corporate presentation - june 2012

48
Building Canada’s Largest Gold Mine Production Early 2013 Corporate Presentation June 18-22, 2012

Upload: detourgold

Post on 16-May-2015

1.473 views

Category:

Business


6 download

TRANSCRIPT

Page 1: Corporate Presentation - June 2012

Building Canada’s Largest Gold Mine Production Early 2013

Corporate Presentation

June 18-22, 2012

Page 2: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 2

This presentation contains certain forward-looking information as defined in applicable securities laws (referred to herein as “forward-

looking statements”). Specifically, this presentation contains forward-looking statements regarding the reserve and resource

estimates, ore grade, expected mine life, anticipated gold production, gold recovery, cash operating costs and other costs, capital

costs, sensitivity to metal prices and other sensitivities, financial analysis of the project, commencement of operations, potential

expansion opportunities, plans for organic growth and expected drilling activities. Forward-looking statements involve known and

unknown risks, uncertainties and other factors which are beyond Detour Gold’s ability to predict or control and may cause Detour

Gold’s actual results, performance or achievements to be materially different from any of its future results, performance or

achievements expressed or implied by forward-looking statements. These risks, uncertainties and other factors include, but are not

limited to, gold price volatility, changes in debt and equity markets, the uncertainties involved in interpreting geological data,

increases in costs, environmental compliance and changes in environmental legislation and regulation, interest rate and exchange

rate fluctuations, general economic conditions and other risks involved in the gold exploration and development industry, as well as

those risk factors discussed in the section entitled “Description of Business - Risk Factors” in Detour Gold’s 2011 AIF and in the

continuous disclosure documents filed by Detour Gold on and available on SEDAR at www.sedar.com. Such forward-looking

statements are also based on a number of assumptions which may prove to be incorrect, including, but not limited to, assumptions

about the following: the supply and demand for gold, and the level and volatility of the price of gold; the availability of financing for

exploration and development activities; the estimated timeline for the development of the Detour Lake gold project; the expected

mine life; anticipated gold production; gold recovery; the development schedule; cash operating costs and other costs; the financial

analysis for the project; capital costs; sensitivity to metal prices and other sensitivities; the accuracy of reserve and resource

estimates and the assumptions on which the reserve and resource estimates are based; the receipt of necessary permits; market

competition; ongoing relations with employees and impacted communities; and general business and economic conditions.

Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements contained

herein are made as of the date hereof, or such other date or dates specified in such statements. Detour Gold undertakes no

obligation to update publicly or otherwise revise any forward-looking statements contained herein whether as a result of new

information or future events or otherwise, except as may be required by law. If the Company does update one or more forward-

looking statements, no inference should be drawn that it will make additional updates with respect to those or other forward-looking

statements.

Forward Looking Information

Page 3: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 3

Information Concerning Estimates of Mineral Reserves and Resources

The mineral reserve and resource estimates reported in this presentation were prepared in accordance with Canadian National

Instrument 43-101Standards of Disclosure for Mineral Projects (“NI 43-101”), as required by Canadian securities regulatory

authorities. For United States reporting purposes, the United States Securities and Exchange Commission (“SEC”) applies different

standards in order to classify mineralization as a reserve. In particular, while the terms “measured,” “indicated” and “inferred” mineral

resources are required pursuant to NI 43-101, the SEC does not recognize such terms. Canadian standards differ significantly from

the requirements of the SEC. Investors are cautioned not to assume that any part or all of the mineral deposits in these categories

constitute or will ever be converted into reserves. In addition, “inferred” mineral resources have a great amount of uncertainty as to

their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred

mineral resource will ever be upgraded to a higher category. Under Canadian securities laws, issuers must not make any disclosure

of results of an economic analysis that includes inferred mineral resources, except in rare cases.

On January 31, 2011, Detour Gold announced an updated mineral resource and reserve estimate. The following QPs participated in

this update: Michel Dagbert, Eng., Senior Geostatistician and André Laferrière, P. Geo., Senior Geologist of SGS Canada Inc.

(mineral resources); and André Allaire, Eng., Director Mining and Metals and Patrice Live, Eng., Mining Manager of BBA Inc (mineral

reserve). The NI 43-101 compliant Technical Report for this update was filed on SEDAR on March 15, 2011.

On January 25, 2012, Detour Gold announced a mineral resource and reserve update. The following QPs participated in this update:

Michel Dagbert, Eng., Senior Geostatistician of SGS Canada Inc (mineral resources) and Patrice Live, Eng., Mining Manager of BBA

Inc (mineral reserves).

