corrigendum no. 1 to rfp notice no. 10 of 2013

Upload: prakash-arthur

Post on 14-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    1/44

    August 19, 2013

    Subject : Corrigendum No. 1 in the RFP Notice No. 10 of 2013

    Reference: RFP Notice No. 10 of 2013

    CORRIGENDUM NO. 1 to RFP Notice No. 10 of 2013 by GSDMA

    Following is the corrigendum to presently available RFP for Selection of Build, Own, Operate, and Transfer (BOOT) Operator to Set-up and

    manage Information & Communication Technology System (ICTS) Infrastructure for Gujarat State Disaster Response.

    Note GSDMA will respond to only those queries received before the end of day (IST) on August 23, 2013. (All emails should be sent to

    [email protected])

    Sr.

    #

    Page

    #Clause #

    Description of

    Terms / HeadingsExisting Clause Query GSDMA Response

    1121

    Annexure

    III Section

    1.2

    Technical

    Specifications for

    Incident

    ManagementApplication

    The system should support:

    Integration with ESRI ARCGIS

    server 9.3 to store, manage and

    analyse spatial data, including

    interoperability with the ARCGIS

    Server Web Application

    Development Framework (ADF).

    Advanced spatial data types

    representing geometries such as

    points, lines, and polygons and

    many functions and features that

    interoperate with these data types.

    All Vendors should ensure that

    proposed GIS platform (s) comply

    to OGC standards such as WMS,

    WPS, WFS, WCS etc.

    Will GSDMA accept IMS software whichuses non-ESRI platforms like Google Map

    or similar as the base layer for the GIS

    module? Google Map provides a lot of

    base data for India out of the box and IMS

    application can take advantage of the

    base data and can provide the capability

    to create/view/update/delete necessary

    layers and provide all functionalities

    referred to in the RFP (and later integrate

    to whatever GIS platform, ESRI ARCGISetc., the government might already have

    if required at all). Essentially we are trying

    to clarify if ESRI product ArcGIS 9.3 Server

    based GIS is an absolute requirement for

    this project, or can vendors propose

    comparable/better mapping capability

    based on Non-ESRI platforms like

    Google Maps?

    IMS software working on Non

    ESRI platform will be accepted.

    Google map or other suitable

    base layer is accepted providedIMS meets other specifications.

    mailto:[email protected]:[email protected]:[email protected]
  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    2/44

    2119

    Annexure

    III 1.2

    Technical

    Specifications forIncident

    Management

    Application

    Operational Requirements for

    Incident Management System (IMS)

    OPEN SOURCE products can be

    downloaded for free from public domain

    and customized but are restricted to

    contributors/volunteers for any

    enhancement to OPEN SOURCE product.

    Can a bidder just download an OPEN

    SOURCE Incident Management Solution

    from some public domain website and

    propose customization to meet GSDMA

    needs? Or does GSDMA want an IMS

    product provided by software companies

    who specialize on providing IMS solution

    to various government agencies

    worldwide?

    Open source IMS software will

    not be accepted. Pre-

    qualification requirement is

    that IMS software should have

    been successfully implementedat least at one location: GSDMA

    expects that OEM would be

    responsible for proper

    functioning and upgradation of

    the system for total operational

    period of 5 years

    3 83 EOC Connectivity and AlertMessage Flow

    Alert messages will be received oncomputer or mobile or on both?

    Alert messages will be delivered

    on various media including

    Computer (e-mail) /Mobile(SMS or Voice mail) in addition

    to Alert and warning towers

    483

    GSDR-ICTS will (subsequently)

    cover all parts of the State using

    multiple communication

    technologies (as a redundancy

    measure), in suitable topology,

    which will be based on open

    standards having scalability,

    flexibility and upgradability

    Please mention the different type of

    networks for communication in order of

    priority in case disaster happens

    Information already included in

    existing RFP (Please refer page

    97)

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    3/44

    5 112 Incident Management Application Please describe the desired unifiedcommunication interface

    Universal communication

    interface (using soft clients and

    VoIP switching matrix) to bridge

    VHF networks of: Police, Fire

    brigade, National Disaster

    Rescue Force (NDRF) and

    Revenue department operating

    in 136 to 174 MHz frequency

    band. Provision is to be made

    for 2 (two) R F channels per

    network and 2 VoIP channels on

    MPLS-VPN and VSAT (total 12

    ports)

    6112

    ScheduleII Annex I

    Section

    1.3.5

    Incident Management Application -

    Emergency Response Vehicle

    Need to describe the interfacing network

    available with ERV. To transfer videoinputs from Disaster sites to Control

    Room using Mobile applications or if ISP

    network is not available. Please confirm

    Only long distance broadband

    connectivity available at ERV is

    via VSAT link (Inmarsat BGAN

    service is not permitted at themoment in India, but will be

    made available once permission

    is granted by DoT). Hence video

    inputs are to be transferred on

    VSAT link.

    7112

    Please describe the prediction data

    required from agencies in detail

    Prediction data received from

    various agencies will include

    probable rain fall rate and area

    over which rain is likely, cyclone

    speed and likely landfall timeand location, height of waves in

    case of Tsunami, flood levels

    and water release rates from

    CWC and irrigation department

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    4/44

    8116 Alert and warning system

    Do we need to integrate Alert and

    warning system real time with Incident

    Management Application?

    Yes, Read page 117 "The

    warning message controller is

    to be installed at GSEOC

    Gandhinagar with back-up

    controls at concerned DEOCs"

    9118 IMPS

    Please describe whether LDAP based

    directories are available now? The system

    should provide mechanisms for

    provisioning user identities and

    relationships among multiple LDAP-based

    directories

    LDAP based directories are notavailable at present. Required

    information on user identities

    and relationships will be

    provided to the operator.

    10119 Incident Management Application

    Asset Management - Please confirm that

    it is linked to offline tracking of assets

    No. Asset tracking is to be done

    on dynamic basis (even if the

    asset is on the move).

    11

    120 Incident Management Application

    Historical context on GIS layer. Please

    describe the exact need

    Required information is

    available on same page (page

    number 120). Historical data

    will be provided by GSDMA.

    12122

    IMA - The system with ability to be

    receive, compile, store and analyse

    data on rainfall, flood, water level,

    wind speed and direction, earth

    shake, temperature, cyclone

    progression provided by various

    Government / Non-Government

    agencies will be preferred

    Need to have integration real time or

    offline. Do we need prediction algorithms

    in built in the system

    Integration on real time basis is

    essential. However prediction is

    not included in the system

    requirement.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    5/44

    13116 1.8 VHF Radio Systems

    The RFP calls for VHF network it is not

    clearly stated whether the system should

    be analogue or Digital and what standard

    is to be adopted, its suggested to choose

    the Digital Mobile Radio ( DMR ) standard

    as this is an European Telecommunication

    Standards Institute ( ETSI) open standard

    The VHF radio network is

    expected to consist of a 25

    Watts base station operating

    from ERV and handheld radios

    used by first responders at

    disaster sites. Requirement is

    for reliable, rugged system;

    hence choice for analog or

    digital radio is left to the bidder.

    Please note that handheld radio

    is expected to have a range of

    5.0 Kilometers to operate with

    base station equipped with 40

    feet high mast and 25 watts RF

    power. It is a closed user

    network hence standard is

    immaterial.

    14116 1.9

    Alert & Warning

    system

    It is not mentioned whether the siren

    should be mechanical or Electronic. It is

    suggested that the siren should be

    electronic sirens as these can be operated

    from standby DC power source, whereas

    the mechanical siren will require AC

    power

    Siren can be either Electronic /

    electricity driven. Suitable

    power supply is to be provided

    by the operator. Demonstration

    of functioning of remote siren

    unit is to be made during NCNC

    Demo

    15134 18

    High Frequency

    Transceiver

    The deployment and location of these are

    not clear. It is important to know the

    exact location for proper antenna designand type of antenna required to be

    specified

    High frequency transceiver is

    part of ERV and will be installedat disaster site.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    6/44

    16136 1.4

    Operation of the

    System

    As the VHF system has to handle voice

    and data, its suggested that the RFP

    specifically as for DMR Radios. The DMR

    radios is an open standard radio that

    works on TDMA platform and allows for 2signaling channel on a single frequency.

