construction sector update_141013

Upload: pinaki-roychowdhury

Post on 03-Feb-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/21/2019 Construction Sector Update_141013

    1/32

    Your success is our success

    Emkay

    Sec

    torUpdate

    Emka Global Financial Services Ltd. 1

    Construction

    Strengthening the Weak Links

    October 14, 2013

    Nitin Arora

    [email protected]

    +91-22-66242491

    Ajit Motwani

    [email protected]

    +91-22-66121255

    Premium restructuring another bid to clear clog, may not be enough to

    improve project viability

    The Cabinet Committee on Economic Affairs (CCEA) has given the principal approval for

    restructuring premium payments for certain projects with the aim to improve projectviability and ease cashflows of already strained developer balance sheets. The deferred

    premium payments would help concessionaires to use cashflows from the initial few

    years for equity commitments for the project. However, it may not be sufficient to improve

    viability of projects due to aggressive bids. In our view, the cancellation and re-bidding of

    projects would be a prudent option [recently the National Highway Authority of India

    (NHAI) cancelled four BOT projects, which are set to come up for re-bidding] against

    premium restructuring, which is likely to face challenges.

    Re-bidding of stalled contracts likely to push awarding activity upwards in

    2HFY14E; NHAI targets 4000km

    In the last 6 months, the NHAI has made attempts to resolve issues pertaining to the

    sector by: a) de-linking forest and environmental clearances for linear projects, b)directing banks to lower land acquisition requirements for disbursal of loans, c) classifying

    debts for BOT projects as secured loans, d) CCEAs exit offer for road developers

    irrespective of the construction stage, and e) restructuring of projects via rescheduling of

    premium. As a result, the NHAI is now aims to award more than 50% of the total target of

    4000km in FY14E on an EPC basis. Given the prevailing financial and structural

    challenges in the sector, we see scope of new orders to emerge from potential re-bidding

    of stalled contracts and EPC projects (will not garner interest of large developers due to

    the small project size). However, the window for resolving the major reform premium

    restructuring is very short given the upcoming elections in 2014. In case the standoff

    continues it is unlikely that NHAI will be able to bid out a sizeable number of BOT projects

    this year/H1FY15.

    Substitution of concessionaire not to address financial unviable projects

    The government/NHAI-approved substitution of developers (to replace SPV in

    consultation with lenders) allowed the latter to sell projects irrespective of the stage of

    construction. The substitution policy entails the SPV to hold a 51% stake in the project

    post the sale. We believe the policy will not make any significant impact to help revive the

    sector sentiment, as it would not largely benefit financially unviable projects, as: a)

    developers opting for substitution of stalled contracts, where delays occurred due to the

    concessionaire default, the new SPV becomes liable to pay a penalty on delayed

    completion, and b) only eight projects of the 47 projects tendered in FY12 have

    commenced construction till June 2013. This implies that the majority of the projects were

    not given the appointed date, since exit policy would be applicable for projects that have

    achieved the appointed date. Also, the ambiguities related to whether tax benefits would

    pass on to the new SPV would involve additional costs (stamp duty that itself is 2.5% ofthe transaction value).

    Authority aims to clear the clog: Maintain Buy on IRB, Ashoka Buildcon

    In the last 2 years, the road sector did not witness any awarding or construction activity.

    A large part of the construction work did not keep up with execution run rates, which led

    to project delays, mainly due to EC FC clearances and the limited ability of prospective

    bidders to mobilize additional equity and competitive bidding, making the project

    cashflows unviable to support premium payments. Heightened risk perception about BOT

    projects causes financial institutions to be reluctant to take additional exposure in

    highway BOT projects.

    In this scenario, we maintain a Buy rating on IRB infrastructure and Ashoka Buildcon

    because of their strong road-asset portfolio and stable order-books. With a minimalfunding requirement, these companies remain well-funded for exploiting new

    opportunities as and when the NHAI awarding activity picks up. We retain a hold rating on

    ITNL, given its high parent leverage, along with decelerating high margin fee income

    could mean rising interest cost pressures, thereby causing deterioration in profitability.

  • 7/21/2019 Construction Sector Update_141013

    2/32

    Construction Sector Update

    Emkay Research October 14, 2013 2

    CCEA in-principle approval for rescheduling of premiums

    With regard to Kishangarh-Udaipur-Ahmedabad, Cuttuck-Angul, and Shivpuri-Dewas

    projects, which have asked for rescheduling of the premium on account of delays in

    acquiring land and variations in traffic seen from the time of bidding (which would make the

    projects financially unviable), CCEA has approved rescheduling of premiums for 23 road

    projects wherein appointed dates were not given . The underlying principle of this

    rescheduling process is to maintain the NPV of these premium payments while allowingsome relief in the initial years to compensate for delays in clearances and traffic slowdown.

    CCEA stated that NHAI would now consider each project on a case-to-case basis to

    determine its eligibility for the rescheduling of restructuring. However, details are still

    awaited regarding broad principles agreed on rescheduling like the discounting rate (10-

    12%), besides conditions such as bank guarantee and upfront penalty. Developers of

    another 16 road projects have also approached the NHAI for restructuring of premiums, but

    the roads ministry is not yet to consider their proposals

    Exhibit 1: Projects considered for premium restructuring

    Projects Concessionaire Length Km Project cost Rsmn Premium Quoted Rsmn Bid date

    Rampur- Kathgodam ERA-Sibmost 93 8,500 340 23-Nov-11

    Lucknow - Sultanpur Essar-Atlanta 123 10,790 96 13-Sep-11Agra - Etawa by pass Ramky Infrastructure 125 13,460 1,281 24-Nov-11

    Hospet-Chitradurga NH-13 Ramky Infrastructure 120 10,450 630 18-Nov-11

    Cuttack-Angul NH-42 Ashoka Buildcon 112 11,240 611 18-Nov-11

    Solapur - MH/KNT border NH-9 Coastal-SREI 100 9,230 280 12-Dec-11

    Shivpuri-Dewas GVK 332 28,150 1,809 1-Aug-11

    Raipur - Bilaspur IVRCL A&H 126 12,160 455 18-Nov-11

    Vijaywada - Gundugolanu Gammon Infrastructure 104 17,430 576 24-Jan-12

    Obdedullganj-Betul Transstroy 123 9,120 330 17-Jan-12

    Solapur - Bijapur Sadbhav 111 10,025 756 26-Mar-12

    Aurangabad-Barwa Adda KMC 222 24,190 1,350 30-Mar-12

    Rajumundary - Gundugulanu IVRCl A&H 121 17,510 721 30-Mar-12

    Jalgaon - Gujarat/MH Border L&T 209 19,730 1,451 30-Mar-12

    Amravati - Jalgaon L&T 275 25,259 1,310 30-Mar-12

    Jind-Punjab/Haryana Border Unity Infra 69 4,388 102 30-Mar-12

    Kota - Jhalwar Keti Constructions 88 5,300 35 15-Apr-11

    Sangareddy to MH-KNT Border NH-9 L&T 145 12,660 800 30-Sep-11

    Hospet-Bellary NH-63 PNC 95 9,101 180 29-Jul-11

    Kishangarh-Udaipur-Ahmedabad GMR Infrastructure 555 53,870 6,360 29-Jul-11

    Anandpuram - Vishakhapatnam - Ankapalli Transstroy 58 8,630 820 30-Mar-12

    Coimbatore Mettupalayam Transstroy-OJSC 53 5,920

    Barwa Adda Panagarh IL&FS Transportation 123 1,665 420 10-Apr-13

    Total 328777 20712

    Source:

    Premium Restructuring: Attempt to resolve developers/project cashflow

    issues for the short term

    The government has made attempts to kick-start the projects worth over Rs300bn, which

    also remains essential in terms of creating appetite for contracts lined up for the next round

    of bidding. However, it remains to be seen whether the relief offered to developers under

    this proposal would be sufficient and acceptable to developers. The underlying statement

    of the NHAI that restructuring would be looked into on a case to case basis implies its

    ambiguous applicability across all projects is likely to engender litigation issues. Our view

    on this development is as follows:

    Loans provided by the NHAI, which will not reflect in developers books; however, itwould provide interim relief to concessionaire, as deferred premium payments would

    help concessionaires to use cashflows from the initial few years for equity

    commitments for the project, ultimately to improve project viability and ease cashflowsof already strained developer balance sheets. At the same time, the government also

    wants to ensure adequate financial commitment from developers so as to ensure

    timely completion of projects.

  • 7/21/2019 Construction Sector Update_141013

    3/32

    Construction Sector Update

    Emkay Research October 14, 2013 3

    As the NHAI would be considering rescheduling on a case to case basis, small-premium projects and premium projects, which have commenced work, are likely to

    remain out of the mechanism. There is a risk that some of these developers may

    litigate if they, too, are not given this premium restructuring option, causing further

    delays.

    The window for resolving this standoff is very short, given the upcoming elections inearly 2014. In case the standoff continues, it is unlikely that the NHAI would be able tobid out a sizeable number of BOT projects in 2HFY14E/1HFY15E.

    The prudent strategy, we believe, is to kick-start the projects that have been weigheddown due to financial closure and aggressive biddings, and re-invite them for re-

    bidding, which would attract serious developers and discover a new premium or a grant

    base.

    In our view, the major persistent issue with regard to projects involves financial

    restructuring, since other structural problems related to land acquisition, re-bidding for

    those projects that have not achieved financial closure (though the intensity can be lower),

    and asking financial Institutions to take additional exposure in highway BOT projects,

    especially in those cases where the NHAI satisfies all precedent conditions, can still be

    resolved.

    Premium restructuring not enough, re-bid of projects the prudent option

    The projects are broadly categorized into four segments: a) projects wherein developers

    are prepared to make progress based on the original bidding parameters as long as the

    NHAI fulfills its obligations, b) projects that need to be terminated with a penalty in cases

    where the concessionaire has defaulted, c) projects that would be terminated and re-bid

    but without a penalty in cases where the concessionaire has defaulted and the NHAI has

    failed to meet its obligations, and d) projects wherein concessionaires may be willing to

    make progress with some changes to bidding conditions (such as premium restructuring).

    As per NHAI estimates, 28 projects (3042.60km) were awarded, but they have not

    achieved financial closure, whose grace period of 120 days (over and above the 180 days

    required to achieve financial closure) end in October 2013. Recently, the NHAI scrapped

    four road projects without penalising the developer as wildlife clearance was still pending.

    Kota-Jhalawar road project (80km, a 4-laning project won by Keti Construction) Meerut Bulandshahr (60km, a 4-laning project won by C&C Construction) Rampur-Kathgodam (93km, a 4-laning project won Era Infrastructure) Agra-Etawah (125km, a 6-laning project, won by Ramky Infrastructure)We have noticed that developers are weighed down by economically unviable road projects

    as a result of aggressive biddings and due to a lack incentives to help them keep the

    projects in their kitty (in some cases the performance guarantee was not submitted which

    forms 1% of the project cost). We have highlighted a list of 21 stalled projects (Exhibit 10)

    on account of land acquisition issues (delay caused due to EC/FC clearances ), with

    majority of them considered for premium for restructuring, part of which is likely to come upfor re-bidding . We believe the solution to kick-start these projects that are weighed down

    due to financial closure is to re-invite them for re-bidding, which would attract serious

    developers and discover a new premium or a grant base.

