwork removing of the first height of ZV.2; Concrete fill-in for ZV.1; Reinforcing and formwork bracing on the foundation of ZXII.1.

Page 5: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 26.04.2015 Sunday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 requests for inspection

5 Earth works Excavation with crushing of stone material.

6 Earth works km 5+094 Excavation of the foundations of pillar S1 and S5.

7 Concrete works km 5+094 requests for inspection

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works requests for inspection

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Concrete fill-in for the foundation of S1 (II part); Reinforcing and formwork bracing of the first height of pillar S1; Reinforcing and formwork bracing of the laid joist of pillar S2 right; Concreting the laid joist of pillar S2 right (II part).

km 4+800~km 4+920

Formwork bracing on the I part pillar S3 left; Formwork removing of the II part of the foundation of pillar S5 left; Digging in of foundation of pillar S5 left; Reinforcing the first part of pillar S5 left; Reinforcing and formwork bracing on the I campade of the foundation of pillar S2 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150 Formwork bracing and concreting of the first height of ZV.2.

Page 6: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 25.04.2015 Saturday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 requests for inspection

5 Earth works Excavation with crushing of stone material.

6 Earth works km 5+094 Excavation of the foundations of pillar S1 and S2 left.

7 Concrete works km 5+094 requests for inspection

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works requests for inspection

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Concreting of the parapet of wing K1'; Concrete fill-in for the foundation of S1; Reinforcing and formwork bracing of the first height of pillar S1; Reinforcing and formwork bracing of the laid joist of pillar S2 right.

km 4+800~km 4+920

Formwork bracing on the I part pillar S3 left; Reinforcing and formwork bracing and concreting of the II part of the foundation of pillar S5 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150 Reinforcing and formwork bracing on the first height of ZV.2.

Page 7: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 24.04.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Earth works Excavation with crushing of stone material.

7 Earth works km 5+094 Excavation of the foundations of pillar S1 and S2 left.

8 Concrete works km 5+094

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works requests for inspection

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of K1' of abutment S4 (campade II and III, Part II); Reinforcing and formwork bracing on the parapet of wing K1'.

km 4+800~km 4+920

Formwork bracing on the I part pillar S3 left; Formwork removing of the I part of the foundation of pillar S5 left; Reinforcing and formwork bracing on the II part of the foundation of pillar S5 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150Formwork bracing and reinforcing the first height of ZV.2; Concreting with concrete fill-in of the foundation of Z XII.2; Concreting with concrete fill-in of the foundation of Z V.1;

Page 8: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 23.04.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Earth works Excavation with crushing of stone material.

7 Earth works km 5+094 Excavation of the foundations of pillar S1 and S2 left.

8 Concrete works km 5+094 request for inspection

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works request for inspection

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of the laid joist of pillar S3 right (I part); Concering of K1' of abutment S4 (campade II and III, Part II).

km 4+800~km 4+920

Reinforcing the I part pillar S3 left; Reinforcing,formwork bracing and concreting of the I part of the foundation of pillar S5 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150Formwork bracing of ZV.2 and Concretong with concrete fill-in of the foundation of Z XII.1

Page 9: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 22.04.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request for inspection

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Preparatory works km 4+011 Preparation of a climbing platform for pillar S2 left.

7 Earth works Excavation with crushing of stone material.

8 Earth works km 5+094 Excavation of the foundations of pillar S1 and S2.

9 Concrete works km 5+094

10 Earth works

11 Preparatory works km 5+784 Drilling for geotechnical investigation.

12 Preparatory works

13 Preparatory works km 9+105 Drilling for geotechnical investigation.

14 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing, formwork bracing and concreting of the laid joist of pillar S3 right (I part)

km 4+800~km 4+920

Reinforcing the pillar S3 left; Reinforcing,formwork bracing and concreting of the I part of the foundation of pillar S5 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700; Blasting.

km 7+800~km 8+150 Concreting of the foundation of ZV.2

Page 10: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 21.04.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request for inspection

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

7 Earth works Excavation with crushing of stone material.

8 Earth works km 5+094 Excavation of the foundations of pillar S1 and S2.

9 Concrete works km 5+094 request for inspection

10 Earth works

11 Preparatory works km 5+784 Drilling for geotechnical investigation.

12 Preparatory works request for inspection

13 Preparatory works km 9+105 Drilling for geotechnical investigation.

14 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing and formwork bracing of wing K1' of abutment S4 (campade II and III, Part II); Reinforcing and formwork bracing on the laid joist of pillar S3 right.

km 4+800~km 4+920

Formwork removing of the second campade of the foundation of pillar S3 left; Reinforcing of the I part of foundation of S3 left; Reinforcing and formwork bracing on the I part of the foundation of pillar S5 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150 Reinforcing the foundation of ZV.1

Page 11: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 20.04.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Preparatory works Preparation for embankment.

7 Earth works Excavation with crushing of stone material.

8 Earth works km 5+094 Concreting of the foundation of pillar S5 left with concrete fill-in request for inspection

9 Concrete works km 5+094 Concreting of the second campade of the foundation of pillar S3 left. request for inspection

10 Earth works

11 Preparatory works km 5+784 Drilling for geotechnical investigation.

12 Preparatory works Construction of access roads.

13 Preparatory works km 9+105 Drilling for geotechnical investigation.

14 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of wing K1' of abutment S4 (campade II and III, Part I); Reinforcing the laid joist of pillar S3 right.

km 4+530~km 4+640

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 12: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 19.04.2015 Sunday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request for inspection

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Earth works km 5+094 Excavation of the foundation of pillar S5 left.

