CS Faculty Lunch, March 10, 2008CS Faculty Lunch, March 10, 2008

Status of Sutardja Dai Hall

Tentative CITRIS Occupancy Plan

Projected Impact on Soda Hall

Proposed Occupancy Plan for Oct. 08

Proposal: How to Handle Surge Phase

Level 1: Computer RoomLevel 1: Computer Room

Level 1: CorridorLevel 1: Corridor

Level 1: Future “Macro-Lab”Level 1: Future “Macro-Lab”

Level 1: Utilities under Marvell LabLevel 1: Utilities under Marvell Lab

Level 2: Machinery under Marvell LabLevel 2: Machinery under Marvell Lab

Level 2: Pete’s CyberCafeLevel 2: Pete’s CyberCafe

Level 2: Atrium StairsLevel 2: Atrium Stairs

Level 3: AtriumLevel 3: Atrium

Level 3: AuditoriumLevel 3: Auditorium

Level 3.5: Lower Marvell Lab Level 3.5: Lower Marvell Lab

(Photolithography)

Level 3.5: Marvel Lab (Air Filtration)Level 3.5: Marvel Lab (Air Filtration)

Level 4: Carrel Space (W)Level 4: Carrel Space (W)

Level 4: Office CorridorLevel 4: Office Corridor

Level 5: Carrel Space (E)Level 5: Carrel Space (E)

Level 5: Lab AdministrationLevel 5: Lab Administration

Level 5: Entry to Marvell LabLevel 5: Entry to Marvell Lab

Level 5: Upper Marvell LabLevel 5: Upper Marvell Lab (Diffusion Furnaces)

Level 6: TerraceLevel 6: Terrace

Level 6: Bridge to CoryLevel 6: Bridge to Cory

Level 6: LoungeLevel 6: Lounge

Level 6: Carrel Space (E)Level 6: Carrel Space (E)

Level 7: Carrel Space (E)Level 7: Carrel Space (E)

Level 7: Carrel Space (W)Level 7: Carrel Space (W)

Level 7: Elevator ShaftLevel 7: Elevator Shaft

Level 7: LoungeLevel 7: Lounge

Level 8: Roof with Air HandlersLevel 8: Roof with Air Handlers

Level 9: Roof of Elevator PenthouseLevel 9: Roof of Elevator Penthouse

Level 9: View of Marvell Lab RoofLevel 9: View of Marvell Lab Roof

Street Level: Corner of Marvell LabStreet Level: Corner of Marvell Lab

Sutardja-Dai Hall: Status SummarySutardja-Dai Hall: Status Summary

It is real

It is on schedule

Move-in starts January 2009

Grand opening on March 6, 2009

Initial occupancy is being finalized now ...

Initial Occupancy -- Phase 1 Move-inInitial Occupancy -- Phase 1 Move-in(tentative)(tentative)

F7: 3 AI-robotics projects: Malik, Fearing, ...

F6: MEMS, sensor appl.: Glaser (CEE), Boser, ...

F5: Lab-proj.: King Liu, Bokor, Majumdar (ME), ...

F4: BID, CNM, TIER, ... : Canny, Niemeyer (AP), Goldberg, Brewer, ...

F3: CITRIS & GLOBE administration; Auditorium.

F2: CyberCafe, Seminar rooms, 24-7 IT room.

F1: Computer room, MacroLab, Motion Capture.

Impact on Soda HallImpact on Soda Hall

AI-group (6 Faculty) will move.

TIER (Brewer + 6-8 students) will move.

UNKNOWNS:

Where will “Cyber-Security” end up ?(Tygar, Samuelson (IS), Saxenian (IS) ...)

Where will “Quantum-Computing” reside ?(Vazirani, Kubiatowicz, ...)

Minimal-Perturbation Goal-StatesMinimal-Perturbation Goal-States

Trying to consolidate Theory (faculty and students) on Floor 6

Potential to consolidate Security(faculty and students) on Floor 7 or 5

How Do We Approach Goal-States ?How Do We Approach Goal-States ?

Discuss more detailed surge plan by Scott McNally.

Discussion about most desirable goal-state should continue through the next weeks and through Spring Retreat.