cor1360 user trials - training week commencing 22/03/2010

25
COR1360 COR1360 User Trials - Training User Trials - Training week commencing 22/03/2010 week commencing 22/03/2010

Upload: gary-dean

Post on 01-Jan-2016

21 views

Category:

Documents


3 download

DESCRIPTION

COR1360 User Trials - Training week commencing 22/03/2010. Workshop Agenda. A refresher of Modification Proposal 0195AV Introduction to NTS Exit Reform Initialisation – Process and Timeline Enduring Annual Application Process Annual Application Window Pricing - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: COR1360 User Trials - Training week commencing 22/03/2010

COR1360COR1360

User Trials - TrainingUser Trials - Training

week commencing 22/03/2010week commencing 22/03/2010

Page 2: COR1360 User Trials - Training week commencing 22/03/2010

Workshop Agenda

A refresher of Modification Proposal 0195AV Introduction to NTS Exit Reform

Initialisation – Process and Timeline Enduring Annual Application Process Annual Application Window Pricing Enduring Annual Reduction Window Adhoc Increase Applications Adhoc Reductions Business Rules Timeline

Introduction to NTS Exit Reform System Solution User Preferences Request Capture Reporting

Page 3: COR1360 User Trials - Training week commencing 22/03/2010

In this presentation….

A blue box in the top right corner states the times at which the rules being explained apply e.g. when talking about the Annual Application Window, 1 – 31 July will be in the top right corner

1- 31 JulySection J

An orange box at the top of the slide states the primary section of legal text where the rules being explained are contained e.g. when talking about Assured Offtake Pressures, Section J will be in the top right corner

Page 4: COR1360 User Trials - Training week commencing 22/03/2010

Definition of Year Y

An Annual Application Window held in July Year Y releasing capacity for Y+1, Y+2 and Y+3 in this example would be: Application Window held July 2012 (Y) Capacity Release

1 October 2012– 30 September 2013 (Y+1) 1 October 2013 – 30 September 2014 (Y+2) 1 October 2014 – 30 September 2015 (Y+3)

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S

YEAR Y YEAR Y+1 YEAR Y+2 YEAR Y+3

2012 2013 2014 2015

Page 5: COR1360 User Trials - Training week commencing 22/03/2010

Change introduced via Modification 0195AV – Approved 19th Jan 2009 with an implementation of 1st April 2009

The current Transitional NTS Offtake arrangements allow Users to procure NTS Exit Capacity for use up to (and inclusive of) 30 th September 2012 and is known as the Transitional Exit Capacity Regime.

The reform to the Transitional arrangements will allow Users to make Capacity bookings and apply for increases or decreases to their Enduring Capacity rights from 2009 onwards, such bookings will be effective from 1st October 2012 and is known as the Enduring Exit Capacity Regime.

Background

Page 6: COR1360 User Trials - Training week commencing 22/03/2010

Overall Regime Objectives & Incentives

Objectives

Long Term Investment signals to National Grid NTS

All NTS Exit Capacity Users are treated equitably

Commercialise the DN interface

Incentives

User Commitment

Overruns

Page 7: COR1360 User Trials - Training week commencing 22/03/2010

Offtake Responsible Parties

CSEPiGTS

(Shipper)

Storage Interconnector

Direct Connects

Reserving

NTS

LDZ

DNs

(Shipper) DM Site

NDM Aggregate

Page 8: COR1360 User Trials - Training week commencing 22/03/2010

Current Exit Regime New Exit Regime (195AV)

DNOs apply for Flat Capacity via OCS Statement. No charge.

DNOs apply for Flat Capacity in Annual Application Window or ad hoc. DNOs charged.

DNOs apply for Flex and Pressures via OCS in July. DNOs apply for Flex and Pressures via OCS in July.

NTS cannot request a permanent reduction in DN pressure.

NTS can request a permanent reduction in DN pressure in April each year.

-Shippers book 12 monthly rolling blocks of Capacity at NTS CSEPs on Gemini.-Interconnectors’ Capacity booked by NTS when Downstream Capacity Holding confirmed.-Daily metered sites – enduring Capacity via Supply Point Administration Service.