  • 7/21/2019 Construction Sector Update_141013

    4/32

    Construction Sector Update

    Emkay Research October 14, 2013 4

    Exhibit 2: Projects delayed due to land acquisition

    Road projects stuck due to land Acquisition Contractor (km) Cost (bn) Lane

    1. Vijayawada-Eluru-Gundu Golanu VG Road project 103.6 16.8 6

    2. Rajahmundry-Gundu Golanu IVRCL 121.0 16.2 6

    3. Anandapuram-Vskp-Anakapalli TRanstroytollway 59.0 8.6 6

    4. Raipur-Bilaspur IVRCLAssets 126.5 12.2 4

    5. Jind-Punjab/Haryana border UnityInfra 69.4 4.4 4

    6. Aurangabad-Barwa Adda KMCConstruction 220.0 24.2 6

    7. Hospet-Bellary PNCBetul 95.4 9.1 4

    8. Sangareddyto Maha border L&T DPL 145.0 12.7

    9. Hospet-Chitradurga RamkeyInfra 120.0 10.3

    10. Shivpuri-Dewas GVK 332.5 28.2 4

    11. Obedullaganj-Betul TRanstroyOJSC 121.0 9.1 4

    12. Solapur-Karnataka border Coartal Srei 100.0 9.2 4

    13. Solapur-Bijapur SadhbhavEngineering 110.0 9.9 4

    14. Jalgaon-Gujaratborder L&T Infra 208.0 19.7 4

    15. Amravati-Jalgaon L&T Infra 275.0 25.4 4

    16. Agra-Etawah RamalkyInfra 124.5 12.1 617. Cuttack-Angul Ashoka Buildcon 112.0 11.2 4

    18. Kota-Jhalawar Keti Construction 88.1 5.3 4

    19. Kishangarh-Ahmedabad GMR Infra 555.5 53.9 6

    20. Lucknow-Sultanpur Essar Atlanta 125.9 10.4 4

    21. Rampur-Kathgodam ERA-Sibmost 93.2 7.9 4

    Source: Emkay Research, NHAI

  • 7/21/2019 Construction Sector Update_141013

    5/32

    Construction Sector Update

    Emkay Research October 14, 2013 5

    Awarding activity to inch upwards in 2HFY14E; NHAI targets 4000km

    In FY13, project award activity fell sharply and was at its lowest levels since FY05, with the

    exception of FY09. Both BOT (build-operate-transfer) and EPC (engineering, procurement

    and construction) project awards by the NHAI declined to 1128km in FY13 from 6380km in

    FY12. We have seen a surge in ordering activity in BOT mode between FY09 and FY12,

    while the contribution of projects awarded in EPC mode was negligible. However, in FY13,

    we noticed the tapering off awarding activity, with 14 BOT projects worth Rs150bn/1822 kmfailing to attract any bids. This led to awarding of only 1128kms of BOT projects as against

    the original target of 8800km. As a result, the NHAI is now aims to award more than 50% of

    the total target of 4000km in FY14E on an EPC basis. Till date, the NHAI has awarded

    (YTD FY14E) 356km and 123km in EPC and BOT modes, respectively. Given the

    prevailing financial and structural challenges in the sector, we see scope of new orders to

    emerge through the EPC route and potential re-bidding of stalled contracts.

    Exhibit 3: Ordering activity remains sedate

    1608 1390 1145 643

    33605058

    6380

    1116 4790

    1000

    2000

    30004000

    5000

    6000

    7000

    FY06

    FY07

    FY08

    FY09

    FY10

    FY11

    FY12

    FY13

    FY14

    (Sep2013)

    Length awarded (Km)

    Source: Emkay Research , NHAI

    Exhibit 4: Construction work per km

    753 635

    16822205

    2693

    17842249

    2848

    6370

    500

    1000

    1500

    2000

    2500

    3000

    FY06

    FY07

    FY08

    FY09

    FY10

    FY11

    FY12

    FY13

    FY14

    (Sep2013)

    Length completed (Km)

    Source: Emkay Research , NHAI

    Exhibit 5: Awarding activity in BOT and EPC

    1608 1390 1145643

    3360

    50586380

    1116

    123

    3055

    345 89 356

    0

    1000

    2000

    3000

    4000

    5000

    60007000

    FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14

    (Sep2013)

    Length aw arded (Km) BOT Length aw arded (Km) EPC

    Source: Emkay Research, NHAI

    Exhibit 6: Balance of work to be awarded

    NHDP component

    Total

    Length (km)

    Completed

    4/6 lane(km)

    Under

    Length (km)

    Implementation

    No. of projects

    Balance for award of

    civil works (km)

    NHDP Phase-I 7522 7514 8 10 -

    NHDP Phase-II 6647 5647 610 52 385

    NHDP Phase-III 12109 5611 4813 89 1685

    NHDP Phase-IV 20000^ 285 4130 33 10384

    NHDP Phase-V 6500 1584 2496 28 2420

    NHDP Phase-VI 1000 - - - 1000

    NHDP Phase-VII 700* 21 20 2 659

    Misc. Projects 656 363 293 9 -

    NH-34 5.5 5.5 1

    SARDP-NE 388 69 43 2 276

    Total 55528 21094 12419 226 16808

    Source: Company, Emkay Research

  • 7/21/2019 Construction Sector Update_141013

    6/32

    Construction Sector Update

    Emkay Research October 14, 2013 6

    Exhibit 7: BOT Projects to be tendered

    Road Stretch State (kms) Cost (Rs.mn) Status

    Barwa Adda-Panagarh West Bengal 122.9 16,650 Work Awarded to ITNL

    Jabalpur-Lakhanadone Madhya Pradesh 80.8 7,770 Bids invited

    Bhavnagar-Verawal (4 lane) Gujarat 260.0 32,400 Bids invited

    Yadgiri-Warangal (4 lane) Andhra Pradesh 99.0 9,570 NA

    Hospet-Hubli (4 lane) Karnataka 143.3 12,930 Bids to be re-invited

    Numaligarh-Jorhat (4 lane) Assam 51.2 5,850 No bids received, project to be restructured

    Ghoshpukur-Salsabari (4 lane) West Bengal 154.9 22,120 Bids to be invited

    Karaikudi-Ramanathapuram (2 lane) Tamil Nadu 80.0 3,360 Bids to be re-invited

    Demoh-Dibrugarh (4 lane) Assam 46.0 4,730 No bids received, project to be restructured

    Jorhat-Demoh (4 lane) Assam 81.8 8,750 No bids received, project to be restructured

    Chas-Ramgarh (2/4 lane) Jharkhand 78.3 2,980

    Aurangabad-Vedishi (4 lane) Maharashtra 189.1 18,710

    Chandikhole-Dubari-Bhuban (4 lane) Odisha 62.2 6,520 Bids invited

    Parwanoo-Shimla (4 lane) Himachal Pradesh 89.6 22,930

    Chhutmalpur-Saharapur-Yamunagarh-Haryana/UP border Uttarakhand/ UP 104.8 10,240

    EPS (6 lane) Haryana/ UP 135.0 NASolapur-Vedishi (4 lane) Maharashtra 98.7 9,700

    Hissar-Dabwali (4 lane) Haryana 145.8 13,320 PPPAC proposal circulated

    Total 2,023.30 208,530

    Source: Emkay Research, NHAI

    Substitution/exit policy to bring back momentum?

    In order to clear the clog in the sector, the government has made provisions to allow

    developers to sell projects (replace the SPV in consultation with lenders) irrespective of the

    stage of construction. The substitution policy entails the SPV to hold a 51% stake in the

    project post the sale. However, according to the NHAI, there are no restrictions on second

    sale. The decision would be applicable to following projects:

    The on-going 2- and 4-laning NHAI projects, where financial closures have beenachieved by the concessionaire, but COD has not yet been declared by the authority.

    The 6-laning NHAI projects, where financial closures have been achieved by theconcessionaire, but a project completion certificate has not yet been declared by the

    authority.

    Completed 2-, 4- and 6-laning NHAI projects awarded in BOT mode. All new NHAI projects under PPP yet to be bid out in BOT mode in line with case a, b,

    and c as the case may be.

    The provision substitution has always been in-built in the model concession

    agreement:

    Concession agreement for 2000: 51% during the construction period for 3 yearsfollowing COD and to hold 26% for the remaining concession period.

    Concession agreement post-November 2009 (B. K. Chaturvedi Committee): 51%during the construction period till COD, and for a period up to 3 years, the bidder can

    reduce the shareholding to 33%. Thereafter, the shareholding can be brought down to

    26% for the remaining concession period.

    The current concession agreement provides a 51% stake during the constructionperiod for 2 years following COD.

    However, the current concession agreement contains provision for substitution of the

    existing concessionaire to lenders, and such a substitution could have been involved in

    case of: (a) financial default (delays of 3 months in servicing debt), (b) concessionaire

    default (lender gets 270 days to substitute concessionaire), and (c) other cases of breachof provisions of MCA.

  • 7/21/2019 Construction Sector Update_141013

    7/32

    Construction Sector Update

    Emkay Research October 14, 2013 7

    Substitution/exit policy to help financially viable projects

    Arguably, the move would benefit only financially viable projects (presumably, the projects

    will not have too many problems), the exit option may not garner interest for projects which

    have been bid aggressively (buyers focus only on value generating projects, and it lacks

    incentives to share upfront losses). But the real problem lies with economically unviable

    projects. However, we do not rule out possibilities, where weaker developers could use this

    exit option to sell their stakes in projects (both completed and under-construction can besold) and use the resulting equity in other projects or on fresh bids without being blacklisted

    for not complying with concession agreement commitments. Besides, such provision can

    also help lenders to exercise greater control over projects funded by them (creates

    flexibility to substitute concessionaires, particularly the non-performing ones).

    Exit policy for projects achieved appointed date

    It is to be noted that the substitution of the SPV would be applicable for projects that have

    achieved the appointed date (all clearances related to EC and FC and other pre-conditions

    of the NHAI). However, we have observed that of the total 47 projects tendered in FY12,

    only eight projects have commenced construction till June 2013. This implies that the

    majority of the projects were not given the appointed date. This move, we believe, would

    not benefit these projects. It also presents ambiguity about whether the tax holiday that thefirst SPV is eligible for would be passed on to the new SPV, the additional cost of new

    stamp duty for forming a new SPV, which is usually 2.5% of the value of the transaction,

    and the imposition of penalty for exiting the projects.

    83% of projects awarded in FY12 yet to commence construction

    The NHAI awarded 15,894km of road projects over FY10-13, both in BOT and EPC mode,

    with 98% of the projects on a BOT basis. However, the strong tendering activity did not

    corroborate the real progress on the execution front. We have observed that of the total 47

    projects tendered during FY12, only eight projects commenced construction activity till

    June 2013, increasing the average time to begin construction after a BOT project is

    awarded to 18 months (the difference between the LOA date and till date). This is likely to

    increase even further if the current clog is not cleared soon. Among the 11 projects

    tendered in FY13, only one has started construction, which implies that the average time to

    commence construction is 10-12 months, as 80% of the projects were tendered in 1HFY13.

    This is expected to increase in the future. The NHAI targets to undertake 2500km of

    construction activity in FY14E (the target was 2580km in FY13), with 637km of road

    construction already completed till July 2013.

