    LARSEN & TOUBRO LIMITED

    MANAMADURAI - TIRUCHULI - VIRUDHUNAGAR RC PROJECT

    ACTION PLAN FOR COMPLETING BALANCE WORKS

    As on : 17.04.13

    Sl. No. Description of workWork

    GroupName of the S/c

    Target

    Completion

    Site

    EngineerRemarks

    APK Station

    1 Septic Tank Work PF Mintu pal 25.04.13 Manikantan Work in progress

    2 White washing of Toilet PF Ravi 20.04.13 Manikantan

    3 Window fixing for Off duty room PF Dept 25.04.13 Manikantan

    4 Tap fixing for toilet , inside toilet of station Building PF Mintu pal 20.04.13 Manikantan

    5 Patch Tiles work for all rooms PF Dept 18.04.13 Manikantan

    6 Duct slab finishing and pointing inside Station Building PF Mintu pal 30.04.13 ManikantanPVC or rubber sheet to be

    ordered

    7 Ticket counter window work at booking office PF Dept 25.04.13 Manikantan To be enquired

    8 Door for public toilet PF Dept 20.04.13 Manikantan Awaiting approval

    9 Roof tiles for public toilet PF Mintu pal Completed Manikantan

    10 Broken glass refixing for windows PF Dept 25.04.13 Manikantan

    11 Glass fixing for ventilator PF Dept 25.04.13 Manikantan

    12 Hand rails for waiting hall ramp & toilet ramp PF Syed 30.04.13 Manikantan

    13 Tap fixing for water cubicle PF Dept Manikantan Before CRS14 Tiles broken by local people to be replaced in water cubicle PF Mintu pal Manikantan Before CRS

    15Balance slab for cable duct in PF. No.2 to be casted and all slabs to be

    pointedPF Ghosh 20.04.13 Manikantan

    16 Finishing of flooring in Equipment room PF Mintu pal 20.04.13 Manikantan

    17 Finishing of steps in battery room PF Mintu pal 20.04.13 Manikantan

    18 Painting of relay room and equipment room PF Ravi 20.04.13 Manikantan

    19 Dressing of platform PF Dept 30.04.13 Manikantan

    20 Soil filling for ramp at VPT end PF Dept 15.04.13 Manikantan

    Page 1 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    2/21

    Sl. No. Description of workWork

    GroupName of the S/c

    Target

    Completion

    Site

    EngineerRemarks

    NKK Station

    1 Septic tank connection works PF Ghosh 30.04.13 Manikantan

    2 Plumbing works inside public toilet(Fitting & fixing) PF Ghosh 18.04.13 Manikantan

    3 Rain water down pipe from building top to be provided PF Ghosh 25.04.13 Manikantan

    4 Chamber towards VPT end of building for collecting rain water PF Ghosh 25.04.13 Manikantan

    5 Indian closet in off duty room toilet to be replaced PF Ghosh 20.04.13 Manikantan During CRS

    6 New physically challenged toilet to be constructed PF ManikantanNew proposal given on

    10.04.13

    7 Broken glass for windows to be replaced PF Ghosh 20.04.13 Manikantan

    8 Glass fixing for ventilator PF Ghosh 20.04.14 Manikantan

    9 Door for ticket store room PF Ghosh 25.04.13 Manikantan

    10 Finishing of slab broken for electrical works in booking office room PF Ghosh 30.04.13 Manikantan

    11 Plastering for CC Blocks steps infront of new station bulding PF Ghosh 25.04.13 Manikantan

    12 Flooring in rear side and VPT side of toilet PF 30.04.13 Manikantan

    13 Pale fencing fixing surrounding toilet in ground floor PF Gopi Manikantan To be discussed with clients

    14 Roof shelter provision between new and old station building PF Syed 20.04.13 Manikantan

    15 Ticket counter window work at booking office PF Dept 30.04.13 Manikantan

    16 Tap fixing for water cubicle PF Dept Manikantan During CRS

    17 Paving for water cubicle PF Murugaya 30.04.13 Manikantan18 Pointing of precast slab in PF. No.2 cable duct PF M.Krisnan 25.04.13 Manikantan Item to be confirmed