Shippers book their own capacity at NTS Exit Points (in effect, DNOs book for DN Shipper requirements at NTS/LDZ offtake).

Shipper accesses Flex through submission of Offtake Profile Notices.

Shipper accesses Flex through submission of Offtake Profile Notices.

Can nominate site as Interruptible. No Capacity booking required.

Site cannot be nominated as interruptible. Off peak Capacity must be booked.

User Commitment determined outside of UNC (ARCAs). 4 years’ User Commitment for Enduring Flat Capacity .

ARCAs available to all Users. ARCAs for developers only.

High Level Principles: Current Exit Regime vs 0195AV

Page 9: COR1360 User Trials - Training week commencing 22/03/2010

UNC Classes of Capacity

NTS Exit FLAT Capacity

NTS Exit FLEXIBILITY

Capacity

NTS Exit Capacity

Annual Capacity Daily Capacity

Daily Off Peak Capacity

Daily Firm Capacity Enduring Annual

Capacity Annual Capacity

Shipper & DN OperatorDeveloperDN Operator

Page 10: COR1360 User Trials - Training week commencing 22/03/2010

InitialisationInitialisation

Page 11: COR1360 User Trials - Training week commencing 22/03/2010

Initialisation

Enduring Annual (Flat) Capacity allocated to Users at all NTS Exit Points

For Direct Connect NTS Exit Points Based on peak 2007/08 Capacity Holdings

Firm booking + Interruptible

For NTS/LDZ Offtakes Based on OCS statement for year 2011/12 agreed in 2008

If total initialised value for site > baseline Scaled back to baseline

1 May 2009TD 8

Page 12: COR1360 User Trials - Training week commencing 22/03/2010

Initialisation - Offline

All Users were notified of initialised values on 1 May 2009

NTS notified Users of allocation Or an agent notified at shared sites

No User Commitment was associated with initialised rights

Users were able to reduce their initialised value in July 2009 reduction window

Sweep ups will be completed at later dates of new sites connecting / ARCAs signed between 1 October 2008 and 30 September 2012

Maximum NTS Exit Point Offtake Rate (MNEPOR) values were communicated prior to 1 May 2009

1 May 2009TD 8

Page 13: COR1360 User Trials - Training week commencing 22/03/2010

Initialisation Timeline

1 April – implementation of new regime

16 April – NTS notifies Exit Capacity Booking Agent of aggregate value of Capacity allocated to site

23 April – Exit Capacity Booking Agent notifies NTS of individual User allocations, which equal aggregate amount previously notified

1 May – NTS notifies each User of initial amount of Enduring Annual (Flat) Capacity allocated to them at each NTS Exit Point

1 April 09 1 May 09

7 April – latest date for notifying NTS of Exit Capacity Booking Agent at NTS Exit Point

TD 8

Page 14: COR1360 User Trials - Training week commencing 22/03/2010

Annual ProcessesAnnual Processes

Page 15: COR1360 User Trials - Training week commencing 22/03/2010

Enduring Annual Application Window Application window open every business day in July

For Capacity to be utilised from 1 October Y+4, Y+5 and/or Y+6

‘Enduring’ Capacity (i.e. evergreen)

4 years’ User Commitment (defined in ExCR)

NTS to allocate no later than 30 September

User does not submit a price

Also includes ‘deemed’ application when a User has overrun (in reality, will not be in play until July 2013 window)

1- 31 JulyTPD B3.2

Annex B-1

Page 16: COR1360 User Trials - Training week commencing 22/03/2010

Annual Application Window

Application Window open every business day in July

Apply for years Y+1, Y+2 and Y+3

First applicable in July 2010 for Y+3 (i.e. Year 2012/2013)

Annual Capacity rights (not enduring)