NI 43-101 Disclosure

Page 4: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 4

Focus on a world-class asset – Detour Lake

Canada’s largest pure gold play with 15.6 M oz in reserves

(@ US$ 850/oz gold price)

Construction progressing on schedule (70% as of May 31)

One of the best cash flow/share opportunities

Gold production starting in Q1 2013

Excellent organic growth potential (5 year plan)

Potential expansion of mill throughput

Invest in Detour Gold

Page 5: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 5

Issued and

Outstanding:

112.6 M

Options & FN Share

Commitments:

8.7 M =

Fully Diluted:

134.3 M

Market cap: C$2.6 Billion

Cash position: C$683 Million

Major shareholders:

Convertible

Notes:

13.0 M

Paulson & Co. 15%

Fidelity Mgmt 8%

Detour Gold Mgmt <2%

Institutions total >90%

Share Capital

Detour Lake

+ +

Note: Share data and cash position as of May 31, 2012.

Page 6: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 6

Strong Share Performance

Osisko

(239%)

Yamana

Randgold

Eldorado

Buenaventura

Newcrest IMG

Kinross

Andina

Hecla Gabriel

Anglo Gold Ashanti AEM

Goldfields CG

NEM

AGI

Aurizon G ABX

GSC

DGC 11/09

DGC 07/10

Jan. 2007 to Present % Change in Shares Outstanding 100 150 0 50 200

Share Issuance vs. Performance

Source: BMO, June 2012

IPO

DGC 07/09

DGC 04/08

DGC 08/11

Ja

n. 2

00

7 t

o P

res

en

t To

tal

Retu

rn

400%

300%

200%

100%

0%

-100%

500%

600%

700%

800%

900%

1000%

571% total return

since IPO DGC 01/12

DGC equity financings

AuRico

Eco Oro

Great Basin

(209%)

Page 7: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 7

DETOUR LAKE:

RECORD TIMING FROM “DISCOVERY” TO PROJECTED PRODUCTION

6 years

Acquisition/

Discovery

2007

Pre-feasibility

Study

2009

Feasibility Study

& Permitting

2010

Development

2011-2012

Production

2013

Successful Focused Approach

Page 8: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 8

Mineral reserves/resources update for 2011 year-end

Top up of $277 million to complete the project and working capital

Second 45 km segment of transmission line complete

230 kV transmission line connection in Q3

Updated mine plan & operational forecast in Q3

Ore stockpile of 3 Mt available in Q4 for processing

Manpower ramp-up to 400 (now 273 employees at site and Cochrane)

Delivery of 12 haul trucks and 2 cable shovels

Drilling programs:

50,000 m on Block A open pit & initiate pre-feasibility study

5,060 m completed on Lower Detour Lake structure (targeting high-

grade mineralization)

Detour Gold 2012 Objectives

Page 9: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 9

2005-05

2006-09

Date Accumulative

DGC Drilling Resources/Reserves (M oz) Inferred M&I 2P

Growing Reserve/Resource Base

RESOURCE GROWTH EXCEEDING 750% SINCE IPO

2007-12 50,000m

2008-06 123,000m

2012-01 523,000m $850/oz 15.6

2011-01 430,000m $850/oz 14.9

2010-06 334,000m $850/oz 11.4

2009-09 249,000m 8.8

Estimated by Pelangio

DGC due diligence

10M 20M 30M

Page 10: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 10

As at Dec. 31, 2011

@ US$850/oz Tonnes

(millions)

Grade

(g/t)

Contained Gold

(‘000 oz)

Reserves (1)

Proven 101.6 1.29 4,222

Probable 368.4 0.96 11,351

P&P 470.0 1.03 15,573

Resources (2)

Measured 124.5 1.36 5,424

Indicated 554.3 1.00 17,836

M&I 678.8 1.07 23,261

Inferred 208.5 0.86 5,785

1. After a 95% mining recovery rate; Mining dilution factor of 15.5%.

2. Inclusive of mineral reserves.

DISCOVERY COST

< $10/oz OF

RESERVES

Detour Lake Reserves & Resources

Page 11: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 11

Detour Lake Profile (@ US$850/oz)

>1.0 g/t Au

0.5 - 1.0 g/t Au

<0.5 g/t Au

20,600E

16,500E

700 m

Open pit

@ 0.5 g/t cut-off

Detour Lake January 2012

update

Production start Q1 2013

OP reserves (M oz) 15.6

Mill throughput (tpd) 55,000

Strip ratio (waste:ore) 3.6

Gold recoveries 91%

Average grade (g/t) 1.03

Estimated mine life (yrs) 22

Avg. production (oz/yr)(1)(2) 657,000

Initial Capex (C$ B)(3) 1.45

1. After full commissioning in Yr 1.

2. Based on March 2011 TR.

3. Initial capex revised in November 2011.

Page 12: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 12

Intermediate Producers Reserves/Share Ratio (Average 0.07)

Source: Bloomberg and Company Reports, Equity Research and Thomson Financial at May 30, 2012.

