CONSTRUCTION PROGRESS
AS ON 30th APR’18
E - BLOCK
STATUS
• 19th floor completed• Internal Painting – 1st & 2nd coat
putty work is in progress• Floor Marble laying work is in progress• Main Floor Tiling work is in progress • Toilet Tiling work is in progress• Fire Fighting – Pipe laying & Testing
work is in progress • Water Proofing work is in progress• Plumbing work is in progress
F - BLOCK
STATUS
• 19th floor completed• Internal Painting – Wall & Ceiling painting
work completed• Floor Marble laying completed• Main Floor Tiling work nearing completion• Toilet Tiling work nearing completion• Fire Fighting – Pipe laying & Testing
work nearing completion• Water Proofing completed• Plumbing work nearing completion• Window fixing work is in progress
F – BLOCK BATHROOM TILING WORK NEARING COMPLETION
F – BLOCK FLOOR TILE WORK NEARING COMPLETION
G - BLOCK
STATUS
• 19th floor completed• Internal Painting – 1st & 2nd coat
putty and primer work nearingcompletion
• Floor Marble laying work nearing completion
• Main Floor Tiling work nearing completion• Toilet Tiling work nearing completion• Fire Fighting – Pipe laying & Testing
work nearing completion• Water Proofing work is in progress• Plumbing work nearing completion• Window fixing work is in progress
H - BLOCK
STATUS
• 19th floor completed• Internal Painting – 1st & 2nd coat Putty &
Primer work nearing completion• Floor Marble laying work nearing
completion• Main Floor Tiling work nearing completion• Toilet Tiling work nearing completion• Fire Fighting – Pipe laying & Testing
work is in progress• Water Proofing work is in progress• Plumbing work is in progress• Window fixing work is in progress
I - BLOCKSTATUS
• 19th floor completed• Internal Painting – Wall & Ceiling painting
work nearing completion• Floor Marble laying completed • Main Floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Windows fixing work completed• Door Frame fixing – Bedroom & Toilet
work completed, Main door frame fixing work nearing completion
• Electrical switch plate fixing workcompleted(Top cover plate fixingwork nearing completion)
• Sanitary fittings work completed• CP fittings work completed
I - BLOCKHALL FRENCH WINDOW LIFT WORK COMPLETED
I - BLOCKELECTRICAL BOARD FIXING
WORK COMPLETEDFIRE FIGHTING FALSE
CEILING WORK COMPLETED
I - BLOCKKITCHEN AREAHALL WINDOW
I – BLOCK BATHROOM FITTINGS WORK COMPLETED
J - BLOCK
STATUS
• 19th floor completed• Internal Painting – Primer work completed,
Wall & Ceiling Painting work is in progress• Floor Marble laying completed • Main floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Window fixing work is in progress• Door Frame Fixing work completed • Electrical switch plate fixing work
completed(Top cover plate fixingwork is in progress)
• Sanitary fittings work nearing completion• CP fittings work is in progress
J - BLOCKFIRE FIGHTING FALSE
CEILING WORK COMPLETED LOBBY AREA
J - BLOCKHALL WASH-BASIN PIPED GAS
J - BLOCKMARBLE LAYING COMPLETEDKITCHEN AREA
J – BLOCK BATHROOM FITTINGS WORK COMPLETED
K - BLOCKSTATUS
• 19th floor completed• Internal Painting – Primer work completed.
Wall & Ceiling Painting work is in progress• Floor Marble laying completed • Main Floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Windows fixing work completed• Door Frame fixing – Bedroom & Toilet
work completed, Main door frame fixing work nearing completion
• Electrical switch plate fixing workcompleted(Except top plate)
• Sanitary fittings work nearing completion• CP fittings work is in progress
K - BLOCKFIRE FIGHTING FALSE
CEILING WORK COMPLETEDLOBBY AREA
K - BLOCKHALL WASH-BASIN PIPED GAS
K - BLOCKMARBLE LAYING COMPLETEDHALL WINDOW
K – BLOCK BATHROOM FITTINGS WORK COMPLETED
L - BLOCK
STATUS
• 19th floor completed• Internal Painting – Wall & Ceiling painting
work nearing completion• Floor Marble laying completed • Main Floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Window fixing work completed• Door Frame Fixing work completed• Electrical switch plate fixing work
completed• CP fittings work completed• Sanitary fittings work completed
L - BLOCKFIRE FIGHTING FALSE
CEILING WORK COMPLETED MAIN DOOR
L - BLOCKLIFT LOBBY AREA
L - BLOCK
INTERNAL DOORS
L - BLOCKMARBLE & TILES LAYING WORK COMPLETED
L - BLOCKBATHROOM FITTINGS HALL FRENCH WINDOW
L - BLOCKPIPED GAS HALL WASH-BASIN
L - BLOCK
P - BLOCK
STATUS
• 19th floor completed• Internal Painting – 1st & 2nd coat putty
and primer work is in progress• Floor Marble laying work is in progress • Main Floor Tiling work is in progress• Toilet Tiling work is in progress• Fire Fighting work is in progress • Water Proofing work is in progress• Plumbing work is in progress
PODIUM AREA (J-K-L)
PODIUM WORK IS IN PROGRESS(I-J-L)
L-BLOCK OPEN AREA
SWIMMING POOL
CLUB HOUSE AREA
CLUB HOUSE AREA
CLUB HOUSE AREA
RAIN WATER SUMP WORK IS IN PROGRESS
BASEMENT PARKING AREA
EB - TRANSFORMER FIXING WORK IS IN PROGRESS
SEWAGE TREATMENT PLANT