conventional facilities status
DESCRIPTION
Conventional Facilities Status. LCLS Conventional Facilities Introduction Key Elements Staff Schedule Construction Status Remaining Issues. LCLS Installation and Commissioning Time-Line. Install Undulators. First Light in FEH. LTU/Und Install. X-Rays in NEH. First Light in FEE. - PowerPoint PPT PresentationTRANSCRIPT
Jess Albino
Accelerator Readiness Review
December 2, 20081
SLAC National Accelerator Laboratory
Conventional Facilities Status
• LCLS Conventional Facilities Introduction
– Key Elements– Staff– Schedule
• Construction Status• Remaining Issues
Jess Albino
Accelerator Readiness Review
December 2, 20082
SLAC National Accelerator Laboratory
Re-establishe- to SL2
LTU/Und
Comm.
Firs
t Li
ght
in
FEE
Firs
t Li
ght
in F
EH
NEH Ops & Commissioning
JJ FF MM AA MM JJ JJ AA SS DD JJ FF AA MM JJ JJ AA SS OO NN DD JJ FF MM AA MM JJ JJONA
2008 2009 2010 2008 2009 2010 DownP
PS
Linac/BC2 Commissionin
g FEL/FEECommissioni
ng Nov. 3, 2008
Inst
all
Undula
tors
D
LCLS Installation and Commissioning Time-Line
LTU
/Und
In
stall
PEP-I
I ru
n
ends
FEE/N
EH
In
stall
CD
-4
(7/3
1/2
01
0)
X-R
ays
in N
EH
now
DDown
?
FEH
Hutc
h B
O
M
Jess Albino
Accelerator Readiness Review
December 2, 20083
SLAC National Accelerator Laboratory
Substantial Completion Dates
Front End EnclosureNOV 08
Central Utility PlantNOV 08Undulator
HallNOV 08 Near Experimental Hall
NOV 08
Beam DumpNOV 08
Beam TransferNOV 08
Xray/DiagnosticsNOV 08
Far Experimental HallNOV 08
Jess Albino
Accelerator Readiness Review
December 2, 20084
SLAC National Accelerator Laboratory
Jess Albino
Accelerator Readiness Review
December 2, 20085
SLAC National Accelerator Laboratory
Jess Albino
Accelerator Readiness Review
December 2, 20086
SLAC National Accelerator Laboratory
Mark up Drawings and Specifications
Equipment Warranties
Equipment Testing Reports
Subcontractor Financial Records
Final Acceptance Records
Jess Albino
Accelerator Readiness Review
December 2, 20087
SLAC National Accelerator Laboratory
Jess Albino
Accelerator Readiness Review
December 2, 20088
SLAC National Accelerator Laboratory
TCCo —> LCLS CF
Status e-beam System (thru e–DUMP)
Install. compl.
Dwgs of Record
Commiss. Test reports
Final Punch List
Final acceptance CF Recip.
Building/Housing shop dwgs n/a 15-Nov-08 30-Nov-08 Saenz
AC Pwr √ shop dwgs √ 15-Nov-08 30-Nov-08 Sevilla
Ch. W. √ shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla
Hot W. √ shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla
LCW √ shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla
HVAC √ shop dwgs √ 15-Nov-08 30-Nov-08 Saenz
C. Air √ shop dwgs √ 15-Nov-08 30-Nov-08 Sevilla
Fire Systems √ shop dwgs 31-Oct-08 15-Nov-08 30-Nov-08 Saenz
Sump 30-Nov shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla
Radio n/a n/a n/a n/a n/a n/a
Phones √ shop dwgs n/a 15-Nov-08 30-Nov-08 Saenz
Magnets n/a n/a n/a n/a n/a n/a
Vacuum n/a n/a n/a n/a n/a n/a
Mag. Power spl n/a n/a n/a n/a n/a n/a
Controls n/a n/a n/a n/a n/a n/a
Jess Albino
Accelerator Readiness Review
December 2, 20089
SLAC National Accelerator Laboratory
Beam Transport Hall
Jess Albino
Accelerator Readiness Review
December 2, 200810
SLAC National Accelerator Laboratory
Undulator Hall
Jess Albino
Accelerator Readiness Review
December 2, 200811
SLAC National Accelerator Laboratory
Electron Beam Dump Area
Jess Albino
Accelerator Readiness Review
December 2, 200812
SLAC National Accelerator Laboratory
Jess Albino
Accelerator Readiness Review
December 2, 200813
SLAC National Accelerator Laboratory
Access Tunnel
Jess Albino
Accelerator Readiness Review
December 2, 200814
SLAC National Accelerator Laboratory
20 ITEMS REMAINING
Jess Albino
Accelerator Readiness Review
December 2, 200815
SLAC National Accelerator Laboratory
Project Director John Galayda
Deputy Proj. Director Mark Reichanadter
Associate Project Director – Civil Construction
Jess Albino
CF System Manager David Saenz
Site ManagerJacobs Facilities, IncDave McDonough
JE Design PMCypress
JE Walnut Creek
JE Portland JE Boston
UTR – CMDumitru Ciorbea
Engineering Group Leader
Javier Sevilla
University Technical Rep – Group Leader
Jesse Saldivar
CM/GC – Turner Mike Owens – Sr. PM
Matt Zybura -APM
UTR – ElectricalLori Shewchuk
UTR – MechanicalJavier Sevilla
UTR – StructuralKen Yang
UTR – CMRichard Maggi
Rutherford /ChekeneGyimah Kasali
General SuperintendentNick Tyler
ElectricalLori Shewchuk
StructuralKen Yang
Project Controls and Support Office
SLAC Services Support
Turner Procurement – Pre-purchased
Equipment
C.M. TunnelsEric Alward - HMM
Turner Project Office
Administrative SupportLee Anne De WanConcepcion Zelaya
SLAC ES&H Subject Matter Experts (SME)
Change ProcessingJim Dee
John Azevedo
Cost / ScheduleAnita Malahowski
Exec. CF CommitteeR. Claus, J. Jobe
B. MillerM. Reichanadter
Turner Bill Jangraw
Project Executive
Sub ContractorsSite Safety RepAndrew Leone
Mechanical EngineerRay Baclit
Electrical EngineerKhalid Ahmed
CF Construction Organization
Jess Albino
Accelerator Readiness Review
December 2, 200816
SLAC National Accelerator Laboratory
Summary
• Substantial Completion has been achieved.• Punch list items are currently being addressed.• Installation tasks were successfully supported with Beneficial Occupancy and logistics under CF direction.• All systems accepted and ready for transfer to installation or laboratory service groups.• Plans are in place for the beam commissioning program.
Jess Albino
Accelerator Readiness Review
December 2, 200817
SLAC National Accelerator Laboratory
End of presentation