CONSTRUCTION PROGRESS

AS ON 30th APR’18

Page 2: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

E - BLOCK

STATUS

• 19th floor completed• Internal Painting – 1st & 2nd coat

putty work is in progress• Floor Marble laying work is in progress• Main Floor Tiling work is in progress • Toilet Tiling work is in progress• Fire Fighting – Pipe laying & Testing

work is in progress • Water Proofing work is in progress• Plumbing work is in progress

Page 3: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

F - BLOCK

STATUS

• 19th floor completed• Internal Painting – Wall & Ceiling painting

work completed• Floor Marble laying completed• Main Floor Tiling work nearing completion• Toilet Tiling work nearing completion• Fire Fighting – Pipe laying & Testing

work nearing completion• Water Proofing completed• Plumbing work nearing completion• Window fixing work is in progress

Page 4: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

F – BLOCK BATHROOM TILING WORK NEARING COMPLETION

Page 5: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

F – BLOCK FLOOR TILE WORK NEARING COMPLETION

Page 6: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

G - BLOCK

STATUS

• 19th floor completed• Internal Painting – 1st & 2nd coat

putty and primer work nearingcompletion

• Floor Marble laying work nearing completion

• Main Floor Tiling work nearing completion• Toilet Tiling work nearing completion• Fire Fighting – Pipe laying & Testing

work nearing completion• Water Proofing work is in progress• Plumbing work nearing completion• Window fixing work is in progress

Page 7: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

H - BLOCK

STATUS

• 19th floor completed• Internal Painting – 1st & 2nd coat Putty &

Primer work nearing completion• Floor Marble laying work nearing

completion• Main Floor Tiling work nearing completion• Toilet Tiling work nearing completion• Fire Fighting – Pipe laying & Testing

work is in progress• Water Proofing work is in progress• Plumbing work is in progress• Window fixing work is in progress

Page 8: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

I - BLOCKSTATUS

• 19th floor completed• Internal Painting – Wall & Ceiling painting

work nearing completion• Floor Marble laying completed • Main Floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Windows fixing work completed• Door Frame fixing – Bedroom & Toilet

work completed, Main door frame fixing work nearing completion

• Electrical switch plate fixing workcompleted(Top cover plate fixingwork nearing completion)

• Sanitary fittings work completed• CP fittings work completed

Page 9: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

I - BLOCKHALL FRENCH WINDOW LIFT WORK COMPLETED

Page 10: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

I - BLOCKELECTRICAL BOARD FIXING

WORK COMPLETEDFIRE FIGHTING FALSE

CEILING WORK COMPLETED

Page 11: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

I - BLOCKKITCHEN AREAHALL WINDOW

Page 12: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

I – BLOCK BATHROOM FITTINGS WORK COMPLETED

Page 13: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

J - BLOCK

STATUS

• 19th floor completed• Internal Painting – Primer work completed,

Wall & Ceiling Painting work is in progress• Floor Marble laying completed • Main floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Window fixing work is in progress• Door Frame Fixing work completed • Electrical switch plate fixing work

completed(Top cover plate fixingwork is in progress)

• Sanitary fittings work nearing completion• CP fittings work is in progress

Page 14: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

J - BLOCKFIRE FIGHTING FALSE

CEILING WORK COMPLETED LOBBY AREA

Page 15: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

J - BLOCKHALL WASH-BASIN PIPED GAS

Page 16: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

J - BLOCKMARBLE LAYING COMPLETEDKITCHEN AREA

Page 17: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

J – BLOCK BATHROOM FITTINGS WORK COMPLETED

Page 18: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

K - BLOCKSTATUS

• 19th floor completed• Internal Painting – Primer work completed.

Wall & Ceiling Painting work is in progress• Floor Marble laying completed • Main Floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Windows fixing work completed• Door Frame fixing – Bedroom & Toilet

work completed, Main door frame fixing work nearing completion

• Electrical switch plate fixing workcompleted(Except top plate)

• Sanitary fittings work nearing completion• CP fittings work is in progress

Page 19: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

K - BLOCKFIRE FIGHTING FALSE

CEILING WORK COMPLETEDLOBBY AREA

Page 20: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

K - BLOCKHALL WASH-BASIN PIPED GAS

Page 21: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

K - BLOCKMARBLE LAYING COMPLETEDHALL WINDOW

Page 22: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

K – BLOCK BATHROOM FITTINGS WORK COMPLETED

Page 23: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

L - BLOCK

STATUS

• 19th floor completed• Internal Painting – Wall & Ceiling painting

work nearing completion• Floor Marble laying completed • Main Floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Window fixing work completed• Door Frame Fixing work completed• Electrical switch plate fixing work

completed• CP fittings work completed• Sanitary fittings work completed

Page 24: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

L - BLOCKFIRE FIGHTING FALSE

CEILING WORK COMPLETED MAIN DOOR

Page 25: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

L - BLOCKLIFT LOBBY AREA

Page 26: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

L - BLOCK

INTERNAL DOORS

Page 27: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

L - BLOCKMARBLE & TILES LAYING WORK COMPLETED

Page 28: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

L - BLOCKBATHROOM FITTINGS HALL FRENCH WINDOW

Page 29: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

L - BLOCKPIPED GAS HALL WASH-BASIN

Page 30: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

L - BLOCK

Page 31: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

P - BLOCK

STATUS

• 19th floor completed• Internal Painting – 1st & 2nd coat putty

and primer work is in progress• Floor Marble laying work is in progress • Main Floor Tiling work is in progress• Toilet Tiling work is in progress• Fire Fighting work is in progress • Water Proofing work is in progress• Plumbing work is in progress

Page 32: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

PODIUM AREA (J-K-L)

Page 33: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

PODIUM WORK IS IN PROGRESS(I-J-L)

Page 34: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

L-BLOCK OPEN AREA

Page 35: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

SWIMMING POOL

Page 36: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

CLUB HOUSE AREA

Page 37: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

CLUB HOUSE AREA

Page 38: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

CLUB HOUSE AREA

Page 39: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

RAIN WATER SUMP WORK IS IN PROGRESS

Page 40: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

BASEMENT PARKING AREA

Page 41: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

EB - TRANSFORMER FIXING WORK IS IN PROGRESS

Page 42: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

SEWAGE TREATMENT PLANT

Page 43: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

LIST OF APPROVED BANKERS

Page 44: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting

Thank You