    VHF radios are meant for

    switching sirens on / off and for

    transmission of voice broadcast

    messages. Switching of sirens

    will be through DTMF tones in

    voice band and pure data

    transmission is not envisaged.

    As such Analog radios will serve

    the purpose.

    17248 4

    Systems installed

    in Emergency

    Response Vehicle

    Is there a requirement for GPS based

    Vehicle location system, where by the

    location of the vehicle can be monitored

    at the DEOC

    Yes

    18

    113 1.5

    For portable VSATs the modem has

    to be inside the chassis of the

    antenna itself with weatherproofing. Is our understanding

    correct?

    For portable VSATs the modem has to be

    inside the chassis of the antenna itself

    with weather proofing. Is ourunderstanding correct?

    The modem can be in a

    separate weatherproof chassis

    if the design permits. However

    overall weight limit of eachpackage and number of

    packages remains same.

    19114 1.5

    Weight per package to be less than

    30 kgs. However, vendor may offer

    systems of higher weight with

    suitable modifications for ease of

    carrying (backpack or other

    methods) it in the field.

    Pls specify the mentioned weight includes

    RF also.

    Yes. The weight includes all

    components in the respective

    package.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    7/44

    20115 1.7

    The remote installations are

    proposed to be connected through

    VSATs on GSDMA/GOG's own hub,

    with an alternate provision toswitch over to share hub owned by

    another government agency.

    Details regarding shared hub owned by

    another government agency are needed.

    The alternative arrangement is

    still not in place. However

    responsibility to t ie-up with

    government agency for this

    purpose as well logistics for

    interconnection will be

    GSDMA's responsibility. Details

    will be provided as and when

    finalized. The bidder need not

    make any financial provision for

    this arrangement.

    21115 1.7

    The network should have the

    capability to work with any satellite

    located in Geostationary Orbit arc

    from 55 E to 115 E and with any

    satellite visible from India.

    Which satellite will be used for thenetwork envisaged for GSDMA and what

    are the satellite parameters for the same?

    The RFP states any INSAT satellite from

    55E to 115E. Different satellites have

    different parameters and RF and

    bandwidth sizing is dependent on these.

    The satellite capacity will be

    provided by Antrix on available

    satellite after installation and

    commissioning of the hub. The

    location arc of the satellite is

    indicated to ensure antennatracking capabilities. RFP has

    included specifications for

    antenna and RF components

    that can support transmission

    up to 45.0 Mbps carrier on any

    satellite even with minimum

    G/T. GSDMA network

    requirement is only around 5.0

    Mbps outroute carrier as such

    no difficulty will be experiencedfor operation with any satellite.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    8/44

    2282 85/82 Integrate GSDR-ICTS with GSWAN

    Page 85 says that operator shall integrate

    GSDR-ICTS with GSWAN, whereas page 82

    states that Gujarat State Wide Area

    Network (an e-Governance infrastructure)

    would be linked to/ Integrated with GSDR-

    would be done by GSDMA.Pls clarify. Isthis integration under bidders scope

    The operator is responsible for

    integration with GSWAN and

    has to ensure proper interface

    and routers, LAN cables etc.

    GSDMA is responsible for laying

    OFC link between SEOC andGSWAN NOC.

    23The operator shall also

    interconnect the SDC with GSDR-

    ICTS.

    pg 85 says that The operator shall also

    interconnect the SDC with GSDR-ICTS,

    whereas page 82 states that State Data

    Centre (SDC) will be integrated with SEOC

    would be provided by GSDMA.Pls clarify.

    Is this integration under bidders scope

    or GSDMA??

    OFC/GB Ethernet would be

    provided by GSDMA. The

    operator is responsible for

    integration with mail and data

    servers to be installed by the

    operator in SDC

    2492 Telephone Network

    Who will provide telephone network at

    SEOC, DEOC, ERC, ESF, and TEOCs? Is it

    under bidder's scope?? Pls clarify

    Telephone links at SEOC to

    operate with GSWAN, SICN areprovided by GSDMA. Operator

    has to provide 2 X E1 ISDN links

    (60 lines) for call centre and

    other users at SEOC. Telephone

    links / wiring at ERC, DEOC and

    TEOC will be provided GSDMA.

    Operator will not be

    responsible for telephone lines

    at ESF offices.

    25102 1.3.3

    GSDMA connectivity at vidan

    sabha, SICN,

    GSWANSOC,SDC,GIDM,Statistical

    bhavan, Gandhinagar SHQ

    Hope SEOC would be connected to vidan

    sabha, SICN,

    GSWANSOC,SDC,GIDM,Statistical bhavan,

    Gandhinagar SHQby GSDMA. Pls clarify.

    Hope this would be under GSDMA Scope.

    Page 263 - "WidebandConnectivity between SEOC and

    GSWAN SOC, SDC, GIDM

    through OFC / GB Ethernet /

    leased lines and telephone

    cables for EPABX connectivity

    with SICN at Vidhan Sabha,

    Gandhinagar".

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    9/44

    26103

    SEOC integration with

    NICNET/National network

    backbone

    Is it under bidder's scope? Pls clarify. If

    yes, what is the bandwidth required?

    The connectivity is not part of

    operator's responsibilities.

    27 94 ESFs at State Head quarters, (14)and ESFs at District Head quarters

    As per page 20, Important Government

    offices (Including 14 ESF) at SHQ will be

    connected for voice and data

    communication with SEOC on SICN which

    would be provided by GSDMA. Pls clarify.

    Will this be under bidders scope? Or

    GSDMA?

    These offices are

    interconnected via GSWAN andthis is not part of operator's

    scope of work

    2894

    The National EOC (NEOC) and

    national level ESF (14) agencies

    Pls clarify. Will this be under bidders

    scope? Or GSDMA?

    This is not part of operator's

    scope of work.

    2995

    TEOC's and ESF for 20 locations on

    MPLS VPN connectivity

    Pls clarify. Will this be under bidders

    scope? Or GSDMA?Yes

    30General

    VSAT connectivity required at

    GIDM

    Is VSAT connectivity required at GIDM?

    Hope GIDM is same as DMI. Pls clarify

    VSAT is required at GIDM.

    Disaster Management institute(DMI) is same as GIDM.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    10/44

    31General

    MPLS bandwidth required at

    DEOC's,ERC's,TEOC's.

    What is the MPLS bandwidth required at

    DEOC's,ERC's,TEOC's. is it 128 Kbps or 1

    Mbps. Pls clarify. Some place it says 128

    Kbps and some places it says 1 Mbps

    Page 92 - Horizontal and

    vertical connectivity between

    SEOC, DEOC, ERC, GIDM, TEOC,

    ESF(s), State Data Center, SICN

    and other nodes on GSWAN

    and public telecom based

    GSDR-ICTS backbone (MPLS-

    VPN). The connectivity on

    MPLS-VPN between SEOC and

    DEOCs will be at 1 Mbps rate

    and between District and TEOC

    will be at 128 Kbps rates.

    Horizontal connectivity means

    connectivity at a particular level

    (state capital or district

    headquarter) for exampledistrict EOC and ESF

    departments in the same

    district. Vertical connectivity

    means connectivity across

    levels for example SEOC and

    DEOC.

    32General

    Is VSAT connectivity required at

    TEOC's?

    Is VSAT connectivity required at TEOC's?

    Pls clarify

    Not required. (please refer to

    page 97 of RFP)

    33General MPLS port sizing at SEOC

    What should be central MPLS port sizing

    at SEOC? Pls suggest

    16.0 Mbps port size for MPLS-VPN at SEOC will take care of

    intercommunication between

    SEOC and other nodes.

    34General

    MESH or Hub spoke topology for

    MPLS

    Should we provide MESH or Hub spoke

    topology for MPLS? Pls suggest

    The vendor needs to decide the

    best topology that will be

    reliable and meet bandwidth /

    communication requirements

    and will be cost effective.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    11/44

    35General Scope of the bidder

    Hope on the connectivity front, MPLS has

    to be provided at SEOC,DEOCs,ERCs,

    TEOCs along with broadband too. Only

    this is the connectivity scope of the

    bidder. Pls suggest if any other

    connectivity would be under bidder

    scope?