NTS to release unsold obligated Capacity

No price, allocated up to obligated level then pro-rate based on volume

NTS has 5 days to allocate

NB Developers cannot apply for Annual Capacity

1- 31 JulyTPD B3.4

Annex B-1

Page 17: COR1360 User Trials - Training week commencing 22/03/2010

Enduring Application Scenario

2011 2012 2013 2014 2015 2016 2017

100

150

200

Committed capacity: 150

Page 18: COR1360 User Trials - Training week commencing 22/03/2010

Application Scenario

2011 2012 2013 2014 2015 2016 2017

Committed capacity: 200

Committed Capacity: 150 – superseded after 2014

100

150

200

2018

Reduction cannot be effective during the commitment period

Page 19: COR1360 User Trials - Training week commencing 22/03/2010

Prices

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

2009 2010 2011 2012

Capacity Application received here … July 2009

…for Capacity to be utilised here in October 2012

Indicative prices published here…. May 2009. (http://www.nationalgrid.com/uk/Gas/Charges/indicativecharges/)

But the price actually paid will be that included in the Transportation Statement published the summer preceding utilisation i.e. August 2012

TPD B3.12

Page 20: COR1360 User Trials - Training week commencing 22/03/2010

Enduring Annual Reduction Window

Became effective in 2009

Every business day from 1 July to 15 July

Users can apply to reduce their Enduring Annual (Flat) Capacity

Subject to User Commitment validation/checks or NTS being able to

utilise the Capacity to meet a request at the same Exit Point

User specifies Reduction Date Can be no earlier than 1 October Y+1

Default is 1 October Y+2, NTS may agree, at its discretion, to reduce

earlier than Y+2

1- 15 JulyTPD B3.2.14 –

3.2.24

Page 21: COR1360 User Trials - Training week commencing 22/03/2010

Adhoc ProcessesAdhoc Processes

Page 22: COR1360 User Trials - Training week commencing 22/03/2010

Ad-hoc Increase Applications

Can apply from 1 October – 30 June

Must be a New Site, or an Existing Site that passes threshold (10

GWh/Day or 125% prevailing baseline)

Can apply for up to 4 separate tranches

The Increase start date for Capacity must not be earlier than 6 months from date of application or later than 1 October Gas Year Y+4 from application

NTS must make an offer in 15 days / 90 days if think that works will be required / more than 90 days if both parties agree Offer specifies Demonstration Date and Capacity date(s) Reasonable endeavours to meet the Capacity date(s) requested User has 30 days to accept

1 October – 30 June

TPD B3.2Annex B-1

Page 23: COR1360 User Trials - Training week commencing 22/03/2010

Ad hoc Reductions

NTS may invite Users to submit a notice of reduction at other times in

order to support a Capacity request at the same NTS Exit Point

NTS will issue an invitation which will specify

The period during which a User may give a notice of reduction

The earliest date on which NTS may give notice to the reduction

The date on which NTS will notify the User as to whether it will give effect to the notice of reduction

TPD B3.2.14 – 3.2.24

Page 24: COR1360 User Trials - Training week commencing 22/03/2010

NTS Exit Reform Timeline: 2010-11 Processes

Bus

ines

s R

ules

Sys

tem

Sol

utio

n

May 2010 June 2010 July 2010 Aug2010 Sept 2010 Oct 2010 Nov 2010 Dec 2010 Jan 2011 Feb 2011 Mar 2011 Apr 2011

NG NTS Submit

ApplicationInvites

User can makeamendmentsto Capacity Requests placedIn July

NG NTS Publish

Application Results

User can submit Ad-Hoc Applications to Increase Capacity Holdings

User submits Applications for

Enduring Capacityfor Y+4, Y+5 & Y+6 and/or Capacity.

Decreases Effective from 1st October 2012. Annual

Capacity Applications can also be made during this window

NG NTS Submit

ApplicationInvites via

email

Application Screens Opened

From 01/07 to 31/07

for UserRequests

Amendmentsplaced withinthe system(Request CaptureScreen)

ResultsPublished via Gemini & MIPI

DNAdjustment

Window OpenFor 5 businessDays following

15/09

Application Screens Available for Ad-Hoc Request within System

View Capacity Holdings via System (Gemini & MIPI)

Decreases can be madein the system

between01/07 to

15/07

Page 25: COR1360 User Trials - Training week commencing 22/03/2010

NTS Exit Reform SolutionNTS Exit Reform Solution