Note: NAV per share figures are based on equity research consensus; Share data on fully diluted in the money shares outstanding.

.

Valuation Re-rating:<1 Yr from Production

0.17

0.04 0.04

0.12

0.03 0.04

0.14

Avg 0.07

1.1x 1.1x

1.0x

0.8x

0.6x

0.8x

0.6x

Avg 0.9x

Intermediate Producers P/NAV (Average 0.9x)

Page 13: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 13

2012E Cash Cost Profile (US$/oz)*

Junior

Producers

Senior

Producers

Intermediate

Producers

$ 796

$ 706 $ 706

$ 800

$ 700

$ 600

$ 500

*Source: BMO Equity Research

Seniors Producers include: Agnico-Eagle, AngloGold Ashanti, Barrick, Gold Fields, Goldcorp, Kinross, Newcrest, Newmont, Polyus and Yamana.

Intermediate Producers include: African Barrick, Alacer, AuRico, Centamin Egypt, Centerra, Eldorado, Harmony, IAMGold, New Gold, Osisko, Petropavlovsk, Randgold and SEMAFO.

Junior Producers include: Alamos Gold, Aurizon, Avion, Avocet, CGA Mining, Cluff Gold, Dundee Precious Metals, Golden Star, Great Basin Gold, Kingsgate, Lake Shore,

OceanaGold, Perseus, Primero, Resolute, San Gold and Teranga.

Total Cash Costs

Since 2010 (release of Feasibility Study),

inflationary pressure seen in operating costs

25%

14%

13% 13%

7%

4%

24% Maintenance Consumables

Royalty

G&A

Diesel Power

Labour

Approx. % of total cash cost/oz in FS1

1. Total estimated cash cost of US$543/oz based on March 2011 TR using cost parameters from feasibility study, including US$850/oz gold price

and US$80/barrel oil.

Page 14: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 14 © 2011 Detour Gold All Rights Reserved. 14

Mine Site Construction Progressing on Schedule

Page 15: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 15

2010 2011 2012 2013

Construction Schedule Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

Award of Engineering Contract

Award of PCM Contract

Detailed Engineering

Construction camp (1,200 people)

Power line (Phase 1&2) – Electrification

Equipment purchase/delivery & assembly

Pre-stripping

Process plant – Commissioning start-up

Tailings dam construction (first cell)

Provincial Permits/Aboriginal IBAs

Federal Permits

Start production and ramp-up

Detour Lake: We are on Schedule

1 2

GOLD PRODUCTION PROJECTED IN 1Q 2013

Page 16: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 16

Capital Expenditures (C$ M)

Description

Spent

May 31,

2012

Committed

May 31,

2012

Project Control

Estimate

(as of 11/2011)

Mining Fleet and Facilities 117 170 203

Crushing and Processing (P&E) 390 586 565

Tailings and Water Mgmt 15 45 65

Infrastructure and Power line 133 148 156

Other Indirect 158 202 310

EPCM 80 100 101

Contingency (10%) - 1 50

Total (pre-production) 893 1,252 1,450

PROJECT CONSTRUCTION 70% COMPLETE

Detour Lake: We are on Budget

Page 17: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 17

2012 Pre-Stripping

Feasibility

Study

PCE

(11/2011)

Status

(05/31/2012)

Overburden/Till 16 Mt 21 Mt 5.50 Mt

Waste - 10 Mt 1.82 Mt

Ore 3 Mt -

Estimated Cost C$30 M C$78 M -

PROJECT CHANGE

OF SCOPE

=

A BENEFIT

Ore available for

processing in 2012

Ore ready to be processed by the fourth quarter of 2012

Pre-production capital costs include $78 M for pre-strip activities

Up to 3 Mt of ore ready for process

2012 Operational Readiness Plan

Page 18: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 18

Mining is Ramping Up

Page 19: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 19

Mining is Ramping Up

Page 20: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 20

10 CAT 795F trucks at site (2 supplied by CAT);

4 more being assembled

2 CAT6060 shovels in operation

Initial Mining Fleet at Site

Loading Units

3 X Hydraulic CAT6060 (25 m3)

2 X Electric cable shovels (48 m3)

Haulers

23 X CAT 795F trucks (320 t);

30-35 at peak of operation

Page 21: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 21

45 km

Powerline

Detour Lake Development Progress

Gravel (34 km)