    List of deliverables that are part

    of operator's responsibilities

    are at Schedule XIII (page 254

    onwards)

    36133

    -

    134

    17VHF Hand Held

    Radio set

    Minimum range for handheld should be

    5KM. Its possible with VHF Repater 50

    watt or VHF Portable repeater.

    Please need confirm requirment of

    repeater is not mentioned.

    No repeater is envisaged.

    Please refer to response to

    query number 13 above.

    37133 18

    Radio Frequency

    transceiver base

    station with

    25Watt poweroutput.

    With DMR Base station/mobile radio set

    will fufill this data & voice

    communication.

    Please confirm the what type datacommunications going do.

    Only voice communication is

    necessary. Analog radio will

    suffice. However operator can

    offer DMR.

    38134 23

    Voice

    communication

    with multiple

    redundancy

    DMR VHF Repeater/base station will have

    an IP port for data & voice over IP

    communication network. Please confirm

    will IP port will able to connect directly to

    VSAT or need any gate way.

    Connectivity with VSAT is

    expected via Universal

    Communication interface at

    ERV. Hence DMR repeater with

    IP port is not essential.

    39136 1.5

    Alert/ Warning

    Announcement

    System

    Hytera Digital Repeater with 50 watts

    power will cover maximum area base on

    the topography.

    As already explained above

    repeater is not necessary for

    required coverage area.

    40 259-

    2607

    Equipment and

    systems at each

    ERV

    VHF base station for local network with

    one base station and 10 Handheld sets:

    Please confirm base station is 50 Watts

    repeater / simple 25 watt static

    set/mobile set.

    Base station with 25 Watts

    power output meets RFP

    requirement. Operator can

    offer higher power base station

    including sufficient back-up

    power system

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    12/44

    41116 1.8

    Please confirm Its VHF base station or

    Repeater ( In vehicle Mount) & whats

    power output.

    Hytera having this solution with 50 watts

    repeater or 10 watts Portable repeater to

    carry any where remote location

    operation.

    Base station with 25 Watts

    power output meets RFP

    requirement. Operator can

    offer higher power base station

    including sufficient back-up

    power system

    42Call Center

    For resilience and redundancies, shall we

    offer inbuilt in a cloud solution, than an

    on-premises solution? Building similar set-

    up on a captive manner involves heavy

    capital outflows, which not only bring

    with them proprietary HW/SW elements,

    but also the complexity of inter-

    operability and the need for specialized

    and skilled manpower to make them work

    on a perpetual basis. Pl suggest.

    It is felt that cloud based

    solution will not meet reliability

    and up-time requirement for

    Disaster Management

    applications. However bidder is

    free to offer any other solution

    for the call centre that can

    meet operational and reliability

    requirements of RFP.

    4392 2.2

    Connectivity and

    Internetworking

    requirements

    Horizontal and vertical connectivity

    between SEOC, DEOC, ERC, GIDM,

    TEOC, ESF(s), State Data Center,

    SICN and other nodes on GSWAN

    and public telecom based GSDR-

    ICTS backbone (MPLS-VPN). The

    connectivity on MPLS-VPN between

    SEOC and DEOCs will be at 1 Mbps

    rate and between District and TEOC

    will be at 128 Kbps rates. Horizontalconnectivity means connectivity at

    a particular level for example

    district EOC and ESF departments in

    the same district. Vertical

    connectivity means connectivity

    across levels for example SEOC and

    DEOC

    Instead of using the MPLS network for the

    Telecom functionality, we propose to

    deploy hosted Telephony to reach out to

    all the required emergency response

    functionaries, in real time basis, in

    compliance with the defined call flow.

    No change

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    13/44

    44142 1.3 b

    UniversalCommunication

    Interface

    The system should provide facility

    to interface communication

    technologies mentioned above for

    mainly voice intercommunication.

    The bidders system should include:

    Interface conversion cards /software systems to bring 4

    different systems on a single VoIP

    platform

    VoIP gateway

    These together should demonstrate

    that internetwork calls can be set-

    up as required by the disaster

    management authority

    Instead of using VoIP as a technology for

    all voice calls, hosted Telephony will bedeployed and the needed integration to

    the universal communication interface

    shall be enabled using APIs.

    No Change

    45250

    Call centre

    operations and

    Alert and warning

    system

    Access to all 60 incoming lines from

    any agents position

    Automatic call distribution system

    with override facility for manager

    Recording of all incoming and

    outgoing calls

    Fall back connectivity from

    redundant sources

    Facility to issue warning messages

    Capability to issue SMS and Voice

    mails to government officials and

    other stake holders

    To be enabled using a hosted Telephony

    platform to meet all these requirements

    with an asset-lite mechanism.

    No Change

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    14/44

    46255

    Schedule

    II Annex I

    Section

    1.3.5

    Call centre

    operations and

    Alert and warning

    system

    Call centre with infrastructure

    (workstations, phones, furniture

    etc.) for 30 agents and 60 ISDN

    telephone lines from Telecom

    service providers with suitable

    EPABX for call handling /

    distribution etc.

    b. Interactive Voice Response

    system

    Call handling and distribution / IVR /

    Business controls to be deployed in the

    Hosted Telephony platform, than in the

    EPABX on premises.

    Not essential but can be offered

    by the bidder

    47Call Center

    Ability to monitor the status of various call

    centre agents located anywhere in any

    geography and manage the operational

    efficiencies is required to be more

    productive. Pl consider.

    Not essential but can be offered

    by the bidder

    48 Call Center

    Feature to barge into any of the live calls,

    by the admin, to ensure needed checksand balances is necessary for better

    functioning. Pl confirm.

    Not essential but can be offeredby the bidder

    49Call Center

    We recommend the feature - Readymade

    reports and also the ability to generate

    reports based on user defined criteria on

    all Call stats / agent performance metrics

    any time and ability to schedule

    predefined reports at defined regular

    intervals to designated email IDs. Pl

    consider.

    Not essential but can be offered

    by the bidder

    50Call Center

    We recommend the ability to integrate

    any of the web applications / data bases

    with the Cloud Agent application and

    agility/ flexibility to deploy, needed call

    flows / IVR changes on the fly.

    Not essential but can be offered

    by the bidder

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    15/44

    51Call Center

    We recommend the ability to listen to any

    conversation recording through a browser

    log-in with Internet connectivity from

    anywhere, any of the calls, as call

    recordings are hosted and can be

    accessed through proper log-in

    credentials by the authorised personnel.

    Call recordings can be listened within

    minutes of the call completion. These

    features are essential to be part of DR

    Management Process.

    Not essential but can be offered

    by the bidder

    5292 2.2

    Connectivity and

    Internetworking

    requirements

    Connectivity between SEOC, DEOC,

    ERC, DMI, and disaster location(s)

    using VSAT network at nominal 512

    Kbps rates that is upgradable to 1.0

    Mbps from affected districts EOCs

    and ERVs

    What is the nominal Outbound and

    Inbound data rate? As Video conference

    too will be using the VSAT (Star network)

    as a medium, it would be better if the

    nominal rates can be defined or may be

    left to the bidder as per their design

    Inbound data rate will be 512.0

    Kbps (1.0 mbps if approved by

    DoT). Outbound rate will be in

    the range of 3.0 to 5.0 Mbps

    (already specified in RFP)

    53114 1.6

    Emergency

    Response Vehicle

    (ERV)

    ERV are vehicle mounted systems

    that can be relocated to wherever

    required in response to an

    emergency incident. .........

    Is it mandatory to propose vehicle

    mounted DSNG antenna system or can we

    propose Flyaway VSAT antenna system?

    Flyaway VSAT not allowed

    instead of ERV mounted VSAT.

    There is a separate provision for

    portable VSAT systems.

    54 260 #7 ERV ERV

    All weather CC TV camera for day

    and nightoperations with PTZ operation

    capability (1)

    Need Clarity on location of Cameras. # No

    of Cameras # Days of Recording Required# Bandwidth and Switching Locations. No

    of Cameras required in each location,

    Very clearly mentions 1 camera

    in the ERV Vehicle. Recording

    for up to one week is sufficient.

    The video output of the camera

    will be transmitted to SEOC /DEOC via VSAT link which will

    operate at 512 kbps, so

    bandwidth is to be adjusted to

    suit capacity of the link.