  • 7/21/2019 Construction Sector Update_141013

    8/32

    Construction Sector Update

    Emkay Research October 14, 2013 8

    Exhibit 8: Out 47 projects tendered during FY12, only eight projects commenced construction till date

    Projects Bidder Award date Km Type Construction Start date

    Nagpur-Wainganga bridge JMC projects, Artefact projects May-11 45 BOT Apr-12

    Panikholi-Rimoli Gayatri projects Aug-11 163 BOT May-13

    2 laning of Kisnagiri-Tindivanam Transitory-OJSC corporation May-11 176 Annuity Apr-12

    Vijaywada-Machhlioatnam Madhucon projects Nov-11 64 BOT

    Kota -Jhalwar Keti construction Apr-11 88 BOT

    Rampur-Kathgodam Era infra-OJSC-SIBMOST Nov-11 93 BOT

    MH/KNT Border Sangareddy L&T IDPL Nov-11 145 BOT

    Hospet Chitradurga Ramkey infra Nov-11 120 BOT

    4-laning Solapur-Bijapur Sadbhav eng Mar-12 110 BOT

    4-laning of Cuttcuk-Aangul Ashoka Buildcon Nov-11 12 BOT

    4-laning of UP Harayana border-Yamunagar-Saha-Barwala Gammon Infra Mar-12 107 BOT

    4-laining of Solapur-Maharashtra/KTK section Coastal-srie Consortium Dec-11 100 BOT

    4-laning of Rohtak-Jind Vijai infra Dec-11 48 BOT

    4-laining of Mulbagal-Karnatka/AP Border JSR Construction Mar-12 22 BOT

    4-laining of Kiratpur ner chowk IL&FS transportation Feb-12 84 BOT

    Beawer-Pali-indwara L&T IDPL May-11 244 BOT Dec-112-laining with PS Motihari-Raxaul Tantia-Jiangsu Jan-11 69 BOT Oct-11

    4-laning of Punjab-Harayana border-Jind Unity Infra Mar-12 68 BOT

    2-laning of Jowai-Meghalaya/Assam border Simplex infra Mar-12 102 BOT

    Patna Buxar Gammon infra Nov-11 124 BOT

    4- laning of Obedullnganj-Betul Transitory Feb-12 125 BOT

    4-laning of Khagaria-Bakhtiarpur Navayuga Engineering Mar-12 112

    4-laning of Hoskote-Dobbaspet Transitory-OJSC Consortium Mar-12 80 BOT

    4-laining of Jalgaon-Maharashtra/Gujarat L&T IDPL Mar-12 208 BOT

    4-laining of Amravati-Jalgoan L&T IDPL Mar-12 275 BOT

    Jabalpur to Lakhanadone Gannon Dunkerley Jul-11 80 BOT

    4-laning of Gwalior-Shivpuri Essel infraprojects Sep-11 125 BOT

    4-laning of Shivpuri-Dewas GVK Transportation Sep-11 330 BOT

    4-laning of Raipur-Bilaspur IVRCL Asset holding Nov-11 126 BOT

    Rehabitation & upgradation to Birmitrapur to barkote Gammon infrastructure Mar-12 125 BOT

    4-laning to Hospet-Bellary-Karnataka/AP PNC Infratech-BF utility Oct-11 95 BOT

    4-laning of Mahulia to Behgora to Kharagpur Simplex infrastructure Dec-11 127 BOT

    4-laning of Gomti-Chauraha-udaipur Sadbhav Engg, Arvee Mar-12 79.3 BOT

    4-laning of Meerut-Bulandshahar C&C construction Sep-11 66 BOT

    4-laning of Lucknow-Sultanpur Essar-Atlanta(JV) Oct-11 125 BOT

    2-laning of Muzaffarpur-Barauni KNR, frischmann prabhu Oct-11 107 BOT Jul-12

    Lucknow-Raibareli Essel infratructure Nov-11 70 Annuity

    4-laning of Angul, Sambalpur Abhijit Roads Nov-11 153 BOT

    4-laining of Jabalpur-Katni-Rewa Soma Tollways Aug-11 225 BOT6-laning of Gundugolanu-Rajamundry IVRCL asset & holding Mar-12 120 BOT

    6-laning of Anandapuram-visakapatnam-Anakapalli Transtroy-OJSC corporation Mar-12 58 BOT

    Ahmedabad to Vadodra IRB infrastructure Apr-11 102 BOT Jan-13

    6-lanining of Aurangabad-Barwa Adda KMC construction Mar-12 221 BOT

    Vijaywada-Gundugolanu Gammon Infra Feb-12 103 BOT

    Eatawah-Chakeri (Kanpur) Oriental structural Nov-11 160 BOT Mar-13

    Agra-Etawah Bypass Ramky Infra Nov-11 124 BOT

    6-laning of Kishangarh-Udaipur-Ahmedabad GMR Infra Sep-11 555 BOT

    Source: Emkay Research, NHAI

  • 7/21/2019 Construction Sector Update_141013

    9/32

    Construction Sector Update

    Emkay Research October 14, 2013 9

    EPC to propel momentum?

    As awarding activity has stagnated in FY13 and 1HFY14E for various reasons discussed

    above, the NHAI is trying to make progress to get the order momentum back on track via

    awarding EPC projects. Till date, the NHAI has awarded six projects of 356km via the EPC

    route. It is targeting to tender awards of 2000km in 2HFY14E.

    Features of EPC Model concession agreement:The agreement is stringent with regard to technical criteria, where EPC contracts have set

    minimum criteria of 2.5x the estimated project cost for projects and construction business

    (both highways and other core sectors combined) carried out by the bidder over the past 5

    financial years. This compares with the BOT contract requirement of 1x the project costs

    worth of project business (highways and other core sectors) accumulated over the past 5

    years.

    Leeway provided on financial net worth. The concession agreement currently providesleeway in terms of minimum net-worth threshold, which is at 10% of the project cost as

    against 25% of the project cost for BOT contracts.

    DLP (defect liability period) of 2 years on completion of the project highway andadditional DLP for major bridges and structures of 3 years (total 5 years).

    Defined maintenance period of 2 years after the completion of work; 1.5% and 2% ofthe contract price to be paid to the contractor in the first and second year, respectively.

    Incentive for the contractor for early completion in the form of a bonus. Damages up to 1% of the project cost would be paid by the authority on account of any

    delay from their side.

    The contractor cannot sub-contract any work in more than 70% of the total projectlength.

    The EPC contractallows for a JV of maximum three players, with the lead memberresponsible for satisfying 60%of technical and financial requirements (others have tosatisfy 30% of requirements). This is in addition to the weighted score exceeding the

    technical and financial requirements.

    Large players may deter to participate in EPC projects

    Our discussions with the NHAI and road companies reveal aggressive biddings across

    EPC projects in the past, since the EPC qualification document, as per our understanding,

    encourages participation with no cap on the number of bidders (it is leant that some bidders

    have quoted at a 30% discount to the NHAI benchmark cost) in small-size projects of

    Rs3bn (20 bidders) and project size of Rs3-5bn (10 bidders). We consider this aggressive

    bidding in EPC projects as generation of negative value for bidders, as: a) scalability of

    margins is capped in EPC, b) project value is at risk due to delays in land acquisition (this

    would increase overheads), and c) if any change in scope of work, which ultimately would

    put project completion at risk.We also believe that small project size of Rs3-4bn (Rs30-

    40mn/km) may dissuade large players such IRB Infrastructure and ITNL.

  • 7/21/2019 Construction Sector Update_141013

    10/32

    Construction Sector Update

    Emkay Research October 14, 2013 10

    Exhibit 9: Projects to tendered on EPC basis

    Road Stretch State (kms) Cost (Rs.mn) Status

    Bheem-Parsoli including Bheem & Parsoli Bypass Rajasthan 33.0 1,000 Awarded

    Parsoli-Gulabpura Rajasthan 36.3 1,140 Awarded

    Jhalawar-Rajasthan/ Madhya Pradesh Border Rajasthan 62.2 1,770 Awarded

    Merta City-Lambia-Jaitaran-Raipur Rajasthan 52.8 1,580 Awarded

    Raipur-Bheem (Jassa Khera) Rajasthan 32.4 1,490 Awarded

    Ambedkarnagar-Raebareilly (2 lane) Uttar Pradesh 155.9 4,960 Bids invited

    Raebareilly-Banda (2 lane) Uttar Pradesh 133.3 3,510 Bids invited

    Ladnu Nimbi Jodhan-Degna-Merta City (2 lane) Rajasthan 139.0 3,680 Bids invited

    Bhilwara-Ladpura (2 lane) Rajasthan 67.8 2,370 Bids invited

    Padhi-Dahod (2 lane) Rajasthan 85.6 2,790 Proposal given

    Unaira-Gulabpura (2 lane) Rajasthan 214.0 5,710 RFP stage

    Sitarganj-Tanakpur (2 lane) Uttarakhand 52.2 2,200 -

    Karauli-Dholpur (2 lane) Rajasthan 100.9 2,890 -

    Biharsharif-Barbigha-Mokama (2 lane) Bihar 56.3 1,940 -

    Chhapra-Rewaghat-Muzzaffarpur (2 lane) Bihar 75.0 3,050 -

    Patna-Gaya-Dhobi (4 lane) Bihar 127.2 10,270 -Jalandhar-Amritsar (6 lane) Punjab 20.0 4,930 -

    Thanjavur-Pudukkotai (2 lane) Tamil Nadu 55.2 1,700 -

    Tirumayam-Mannamadurai (2 lane) Tamil Nadu 77.7 2,520 -

    Bareilly-Sitarganj (2 lane) UP 74.5 2,970 -

    Uncha Nagar-Khanuawa-Roppas-Dholpur (4 lane) Rajasthan 75.0 - -

    Bar-Bilara-Jodhupur (2 lane) Rajasthan 125.0 - -

    Barmer-Sanchor-Gujarat Border (2 lane) Rajasthan 154.0 - -

    Total 2,005.10 62,470

    Source: NHAI

  • 7/21/2019 Construction Sector Update_141013

    11/32

    Construction Sector Update

    Emkay Research October 14, 2013 11

    To reduce competitive intensity further among new BOT projects

    With the competitive intensity edging lower in FY13 across 11 projects, developers stayed

    away for putting final bids across projects barring one project, where erratic bidding was

    witnessed in the Walajahpet-Poonamallee road project, with 19 financial bids being placed.

    We analysed 38 projects accounting for around 50% of the total length awarded by the

    NHAI since FY11. In FY13, the final participation (final bids submitted as percentage of pre-

    qualified bidders) has fallen sharply, barring four projects, which witnessed double-digitparticipation. The average participation from pre-qualified players in the final bidding for the

    projects awarded between FY11-12 has declined from 36% to 13% for the projects

    awarded in FY13. We also see an increase in the awarding activity of EPC road projects

    will garner interest for core construction players, thereby further reducing competitive

    intensity in the BOT space. Given that 2000km is ready to get awarded via the BOT route,

    we believe, developers who have the financial muscle will benefit the most in the next

    round of bidding.

