company index top 100 badge programme

60
Top 100 Projects 2011 Romaine Complex A Renewable Energy Project 1 $6.5 billion Key Players: Thirau ltée, a subsidiary of CVTech Group Inc. (builder); AECOM (detailed engineering on Romaine 1, preliminary engineering on Romaine 4) Funding: Public Status: Construction began in mid-2009 and is scheduled for completion in 2020. The frst Romaine commissioning is planned for 2014, but the proposed transmission lines run through the ancestral lands of the Uashaunnuat and Innu (Innu Uashat Mak Mani- Utenam), and in May 2010 they fled for an interlocutory injunction against the project. In response, the federal government is rumoured to have stepped in and delayed the transmission element of the project. A spokesperson for the Environmental Assessment Offce couldn’t confrm but said the offce is still having discussions with Hydro-Québec. 2010 Rank: 1 Location: Havre-Saint-Pierre, Quebec Owner: Hydro-Québec Hydro-Québec is building a 1,550-megawatt (MW) hydroelectric complex on the shores of the Rivière Romaine, north of the municipality of Havre-Saint-Pierre on the north shore of the St. Lawrence River. Electricity from the four hydropower stations will fow along transmission lines, also funded by Hydro-Québec, to the des Montagnais and Arnaud substations. Credit: Nalcor The dam at Muskrat Falls will be built in Phase 1 of this megaproject. Key players: Key players have not been confrmed, but an RFP has been issued for engineering and project management to Black & Veatch, Hatch, and SNC-Lavalin. Funding: Public/Private Status: A Nalcor/Emera partnership, announced in November 2010, will result in the development of Muskrat Falls, with transmission from Labrador across the Strait of Belle Isle for use on the island of Newfoundland. Milestones that remain before the project is sanctioned for construction include EAs for both the generation and transmission projects, fnalization of fnancing, and completion of pre-front end engineering work. The existing 5,428 MW Churchill Falls Generating Station, which began producing power in 1971, harnesses about 65 per cent of the Churchill River’s potential generating capacity. The remaining 35 per cent is located at two sites on the lower Churchill River. The lower Churchill River system is comprised of two sites: Muskrat Falls with 824 MW of power and Gull 2 Lower Churchill Hydro Project $6.2 billion 2010 Rank: NEW Location: Central Labrador (generating facility), Muskrat Falls to Churchill Falls, Labrador to the island of Newfoundland, and Newfoundland to Nova Scotia (transmission systems) Owner: Nalcor Energy (Muskrat Falls and Generating Station), Emera (49 per cent of transmission assets) Island with 2250 MW. The current project cost accounts for Phase 1 of the project, the development of Muskrat Falls and associated transmission, including transmission links from Muskrat Falls to Churchill Falls, Labrador to the island of Newfoundland and Newfoundland to Nova Scotia. Phase 2 of the project will be the development of Gull Island, for which construction is expected to start several years after Muskrat Falls. Nalcor will transmit surplus power from the island to Nova Scotia Power, a subsidiary of Emera, across the Cabot Strait into Cape Breton, Nova Scotia. “The goal is to have a 100 per cent renewable electricity sector in Newfoundland—and we plan on getting there with hydroelectric power.” —Newfoundland and Labrador’s Natural Resources Minister Kathy Dunderdale Eastmain-1-A/ Sarcelle/Rupert Project $5 billion Key Players: Société d’énergie de la Baie James (project manager); AECOM (detailed engineering on Rupert River Diversion and La Sarcelle Power Plant) Funding: Public Status: Under construction with expected completion in 2012. 2010 Rank: 2 Location: James Bay Territory, Quebec Owner: Hydro-Québec Until Romaine catches up, this is still the largest construction site in Quebec, and it plays a critical role in Hydro-Québec’s plans to increase annual hydroelectric output by 15.8 terawatt hours (TWh) between 2006 and 2014. Components of the superstructure will be prefabricated at the job site and transported to the powerhouse site for assembly. Also part of construction is a new drinking water plant in Waskaganish, which will meet the community’s needs until 2025. Transmission is also being developed: 315-kilovolt (kV) lines will be built between Eastmain-1 and Eastmain-1-A, and between Sarcelle and Eastmain-1. 8 ReNew Canada top100projects.ca 3

Upload: others

Post on 11-Feb-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Company Index Top 100 Badge Programme

Top 100 Projects 2011

Romaine Complex A Renewable Energy Project 1 $6.5 billion Key Players: Thirau ltée, a subsidiary of CVTech Group Inc. (builder); AECOM (detailed engineering on Romaine 1, preliminary engineering on Romaine 4)

Funding: Public

Status: Construction began in mid-2009 and is scheduled for completion in 2020. The first Romaine commissioning is planned for 2014, but the proposed transmission lines run through the ancestral lands of the Uashaunnuat and Innu (Innu Uashat Mak Mani-Utenam), and in May 2010 they filed for an interlocutory injunction against the project. In response, the federal government is rumoured to have stepped in and delayed the transmission element of the project. A spokesperson for the Environmental Assessment Office couldn’t confirm but said the office is still having discussions with Hydro-Québec.

2010 Rank: 1

Location: Havre-Saint-Pierre, Quebec

Owner: Hydro-Québec

Hydro-Québec is building a 1,550-megawatt (MW) hydroelectric complex on the shores of the Rivière Romaine, north of the municipality of Havre-Saint-Pierre on the north shore of the St. Lawrence River. Electricity from the four hydropower stations will flow along transmission lines, also funded by Hydro-Québec, to the des Montagnais and Arnaud substations.

Cred

it: Nalcor

The dam at Muskrat Falls will be built in Phase 1 of this megaproject.

Key players: Key players have not been confirmed, but an RFP has been issued for engineering and project management to Black & Veatch, Hatch, and SNC-Lavalin.

Funding: Public/Private

Status: A Nalcor/Emera partnership, announced in November 2010, will result in the development of Muskrat Falls, with transmission from Labrador across the Strait of Belle Isle for use on the island of Newfoundland. Milestones that remain before the project is sanctioned for construction include EAs for both the generation and transmission projects, finalization of financing, and completion of pre-front end engineering work.

The existing 5,428 MW Churchill Falls Generating Station, which began producing power in 1971, harnesses about 65 per cent of the Churchill River’s potential generating capacity. The remaining 35 per cent is located at two sites on the lower Churchill River. The lower Churchill River system is comprised of two sites: Muskrat Falls with 824 MW of power and Gull

2 Lower Churchill Hydro Project $6.2 billion

2010 Rank: NEW

Location: Central Labrador (generating facility), Muskrat Falls to Churchill Falls, Labrador to the island of Newfoundland, and Newfoundland to Nova Scotia (transmission systems)

Owner: Nalcor Energy (Muskrat Falls and Generating Station), Emera (49 per cent of transmission assets)

Island with 2250 MW. The current project cost accounts for Phase 1 of the project, the development of Muskrat Falls and associated transmission, including transmission links from Muskrat Falls to Churchill Falls, Labrador to the island of Newfoundland and Newfoundland to Nova Scotia. Phase 2 of the project will be the development of Gull Island, for which construction is expected to start several years after Muskrat Falls. Nalcor will transmit surplus power from the island to Nova Scotia Power, a subsidiary of Emera, across the Cabot Strait into Cape Breton, Nova Scotia.

“The goal is to have a 100 per cent renewable electricity sector in Newfoundland—and we plan on getting there with hydroelectric power.” —Newfoundland and Labrador’s Natural Resources Minister Kathy Dunderdale

Eastmain-1-A/ Sarcelle/Rupert Project $5 billion

Key Players: Société d’énergie de la Baie James (project manager); AECOM (detailed engineering on Rupert River Diversion and La Sarcelle Power Plant)

Funding: Public

Status: Under construction with expected completion in 2012.

2010 Rank: 2

Location: James Bay Territory, Quebec Owner: Hydro-Québec

Until Romaine catches up, this is still the largest construction site in Quebec, and it plays a critical role in Hydro-Québec’s plans to increase annual hydroelectric output by 15.8 terawatt hours (TWh) between 2006 and 2014. Components of the superstructure will be prefabricated at the job site and transported to the powerhouse site for assembly. Also part of construction is a new drinking water plant in Waskaganish, which will meet the community’s needs until 2025. Transmission is also being developed: 315-kilovolt (kV) lines will be built between Eastmain-1 and Eastmain-1-A, and between Sarcelle and Eastmain-1.

8 ReNew Canada top100projects.ca

3

Page 2: Company Index Top 100 Badge Programme

The City of Toronto is scheduled to receive 35 light rail vehicles (LRVs) out of the 182 LRVs ordered from Bombardier for $770 million.

Eglinton Crosstown Light Rail Transit (LRT) Project $4.6 billion

This project is part of the largest public transit investment in Canadian history, committed under Metrolinx’s Big 5 priority transit projects. Phase 1 of the Eglinton Crosstown LRT line will be 20 km of light rail service across the Eglinton Avenue corridor in mid-town Toronto, with a 12 km segment to be tunnelled from around Black Creek Drive in the west to Brentcliffe Road in the east. Newly elected Toronto mayor, Rob Ford, ran on a campaign pledge to remove streetcars, but his campaign manager recently suggested his office wouldn’t adopt any plans that would cost the city more money—that would include cancelling the order with Bombardier for new streetcars.

2010 Rank: NEW

Location: Toronto, Ontario

Owner: Metrolinx/GO Transit

Key Players: Bombardier (supplier: light rail vehicles), Lovat (supplier: boring machines)

Funding: Public

Status: Tunnelling will commence under Eglinton Avenue in the spring of 2011 with project completion scheduled for 2020.

4

10 ReNew Canada

Top 100 Projects

2011C

redit: B

omb

ardier

Turcot Interchange5 $3 billion

Key Players: Ministère des Transports du Québec (principal contractor); AECOM (project manager); SNC-Lavalin, CIMA+ (feasibility study)

Funding: Public

Status: Construction is set to begin in fall 2010, with completion in 2018.

In November 2010, Quebec Transport Minister Sam Hamad released the final plans for reconstruction of the crumbling expressway. This new plan is in response to concerns expressed by the Bureau d’audiences publiques sur l’environnement, the City of Montreal, and the public. It also comes with a much bigger price tag—$3 billion, compared with the $1.2 billion to $1.5 billion announced in

2010 Ranking: 10

Location: Montreal, Quebec

Owner: Province of Quebec, Ministère des Transports du Québec

2007. Opponents complained the 2007 plan would increase capacity to 320,000 cars daily, encourage urban sprawl and do nothing to cut car use. While the new plan still keeps the expressway at its current capacity, it includes reserved lanes for buses (and possibly cars with multiple occupants). It will be designed to accommodate future transit—the minister mentioned a potential airport shuttle or even streetcars. A park with foot and bike paths will be created along the Saint-Jacques Escarpment just north of Highway 20; a foot/bike path will also connect that new park and the Lachine Canal; it will include a bridge over Highway 20. These changes weren’t enough to impress Projet Montreal leader Richard Bergeron, who told reporters this November that Montreal’s Mayor Gérald Tremblay asked him to leave the City’s executive committee because he refused to support the plan. At a news conference in Montreal, Bergeron said he couldn’t support a plan that didn’t promote public transit.

top100projects.ca

Page 3: Company Index Top 100 Badge Programme

New plans for Montreal’s aging Turcot Expressway have Highway 20 moving north toward the Saint-Jacques Escarpment, opening up a large area for future residential and commercial developments.

Cred

it: Serge M

aheu (sergemaheu.com

)

Page 4: Company Index Top 100 Badge Programme

6

Top 100 Projects 2011

Spadina Subway Extension $2.63 billion

Key Players: Spadina Link Project Managers— a joint venture between Delcan, Hatch Mott MacDonald, and MMM Group (project management consultants); Hatch Mott MacDonald (tunnel design consultant); IBI Group (subconsultant to Hatch Mott MacDonald for tunnelling contract); AECOM (engineering design); H. H. Angus (mechanical and electrical engineering consultants); Morrison Hershfield (construction management services); INSPEC-SOL, Coffey Geotechnics (geo-engineering consultants and electrical engineering consultants); Golder Associates (principal geo­engineering consultant); Trow Global (condition surveying and monitoring consultant); Lovat (supplier: tunnel boring machines)

Downsview Station to Wilson Yard Connection: Belor Construction (construction)

Finch West and Steeles West Subway Stations: A joint venture of IBI Group Architects, LEA Consulting and Halsall Associates, in association with Will Alsop (design)

York University Station: Arup Canada in association with Foster + Partners (design)

2010 Ranking: 3

Location: Toronto, Ontario Owner: TTC

Sheppard West Station: Aedas (design); Varcon Construction (tunnel boring machines launch shaft at Sheppard West Station)

Downsview to Sheppard West to Finch West Station: McNally Construction, Kiewit, and Aecon in a joint venture (construction of 2.6 kms of wind tunnel subway track, construction of new Sheppard West station)

Funding: Public

Status: Construction began in 2009 and is expected to be complete by 2015.

The largest transit expansion project to be undertaken by the Toronto Transit Commission (TTC) since the Bloor-Danforth Subway line was built 40 years ago, the subway network will link Toronto with communities in York Region. The 8.6 km extension to the existing Spadina subway line will include six new stations, including one at York University. The TTC is managing the project’s design and construction.

Lower Mattagami Hydroelectric Complex 7 $2.6 billion

Key Players: The Kiewit Alarie Partnership— Kiewit and Leo Alarie and Sons Construction, a subsidiary of Aecon (design, construction); Alston (supplier: hydro turbine generators)

Funding: Public (funding has yet to be arranged)

Status: Construction began in 2010 and is expected to be complete by 2015.