    Switching location will be SEOC.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    16/44

    55263 Note

    SEOC building at Gandhinagar is

    equipped with mains and back-up

    generator power supply ,

    general air-conditioning, furniture

    and fixtures in some of the

    rooms as described in RFP,access control and CCTV system for

    security and PA system

    Need Clarity to understand, if all the

    cameras need to be displayed in main

    command control room. Also request

    information on Make/Model of system

    present in SEOC Building.

    Security system is not part of

    operator's responsibilities.

    56121

    Section

    1.2,

    Clause

    1.17

    TechnicalSpecifications for

    Incident

    Management

    Application

    The system should support:

    Integration with ESRI ARCGIS

    server 9.3 to store, manage and

    analyse spatial data, including

    interoperability with the ARCGIS

    Server Web Application

    Development Framework (ADF).

    Advanced spatial data types

    representing geometries such as

    points, lines, and polygons and

    many functions and features that

    interoperate with these data types.

    All Vendors should ensure that

    proposed GIS platform (s) comply

    to OGC standards such as WMS,

    WPS, WFS, WCS etc.

    Will GSDMA accept IMS software which

    uses non-ESRI platforms like Google Map

    or similar as the base layer for the GIS

    module? Google Map provides a lot of

    base data for India out of the box and IMS

    application can take advantage of the

    base data and can provide the capability

    to create/view/update/delete necessarylayers and provide all functionalities

    referred to in the RFP (and later integrate

    to whatever GIS platform, ESRI ARCGIS

    etc., the government might already have

    if required at all). Essentially we are trying

    to clarify if ESRI product ArcGIS 9.3 Server

    based GIS is an absolute requirement for

    this project, or can vendors propose

    comparable/better mapping capability

    based on Non-ESRI platforms likeGoogle Maps?

    Refer Query 1

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    17/44

    5742

    Clause

    3.2.1 (3 -

    D)

    Pre Qualification

    Criteria

    The bidder must have experience of

    implementing at least one project

    related to:

    Emergency Operations Centre or

    Network Operations Centre

    experience Mission Critical, WAN,

    LAN, Security, managing E-mail

    services, Internet services etc., for

    24x7 operations ) in Projects with

    over 50 WAN nodes for Defence or

    Finance organization

    The bidder must have experience of

    implementing at least one project related

    to:

    Emergency Operations Centre or Network

    Operations Centre experience Mission

    Critical, WAN, LAN, Security, managing E-mail services, Internet services etc., for

    24x7 operations ) in Projects with over 50

    WAN nodes for Defence/Finance

    organization/Central or State Government

    Suggested change Accepted

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    18/44

    58132

    Clause

    1.4

    Components and

    capability

    requirements for

    ERV

    Chassis To provide minimum

    operational are 5 meters long and

    2.4 meter wide, diesel vehicle

    chassis, or custom trailer.

    For 2400mm wide internal optional area,

    the outer side body will become 2500mm

    (approximately). This width may not be

    permitted by RTO rules. Request to limit

    the internal operational area width =

    2040mm for which the outer width willbecome 2150mm (Standard outer width

    of LCVs in the market)

    For internal operational area

    length=5000mm and length to be kept

    free for 10 KVA Diesel Generator (say

    1000mm) the overall loading length on

    the chassis required will be 6000mm. For

    this requirement one will have to go for

    Medium/Heavy Commercial Vehicles.

    Maneuvering such type of Heavy Vehicles

    on village rough roads may face problems.

    Request to limit the Operational area

    length = 4000mm. With Generator space

    this will need chassis length = 5000mm

    (approximately). For this, standard chassis

    length of 5000 mm in many Light

    Commercial Vehicles will be sufficient.

    Maneuvering of Light Commercial vehicles

    on village rough roads will also be easy.

    Suggested changes not

    accepted. The generator set is

    expected to be mounted below

    the chassis and use of heavy

    vehicle is envisaged. These

    vehicles can only offer required

    ground clearance. ERV is not

    expected to enter narrow

    village roads but be at suitablelocation at disaster site.

    59132

    Clause

    1.4

    Components andcapability

    requirements for

    ERV

    How many persons are required to travel

    along with ERV in Driver Cabin? Normally

    there is a provision for Driver + 2 persons

    in LCV type of vehicle which are good for

    such applications

    Assumption is correct.

    60132

    Clause

    1.4

    Components and

    capability

    requirements for

    ERV

    Is the facility of Air conditioner (working

    on vehicle engine) required in Driver

    Cabin for the persons traveling?

    AC in driver's cabin is not

    essential

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    19/44

    61132

    Clause

    1.4

    Components and

    capability

    requirements for

    ERV

    How many persons are required to seat

    inside the ERV during operation.

    Accordingly the seating arrangement and

    Air- conditioning capacity can be

    provided.

    Maximum of 7 (2 operators and

    5 Government functionaries

    responsible for DM activities)

    are likely in the internal

    operational area of the vehicle.

    62132

    Clause

    1.4

    Components andcapability

    requirements for

    ERV

    Is there any specific type of Airconditioner required in operation area i.e.

    window AC, Split AC etc

    No

    63113

    Portable VSAT

    System

    Please indicate what are the peripherals

    required to be configured with portable

    VSAT terminal?

    Ref page 113-114. Kindly detail

    the peripherals being asked

    here

    64113

    Portable VSAT

    System

    Do we need to supply

    Laptop/VC/VOIP/UPS per configured/pre

    wired fitted in a compact rack with

    transportable/flyaway terminal?

    No Laptop or VC is necessary

    with portable VSAT. However at

    least 2 Ethernet ports (RJ 45)

    and at least one telephone port(RJ-11) should be provided. A

    back-up battery and 500 VA

    generator set for power back-

    up is already specified in the

    RFP.

    65113

    Portable VSAT

    System

    There is no mention of generator

    requirement in case of Transportable

    terminal for operation at remote/disaster

    location.

    Generator requirement is

    already indicated (refer page

    number 131)

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    20/44

    6617

    Data on disaster parameters,

    information received from

    organizations responsible for

    disaster predictions such as

    Meteorological Department,

    Central Water Commission, State

    Irrigation departments,

    International weather and

    earthquake information portals as

    well as organizations responsible

    for Tsunami prediction etc. in

    addition to visual data from

    disaster sites, will be transferred to

    operations centre for processing,

    analysis and archiving.

    a) Kindly specify the protocols, interface

    and format of the data

    b) Is the data going to be real time or

    historical. If historical then what shall be

    the frequency of collection.

    c) Is the data going to be push or pull from

    various sites

    d) What is the volume of data that shall

    be transferred to operations centre for

    processing

    e) What is type of processing to be doneon these types of data at GSDR-ITCS Site

    f) What is the back-up policy of the data

    g) What is the archival policy

    h) All the above questions need to be

    answered to size the hardware

    a) As of today data is received

    in text format. The format may

    change in future, however

    details will be shared with

    operator as and when available

    from organizations responsible

    for predictions

    b) It will be real time. Historical

    data will be made available by

    GSDMA (normally once in a

    quarter)

    c) Data will be normally push

    type. However any changes will

    be notified to the operator

    d) Volume will not be significant

    (in the range of few Mbytes)

    e) Incident managementsolution is expected to analyze

    data for DSS. Data is also to be

    archived for future reference

    f) On line back-up should be

    available for a period of up to 6

    months and subsequently same

    should be stored on long term

    memory g) Archivival should be

    for a long period for use as

    historical data and to be doneon CD or similar devices

    6719 Pt 1.2.7

    Back-up power supply (UPS) and

    diesel-generator of adequate

    capacity (excluding mains power

    supply made available by GSDMA,

    however all operating costs have to

    be borne by the operator)

    It is requested that operating costs

    related to diesel be borne by the client on

    actuals as the same is very difficult to

    predict. The operator does not have any

    control on the prices. Kindly confirm the

    same.

    No Change

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    21/44

    6819 Pt "c" Connectivity

    It is assumed that bidder's responsibility is

    till keeping his equipment up for

    connectivity using GSWAN and Public

    Telecom Infrastructure. Availability of

    both these mediums is the responsibility

    of the client. Kindly confirm the same.

    Yes

    6919 1.2.8 Available Resources

    Is SDRN information on demographics,

    livelihood activities, shelters etc data

    available in Lat/Long? What is the file

    format of the data?

