Jess Albino Accelerator Readiness Review [email protected] December 2, 2008 1 SLAC National Accelerator Laboratory Conventional Facilities Status • LCLS Conventional Facilities Introduction – Key Elements – Staff – Schedule • Construction Status • Remaining Issues

Upload: dobry

Post on 23-Jan-2016

33 views

Category:

Documents


0 download

DESCRIPTION

Conventional Facilities Status. LCLS Conventional Facilities Introduction Key Elements Staff Schedule Construction Status Remaining Issues. LCLS Installation and Commissioning Time-Line. Install Undulators. First Light in FEH. LTU/Und Install. X-Rays in NEH. First Light in FEE. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 20081

SLAC National Accelerator Laboratory

Conventional Facilities Status

• LCLS Conventional Facilities Introduction

– Key Elements– Staff– Schedule

• Construction Status• Remaining Issues

Page 2: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 20082

SLAC National Accelerator Laboratory

Re-establishe- to SL2

LTU/Und

Comm.

Firs

t Li

ght

in

FEE

Firs

t Li

ght

in F

EH

NEH Ops & Commissioning

JJ FF MM AA MM JJ JJ AA SS DD JJ FF AA MM JJ JJ AA SS OO NN DD JJ FF MM AA MM JJ JJONA

2008 2009 2010 2008 2009 2010 DownP

PS

Linac/BC2 Commissionin

g FEL/FEECommissioni

ng Nov. 3, 2008

Inst

all

Undula

tors

D

LCLS Installation and Commissioning Time-Line

LTU

/Und

In

stall

PEP-I

I ru

n

ends

FEE/N

EH

In

stall

CD

-4

(7/3

1/2

01

0)

X-R

ays

in N

EH

now

DDown

?

FEH

Hutc

h B

O

M

Page 3: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 20083

SLAC National Accelerator Laboratory

Substantial Completion Dates

Front End EnclosureNOV 08

Central Utility PlantNOV 08Undulator

HallNOV 08 Near Experimental Hall

NOV 08

Beam DumpNOV 08

Beam TransferNOV 08

Xray/DiagnosticsNOV 08

Far Experimental HallNOV 08

Page 4: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 20084

SLAC National Accelerator Laboratory

Page 5: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 20085

SLAC National Accelerator Laboratory

Page 6: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 20086

SLAC National Accelerator Laboratory

Mark up Drawings and Specifications

Equipment Warranties

Equipment Testing Reports

Subcontractor Financial Records

Final Acceptance Records

Page 7: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 20087

SLAC National Accelerator Laboratory

Page 8: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 20088

SLAC National Accelerator Laboratory

TCCo —> LCLS CF

Status e-beam System (thru e–DUMP)

Install. compl.

Dwgs of Record

Commiss. Test reports

Final Punch List

Final acceptance CF Recip.

Building/Housing   shop dwgs n/a 15-Nov-08 30-Nov-08 Saenz

  AC Pwr √ shop dwgs √ 15-Nov-08 30-Nov-08 Sevilla

  Ch. W. √ shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla

  Hot W. √ shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla

  LCW √ shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla

  HVAC √ shop dwgs √ 15-Nov-08 30-Nov-08 Saenz

  C. Air √ shop dwgs √ 15-Nov-08 30-Nov-08 Sevilla

 

Fire Systems √ shop dwgs 31-Oct-08 15-Nov-08 30-Nov-08 Saenz

  Sump 30-Nov shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla

  Radio n/a n/a n/a n/a n/a n/a

  Phones √ shop dwgs n/a 15-Nov-08 30-Nov-08 Saenz

Magnets n/a n/a n/a n/a n/a n/a

Vacuum n/a n/a n/a n/a n/a n/a

Mag. Power spl n/a n/a n/a n/a n/a n/a

Controls n/a n/a n/a n/a n/a n/a

Page 9: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 20089

SLAC National Accelerator Laboratory

Beam Transport Hall

Page 10: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 200810

SLAC National Accelerator Laboratory

Undulator Hall

Page 11: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 200811

SLAC National Accelerator Laboratory

Electron Beam Dump Area

Page 12: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 200812

SLAC National Accelerator Laboratory

Page 13: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 200813

SLAC National Accelerator Laboratory

Access Tunnel

Page 14: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 200814

SLAC National Accelerator Laboratory

20 ITEMS REMAINING

Page 15: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 200815

SLAC National Accelerator Laboratory

Project Director John Galayda

Deputy Proj. Director Mark Reichanadter

Associate Project Director – Civil Construction

Jess Albino

CF System Manager David Saenz

Site ManagerJacobs Facilities, IncDave McDonough

JE Design PMCypress

JE Walnut Creek

JE Portland JE Boston

UTR – CMDumitru Ciorbea

Engineering Group Leader

Javier Sevilla

University Technical Rep – Group Leader

Jesse Saldivar

CM/GC – Turner Mike Owens – Sr. PM

Matt Zybura -APM

UTR – ElectricalLori Shewchuk

UTR – MechanicalJavier Sevilla

UTR – StructuralKen Yang

UTR – CMRichard Maggi

Rutherford /ChekeneGyimah Kasali

General SuperintendentNick Tyler

ElectricalLori Shewchuk

StructuralKen Yang

Project Controls and Support Office

SLAC Services Support

Turner Procurement – Pre-purchased

Equipment

C.M. TunnelsEric Alward - HMM

Turner Project Office

Administrative SupportLee Anne De WanConcepcion Zelaya

SLAC ES&H Subject Matter Experts (SME)

Change ProcessingJim Dee

John Azevedo

Cost / ScheduleAnita Malahowski

Exec. CF CommitteeR. Claus, J. Jobe

B. MillerM. Reichanadter

Turner Bill Jangraw

Project Executive

Sub ContractorsSite Safety RepAndrew Leone

Mechanical EngineerRay Baclit

Electrical EngineerKhalid Ahmed

CF Construction Organization

Page 16: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 200816

SLAC National Accelerator Laboratory

Summary

• Substantial Completion has been achieved.• Punch list items are currently being addressed.• Installation tasks were successfully supported with Beneficial Occupancy and logistics under CF direction.• All systems accepted and ready for transfer to installation or laboratory service groups.• Plans are in place for the beam commissioning program.

Page 17: Conventional Facilities Status

Jess Albino

Accelerator Readiness Review

[email protected]

December 2, 200817

SLAC National Accelerator Laboratory

End of presentation