2010 Ranking: NEW Location: 70 kms northeast of Kapuskasing, Ontario Owner: Ontario Power Generation (OPG), Moose Cree First Nation

The new 440 MW generating station will replace the existing station. By using existing sites, OPG is hoping to minimize the project’s environmental footprint. The new facilities will also use water more efficiently. Hydro One Networks will add about four km of 230 kV circuit to the existing towers that run from Harmon Junction to Kipling Generating Station. OPG and the Ontario Power Authority are working to finalize and execute a Hydroelectric Energy Supply Agreement for the project. The Moose Cree First Nation will have up to a 25 per cent equity share in the project.

BuILdIngS

new vs. expansion 31 projects (Out of 100 projects)

55% are new builds 45% are redevelopments/expansions

47% 41% 12% 14% 86%

Health Care Public Buildings Education Health Care Public Buildings

12 ReNew Canada top100projects.ca

Page 5: Company Index Top 100 Badge Programme
Page 6: Company Index Top 100 Badge Programme

Initiated in 2007, the Ministry of Transportation and Infrastructure’s Gateway Program, one of the largest transportation network projects currently underway in North America, includes the Port Mann/Highway 1 Project as its largest component.

14 ReNew Canada

Top 100 Projects

Cred

it: CH

UM

Cred

it: Transportation Investm

ent Corp

oration

CHUM is one of the largest university hospital centres in North America and the contract for the new medical research centre is the first health P3 for Quebec.

Key Players: Infrastructure Québec, formerly PPP Québec (procurement advisor); a consortium of SNC-Lavalin and GENIVAR (owner’s advisor, project management; AECOM (structural and civil engineering)

Research Centre: Accès Recherche Montréal, a joint venture of Pomerleau and Verreault, a subsidiary of Dessau (design-build­finance-maintain); BPYA—Birtz Bastien Beaudoin Laforest Architectes, Provencher Roy, Yelle Maillé, Arcorp (architects)

Hospital: Two consortiums are now bidding on the project— CHUM collectif and Accès Santé CHUM

8 CHuM (Centre hospitalier de l’université de Montréal) Redevelopment $2.5 billion

2010 Ranking: NEW

Location: Montreal, Quebec Owner: CHUM

Funding: P3 (DBFM)

Status: The Research Centre is under construction, with completion expected in 2013. There is a request for proposals out for the hospital, which will be completed in 2020.

A new hospital and research centre will replace the three facilities which currently make up the CHUM—the Hôtel-Dieu de Montréal, Hôpital Notre-Dame, and Hôpital Saint-Luc. Both old and new buildings will have to meet the national building code requirements, which involves a major seismic retrofit, site decontamination, vibration and water control, built environment preservation, and so on.

LEED Target: Certification for Research Centre

9 Port Mann/ Highway 1 Project

$2.46 billion

2010 Ranking: 4

Location: About 37 kms from Vancouver to Langley, British Columbia

Owner: Province of British Columbia (Transportation Investment Corporation)

Key Players: Partnerships BC (procurement manager and project development); Kiewit-Flatiron General Partnership (design-build contractor); H5M—a joint venture of Hatch Mott MacDonald and MMM Group (prime design consultants—onshore works); T.Y. Lin International (prime design consultant—New Concession Bridge); Delcan (program engineer); Golder, CH2M HILL (sub-consultants to Delcan)

Funding: Public

Status: Under construction with completion expected in 2013.

The project involves widening 37 km of highway and replacing the existing Port Mann Bridge crossing of the Fraser River. Initially pursued in 2007 as a design­build-finance-operate (DBFO) project, the majority of the project is being delivered as a fixed-price, design-build project between the TIC and Kiewit Flatiron.

top100projects.ca

Page 7: Company Index Top 100 Badge Programme

2011

Cred

it: City O

f Ottaw

a

The new LRT system includes a 3.2-kilometre downtown tunnel from LeBreton Flats to the University of Ottawa.

10 ottawa Light Rail Project Phase 1 $2.1 billion

Key Players: Delcan (LRT planning, EA, functional design); Halcrow Group (tunnel design for EA Report); Capital Transit Partners—a joint venture of Morrison Hershfield, Jacobs Associates, STV Canada Consulting, and URS Canada (preliminary engineering)

Funding: Public

2010 Ranking: NEW

Location: Ottawa, Ontario Owner: City of Ottawa

Status: The EA was approved in August 2010 and completion is expected in 2019.

The system includes 13 new stations from Tunney’s Pasture to Blair Road, four of which are in a 3.2 km tunnel located under downtown Ottawa. The line is expected to cut the number of buses traveling through the city’s downtown core in half, and the number of buses running along Rideau and Wellington streets from 2,600 per day to 600 per day. Combined with a redesigned bus system, the LRT is expected to reduce transit-related operating costs by up to $100 million annually starting in 2019.The line is part of a larger LRT network that the City of Ottawa plans to build.

11 Keephills 3 2010 Ranking: 8

generating Plant Location: Keephills, Alberta Owner: TransAlta and Capital Power

Status: Under construction with completion expected in 2011.$1.9 billion The 450 MW coal-fired generating plant will use supercritical boiler technology, which

Key Players: Graham Group features higher boiler temperatures and pressures, and a high-efficiency steam turbine. (general contractor); Capital According to Capital Power, carbon dioxide (CO2) emissions will be 24 per cent lower Power Corporation (construction); for the same amount of power produced by the Wabamum plants, scheduled to be retired TransAlta (operator) by TransAlta in 2010. This plant could also further reduce emissions by being part of Funding: Private Project Pioneer—a plan to capture and store up to one million tonnes of C02 a year.

“If you look at replacing coal with other sources, the numbers don’t add up.” —Gregory H. Boyce, CEO, Peabody Energy (at the World Energy Congress)

12 Edmonton International Airport Expansion$1.8 billion

Key Players: MMM Group (project manager); Stantec (prime consultant—architecture, and structural, mechanical, electrical engineering); EllisDon (construction management—combined office tower, design input); Cohos Evamy, a part of DIALOG (design— combined office tower ); PCL (construction—terminal building expansion); Stuart Olson Dominion Construction (construction manager—services feeding the new terminal, site infrastructure— new lot development); Morrison Hershfield (commissioning services)

Funding: Public

Status: Under construction with completion expected in 2012.

2010 Ranking: 12

Location: Edmonton, Alberta

Owner: Edmonton Regional Airports Authority

The project includes a terminal building expansion and renovations and a new combined office and air traffic control tower. The first phase of the project, completed in 2009, consisted of building six new gates. The temporary walkways linking the terminal to these new gates were designed (by PCL, its subcontractors, and the project consultants) to be reused once construction is complete.

LEED Target: New terminal—Certified; combined office tower—Silver

top100projects.ca ReNew Canada 15

Page 8: Company Index Top 100 Badge Programme

Cred

it: Ministry of Transp

ortation, Ontario

Wuskwatim generation Project $1.6 billion

13

One of the province’s largest construction projects, the 200 MW station will be part-owned by the NCN. A Project Development Agreement between Manitoba Hydro gives the First Nations community up to 33 per cent ownership of the station. This is the first time Manitoba Hydro has entered into an equity partnership with a First Nations community on a generating station project.

Key Players: Hatch, KGS Group (consultants)

Funding: Public

Status: Concrete placement on the station’s spillway structure began in 2009. Current projections show that Manitoba won’t need this new power until 2020, but WPLP is hoping to gain additional export revenues and profits by advancing the in-service date of Wuskwatim from 2012 to 2011.

2010 Ranking: 6

Location: Taskinigup Falls, about 45 kms southwest of Thompson, Manitoba

Owner: Wuskwatim Power Limited Partnership (WPLP)—an equity partnership between Nisichawayasihk Cree Nation (NCN) and Manitoba Hydro

As Ontario’s biggest single highway investment, this 11 km stretch will connect Highway 401 to the proposed Detroit River International Crossing, and ultimately to the U.S. Interstate system, while separating local and international traffic and eliminating stop-and-go traffic on the way to the border. This is a critical link for international trade as current Windsor crossings account for 31 per cent of Canada’s road trade with the United States.

Key Players: Infrastructure Ontario (procurement manager and project development); The Windsor Essex Mobility Group—Hatch Mott MacDonald, ACS Infrastructure Canada, Acciona, Fluor Canada, Dragados Canada (design-build-finance-maintain); Facca Construction (bridges, noise barrier); CH2M HILL, Morrison Hershfield (Infrastructure Ontario’s technical advisory team); URS Canada (prime consultant); Golder Associates (subconsultant to URS, geotechnical advisor)

Funding: P3 (DBFM)

Status: The project cost will be confirmed following financial close in early 2011. Preparatory work, including demolition and construction of a noise barrier and two bridges has been underway since 2009. Construction of the parkway is set to begin in 2011, and the preferred bidder targets completion of the Parkway by the end of 2014.

Ranking in 2010: 7

Location: Windsor, Ontario

Owner: Ontario Ministry of Transportation

niagara Tunnel Project $1.6 billion

15

Status: Under construction, with completion expected in 2013.

A regular on the Top 100—it’s been on the list since 2007—this new tunnel will divert an additional 500 cubic metres (m3) of water per second and, with an internal diameter of 12.7 m and a length of 10.2 km, is expected to be one of the largest tunnels ever built in North America.

Key Players: Strabag AG (design-build contactor); Dufferin Construction (main subcontractor); ILF Consulting Engineers (tunnel designer); Morrison Hershfield (design—above-ground work); Hatch Mott MacDonald, in association with Hatch (owner’s representative); The Robbins Company (supplier: tunnel boring machine); Rowa Tunnelling Logistics (supplier: TBM backup equipment)

Funding: Public

2010 Ranking: 9

Location: Niagara Falls, Ontario

Owner: Ontario Power Generation (OPG)

Windsor-Essex Parkway Project $1.6 billion

14

16 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 9: Company Index Top 100 Badge Programme
Page 10: Company Index Top 100 Badge Programme

Cred

it: AE

CO

M

Point Lepreau nuclear generating Station Refurbishment $1.4 billion

18

The Point Lepreau Nuclear Generating Station is the first CANDU-6 reactor to undergo a refurbishment involving the installation of the new calandria tubes in the reactor vessel. According to AECL, project delays are largely due to problems encountered in refitting these calandria tubes. The seal tightness of some of the new tubes does not meet the acceptance criteria standards. As of October 2010, project staff are proceeding with the removal of all 380 calandria tubes.

Key Players: Atomic Energy of Canada Limited (main contractor); Arvin Machine Works, Opron Maritimes Construction (subcontractors); Sunny Corner Enterprises (electrical services); ADI Limited, a Trow Global company (concept and design); Automation Tooling Systems (supplier: parts)

Funding: Public

Status: Under construction. AECL has again revised its project schedule with expected completion in 2012.

2010 Ranking: 15

Location: Point Lepreau, New Brunswick

Owner: NB Power

Autoroute 30 $1.5 billion

16

Status: Under construction with completion expected in 2012.

The plan to extend Quebec’s Highway A-30 includes a tunnel under the Soulanges Canal and two major bridges, the first over the St. Lawrence River and the second over the St. Lawrence Seaway at the Beauharnois. Design, construction, financing, operation, maintenance and rehabilitation of the 42 km autoroute will be done by the NA-30 consortium, with additional sections to be built by the MTQ and operated, maintained, and repaired by the consortium.

Key Players: Nouvelle Autoroute 30, s.e.n.c. (NA-30)—Acciona, Iridium Concessions Canada (concession); Dragados Canada, Aecon, Verreault, a subsidiary of Dessau (subcontractor of NA-30—design and construction); MMM Group (independent engineer—design review, attestation and oversight of project design and construction); Delcan (lender’s technical advisor)

Funding: P3 (DBFOM)

2010 Ranking: 11

Location: Châteauguay, Mercier, Léry, Beauharnois, Salaberry-de-Valleyfield, Les Cèdres, and Vaudreuil-Dorion, Quebec

Owner: Ministère des Transports de Québec (MTQ)

2010 Ranking: 13

Location: Edmonton, Alberta Owner: Province of Alberta

Key Players: Northwestconnect General Partnership— Northwestconnect Investments and Northwestconnect, both entities of Bilfinger Berger Project Investments (design-build-finance-operate); Flatiron-Graham-Parsons—a joint venture of Flatiron Constructors Canada, Parsons Overseas Company of Canada, and Graham Group (design-build contractor); AECOM (design); Delcan (independent design review—bridges, lender’s technical advisor); Carmacks Maintenance Services (maintenance contractor)

Funding: P3 (DBFO)

Status: Under construction with completion expected in the first quarter of 2011.

This new 21 km section of highway with four and six lanes will extend from Anthony Henday Drive at Yellowhead Trail on the west side of Edmonton to Manning Drive Freeway in the north.

Edmonton Ring Road, Anthony Henday drive nW $1.42 billion

17

18 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 11: Company Index Top 100 Badge Programme
Page 12: Company Index Top 100 Badge Programme

19

Top 100 Projects

york VIVA Bus Rapid Transit 2010 Ranking: NEW

(vivanext) Project Location: York Region, Ontario

Owner: York Region Rapid Transit Corporation; $1.4 billion Metrolinx/GO Transit

Key Players: York Region Rapid Transit Corporation - AECOM/DMJM Harris (program management), Delcan (planning and design), Kiewit (design, construction management), EllisDon (construction), Nord/LB (financial advisor and arranger of debt equity), Siemens (supplier: rail and bus, ITS, vehicles), and IBI Group (architecture, systems technology); McCormick Rankin Corporation, a member of MMM Group (owners’ engineer); Ecoplans Limited, a member of MMM Group (environment); URS Canada (engineering); Thurber Engineering (geotechnical); Hanscomb (costing); Revay and Associates (controls)

Funding: Public

Status: Construction began in 2009. The VIVA BRT bus lanes will open in operational segments as they are completed, with the entire project expected to be complete in 2020.

The dedicated bus lanes, which VIVA is calling Rapidways, are separate centre lanes that will allow VIVA buses to travel freely no matter how much traffic is using the conventional roadway. Some of the new stations will connect to the TTC subway system, GO Transit commuter rail, and express buses, York Rapid Transit local bus services, and other transit systems operating in neighbouring regions.

