current status of nuclear construction best practice forum

18
Vanbrugh Consulting Evolution of the Global Nuclear Supply Chain Chris Savage OECD Nuclear Energy Agency Workshop March 11 th 2014

Upload: others

Post on 16-Oct-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Current status of Nuclear Construction Best Practice Forum

Vanbrugh Consulting

Evolution of the Global Nuclear Supply Chain

Chris Savage

OECD Nuclear Energy Agency Workshop

March 11th 2014

Page 2: Current status of Nuclear Construction Best Practice Forum

Scope

• Economic context • Why supply chain matters

• Industry adaptation

• Options for the future

• Issues to be addressed

Vanbrugh Consulting

Page 3: Current status of Nuclear Construction Best Practice Forum

Levelised Costs of Nuclear

Vanbrugh Consulting

Nuclear is highly capital intensive

Page 4: Current status of Nuclear Construction Best Practice Forum

Levelised Costs of Nuclear

Vanbrugh Consulting

Estimated value of differing cost elements per kW over 40 year life

Source KPMG 2010

Page 5: Current status of Nuclear Construction Best Practice Forum

Value Breakdown of a New Nuclear Plant

Equipment = 48% of value

• Nuclear Island

• Conventional Island

• Balance of Plant

Vanbrugh Consulting

NSSS

Electrical

Mechanical

C&I

Fuel

Construction

Proj Man

Page 6: Current status of Nuclear Construction Best Practice Forum

Nuclear construction costs

Vanbrugh Consulting

Falling costs during 90s Regulatory certainty Construction periods

Rising after 2005

Resource costs Manufacturing capacity

Page 7: Current status of Nuclear Construction Best Practice Forum

Outturn costs escalate

Vanbrugh Consulting

Source: KPMG 2012

Page 8: Current status of Nuclear Construction Best Practice Forum

Generation III designs

Very large components

Pressure vessels require 14000 tonnes+ press

Steam generators • EPR: 4 x 25m

• AP1000: 2 x 23m

Single turbine

Vanbrugh Consulting

Page 9: Current status of Nuclear Construction Best Practice Forum

Olkiluoto

Luc Oursel Areva NP not “100 percent assured to have a good quality of supply”

STUK Supply chain “not used to working to the exacting standards required on nuclear construction sites since so few new reactors have been built in recent years”

Vanbrugh Consulting

Page 10: Current status of Nuclear Construction Best Practice Forum

Supply Chain Consolidation

Vanbrugh Consulting

Babcock & Wilcox

Framatome

Siemens

Mitsubishi Heavy Industries

Combustion Engineering

Asea

Brown Boveri

Westinghouse

Toshiba

Hitachi

GE

Hanjung

Framatome Framatome ANP AREVA NP

Mitsubishi HI

ABB

Doosan Heavy Industries

BNFL

Toshiba Westinghouse

Hitachi GE

Doosan Group

Skoda

Collaboration agreement

1980s 1990s 2000s

Page 11: Current status of Nuclear Construction Best Practice Forum

Consolidation driven by slowdown

Vanbrugh Consulting

Construction starts 1951-2011

Page 12: Current status of Nuclear Construction Best Practice Forum

Large forgings

• Investment requires firm orders

• New capacity coming on line

• Emerging spare capacity

Vanbrugh Consulting

0

5

10

15

20Europe

0

5

10

15

20Japan

0

5

10

15

20

China

0

5

10

15

20USA

0

5

10

15

20Russia

0

5

10

15

20India

0

5

10

15

20S Korea

Page 13: Current status of Nuclear Construction Best Practice Forum

Industry Structure

Consolidation v diversification • New entrants

• Localisation

• Growth and additional capacity required

Integration v diversity

Partnerships • Technology transfer

• Quality

Vanbrugh Consulting

Page 14: Current status of Nuclear Construction Best Practice Forum

Project Structuring

Vanbrugh Consulting

Procurement options EPC Island

Multi-packages

Number of projects

Page 15: Current status of Nuclear Construction Best Practice Forum

Regulatory Constraints

Principle 1: Responsibility for safety

The prime responsibility for safety must rest with the person or organization

responsible for facilities and activities that give rise to radiation risks

The licensee retains the prime responsibility for safety throughout the

lifetime of facilities and activities, and this responsibility cannot be delegated.

Vanbrugh Consulting

Page 16: Current status of Nuclear Construction Best Practice Forum

Learning from elsewhere?

Vanbrugh Consulting

Incentives

risk

innovation

design

costs

Page 17: Current status of Nuclear Construction Best Practice Forum

Procurement Structure

• Vendor financing

• Build-Own-Operate franchise

• Merchant utilities

• Market reform

• Structured project finance

Vanbrugh Consulting

Customer

Supply chain Technology

Page 18: Current status of Nuclear Construction Best Practice Forum

Conclusions

No single route to change

Transition from industrial-led consortia to diverse structures

Cost as a driver

Adopting strategic supply chain relationships

Vanbrugh Consulting