    19 Painting of relay room and equipment room PF Ravi 25.04.13 Manikantan

    20 Finishing of flooring in rooms broken for S&T and electrical works PF Ghosh 20.04.13 Manikantan

    21 Pointing & finishing of precast slab for cable duct inside station building PF Murugaya 25.04.13 Manikantan

    Page 2 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    3/21

    Sl. No. Description of workWork

    GroupName of the S/c

    Target

    Completion

    Site

    EngineerRemarks

    TIRUCHULI

    Septic Tank Work Building Mintu pal 20.04.13 Damodharan Work in progress

    White washing of Toilet Building Ravi 22.04.13 Damodharan

    Facia board fixing PF syed 18.04.13 Damodharan

    Tap fixing for toilet , inside toilet of station Building Building Mintu pal 20.04.13 Damodharan

    Patch Tiles work for all rooms Building Mintu pal 20.04.13 Damodharan

    Duct slab finishing and pointing inside Station Building Building Mintu pal Damodharan Before CRS

    Ticket counter window work at booking office Building Dept 30.04.13 Damodharan

    Door for public toilet Building RAJA 19.04.13 Damodharan

    Roof tiles for public toilet Building Mintu pal 18.04.13 Damodharan

    Broken glass refixing for windows Building Mintu pal 20.04.13 Damodharan

    Glass fixing for ventilator Building Mintu pal 20.04.13 Damodharan

    Hand rails for toilet ramp Building Syed 22.04.13 Damodharan

    Tap fixing for water cubicle PF Mintu pal Damodharan Before CRS

    Facia board fixing PF Syed 20.04.13 Damodharan

    Balance slab for cable duct in PF. No.2 to be cast and all slabs to be pointed PF Mintupal 22.04.13 Damodharan WIP

    Dressing of platform PF Mintupal 20.04.13 Damodharan WIP

    Soil filling for ramp at VPT end PF Mintupal 20.04.13 Damodharan

    Pale fencing casting PF Gopi 20.04.13 Damodharan Post - 250/250;Walling- 200/250

    Pale fencing erection PF Gopi 30.04.13 Damodharan To commence by 15.04.13

    Page 3 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    4/21

    LARSEN & TOUBRO LIMITED

    TIRUCHULI - VIRUDHUNAGAR RC PROJECT

    ACTION PLAN FOR COMPLETING BALANCE WORKS

    As on : 17.04.13

    SI

    No.Description Qty Start Date End Date

    Name of the

    S/c

    Site

    Engg.REMARKS

    VIRUDHUNAGAR YARD

    1Fixing of coping slab for

    PF no.: 2,3 & 5Muthupandi Alwin

    PF no: 5 after wall

    clearance by client side

    2

    Construction of PF wall

    in the portion of exg.