    Can we know number of attributes with

    each layer?

    Yes

    7020 Pt 1.2.9

    The SEOC infrastructure facilities

    shall include, inter alia, thefollowing system elements:

    Audio / Video conferencing; and

    SEOC Building Management and

    security system

    a) Building Management includes

    Centralised Airconditioning, Fire Alarm

    and Smoke detection. Is bidder expected

    to provide and maintain the same. If yes,

    then please provide the specifications

    alongwith BOQ.

    b) Please elaborate on Security System

    and give specifications of the same

    alongwith BOQ.

    Split type Air-conditioning has

    already been provided in all

    rooms of SEOC. The vendor is

    expected to operate, maintain

    and pay for electricity charges

    for the same

    Access control and CCTV system

    for security will be provided by

    GSDMA - ref page 263

    7121

    Pt. 1.2.9

    The Operator should ensure that all

    communication network elements

    and systems meet the guidelinesand regulations set by GoG and the

    relevant regulatory authority

    It is requested that the clause be

    amended as "The Operator should ensure

    that all communication network

    elements(except GSWAN and Public

    Telecom Network which is client'sresponsibility) and systems meet the

    guidelines and regulations set by GoG and

    the relevant regulatory authority

    Suggested change is accepted

    will be included in corrigendumor revised RFP

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    22/44

    7222 Pt. 1.3.4

    These short listed Bidders will be

    asked to demonstrate performance

    of various applications / software

    offered for the Project at No Cost(to GSDMA) and No Commitment

    (NCNC) for placement of orders

    even in case of successful

    demonstration of capabilities of

    offered systems

    a) Pls elaborate in detail the POC need to

    be done i.e what all shall be covered

    under POC

    b) What shall be duration of the POC

    c) What shall be the location of POC as

    arrangements need to be made for the

    same in terms of equipment and moving

    them to the required location.

    a) Details of NCNC demo are

    given at clause 1.3, Annexure-

    IV, page number 141

    b) The demo is expected to

    show functionality of various

    systems and can be completed

    within one working day

    c) POC has to demonstrated at

    Gandhinagar. GSDMA will

    provide infrastructure support.

    However any additional

    requirements of the bidder will

    be mutually discussed and

    agreed to

    7328 Pt a

    where a Consortium consisting of

    two companies A and B are the

    Selected Bidder, then the Service

    Agreement will have to be

    executed by each of A and B as

    parties to the Service Agreement.

    One of A or B cannot be a sub

    contractor to the other

    a) Can these A & B consortium partners

    have sub-contractors for technologies

    which are not their core businessb) For such sub-contractors, who shall be

    responsible for SLA, A & B both or the

    Lead Consortium member between A & B

    c) Can this sub-contractor of A&B be a

    sub-contractor of another consortium

    C&D

    a) Yesb) Lead consortium member

    shall be responsible for the

    subcontractors

    c) Yes

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    23/44

    7484 1.2

    The Operator shall obtain all

    necessary approvals/ clearances

    from concerned authorities /

    departments, as applicable

    It is requested that the client takes the

    responsibility of obtaining clearances

    from the departments as it shall be

    processed faster

    a) GSDMA has already obtained

    VSAT service license and

    allottment of satellite spectrum

    from Antrix

    b) GSDMA has taken necessary

    clearnace from concerned

    departments for right of the

    way to lay OFC / telephone

    cables between SEOC, SDC,

    SICN and GIDM and has laid the

    cables c)

    GSDMA will extend necessary

    support to operator to get

    wireless radio license in the

    name of GoG , well approval

    from DoT for integration

    between GSWAN and VSATnetwork and any other

    regulatory clearance that may

    be necessary

    7585 Pt. 1.4 (iv)

    The Operator shall be responsible

    for storage and security of material

    on receipt at the site

    It is requested that requisite space for

    storage alongwith A.C. be provided by the

    client

    GSDMA will attempt to provide

    covered and secure place for

    storage of equipment before

    installation, however it may not

    be guaranteed at all locations

    where operator will have to

    make own arrangements.Operator will have to employ

    security staff at each location

    where equipment is stored and

    also will have to take care of

    insurance against fire, theft etc.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    24/44

    7691 Pt c

    Expenses for consumables (eg:

    paper, ink cartridges, fuel etc),

    generator fuel /lubricant, electricity

    consumed at the POP (incl. AC).

    It is requested that expenses for

    consumables be treated on actuals.No change

    7791

    Pt ii - Manpower

    Charges

    This includes salary, travel, stay,

    communication and other out of

    pocket expenses, for manpower

    deployed at various locations

    including ERVs

    It is requested that manpower for the

    disaster site be owned by the client andall the expenses related to the same shall

    also be borne by the client. The bidder's

    manpower shall be working at locations

    which are not affected by the disaster.

    The bidder shall train the client identified

    manpower to handle equipment so that

    they can replace Field replaceable parts

    and take guidance from bidder's

    engineers remotely.

    No Change

    7891 Pt. 1.11

    The GSDR-ICTS project will have to

    be implemented within 6 months

    from the date of signing the Service

    Agreement

    As there shall be interaction with multiplevendors and integration with their

    products it is requested that the

    implementation time be amended after

    taking into consideration inputs from

    major vendors like ERV, VSAT etc.

    No Change

    7998 Pt 2.9

    The ERV should reach the assigned

    location from the time orders for

    movement are received, within

    travel time calculated @ an average

    speed of 50 KM / Hour (e.g. within

    4 hours when ERV has to travel 200

    Kilometers to reach disaster site).

    Above mentioned speed is

    applicable for normal and motor-

    able road conditions and time will

    be adjusted upwards in case of

    inferior road conditions.

    Will the time be adjusted upwards in caseof Traffic Jams or lower speed due to

    heavy traffic conditions?

    Suitable adjustment to time

    schedule will be made in case of

    genuine difficulties beyond the

    control of operator

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    25/44

    8099 Pt. 2.13

    Initial network will cover limited

    Talukas on pilot basis

    Please let us know how many Talukas on

    pilot basis. Will the project

    implementation time start after the pilot.

    RFP includes list of talukas (29)

    at Appendix F (page-80). Pilot is

    part of the project and runs

    concurrently.

    81101 Pt. 1.2

    SEOC building is provided with the

    main power supply through

    redundant feeders (two sources)

    from domestic electric distribution

    company. The building also has a

    Diesel generator of requisite

    capacity as a backup arrangement

    and it automatically takes over the

    load during interruption of the

    normal source.

    As per the statement it is assumed that

    whatever load is asked for, shall be

    provided by the client.

    Mains power of required

    capacity can be provided.

    However back-up generator

    capacity is limited to 125 KVA.

    82120

    1.3

    Technical Specifications for Incident

    Management Application.

    Operational Requirements forIncident Management System (IMS)

    Is the historical data on Disasters and

    resources available in digital format? Is it

    textual or with Lat/Long location. Arethese data sets complete?

    Historical data is available in

    textual format and Lat / Longinformation is available..

    83121 1.17

    Integration with ESRI ARCGIS server

    9.3 to store, manage and analyse

    spatial data, including

    interoperability with the ARCGIS

    Server Web Application

    Development Framework (ADF).

    Currently the version for ARCGIS server is

    10.2. Do we assume the latest s/w will be

    used for integration and apps

    development?

    Yes. Please Refer to response to

    query number 1

    84139

    Annex IV 1.1 Additional Details GIS System

    Approximately how many GB is Oil & Gas

    pipeline data? Is it available in GIS formatwith Lat/Long?

    The data is available in GIS

    format with Lat / long. Size of

    the data base will be intimatedwithin next 3/4 days.

    85139 Annex IV 1.1 Additional Details GIS System

    Can we assume that the administrative

    boundaries etc. are current?Yes

    86General

    We would like to know the number of

    concurrent users accessing the servers in

    SEOC

    Information is provided in RFP

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    26/44

    87General

    How many users will be there at each

    locations?

    It is difficult to exactly

    anticipate

    88General

    We recommend to get Complete Endpoint

    security suite instead of only Antivirus on

    workstations and Servers

    Bidder may provide security as

    suggested

    89General

    How the servers in DR server roomconnecting to core/ DMZ switch i.e. via 1G

    or 10G

    Bidder to decide as per design

    requirements

    90General

    Please mention minimum technical

    specification for Core, Access , DMZ

    switch along with backplane capacity

    Bidder to decide as per design .