    Exhibit 10: Competitive intensity amongst developers

    Date Name of Project Winners

    Cost

    (Rs

    bn)

    Length

    (km)

    Final

    bidders

    Players

    pre-

    qualified

    % Final

    bids

    participationApr-11 Ahmedabad Vadodara IRB Infrastructure 49.2 195 13 22 59%

    Apr-11 Beawar-Pali-Pindwara L&T 23.9 244 16 19 84%

    May-11 Barwa Panagarh DSC 16.7 123 9 20 45%

    Jul-11 Kishangarh--Ahmedabad GMR Infra 53.9 556 7 11 64%

    Sep-11 Gwalior Shivpuri Essel Infraprojects 10.6 125 15 28 54%

    Sep-11 Shivpuri Dewas GVK 28.2 330 14 19 74%

    Oct-11 Lucknow Sultanpur Essar - Atlanta 10.4 126 12 34 35%

    Nov-11 Cuttak Angul Ashoka Buildcon 11.2 112 16 27 59%

    Nov-11 Etawah and Chakeri (Kanpur) Oriental Structural 14.9 160 9 35 26%

    Nov-11 Hospet Chitradurga Ramky Infra 10.5 120 14 37 38%

    Nov-11 Mah/KNT- Sangareddy L&T 12.7 145 19 37 51%

    Nov-11 Patna - Buxar Gammon Infra 8.1 105 1 36 3%

    Nov-11 Raipur Bilaspur IVRCL 12.2 127 17 33 52%

    Dec-11 Bikaner - Suratgarh MBL Infra 5.1 172 6 33 18%

    Dec-11 Chittorgarh Neemachah Chetak Enterprises Ltd. 5.1 117 9 36 25%

    Jan-12 Kiratpur - Ner chowk IL&FS Transportation 18.2 113 4 28 14%

    Jan-12 Obdellagang - Betul Transtroy 9.1 121 6 36 17%

    Mar-12 Amravati Jalgaon L&T 25.4 275 12 22 55%

    Mar-12 Anadpuram- Visakhapatnam - Ankapalli Transtroy - OJSC 8.4 58 6 35 17%

    Mar-12 Gomti Chauraha - Udaipur Sadbhav Engineering 11.1 79 10 39 26%

    Mar-12 Hoskote - Dobaspet Transtroy - OJSC 7.2 80 4 36 11%

    Mar-12 Jalgaon - Guj/Mah Border L&T 19.7 209 17 29 59%

    Mar-12 Jind - Punjab/Haryana Border Unity infrastructure 4.4 69 5 40 13%

    Mar-12 Kharagpur-Baleshwar IL&FS Transportation 4.8 119 5 40 13%

    Mar-12 Rajahmundry - Gundugulunu IVRCL Asset 16.2 121 3 35 9%Mar-12 Sikar - Bikaner IL&FS Transportation 6.3 238 1 30 9%

    Mar-12 Solapur - Bijapur Sadbhav engineering 11.0 110 16 38 42%

    Apr-12 Bridge across Narmada (Vadodara - Surat section) HCC 5.1 6 2 35 6%

    May-12 Walajahpet - Poonamallee Essel project 12.9 93 19 37 51%

    May-12 Goa karnataka - Kundapur IRB Infra 24.0 187 2 35 6%

    Jul-12 Raebareli-Jaunpur PNC Infratech 5.7 166 8 30 27%

    Jul-12 Coimbatore-Mettupalayam Transstroy-OJSC Consortium 5.9 54 6 35 17%

    Aug-12 Walayar-Vadakkancherry KNR Construction 6.8 54 1 32 3%

    Nov-12 Kashipur-Sitarganj Galfar Engg & Contracting SAOG 6.1 77 1 30 3%

    Nov-12 Rajasthan border-Fatehpur-Salasar Galfar Engg & Contracting SAOG 5.3 154 2 32 6%

    Nov-12 Rajsamand-Gangapur-Bhilwara 87 6.8 Sadbhav Engg Ltd Sadbhav Engg Ltd 6.8 87 1 35 3%

    Mar-13 Rohtak-Hissar Sadbhav Engg Ltd 9.6 99 5 34 15%

    Mar-13 Khed-Sinnar IL&FS Transportation Networks 13.5 138 4 40 10%

    Total 479.6 5,686 296 942 33%

    Source:

  • 7/21/2019 Construction Sector Update_141013

    12/32

    Construction Sector Update

    Emkay Research October 14, 2013 12

    Traffic growth muted

    Our analysis of traffic growth over a period of 17 quarters in 21 road projects owned by IRB

    infrastructure, Ashoka Buildcon, ITNL, GMR Infrastructure and Sadbhav Engineering

    shows a declining trend. The sectors flat traffic growth in the past 2-3 quarters can be

    attributed largely to: a) lower port traffic witnessed across major ports, which has been

    declining for seven consecutive quarters, b) early arrival of the monsoon, with the higher-

    than-expected rainfall during June-July 2013, and c) overall economic slowdown and theresultant lower GDP growth.

    Exhibit 11: Road Traffic growth Flattish

    Traffic grow th9.7

    3.74.9

    6.9

    3.1

    5.8

    1.8

    0.41.2

    0.0(1.3)

    0.0 (0.1)

    (2.0)

    -

    2.0

    4.0

    6.0

    8.0

    10.0

    12.0

    Q1FY11

    Q2FY11

    Q3FY11

    Q4FY11

    Q1FY12

    Q2FY12

    Q3FY12

    Q4FY12

    Q1FY13

    Q2FY13

    Q3FY13

    Q4FY13

    Q1FY14

    Source: Emkay Research , Companies

    Exhibit 12: Port traffic edged lower

    54 4

    55.8

    0.8

    (1.4)(1.4)

    (0.8)(5.4)(4.8)

    (2.2)(7.2)

    -8

    -6

    -4

    -2

    0

    2

    4

    6

    8

    Q

    1FY11

    Q

    2FY11

    Q

    3FY11

    Q

    4FY11

    Q

    1FY12

    Q

    2FY12

    Q

    3FY12

    Q

    4FY12

    Q

    1FY13

    Q

    2FY13

    Q

    3FY13

    Q

    4FY13

    Q

    1FY14

    Port traffic

    Source: Emkay Research , IPA

    Exhibit 13: Container traffic declined

    5.06.0

    5.06.0

    3.3

    5.7

    3.2

    0.2 (0.3)

    2.5

    (6.3)

    1.0

    (3.8)

    (8.0)

    (6.0)

    (4.0)

    (2.0)-

    2.0

    4.0

    6.0

    8.0

    Q1FY11 Q2FY11 Q3FY11 Q4FY11 Q1FY12 Q2FY12 Q3FY12 Q4FY12 Q1FY13 Q2FY13 Q3FY13 Q4FY13 Q1FY14

    Container traffic

    Source: Emkay Research, IPA

  • 7/21/2019 Construction Sector Update_141013

    13/32

    Construction Sector Update

    Emkay Research October 14, 2013 13

    Major amendments discussed under Model ConcessionAgreement

    Proposed amendments in pre-qualification criteria of the RFQ document

    The current RFQ document has been able to encourage a large number of bidders to

    participate in the pre-qualification process. It has also been observed that many bidders,

    who are not competent to undertake the project, are also getting pre-qualified. This isleading to problems in the post-award scenario of the projects with such bidders. The

    overcrowding and aggressive bidding by such bidders have also led to a situation, where

    reputed and competent bidders stay away. Lately, a number of projects with such bidders

    either have failed to achieve financial closure or are facing substantial delays in completion.

    Such projects in distress are susceptible to defaulting on loan repayments and becoming

    non-performing assets (NPAs). In the course of experience gained in evaluating the RFQ

    applications for various projects, it has been felt that some provisions of the Model RFQ

    required modifications and/or clarifications.

    A) Assessment of Available Capacity for execution of future projects

    The technical capacity of the applicant is calculated on the basis of aggregate

    project/construction execution experience under different categories of projects during thelast 5 financial years preceding the applications due date. However, the above

    methodology of assessing technical capacity only takes into account the past experience of

    the applicant and does not capture the available technical capacity of the firm at the time of

    bidding with respect to present commitment on deployment of resources for other projects

    undertaken by the firm for development/implementation. As a result, applicants with limited

    or no capacity available for execution of additional projects are also pre-qualified, and in

    the event of the project award are failing to either achieve financial closure or execute the

    project in a timely manner. Therefore, it is pertinent to consider the applicants

    committed resources/investments on the ongoing projects to arrive at the available

    technical capacity. Thus, it is proposed that in addition to assessing the past

    performance of project executions, the available bid capacity with respect to

    resource commitment in projects under development/execution may also be

    assessed while pre-qualifying the applicants.

    B)Assessment of Financial Capacity

    The applicants financial capacity is assessed on the basis of the net worth of the firm in the

    preceding financial year. In order to qualify, the net worth of the applicant is required to be

    minimum 25% of the total project cost for which the applications are invited, and the net

    worth of the applicant is computed as the sum of subscribed and paid-up equity and

    reserves from which the sum of revaluation reserve, miscellaneous expenditure not written-

    off and reserves not available for distribution to equity shareholders is deducted. However,

    it has been observed in a number of cases that applicants qualifying in the net worth

    criteria are failing to achieve financial closure or unable to infuse equity in the awarded

    projects due to unavailability of adequate equity capital and/or a highly leverage balance

    sheet of the applicant. It clearly demarcates that net worth as the only deciding factoris not the sufficient parameter to assess the applicants ability to arrange financing

    required for the project.

    Therefore, it has proposed to introduce the following additional qualification criteria in the

    RFQ document with respect to financial capacity of the applicants:

    (i) Adjustment of Net Worth with respect to Debt-Equity ratio of the Applicant:

    It is proposed that net worth of the applicants shall be suitably adjusted with a factor linked

    to the debt-to-equity ratio of the applicant. This will reduce the applicable net worth of the

    applicant in case of a highly leveraged entity, thus preventing it from qualifying for high-

    value projects.

  • 7/21/2019 Construction Sector Update_141013

    14/32

    Construction Sector Update

    Emkay Research October 14, 2013 14

    Exhibit 14: Adjustment to net worth for debt-equity ratio

    Debt-Equity Ratio Applicable Factor

    Less than or equal to 3:1 1

    More than 3:1 & upto 6:1 0.85

    More than 6:1 &upto 10:1 0.6

    More than 10:1 0.2

    Source: Emkay Research, NHAI

    (ii) Submission of Equity Financing Plan by the Applicants:

    It is proposed that applicants will have to furnish a detailed equity financing plan on the

    equity requirement with regard to the total project cost for the project indicated in the RFQ

    document. The proposed equity financing plan shall include submission of certificates with

    regard to sources of equity to the applicant. Additionally, the applicants shall also require to

    furnish their equity commitment for projects to be executed during the construction period

    of the project, which will prevent bidders from participating in projects unrealistically without

    ensuring availability of equity required for the project.

    Exhibit 15: TPC of the project that bidder has applied (Rsbn)

    Debt-Equity Project cost

    0-2.5 30% of TPC

    Above 2.5-upto-6.5 25% of TPC

    Above 6.5 205 of TPC

    Source: Emkay Research, NHAI

    (iii) Restriction on the Applicants on account of pending financial closure and non-

    performing assets

    It is proposed that applicants shall be restricted from participating in the project in case

    financial closure of three or more awarded projects is pending on the date of the RFQ

    submission for reasons attributable solely to the applicant. Currently, this provision is

    provided in the RFP document.

    Payment of Premium by the ConcessionaireWith a view to mitigating the initial cash-flow constraints, it is proposed that the payment of

    premium may start 3 years after COD for 4-laning projects, and from the scheduled project

    completion date for 6-laning projects. Further, keeping in view the likely increase in the

    cashflows of the projects and the reduction in debt service requirements, it is proposed that

    after the 10th anniversary of COD for 4-laning projects/project completion date for 6-laning

    projects, the percentage/absolute increase in premium would be higher compared with the

    initial period.

    The following options are being proposed:

    Option 1 Revenue Sharing Principle

    To ensure that there is no revenue sharing during the initial years of the project, it isproposed to modify the concession agreement provision as per the following:

    For 4-laning projects: Percentage revenue sharing would start from the fourth year ofCOD or thereafter (depending on the bid), and would increase by 1% every year till the

    tenth anniversary of COD. Thereafter, the increase would be 2% per year for the rest of

    the phase of the concession period.

    For 6-laning projects: Percentage revenue sharing would start from the scheduledproject completion date or thereafter (depending on the bid), and would increase by 1%

    every year till the tenth anniversary of project completion date. Thereafter, the increase

    would be 2% per year for the rest of the phase of the concession period.

    Option 2 Fixed Monetary Value Principle

    For 4-laning projects: Bidders should quote a specific monetary amount that is payableto the authority from the fourth year of COD, and this amount should increase by 5%

    per year till the tenth anniversary of COD. Thereafter, the increase would be 8% per

    year for the rest of the phase of the concession period.