Cred

it: Partnership

s BC

The Evergreen Line will use the same Advanced Light Rapid Transit technology as the current SkyTrain system.

Key Players: Partnerships BC (procurement partner and project implementation)

Funding: P3 (DBF)

Status: In July 2010, the B.C. Ministry of Transportation and Infrastructure issued a RFQ to identify private partners to design, build, and finance the project, and will now choose up to three teams to submit RFPs. Construction is set to begin in summer 2011, once the EA certificate has been issued, with completion expected in 2014.

20 Evergreen Line Rapid Transit Line $1.4 billion

2010 Ranking: NEW

Location: Metro Vancouver, British Columbia

Owner: TransLink

This 11 km rapid transit rail line will extend from the existing Millennium SkyTrain Line at the Lougheed Town Centre station in Burnaby to the Coquitlam Town Centre, through the community of Port Moody. Plans for the system inclide elevated, at-grade, and tunnelled guideways.

Mcgill university Health Centre (MuHC) Redevelopment at the glen Campus $1.34 billion

Key Players: McGill Health Infrastructure Group—SNC-Lavalin and Innisfree (design, construction, financing, maintenance); SNC-Lavalin (design-build); IBI Group, HDR, Yelle Maillé, and NFOE (architects); Bouthillette, Parizeau et associés (engineering support for mechanical and electrical design); Les Services SNC-Lavalin ltée with Pomerleau and Verreault, a subsidiary of Dessau (construction); SNC-Lavalin O&M, in collaboration with Johnson Controls (operation, maintenance, life cycle)

2010 Ranking: NEW

Location: Montreal, Quebec Owner: MUHC

Funding: P3 (DBFM)

Status: Under construction with completion expected in 2014.

The MUHC’s new Glen Campus includes the Montreal Children’s Hospital, the Royal Victoria Hospital and the Montreal Chest Institute, the Research Institute of the MUHC and a Cancer Centre. The Glen Campus is part of the MUHC’s $2.25-billion redevelopment, which also includes the Lachine and Mountain campuses. Lachine and Mountain will be built through public financing methods and are currently being planned.

LEED Target: Silver

20 ReNew Canada top100projects.ca

21

Page 13: Company Index Top 100 Badge Programme

22

2011C

redit: The C

algary Airp

ort Authority

Cred

it: EllisD

on C

redit: S

TM

South Health Campus Phase 1 $1.31 billion

2010 Ranking: 14

Location: Calgary, Alberta Owner: Alberta Health Services

Key players: EllisDon (general contractor); Kasian Architecture (architects); Lockerbie & Hole (mechanical construction manager)

Funding: Public

Status: Under construction with completion expected in December 2011 and opening in 2012.

The initial phase will consist of approximately 156,000 square metres of developed space. Last year’s Top 100 listed this project’s cost as $1.4 billion. The revised cost is the result EllisDon having reimbursed $100 million due to revised escalation forecasts.

LEED Target: Silver

23 Calgary International Airport development Program $1.3 billion

Status: Under construction with completion expected in 2015.

The overall program includes a temporary baggage hall expansion, terminal renovations and the new terminal expansion for the E Pier. There will be an addition to the existing terminal and extensive renovations to address projected passenger levels for both transborder and international travel.

2010 Ranking: 16

Location: Calgary, Alberta

Owner: The Calgary Airport Authority

Key Players: EllisDon (construction manager); AECOM (project management consultant, electrical and mechanical consultant); Cohos Evamy, a part of DIALOG (prime design consultant)

Funding: Public

The 468 new cars will bear the name MPM-10 (for Matériel Pneumatique de Montréal, acquired in 2010). 24 2010 Ranking: NEW

Replacement of the Montreal Subway’s Rolling Stock $1.2 billion

Key Players: Dessau (engineering, project management, in-plant quality

Location: Montreal, Quebec

Owner: Société de transport de Montréal

Funding: Public

Status: All trains are expected to be delivered by 2018.

The Société de transport de Montréal is gradually replacing its old fleet of MR-

control); AECOM (studies and engineering for new train maintenance 63 metro cars—in service since 1966. workshops, specification for a new driving simulation system, train maintenance Maintenance facilities will also be upgraded, processes optimization); Bombardier-Alstom consortium (supplier: cars) and a new workshop will be designed.

top100projects.ca ReNew Canada 21

Page 14: Company Index Top 100 Badge Programme

Autoroute 185 $1 billion

The eight km extension to the Calgary LRT Transit System is the largest infrastructure project in the history of Calgary and the first new LRT line in 20 years, including the first underground and elevated stations. According to MMM Group, since construction started in February 2010, challenges have included traffic accommodation within restricted urban roadway right-of-ways, and coordinating the relocation of unanticipated utilities. That said, the project is on track for its completion in 2012—westlrt.ca has time-lapse videos of bridge removal and truss assembly.

2010 Ranking: 19

Location: Calgary, Alberta

Owner: City of Calgary

West LRT Line $1 billion 25

Key Players: SNC-Lavalin in a joint venture with Graham Group, Cana Construction, and Enmax Power Services Corporation (design-build); MMM Group (civil and structural design)

Funding: Public

Status: Construction began in 2010 with completion expected in 2012.

26

The project will expand 94 km of route 185 from two lanes to a divided four-lane highway. Work has been divided into six sections, three of which have been awarded to AECOM.

Key Players: AECOM (environmental impact study, hydraulic and hydrologic studies, preliminary and final designs, work supervision)

Funding: Public

Status: Under construction, with completion expected in 2016.

2010 Ranking: NEW

Location: Rivière-du-Loup to the New Brunswick border, Quebec

Owner: Ministry of Transportation of Québec

20 20

15

10

5

0

$13,350,100,000 Health Care

$14,879,200,000

Highway/ Bridge

$4,378,000,000

Water/ Wastewater

$25,100,000,000 Hydroelectric

$3,223,500,000 Rail

$11,120,000,000 LRT

$3,055,900,000 Justice

$1,455,000,000 Wind

$1,432,000,000 Social 15

9 8 7 7 4 4 5

ToTAL ToP 100 InVESTMEnT:

$96,096,400,000

num

ber

of P

roje

cts

22 ReNew Canada

Top 100 Projects

top100projects.ca

Page 15: Company Index Top 100 Badge Programme

georgetown South Track Layout and grading design Assignment $1 billion

27

This expansion will address both the forecasted increase in GO ridership along the corridor as well as the new proposed Union-Pearson Rail Link. Because of the size and complexity of the program, Metrolinx divided work on the corridor into nine individual segments, five of which have been awarded to Hatch Mott MacDonald. The contract is for detailed design and construction management of 14.8 km of corridor, which includes 30 km of new track, numerous retaining walls, sound walls, utility relocations and, site grading and drainage.

Key Players: Hatch Mott MacDonald (design, construction management); Delcan (prime consultant, Weston Tunnel)

Funding: Public

Status: Design work is expected to be completed in the first quarter of 2011 and construction completed by 2014.

2010 Ranking: NEW

Location: Toronto, Ontario

Owner: Metrolinx, a division of GO Transit

Sainte-Justine university Hospital Centre Modernization $995 million

28

Funding: Public, with some private sources of funding from the Hospital foundation ($70 million)

Status: Under construction with completion expected in 2018.

The Grandir en santé project involves the construction of some new buildings and the modernization of others. The project is being carried out in several phases, some of which have already been completed.

LEED Target: Silver

Key Players: TDC Consortium—Tecsult, DECASULT, and CIMA+ (project management); SKD/NCK Consortium— Saïa, Deslauriers, Kadanoff, Leconte, Brisebois, and Blais/Nicolet Chartrand Knoll (civil engineering and structural work); Lemay et associés, Jodoin, Lamarre, Pratte et associés, Brière, Gilbert et associés and Demontigny, Métivier, Hébert, Fortin, Martin Consortium (architects); Pellemon/Bouthillette, Parizeau et associés (electrical and mechanical engineering)

2010 Ranking: NEW

Location: Montreal, Quebec

Owner: Sainte-Justine University Hospital Centre

Transmission $1,564,000,000

3

BRT $2,005,000,000

3

$3,600,000,000 Airport

3

Subway $3,830,000,000

2

$1,003,700,000 Port

2

natural gas $1,037,000,000

2

$1,065,000,000 Environment

2

$698,000,000 Education

2

nuclear $1,400,000,000

1

Coal 1,900,000,000

1

Projects have been divided into sectors and subsectors. Some sectors dominate the list; others make less of an impression. Some sectors, by nature, involve smaller projects that won’t make the Top 100, while others simply aren’t seeing the investment that would result in a higher volume of projects.

Cross-Canada Project Tally: By Sector

ReNew Canada 23top100projects.ca

2011

Page 16: Company Index Top 100 Badge Programme

$966 million

Key Players: Green Timbers Accommodation Partners—Bird Construction, Bouygues Building Canada, HSBC Infrastructure, and ETDE Facility Management Canada (design-build-finance-maintain); Kasian Architecture (architect); Morrison Hershfield (building envelope services)

Funding: P3 (DBFM)

2010 Ranking: NEW

Location: Surrey, British Columbia

Owner: Government of Canada

$950 million 30

24 ReNew Canada

Top 100 Projects

2011

29 RCMP E division Headquarter Relocation Project

Cred

it: PW

GC

Status: Under construction with completion expected in 2012.

An initiative of Public Works and Government Services Canada and the Royal Canadian Mounted Police (RCMP), this project involves the relocation and consolidation of existing RCMP headquarters throughout Metro Vancouver to a new site in the City of Surrey.

LEED Target: Gold

Sheppard East LRT Project

Key Players: URS Canada (design, engineering); Hatch Mott MacDonald (Don Mills station—tunnel designer); Bombardier (supplier: light rail vehicles)

Funding: Public

Status: Construction began at the Agincourt GO station in 2009. Phase 2 of the project continues along Sheppard East from Conlins Yard to Meadowvale with expected completion in 2014.

2010 ranking: 20

Location: Toronto, Ontario

Owner: Metrolinx/GO Transit

This 14 km light rail line is part of the TTC’s Transit City plan. Metrolinx will oversee the TTC’s implementation of the project. The new line will be integrated into Toronto’s current transit system, replacing the Scarborough East bus line along a dedicated right-of-way from the Don Mills Subway Station to Meadowvale Road. The Sheppard LRT line is scheduled to receive 35 LRVs out of the 182 ordered from Bombardier.

Cred

it: Colum

bia P

ower C

orporation

The Waneta Expansion

Key Players: SNC-Lavalin (design-build, geotechncial consulting); Aecon (civil design and construction) Hatfield Consultants, Golder Associates (environmental consulting engineers)

Funding: P3 (Design-Build)

Status: Construction will begin in October 2011, with completion expected in 2015.

This 335 MW hydroelectric generating facility is adjacent to the existing Waneta Dam and powerhouse facilities on the Pend d’Oreille River. Fortis will own 51 per cent of the Waneta Expansion and will operate and maintain the non-regulated investment when the facility comes into service. Columbia Power, which will act as construction 31 $900 million manager for the partners, owns 32.5 per cent, and Columbia Basin Trust has a 16.5 per cent share. The Waneta Expansion will become 2010 Ranking: NEW part of the Canal Plant Agreement and will receive fixed energy and

Location: At the confluence of the Pend d’Oreille and capacity entitlements based on long-term average water flows. The Columbia Rivers, south of Trail, British Columbia energy will be sold to BC Hydro under a long-term energy purchase Owner: Fortis, Columbia Power Corporation, and agreement at prices comparable to those for projects recently Columbia Basin Trust accepted by BC Hydro under its 2008 Clean Power Call.

top100projects.ca

Page 17: Company Index Top 100 Badge Programme
Page 18: Company Index Top 100 Badge Programme

Southeast Stoney Trail Project $769 million

33

The Alberta government signed a 33-year contract with Chinook Roads Partnership to design, build, operate and partially finance Southeast Stoney Trail from the south side of the current Stoney Trail / 17th Avenue SE intersection south along the east perimeter of the City to Highway 22X, then west to the east side of the Highway 22X / Macleod Trail interchange. The contract also includes maintenance of Deerfoot Trail from its junction with Stoney Trail SE (currently Highway 22X) to its junction with Highway 2A.

Key Players: Chinook Roads Partnership—SNC-Lavalin Group and Acciona (design-build-operate-finance)

Funding: P3 (DBFO—only partial financing coming from the private-sector partner)

Status: Construction began spring 2010 with expected completion in 2013.

2010 Ranking: NEW

Location: Calgary, Alberta Owner: Government of Alberta

Capital Regional district Sewage Treatment Plant Program $782 million

32

centralized, liquids-only treatment facility at McLoughlin Point in Esquimalt and a separate biosolids digestion facility, located either at the Hartland Landfill or another suitable location. The system will also make it possible the defer the West Shore wastewater treatment plant until 2030. The proposed Clover Point wet weather facility has been eliminated from the project plan pending the minster of environment’s approval. The Clover and Macaulay facilities will be upgraded to pump wastewater to McLoughlin, and grit removal facilities will be added to the existing screening facilities at both locations. The Craigflower pump station will also be upgraded. The B.C. Ministry of Community and Rural Development has suggested a P3 model for the larger projects (treatment facilities) and a traditional funding model for smaller aspects of the project (upgrades to pump stations and pump lines). More on this project at watercanada.net/2010/sea-change/

Key Players: Stantec (business case, management and technical planning services); CH2M HILL (preliminary planning/study); Ernst & Young (business case); Westland Resource Group, Associated Engineering, Kerr Wood Leidal Associates (consultants); C N Ryzuk & Associates (geotechnical consultant); Delcan (independent design services, road/railway; subcontractor to SNC-Lavalin)

Funding: The procurement model is still being chosen.

Status: Approval has been granted by the B.C. government. The full project is expected to take ten years to complete.

