Southwest Health System Construction Newsletter September 16, 2017
A Week in Review Construction Newsletter September 16, 2017 Patient Wing • Excavation to subgrade for the north section of the parking lot is in progress • Interior sheetrock is continuing to go up from the ICUs south in the rooms and corridors
• Taping and finishing is in progress, paint will follow soon • Interior blocking is substantially complete in the rooms and corridors • The stucco finish coat is being applied, the east wall is complete and crews were working on the west side Friday
• The three layers in stucco consist of a scratch coat at the bottom, a brown coat in the middle, and a final finish coat on top • Fireproofing is complete at the ED canopy and the ED corridor is almost complete
• Fireproofers will return next week to finish up ED corridor and family waiting • MEP rough-in for the ED corridor is about 50% complete, once the fireproofing is complete everything should wrap up quickly • Asphalt paving was placed at the emergency entrance Friday • The switch-over for ATS-3 and ATS-4 took place Thursday night, heavy rain prevented the switch-over for the EMS/Plant Ops from
happening • Nunn held a barbecue for all the subcontractors on site Thursday (around 120+ people!) MOB • Exterior windows on the west side have been installed and flashing is installed on the west and south walls • Exterior sheathing is complete on the new building
• Screw inspection Thursday morning, insulation is ready to begin next week • Interior wall blocking started this week and they are approximately half way through the first level • Blocking layout started on the second floor
Patient Wing Construction Newsletter September 16, 2017
Excavation to bring to the north parking lot to subgrade is in progress and
islands have been staked
Patient Wing Construction Newsletter September 16, 2017
Fireproofing at the ED canopy is complete and the corridor is almost complete
Patient Wing Construction Newsletter September 16, 2017
Asphalt was placed for the ED drive Friday
What’s Next? Construction Newsletter September 16, 2017 Patient Wing • Work will continue on the north section of the parking lot, the entrance from Mildred will be left open until the public entrance is
temporarily relocated • Irrigation work is planned to begin next week, with a new irrigation main to get water back to the SW corner of the hospital grounds • The exterior stucco finish coat will be complete next week and exterior stone is scheduled to begin Monday • Fireproofers are almost complete and will resume work next week
• Overhead mechanical, plumbing, and electrical can begin once fireproofing is complete • The small amount of interior wall framing will follow next week once fireproofing is complete and MEP in the corridor will wrap up after
that MOB • Exterior insulation will continue next week now that the sheathing has been completed and inspected and liquid flashing will follow behind
insulation • The building should be dried in within the next few weeks
• Stucco is planned to shift over to the MOB once the Patient Wing stucco is completed and after air and weather barrier system is complete • Interior blocking will resume next week on both floors • The elevator subcontractor is scheduled to begin their installation on Monday
MOB Construction Newsletter September 16, 2017 Exterior sheathing is complete and has been
inspected, and now insulation is following
MOB Construction Newsletter September 16, 2017
Interior wall blocking started on the first floor this week
Subcontractors on Site Construction Newsletter September 16, 2017 Present • CRG (Excavation & Utilities) • Miller Bonded (Patient Wing Electrical) • Nichols Electric (MOB Electrical) • Reigles Mechanical (Plumbing) • Four Suns Builders (Framing & Sheetrock) • Garrhs (HVAC) • Cooper Fire Protection (Fire Suppression) • Cruzan Construction (Demolition & Backing) • Sun Glass (Windows and Storefronts) • USI Herblan Insulation (Fireproofing) • Four Corners – Asphalt (Asphalt paving) • Nunn Construction (General Work)
Arriving Soon • Advanced Concrete (Concrete) • OTIS Elevator (MOB Elevator)
Weekly Weather Construction Newsletter September 16, 2017
Nunn held a barbecue Thursday for every subcontractor on site to thank
them for all their hard work