9 Concrete works km 5+094

10 Earth works

11 Preparatory works km 5+784 Drilling for geotechnical investigation.

12 Preparatory works Construction of access roads.

13 Preparatory works km 9+105 Drilling for geotechnical investigation.

14 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Concreting of wing K1' of abutment S4 (campade II and III, Part I); Formwork bracing on the laid joist of pillar S3 right.

km 4+530~km 4+640Formwork removing of the first height of camapde ZXV; Coating with hydro insulation the first height of campade ZXV.

km 4+800~km 4+920

Formwork removing of the first campade of the foundation of pillar S3 left; Formwork bracing on the second campade of the foundation of pillar S3 left.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 13: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 18.04.2015 Saturday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Earth works km 5+094 Excavation of the foundation of pillar S5 left.

8 Concrete works km 5+094 Concreting of the foundation of pillar S3 left. Request for inspection

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Construction of access roads.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing and formwork bracing on wing K1' of abutment S4 (campade II and III); Formwork removing of wing K2' of abutment S4;Formwork bracing on the laid joist of pillar S3 right

km 4+530~km 4+640Formwork removing of the foundation of camapde ZXV; Formwork removing of the first height of campade ZXIV; Coating with hydro insulation the first height of campade ZXIV and the foundations of campade ZXIV and campade ZXV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 14: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 17.04.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Formwork removing of wing K2' of abutment S4.

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Preparatory works km 4+011 Preparation of climbing platforms for laid joist of pillar S3 right.

7 Concrete works

8 Earth works Excavation with crushing of stone material.

9 Earth works km 5+094 Excavation of the foundation of pillar S5 left.

10 Concrete works km 5+094 Reinforcing and formwork bracing of the foundation of pillar S3 left.

11 Earth works

12 Preparatory works km 5+784 Drilling for geotechnical investigation.

13 Preparatory works Construction of access roads.

14 Preparatory works km 9+105 Drilling for geotechnical investigation.

15 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+530~km 4+640Concreting of the foundation of camapde ZXV; Formwork removing of the first height of campade ZXIV; Coating with hydro insulation the first height of campade ZXIV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700; Blasting.

km 7+800~km 8+150

Page 15: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 16.04.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request for inspection

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Preparatory works km 4+011 Preparation of climbing platforms for laid joist of pillar S3 right.

7 Concrete works request for inspection

8 Earth works Excavation with crushing of stone material.

9 Earth works km 5+094 Excavation of the foundation of pillar S5 left.

10 Concrete works km 5+094 Concreting of the foundation of pillar S3 left with concrete fill-in. request for inspection

11 Earth works

12 Preparatory works km 5+784 Drilling for geotechnical investigation.

13 Preparatory works Construction of access roads.

14 Preparatory works km 9+105 Drilling for geotechnical investigation.

15 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of campade III of the foundation of wing K1' of abutment S4; Reinforcing and concreting of wing K2' of abutment S4.

km 4+530~km 4+640Reinforcing and formwork bracing on the foundation of camapde ZXV; coating with hydro insulation the second height of campade ZXIII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 16: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 15.04.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request for inspection

5 Earth works km 4+011 Excavation of the foundation of pillar S1 with blasting.

6 Concrete works request for inspection

7 Earth works Excavation with crushing of stone material; Blasting.

8 Earth works km 5+094 Excavation of the foundation of pillar S3 left.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Concreting of campade III of the foundation of wing K1' of abutment S4; Reinforcing and formwork bracing on wing K2' of abutment S4.

km 4+530~km 4+640Concreting of the first height of campade ZXIV; Concreting of the foundation of camapde ZXV with concrete fill-in.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 17: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 14.04.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Earth works km 5+094 Excavation of the foundation of pillar S3 left.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing and formwork bracing on campade III of the foundation of wing K1'.

km 4+530~km 4+640Reinforcing and formwork bracing on the first height of campade ZIV; formwork removing of the foundation of campade ZXIV and of the second height of camapde ZXIII; Concreting of the first height of campade ZXIV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 18: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 09.04.2015 Thursday

No. Type of work Chainage Construction content Notes

1 Earth works km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Due to unfavourable weather conditions all other works have been postponed until weather conditions improve

Page 19: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 08.04.2015 Wednesday

No. Type of work Chainage Construction content Notes

1 Earth works km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Due to unfavourable weather conditions all other works have been postponed until weather conditions improve

Page 20: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 07.04.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Dumping Area 1

2

3

4 km 4+011

5 km 4+011

6

7

8 km 5+094

9

10 km 5+78411

12 km 9+105

Due to unfavourable weather conditions all the works have

been postponed until weather conditions improve

km 3+520~km 3+840

km 4+160~km 5+000

km 4+530~km 4+640

km 4+800~km 4+920

km 5+400~km 5+700

km 7+800~km 8+150

Page 21: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 06.04.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing and formwork bracing on campade III of the foundation of wing K1'.

km 4+530~km 4+640Reinforcing and formwork bracing on the foundation of campade ZXV; formwork removing of the first height of campade ZXIV;

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 22: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 05.04.2015 Sunday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Concreting of campade II of the foundation of wing K2' of abutment S4 request for inspection

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Concrete works request for inspection