Andy Orr with the Capital Regional District says this is the largest wastewater treatment project currently underway in the country. The system configuration will include a

2010 Ranking: NEW

Location: Southern Vancouver Island, British Columbia

Owner: Capital Region District

Total amount spent on water/wastewater projects in the Top 100 4,000 wastewater treatment

facilities or more across the country in need of upgrades

$24,000,000,000 in upgrades needed (according to the Canadian Water and Wastewater Association) to meet proposed new CCME standards

$4,378,000,000

Percentage of cost

63% $2,756,000,000 Expansions or upgrades to

existing facilities

37% $1,622,000,000 new facilities

26 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 19: Company Index Top 100 Badge Programme
Page 20: Company Index Top 100 Badge Programme

north LRT Extension, downtown to nAIT $725 million

Forrest Kerr Run-of-River Project $700 million

36

The 195 MW run-of-river hydroelectric generation project will channel a portion of the Iskut River flow and deliver electricity to the BC Hydro grid at its proposed Bob Quinn Lake Substation. AltaGas has a 60-year Electricity Purchase Agreement with BC Hydro and has an Impact Benefit Agreement with the Tahltan Nation, as well as an agreement to contribute to the construction of the Northwest Transmission Line, which runs from Terrace to the proposed interconnection point of Forrest Kerr, at BC Hydro’s proposed substation at Bob Quinn Lake.

Key Players: Coast Mountain Hydro Limited Partnership, a wholly owned subsidiary of AltaGas (developer); SNC-Lavalin (engineering procurement)

Funding: Private

Status: Site development and construction are underway, with expected completion in 2014.

2010 Ranking: NEW

Location: Northwestern British Columbia

Owner: AltaGas

Funding: P3 (DBFM)

Status: Under construction, with expected completion in 2013.

The new health care complex will be built on a 32-acre section of the 40-acre site in St. Catharines, replacing the aging St. Catharines General and Ontario Street sites. This is the largest infrastructure project currently undertaken by the Province of Ontario under the P3 model.

LEED Target: Certification

Key Players: Infrastructure Ontario (procurement manager and project development ); Plenary Health Niagara—Plenary Group, Borealis Infrastructure, PCL, B+H and Silver Thomas Hanley Architects, and Johnson Controls (design-build-finance-maintain); Trow Global (quality control); Smith + Andersen (mechanical and electrical consultant); Halsall Associates (structural engineering, envelope, and sustainability); A.M. Candaras Associates (civil engineering); BTY Group (independent certifier)

niagara Health System Health Care Complex $759 million

34

2010 Ranking: 23

Location: St. Catharines, Ontario

Owner: Niagara Health System

Cred

it: PC

L

35

Status: Under construction with expected completion in 2014.

The City of Edmonton is extending its LRT system 3.3 km north from the existing downtown Churchill Station to the Northern Alberta Institute of Technology (NAIT). The extension incorporates 700 metres of tunnel, including twin sequential excavation method tunnels from Churchill Station to a portal east of MacEwan Station. Three stations are being designed as part of the extension: MacEwan Station, Kingsway Station, and NAIT Station. This Extension is the first step in a plan that will ultimately see the LRT extended to the City’s northwestern limits near St. Albert.

Key Players: AECOM (detailed design, overall project management, coordination of consultant team); Stantec (design consultants); ISL Engineering and Land Services (design consultants); AMEC Earth and Environmental, SMA Consulting, ILF Consulting Engineers (subconsultants)

Funding: Public

2010 Ranking: NEW

Location: Edmonton, Alberta Owner: City of Edmonton

28 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 21: Company Index Top 100 Badge Programme
Page 22: Company Index Top 100 Badge Programme

north Battleford natural-gas-Fired Power Plant $700 million

Bruce to Milton Power Line $695 million

38

A 180 km, double-circuit, 500 kV transmission line is being built on a widened existing corridor between the Bruce Power Facility in Kincardine and Hydro One’s switching station in Milton. This project represents the largest expansion to Ontario’s transmission system in 20 years and, according to Hydro One, it’s much needed. Bruce Power is returning two nuclear units to service over the next few years, and about 700 MW of wind development projects have been identified in the Bruce area to date, with another 1000 MW of future renewable energy potential.

Key Players: Valard Construction (power line construction); Dillion (prime consultant)

Funding: Public

Status: Construction has begun on lands where Hydro One has acquired property rights and the necessary approvals, with expected completion in 2012.

2010 Ranking: 38

Location: Kincardine to Milton, Ontario

Owner: Hydro One Networks

37

Funding: Private

Status: Under construction, with expected completion in 2013.

All power produced by this 261 MW natural-gas-fired combined cycle plant will be sold under the Power Purchase Agreement to SaskPower.

Key players: SaskPower (power purchase agreement); Kiewit Power Partners (engineering, procurement, construction); General Electric (supplier: gas turbines); Alstom (supplier: steam turbine, generator, heat recovery steam generator, six turbine control system)

2010 Ranking: NEW

Location: North Battleford, Saskatchewan

Owner: Northland Power

Woodstock general Hospital $685 million

39

Funding: P3 (Build-Finance-Maintain)

Status: Under construction with expected completion in late 2011.

Woodstock General Hospital’s new health care facility will replace and double the size of the current hospital.

Key Players: Infrastructure Ontario (procurement manager and project development ); Parkin Architects (architects); Integrated Team Solutions (ITS)—EllisDon (construction contractor, developer, equity provider), LPF Infrastructure Fund, Honeywell, CIT Canada, Sun Life Assurance Company of Canada, Great West Life and Industrial Alliance (build-finance-maintain)

2010 Ranking: 26

Location: Woodstock, Ontario

Owner: Woodstock General Hospital

Total amount invested in energy projects in the Top 100 $32,456,000,000

Hydroelectric $25,100,000,000

77%

Coal $1,900,000,000

6%

nuclear $1,400,000,000

4%

natural gas $1,037,000,000

3%

Wind $1,455,000,000

5%

Transmission $1,564,000,000

5%

30 ReNew Canada

Top 100 Projects

top100projects.ca

Page 23: Company Index Top 100 Badge Programme

South Fraser Perimeter Road (SFPR) Project $658 million

BC Children & Women’s Hospital— Health Centre Redevelopment $682.2 million

40

The first phase will include the opening of additional neonatal intensive care unit beds at the BC Women’s Hospital & Health Centre, site preparations for the new hospital, scheduled to begin in early 2014, and construction of a new clinical support building and free-standing child day-care centre. The second and third phases of the project will include the building of the new BC Children’s Hospital and renovations and expansion of the BC Women’s Hospital. The Province is contributing $90.5 million for Phase 1, while the BC Children’s Hospital Foundation has pledged to raise $200 million through the Campaign for BC Children, with $150 million going toward the new BC Children’s Hospital.

Key Players: Hugh Condon Marler Architects (HCMA), in partnership with Callison (clinical support building—indicative design); HCMA (technical specifications); Resource Planning Group (clinical specifications). Three qualified proponent teams have been shortlisted to participate in the RFP phase of the competition to design and build the Clinical Support Building.

Funding: Public/Private

Status: In procurement for the clinical support building—right now, the project cost is an estimate.

2010 Ranking: NEW

Location: Vancouver, British Columbia

Owner: Provincial Health Services Authority

42

Status: Under construction, with expected completion in 2013.

The new 40 km, four-lane SFPR will run along the south side of the Fraser River, extending from Deltaport Way in southwest Delta to 176th Street (in Surrey with connections to Highways 1, 91, 99 and TransLink’s Golden Ears Bridge.

Key Players: Partnerships BC (procurement manager and project development); The Fraser Transportation Group—ACS Infrastructure Canada, Ledcor Development, Dragados Canada, Ledcor CMI, Belpacific Excavating & Shoring Limited Partnership, Vancouver Pile Driving (design, build, finance and operate); Delcan (program engineer); Atkins’ Lenders Technical Advisor team—Morrison Hershfield

Funding: P3 (DBFO)

2010 Ranking: 31

Location: Delta to Surrey, British Columbia

Owner: British Columbia Ministry of Transportation and Infrastructure

Red River Floodway Expansion Project $665 million

41

Funding: Public

Status: Work on the final stages of the project, including the replacement of two highway bridges and improvements to the Inlet Control Structure, is currently underway. Completion is expected in 2011.

In the spring of 2009, the expansion project achieved 1-in-700-years flood protection. One of the largest civil engineering projects in the world, this will increase flood protection for residents of the City of Winnipeg, East St. Paul and West St. Paul. The Manitoba Floodway Authority (MFA) is responsible for the expansion project, coordinating the work of about 150 companies and 3,000 workers on the project.

Key Players: Hatch, KGS Group, Dillon Consulting, AECOM, SNC-Lavalin, MMM Group, Earth Tech Canada, Wardrop Engineering—a Tetra Tech company, Ayshkum Engineering Ininew Project Management, First Canadian Engineers, Barnes & Duncan Land Surveying and Geomatics (engineering); PCL, Strilkiwski Contracting, Nelson House Forest Industries, Erickson Construction, Barkman Concrete—a division of M.D. Steele Construction, Structal-Bridges, Lafarge Canada, Camster Construction, Dyck Construction o/a Skownan/Dyck Joint Venture Construction Company, H. Baudry Construction, L. Chabot Enterprises, Hugh Munro Construction, Sigfusson Northern, MLA Northern Contracting, Kelly Panteluk Construction, 5456291 Manitoba, Cree West Contractors, Pritchard Engineering (contractors)

2010 Ranking: 29

Location: Winnipeg, Manitoba

Owner: The Province of Manitoba (Manitoba Floodway Authority)

ReNew Canada 31top100projects.ca

2011

Page 24: Company Index Top 100 Badge Programme

43

Top 100 Projects 2011

Prince Rupert Container Terminal development—Phase 2 $650 million

2010 Ranking: 22

Location: Prince Rupert, British Columbia

Owner: Prince Rupert Port Authority

Key Players: Maher Terminals— Deutsche Band (developer)

Funding: Private

Status: The environmental review is underway, with expected project completion in 2014.

This expansion is being undertaken to accommodate the continued growth in regional export traffic anticipated over the next decade.

Cred

it: Prince R

upert P

ort Authority

Cred

it: NO

RR

Limited

Architects E

ngineers Planners

New glass protected coverings over the east moat along Front Street.

Key Players: Vanbots, a division of Carillion Construction (contractor, construction management); Arup Canada (4D modelling, pedestrian flow, construction coordination analyses); NORR Limited Architects & Engineers, part of the Ingenium Group (design); PCL (general contractor); Clifford Restoration (building envelope restoration)

Funding: Public

Status: Under construction with expected completion in 2018.

44 union Station Revitalization $640 million

2010 Ranking: 34

Location: Toronto, Ontario

Owner: A co-production of federal, provincial, municipal governments and Metrolinx/GO Transit

Metrolinx has identified Union Station’s expansion as one of the key priorities in its Regional Transportation Plan for the Greater Toronto and Hamilton Area. The project includes a threefold increase in the GO Transit concourse space to accommodate the expected doubling of GO passengers at Union Station by 2030, and restoration of heritage aspects of the main building.There are also plans to enhance pedestrian concourses, including the construction of a new northwest PATH connection that will join the northwest corner of Union Station to Wellington Street. The City also plans to create a new lower retail level below the station.

32 ReNew Canada top100projects.ca

Page 25: Company Index Top 100 Badge Programme
Page 26: Company Index Top 100 Badge Programme

The Edmonton new Remand Centre $620 million

Cred

it: Stantec

2010 Ranking: NEW

Owner: Centre Hospitalier Universitaire de Québec (CHUQ)

Location: Quebec City, Quebec

Expansion and Renovation of L’Hôtel dieu de Québec $635 million

45

Key Players: BPR-Batiment, CIMA + (project manager)

Funding: Public

Status: With an EA still in progress, demolition work is planned for early 2011.

Two new buildings will be built, and the existing hospital expanded, while other existing buildings will be restored.

LEED Target: New buildings—Silver

2010 Ranking: 35

Location: Toronto, Ontario

Owner: Bridgepoint Health

Bridgepoint Health $622 million 46

Key Players: Infrastructure Ontario (procurement manager and project development ); Plenary Health Bridgepoint—Plenary Group, Innisfree, HDR/Diamond+Schmitt Architects, PCL, Johnson Controls, RBC Capital Markets (design-build-finance-maintain); Stantec Architecture/KPMB Architects (planning and design)

Funding: P3 (DBFM)

Status: Construction began in August 2009 with expected completion in 2013.

2010 Ranking: 36

Location: Edmonton, Alberta

Owner: Alberta Infrastructure

47

Key Players: Stuart Olson Dominion Construction (construction manager); ONPA Architects (architect); BPTEC-DNEngineering (structural engineering); Hemisphere Engineering (mechanical engineering); MP&P/GENIVAR (electrical engineering); ISL Engineering and Land Services (civil engineering); Lockerbie & Hole (mechanical engineering); Canem System (electrical engineering)

Funding: Public

Status: Under construction, with expected completion in 2012.

The remand facility in the city’s north end will replace the 29-year-old facility located downtown, which is currently over capacity. It will be the largest correctional facility in Canada.

LEED Target: Silver

Credit: L’H

ôtel Dieu d

e Québec

This new building will replace the existing aging hospital on the site. As part of the project scope, the historic Don Jail, which was built in the 1860s, will be preserved and integrated into the function of the hospital as administrative offices.

LEED Target: Certification

34 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 27: Company Index Top 100 Badge Programme
Page 28: Company Index Top 100 Badge Programme

The building plans are a function of the internal engineering processes, with large buildings broken down into a series of smaller visual elements to reduce the apparent scale of the structures.

Interior to Lower Mainland Transmission Project $602 million

48

BC Hydro’s plan to build a new 500 kV transmission line mostly along an existing right-of-way between the Nicola Substation near Merritt and the Meridian has been met with opposition. In November 2009, the Upper Nicola Indian Band, Okanagan Nation Alliance, and Nlaka’pamux Nation Tribal Council filed judicial review applications in B.C. Supreme Court challenging the EA for the project. The applications will be heard together by the court later this year. Donna McGeachie with BC Hydro says the company “takes its obligation to consult with First Nations very seriously.” According to BC Hydro, the new lines will mean a more efficient transfer of electricity, saving enough energy to supply about 80,000 homes per year.

