CONCEPTUAL DESIGN FOR WILLIAMS ROAD BIKE AND PEDESTRIAN IMPROVEMENTS
BRENT ADDISON, P.E.
End ProjectSta. 88+15
Begin ProjectSta. 13+25
Thre
e O
aks P
arkw
ay
Williams Road
Estero High School
Hertz
DAVID WILLEMS, P.E.
OBJECTIVE
The goal of this project is to improve the bicycle andpedestrian facilities for Williams Road from US 41 toThree Oaks Parkway.
DISCUSSION TOPICS
•Conceptual Plan Views
•Conceptual Section Views
•Enhancements
•Preliminary Cost Analysis
CONCEPTUAL PLAN VIEWS
Proposed 12’ Multi-use Path
Proposed 7’ Bike Lane
Existing 5’ Sidewalk
Future 4 Lane Expansion
US 41 TO VIA COCONUT
Proposed 7’ Bike Lane
Proposed 7’ Bike Lane
Proposed 12’ Multi-use Path
Proposed 8’ Concrete Sidewalk
Proposed 7’ Bike Lane
Proposed 8’ Concrete Sidewalk
RAILROAD TO ESTERO HIGH SCHOOL
Proposed 8’ Concrete Sidewalk
Proposed 12’ Multi-use Path
Proposed 7’ Bike Lane
Proposed 12’ Multi-use Path
RoundaboutPer River Ranch Road Project
Proposed 8’ Concrete Sidewalk
ESTERO HIGH SCHOOL TO RIVER RANCH
Proposed 8’ Concrete Sidewalk
Proposed 12’ Multi-use Path
Proposed 7’ Bike Lane
Proposed 8’ Concrete Sidewalk
RIVER RANCH TO THREE OAKS PARKWAY
CONCEPTUAL SECTION VIEWS
US 41 TO VIA COCONUT
VIA COCONUT TO SEMINOLE GULF RAILWAY
SEMINOLE GULF RAILWAY TO ESTERO HIGH SCHOOL
ESTERO HIGH SCHOOL TO RIVER RANCH ROAD
RIVER RANCH ROAD TO THREE OAKS PARKWAY
ENHANCEMENTS
• Decorative lighting to allow safe nighttime use of bicycle and pedestrian facilities
• Landscaping to improve aesthetics, comfort and safety
PRELIMINARY COST ANALYSIS(For Via Coconut to Three Oaks Parkway Only)
Bike Lanes $249,952.00
North Side (Sidewalk and Asphalt Path) $564,420.00
South Side Multi-Use Path $742,812.00
Irrigation and Landscaping $1,272,000.00
Lighting $622,272.00
Misc. (Mobilization, Survey, Design, MOT, Inspection) $663,000.00
Total Estimated Costs $4,114,456.00