7 Earth works

8 Earth works Excavation with crushing of stone material.

9 Preparatory works km 5+094 Drilling for geotechnical investigation.

10 Earth works

11 Preparatory works km 5+784 Drilling for geotechnical investigation.

12 Preparatory works Redesigning due to unfavorable geotechnical conditions.

13 Preparatory works km 9+105 Drilling for geotechnical investigation.

14 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+530~km 4+640Reinforcing and formwork bracing on the first height of campade ZIV; formwork removing of the foundation of campade ZXIV and of the second height of camapde ZXIII; Concreting of the first height of campade ZXIV.

km 4+530~km 4+640 Excavation of the foundation of campade ZXV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 23: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 04.04.2015 Saturday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of the foundation of wing K2' of abutment S4; Formwork removing of the fifth height of pillar S2 left; Formwork bracing and reinforcing of campade II of the foundation of wing K1'.

km 4+530~km 4+640Coating with hydro insulation the second height of campade ZI and the second height of campade ZXII; Reinforcing of the first height of campade ZXIV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 24: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 03.04.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for Inspection

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Concrete works Request for Inspection

7 Earth works Excavation with crushing of stone material; Blasting

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Blasting.

Concreting of the foundation of wing K2' of abutment S4 (campade I); Concreting of the fifth height of pillar S2 left; Formwork removing of the laid joist of abutment S4.

km 4+530~km 4+640

Formwork removing of the second height of campade ZI; Formwork removing of the second height of campade ZXII; Concreting the foundation of campade ZXIV; Reinfocing,formwork bracing and concreting of the second height of campade ZXIII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 25: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 02.04.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for Inspection

5 Earth works km 4+011 Excavation of the foundation of pillar S1.

6 Concrete works Request for Inspection

7 Earth works Excavation with crushing of stone material; Blasting

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Blasting.

Concreting with concrete fill-in of the foundation of wing K1' of abutment S4 (campades I and II)

km 4+530~km 4+640Formwork removing of the second height of campade ZI; Formwork removing of the second height of campade ZXII; Formwork bracing and reinforcing the foundation of campade ZXIV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 26: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 01.04.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011

6 Concrete works Request for Inspection

7 Earth works

8 Earth works Excavation with crushing of stone material.

9 Preparatory works km 5+094 Drilling for geotechnical investigation.

10 Earth works

11 Preparatory works km 5+784 Drilling for geotechnical investigation.

12 Preparatory works Redesigning due to unfavorable geotechnical conditions.

13 Preparatory works km 9+105 Drilling for geotechnical investigation.

14 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of the fifth height of pillar S2 left; Formwork removing of the laid joist of abutment S4.

Excavation of the foundation of wing K1' of abutment S1; Excavation of the foundation of S1.

km 4+530~km 4+640Formwork bracing, reinforcing and concreting of the second height of campade ZI; Formwork bracing, reinforcing and concreting of the second height of campade ZXII.

km 4+530~km 4+640 Excavation of the foundation of campade ZXIV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 27: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 31.03.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of wing K1' of abutment S1.

6 Concrete works

7 Earth works

8 Earth works Excavation with crushing of stone material.

9 Preparatory works km 5+094 Drilling for geotechnical investigation.

10 Earth works

11 Preparatory works km 5+784 Drilling for geotechnical investigation.

12 Preparatory works Redesigning due to unfavorable geotechnical conditions.

13 Preparatory works km 9+105 Drilling for geotechnical investigation.

14 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Concreting and formwork bracing of the fifth height of pillar S2 left; Concreting of the laid joist of abutment S4.

km 4+530~km 4+640Formwork bracing and reinforcing the second height of campade ZI; Formwork bracing and reinforcing the second height of campade ZXII

km 4+530~km 4+640 Excavation of the foundation of campade ZXIII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 28: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 30.03.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of wing K1' of abutment S4.

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of the fifth height of pillar S3 left; Formwork removing of the fourth height of pillar S3 right; Formwork bracing on the laid joist of abutment S4.

km 4+530~km 4+640Concreting of the first height of campade ZI; Concreting of the first height of campade ZXIII; Concreting of the second height of campade ZXI; Formwork bracing and reinforcing the third height of campade ZIV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 29: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 29.03.2015 Sunday

No. Type of work Chainage Construction content Notes

Due to unfavorable weather forecast all works have been cancelled

Page 30: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 28.03.2015 Saturday

No. Type of work Chainage Construction content Notes

1 Earth works km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Due to unfavorable weather forecast all other works have been cancelled

Page 31: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 27.03.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of wing K1' of abutment S4.

6 Concrete works Request for inspection

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Blasting.

Formwork removing of the fifth height of pillar S3 left; Formwork removing of the fourth height of pillar S3 right; Formwork bracing on the laid joist of abutment S4.

km 4+530~km 4+640Concreting of the first height of campade ZI; Concreting of the first height of campade ZXIII; Concreting of the second height of campade ZXI; Formwork bracing and reinforcing the third height of campade ZIV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 32: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 26.03.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of wing K1' of abutment S4.

6 Concrete works Request for inspection

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of the the fifth height of pillar S3 left; Formwork removing of the fourth height of pillar S3 right; Formwork bracing on the laid joist of abutment S4.

km 4+530~km 4+640

Concreting of the first height of campade ZI; Concreting of the third height of campade ZIV; Formwork removing of the second height of campade ZII; Formwork removing of the second height of campade ZIV; Formwork bracing and reinforcing the second height of campade ZXII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 33: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 25.03.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation of the foundation of wing K1' of abutment S4.