Key Players: Golder Associates (EA)

Funding: Public

Status: An EA has been issued but contracts have yet to be awarded. The BC Utilities Commission is currently assessing the adequacy of First Nations consultation for the ILM Project. In the meantime, the Certificate of Public Convenience and Necessity for the project, issued by the Commission in 2008, has been suspended. Completion is still expected in 2014.

2010 Ranking: 37

Location: Merritt to Coquitlam, British Columbia

Owner: BC Hydro

Key Players: Seymour Capilano Filtration Plant: SSBV Consultants—a joint venture of Stantec, AMEC Earth and Environmental, Black & Veatch (project consultants); NAC Constructors (builder); Graham Group (general contractor, batch concrete)

Capilano Pumping Station: SSBV Consultants; Kingston Construction (builder)

Twin Tunnels: Hatch Mott MacDonald (consultants); Pacific Liaicon Associates (construction management); Knight Piesold Consulting, Kingston Construction (energy recovery facility/break head tank); Seymour-Cap Partnership—Aecon, Frontier-Kemper Constructors, J.F. Shea Construction (twin tunnel completion); Northwest Pipe Company (supplier: carbon steel pipe)

Funding: Public

Status: Under construction, with expected completion in 2013.

This project is part of the Greater Vancouver Water District’s Drinking Water Treatment Program. Projects include a new drinking water filtration plant—the world’s largest ultraviolet disinfection facility—along with twin tunnels linking the Seymour and Capilano watersheds, a new communications tower at the Seymour Falls Dam, a seismic upgrade to the Seymour Falls Dam and a new watermain twinning the existing main linking the Seymour plant to Burrard Inlet.

LEED Target: Seymour Capilano Filtration Plant—Gold

2010 Ranking: 39

Location: Vancouver, British Columbia

Owner: Metro Vancouver

Woodward Avenue Wastewater Treatment Plant Expansion and upgrades $600 million

49

Hamilton’s main wastewater treatment facility will be expanded to accommodate population growth, improve effluent quality, and increase treatment for wet weather flow. The program includes a new 1,700-millilitre-per day raw sewage pumping station, upgrades to existing primary clarifiers, a new membrane bioreactor facility (which will be one of the largest in the world), a new chlorine contact tank, new tertiary effluent outfall and upgrades to the Red Hill Creek (such as widening the creek to accommodate increased flows and works to mitigate erosion), upgrades to the power supply, electrical distribution system and standby power, solids handling and other ancillary upgrades. The project cost as it is currently listed is an approximation.

Key Players: CH2M HILL (design); AECOM (lead subconsultant, detail design and construction management)

Funding: Public

Status: Currently in the design phase with construction scheduled to begin in early 2011 and expected completion in 2014.

2010 Ranking: 24

Location: Hamilton, Ontario

Owner: City of Hamilton

Seymour-Capilano Water utility Projects $600 million

50

36 ReNew Canada

Top 100 Projects

top100projects.ca

Page 29: Company Index Top 100 Badge Programme

Cred

it: York

Funding: P3 (DBFM)

Status: Construction began in 2009, with expected completion in 2012.

The TSDC is being built to replace the Don Jail which is located on the south portion of the Mimico Correctional Centre property. It will be built with a geothermal ground source heat exchanger that will produce 7.8 terajoules of energy per year.

LEED Target: Silver

Key Players: Infrastructure Ontario (procurement manager and project development); ITS Consortium—EllisDon, Fengate Capital Management, RBC Dominion Securities, Zeidler Partnership Architects, Johnson Controls (design-build-finance-maintain); Stantec (planning and design compliance architects); Geo A. Kelson Company (mechanical design builder); Stephenson Engineering (structural engineer); Smith + Andersen (mechanical engineer); Crossey Engineering (electrical engineer); OZZ Electric, Univex joint venture, (electrical design builder); Vipond Systems Group (security systems integrator); DMJMH+N (security consultant)

2010 Ranking: NEW Location: Toronto, Ontario

Owner: Ministry of Community Safety and Correctional Services

Funding: Public

Status: The entire project is expected to be complete in spring 2012.

In 2003, the Regions of Durham and York were working on an expedited timeline to commission this expansion. According to CH2M HILL, the Class EA was challenging, as it meant involving numerous stakeholders including the regions’ staff, neighbouring municipalities, regulatory agencies, and the local conservation authority. The project team had to address concerns including nearshore algae, beach impacts, endocrine disrupting compounds, odour, air emissions, and impacts to nearby lakeshore trails.

LEED Target: Biosolid dewatering building— Silver

Key Players: CH2M HILL (prime consultant—EA, design, and resident inspection); AECOM (design and resident inspection); NAC Constructors (construction of liquid process modules, preliminary treatment, electrical substation); Kenaidan Contracting (construction of dewatering and incineration facilities); Graham Group (construction of digester modifications and new boiler building); Revay and Associates (project planning and management); Resource Environmental Associates (health and safety)

2010 Ranking: 41 Location: Pickering, Ontario

Owners: The Regional Municipalities of York and Durham

new Brunswick Route 1 gateway Project $580 million

53

Status: Construction began in 2010, with expected completion in 2013.

This project involves the design and construction of 55 km of new highway between Waweig and Lepreau. It will be New Brunswick’s first six-lane highway. Transfield Dexter Gateway Services Limited will be responsible for the operation, maintenance and rehabilitation of 235 km between St. Stephen and River Glade, excluding the Saint John Harbour Bridge

Key Players: R1G Project Company and Dexter Developer General Partnership, an affiliate of Municipal Enterprises (developer); Transfield Dexter Gateway Services (operator); MMM Group (lead engineer)

Funding: P3 (DBOM)

2010 Ranking: NEW

Location: Between Waweig and Lepreau, New Brunswick

Owner: Province of New Brunswick

Toronto South detention Centre $593.9 million

51

duffin Creek Water Pollution Control Plant $585 million

52

Cred

it: Stantec

ReNew Canada 37top100projects.ca

2011

Page 30: Company Index Top 100 Badge Programme

Southeast Collector Trunk Sewer $546 million

55

Status: Design of the tunnel is currently being completed. Construction will start in 2011 and completion is expected in 2014.

This project—funded completely by The Regional Municipality of York— has been in development since 2002—though the EA was just approved in early 2010. The earth pressure balance tunnel boring machines (which avoid requirements for dewatering and impacting the aquifers) and the segmental precast concrete tunnel lining have both been procured.

Key Players: Hatch Mott MacDonald and AECOM in a joint venture (detailed design and construction management); AECOM (integrated EA); Lovat (supplier: tunnel boring machines); Armtec Holdings (supplier: pre-cast concrete tunnel lining)

Funding: Public

2010 Ranking: 45

Location: The Regional Municipalities of York and Durham

Owner: The Regional Municipality of York

BC Place Revitalization $563 million 54

Funding: Public

Status: The interior upgrades were completed in 2009. Work on the new retractable roof has begun and will be finished in 2011.

The biggest part of this revitalization project is the installation of the largest cable-supported retractable roof of its kind in the world. In fact, the fixed-price contract for the roof alone is $458,000,000—a significant portion of the project cost.

Key Players: PCL (general contractor); Stantec (architectural and interior design); Geiger Engineers (structural engineer); Schlaich Bergermann und Partner SBP (consulting engineer); GENIVAR (mechanical and electrical engineers); C.M. Kling & Associates (specialty lighting); Acoustical Design Group (acoustic consultant); Morrison Hershfield (building envelope consultant); LMDG Building Code Consultants (code consultant); Western Pacific Enterprises (electrical); Fred Welsh (mechanical); Pacific Blasting & Demolition (demolition); Seda Seating (supplier: seating); Structal, a division of Canam Group (supplier: structural steel, cables); Hightex (supplier: retractable fabric roof); Fabritec/Shade Canada (supplier: fixed fabric roof)

2010 Ranking: BC Place’s roof replacement was 47

Location: Vancouver, British Columbia

Owner: BC Pavilion Corporation (PavCo), a Crown Corporation of the Province of British Columbia

Peace Country Regional Health Centre $520 million

56

The existing hospital site will be retained and used for ambulatory and primary care. The design will incorporate natural daylighting—a first for an Alberta hospital. While the building won’t be LEED certified, designers are using the Green Guide for Health Care, an adaptation of the LEED design guidelines specific to health care design.

Key Players: Stantec with HOK (design); Stantec (structural, mechanical, and electrical engineering, landscape architecture, civil engineering, transportation, helicopter consulting)

Funding: Public

Status: Renovations already underway at one of the project sites, the existing Queen Elizabeth II hospital. Construction of the new hospital will begin in 2011, with expected completion in 2015.

2010 Ranking: NEW

Location: Grande Prairie, Alberta

Owner: Peace Country Health

Cred

it: BC

Pavillion C

orporation (P

avCo)

38 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 31: Company Index Top 100 Badge Programme

Exclusive interviews, features and daily news at watercanada.net

[email protected]

Lee Scarlett, Associate Publisher [email protected]

Coming in January/February 2011:

Groundbreakers: How Canadian research is changing the waterscape

First Nations respond to Bill S-11

Road salt: winter’s friend, groundwater’s foe

What does 2011 hold for Canada’s water industry?

and

Celebrating the best and brightest in Canada’s water sector.

watercanada.net/watersnext

Kerry Freek, Editor

Page 32: Company Index Top 100 Badge Programme

“Wind is the most competitive with traditional sources of power generation of all the renewables.” —Dan Balaban, Founder and CEO, Greengate Power

Parallel Runway Project $500 million

57

Status: Construction scheduled to begin in April 2011—a construction manager is currently being selected. The project is expected to be complete in 2014.

The Airport Development Program, which includes the building of the new runway and concourse at YYC, will be the largest construction project in Calgary’s history. At 14,000 feet, the new surface will be the longest commercial runway in Canada. This land was acquired and designated for this purpose in the 1970s and has been a part of the CAA’s long-term Master Plan since 1992.

Key Players: AECOM (program manager, EA consultant); Hatch Mott MacDonald (preliminary design consultant); Associated Engineering/CH2M HILL (prime consultant, engineer of record)

Funding: Public

2010 Ranking: 44

Location: Calgary, Alberta Owner: The Calgary Airport Authority

Forensic Services and Coroner’s Complex (FSCC) $497 million

59

The new facility will consolidate the operations of the Centre of Forensic Sciences, Office of the Chief Coroner, and the Ontario Forensic Pathology Unit from their current location in downtown Toronto. The new complex will accommodate increased capacity, while housing the three agencies on one site will increase construction and operational efficiencies. Carillion Construction is the design-build contractor. As part of the same consortium, Stantec is the lead architect, McClaren, Wilson & Lawrie is the forensic architect, and Modern Niagara Toronto and the Univex Group of Companies are the electrical contractors.

LEED Target: Gold

Key Players: Infrastructure Ontario (procurement manager and project development ); Carillion Secure Solutions consortium—Carillion, Concert Properties, Stantec, McClaren, Wilson & Lawrie, Modern Niagara Toronto, the Univex Group of Companies, BMO Capital Markets (design-build-finance-maintain); WZMH Architects (master planning, schematic design, planning and design compliance architects); Crossey Engineering (mechanical engineering consultant)

Funding: P3 (DBFM)

Status: Construction began in 2010, with expected completion in 2013.

2010 Ranking: NEW

Location: Toronto, Ontario

Owner: Ministry of Community Safety and Correctional Services

Comber Wind Project $500 million 58

The project is expected to have an installed capacity of 165 MW. Brookfield Renewable Power has a 20-year contract under Ontario’s Feed-in Tariff (FIT) Program.

Key Players: Stantec (environmental and planning aspects); Mortenson Construction (contractor); Siemens (supplier: turbines)

Funding: Private

Status: Under construction, with expected completion in late 2011.

2010 Ranking: NEW

Location: Lakeshore, Essex County, Ontario

Owner: Brookfield Renewable Power

Cred

it: Stantec

40 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 33: Company Index Top 100 Badge Programme
Page 34: Company Index Top 100 Badge Programme

Eastern Commuter Train Line $478.5 million

60 The Train de l’Est is intended to make up for the lack of permanent mass transit infrastructure serving Montreal East and the North-East Ring (Repentigny, Terrebonne and Mascouche) of the metropolitan region. The AMT awarded Bombardier a contract for the acquisition of 160 new two-storey cars, 30 of which will be assigned to the Train de l’Est. AMT (with New Jersey Transit) also awarded Bombardier a contract for the acquisition of five dual-mode (diesel and electric powered) locomotives. Given the proximity of the route to General Dynamics propane plant, a protective berm and a metal structure with a roof will be built along the section that crosses that site.

Key Players: Bombardier (supplier: trains)

Funding: Public

Status: Under construction, with expected completion in 2012.

2010 Ranking: NEW Location: Montreal, Quebec

Owner: Agence métropolitaine de transport (AMT)

Status: Construction is expected to begin in fall 2010, with expected completion in 2016.

A new facility is being built on the current Grenville Street site. The redeveloped Women’s College Hospital will replace all existing buildings and consolidate most hospital services into one location.

LEED Target: Certification

Key Players: Infrastructure Ontario (procurement manager and project development ); Women’s College Partnership—Bilfinger Berger Project Investments, Perkins Eastman Black/IBI Group (design-build-finance-maintain); The Walsh Group/Bondfield Construction (construction); Black & McDonald/HSG Zander (facilities management)

Funding: P3 (DBFM)

2010 Ranking: NEW

Location: Toronto, Ontario

Owner: Women’s College Hospital

Funding: Public

Status: Under construction, with expected completion in 2011.