  • 7/21/2019 Construction Sector Update_141013

    15/32

    Construction Sector Update

    Emkay Research October 14, 2013 15

    For 6-laning projects: Bidders should quote a specific monetary amount that is payableto the authority from the scheduled project completion date, and this amount should

    increase by 5% per year till the tenth anniversary of completion of construction.

    Thereafter, the increase would be 8% per year for the rest of the phase of the

    concession period.

  • 7/21/2019 Construction Sector Update_141013

    16/32

    Your success is our success

    Emkay

    Comp

    anyUpdate

    Emkay Global Financial Services Ltd. 16

    Financial Snapshot (Consolidated) (Rsmn)

    YE- Net EBITDA EPS EPS RoE EV/

    Mar Sales (Core) (%) APAT (Rs) % chg (%) P/E EBITDA P/BV

    FY12A 31,307 13,735 43.9 4,960 14.9 9.6 18.8 5.3 5.6 0.9

    FY13A 36,872 16,333 44.3 5,567 16.7 12.2 20.4 4.7 5.5 1.0

    FY14E 41,433 18,705 45.1 4,471 13.5 -19.7 16.1 5.8 5.7 0.9

    FY15E 44,109 21,184 48.0 5,636 17.0 26.1 17.8 4.6 5.9 0.8

    IRB Infrastructure

    Separating Fundamentals from the Noise

    October 14, 2013

    Rating

    Buy

    Previous Reco

    Buy

    CMP

    Rs78

    Target Price

    Rs158

    EPS Chg FY14E/FY15E (%) NA/NA

    Target Price change (%) -7

    Nifty 6,096

    Sensex 20,529

    Price Performance

    (%) 1M 3M 6M 12M

    Absolute 1 -22 -31 -50

    Rel. to Nifty -1 -25 -38 -54

    Source: Bloomberg

    Relative price chart

    50

    75

    100

    125

    150

    175

    Oct-12 Dec-12 Feb-13 Apr-13 Jun-13 Aug-13 Oct-13

    Rs

    -70

    -56

    -42

    -28

    -14

    0%

    IRB Infrast ructure (LHS) Rel to Nifty (RHS) Source: Bloomberg

    Stock DetailsSector Construction

    Bloomberg IRB IB

    Equity Capital (Rs mn) 3,324

    Face Value(Rs) 10

    No of shares o/s (mn) 332

    52 Week H/L 158/ 52

    Market Cap (Rs bn/USD mn) 26/ 427

    Daily Avg Volume (No of sh) 3,061,331

    Daily Avg Turnover (US$mn) 3.7

    Shareholding Pattern (%)

    Sep'13 Mar'13 Dec'12

    Promoters 62.9 62.9 62.7

    FII/NRI 22.3 22.3 22.7

    Institutions 4.0 4.0 4.0

    Private Corp 3.9 3.9 4.3

    Public 6.9 6.9 6.3

    Source: Bloomberg

    Nitin Arora

    [email protected]

    +91-22-66242491

    Ajit Motwani

    [email protected]

    +91-22-66121255

    n Strong cashflows from a healthy mix of operating and under-

    construction assets, and moderate gearing the key

    competitive differentiators in a capital-intensive business

    n Earnings to remain flat over FY13-15E. But we expect a

    CAGR of 10% in cash profits, providing the ability to fund

    equity in new projects

    n Biggest beneficiary of new road projects to be tendered out

    in 2HFY14E. 4 projects scheduled to commence toll

    collections over the next.

    n Attractive valuations at 0.8x P/BV & 5.9x PE near the end

    2008 troughs IRB remains our preferred road BoT asset play.

    Maintain buy with the revised target price of Rs158/share

    Equity requirement of Rs3-4bn in FY14E, Rs17-18bn over 2-3 yearsIRB Infrastructure Developers (IRB) has 15 road projects under it portfolio, of which 10

    are currently operational and the rest are under construction. The companys total equity

    requirements over the next 2-3 years have been estimated at Rs17bn. On account of

    commissioning of 4 road projects i.e. Jaipur-Deoli, Amravati-Talegaon, Amritsar-

    Pathankot, & Ahmedabad-Vadodra along with EPC arm will garner cumulative operating

    cash flow Rs19.6 bn from FY13-15E. These, coupled with current cash of Rs14.7bn,

    would be sufficient to meet equity requirements of the company for the next 2 years.

    Peak D:E of 2.33x still manageable

    IRB Infrastructures consolidated debt (adjusted for loans and advances) stands at

    Rs79bn, including its standalone debt of Rs11.4bn, with cash balance of Rs14.7bn as of

    March 31, 2013. Debt worth Rs71.3bn, accounted for individual road projects, is fairlypositive for the company compared to other road developers like ITNL, which has debt

    worth Rs37bn on its standalone balance sheet as of March 2013, with no certainty of

    recurring income to offset the surge in the interest cost. We estimate peak debt (for

    current projects in its kitty) of Rs116bn, which would imply debt equity of 2.33x.

    Current price implies less than 1x book value adjusted for Mumbai-Pune

    The stock has corrected 34% over the last 3 months. The current market price of Rs79

    (market capitalization of Rs26.2bn) implies value of 0.4x the invested book (historically

    seen at 1x) adjusted for the Mumbai-Pune Expressway Project (MIPL). IRB has invested

    Rs33bn in FY13 as equity investments, and loans and advances in BOT road projects.

    We have adjusted the value for MIPL of Rs13.6bn (FY13 revenue is Rs4.16bn; likely to

    report revenue of Rs4.39bn and Rs5.43bn in FY14E and15E, respectively), with

    relatively low debt of Rs8.76 bn. MIPL (Mumbai - pune ) accounts for 24% of our SOTPand 40% of value derived for the total BOT road assets. This is one the non-disputable

    road assets, which has certainty of cashflows, with a revenue CAGR of 14% over FY13-

    15E as against 13% during FY11-13. We understand that there have been concerns

    over the recent project (Ahmedabad-Vadodara), with relatively aggressive bid & traffic

    disappointment. However, we believe, Amritsar-Pathankot, Jaipur-Deoli and Amravati-

    Talegaon projects have potential value, as these were won in a low-competitive

    environment and at high grant levels (close to 40%).

  • 7/21/2019 Construction Sector Update_141013

    17/32

    IRB Infrastructure Company Update

    Emkay Research October 14, 2013 17

    Despite strong execution E&C order-book at Rs56bn provide reasonable

    visibility; however, growth could remain subdued

    IRB Infrastructures order-book at the end of March 2013 stood at Rs 76.6bn. Out of this,

    Rs56bn worth of orders would be executed over the next 3 years. The backlog includes

    Rs23bn worth of Goa-Kundapur project, which the company added in Q2FY13.

    The companys construction revenue is likely to moderate, due to completion or nearingcompletion of its key projects. Recently, the Talegaon-Amravati project was completed,

    while Jaipur-Deoli, Amritsar-Pathankot and Tumkur are complete 95%, 90% and 85%,

    respectively. Irrespective of the completion of its four key projects, the company would able

    to maintain construction revenue for FY14E at the similar level of what it had garnered in

    FY13, due to increase in contributions from Ahmedabad-Vadodara and Goa-Kundapur

    (which is expected to be executed in 2HFY14E; it is waiting for financial closure) .

    IRB Infrastructure expects the bidding activity to regain momentum during Q3/Q4FY14

    (expects 1,000-2,000km of fresh projects to come up from the NHAI, while 3,000-4,000km

    to be bid out during 3Q/4QFY14E), and expects new orders to come from potential re-bids

    (projects stalled on account of non-achievement of financial closure and fresh biddings).

    Exhibit 16: Revenue CAGR of 9.4% over FY13-15E

    1724

    31 37

    41 44

    -

    10

    20

    30

    40

    50

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay Research

    Exhibit 17: EBITDA CAGR of 14% over FY13-15E

    8 10

    14 16

    19 21

    -

    5

    10

    15

    20

    25

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay Research

    Exhibit 18: PAT growth to remain Flat

    4.5 4.05.0

    5.64.5

    5.6

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay Research

    Exhibit 19: EPS

    13 1215

    1713

    17

    -

    2

    4

    6

    8

    10

    12

    14

    16

    18

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay Research

  • 7/21/2019 Construction Sector Update_141013

    18/32

    IRB Infrastructure Company Update

    Emkay Research October 14, 2013 18

    Exhibit 20: Flat EPC revenue growth

    10

    1721 26 26 24

    0

    5

    10

    15

    20

    25

    30

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay Research

    Exhibit 21: BOT revenue to surge higher

    7 8 9 11

    1520

    -

    5

    10

    15

    20

    25

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay Research

    Exhibit 22: Current market price implies less than 1x invested book value

    CMP 79

    No of shares 332

    Market cap Rsmn 26260

    Value for Mumbai Pune Rsmn 13,411

    Market cap adj. for Mumbai Pune project 12,849

    Investments (equity + L&A) in road projects at end-FY2013 33,075

    Investments in MIPL at end-FY2013 1,073

    Investments adjusted for MIPL 32,002

    Implied P/B (x) 0.40

    Source: Company, Emkay Research

  • 7/21/2019 Construction Sector Update_141013

    19/32

    IRB Infrastructure Company Update

    Emkay Research October 14, 2013 19

    Exhibit 23: Total Investments (Equity, Loans & advances )

    FY11 FY12 FY13

    Project Rsmn Loans & advances Loans & advances Loans & advances

    Investments in road projects Equity

    Short

    term

    Long

    term Total Equity

    Short

    term

    Long

    term Total Equity

    Short

    term

    Long

    term Total

    Thane-Bhiwandi bypass 611 611 611 18 629 611 611

    Mumbai-Pune Expressway 778 200 978 778 434 1212 778 295 1,073

    Pune-Sholapur 451 451 451 451 451 451

    Pune-Nashik 519 12 531 519 15 534 519 519

    Ahmednagar-Karmala-Tembhurni 80 0 80 80 80 80 80

    Bridge over Patalganga River-Kharpada 80 80 80 80 80 80

    Thane-Ghodbunder 222 707 929 222 500 722 222 6 228

    Bharuch-Surat 872 2,297 3169 872 5,472 6344 872 2680 3,552

    Integrated Road Development in Kolhapur 855 855 1,336 227 1563 1,336 566 1,902

    Surat-Dahisar 2,611 2611 4,653 1,117 5770 4,653 847.8 5,501

    Pathankot-Amritsar 355 1,180 257 1792 355 162 1,145 1662 774 7.9 2326.3 3,109

    Talegaon-Amravati 322 2 57 381 322 151 828 1301 364 352 1093.4 1,810

    Jaipur-Deoli 390 264 272 926 780 200 1,837 2817 975 480.62 2924.9 4,380Panji-Goa 311 929 1240 311.4 1,173 1484 311 1173.1 1,485

    Tumkur-Chitradurg 0 1,181 156 1337 476 476 952 1110 315.727 1110.7 2,537

    Ahmedabad-Vadodara Expressway 1,000 69 2,950 4019 1000 33.61 2950.0 3,984

    MVR Infra 801 972.92 1,775

    Subtotal - Investment in road projects 8,457 6,772 742 15971 12,846 7,832 8,942 29620.4 14,939 6,558 11578.2 33,075

    Investments in other subsidiaries

    Construction subsidiary 312 1,588 1900 312 1353.2 1665.2 312 957 1,269

    Real estate subsidiary 586 1 587 586 1 587 586 1 587

    Hospitality subsidiary 0 26 26 0 119.4 119.5 0.09 182 182

    Sindhudurg Airport 0 182 182 0 10.1 10.2 0.09 211 211

    Subtotal - Investment in other subsidiaries 898 1,796 2694 898 1483.81 2381.81 898 1351 2,249

    Total investments in subsidiaries 9,354 8,570 742 18666 13,744 9,316 8,942 32002 15,837 7,909 11,578 35,324

    Source: Company, Emkay Research

  • 7/21/2019 Construction Sector Update_141013

    20/32

    IRB Infrastructure Company Update

    Emkay Research October 14, 2013 20

    Maintain Buy with a Revised Target price of Rs 158

    With significant slow down in NHAI awarding activity (only 1300 km awarded in FY13

    Annual target ~9K kms) and possibly impact on NHAI funding plan on account of recent

    termination of road project we do not foresee meaningful increase in awarding activity by

    NHAI. Hence we have build in just Rs20bn of new project wins for IRB in FY14 similar to

    levels the company has achieved till FY13.