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing the fifth height of pillar S2 left; Formwork bracing on the laid joist of abutment S4.

km 4+530~km 4+640Concreting of the second height of campade ZXI; Formwork bracing and reinforcing the third height of campade ZIV; Formwork bracing and reinforcing the second height of campade ZXII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 34: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 24.03.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Reinforcing and formwork bracing on the fifth height of pillar S3 left. Requests for inspection

5 Earth works km 4+011 Excavation of the foundation of wing K1' of abutment S4.

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+530~km 4+640Concreting of the second height of campade ZII; Reinforcing the second height of campade ZXI; Concreting of the foundation of camapde ZXIII; Formwork bracing and reinforcing the second height of campade ZIV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700; Mining.

km 7+800~km 8+150

Page 35: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 23.03.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Reinforcing and formwork bracing on the fourth height of pillar S3 right.

5 Earth works km 4+011

6 Concrete works Requests for inspection

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Excavation on the foundation of pillar S1; Excavation of the foundation of wing K1' of abutment S4.

km 4+530~km 4+640

Formwork removing of the third height of campade ZV; Formwork removing of the first height of campade ZXII; Formwork removing of the foundation of campade ZI; Formwork removing of the second height of campade ZIII; Formwork removing of the second height of campade ZX; Reinforcing and formwork bracing on the foundation of camapde ZXIII; Formwork bracing on the second height of campade ZIV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 36: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 22.03.2015 Sunday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 37: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 21.03.2015 Saturday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 38: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 20.03.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works km 4+011 Excavation on the foundation of pillar S1.

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Mining.

Reinforcing the fourth height of pillar S3 right; Reinforcing the fourth height of pillar S2 right.

km 4+530~km 4+640

Concreting of the third height of campade ZV; Concreting of the first height of campade ZXII; Concreting of the foundation of campade ZI; Formwork removing of the second height of campade ZII; Formwork removing of the second height of campade ZX.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 39: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 19.03.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Earth works km 4+011 Excavation on the foundation of pillar S1.

6 Concrete works Requests for inspection

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing the fourth height of pillar S3 right; Formwork bracing and concreting the fourth height of pillar S2 left.

km 4+530~km 4+640Concreting the third height of campade ZV; Reinforcing and formwork bracing on the first height of campade ZXII; Reinforcing and formwork bracing on the foundation of campade ZI.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 40: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 18.03.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Earth works km 4+011 Excavation on the foundation of pillar S1.

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork bracing on the fourth height of pillar S2 left; Reinforcing the laid joist of abutment S4.

km 4+530~km 4+640Reinforcing and formwork bracing on the third height of campade ZV; Reinforcing and formwork bracing on the second height of campade ZX; Reinforcing and formwork bracing on the second height of campade ZIII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 41: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 17.03.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing and formwork bracing on the fourth height of pillar S3 left; Formwork removing of pillar S2 left and right; Formwork removing of the laid joist of abutment S4.

km 4+530~km 4+640Reinforcing the third height of campade ZV; Reinforcing and formwork bracing on the first height of campade ZXII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 42: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 16.03.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of the third height of pillar S2 right; Formwork removing of the laid joist of abutment S4.

km 4+530~km 4+640Formwork removing of the third height of campade ZVI; Reinforcing and formwork bracing the second height of campade ZV; Reinforcing the third height of campade ZIX.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 43: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 15.03.2015 Sunday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Concreting the third height of pillar S2 right; Concreting the laid joist of abutment S4.

km 4+530~km 4+640Formwork removing of the fourth height of campade ZVIII-1; Reinforcing and formwork bracing the second height of campade ZV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 44: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 14.03.2015 Saturday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Earth works km 4+011 Excavation on the foundation of pillar S1.

5 Concrete works km 4+011 Reinforcing the third height of pillar S2 right. Requests for inspection

6 Concrete works Request for inspection

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Mining.

km 4+530~km 4+640Concreting the third height of campade ZVI; Reinforcing the second height of campade ZV.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 45: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 13.03.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing the third height of pillar S2 left; Formwork; Concreting the third height of pillar S3 left and right; Reinforcing the third height of pillar S2 left; Formwork bracing the laid joist of abutment S4.

km 4+530~km 4+640Formwork bracing and reinforcing the third height of campade ZVI; Concreting the fourth height of campade ZVIII-1.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 46: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 12.03.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing the third height of pillar S3 right; Formwork bracing and concreting the third height of pillar S3 left; Reinforcing the third height of pillar S2 left; Formwork bracing the laid joist of abutment S4.

km 4+530~km 4+640Formwork removing of the second height of campade ZVI; Concreting the fourth height of campade ZVIII-1.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 47: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 11.03.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Concrete works Request for inspection

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork bracing and reinforcing the third height of pillar S3 right; Concreting the third height of pillar S3 left; Reinforcing the laid joist of abutment S4.

km 4+530~km 4+640Concreting the second height of campade ZVI; Reinforcing and formwork bracing on the fourth height of campade ZVIII-1.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 48: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 10.03.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Mining.

Formwork bracing and reinforcing the third height of pillar S3 left; Reinforcing the laid joist of pillar S4.

km 4+530~km 4+640Concreting the second height of campade ZVI; Reinforcing the first height of campade ZXII; Formwork removing of the third height of campade ZVIII-1.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 49: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 09.03.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Mining.

