crenshaw//jlax transit corridor project rigid rail...
TRANSCRIPT
Crenshaw/LAX Transit Corridor Project/ jRigid Rail Overhead Contact System
TABLE OF CONTENTSTABLE OF CONTENTS
A. IntroductionB. Project DescriptionC. Performance RequirementsD. Operational Data for Load Flow AnalysisE. Load Flow Analysis Results
1. Case 1 – 1 Messenger & 1 Contact Wire2. Case 2 – 1 or 2 Messengers & 1 Contact Wire Plus
Parallel Feeders as Requiredq3. Case 3 – 1 or 2 Messengers & 1 Contact Wire and Rigid
Rail OCS as RequiredF ConclusionsF. Conclusions
A. IntroductionThis presentation is to present a summary of the
process to recommend the use of the Rigid Rail OCS for the underground sections of the Crenshaw/LAX LRT Project
In the presentation we will show the following:1. Brief Project descriptione oject desc pt o
2. Metro Design Criteria for Traction Power System
3 Operational Data3. Operational Data
4. Selected Results of Load Flow Analysis
5 Recommendations5. Recommendations
B. Project Descriptionh h• The Crenshaw Project is a
Light Rail Transit (LRT) Project that extends approximately 8.4 miles.
• The Crenshaw LRT alignment runs north to south from u s o t to sout onear the Crenshaw Station in the new Exposition Line to the existing Metro Greenthe existing Metro Green Line (MGL) where the Crenshaw LRT tracks merge into the MGL in a double-Yinto the MGL in a double Y configuration (half-grand) on the west side of the Aviation/LAX Station of theAviation/LAX Station of the MGL.
• The Crenshaw LRT will operate mainly in a protected guideway with a small section of guideway in street g y g yrunning where the trains share the unprotected street intersections with road vehicles.
• The Crenshaw LRT guideway is divided as follows:
Guideway Type Approximate LengthGuideway Type Approximate Length (miles)
Aerial Structures and Retain Filled 1.59At Grade (Exclusive ROW) 2 67At-Grade (Exclusive ROW) 2.67Depressed (Exclusive ROW) 0.78U-Sections (Approach to Tunnels) 0.35C t d C T i C ll 0 64Cut-and-Cover - Twin Cells 0.64Tunnels - Twin Bores 1.39Street Running 0.93
A i P j L h 8 35Approximate Project Length 8.35
• The Project baseline includes 6 stations with options to include 2 more as indicated:
StationStationName Type Platform
Crenshaw / Exposition Below Grade CenterCrenshaw / Martin Luther King Jr. Below Grade CenterCrenshaw / Vernon (optional) Below Grade CenterCrenshaw / Slauson Grade CenterFl / W t G d C tFlorence / West Grade CenterFlorence / La Brea Grade CenterHindry (optional) Grade SideAviation / Century Aerial CenterAviation / Century Aerial Center
C. PERFORMANCE REQUIREMENTS
Metro Rail Design Criteria, Section 9.18 – Traction Power and Distribution System key criteria isPower and Distribution System key criteria is summarized as follows:1 TPSS’s sized and located at suitable intervals;1. TPSS s sized and located at suitable intervals;
2. System to provide 750 VDC, range 500 VDC to 950VDC;
3. System to meet service requirements without degradation of service even with any one TPSS out of service;
4. System designed for simultaneous acceleration of two AW2 loaded 3-car trains with one TPSS out of service at farthestloaded 3 car trains with one TPSS out of service, at farthest apart TPSS location:
a) Acceleration close to in-service substation;
b) Acceleration close to out-of-service substation
5. Negative to ground voltages maintained below 50V under normal operation and under 70V when one TPSS out of service
6. Traction Power Electrical Design Criteria Requirements
DESCRIPTION VOLTAGE
Nominal Voltage (V dc) 750
Maximum Voltage for Regeneration (V dc) 950
h l l ( d )Minimum Vehicle Operating Voltage (V dc) 525
Substation No Load Voltage (V dc) (Assumed: 6% 795Regulation)
Substation Rating (MW) 1.5
D. OPERATIONAL DATA FOR LFA1 LIGHT RAIL VEHICLE DATA
DESCRIPTION INPUTTrain Model Type: Siemens P2000 LRV - 3 car
1. LIGHT RAIL VEHICLE DATA
yptrain
Weight per car (AW0) (t)(AW2) (t)
49.064.1
Train Model Type: P3010 LRV - 3 car trainWeight per car (AW3) (t) 61.2Auxiliary Power (kW/car) 40Length of 3-Car Train (ft) 270Maximum Acceleration (mph/s) 3Maximum Deceleration (mph/s) 2( p )Tractive Effort (Assumed: 80% Efficiency) AttachedMaximum Current Based on Appendix B (A/car) 1400Regeneration Used NoRegeneration Used No
2. TRAIN OPERATION
DESCRIPTION INPUTDESCRIPTION INPUT
Station dwell time (sec) (Aviation Station: 30 seconds)
20)
Speed Limit (mph) – Between Aviation/Century Station and Crenshaw/Exposition Station – Both Directions
55
DirectionsSpeed Limit (mph) - Between MGL Interface and Aviation/Century Station – Both Directions
65
Maximum Train Consist 3-Car Train
Headways
Bet een MGL Interface and A iation/Cent r 2 ½ min tesBetween MGL Interface and Aviation/Century Station – Both Directions
2 ½ minutes
Between Aviation/Century Station and 5 minutes/ yCrenshaw/Exposition Station – Both Directions
The Crenshaw LRT Baseline (full build-out) consists of 10 T i P S b i
3. BASELINE SUBSTATION LOCATION
Traction Power Substations.