    Trolly path

    12.04.13 20.04.13 Muthupandi AlwinPF no: 5 after wall

    clearence by client side

    PCC 6.75 Muthupandi Alwin

    CC wall 21.6 Muthupandi Alwin

    Carballing 1.69 Muthupandi Alwin

    Fixing 120 Muthupandi Alwin

    3

    Attending PF wall &

    coping so as to be keep

    distance of 1.67m to

    1.68m from c/l of track

    to face of coping and

    .76m to .84m from top

    of rail level to coping

    Muthupandi Alwin

    Balance 40m alignment

    detail to be given by

    clients

    4

    Tiling work for the

    proposed toilet @ vpt

    and drainage

    connection

    Muthupandi Alwin

    Tiling work completed,

    drainage connection not

    in our scope

    5Water cubical &

    benches

    5 Nos.

    Each17.04.13 24.04.13 Mintupaul Alwin

    Since width of platform is

    less on Tvnli end , we can

    construct only 2nos

    immediately balance will

    be done after completing

    FOB foundation works

    6Pale fencing left out in

    the proposed PF no:535 Mtr 18.04.13 23.04.13 Gopi Alwin

    7 Colour washing of palefencing

    20.04.13 Gopi Alwin Work in progress

    8Colour washing of toilet

    building23.04.13 25.04.13 Ravi Alwin

    9Toilet building, pvc

    door fixing1 No 18.04.13 19.04.13 Raja Alwin

    10 Roof tiles fixing 23.04.13 26.04.13 Mintupaul Alwin

    11 Water tap fixing 12.04.13 14.04.13 Mintupaul Alwin Completed

    Page 4 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    5/21

    SI

    No.Description Qty Start Date End Date

    Name of the

    S/c

    Site

    Engg.REMARKS

    12Physically challenged

    portion18.04.13 Mintupaul Alwin Work in progress

    13Name board in the PF

    no:52 Nos. 18.04.13 25.04.13 Kuppan Alwin

    14Connection of leach pit

    in lc gate2 Nos. 23.04.13 24.04.13 Murugaiya Alwin Perali, Villipathiry

    15 LC gate toilet room 2 Nos. 23.04.13 26.04.13 Department AlwinNagampatti,

    Thottiyankulam

    Gate lodge building

    1

    Sanitary connection

    and construction of

    leach pit

    4 Nos. 18.04.13 22.04.13 Murugaiya Alwin Leach Pit Completed

    2Paving from gate lodge

    to road4 Nos. 23.04.13 03.05.13 Murugaiya Alwin

    3Colour washing of

    fencing2 Nos. 18.04.13 19.04.13 Gopi Alwin

    Irrunchirai , Narikudi

    balance

    4

    Level crossing - filling

    the surroundings with

    Earth b/w pale fencing

    and gate lodgee

    2 Nos.

    100cum

    each

    18.04.13 22.04.13 Dept AlwinKeelapasali,

    Chinnakannanur.

    5 New toilet room 1 No. 13.04.13 23.04.13 Murugaiya Alwin Irrunchirai

    Page 5 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    6/21

    LARSEN & TOUBRO LIMITED

    MANAMADURAI - TIRUCHULI RC PROJECT

    ACTION PLAN FOR COMPLETING BALANCE WORKS - VENT WAY CLEARANCE

    Date : 17.04.13

    Sl. No. Br. No. Location Span Barrel length Width Depth Total (Cum) Completion date

    1 199 55613-14 1 x2x 3 RCB 8.000 2 0.30 4.80 Completed

    2 200 556/14-15 1x1.2x1.2 RCB

    3 201 556/16-17 1x1.2x1.2 RCB

    4 202 557/2-3 1x1.2x1.2 RCB 7.650 1.2 0.40 3.67 Completed

    5 203 557/5-6 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 Completed

    6 204 557/6-7 1x6x2.3 RCB 6.850 6 0.37 15.07 Completed

    7 205 557/9-10 1x1.2x1.2 RCB 7.650 1.2 0.23 2.14 Completed

    8 206 557/10-11 1x1.2x1.2 RCB 7.650 1.2 0.33 3.06 Completed

    9 207 559/3-4 1x6x3.1 RCB 6.850 6 0.40 16.44 Completed

    10 208 559/6-7 1x6x2.4 RCB 6.850 6 0.50 20.55 Completed

    11 209 559/8-9 1x4x2.5 RCB 6.850 4 0.57 15.53 Completed

    12 210 559/9-10 1x1.2x1.2 RCB 7.650 1.2 0.30 2.75 Completed

    13 211 559/11-12 1x1.2x1.2 RCB 7.650 1.2 0.40 3.67 Completed

    14 212 559/14-15 1x1.2x1.2 RCB 7.650 1.2 0.57 5.20 Completed

    15 212A 559/16-17 1x1.2x1.2 RCB 7.650 1.2 0.10 0.92 Completed

    16 213 559/16-560/1 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 Completed

    17 214 560/4-5 1x1.2x1.2 RCB 10.710 1.2 0.53 6.85 Completed

    18 215 560/5-6 1x1.2x1.2 RCB 9.180 1.2 0.40 4.41 Completed

    19 216 560/10-11 1x1.2x1.2 RCB 7.650 1.2 0.53 4.90 17.04.13

    20 217 561/1-2 1x4.5x3 RCB 6.850 4.5 0.77 23.63 18.04.13

    21 218 561/3-4 6x12.2 PSC 16.04.13

    22 219 561/5-6

    23 220 561/11-12 1x1.2x1.2 RCB 9.180 1.2 0.47 5.14 20.04.13

    24 221 562/1-2 1x4x2.4 RCB 6.850 4 0.47 12.79 21.04.13

    25 222 562/3-4 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 22.04.13

    26 223 562/6-7 1x1.2x1.2 RCB 7.650 1.2 0.27 2.45 22.04.13

    27 224 562/8-9 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 23.04.13

    Constructed in MNM-RMM GC Project

    Major Bridge

    Closed Bridge

    Page 6 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    7/21

    Sl. No. Br. No. Location Span Barrel length Width Depth Total (Cum) Completion date