    Performance requirements are

    already specified in RFP.

    91119-

    1221.17

    Incident

    Management

    System

    The system should support:

    Integration with ESRI ARCGIS

    server 9.3 to store, manage and

    analyse spatial data, including

    interoperability with the ARCGIS

    Server Web Application

    Development Framework (ADF).

    Advanced spatial data types

    representing geometries such as

    points, lines, and polygons and

    many functions and features that

    interoperate with these data types.

    All Vendors should ensure that

    proposed GIS platform (s) comply

    to OGC standards such as WMS,

    WPS, WFS, WCS etc.

    Please explain why integration with ESRI

    ARCGIS is required which is very specific

    brand please allow other globally

    accepted GIS software used in emergency

    management. If OGC compliant software

    should be used for the equal opportunity

    is that acceptable?

    You must be asking for producing OGC

    Certificate.

    Ref Query 1

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    27/44

    92119-

    1221.17

    Incident

    Management

    System

    The system should support Web-

    based administration tools to

    enable remote system

    management at any time or place

    Is it mandatory to have web admin or

    combination of web and desktop can also

    be used?

    Webbased application is

    necessary for remote access

    and operations through

    Internet (using wired or

    wireless networks). Any

    alternate solution to addressthis issue will be accepted.

    93119-

    1221.18

    Incident

    Management

    System

    The system should ensure

    comprehensive protection of web

    content and applications on back-

    end application servers, by

    performing authentication,

    credential creation and

    authorization.

    The System Is Mix of Client server

    architecture and web based Net viewerPlease elaborate

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    28/44

    94119-

    1221.2

    Incident

    Management

    System

    The system providing following

    facilities will be preferred:

    Instant messaging (chat) to

    converse virtually through the

    exchange text-, audio- and/or

    video-based information in realtime,

    Screen sharing, Shared electronic

    whiteboard, Online meeting

    management services to schedule,

    attend or view information about

    scheduled and finished meetings,

    Web conferencing with click-to-

    call on instant messaging contacts,

    instantly placing a telephone call orstarting a conference call from the

    instant messaging client,

    Integration of teleconferences

    and meeting rooms enabling

    participants to mute participants,

    raise and lower volume, or have the

    conference call them directly

    Are you looking like a web conference

    solution, this is standard web conference,

    do you think at time of disaster Web

    conference is a feasible alternate GSDMA

    would like to have ?

    No change in specifications,

    95119-

    1221.23

    Incident

    Management

    System

    The system with ability to automate

    publishing of drawings/plotted data

    to functional groups & agencies as

    well as for non-geospatial data such

    as documents, emergency plans,

    risk assessments etc. will be

    preferred

    Print Plot all the template and publishing

    is available for Geo Spatial Data. But in

    order to Automate the process the

    Workflow needs to be defined.

    Workflow will not help if the

    offered system doesn't have in

    built capabilities.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    29/44

    96 Connectivity

    Require the list of the locations with

    address, Bandwidth and Type of

    connectivity

    Information already included in

    RFP schedule XIII

    97 Connectivity Partner ScopePlease define the scope of Connectivity

    Partner in one page

    Please elaborate

    98 113 1.5

    For portable VSATs the modem has

    to be inside the chassis of the

    antenna itself with weather

    proofing. Is our understanding

    correct?

    For portable VSATs the modem has to be

    inside the chassis of the antenna itself

    with weather proofing. Is our

    understanding correct?

    Yes. However a solution with

    separate water proof enclosure

    for modem will be accepted in

    case it meets functional and

    weight criteria.

    99 114 1.5

    Weight per package to be less than

    30 kgs. However, vendor may offer

    systems of higher weight with

    suitable modifications for ease of

    carrying (backpack or other

    methods) it in the field.

    Pls specify the mentioned weight includes

    RF also.Yes it includes RF equipment.

    100 115 1.7

    the remote installations are

    proposed to be connected through

    VSATs on GSDMA/GOG's own hub ,

    with an alternate provision toswitch over to shared hub owned

    by another government agency.

    Details regarding shared hub owned by

    another government agency are needed.

    The proposal is under

    considerations and information

    will be provided to operator

    when finalised. Regulatory

    issues need to be addressed assuch bidder need not worry

    about this issue while

    preparation of the bid.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    30/44

    101 115 1.7

    The network should have the

    capability to work with any satellitelocated in Geostationary Orbit arc

    from 55 E to 115 E and with any

    satellite visible from India.

    Which satellite will be used for the

    netwrok envisaged for GSDMA and what

    are the satellite parameters for the same?The RFP states any INSAT satellite from

    55E to 115E. Different satellites have

    different parameters and RF and

    bandwidth sizing is dependent on these.

    Satellite spectrum will be

    allotted by Antrix as per existing

    regulations. It is not possible to

    indicate spectrum will be

    allotted on which satellite when

    VSAT network is commissioned.The arc specified covers all

    possible locations for INSAT

    satellites.

    Equipment specifications for

    VSAT network elements has

    already taken care of variations

    in satellite parameters.

    102112,

    141

    Specifications for the Incident

    Management System in general in this

    RFP as stated refers to four core

    capabilities. They are Collaboration/

    Communication, Planning, Response, and

    Recovery. But then it emphasizes more on

    creating/modifying custom web based

    dashboards. This is also repeated in page

    141 as a requirement for NCNC demo. We

    believe that providing dashboard views

    of various incident related information

    should be emphasized rather than

    creation/modification of the same, since

    that might become a particular

    product/vendor specific requirement

    No change in specifications.

    However bidder can explain

    reasons for offering different

    capabilities and advantages if

    any. The evaluation committee

    will give due considerations to

    products in case it meets major

    functionalities.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    31/44

    103 119

    In the Technical Specifications Annexure

    III Section 1.2 the RFP clearly describes a

    detailed specification of all the

    components that the IMS system should

    have. In Page 141 Section 1.3 (NCNC

    Demonstration) the RFP contains a list ofIMS capabilities for demonstration. The

    list for NCNC demo on Page 141 is

    somewhat different from Technical

    Specifications defined in page 119. We

    request that the list in page 141 for NCNC

    demonstration be modified/removed and

    the vendors be asked to demonstrate the

    IMS capabilities defined in the Technical

    Specifications Annexure III Section 1.2.We believe that this will eliminate all

    ambiguities and help the vendors and the

    government to assess and chose the

    correct product with required

    functionalities.

    Reconciliation between

    technical specifications in

    Annexure III section 1.2 of RFP

    and details of NCNDEMO will bemade and corrections will be

    issued in corrigendum

    Please note that technical

    specifications will prevail in

    case of any doubts /

    descrpancies.

    Final specifications for NCNC

    demo will be worked out on the

    basis of system offered byrespective bidder and will be

    finalised in consultation with

    the bidder.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    32/44

    104 118Annexure III

    Section 1.1, 1.1

    RFP states the need for 1,000 concurrent

    users. If this portal is going to be

    disseminating relevant information to

    general public during a real disaster, then

    people will be accessing this site from all

    over the world and the need forconcurrent users might become 10 or 100

    times higher. If vendors propose certain

    hardware based on the listed specification

    it might not sufficient to scale to such

    volume during a disaster. We will really

    like to know the KEY DIFFERENCES

    (Overlaps) between the IMPS and GSDMA

    Website.

    Portal will have only limited

    sections accessible to publicand overloading of system will

    be tolerated. Vendor has to

    meet required RFP

    specifications.

    105 118Annexure III

    Section 1.1, 1.4

    RFP states that system should support

    various JAVA Applications. Are there any

    particular applications that GSDMA wants

    to support? What about .NET

    applications? This clause might create a

    little confusion and we request that it be

    removed or wordings be changed to make

    it more generic and not platform specific

    Requirement is for services on

    mobile platform. Operator may

    offer suitable platform so that

    officials responsible for disaster

    management can access various

    software applications, alert

    messages etc.

    106 118

    Annexure III

    Section 1.1,

    1.5/1.6

    RFP states that system should support

    LDAP. Is GSDMA using Active Directory or

    something else as their directory structure

    in their domain? We will like to get a

    clarification to this Directory Server so

    proper integration and proper platform

    can be determined for this portal.