    With minimal funding requirement IRB remains well funded for exploiting new opportunities

    as and when NHAI awarding activity pick up. However in the mean time company is

    focusing on reducing its interest cost and has managed to lower the interest rates at

    Bharuch Surat by 150bps to 10.65% and is evaluating the prospect of refinancing debt of

    Surat Dahisar from IIFCL which will again lead to similar correction in interest rates at the

    project debt level.

    We have revised our target price lower by 6% as we lowered E&C multiple for construction

    business from 4x to 5x at Rs42/share (Earlier Rs53/share) on account lower carry forward

    order backlog as order offtake slows down.

    With 4 projects schedule to commence toll collection over the next year, minimal funding

    requirement and benefits of lower interest rate, we believe IRB remains the Road BoT

    asset to play. We maintain our BUY rating and revised our TP to Rs 158 as compared toRs169 earlier.

    Exhibit 24: SoTP Fair value at Rs 158

    Asset Operated Holding

    Valuation

    Measure Disc rate

    Value

    (Rs mn)

    Value

    /Share

    EPC Business 100% PER 4 14128 42.5

    PV of O&M Contracts 100% NPV 13.5% 3,178 9.6

    Value of Construction segment - (a) 17,306 52

    Mumbai Pune Expressway & NH4 100% FCFE 12.5% 13,411 40.3

    Surat Dahisar 90% FCFE 13.5% 2,590 7.8

    Bharuch Surat 100% FCFE 13.5% 3,442 10.4

    Mohol-Mandrup Road 100% FCFE 13.5% -37 -0.1

    Kharpada-Patalganga Bridge 100% FCFE 13.5% 226 0.7

    Ahmednagar Tembhurni Road 100% FCFE 13.5% 244 0.7

    Thane Ghodbunder 100% FCFE 13.5% 1,109 3.3

    Pune Nashik 100% FCFE 13.5% 306 0.9

    Pune Sholapur 100% FCFE 13.5% 522 1.6

    Thane Bhiwandi Bypass 100% FCFE 13.5% 1,462 4.4

    Kolhapur City Roads 100% FCFE 14.5% 3,268 9.8

    Namakkal - Omallur - NH-7 100% FCFE 13.0% 656 2.0

    Amritsar Pathankot 100% FCFE 14.5% 6,531 19.7

    Jaipur - Deoli 100% FCFE 14.5% 6,952 20.9

    Amravati Talegaon 100% FCFE 14.5% 2,970 8.9Tumkur Chitradurga 100% FCFE 14.5% 200 0.6

    Ahmedabad Vadodara 100% FCFE 14.5% -3,731 -11.2

    Goa - Kundapur 100% FCFE 15.5% -610 -1.8

    Gross value of BOT 39,513 119

    Add: PV of Loans to SPV 2,411 7.3

    Less : Net Debt at Parent Level -8,275 -24.9

    Value of BOT - Net of debt - (b) 33648.7 101.2

    Aryan Infra Investment - (C) 66% Book value 1,650 5.0

    Total Value - (a+b+c) 56,137 158

    Source: Emkay Research

  • 7/21/2019 Construction Sector Update_141013

    21/32

    IRB Infrastructure Company Update

    Emkay Research October 14, 2013 21

    Key Financials (Consolidated)

    Income Statement

    Y/E Mar (Rsmn) FY12A FY13A FY14E FY15E

    Net Sales 31,307 36,872 41,433 44,109

    Growth (%) 28.4 17.8 12.4 6.5

    Expenditure 17,572 20,540 22,728 22,925

    Employee Cost 1,376 1,557 1,731 1,722

    Other Exp 0 0 0 0

    SG&A 970 1,223 1,330 1,330

    EBITDA 13,735 16,333 18,705 21,184

    Growth (%) 25.6 18.9 14.5 13.3

    EBITDA marg in (%) 43.9 44.3 45.1 48.0

    Depreciation 2,970 4,415 5,581 6,538

    EBIT 10,765 11,918 13,124 14,646

    EBIT mar gin (%) 34.4 32.3 31.7 33.2

    Other Income 1,252 1,301 1,236 1,193

    Interest expenses 5,505 6,153 7,730 7,917

    PBT 6,512 7,066 6,630 7,923

    Tax 1,552 1,530 2,221 2,390

    Effective tax rate (%) 23.8 21.7 33.5 30.2

    Adjusted PAT 4,960 5,536 4,409 5,533

    Growth (%) 6.9 11.6 -20.4 25.5

    Net Marg in (%) 15.8 15.0 10.6 12.5

    (Profit)/loss from JVs/Ass/MI 0 -31 -62 -103

    Adj. PAT After JVs/Ass/MI 4,960 5,567 4,471 5,636

    E/O items 0 0 0 0

    Reported PAT 4,960 5,567 4,471 5,636

    PAT after MI 4,960 5,567 4,471 5,636

    Growth (%) 9.6 12.2 -19.7 26.1

    Balance Sheet

    Y/E Mar (Rsmn) FY12A FY13A FY14E FY15E

    Equity share capital 3,324 3,324 3,324 3,324

    Reserves & surplus 25,243 29,232 32,630 37,139

    Net worth 28,566 32,556 35,954 40,463

    Minority Interest 1,123 1,092 1,030 927

    Secured Loans 50,455 66,349 72,259 90,491

    Unsecured Loans 17,913 12,712 12,712 12,712

    Loan Funds 68,367 79,060 84,970 103,203

    Net deferred tax liability 259 259 259 259

    Total Liabilities 98,315 112,967 122,213 144,851

    Gross Block 57,817 57,918 91,005 96,030

    Less: Depreciation 2,283 2,830 3,368 3,917

    Net block 55,534 55,088 87,636 92,113

    Capital work in progress 24,452 49,160 36,024 48,548

    Investment 186 620 620 620

    Current Assets 28,399 27,205 17,714 16,802

    Inventories 1,624 2,488 2,171 1,003

    Sundry debtors 141 310 1,033 1,046

    Cash & bank balance 18,208 14,710 4,813 5,057

    Loans & advances 8,427 9,696 9,696 9,696

    Other current assets 0 0 0 0

    Current lia & Prov 10,265 19,106 19,954 13,403

    Current liabilities 10,017 15,996 16,844 10,293

    Provisions 248 3,110 3,110 3,110

    Net current assets 18,134 8,099 -2,240 3,399

    Misc. exp 9 0 0 0

    Total Assets 98,315 112,967 122,041 144,680

    Cash Flow

    Y/E Mar (Rsmn) FY12A FY13A FY14E FY15E

    PBT (Ex-Other income) 5,260 5,765 5,394 6,730

    Depreciation 2,970 4,415 5,581 6,538

    Interest Provided 5,505 6,153 7,730 7,917

    Other Non-Cash items 0 0 0 0

    Chg in working cap -779 476 442 -5,395

    Tax paid -1,587 -2,422 -2,221 -2,390

    Operating Cashflow 11,369 14,387 16,925 13,400

    Capital expenditure -24,201 -25,456 -24,994 -23,538

    Free Cash Flow -12,832 -11,069 -8,068 -10,138

    Other income 1,252 1,301 1,236 1,193Investments -3,702 1,680 0 0

    Investing Cashflow -25,484 -21,167 -23,758 -22,344

    Equity Capital Raised 0 0 0 0

    Loans Taken / (Repaid) 24,457 14,815 5,910 18,232

    Interest Paid -5,505 -6,153 -7,730 -7,917

    Dividend paid (incl tax) -1,319 -1,191 -1,245 -1,127

    Income from investments 0 0 0 0

    Others 0 0 0 0

    Financing Cashflow 17,633 7,471 -3,064 9,188

    Net chg in cash 3,518 691 -9,897 244

    Opening cash position 12,000 18,208 14,710 4,813

    Closing cash position 15,518 18,899 4,813 5,057

    Key Ratios

    Y/E Mar FY12A FY13A FY14E FY15E

    Profitability (%)

    EBITDA Margin 43.9 44.3 45.1 48.0

    Net Margin 15.8 15.0 10.6 12.5

    ROCE 14.1 12.9 12.9 12.5

    ROE 18.8 20.4 16.1 17.8

    RoIC 24.0 22.9 20.3 17.1

    Per Share Data (Rs)

    EPS 14.9 16.7 13.5 17.0

    CEPS 23.9 30.0 30.2 36.6

    BVPS 85.9 78.4 88.7 102.2DPS 1.8 4.0 3.2 0.0

    Valuations (x)

    PER 5.3 4.7 5.8 4.6

    P/CEPS 3.3 2.6 2.6 2.1

    P/BV 0.9 1.0 0.9 0.8

    EV / Sales 2.4 2.5 2.6 2.8

    EV / EBITDA 5.6 5.5 5.7 5.9

    Dividend Yield (%) 2.3 5.1 4.1 0.0

    Gearing Ratio (x)

    Net Debt/ Equity 1.8 2.5 2.7 2.9

    Net Debt/EBIDTA 3.7 3.9 4.3 4.6

    Working Cap Cycle (days) -0.9 -65.4 -62.1 -13.7

  • 7/21/2019 Construction Sector Update_141013

    22/32

    Your success is our success

    Emkay

    Compa

    nyUpdate

    Emkay Global Financial Services Ltd. 22

    Financial Snapshot (Consolidated) (Rsmn)

    YE- Net EBITDA EPS EPS RoE EV/

    Mar Sales (Core) (%) APAT (Rs) % chg (%) P/E EBITDA P/BV

    FY12A 56,056 14,656 26.1 4,970 25.6 14.8 20.2 4.3 8.3 0.8

    FY13A 66,449 18,396 27.7 5,194 26.7 4.5 16.4 4.2 8.8 0.6

    FY14E 64,185 19,171 29.9 4,368 22.5 -15.9 11.4 4.9 8.8 0.5

    FY15E 77,908 24,430 31.4 4,711 24.2 7.8 11.2 4.6 7.7 0.5

    IL&FS Transportation

    Higher Leverage to Suppress Earnings

    October 14, 2013

    Rating

    Hold

    Previous Reco

    Buy

    CMP

    Rs111

    Target Price

    Rs134

    EPS Chg FY14E/FY15E (%) NA/NA

    Target Price change (%) 3

    Nifty 6,096

    Sensex 20,529

    Price Performance

    (%) 1M 3M 6M 12M

    Absolute -7 -25 -39 -40

    Rel. to Nifty -9 -28 -45 -45

    Source: Bloomberg

    Relative price chart

    100

    125

    150

    175

    200

    225

    O ct -1 2 D ec -1 2 F eb -1 3 A pr -1 3 J un -1 3 A ug -1 3 O ct -1 3

    Rs

    -60

    -44

    -28

    -12

    4

    20%

    IL&FS Transportation (LHS) Rel to Nifty (RHS) Source: Bloomberg

    Stock DetailsSector Construction

    Bloomberg ILFT IB

    Equity Capital (Rs mn) 1,943

    Face Value(Rs) 10

    No of shares o/s (mn) 194

    52 Week H/L 229/ 97

    Market Cap (Rs bn/USD mn) 22/ 353

    Daily Avg Volume (No of sh) 88,829

    Daily Avg Turnover (US$mn) 0.2

    Shareholding Pattern (%)Jun10 May10 Dec10

    Promoters 46.3 46.5 46.5

    FII/NRI 43.3 43.6 42.6

    Institutions 6.5 7.0 7.0

    Private Corp 1.8 1.0 1.2

    Public 2.2 2.1 2.6

    Source: Bloomberg

    Nitin Arora

    [email protected]

    +91-22-66242491

    Ajit Motwani

    [email protected]

    +91-22-66121255

    n Robust order backlog (3x FY13 E&C rev) to help construction

    income CAGR of 24% over FY13-15E, but high margin fee

    income to stagnate, implying a muted EBITDA CAGR of 4%

    n Standalone leverage to surge higher to 2.2x, as ITNL pumps

    in equity (Rs24bn) to complete the projects

    n High leverage in the absence of meaningful rate cuts to

    exert pressure on standalone profitability

    n Dilution imminent in and post-FY15E, as standalone leverage

    unsustainable. Earnings highly leveraged to new orders.