    28 225 563/7-8 1x6x2.2 RCB 6.850 6 0.50 20.55 Completed

    29 226 563/8-9 1x6x3 RCB 6.850 6 0.67 27.40 Completed

    30 227 563/10-11 1x4x3 RCB 6.850 4 0.50 13.70 Completed

    31 228 564/1-2 2x4x1.7 RCB 7.000 4 0.50 14.00 Completed

    32 229 564/15-565/1 1x1.2x1.2 RCB 7.650 1.2 0.60 5.51 25.04.13

    33 230 565/7-8 1x4x1.6 RCB 6.85 4 0.53 14.61 25.04.13

    34 231 565/8-9 1x4.5x1.8 RCB 6.850 4.5 0.60 18.50 25.04.13

    35 232 565/9-10 1x1.2x1.2 RCB 7.650 1.2 0.27 2.45 25.04.13

    36 233 565/13-14 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 25.04.13

    37 234 566/1-2 1x1.2x1.2 RCB 7.650 1.2 0.47 4.28 27.04.13

    38 235 566/3-4 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 27.04.13

    39 236 566/3-4 1x1.2x1.2 RCB 7.650 1.2 0.60 5.51 27.04.13

    40 237 567/4-5 1x4.5x1.8 RCB 6.850 4.5 0.47 14.39 27.04.13

    41 238 568/1-2 1 x4x 2 RCB 6.850 4 0.40 10.96 27.04.13

    42 239 568/2-3 1x4x2.3 RCB 6.850 4 0.50 13.70 27.04.13

    43 240 568/7-8 4x12.2 PSC Completed

    44 241 568/8-9 1x4.5x2.6 6.850 4.57 0.27 8.35 30.04.13

    45 242 569/3-4 1x1.2x1.2 RCB 9.180 1.2 0.50 5.51 30.04.13

    46 243 569/5-6 1x1.2x1.2 RCB 10.710 1.2 0.20 2.57 30.04.13

    47 244 569/6-7 1x1.2x1.2 RCB 10.710 1.2 0.27 3.43 30.04.13

    48 245 569/7-8 1x2.5x2.6 RCB 6.850 2.5 0.33 5.71 30.04.13

    49 246 569/8-9 1x4.5x4.4 RCB 6.850 4.5 0.40 12.33 02.05.13

    50 247 569/14-15 1x1.2x1.2 RCB 9.180 1.2 0.27 2.94 02.05.13

    51 248 570/14-15 1 x4x 1.9 RCB 6.850 4 0.20 5.48 02.05.13

    52 249 572/3-4 1x1.2x1.2 RCB 7.650 1.2 0.17 1.53 02.05.13

    53 250 572/13-14 1x 6x 3 RCB 6.850 6 0.10 4.11 02.05.13

    54 251 572/14-15 1x6x5.3 RCB 6.850 6 0.37 15.07 05.05.13

    55 252 573/3-5 9x12.2 PSC 20.04.13

    56 252 A 573/5-6

    57 253 573/8-9 1x1.2x1.2 RCB 10.710 1.2 0.23 3.00 Completed

    Major Bridge

    Closed Bridge

    Major Bridge

    Page 7 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    8/21

    Sl. No. Br. No. Location Span Barrel length Width Depth Total (Cum) Completion date