    As at present GSDMA has no

    directory services. Bidder has to

    offer the service to meet

    requirements of service

    specified in the RFP

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    33/44

    107

    Optional but Preferred Specifications for

    both IMS and IMPS are almost identical

    (e.g. Web Conferencing, IM, Screen

    Sharing, Whiteboard etc.) Generally

    specific products (e.g. Microsoft Lync

    Server, CITRIX GOTOMEETING, CISCOJabber etc.) are designed just for this

    purpose. Is it OK for bidders to pick any

    particular solution and perform

    integration with IMS and IMPS so the

    same is accessed by both systems? Or

    does GSDMA want the PORTAL solution to

    have a built-in provisioning for such

    capability?

    Bidder may choose any solution

    that meets operationalrequirements for IMS and IMPS

    mentione in the RFP. IMPS is

    expected to be independent of

    IMS.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    34/44

    108

    The GIS functionality has been specified in

    Section 1.2 Technical Specifications for

    Incident Management Application (Point

    1.17 page 121). Will GSDMA accept IMS

    software which uses non-ESRI platforms

    like Google Map or similar as the baselayer for the GIS module? Google Map

    provides a lot of base data for India out of

    the box and IMS application can take

    advantage of the base data and can

    provide the capability to

    create/view/update/delete necessary

    layers and provide all functionalities

    referred to in the RFP (and later integrate

    to whatever GIS platform, ESRI ARCGISetc., the government might already have

    if required at all). Essentially we are trying

    to clarify if ESRI product ArcGIS 9.3 Server

    based GIS is an absolute requirement for

    this project, or can vendors propose

    comparable/better mapping capability

    based on Non-ESRI platforms like

    Google Maps?

    Ref Query 1

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    35/44

    109

    OPEN SOURCE/Freeware products can be

    downloaded for free of charge from public

    domain and customized but they are

    restricted to contributors/volunteers for

    any enhancement. Can bidders download

    an OPEN SOURCE Incident ManagementSolution from some public domain

    website and propose customization to

    meet GSDMA needs? Or does GSDMA

    want an IMS product provided by reputed

    software companies who specialize on

    providing IMS solution to various

    government agencies worldwide?

    Ref query 2

    110

    1.3.1 General

    Specifications

    2. Remote

    Terminals

    2.5 Antenna system for ERVs should

    :

    Not weight more than 80

    Kilograms including Ku Feed

    Controller

    This may be please change to: Antenna

    system for ERVs should not weight more

    than 80 5 Kilograms including Ku Feed

    Controller

    Will make necessary changes in

    specifications as following:

    "Nominal weight of antenna

    may be les than 100.0 Kgs.

    Operator is responsible for

    proper installation of antenna

    system on ERV rooftop with

    necessary structural

    fortifications"

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    36/44

    111

    1.3.2.2 BUC (200

    Watts rating) and

    LNB for HUB

    Specifications PLL LNB:

    RF input Frequency Range:

    10.95 to 12.75 GHz

    There is no existing high stability LNB for

    the HUB which covers RX complete range:

    10-95-12.75GHz.

    One of the Sub bands needs to be define:

    a) 10-95 - 11.7GHz

    b) 11.7 12.2 GHz

    c) 12.2 12.75 GHz

    No change in specifications as

    system is expected to operate

    with any satellite during its

    operational life. Operator may

    ensure that LNB suitable to

    operate with satellite frequencyband are available as and when

    required (for example can have

    multiple LNBs to cover whole

    band and install suitable LNB

    and change in future if

    required)

    Please note that Specifications

    given in RFP are standard for

    products such as NORSAT KU-BAND PLL 1000HE

    112

    1.3.2.5 - BUC (4

    Watts) and LNB for

    Fixed Remotes

    Specifications - 4 W BUC

    Output Freq Range: 13.75 14.50

    GHz

    Input Freq 950 1450 MHz

    The input freq range corresponds to 500

    MHz of BW

    so Output freq. range may be please

    change to 13.75

    14.25 GHz and 14.0 14.5 GHz

    There is a mistake in

    specification for IF frequency

    range. This will be corrected in

    the corrigendum. Required IF

    range will be 950 - 2150 MHz

    113

    1.3.2.8 BUC (25

    Watts) and LNB for

    portable VSATs

    Specifications - 25 W BUCOutput Freq Range: 13.75 14.50

    GHz

    Input Freq 950 1450 MHz

    The input freq range corresponds to 500

    MHz of BW

    so Output freq. range may be please

    change to 13.75

    14.25 GHz and 14.0 14.5 GHz

    There is a mistake in

    specification for IF frequency

    range. This will be corrected in

    the corrigendum. Required IF

    range will be 950 - 2150 MHz

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    37/44

    114

    1.3.2.1 Hub

    Antenna(9 Meter nominal

    diameter)

    Environmental Specifications

    Operational Temperature -45.5C

    to 52C (- 40F to 125F)

    Operational within tracking

    accuracy for Wind speeds

    45 mph (72 km/h) Gusts to 65 mph

    (105 km/h)

    The operational temperature range asked

    is too low The Antenna comes with a

    special low temperature

    kit to support up to -30 C.

    The operational wind speed within

    tracking accuracy may please change to

    up to 95 Km/h.

    Suggested changes for

    operational temperature are

    accepted and will be included in

    corrigendum.

    However operational wind

    conditions will remain asminimal specifications. The

    Operator should offer the

    system suitable to meet

    required level of up time at

    Gandhinagar based on local

    wind conditions.

    115

    1.4 Components

    and capability

    requirements for

    ERV

    Specification of chassis: To provide

    minimum operational area 5

    meters long and 2.4 Meter wide ,

    diesel vehicle chassis, or custom

    trailer "Dimensions (within +/-

    10% )" :Overall dimensions

    7500mm X 2500 mm or more

    "Command Center operations

    area":5000 X 2400 X 1800 mm

    "Minimum Ground: clearance" :350

    mm

    The mentioned specifications of ERV are

    complied with only Defense Category

    Vehicle, which are not available for

    civilian purposes. None of the

    Commercially Available vehicle meet the

    specs. This may be please modify the

    specifications to allow

    civilian vehicle to be complied. Eg. Swaraj

    Mazda

    No change in specifications ofERV. Suitable vehicles are

    available for civilian purposes.

    GSDMA will issue an end user

    certificate and write to

    concerned authorities if a

    special permission is required

    to get suitable vehicle.

    1161.5 Portable VSAT

    system

    Vendors may offer 1 meter nominal

    diameter antenna

    The antenna required in Portable VSAT is

    a auto pointing antenna or is it a Manual

    antenna?

    Antenna should autopoint and

    autolock / track the satellite.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    38/44

    1171.2.6 Briefdescription of the

    project

    Communication between first

    responders such as police, disaster

    rescue forces, fire brigades that use

    wireless communication systems

    mostly equipment operating in

    Very High Frequency (VHF) bandand

    administrators on terrestrial or

    satellite based Very Small Aperture

    Terminals (VSAT), should be

    possible with Voice over Internet

    Protocol (VoIP) based

    unified communication system.

    Please clarify how this will be achieved.The solution is to use UniversalCommunications Interface

    system described in the RFP

    1181.5 Portable VSAT

    system

    A telescopic mast to mount

    wireless network antenna and

    electrical hoisting mechanism for

    the mast should

    be provided with the system.

    What should be the height of telescopic

    mast with

    portable VSAT system to install the

    Wireless antenna?

    The height of telescopic mast

    should be sufficient to provide

    local coverage up to 5.0

    Kilometers. The design is to

    provided access to first

    responders working within

    coverage area at disaster site.

    1192.2 Eligibility of

    Bidders

    The Bidder may be a Sole Bidder or

    a group of entities (Consortium),coming together to implement the

    Project. However, no Bidder

    applying individually or as a

    member of a Consortium

    (Member), as the case may be,

    can be member of another Bidder.

    Can a sole bidder or a member of a

    consortium be a service provider to one

    or more other bidders or consortiums?

    For example, if company A is a bidder,

    can Connectivity Service Provider to

    Company B and Consortium C?

    Also can a service provider provide

    network services (MPLS, VSAT, etc.) to

    multiple bidders?