Paved road (151 km)

45 km

Powerline

Detour Lake

Detailed engineering, procurement

of major equipment and awarding

of major contracts complete

Second 45 km segment of

powerline complete

Pre-stripping program ongoing

Installation of mill equipment

underway

Truck wash facilities complete

Permanent camp construction

completed

Page 22: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 22 22 Note: Open pit reserves using US$850/oz gold

Detour Lake

Mining Facilities

Page 23: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 23

12-06-08

Overview Detour Lake Facilities

Truck Wash Truck Shop &

Warehouse

Mine Offices

Processing Plant

Page 24: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 24

12-06-08

Overview Detour Lake Facilities

Primary

Crusher

Stockpile

Reclaim Secondary

Crushers

Page 25: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 25

Gyro is

9 m high

Here now

Primary Crusher (up to 100,000 tpd capacity)

35 m

Surface 12-06-08

Page 26: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 26

Stockpile Reclaim

12-06-08

Cover Stockpile

Reclaim

Secondary and

Pebble Crushers

12-06-08

Page 27: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 27

SAG Mills

12-06-08

Ball Mills

Processing Plant Building

Page 28: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 28

Processing Plant Building

Hydrocyclones

CIP Tanks

12-06-08

Pumps

Page 29: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 29

Conventional gravity and CIP plant

55,000 tpd (=92% availability of 60,000

tpd capacity)

2 parallel lines (each with 1 secondary

cone crusher + 1 SAG and 1 ball mill)

A

A

Simple Process Plant

Estimated gravity recovery: 30-40%

Estimated overall gold recovery: 91.0%

Leach time 29 hours

Leach feed size 80% passing 95 μm

Page 30: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 30

Detour Lake Employees & Contractors

Construction Phase

>1,500 workers (currently)

Ramping up DGC team (273)

Operation Phase (Starting 2013)

400-500 employees

Rotation 1 week in /out

New modern camp facilities with

400 en-suite rooms completed

Page 31: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 31

Focus: Hiring Local First

28%

22%

44%

4% 2%

Workforce Origin

Cochrane

Cochrane Area

Northern Ontario

Rest of Ontario

Other

*25% of employees are Aboriginals

Professional are: MGMT, Eng., Geo., Supt.

Front Line are: Operators, Admin, Support

28% Reside in Cochrane

Continuing focus on hiring local/regional

25%

75%

Professional

Front Line

273 DETOUR GOLD EMPLOYEES (May 30, 2012) Require a complement of +400 employees by production start in early 2013

Page 32: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 32 © 2011 Detour Gold All Rights Reserved. 32

Planning for Organic Growth Under-explored Greenstone Belt

Page 33: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 33

Large prospective land position of approx. 540 km2

Land position increased with acquisition of Trade Winds properties

Two main gold structures with total strike length of >80 km

Continue focus on Detour Lake deposit extension (northern structure)

Test targets on structure south of Detour Lake

Future Objectives

Grow reserve base to +20 M oz (@ US$850/oz)

Increase mill throughput to above 75,000 tpd for gold production

output of +800,000 oz/yr

Find high-grade ore near-surface within trucking distance to

supplement mill

5 yr plan for successful organic growth

Planning for Organic Growth

Page 34: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 34

Priority #1 on Block A

Area between Block A open pit resource (M-Zone) and the

underground QK Zone discovered by Placer in mid-90’s

Drilling program of 50,000 m in 1H 2012

Start pre-feasibility study for small open pit (Block A resource)

Advance exploration of QK underground zone

Priority #2 on Lower Detour Deformation Zone (+40 km)

5,060 m of diamond drilling completed: N-S drill fence on high-grade drill

hole intercepts (53 g/t Au / 3 m & 22.6 g/t Au / 1 m)

115 km of IP geophysical survey completed

Geological and structural mapping; data compilation

2012 Plan for Successful Organic Growth

Page 35: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 35

*Not updated with TWD Dec. 30th PR. On Dec. 1, 2011, Detour Gold announced the acquisition of TWD.