Formwork bracing and reinforcing the third height of pillar S3 left; Reinforcing the laid joist of pillar S4.

km 4+530~km 4+640Concreting the second height of campade ZVI; Reinforcing the first height of campade ZII; Formwork removing of the foundation of campade ZXII; Formwork removing of the third height of campade ZVIII-1.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 50: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 06.03.2015 Friday

No. Type of work Chainage Construction content Notes

1 Earth works km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

All other works have been cancelled due the unfavorable weather

conditions (snowing)

Page 51: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 05.03.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Mining.

Formwork bracing and reinforcing the third height of pillar S3 left; Reinforcing the sleeper beam of pillar S4.

km 4+530~km 4+640Formwork bracing and reinforcing the second height of campade ZVI; Reinforcing the first height of campade ZII; Formwork removing of the foundation of campade ZXII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 52: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 04.03.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork bracing and reinforcing the second height of pillar S2 left; Formwork bracing and reinforcing the second height of pillar S3 right; Reinforcing the sleeper beam of pillar S4.

km 4+530~km 4+640Formwork bracing and reinforcing the second height of campade ZVI; Reinforcing the first height of campade ZII; Concreting the foundation of campade ZXII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 53: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 03.03.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing the second height of pillar S2 left; Formwork bracing on the second height of pillars S2 left and S2 right.

km 4+530~km 4+640Concreting of the third height of campade ZVIII-1; Reinforcing and formwork bracing on the foundation of campade ZXII; Concreting the foundation of campade ZXII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 54: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 02.03.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Reinforcing and formwork bracing on the second height of pillar S2 left. Request

5 Concrete works Request

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+530~km 4+640Concreting of the third height of campade ZVII; Reinforcing and formwork bracing on the foundation of campade ZXII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 55: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 01.03.2015 Sunday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Digging in the foundation pits of middle pillars; Reinforcing the sleeper beam of pillar S4.

km 4+530~km 4+640Reinforcing and formwork bracing on the third height of campade ZVII; Reinforcing and formwork bracing on the third height of campade ZVIII-1; Reinforcing and formwork bracing on the foundation of campade ZXII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 56: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 28.02.2015 Saturday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Formwork bracing on the second height of pillar S3 right; Reinforcing the second height of pillar S2 right.

km 4+530~km 4+640Reinforcing and formwork bracing on the third height of campade ZVII; Reinforcing and formwork bracing on the third height of campade ZVIII-1.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 57: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 27.02.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request

5 Concrete works request

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Digging in the foundation pits of pillar S3 left and right; Reinforcing the sleeper beam of pillar S4; Reinforcing the second height of pillar S3 right.

km 4+530~km 4+640Reinforcing and formwork bracing on the third height of campade ZVII; Formwork removing of the third height of campade ZVIII; Reinforcing the first height of campade campade ZII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 58: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 26.02.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request

5 Concrete works request

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Mining.

Formwork bracing and reinforcing the first height of pillar S2 right; Reinforcingthe second height of pillar S3 left.

km 4+530~km 4+640

Reinforcing and formwork bracing on the third height of campade ZVII; Reinforcing and formwork bracing on the foundation of campade campade ZII; Reinforcing and formwork bracing on the foundation of campade campade ZXII

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 59: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 25.02.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request

5 Concrete works request

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Formwork bracing, reinforcing and concreting the first height of pillar S2 left and right; Formwork removing of pillar S3left and right.

km 4+530~km 4+640Reinforcing and formwork bracing on the third height of campade ZVII; Reinforcing and formwork bracing on the foundation of campade campade ZII; Concreting the third height of campade ZVIII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 60: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 24.02.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Formwork bracing and reinforcing the first height of pillar S2 left and right. request

5 Concrete works 2 requests

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

km 4+530~km 4+640Concrete fill-in for the foundations campade ZI and campade ZII; Formwork bracing and reinforcing the third height of campade ZVIII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 61: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 23.02.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works

6 Concrete works

7 Earth works Excavation with crushing of stone material.

8 Preparatory works km 5+094 Drilling for geotechnical investigation.

9 Earth works

10 Preparatory works km 5+784 Drilling for geotechnical investigation.

11 Preparatory works Redesigning due to unfavorable geotechnical conditions.

12 Preparatory works km 9+105 Drilling for geotechnical investigation.

13 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Formwork bracing on pillar S2 left and right; Formwork removing of pillar S3 left and right.

km 4+530~km 4+640 Excavation on the foundation of campade ZII.

km 4+530~km 4+640Formwork removing of the second height of campade ZVII; Formwork bracing and reinforcing the third height of campade ZVIII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 62: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 21.02.2015 Saturday

No. Type of work Chainage Construction content Notes

1 Earth works

2 Earth works

3 Concrete works km 4+011 Reinforcing the first height of pillar S2 left and right.

4 Earth works Excavation with crushing of stone material.

5 Earth works

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

Page 63: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 20.02.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 request

5 Concrete works request

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Mining.

Concreting the first campade of pillar S3 left; Formwork bracing on pillar S4; Formwork removing of the first height of pillar S3 right.

km 4+530~km 4+640Formwork removing of the second height of campade ZVIII; Concreting the second height of campade ZVII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 64: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 19.02.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Concrete works

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Preparatory works km 5+784 Drilling for geotechnical investigation.

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Concreting the second camapde of the foundation of pillar S2 left; Concreting the first height of pillar S3 right.

km 4+530~km 4+640Reinforcing and formwork bracing on the third height of campade ZVIII-1; Reinforcing the second height of campade ZVII.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 7+800~km 8+150

Page 65: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 18.02.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Earth works Excavation with crushing of stone material.