    Retain hold with the revised target price of Rs134

    Construction revenue growth intact, but fee income to stagnate

    Supported by back-ended FY13 order wins (Rs38bn), ITNLs order-book currently

    stands at healthy Rs146bn. With robust revenue visibility (3.1x FY13E constructionrevenues), we expect the standalone construction revenues to surge at a CAGR of 24%

    over FY14-15E. In Q1FY14, the company witnessed execution delays in projects such

    as Chennai Nashri (due to regional violence and unrest) and Moradabad Bareilly (delays

    in land acquisition), besides delays in other projects caused by early monsoons.

    However, with majority of the fee income on new order wins has already been booked in

    FY13, we see fee income stagnating over FY13-15E (50% of the booked FY14E fee

    income in Q1 to edge lower from Q2 onwards). With only Rs3-3.5bn of residual fee

    income to be booked on the current backlog (driven largely by projects such as Khed-

    Sinnar and Barwa-Adda), arguably the company will have to significantly depend on new

    order wins for fee income growth. Hence, we see ITNLs fee income stagnating at

    Rs5.5bn, as we model an order inflow of Rs90bn over FY14-15E (Rs45bn each year).

    Muted EBIDTA a CAGR of 4%

    Since fee income is a high-margin stream of revenue for ITNL and the contribution of fee

    income to total revenues is expected to tumble from 17% in FY13E to 10.9% in FY15E

    as per our calculations, we estimate standalone EBIDTA growth to remain muted at a

    CAGR of 4% over FY13-15E, with the EBITDA margin likely to contract by 200bps and

    260bps in FY14E and FY15E, respectively.

    Leverage to surge higher putting pressure on standalone profitability

    Due to lower contribution of fee income to overall revenue, we see ITNL resorting to

    taking further debt on the standalone book to infuse equity requirements towards funding

    its new projects. The company plans to raise Rs15.5 bn via preferential issue (already

    raised Rs4 bn) and rights issue to address the equity requirement (Rs24 bn over FY13-

    15E) for future projects. We believe that even after raising funds at upper end 40% ofthe equity requirements will be funded by taking debt on standalone books (Q1FY14

    debt at Rs40 bn) and will increase further on account of new orders. Hence, we see a

    surge in debt on the standalone balance-sheet from Rs37bn in FY13 to Rs53 bn by

    FY15E, which would lead to further deterioration in its leverage ratios, which would

    increase the interest burden on ITNL. However, in case leverage increases further, it

    would become essential for the company to maintain its EBITDA at Rs6.5bn and Rs7bn

    in FY14E and FY15E, respectively, to service interest costs on standalone level.

  • 7/21/2019 Construction Sector Update_141013

    23/32

    IL&FS Transportation Company Update

    Emkay Research October 14, 2013 23

    Earnings highly leveraged to order inflows, high debt still remain a concern:

    Maintain Hold

    With robust order inflow in till FY13, ITNL has been able to deliver 17% earnings growth

    over FY10-13 led by its high margin fee income. However as ITNLs earning & cash flows

    are highly leverage to new order inflows, we believe sustaining such high growth rate in fee

    income is unlikely. Given this backdrop of decelerating high margin fee income growth, the

    high parent leverage (standalone debt at Rs53 bn with D:E at 2.2x in FY15E) could meanincreasing interest cost pressures for ITNL. High leverage in absence on meaningful rate

    cuts to put pressure on standalone profitability and could mean increasing interest cost

    pressures for ITNL. Dilution eminent in/post FY15E as standalone leverage unsustainable.

    We have cut our target price to Rs134 (Earlier TP 150) as we have adjusted traffic for some

    of the projects like kiratpur ner chowk (implied P/BV0.45x) as well as for projects like sikar

    Bikaner & khed sinnar and reduced our E&C multiple to EV EBITDA of 3x from 3.5x as

    construction earnings will edge lower in FY14E and construction earnings trajectory

    remains uncertain as some projects faces structural issues.

    Exhibit 25: Fee income to stagnate

    6.95.6 5.7 5.7 5.7

    5.2

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    (Rsbn)

    Fee income

    Source: Company, Emkay Research

    Exhibit 26: Fee income as a % of total revenue

    34%

    21%17%

    15%10.9%

    0%

    5%

    10%

    15%

    20%

    25%

    30%

    35%

    40%

    FY11 FY12 FY13 FY14E FY15E

    (Rsbn)

    Fee income as a % total revenue

    Source: Company, Emkay Research

    Exhibit 27: Consolidated debt to inch higher

    169

    3355

    102

    144 148

    1.6

    2.1

    3.3 3.6 3.4 3.5

    -

    50

    100

    150

    200

    FY10 FY11 FY12 FY13 FY14E FY15E

    (Rsbn)

    -

    0.5

    1.0

    1.5

    2.0

    2.5

    3.0

    3.5

    4.0

    Consolidated Debt Net Debt/equity

    Source: Company, Emkay Research

    Exhibit 28: Standalone debt to surge higher

    15.3 18.927.3

    37.4 41.553.5

    0.91.1

    1.4

    1.8 1.8

    2.2

    -

    0.5

    1.0

    1.5

    2.0

    2.5

    FY10 FY11 FY12 FY13 FY14E FY15E

    (Rsbn)

    0

    10

    20

    30

    40

    50

    60

    Standalone Debt Debt/equity

    Source: Company, Emkay Research

    Exhibit 29: Consolidated revenue

    24.1

    40.5

    56.166.4 64.2

    77.9

    0.0

    20.0

    40.0

    60.0

    80.0

    100.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    (Rsbn)

    Revenue

    Source: Company, Emkay Research

    Exhibit 30: Consolidated EBITDA

    8

    12

    1518 19

    24

    0

    5

    10

    15

    20

    25

    30

    FY10 FY11 FY12 FY13 FY14E FY15E

    (Rsbn)

    EBITDA

    Source: Company, Emkay Research

  • 7/21/2019 Construction Sector Update_141013

    24/32

    IL&FS Transportation Company Update

    Emkay Research October 14, 2013 24

    Exhibit 31: Consolidated PAT

    3.4

    4.35.0 5.2

    4.4 4.7

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    (

    Rsbn)

    PAT

    Source: Company, Emkay Research

    Exhibit 32: Consolidated ROE

    27.0

    22.220.2

    16.4

    11.4 11.1

    -

    5.0

    10.0

    15.0

    20.0

    25.0

    30.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    (%)

    ROE

    Source: Company, Emkay Research

    Exhibit 33: Standalone revenue

    8.5

    16.2

    27.733.7

    37.7

    47.9

    0

    10

    20

    30

    40

    50

    60

    FY10 FY11 FY12 FY13 FY14E FY15E

    (Rsbn)

    Revenue

    Source: Company, Emkay Research

    Exhibit 34: Standalone EBITDA

    5.48 5.32 5.52

    6.46 6.496.98

    0

    1

    2

    3

    4

    5

    6

    7

    8

    FY10 FY11 FY12 FY13 FY14E FY15E

    (Rsbn)

    EBITDA

    Source: Company, Emkay Research

  • 7/21/2019 Construction Sector Update_141013

    25/32

    IL&FS Transportation Company Update

    Emkay Research October 14, 2013 25

    Exhibit 35: SOTP fair value at Rs134hare

    SPV Holding

    Valuation

    Measure

    Disc

    rate

    Equity

    alue

    (Rs mn)

    Stake

    alue

    (Rs mn)

    alue/

    Share

    BOT

    Gujarat Road and Infrastructure company ltd 83.6% Operational FCFE 13% 7,525.5 6,292.1 32.4

    WGEL 100.0% Operational FCFE 14% 1,613.9 1,613.9 8.3

    Delhi - Noida 25.4% Operational FCFE 14% 6,268.8 1,589.1 8.2

    Gomti - Beawar 100.0% Operational FCFE 14% 350.4 350.4 1.8

    RIDCOR 50.0% Operational FCFE 14% 8,130.2 4,065.1 20.9

    RIDCORII 50.0% Under development FCFE 15% 3,783.6 1,891.8 9.7

    Pune Sholapur NH-9 Road Project 100.0% Under Construction FCFE 15% 2,846.3 2,846.3 14.7

    Chadrapur Warora Road Project 35.0% Under development FCFE 15% 1,683.5 589.2 3.0

    Narkatapally to Addanki Road Project 50.0% Under development FCFE 15% 3,288.7 1,644.3 8.5

    Moradabad Bareili Road Project 100.0% Under development FCFE 15% 7,088.7 7,088.7 36.5

    Kharagpur - Baleshwar 100.0% Under development FCFE 15% -258.3 -258.3 -1.3

    Kiratpur Ner Chowk 100% Under development FCFE 15% 2923 2923 15Sikar Bikaner 100% Under development FCFE 15% 829.8 829.8 4.3

    Khed Sinnar 100% Under development FCFE 15% 816.5 816.5 4.2

    Barwa Adda Panagarh 100% Under development FCFE 15% 623.5 623.5 3.2

    Toll Projects - (A) 47,514 32,905.4 169

    North Karnataka expressway ltd Road Project 94% Operational FCFE 13% 1,145.6 1,071.2 5.5

    Thiruvananthpuram Road Development Company Ltd Road Project 50% Operational FCFE 13% -468.7 -234.0 -1.2

    Andhra Pradesh expressway ltd Road Project 100% Operational FCFE 13% -494.9 -494.9 -2.5

    East Hyderabad expressway ltd Road Project 74% Under Construction FCFE 13% 537.2 397.5 2.0

    Hyderabad Ring Road 26% Under Construction FCFE 13% -54.9 -14.3 -0.1

    Hazaribaug Ranchi expressway ltd Road Project 74% Under Construction FCFE 14% 185.0 136.9 0.7

    Jharkhand - Ph - I Road Project 100% Under Construction FCFE 14% 157.2 157.2 0.8

    Jharkhand Ph - II Road Project 100% Under development FCFE 14% 544.9 544.9 2.8

    Shillong Jorbat Road Project 50% Under development FCFE 14% 1121.2 560.6 2.8

    Chenani Nashri Road Project 100% Under development FCFE 14% 1,791.0 1,791.0 9.2

    Annuity Projects - (B) 4,463.6 3,915.9 20.2

    Vansh Nimay infraprojects Ltd 100% Operational FCFE 14% 301.6 301.5 1.6

    ITNL ENSO Rail system limited 70% Under Construction FCFE 14% 1,159.2 811.5 4.2

    MP Check post 51% Under development BV 0.75x 1,174.2 880.6 4.5

    YuHe Project - Chonguin Road project 49% Operational BV 0.8x 1,176.0 6.1

    Urban Infra Projects - '(C) 2,635.0 3,169.6 16.3

    Investments in Elsamax 100% BV 1.0x 14.0 2,722.2 14.0Investments in other Companies 1,109.3 1,109.3 5.7