The four contracts involve widening the highway and adding high-occupancy vehicle (HOV) lanes. The HOV lanes through Halton Region opened in November 2010. Construction also included a new QEW/Bronte Creek Twin Bridge—a new five-span, high level, precast concrete girder bridge spanning the Bronte Creek Valley. QEW/Bronte Creek Twin Bridge (the contract included Aecon, Dufferin, and MRC, a member of MMM Group). According to MRC, which acted as MTO’s consultant for preliminary and detailed design, as part of the reconstruction, all associated highway infrastructure was replaced and upgraded to current standards, including storm sewer infrastructure and Advanced Traffic Management Systems for the QEW.

2010 Ranking: The St. Catharines/Niagara Region contract ($167 million) was 87

Owner: Ontario Ministry of Transportation (MTO)

Location: Halton Region and Niagara Region, Ontario

Women’s College Hospital Redevelopment $460 million

61

Queen Elizabeth Way Widening $457.7 million 62

Key Players: Contract 1: $65 million Widening of 6.1 km to six lanes from Guelph Line to Burloak Drive. Dufferin Construction (contractor); IBI Group/Giffels, part of the Ingenium Group (design)

Contract 2: $92.4 million Widening of 4.5 km to six lanes from Burloak Drive to Third Line. Aecon (contractor); McCormick Rankin Corporation, a member of MMM Group (design)

Contract 3: $133.3 million Widening of 5.7 km to six lanes from Third Line to Trafalgar Road. Dufferin Construction (contractor); URS Canada (design, construction administration)

Contract 4: $167 million Queen Elizabeth Way Widening through to St. Catharines. Dufferin Construction (contractor); Morrison Hershfield (design); Golder Associates (subconsultant to Morrison Hershfield for geotechnical design)

Cred

it: Infrastructure Ontario

42 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 35: Company Index Top 100 Badge Programme
Page 36: Company Index Top 100 Badge Programme

63

Top 100 Projects

SAIT Polytechnic Trades and Technology Complex $445 million

2010 Ranking: NEW

Location: Calgary, Alberta

Owner: SAIT Polytechnic

Key Players: PCL (general contractor); Gibbs Gage Architects (architect); Carma Developers (builder); Morrison Hershfield (engineering consulting) ; Enermodal Engineering, a member of MMM Group (LEED, energy, commissioning consultant)

Funding: Public/Private

Status: Under construction, with expected completion in 2012.

This image shows the Aldred Centre, the largest of the three buildings that will make up the Trades and Technology Complex.

Cred

it: SA

IT

Over the past five years, SAIT has had to turn away an average of 4,000 qualified applicants each autumn due to capacity issues. Once complete, the new complex is expected to allow for 8,100 more apprenticeship and full-time students each year for hands-on, career-oriented training. The Province of Alberta is contributing $300 million to the project; SAIT is hoping to raise the remainder through philanthropic partnerships. So far, $62.5 million has been contributed towards the $75-million goal.

LEED Target: Silver

Cred

it: Partnership

s BC

Key Players: Partnerships BC (procurement manager and project development ); Infusion Health—Bilfinger Berger Project Investments, John Laing Infrastructure, Graham Group, Stantec, Black & McDonald, Royal Bank of Canada, Dexia Crédit Local (design-build-finance­maintain); H.H. Angus (compliance engineers)

Funding: P3 (DBFM)

64 Kelowna and Vernon Hospitals Project $432.9 million

LABEL MAKER

Out of all 100 projects, 47 are in sectors that could apply for LEEd certification (Education, Health Care, Public Buildings, Airports, Water/Wastewater)

2010 Ranking: 48

Location: Kelowna and Vernon, British Columbia

Owner: Interior Health Authority

Status: Under construction, with expected completion in 2012.

In addition to upgrades at Kelowna General Hospital and Vernon Jubilee, a new University of British Columbia Clinical Academic Campus (a two-storey building) and parkade is being built. Stantec Consulting is responsible for the architectural design, civil, structural, mechanical, and electrical engineering, internal project management, energy modeling, LEED consulting, interior design, and landscape design. As part of the same consortium, Graham Group is the design-builder, Black & McDonald are responsible for facilities maintenance, and H.H. Angus are the compliance engineers.

LEED Target: Gold

Of those 47, total projects targeting some level of LEED certification: 28 (60%)

20Health Care

9 Water/Wastewater

Public Building

0 5 10 15 20

Silver 15 (54%)

gold 8 (29%)

Certification 5 (18%)

number of Projects 44 ReNew Canada top100projects.ca

9

4 Education

Airport 3

Page 37: Company Index Top 100 Badge Programme

Status: Under construction, with expected completion in 2013.

Currently, SickKids research teams are scattered across six different locations in downtown Toronto. This project brings them together in what will be the largest high-rise research facility in Canada. While SickKids has received $91.1 million from the Canada Foundation for Innovation’s Research Hospital Fund, there’s an ongoing fundraising campaign to raise another $200 million (last year’s Top 100 wrongly listed this project as a P3).

LEED Target: Gold

Sydney Tar Ponds Cleanup $400 million

65

In October 2010, the Sydney Tar Ponds Agency announced HAZCO Environmental Services as the successful bidder for the $19.1-million project to build a protective cap on top of treated material. This is one of the final steps in this massive remediation. AECOM’s Doug Allingham calls this its biggest initiative in the Maritimes. To date, the south tar pond has been remediated. The north pond, from Ferry Street to the north pond narrows, is scheduled to be treated by fall 2012 and the last section in 2013.

Key Players: AECOM, CBCL (design); Stantec (environmental consultant); ADI Limited, a Trow Global Company, AMEC Earth and Environmental (environmental impact statement); Nordly’s Environmental (S/S remediation); MB2 Excavating and Construction and Beaver Marine in a joint venture (groundwater collection system, water treatment plant); Mikjikj Enterprises (plant operations, maintenance); HAZCO Environmental Services (builder—protective cap)

Funding: Public

Status: Under construction, with expected completion in 2014.

2010 Ranking: 51

Location: Sydney, Nova Scotia Owner: Sydney Tar Ponds Agency

Status: Under construction, with expected completion in 2014.

This major highway project in the rapidly growing Fort McMurray area includes construction of a new Franklin Avenue Tunnel to direct the Grant MacEwan traffic. Due to compressible clays and layers of tar sands in the subsurface, the design will involve building large extensive retaining structures to mitigate slope failures to enable the realignment of Highway 63 into the valley slope. According to AECOM, challenges also include large-scale, multi-million-dollar utility relocations and installations throughout the project limit to tie in to various infrastructures.

2010 Ranking: NEW

Location: Fort McMurray, Alberta Owner: Province of Alberta

Cred

it: AE

CO

M

Key Players: Stantec (prime consultant and design); AECOM, CH2M HILL (design); Thurber Engineering (geotechnical); Gan & Gan Utilities & Engineering (utilities); Dallas E. Maynard and Associates (land acquisition); HyRoad Surveys (survey)

Funding: Public

Highway 63 Corridor $400 million 67

“The issues are different; they don’t have as many big projects.” —AECOM’s Doug Allingham on Atlantic Canada’s presence in the Top 100.

The Research & Learning Tower, The Hospital for Sick Children (SickKids) $400 million

2010 Ranking: 62

Location: Toronto, Ontario

Owner: The Hospital for Sick Children (SickKids)

Key Players: EllisDon (general contractor); Diamond+Schmitt Architects with HDR Architecture (architects); Halcrow Yolles, part of the Halcrow Group (structural engineer); H.H. Angus (mechanical engineer, electrical engineer); du Toit Allsop Hillier (landscape architect); Hanscomb (cost consultant); Leber Rubes (code consultant); Cobalt Engineering (sustainability, LEED consultant)

Funding: Public

66

Cred

it: Sick K

ids H

ospital

ReNew Canada 45top100projects.ca

2011

Page 38: Company Index Top 100 Badge Programme

Top 100 Projects 2011

68 Halkirk I Wind Project $380 million

Cred

it: Greengate

Upon completion, Halkirk I will be Alberta’s largest operating wind energy project.

Key players: Greengate Power Corporation (developer); GL Garrad Hassan (consultant)

Funding: Private

Status: The project has been fully permitted and expected completion is in 2011.

2010 Ranking: NEW

Location: Halkirk, Alberta

Owner: Greengate Power Corporation

The 150 MW wind energy project is located 10 km from a 240 kV transmission line with available capacity. Greengate has obtained approval to connect to this transmission line from the Alberta Electric System Operator. According to Greengate’s founder and CEO, Dan Balaban, “The challenge in the wind business is that in order to have an economically viable site, it needs to be an area with strong wind resource. But unless [it’s near existing] transmission there’s no way of selling the product.”

69 Waterloo Region Consolidated Courthouse $379 million

2010 Ranking: NEW

Location: Kitchener, Ontario

Owner: Ontario Ministry of the Attorney General

Key Players: Infrastructure Ontario (procurement manager and project development ); Integrated Team Solutions— Fengate Capital Management/LPF Infrastructure Fund, EllisDon, NORR Limited Architects & Engineers, part of the Ingenium Group/AECOM Services, CIT Canada (design­build-finance-maintain); Enermodal Engineering, a member of MMM Group (LEED, energy, commissioning consultant)

TRAnSIT VS. TRAnSPoRT

Cred

it: Infrastructure Ontario

The new Waterloo Region Consolidated Courthouse will gain LEED points with energy efficiency, healthy indoor environments, and reduced greenhouse gas emissions.

Funding: P3 (DBFM)

Status: Under construction, with expected completion in 2013.

The new facility will consolidate the Superior Court of Justice and Ontario Court of Justice, currently operating in three locations across Waterloo Region.

LEED Target: Silver

Top 5 Projects Transit Eglinton Crosstown Light Rail Transit (LRT) project

Spadina Subway Extension

$4,600,000,000

$2,630,000,000

ON

ON

LRT

Subway 19

transit Ottawa Light Rail Project Phase 1 $2,100,000,000 ON LRT projects York Viva Bus Rapid Transit (vivaNext) project $1,400,000,000 ON BRT A total investment of

Evergreen Line Rapid Transit Line $1,400,000,000 BC LRT $20,178,500,000 Top 5 Projects Transportation Turcot Interchange $3,000,000,000 QC Highway 15 Port Mann/Highway 1 Project

Windsor-Essex Parkway Project

$2,460,000,000

$1,600,000,000

BC

ON

Bridge, Highway

Highway transportation

projects Autoroute 30 $1,500,000,000 QC Highway A total investment of

Edmonton Ring Road, Anthony Henday Drive NW $1,420,000,000 AB Highway $14,879,200,000

46 ReNew Canada top100projects.ca

Page 39: Company Index Top 100 Badge Programme
Page 40: Company Index Top 100 Badge Programme

When phase 1 of the project is completed, the terminal will comprise two berths with initial projected capacity of 1.5 million twenty-foot equivalent units per year.

48 ReNew Canada

Top 100 Projects

Royal Victoria Hospital 70 $370 million

Key Players: Infrastructure Ontario (procurement manager and project development ); Vanbots, a division of Carillion Construction (general contractor); H.H. Angus (mechanical and electrical engineering)

Funding: P3 (Build-Finance)

Status: Under construction, with expected completion in 2013.

2010 Ranking: 67

Location: Barrie, Ontario Owner: Royal Victoria Hospital

This project nearly doubles the size of the existing hospital. Last year’s Top 100 listed the contract price at $258.5 million. The estimated total cost of the project is $370 million. This cost includes the fixed construction contract with Vanbots as well as other estimated costs related to the project such as furniture, equipment, permits, architectural and engineering fees, transactional and project management fees and the hospital’s early works projects.

71 Maher Melford Terminal $353.7 million

2010 Ranking: NEW

Location: Strait of Canso, Nova Scotia

Owner: Melford International Terminal

Key Players: Melford International Terminal, Cyrus Capital Partners, Maher Terminals (developers); RailAmerica (rail service providers); Millbrook First Nation (investment, consulting services)

Funding: Private

Status: Construction is scheduled to start in 2011, with expected completion in 2013.

The new Maher Melford Terminal will connect to key interior North American markets through intermodal rail service which serves Nova Scotia via its East Coast Main Line.

Cred

it: Melford

International

72 Kitchener Wastewater Treatment Plant upgrade $350 million

Key Players: Phase 1: Tetra Tech, formerly Wardrop/ Hydromantis (design, contract administration for Manitou Drive Biosolids Dewatering Facility)

Phase 2: CH2M HILL (design, construction administration for the Kitchener WWTP UV and Plant 2 upgrades)

Phase 3: AECOM (design consultant for Plant 3 Upgrades)

Funding: Public

Status: Phase 1 is under construction, with expected completion in 2011. Phase 2 is expected to be complete by 2013, and Phase 3 upgrades will continue until 2019.

2010 Ranking: NEW

Location: Kitchener, Ontario

Owner: Region of Waterloo

This project includes a new biosolids dewatering facility, refurbishment of the Plant 2 secondary treatment processes, a new ultraviolet disinfection facility and effluent pumping station and, finally, decommissioning of the biosolids lagoons, refurbishing of the preliminary and primary unit processes, adding standby power, and building a new Plant 3 process train. Mostly funded by the Region of Waterloo, a small percentage of project funding ($2-million loan; $200,000 grant) is coming through the Federation of Canadian Municipalities’ Green Municipal Fund.

LEED Target: Dewatering biosolids facility—Silver

top100projects.ca

Page 41: Company Index Top 100 Badge Programme

Because of the visually sensitive nature of the site, AECOM commissioned a landscape architecture firm through a public design competition. The carhouse is designed with a large sloping green roof which will cover more than 90 per cent of the building and is a prominent feature when viewed from outside the site.

73

2011

Lakeview Water Treatment Plant Expansion $350 million

Cred

it: Hatch M

ott Macd

onald

Fully funded by the Region of Peel, through its Capital Projects Delivery Program, the plant is being expanded from 820 megalitres per day (ML/day) to 1,150 ML/day.