6 Preparatory works km 5+094 Drilling for geotechnical investigation.

7 Earth works

8 Concrete works

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Drilling for geotechnical investigation.

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Concreting the second camapde of the foundation of pillar S2 left; Concreting the first height of pillar S3 right; Formwork removing of the second campade of the foundation of pillar S2 right; Reinforcing the first height of pillar S3 left.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640

Concreting the second height of campade ZVIII; Formwork bracing and reinforcing the second height of campade ZVII; Coating with hydro insulation the first height of campade ZXI and the second height of campade ZIX.

km 7+800~km 8+150

Page 66: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 17.02.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Earth works Excavation with crushing of stone material; Mining.

6 Preparatory works km 5+094 Drilling for geotechnical investigation.

7 Earth works

8 Earth works

9 Concrete works Request for inspection

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Reinforcing the second camapde of the foundation of pillar S2 left; Reinforcing the first height of pillar S3; Formwork removing of the second campade of the foundation of of pillar S2 right.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700; Mining.

km 4+530~km 4+640 Excavation on the foundation of campade ZII.

km 4+530~km 4+640Formwork bracing and reinforcing the second height of campade ZVII and capamde ZVIII.

km 7+800~km 8+150

Page 67: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 16.02.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Earth works km 4+011 Excavation of the foundation of pillar S1.

5 Concrete works km 4+011 Request for inspection

6 Earth works Excavation with crushing of stone material.

7 Preparatory works km 5+094 Drilling for geotechnical investigation.

8 Earth works

9 Concrete works Request for inspection

10 Preparatory works Redesigning due to unfavorable geotechnical conditions.

11 Preparatory works km 9+105 Drilling for geotechnical investigation.

12 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Concreting of the II camapde of the foundation of pillar S2 left and right; Climbing console platforms on abutment S4.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700; Mining.

km 4+530~km 4+640Formwork removing of the second height of campade ZIX; Concreting the first height of campade ZIII; Formwork bracing and reinforcing the second height of campade ZVII.

km 7+800~km 8+150

Page 68: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 15.02.2015 Sunday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Preparatory works km 5+094 Drilling for geotechnical investigation.

7 Earth works

8 Concrete works

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Drilling for geotechnical investigation.

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Formwork bracing and reinforcing of the II camapde of the foundation of pillar S2 left and right; Formwork removing of the II part of abutment S4.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640

Formwork bracing and reinforcing the first height of campade ZIII; Formwork removing of the first height of campade ZXI; Formwork removing of the foundation of camapde ZIII; Formwork bracing and reinforcing the second height of campade ZVII.

km 7+800~km 8+150

Page 69: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 14.02.2015 Saturday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Preparatory works km 5+094 Drilling for geotechnical investigation.

7 Earth works

8 Concrete works Request for inspection

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Drilling for geotechnical investigation.

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Formwork bracing and reinforcing of the II part of pillar S3 left and right; Formwork removing of the II part of abutment S4.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640Concreting of the second height of ZIX; Formwork bracing and reinforcing the first height of campade ZIII; Reinforcing the second height of campade ZVII.

km 7+800~km 8+150

Page 70: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 13.02.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Preparatory works km 5+094 Drilling for geotechnical investigation.

7 Earth works

8 Concrete works Requests for Inspection

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Drilling for geotechnical investigation.

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction;

Concreting the abutment S4 and wing K2'; Formwork bracing of pillar S2 left and right; Reinforcing the pillar S3 left and right.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700; Mining.

km 4+530~km 4+640

Formwork bracing and reinforcing the foundation of campade ZIII;Formwork bracing on the first height of cmapade ZXI;Concreting the foundation of campade ZIII and the first height of campade ZXI; Formwork bracing and reinforcing the second height of ZIX.

km 7+800~km 8+150

Page 71: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 12.02.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Preparatory works km 5+094 Drilling for geotechnical investigation.

7 Earth works

8 Concrete works

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Drilling for geotechnical investigation.

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Mining.

Formwork bracing on the of abutment S4 and pillar S2 left and right; Clearing of the terrain.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640Formwork bracing on the first height of cmapade ZXI; Formwork bracing and reinforcing the second height of ZIX.

km 7+800~km 8+150

Page 72: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 11.02.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Formwork bracing on the of abutment S4 and pillar S2 left and right.

5 Earth works Excavation with crushing of stone material.

6 Earth works

7 Concrete works

8 Preparatory works Redesigning due to unfavorable geotechnical conditions.

9 Preparatory works km 9+105 Excavation for geotechnical investigation

10 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640Formwork bracing and reinforcing the first height of cmapade ZXI; Formwork bracing and reinforcing the second height of ZIX.

km 7+800~km 8+150

Page 73: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 10.02.2015 Tuesday

No. Type of work Chainage Construction content Notes

1 Earth works km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction; Drilling for mining.

Page 74: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 09.02.2015 Monday

No. Type of work Chainage Construction content Notes

1 Earth works km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Page 75: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 07.02.2015 Saturday

No. Type of work Chainage Construction content Notes

1 Earth works km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Page 76: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 06.02.2015 Friday

No. Type of work Chainage Construction content Notes

1 Earth works km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Page 77: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 04.02.2015 Wednesday

No. Type of work Chainage Construction content Notes1

2

3

4 Concrete works km 4+011 Formwork bracing on the of abutment S4 and pillar S2 left and right.

5 Earth works Excavation with crushing of stone material.

6 Earth works

7 Concrete works

8

9

10

11

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640Formwork bracing and reinforcing the first height of cmapade ZXI; Formwork bracing and reinforcing the second height of ZIX.