In the Initial installation, TPSS #4, 7, and 10 will be deferred.
Substation Full Build-out Location
Distance between TPSS’s (ft)
Value EngineeringReduced Build-out
TPSS 01 10+00 TPSS 016200
TPSS 02* 72+00 TPSS 02*5200
TPSS 03* 124+00 TPSS 03*4350
TPSS 04 167+50 Deferred InstallationTPSS 04 167+50 Deferred Installation4700
TPSS 05 214+50 TPSS 055650
TPSS 06 271+00 TPSS 0641504150
TPSS 07 312+50 Deferred Installation5300
TPSS 08 365+50 TPSS 083800
TPSS 09 403+50 TPSS 094150
TPSS 10 445+00 Deferred Installation
E. LOAD FLOW ANALYSIS RESULTSThe following summarizes selected results of the
Load Flow Analysis (LFA) for the Baseline Configuration:
1. Case 1 – Baseline with Standard OCS (1-messenger & 1-contact wire only)
2. Case 2 – Baseline with 1 or 2-messengers & 1-contact Wire Plus Parallel Feeders where Required
l h3. Case 3 – Baseline with 1 or 2-messengers & 1-contact wire and Rigid Bar OCS instead of parallel Feeders where RequiredFeeders where Required
CASE 1- Base Case Simulation - 1 Messenger Wire & 1 Contact Wire
CASE 2- Base Case Simulation - 1 or 2 Messenger Wires &1 Contact Wire Plus Parallel Feeders as Required
FIGURE No. 1: CASE 2- Base Case Simulation – NETWORK DIAGRAM
FIGURE No.2: CASE 2 – Cut-and-Cover: Standard OCS with Parallel Feeders Configuration
FIGURE No.3: CASE 2 – Bored Tunnel: Standard OCS with Parallel Feeders Configuration
CASE 3- Base Case Simulation - 1 or 2 Messenger Wires &1 Contact Wire and Rigid BAR OCS Where Indicated
FIGURE No. 4: CASE 3- Base Case Simulation – NETWORK DIAGRAM
FIGURE No.5: CASE 2 – Cut-and-Cover: Rigid OCS Configuration
FIGURE No.6: CASE 2 – Bored Tunnel: RIGID RAIL OCS Configuration
The results of the LFA indicate a large amount of copper cross-F. CONCLUSIONS
The results of the LFA indicate a large amount of copper cross-section for the OCS is required to carry the traction power loads based on Metro Criteria and operational requirements; It is concluded that for the tunnel sections the Rigid Bar OCSIt is concluded that for the tunnel sections the Rigid Bar OCS will provide benefits as follows:
1. It requires less initial capital investment over the simple t ith 3 ll l f dcatenary with 3-parallel feeders
2. It requires less maintenance since the OCS is not under tension – No wire creepage; therefore, no adjustments required
3. It provides ample current capacity to carry the loads at the worst condition without overheatingworst condition without overheating
4. It is commonly used in Europe and Asia because or reliability and low maintenance
5 C l LRT i tl i t lli Ri id R il OCS i th W t5. Calgary LRT is currently installing Rigid Rail OCS in the West Valley Project (Approximately 5000’)