Planning for Organic Growth

Deposit open to the west and at depth

+50,000 m of drilling for 2012 (Block A open pit above QK Zone)

2012 target

Page 36: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 36

Block A near-surface resource

Detour Lake

2011 year-end reserves = 15.6 M oz

Priority # 1 - Block A Target

DH included in 2011 year-end reserves

DH not included in 2011 year-end reserves

2012 proposed DH

2012 extension DH

Historical DH

Page 37: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 37

Priority # 1 - Block A Target

June 10, 2012

2012 proposed DH

2012 extension DH

2012 completed DH

Historical DH

Cancelled or

not accessible

2011 year-end reserves

= 15.6 M oz

Block A

2012 Drilling Program

Page 38: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 38

Existing DDH Gold occurrence (OGS)

DDH intersection >1g/2m DDH intersection >1g/10m

*Note: Excludes drilling around Detour Lake and M zone (Block A).

+80 km of favourable

geology

Insert- see next slide

MMI Survey Coverage

MMI Au Anomaly

Planning for Organic Growth

Sunday Lake Option

15.6 M oz in Reserves

Page 39: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 39

Planning for Organic Growth

Completed drilling

Page 40: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 40

?

?

Planning for Organic Growth

Page 41: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 41

2013

2012

2014

Best scenario is throughput

increase from 55,000 to 75,000 tpd

@ US$1,200/oz

Start pre-feasibility on Block A

Complete feasibility study and

assess technical feasibility and

resultant project economics

At >US$1,000/oz and after

successful commercial production

is achieved, proceed with plant

expansion

Complete expansion within 2 years

Evaluating Expansion Opportunities

Page 42: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 42

Focus on a world-class asset – Detour Lake

Canada’s largest pure gold play with 15.6 M oz in reserves

(@ US$ 850/oz gold price)

Construction progressing on schedule (70% as of May 31)

One of the best cash flow/share opportunities

Gold production starting in Q1 2013

Excellent organic growth potential (5 year plan)

Potential expansion of mill throughput

Invest in Detour Gold

Page 43: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 43 © 2011 Detour Gold All Rights Reserved. 43

Additional Information

Page 44: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 44

Detour Lake – Surface Plan

2011 Year-end reserves

= 15.6 M oz

DH included in the 2011 year-end

reserves

DH not included in the 2011 year-end

reserves

Pre 2007 DH

Page 45: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 45

QK Zone

Looking 20,070 N

Detour Lake – Long Section

DH included in the 2011 year-end

reserves

DH not included in the 2011 year-end

reserves

Pre 2007 DH

Page 46: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 46

1,600

1,400

1,200

1,000

800

600

400

200

0

Ou

nce

s (0

00’s

)

0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 3.0

Cut-off BINs

OK (oz Au)

ID3 (oz Au)

Approx. 3 M oz. between 0.3-0.5 g/t Au

Block Model - Gold Distribution

Page 47: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 47

Directors

Peter Crossgrove

Louis Dionne

Robert E. Doyle

Ingrid Hibbard

Michael Kenyon

Alex G. Morrison

Gerald Panneton

Jonathan Rubenstein

Graham Wozniak

Management

Gerald Panneton, Founder, President & CEO, Director

Michael Kenyon, Chairman

Paul Martin, CFO

Pierre Beaudoin, Sr. VP Capital Projects

Pat Donovan, VP Corporate Development

Julie Galloway, VP General Counsel & Corporate Secretary

James Mavor, VP Finance

Rachel Pineault, VP HR & Northern Affairs

James Robertson, VP Environment & Sustainability

Derek Teevan, VP Aboriginal & Government Affairs

Eric Josipovic, Controller

Drew Anwyll, Director of Operations

Andrew Croal, Dir. Technical Services

Laurie Gaborit, Dir. Investor Relations

Greg Miazga, Dir. Construction & Engineering

Bill Snelling, Director Corporate Systems and Controls

Christian Brousseau, Project Manager

Patrik Gillerstedt, Mine Manager

Management & Directors

Page 48: Corporate Presentation - June 2012

© 2011 Detour Gold All Rights Reserved. 48

© 2011 Detour Gold All Rights Reserved. 48

Gerald Panneton, President & CEO

Email: [email protected]

Ph: 416 304 0800

Laurie Gaborit, Director Investor Relations

Email: [email protected]

Ph: 416 304 0800

www.detourgold.com

Contact Information