Page 78: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 03.02.2015 Monday

No. Type of work Chainage Construction content Notes1

2

Only if the conditions allow it.

3

4

5 Earth works Excavation with crushing of stone material.

6 Earth works

7

8

9

10

11

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

Page 79: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 02.02.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Earth works

7 Earth works

8 Concrete works

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Excavation for geotechnical investigation

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of the first height of abutment S4; Formwork bracing on the second height of abutment S4; Cleaning of the terrain for pillar S2 left and right.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640 Excavation of the foundation of campade ZII.

km 4+530~km 4+640Formwork bracing and reinforcing the first height of cmapade ZXI; Formwork bracing and reinforcing the second height of ZIX.

km 7+800~km 8+150

Page 80: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 31.01.2015 Saturday

No. Type of work Chainage Construction content Notes

1 Earth works

2 Earth works Drilling for mining.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 5+400~km 5+700

Page 81: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 30.01.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Earth works

7 Concrete works Request for inspection

8 Preparatory works Redesigning due to unfavorable geotechnical conditions.

9 Preparatory works km 9+105 Excavation for geotechnical investigation

10 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing the pillar S3 right; Formwork bracing on the pillar S2 left and right; Concreting of pillar S3 left and right.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640Concrete fill-in for the foundation of ZIII; Formwork bracing on the first height of cmapade ZXI; Reinrocing the second height of ZIX.

km 7+800~km 8+150

Page 82: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 29.01.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Request for inspection

5 Earth works Excavation with crushing of stone material; Mining

6 Earth works

7 Earth works

8 Concrete works

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Excavation for geotechnical investigation

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing the second campade of pillar S2 left and right; Reinforcing the second campade of pillar S3 left and right.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640 Excavation of the foundation of campades ZIII and ZII.

km 4+530~km 4+640 Reinforcing and formwork bracing on the first height of cmapade ZXI.

km 7+800~km 8+150

Page 83: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 28.01.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Concreting of abutment S4.

5 Earth works Excavation with crushing of stone material.

6 Earth works

7 Earth works

8 Concrete works

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Excavation for geotechnical investigation

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640 Excavation of the foundation of campades ZIII.

km 4+530~km 4+640Formwork removing of the foundation of campade ZXI; Reinforcing the first height of cmapade ZXI.

km 7+800~km 8+150

Page 84: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 27.01.2015 Tuesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Concreting of abutment S4.

5 Earth works Excavation with crushing of stone material; Mining.

6 Earth works

7 Earth works

8 Concrete works Request for Inspection

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Excavation for geotechnical investigation

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640 Excavation of the foundation of campades ZIII and ZXII.

km 4+530~km 4+640Coating with hydroinsulation the first heights of campades ZIV and ZXI; Reinforcing and formwork bracing on the foundation of cmapade ZXI.

km 7+800~km 8+150

Page 85: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 26.01.2015 Monday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Earth works

7 Earth works

8 Concrete works

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Excavation for geotechnical investigation

11 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Reinforcing of pillar S3 right and S2 left; Formwork removing of S2 left and right; Concreting of abutment S4.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640 Excavation of the foundation of campades ZIII and ZXI.

km 4+530~km 4+640 Formwork removing of the first height of campade ZX.

km 7+800~km 8+150

Page 86: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 25.01.2015 Sunday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works

6 Earth works

7 Concrete works

8 Preparatory works

9 Preparatory works km 9+105

10 Preparatory works

km 3+520~km 3+840

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640

km 7+800~km 8+150

Page 87: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 24.01.2015 Saturday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works

6 Earth works

7 Concrete works

8 Preparatory works

9 Preparatory works km 9+105

10 Preparatory works

km 3+520~km 3+840

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640

km 7+800~km 8+150

Page 88: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 23.01.2015 Friday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011 Reinforcing of pillar S3 left and right.

5 Earth works Excavation with crushing of stone material.

6 Earth works

7 Concrete works

8 Preparatory works Redesigning due to unfavorable geotechnical conditions.

9 Preparatory works km 9+105 Excavation for geotechnical investigation

10 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640 Formwork bracing on campade ZIV; Concreting of campades ZXI and ZIV.

km 7+800~km 8+150

Page 89: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 22.01.2015 Thursday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Earth works

7 Concrete works

8 Preparatory works Redesigning due to unfavorable geotechnical conditions.

9 Preparatory works km 9+105 Excavation for geotechnical investigation

10 Preparatory works Marking of the route, survey of ground level.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Formwork removing of pillar S2 left and right; Reinforcing of pillar S3 left and right.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640 Formwork bracing on campade ZIV.

km 7+800~km 8+150

Page 90: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 21.01.2015 Wednesday

No. Type of work Chainage Construction content Notes1 Preparatory works Dumping Area 1 Preparation for drainage canals.