    Pipavav rail corporation BV 1.0x 179.1 179.1

    Autovia Spain 48% BV 1.0x 930.2 930.2

    Other Subsidiaries - (D) 1,123.4 3,831.6 19.7

    E&C business EV/EBITDA 3x 19,525 19,525 100.5

    Construction business - (E) 26,663.4 26,663.4 117

    Net Debt at parent levels -37,329 -37,329 -192

    Total Value (A+B+C+D+E) 37,931.7 26,018.2 134

    Source:

  • 7/21/2019 Construction Sector Update_141013

    26/32

    IL&FS Transportation Company Update

    Emkay Research October 14, 2013 26

    Key Financials (Consolidated)

    Income Statement

    Y/E Mar (Rsmn) FY12A FY13A FY14E FY15E

    Net Sales 56,056 66,449 64,185 77,908

    Growth (%) 38.5 18.5 -3.4 21.4

    Expenditure 41,401 48,053 45,014 53,478

    Employee Cost 3,694 3,819 4,074 4,775

    Other Exp 1,704 2,016 2,016 2,016

    SG&A 3,210 4,483 4,957 5,816

    EBITDA 14,656 18,396 19,171 24,430

    Growth (%) 26.9 25.5 4.2 27.4

    EBITDA marg in (%) 26.1 27.7 29.9 31.4

    Depreciation 766 944 1,336 1,826

    EBIT 13,890 17,452 17,835 22,604

    EBIT mar gin (%) 24.8 26.3 27.8 29.0

    Other Income 1,238 1,414 1,591 1,769

    Interest expenses 7,282 11,190 12,672 17,204

    PBT 7,846 7,676 6,754 7,169

    Tax 2,457 2,274 2,001 2,124

    Effective tax rate (%) 31.3 29.6 29.6 29.6

    Adjusted PAT 5,389 5,402 4,753 5,045

    Growth (%) 19.8 0.2 -12.0 6.1

    Net Margin (%) 9.6 8.1 7.4 6.5

    (Profit)/loss from JVs/Ass/MI 419 208 385 334

    Adj. PAT After JVs/Ass/MI 4,970 5,194 4,368 4,711

    E/O items 0 0 0 0

    Reported PAT 4,970 5,194 4,368 4,711

    PAT after MI 4,970 5,194 4,368 4,711

    Growth (%) 14.8 4.5 -15.9 7.8

    Balance Sheet

    Y/E Mar (Rsmn) FY12A FY13A FY14E FY15E

    Equity share capital 1,943 1,943 1,943 1,943

    Reserves & surplus 24,834 34,456 38,028 41,943

    Net worth 26,777 36,398 39,970 43,885

    Minority Interest 2,935 2,716 3,444 3,778

    Secured Loans 81,124 135,931 104,735 113,801

    Unsecured Loans 21,996 8,522 44,524 56,149

    Loan Funds 103,120 144,453 149,259 169,951

    Net deferred tax liability 2,047 2,425 2,425 2,425

    Total Liabilities 134,878 185,992 195,098 220,039

    Gross Block 122,174 174,991 176,703 198,337

    Less: Depreciation 4,412 5,356 6,692 8,518

    Net block 117,762 169,635 170,011 189,820

    Capital work in progress 0 0 0 0

    Investment 3,954 6,871 6,871 7,077

    Current Assets 30,759 29,277 37,671 46,232

    Inventories 210 169 311 311

    Sundry debtors 8,820 7,517 10,276 12,728

    Cash & bank balance 2,838 4,544 1,679 4,273

    Loans & advances 17,143 14,170 19,629 22,024

    Other current assets 1,748 2,877 5,777 6,896

    Current lia & Prov 17,602 19,911 19,574 23,209

    Current liabilities 15,455 17,297 17,458 21,093

    Provisions 2,146 2,614 2,116 2,116

    Net current assets 13,157 9,367 18,098 23,024

    Misc. exp 0 0 0 0

    Total Assets 134,873 185,873 194,980 219,921

    Cash Flow

    Y/E Mar (Rsmn) FY12A FY13A FY14E FY15E

    PBT (Ex-Other income) 7,846 7,676 6,754 7,169

    Depreciation 766 944 1,336 1,826

    Interest Provided 7,282 11,190 12,672 17,204

    Other Non-Cash items 0 0 0 0

    Chg in working cap 3,212 5,497 -11,597 -2,332

    Tax paid -2,457 -2,274 -2,001 -2,124

    Operating Cashflow 16,648 23,033 7,164 21,744

    Capital expenditure -56,318 -47,495 -1,712 -21,634

    Free Cash Flow -39,670 -24,462 5,453 109

    Other income 0 0 0 0Investments -2,010 -2,917 0 -206

    Investing Cashflow -58,328 -50,412 -1,712 -21,840

    Equity Capital Raised 0 0 0 0

    Loans Taken / (Repaid) 47,590 41,332 4,806 20,692

    Interest Paid -7,282 -11,190 -12,672 -17,204

    Dividend paid (incl tax) -903 -786 -796 -796

    Income from investments 0 0 0 0

    Others -162 -271 343 0

    Financing Cashflow 39,242 29,085 -8,318 2,691

    Net chg in cash -2,438 1,707 -2,866 2,594

    Opening cash position 5,275 2,838 4,544 1,679

    Closing cash position 2,838 4,544 1,679 4,273

    Key Ratios

    Y/E Mar FY12A FY13A FY14E FY15E

    Profitability (%)

    EBITDA Margin 26.1 27.7 29.9 31.4

    Net Margin 9.6 8.1 7.4 6.5

    ROCE 14.0 11.8 10.2 11.7

    ROE 20.2 16.4 11.4 11.2

    RoIC 13.8 11.5 9.9 11.4

    Per Share Data (Rs)

    EPS 25.6 26.7 22.5 24.2

    CEPS 29.5 31.6 29.4 33.6

    BVPS 137.8 187.4 205.7 225.9DPS 4.0 3.4 3.4 0.0

    Valuations (x)

    PER 4.3 4.2 4.9 4.6

    P/CEPS 3.8 3.5 3.8 3.3

    P/BV 0.8 0.6 0.5 0.5

    EV / Sales 2.2 2.4 2.6 2.4

    EV / EBITDA 8.3 8.8 8.8 7.7

    Dividend Yield (%) 3.6 3.1 3.1 0.0

    Gearing Ratio (x)

    Net Debt/ Equity 3.7 3.8 3.7 3.8

    Net Debt/EBIDTA 6.8 7.6 7.7 6.8

    Working Cap Cycle (days) 67.2 26.5 93.4 87.8

  • 7/21/2019 Construction Sector Update_141013

    27/32

  • 7/21/2019 Construction Sector Update_141013

    28/32

    Ashoka Buildcon Company Update

    Emkay Research October 14, 2013 28

    Exhibit 36: EPC Revenue to propel higher

    5.5

    10.3 11.414.8 14.7 16.8

    -

    2.0

    4.0

    6.08.0

    10.0

    12.0

    14.0

    16.0

    18.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay research

    Exhibit 37: Toll revenue CAGR 13.4% over FY13-15E

    1.7 1.92.6 2.9 3.0

    4.3

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay research

    Exhibit 38: Revenue CAGR 8.8% over FY13-15E

    8.0

    13.015.0

    18.5 18.421.9

    0.0

    5.0

    10.0

    15.0

    20.0

    25.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay research

    Exhibit 39: EBITDA to inch higher

    2.1 2.53.3

    3.7 4.0

    5.3

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay research

    Exhibit 40: EPS

    5.46.5

    7.3

    3.9

    5.74.9

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay research

    Exhibit 41: EBITDA Margin

    26.9

    19.4 21.7 20.1 21.724.0

    -

    5.0

    10.0

    15.0

    20.0

    25.0

    30.0

    FY10 FY11 FY12 FY13 FY14E FY15E

    Source: Company, Emkay research

    Exhibit 42: Incremental Equity requirement over FY14-15E

    Project Rsmn Source of funds Rsmn

    Dhankuni , Belguam, Sambalpur(adj for stake) 1,500 FY13 Cash 338

    Chennai orr(adj for stake) 1,000 BoT CFO over FY13-15E 1,919

    Working capital Requirement 1,000 E&C CFO Over FY13-15E 2549

    Debt repayment 2,695

    Total 6,195 4,806

    Surplus/(Shortfall) (1,389)

    Source: Emkay research

  • 7/21/2019 Construction Sector Update_141013

    29/32

    Ashoka Buildcon Company Update

    Emkay Research October 14, 2013 29

    New projects to drive Toll revenue growth

    Revenue from BOT business adjusted for stake to surge higher 13.4% CAGR over FY13-

    15E whereas total revenue from BOT to post CAGR of 23% over FY13-15E. Majority of the

    ramp in revenue will come from projects like Durg Chattisgarh and Chattisgarh Bhandara in

    FY14E followed by commissioning of Sambalpur Baragarh & Belgaum Dharwad. The

    Belgaum-Dharwad (have scalability for high traffic growth due to traffic running from

    Mumbai to Bangalore on GQ) and Dhankuni-Kharagpur projects (Goods to Eastern belts ,Traffic from Haldia post to Northern & Southern region , handles minerals as well ) being 6-

    laning projects, impart high visibility and comfort over futurerevenue ramp-up.

    Partnership with SBI-Macquarie gives scalability

    SBI Macquarie (SBI-M) has committed to invest Rs7bn (Already invested till sate of Rs3.8

    bn in ACL), the holding company for ABLs new road concessions (ABL is required to invest

    its share of equity of Rs8.5bn, already invested Rs7 bn). According to the agreement SBI

    will have 34% stake in ACL which implies pre-money valuation of 1.6x P/B for ACL. These

    valuations appear attractive considering the IRR profile of the underlying projects, and also

    lend considerable credibility to ACLs project portfolio. The terms of the agreement assure

    SBI-M a guaranteed 12% IRR on its initial investment of Rs7bn in ACL which entails outgo

    of Rs14.6 bn by FY20E.According to the agreement there are three ways that the private investor can exit:

    IPO of ACL Sale to others or swap into the individual asset SPVs. In case of a shortfall in realizing

    the guaranteed returns even after swapping into the SPVs, SBI-M can increase its

    stake in ACL to a maximum of 49% however; no provision to swap into the parent

    company, ABL which we believe is a key positive for the shareholders of ABL.

    We believe that investment is a value creating proposition considering the interest rates are

    currently holding up for road project financing at 12-13% and availability of equity capital

    ensures timely project completion and faster cash generation from the BOT assets. We

    dont believe that 12% capital protection rate a concern considering the IRR of ACL

    projects under ranges between 13-20%.

    Exhibit 43: NPV of ACL portfolio

    NPV ACL Stake FY14E FY15E FY16E FY17E FY18E FY19E FY20E

    Dhankuni - Kharagpur 100% 3732 6241 8332 10175 12174 13820 15435

    Sambhalpur - Baragarh 100% 1216 2228 2562 2937 3360 3861 4438

    Belgaum - Dharwad 100% 860 972 1484 2008 2563 3145 3981

    Pimpalgaon - Nasik 26% 1008 1242 1408 1612 1789 2090 2340

    Under construction project