    Sole bidder or a member of the

    consortium can provide servicesto other bidders only in case

    such a bidder (service provider)

    is a licensed Telecom Network

    Operator and offers these

    services to other bidders as per

    license conditions.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    39/44

    120

    SCHEDULE IX

    PENALTIES

    (DURING

    IMPLEMENTATION

    AND OPERATIONS)

    Penalties during the Operation and

    Maintenance

    Phase

    Penalty is suggested to be per site 1% for

    every 1% drop in uptime beyond 99.5%

    subject to a maximum cap of 5%.

    Suggested that Penalties Shall be

    applicable only for the affected links and

    value should also be for the unaffected

    links.

    No change will be made in

    penalty conditions.

    Please note that the facility is

    expected to be operational with

    required level of reliability and

    up time during disastersituations. Penalties are

    proposed only for those

    systems that are exclusively

    supplied and operated by the

    Operator's manpower, hence

    expected performance

    standards should be

    maintained.

    Specified up time requirementsare well within performance

    records of similar systems in

    actual operating conditions.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    40/44

    121

    SCHEDULE IX

    PENALTIES

    (DURING

    IMPLEMENTATION

    AND OPERATIONS)

    Penalty for delay in completion of

    Implementation Phase

    For every week or part thereof of

    delay until actual completion of

    Implementation Phase, the penalty

    imposed on the Operator, withoutprejudice to GSDMAs other

    remedies under the Agreement,

    shall be 10% of the QGR. If the

    delay continues beyond 10

    weeks, GSDMA shall have the right

    to terminate the Agreement.

    Penalty for delay in completion

    and commissioning of sites other

    than SEOCFor every three months or part

    thereof of delay until actual

    completion and commissioning of

    all the sites

    that have been handed over to the

    Operator, the penalty imposed on

    the Operator, without prejudice to

    GSDMAs other remedies under the

    Agreement,shall be 10% of QGR.

    Penalty is suggested to be 0.5% of price of

    undelivered services per site per week

    subject to a maximum cap of 5%. It is also

    requested to delete the clause

    mentioning right to termination on 10

    weeks of delay.

    No changes in penalties during

    implementation phase will be

    made.

    The SEOC is critical component

    of the project and the operator

    should ensure availability of

    sufficient resources to complete

    the project as per schedule. RFP

    has lenient conditions for other

    sites.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    41/44

    122

    4.1 Terms of

    Payment and

    Service Credits and

    Debits

    The Operator is not entitled to be

    paid by GSDMA during this phase.

    Payment shall only be made after

    successful completion of AT i.e.

    once the Operation &

    Maintenance Phase is commenced.

    Since the project may get completed in a

    staggered manner, we would request to

    have payment to be made site-wise and

    link-wise.

    Whole project is expected to be

    completed at one go. Hence no

    changes in payment terms will

    be made.

    1231.2.9 Scope of

    Work

    A tripartite agreement between

    GSDMA, MPLS Network service

    provider and the Operator has to

    be drawn. Payment for the network

    will be made by GSDMA.

    How will the payment distribution be

    done between Bidder and Service

    Provider? How will the penalties

    be calculated as per the scope of each? It

    is suggested to have billing site-wise and

    link-wise.

    The tripartite agreement is only

    to establish legitimate user of

    MPLS network as Operator

    can't resale the bandwidth. The

    bill will be issued by the

    operator in the name of

    GSDMA, the operator will make

    initial payment and GSDMA will

    reimburse the payment to

    operator as part of QGR

    124 1.7 VSAT Network

    Proposed VSAT system will be

    capable to operate on

    the captive Hub (GSDMA/GoG)

    Since setting up of a captive VSAT hub is

    time consuming and highly expensive, we

    suggest GSDMA to consider VSAT services

    on a shared hub.

    Transportable and portable

    VSATs are not allowed in shared

    Hub services; hence GSDMA has

    opted for captive hub.

    Necessary funds are allocated

    towards cost of captive hub.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    42/44

    1251.2.9 Scope of

    Work

    It is suggested that VSAT

    communication network be

    set-up to operate in Ku-Band.

    Since VSAT network has to be operational

    in heavy rain and other adverse weather,

    it is suggested to use Extended C band

    instead of Ku band.

    This point was considered and

    final decisionwas to operate on

    Ku band was taken. Necessary

    margins in antenna gain and RF

    power are included in

    specifications to ensure reliableoperations even during heavy

    rains

    126

    2.2 Connectivity

    and

    Internetworking

    requirements

    The connectivity on MPLS-VPN

    between SEOC and

    DEOCs will be at 1 Mbps rate and

    between District and

    TEOC will be at 128 Kbps rates.

    What should be assumed as the

    concurrency for the backhauling of all

    DEOC B/W to SEOC and for backhauling all

    TEOC B/W to DEOC?

    Suggested bandwidth will be

    sufficient for peak traffic loads

    at respective nodes. The node

    at SEOC may be at 16.0 mbps

    rate.

    127

    2.2 Connectivity

    and

    Internetworking

    requirements

    Connectivity between SEOC, DEOC,

    ERC, DMI, and disaster location(s)

    using VSAT network at nominal 512

    Kbps rates that is upgradable to 1.0

    Mbps from affected districts EOCs

    and ERVs

    What is the uplink and downlink B/W

    requirement at each SEOC, DEOC, ERC,

    DMI and ERV?

    Up link data rate from all

    locations (other than SEOC) will

    be 512 kbps as per existing

    regulations and may be

    increased to 1.0 Mbps if

    regulations are revised in

    future. Up

    link from SEOC (down link at

    VSATs) will be up to 5.0 Mbps.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    43/44

    1282.14 Quality of

    Service

    Bit Error Rate (BER): Better than

    10e-6

    End to end delay: 700

    milliseconds

    It is suggested to have BER of 10e-4 or

    better for voice, VC and Data.Also suggested to have end to end delay

    (latency) to be 2000 milliseconds since

    VSAT network is involved.

    BER of 10-4

    is accepted for voice

    services , however quality (and

    link throughput) for data

    services including

    Videoconferencing will be

    unacceptable.End to end delay is time

    elapsed for travel form remote

    VSAT to another VSAT via Hub.

    The expected time delay will be

    within 700 Milli seconds.

    However latency up to 1000

    Milli seconds will be accepted

    129

    Schedule V

    Invoicing and

    Settlement

    Schedule

    In the event GSDMA makes

    payment on an invoice after the

    due date for payment thereof, it

    shall be liable to pay interest

    calculated at the rate of SBI PLR

    plus 2%,

    It is suggested that the Payments

    Pertaining to the services should not be

    with-held and should not be

    charged with any 2% Interest Rate

    No change

    130

    4.3 Payment

    Article IV Payment

    Terms/Invoicing /

    Tax

    In case of consortium, the

    payments will be made to an

    escrow account jointly operated by

    all members of the consortium

    unless the project entity is an SPV

    in which case the payment shall be

    made in SPV account

    It is requested to confirm that whether

    GSDMA will pay the telecom service

    directly irrespective of the consortium

    and as per tripartite agreement.

    No change even in case of

    tripartite agreement. The

    tripartite agreement is only to

    meet regulatory requirements

    that telecom bandwidth is not

    resold. The telecom service

    operator will provide services

    (MPLS-VPN or broadband ) to

    GSDMA, however charges will

    be settled by the operator.

  • 7/27/2019 Corrigendum No. 1 to Rfp Notice No. 10 of 2013

    44/44

    131 45Clause

    3.3

    Evaluation of

    Commercial BidQGR

    The bidders from different states, union

    territories, SEZs etc. will be required to

    pay VAT applicable for their states, inter-

    state taxes and/or Central State Tax (CST)

    as applicable and are going to differ from

    case to case. It is therefore requested thatCommercial (Price) comparison be done

    for arriving at inter-se ranking excluding

    the taxes and duties so as to provide a

    level playing field to all bidders. The taxes

    paid and added to vendors billing in any

    case flow back (pass through) to the

    Government and hence should be

    excluded (Net of Taxes) for comparison

    for ranking.

    No Change. The QGR to be

    quoted in the commercial bid is

    inclusive of all taxes

    Note Other queries received by GSDMA will be answered in the subsequent corrigendums