2 Earth works

3 Earth works

4 Concrete works km 4+011

5 Earth works Excavation with crushing of stone material.

6 Earth works

7 Concrete works

8 Earth works

9 Preparatory works Redesigning due to unfavorable geotechnical conditions.

10 Preparatory works km 9+105 Excavation for geotechnical investigation

11 Preparatory works Marking of the route, survey of ground level.

12 Preparatory works Performing final works at the site accommodation.

km 3+520~km 3+840Excavation; Transport of the material on Dumping Area No.1 with leveling and compaction.

km 4+160~km 5+000Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Preparation for concreting of abutment S4; Formwork removing of pillar S3 left and right.

km 4+800~km 4+920

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

km 4+530~km 4+640Formwork bracing on the first height of campade ZX; Reinforcing and formwork bracing on the first height of campade ZIV.

km 4+530~km 4+640 Excavation of the foundation of campade ZIII.

km 7+800~km 8+150

Page 91: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 20.01.2015 Tuesday

No. Type of work Chainage Construction content Notes

1 Earth works

2 Earth works

3

Preparatory works

Dumping Area 14

5

6 km 4+011

7

8

9 km 9+105

km 4+800~km 4+920Excavation with crushing of stone material; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

Clearing of the access roads; Spreading and compaction of crushed stone material on the access roads; Placing pipes for passing of water from the melting snow; Marking of the route, survey of ground level.

km 3+520~km 3+840

km 4+160~km 5+000

km 4+540~km 4+640

km 7+800~km 8+150

Page 92: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 17.01.2015 Saturday

No. Type of work Chainage Construction content Notes

1 Earth works

2 Earth works

3

Preparatory works

Dumping Area 14

5

6 km 4+011

7

8

9 km 9+105

km 4+800~km 4+920Excavation with crushing of stone material; Transport of the material on Dumping Area No.2 with leveling and compaction.

km 5+400~km 5+700 Excavation from 5+400~km 5+700.

Clearing of the access roads; Spreading and compaction of crushed stone material on the access roads; Placing pipes for passing of water from the melting snow; Marking of the route, survey of ground level.

km 3+520~km 3+840

km 4+160~km 5+000

km 4+540~km 4+640

km 7+800~km 8+150

Page 93: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 16.01.2015 Friday

No. Type of work Chainage Construction content Notes

1 Earth works

2

Preparatory works

Dumping Area 13

4

5 km 4+011

6

7

8

9 km 9+105

km 4+800~km 4+920Excavation with crushing of stone material; Transport of the material on Dumping Area No.2 with leveling and compaction.

Clearing of the access roads; Spreading and compaction of crushed stone material on the access roads; Placing pipes for passing of water from the melting snow; Marking of the route, survey of ground level.

km 3+520~km 3+840

km 4+160~km 5+000

km 5+400~km 5+700

km 4+540~km 4+640

km 7+800~km 8+150

Page 94: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 15.01.2015 Thursday

No. Type of work Chainage Construction content Notes

1 Earth works

2

Preparatory works

Dumping Area 13

4

5 km 4+011

6

7

8

9 km 9+105

km 4+800~km 4+920Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Clearing of the access roads; Spreading and compaction of crushed stone material on the access roads; Placing pipes for passing of water from the melting snow; Marking of the route, survey of ground level.

km 3+520~km 3+840

km 4+160~km 5+000

km 5+400~km 5+700

km 4+540~km 4+640

km 7+800~km 8+150

Page 95: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 14.01.2015 Wednesday

No. Type of work Chainage Construction content Notes

1 Earth works

2

Preparatory works

Dumping Area 13

4

5 km 4+011

6

7

8

9 km 9+105

km 4+800~km 4+920Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Clearing of the access roads, spreading of crushed stone material on the access roads and placing pipes for passing of water from the melting snow.

km 3+520~km 3+840

km 4+160~km 5+000

km 5+400~km 5+700

km 4+540~km 4+640

km 7+800~km 8+150

Page 96: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 13.01.2015 Tuesday

No. Type of work Chainage Construction content Notes

1 Earth works

2

Preparatory works

Dumping Area 13

4

5 km 4+011

6

7

8

9 km 9+105

km 4+800~km 4+920Excavation; Transport of the material on Dumping Area No.2 with leveling and compaction.

Clearing of the access roads and placing pipes for passing of water from the melting snow.

km 3+520~km 3+840

km 4+160~km 5+000

km 5+400~km 5+700

km 4+540~km 4+640

km 7+800~km 8+150

Page 97: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 12.01.2015 Monday

No. Type of work Chainage Construction content Notes1 Dumping Area 1 Clearing of Dumping Area2

3

4 km 4+011

5

6

7

8

9 km 9+105

km 3+520~km 3+840

Clearing of the access roads to the excavations and clеаring of Dumping Areas

km 4+160~km 5+000

km 4+800~km 4+920

km 5+400~km 5+700

km 4+540~km 4+640

km 7+800~km 8+150

Page 98: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 10.01.2015 Saturday

No. Type of work Chainage Construction content Notes1 Dumping Area 1 Clearing of Dumping Area2

3

4 km 4+011

5

6

7

8

9 km 9+105

km 3+520~km 3+840

Clearing of the access roads to the excavations and clеаring of Dumping Areas

km 4+160~km 5+000

km 4+800~km 4+920

km 5+400~km 5+700

km 4+540~km 4+640

km 7+800~km 8+150

Page 99: Daily Work Plan

Daily work plans

Section from km 0+000.00~ km 10+424.88 Granit 09.01.2015 Friday

No. Type of work Chainage Construction content Notes1 Dumping Area 1 Clearing of Dumping Area2

Clearing of the access roads to the excavations and Dumping Areas

3

4 km 4+011

5

6

7

8

9 km 9+105

km 3+520~km 3+840

km 4+160~km 5+000

km 4+800~km 4+920

km 5+400~km 5+700

km 4+540~km 4+640

km 7+800~km 8+150