LEED Target: Administration and maintenance building at Lakeview—Silver

2010 Ranking: 52

Location: Mississauga, Ontario

Owner: Peel Region

Key Players: CH2M HILL (design consultant); Hatch Mott MacDonald; MACTEC Federal Programs (value engineering); Ontario Clean Water Agency (operations); General Electric (supplier: membranes)

Funding: Public

Status: Under construction, with expected completion in 2014.

Cred

it: TTC

74 Ashbridges Bay LRV Maintenance and Storage Facility $345 million

Key Players: AECOM (detailed design, site evaluation, EA, construction phase support); Brown and Storey Architects (urban/landscape design); Scott Torrance Landscape Architect (landscape architecture)

Funding: Public

Status: Construction is expected to begin in 2011, with completion scheduled for 2013.

2010 Ranking: NEW

Location: Toronto, Ontario

Owner: TTC

This new facility will provide service and storage for the new low-floor LRVs that will be replacing the current fleet of streetcars in Toronto. The new vehicles will begin arriving in 2013.

A key element of the project is the decommissioning of 375,000 m3 of contaminated fill that was stockpiled on the site. A separate substation building and a large stormwater management pond is located on the site. According to AECOM, the detailed design process included developing special footings to support the building on the poor ground on the site, and a difficult relocation of six 115 kV underground Hydro One feeders which crossed the site. Design also had to comply with the City of Toronto’s Green Standards.

top100projects.ca ReNew Canada 49

Page 42: Company Index Top 100 Badge Programme

Top 100 Projects 2011

york Energy Centre 75 $337 million

Key Players: Pristine Power (developer); Lill & DiFazio Constructors (contractor); POWER Engineers (engineer); EPTCON (electrical); Gryphon International Engineering Services (collaborating engineer); Dillon Consulting (EA and permitting manager); Siemens (supplier: gas turbine generators, supporting gas turbine auxiliaries)

2010 Ranking: NEW

Location: King Township, Ontario

Owner: Pristine Power, Harbert York Canada Company

Funding: Private

Status: Financial close occurred in August 2010, with construction expected to be complete in 2012.

This 400 MW gas-fired peaking generation facility has a 20-year peaking generation contract with the Ontario Power Authority.

Key Players: PCL (construction); Associated Engineering (prime consultant)

HoT dAM

76 glenmore and Bearspaw Water Treatment Plants upgrade $325 million

2010 Ranking: 53

Location: Calgary, Alberta Owner: City of Calgary

Funding: Public

Status: Under construction, with expected completion in May 2011.

This is one of the largest construction management projects delivered by the City of Calgary. According to PCL, it was extremely difficult to incorporate construction tie-in activities within the live operating plant. Typically scheduled during the low water consumption months of November and December, shifts that run 24 hours a day, seven days a week are often required to ensure deadlines are met.

The amount of power produced 6,788 by all 8 hydroelectricMegawatts projects on the list

25% British Columbia 25% ontario 25% Quebec

12.5% Manitoba 12.5% newfoundland

Breakdown by projects/region

5 Traditional

dams

3 Run-of-river

50 ReNew Canada top100projects.ca

Page 43: Company Index Top 100 Badge Programme
Page 44: Company Index Top 100 Badge Programme

Mississauga Bus Rapid Transit (BRT) Project $320 million

2010 Ranking: 56

Location: Mississauga, Ontario

Owner: City of Mississauga; Metrolinx/GO Transit

77

Key Players: BRT East (Hurontario to Renforth)— McCormick Rankin Corporation, a member of the MMM Group (prime consultant, design, contract administration); MMM Group (station structural consultant); IBI Group (station architecture); H.H. Angus (station mechanical/electrical consultant); Thurber Engineering (geotechnical)

BRT West (Winston Churchill to Erin Mills)—Giffels, a part of the Ingenium Group, IBI Group (prime consultant, design); Golder Associates (subconsultant to Giffels—IBI Group, geotechnical)

Funding: Public

Status: Under construction, with expected completion in 2013.

This dedicated east-west transit corridor (busway) across Mississauga will run along Highway 403 (combining the use of the existing bus bypass shoulders), Eastgate Parkway and Eglinton Avenue corridors connecting Winston Churchill Boulevard in the west to Renforth Drive in the east. The project incorporates 32 bridge structures including three river crossings, extensive utility works and several kilometres of retaining walls. The busway will connect with local bus service (Mississauga Transit), inter-regional bus service (GO), the TTC Bloor Subway (Kipling Station) and the planned Eglinton Crosstown LRT, with additional service to Toronto Pearson Airport.

2010 Ranking: 54

Location: Winnipeg, Manitoba

Owner: Canadian Museum for Human Rights

Key Players: PCL (construction manager, concrete structure); Smith Carter Architects (executive architect/prime consultant); Antoine Predock Architect (design architect); Halcrow Yolles, part of Halcrow Group and Crosier Kilgour & Partners (structural engineers); The Mitchell Partnership, SMS Engineering (mechanical engineers); Mulvey+Banani International, AGE Power Consultants, part of MCW Group (electrical engineers); KGS Group (civil engineers); Scatliff+Miller+Murray (landscape architects); Enermodal Engineering, a member of MMM Group (LEED, energy, commissioning consultant); Subterranean (Manitoba) (foundations); ThyssenKrupp Elevator Canada (elevators); Derksen Plumbing and Heating (mechanical systems); Wescan Electrical and Mechanical Services (electrical systems); Design For All (design consultant); G A Masonry (supplier: masonry); Walters (supplier: structural steel); Josef Gartner (supplier: exterior glazed façade); Border Glass & Aluminum (supplier: miscellaneous glazing systems); Allmar International (supplier: doors frames and hardware); Gracom Masonry (supplier: interior stone finishes)

Funding: Public/Private

Status: Construction began in 2009, with expected completion in 2012.

The Museum features three major components: concrete, steel and glass. Finishing includes Tyndall stone, alabaster, and a large glazed glass superstructure. It is Canada’s first national museum to be established with financial contributions from all levels of government and with very significant contributions from the private sector—a total of $117 million has been raised by the Friends of the Canadian Museum for Human Rights.

LEED Target: Silver

Kingston Subdivision Project $300 million

2010 Ranking: 57

Location: Montreal to Ottawa to Toronto, Quebec and Ontario

Owner: VIA Rail

79

Key Players: CN Rail (contractor); AECOM (engineering); Stantec (EA); New Alliance (bridges); Cruickshank Construction (grading); PNR RailWorks (signal upgrades)

Funding: Public

Status: Under construction, with expected completion in 2011.

This project involves a series of infrastructure improvements at eight locations along the 539 km, double-track rail line. The intent is to boost capacity by eliminating bottlenecks and to reduce conflicts between VIA passenger and CN freight trains.

Canadian Museum for Human Rights $310 million

78

Cred

it: Dan H

arper

52 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 45: Company Index Top 100 Badge Programme
Page 46: Company Index Top 100 Badge Programme

Cape Scott Wind Farm Phase I $300 million

2010 Ranking: 58

Location: Toronto, Ontario

Owner: Metrolinx/GO Transit

Key Players: Siemens Canada (contractor); Delcan (program management, concept design, facility planning, design management, rail design); IBI Group (consultant up to and including contract award, owner’s representative); Morrison Hershfield (engineering, construction administration for civil enabling works)

Funding: Public

Status: Under construction, with expected completion in 2014.

The project involves the design, supply, installation and commissioning of a new control signals system for Union Station, replacing a system that has been in place since 1920. The goal is to bring more trains in and out of Union Station, in addition to creating more reliable operations, improved communications, and increased scheduling flexibility. Expired signalling, electrical and communications equipment will also be replaced with modern electronic equipment.

2010 Ranking: 68

Location: Edmonton, Alberta

Owner: Alberta Health Services

Key Players: PCL (construction manager); DIALOG (prime consultants)

Funding: Public

Status: Under construction, with expected completion in 2012.

The new building, to be built on an existing site at the University of Alberta, was listed at $228 million on last year’s Top 100. Updated information shows that costs may be in excess of $300 million.

2010 Ranking: NEW

Location: North of Holberg, British Columbia

Owner: Sea Breeze Power, International Power Canada

82

Key players: Hatch (consulting engineer)

Funding: Private

Status: Construction is expected to begin in 2011, with expected completion in 2012.

The 99 MW wind farm is the first British Columbia wind project to receive an EA certificate. In March 2010, it recieved a 20-year electricity purchase agreement with BC Hydro. An Impact Benefits Agreement with the three First Nations is progressing through negotiation. This will be Sea Breeze’s first operating power generation facility.

union Station Rail Signalling Program $300 million

80

Edmonton Clinic South at the university of Alberta $300 million

81

Cred

it: PC

L

54 ReNew Canada

Top 100 Projects

top100projects.ca

Page 47: Company Index Top 100 Badge Programme

2011

Ismaili Centre Toronto, Aga 2010 Ranking: NEW

Khan Museum and Park Location: Toronto, Ontario

Owner: Aga Khan Development Network $300 million

83

Key Players: Vanbots, a division of Carillion Construction (contractor); Charles Correa Associates (design—Ismaili Centre); Fumihiko Maki (design—Aga Khan Museum); Vladimir Djurovic Landscape Architecture (design— landscaped park); Moriyama & Teshima (architects of record)

Funding: Private

Cred

it: Partnership

s BC

LEED elements include a plan to reduce waste by 75 per cent, incorporate stormwater management, and use local construction materials.

Status: Under construction, with expected completion in 2012.

The Ismaili Centre Toronto will be the newest addition to a network of such centres worldwide—and the second in Canada. The site is being developed into a park where the Ismaili Centre Toronto and the Aga Khan Museum will be situated.

2010 Ranking: NEW

Location: Fort St. John, British Columbia

Owner: Northern Health Authority

Funding: P3 (DBFM)

Status: Under construction, with expected completion in 2012.

These two new buildings on a single 40-acre greenfield site donated by the City will be the

84 Fort St. John Hospital and first hospital replacement of its size in Northern Residential Care Project Canada. Health Care Projects Canada is acting as

project manager. As part of the same consortium, $297.9 million

Key Players: Partnerships BC (procurement manager and project development ); ISL Health—Health Care Projects Canada, Stuart Olson/Acciona Infrastructures Canada, Cannon Design Architecture, Innisfree and Acciona S.A., Angus Consulting Management Western (design-build-finance-maintain)

Stuart Olson/Acciona Infrastructures Canada is the design-build contractor, Cannon Design Architecture designed the facility, and Angus Consulting Management Western will be responsible for facilities maintenance.

85 Centre for Addiction and Mental Health Phase 1B$293 million

2010 Ranking: NEW

Location: Toronto, Ontario

Owner: Centre for Addiction and Mental Health

Key Players: Infrastructure Ontario (procurement manager and project development ); Carillion Health Services team—Carillion’s Construction and Facility Management Divisions, Stantec Architecture, and Scotia Capital (design­build-finance-maintain); KPMB Architects, Montgomery Sisam Architects and Kearns Mancini Architects (master planning, design compliance architects)

Funding: P3 (DBFM)

Status: Under construction with expected completion in 2012.

Phase 1B of the CAMH redevelopment will see the construction of three new buildings: the CAMH Gateway Building, the Intergenerational Wellness Centre, and the Utilities and Parking Building.This project is the first phase of CAMH’s 10-year, three-phase redevelopment plan for its Queen Street site in Toronto.

LEED Target: Gold

Cred

it: Stantec

top100projects.ca ReNew Canada 55

Page 48: Company Index Top 100 Badge Programme

Key Players: ENTRA Consultants, a subsidiary of GENIVAR (master plan); Graham Bros. Construction (road construction); ACS Transport Solutions (ITS components); McCormick Rankin Corporation, a member of MMM Group (engineering); Enseicom (station stops); Moffet & Duncan Architects (terminal design); New Flyer Industries (supplier: hybrid diesel-electric vehicles)

Funding: Public

Status: Under construction with expected completion in 2012.

Cred

it: City of B

ramp

ton

Züm (formerly known as Brampton Acceleride) will be launched over a three-year period. Phase one of Züm begins with the opening of the Queen Street line (Downtown Brampton to York University) in September 2010. The Main Street line (Sandalwood Parkway to Mississauga City Centre) follows in fall 2011, and the Steeles Avenue line (Shoppers World to Humber College) will complete phase one of the BRT implementation in fall 2012. Phase one also includes significant redesigns and/ or relocations of three of Brampton’s key transit terminals. Both the Bramalea Transit Terminal and the Shoppers World Transit Terminal will be relocated and redesigned for increased capacity. The Downtown Transit Terminal will also undergo an upgrade.

Züm—Brampton BRT $285 million 87

2010 Ranking: 60

Location: Brampton, Ontario

Owner: City of Brampton

Key Players: Graham Group and Flatiron Constructors Canada in a joint venture (design-build contractor); AECOM (design subcontractors to Graham-Flatiron JV); Wardrop, a Tetra Tech company (main design subcontractors to AECOM); Delcan (independent design review); Stantec (public consultation, environmental screening, traffic analysis and roadway); Golder Associates (geotechnical and material testing services)

86

Funding: Public

Status: Under construction, with expected completion in 2012.

Work includes construction of a new six-lane bridge over the South Saskatchewan River. The roadway will include provisions for pedestrians and cyclists to cross and have access to various recreational trails on both sides of the river.

2010 Ranking: NEW

Location: Saskatoon, Saskatchewan

Owner: City of Saskatoon

Cred

it: AE

CO

M

Circle Drive is the province’s first alternative delivery design-build transportation contract, and the single largest project in the city’s history.

56 ReNew Canada

Top 100 Projects

2011

Circle drive South Project $288 million

top100projects.ca

Page 49: Company Index Top 100 Badge Programme
Page 50: Company Index Top 100 Badge Programme

Top 100 Projects 2011

West Toronto diamond/Rail grade Separation Project88 $277 million

Key Players: McCormick Rankin Corporation, a member of the MMM Group (construction management, contract administration); AGM Program Managers –Hatch Mott MacDonald, Giffels, a part of the Ingenium Group and MMM Group in a joint venture (program managers); Delcan (track alignment design, contract drawings, drainage analysis, regulatory analysis); Golder Associates (subconsultant to Delcan for geo-technical design, vibration monitoring; noise monitoring for Metrolinx); CN Rail (construction manager—advance piling, supplier: material for advance piling contract)

Funding: Public

89 greenwich Wind Farm $275 million

Key Players: RES Canada (developer, site clearing); Siemens (supplier: turbines)

Funding: Private

Status: Under construction, with expected completion in late 2011.

2010 Ranking: 61 Location: Toronto, Ontario

Owner: Metrolinx/GO Transit

Status: Under construction, with expected completion in 2014.

This project will improve commuter service reliability, eliminate at-grade conflicts with freight rail traffic, and support overall improvements to service on the GO Transit Georgetown/Weston rail corridor through the construction of a new rail-rail grade separation. Interlocking steel pipe piles are being used to form the outer walls of the depressed corridor. The main contract involves the construction of several precast, prestressed, rail carrying bridges that will be erected by lateral sliding during rail track blocks.

2010 Ranking: NEW Location: Dorion, Ontario

Owner: Enbridge, in partnership with Renewable Energy Systems Canada

The 100 MW wind farm will be connected to high-voltage transmission circuits located approximately 15 km away from the centre of the project site. A 34.5 kV connection system will be installed to connect the wind turbines to the substation, and a 34.5/230 kV substation will be built to step-up the generation to 230 kV for connection to Hydro One’s 230 kV circuits to feed into the Ontario electricity market.

90 Riel Converter Station 2010 Ranking: NEW

$267 million Location: Rosser, Manitoba Owner: Manitoba Hydro

The station will serve as a backup for the Dorsey Converter Station, located west of Key Players: PCL the city near Rosser. It will also serve as the converter station for the new $2.2-billion (general contractor) Bipole III transmission line that Manitoba Hydro hopes to begin building in the fall

Funding: Public of 2012 and to have in service by mid-2017. Manitoba Hydro needs a backup station in case there’s a power disruption at the Dorsey Station, which converts power that’s

Status: Under construction, transmitted from northern Manitoba over the Bipole I and II transmission lines to A/C with expected completion in 2014. from D/C, and then sends it out to Winnipeg, southern Manitoba and Minnesota.

ToP 10 P3 PRoJECTS CHUM (Université de Montréal hospital centre) Redevelopment $2,500,000,000 QC Health Care

Windsor-Essex Parkway Project

Autoroute 30

$1,600,000,000

$1,500,000,000

ON

QC

Transportation

Transportation 26 Edmonton Ring Road, Anthony Henday Drive NW $1,420,000,000 AB Transportation P3 projects Evergreen Line Rapid Transit Line $1,400,000,000 BC Transportation

McGill University Health Centre at Glen Campus

RCMP E Division Headquarter Relocation Project

$1,340,000,000

$966,000,000

QC

BC

Health Care

Public Building

A total investment of

The Waneta Expansion $900,000,000 BC Energy $20,032,800,000 Southeast Stoney Trail Project $769,000,000 AB Transportation

Niagara Health System Health Care Complex $759,000,000 ON Health Care

58 ReNew Canada top100projects.ca

Page 51: Company Index Top 100 Badge Programme
Page 52: Company Index Top 100 Badge Programme

2010 Ranking: 71

Location: Winnipeg, Manitoba

Owner: Province of Manitoba

Key Players: Phase 1: Grade separation for Canada Way— MMM Group (functional planning study, procurement of a design-build contractor, construction oversight); SNC Lavalin (design-build contractor); TBT Engineering (consulting engineer)

Funding: Public

Status: Construction began in spring 2010, with expected completion in 2014.

CentrePort Canada Highways $262.5 million

91

Cred

it: Centrep

ort C

redit: IS

L Engineering

CentrePort Canada is a transportation, logistics, manufacturing and distribution hub. The most significant project of the three is CentrePort Canada Way (CCW), a $212.5-million, 10 km, high-speed expressway that will run through the inland port connecting it to the province’s major trading corridors. The remaining two projects are $26 million for reconstruction of the Trans-Canada Highway just outside of Winnipeg (Manitoba’s major east-west link) and $24 million for improvements to Highway 75, the Mid-Continent Trade and Transportation Corridor (Manitoba’s major north-south connection)

Status: Under construction, with expected completion in 2011.

The interchange at 23rd Avenue and Calgary Trail/Gateway Boulevard involves building a split-diamond interchange, taking 23rd Avenue over Calgary Trail, Gateway Boulevard and the railway and building an overpass taking 19th Avenue over Calgary Trail and Gateway Boulevard.

2010 Ranking: 64

Location: Edmonton, Alberta

Owner: City of Edmonton Key Players: Kiewit (general contractor); ISL Engineering and Land Services (concept plan review, preliminary and detailed design, construction monitoring, contract administration, and public and stakeholder consultation and communication)

Funding: Public

23rd Avenue Interchange $260 million 92

60 ReNew Canada

Top 100 Projects

top100projects.ca

Page 53: Company Index Top 100 Badge Programme

Cred

it: Diam

ond &

Schm

itt C

redit: E

llisDon

Funding: P3 (Build-Finance)

Status: Under construction, with expected completion in 2012.

The redevelopment consists of about 425,000 square feet of new construction and more than 35,000 square feet of renovations.

2010 Ranking: 66

Location: Hamilton, Ontario

Owner: Hamilton Health Services

Key Players: Infrastructure Ontario (procurement manager and project development ); EllisDon (general contractor); Zeidler Partnership Architects in partnership with Garwood-Jones & Hanham (architects); PRISM Partners (project management); Equipment Planning Associates, Group Eight Engineering, a Trow Global company (mechanical and electrical)

Henderson general Hospital Redevelopment— Juravinski Hospital and Cancer Centre $259 million

94

Status: Under construction, with expected completion in 2011.

This acoustic concert hall is designed in such a way that passersby can see theatregoers from outside. The goal is to cultivate a new audience by allowing pedestrians to see into the theatre.

Key Players: Aedifica/Diamond+Schmitt Architects (architect); SNC-Lavalin (structural, mechanical and electrical engineering, design-builder); Fisher Dachs & Associates (theatre consultants)

Funding: P3 (DBFOM)

2010 Ranking: 65

Location: Montreal, Quebec

Owner: Groupe immobilier Ovation (until 2038)

Montreal Symphony orchestra Concert Hall $259 million

93

ReNew Canada 61top100projects.ca

2011

Page 54: Company Index Top 100 Badge Programme

Port Mann Main Water Supply Tunnel—Fraser River Crossing $240 million

2010 Ranking: NEW

Location: Vancouver, British Columbia

Owner: Metro Vancouver

97

Key Players: Hatch Mott MacDonald (project manager); Ausenco Sandwell with Jacobs Associates (engineer); Golder Associates (geotechnical investigation and design services as a subconsultant to Ausenco, EA and permitting)

Funding: Public

Status: Design has been completed; a contractor is being selected in late 2010, with expected completion in 2014.

Metro Vancouver delivers water to 21 Lower Mainland municipalities, which in turn deliver water to more than two million people. The water is collected from three mountainous watersheds—Capilano, Seymour and Coquitlam—by an extensive system of 22 reservoirs, 15 pumping stations and over 500 km of supply mains. The new Port Mann Main Water Supply Tunnel under the Fraser River will convey drinking water from the Coquitlam watershed to municipalities south of the Fraser River. The new crossing will replace the existing crossing which rests on the river bottom and is vulnerable to river scour and seismic-induced damage. The new crossing has been sized to accommodate future growth in the region and has been designed to remain functional following a seismic event with an annual probability of occurrence of one in 10,000 years.

Key Players: B2L Partnership— Gracorp Capital Advisors, HOCHTIEF PPP Solutions North America and Connor, Clark & Lunn GVest Traditional Infrastructure, Graham Group, Bird Construction, GEC Architecture, Gibbs Gage Architects and Honeywell (design-build-finance-maintain); Golder Associates (preliminary geotechnical investigations)

Funding: P3 (DBFM)

Status: Under construction, with expected completion in 2012.

2010 Ranking: NEW

Location: Calgary and Edmonton Capital regions

Owner: Government of Alberta

Alberta Schools Alternative Procurement (ASAP) Phase 2 $253 million

95

2010 Ranking: 55

Location: Edmonton, Alberta

Owner: The Governors of the University of Alberta

Key Players: PCL (construction manager); HOK with Stantec (architect); Stantec (subconsultant— electrical engineering design, program and project management)

Funding: Public

Status: Under construction, with expected completion in 2011.

Edmonton Clinic north at university of Alberta $250 million

96

Cred

it: Stantec

This new building compliments the Edmonton South Clinic (number 81 on this year’s list). The cost was listed as $303 million on last year’s Top 100, but it’s been adjusted to reflect a more up-to-date estimate.

Phase 1 of the project saw 18 new schools completed in the autumn of 2010 under a full P3 contract. Phase 2 of the project, however, will be built using a combined procurement approach. Ten new elementary and middle schools and will be built during Phase two under a P3 contract for $253 million. The design-build of four high schools in Edmonton, Calgary, Spruce Grove and Sherwood Park are also part of Phase 2, but will be financed publicly by the Government of Alberta. Clark Builders has a roughly $96.8-million design-build contract for the high schools which will be built by January 2013.

LEED Target: Silver

62 ReNew Canada

Top 100 Projects

2011

top100projects.ca

Page 55: Company Index Top 100 Badge Programme
Page 56: Company Index Top 100 Badge Programme

98

Top 100 Projects 2011

Cred

it: Bird

Construction C

omp

any

Surrey outpatient Hospital $239.1 million

99 union Station Train Shed Revitalization Project $228 million

Key Players: Aecon (refurbishment of tracks and platforms, installation of new steel roof and glass atrium ); Halcrow Yolles, part of Halcrow Group (design consultant); Zeidler Partnership Architects (architectural sub-consultant); Read Jones Christoffersen (contract administration); Parks Canada (heritage preservation); Morrison Hershfield (construction administration—roof maintenance program); Delcan (concept, RFP design and construction tender management)

Funding: Public

2010 Ranking: 85

Location: Surrey, British Columbia

Owner: Fraser Health Authority

Key Players: Partnerships BC (procurement manager and project development ); BCHS Healthcare (Surrey) Limited Partnership— Bird Construction, Bouygues , HSBC Infrastructure, ETDE Facility Management Canada, Helios Group (design-build-finance­maintain); Kasian Architecture (architect)

Funding: P3 (DBFM)

Status: Under construction, expected completion in 2011.

The new building will provide centralized outpatient services, which means faster diagnosis, improved access and reduced wait times, and better health management and recovery. Bird Construction and Bouygues are acting as design-build contractor on the project. As part of the same consortium, ETDE Facility Management Canada and Helios Group will be responsible for facilities maintenance.

LEED Target: Gold

2010 Ranking: NEW

Location: Toronto, Ontario

Owner: Metrolinx,/GO Transit

Status: Under construction, with expected completion in 2015.

The existing train shed at Canada’s busiest transportation hub was built in the 1920s and is a designated heritage structure. The shed roof will be completely rebuilt, and the north section will be restored to the original finish, while the rest of the structure will feature a new 6,000 square foot glass atrium rising 50 feet above platform level at the centre of the roof. The east and west portions of the remaining roof will be restored and fitted with a combination of a green roof and solar panels.

dorval Interchange Redevelopment Project$224 million

Key Players: Ministère des Transports du Québec (contractor); CIMA+ (environmental impact study, construction site supervision)

Funding: Public

Status: Under construction, with expected completion in 2013.

2010 Ranking: 69

Location: Montreal, Quebec

Owner: Ministère des Transports du Québec

A project that’s been in the works for 15 years, redevelopment work on the interchange is finally being done in five phases. The Dorval Interchange includes the infamously confusing Dorval Circle and the interchange of autoroutes 20 and 520, which currently causes constant congestion.

64 ReNew Canada top100projects.ca

100

Page 57: Company Index Top 100 Badge Programme
Page 58: Company Index Top 100 Badge Programme

Company Index Top 100 Badge Programme

68 3M Canada 3m.com/ca

67 AECOM aecom.com

63 Bennett Jones bennettjones.com

29 Borden Ladner Gervais (BLG) blg.com

41 CanWEA canwea.ca

27 CH2M HILL ch2m.com

51 Davis davis.ca

53 Delcan delcan.com

33 EllisDon ellisdon.com

57 Fasken Martineau fasken.com

19 Flatiron Constructors Canada flatironcorp.com

25 Gowlings gowlings.com

13 Hatch Mott MacDonald hatchmott.com

43 MMM Group www.mmm.ca

2 PCL pcl.com

4 Scotia Capital scotiacapital.com

9 SNC-Lavalin www.snclavalin.com

6 Sodexo sodexo.com

35 Stuart Olson Dominion Construction stuartolson.com

47 Thales Canada thalesgroup.com

65 United Rentals ur.com

16 URS Canada urs.ca

59 WeirFoulds weirfoulds.com

The Top 100 Badge programme was created to give

companies engaged in the biggest Canadian infrastructure

projects a way to celebrate their accomplishments.

Badges are sent to companies involved as key players on

multiple infrastructure projects on the Top 100 list. Companies

use these icons to identify themselves as top key players.

PLATINUM 2011

GOLD 2011

SI LVER 2011

BRONZE 2011

10 projects 6 to 9 3 to 5 2 projects or more projects projects

Visit top100projects.ca for a company index and list of badge recipients.

Coming in Spring 2011: Top 100 white paper • expanded project listings

• expanded key players listings (including lawyers and financiers)

• stats about economic impact and job creation

top100projects.ca

Submit projects for our 2012 list

update existing projects

View unique video and news content

Locate projects using our interactive map

For further details, contact [email protected]

66 ReNew Canada top100projects.ca

Page 59: Company Index Top 100 Badge Programme
Page 60: Company Index Top 100 Badge Programme