    58 254 573/9-10 1x1.2x1.2 RCB 9.180 1.2 0.10 1.10 Completed

    59 255 573/11-12 1x1.2x1.2 RCB 7.650 1.2 0.17 1.53 Completed

    60 256 573/14-15 1x1.2x1.2 RCB 7.650 1.2 0.17 1.53 Completed

    61 257 574/2-3 1x1.2x1.2 RCB 7.650 1.2 0.38 3.52 03.05.13

    62 258 574/4-5 1x1.2x1.2 RCB 7.650 1.2 0.20 1.84 03.05.13

    63 259 574/5-6 1x6x2.3 RCB 6.850 6 0.27 10.96 10.05.13

    64 260 574/12-13 1x1.2x1.2 RCB 7.650 1.2 0.27 2.45 03.05.13

    65 261 575/5-6 1x4.5x3 RCB 6.850 4.5 0.53 16.44 12.05.13

    66 262 575/15-576/1 1x1.2x1.2 RCB 7.650 1.2 0.27 2.45 13.05.13

    67 263 575/15-576/1

    68 264 576/7-8 1x1.2x1.2 RCB 32.130 1.2 0.20 7.71 13.05.13

    69 265 576/10-11 1x2x2.3 RCB 32.325 2 0.17 10.78 15.05.13

    70 266 577/6-7 1x4.5x3.4 RCB 6.850 4.5 0.17 5.14 13.05.13

    71 267 577/9-10 1x1.2x1.2 RCB 10.710 1.2 0.33 4.28 13.05.13

    72 268 577/12-13 1x1.2x1.2 RCB 9.180 1.2 0.23 2.57 13.05.13

    73 269 577/12-13 1x2.5x2.8 RCB 6.850 2.5 0.30 5.14 15.05.13

    74 270 577/14-15 2x4x2.1 RCB 6.850 4 0.17 4.57 15.05.13

    75 271 577/16-578/1 1x2x1.2 RCB 6.850 2 0.50 6.85 Completed

    76 272 579/7-8 1x3x1.2 RCB 6.850 3 0.40 8.22 Completed

    77 273 580/3-4 1x4.5x1.4 RCB 6.850 4.5 0.37 11.30 17.05.13

    78 274 580/13-14 1x1.2x1.2 RCB 7.650 1.2 0.20 1.84 17.05.13

    79 275 581/2-3 1x1.2x1.2 RCB 7.650 1.2 0.43 3.98 17.05.13

    80 276 581/5-6 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 17.05.13

    81 277 581/7-8 1x1.2x1.2 RCB 7.650 1.2 0.43 3.98 17.05.13

    82 278 581/13-14 1x1.2x1.2 RCB 7.650 1.2 0.47 4.28 17.05.13

    83 279 581/15-582/1 1x4.5x1.6 RCB 6.850 4.5 0.37 11.30 17.05.13

    84 280 582/8-9 1x1.2x1.2 RCB 7.650 1.2 0.43 3.98 17.05.13

    85 281 582/10-11 1x1.2x1.2 RCB 7.650 1.2 0.40 3.67 17.05.13

    86 282 583/11-12 Completed

    87 283 583/12-13 1x1.2x1.2 RCB 9.180 1.2 0.38 4.22 20.04.13

    Retained

    Closed Bridge

    Page 8 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    9/21

    Sl. No. Br. No. Location Span Barrel length Width Depth Total (Cum) Completion date

    88 284 583/12-13 1x1.2x1.2 RCB 9.180 1.2 0.47 5.14 Completed

    89 285 583/14-15 1x1.2x1.2 RCB 10.710 1.2 0.50 6.43 Completed

    90 286 584/1-2 1x1.2x1.2 RCB 10.710 1.2 0.37 4.71 Completed

    91 287 584/4-5 1x6x2.3 RCB 13.760 6 0.24 19.81 Completed

    92 288 584/7-8 5X12.2 PSC Completed

    93 288A 584/8-9 1x1.2x1.2 RCB 13.000 1.2 0.30 4.68 05.05.13

    94 289 585/5-6 1x1.2x1.2 RCB 9.180 1.2 0.17 1.84 05.05.13

    95 290 585/6-7 1x4.5x3.1 RCB 6.850 4.5 0.43 13.36 07.05.13

    96 291 587/1-2 1x1.2x1.2 RCB 7.650 1.2 0.38 3.52 05.05.13

    97 292 588/5-6 1x4.5x3.7 RCB 6.850 4.5 0.67 20.55 Completed

    98 293 588/7-9 11 x12.2 PSC Completed

    647.33

    Major Bridge

    Total ASSESSMENT QTY

    Major Bridge

    Page 9 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    10/21

    LARSEN & TOUBRO LIMITED

    TIRUCHULI - VIRUDHUNAGAR RC PROJECT

    ACTION PLAN FOR COMPLETING BALANCE WORKS - WEARING COAT

    Date : 17.04.13

    Sl. No. Br. No. Location Wearing Coat (Cum) Completion date

    1 294 589/11-12 9.00 20.04.13

    2 296 590/14-15 33.00 27.04.13

    3 299 591/10-11 3.00 28.04.13

    4 300 591/12-13 1.38 29.04.13

    5 302 592/15-593/1 4.50 30.04.13

    6 308 595/3-4 3.60 2/05,13

    7 313 595/12-13 11.00 03.05.13

    8 329 608/9-10 5.00 04.05.13

    9 330 609/5-6 4.50 06.05.13

    10 331 611/12-13 5.00 07.05.13

    11 333 612/9-10 12.30 10.05.13

    12 338A 613/14-15 6.10 11.05.13

    13 340 613/15-614/1 5.00 12.05.13

    14 348 618/12-13 12.00 13.05.13

    115.38

    Page 10 of 21

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    11/21

    LARSEN & TOUBRO LIMITED

    TIRUCHULI - VIRUDHUNAGAR RC PROJECT

    ACTION PLAN FOR COMPLETING BALANCE WORKS - WEARING COAT

    Date : 17.04.13

    Sl. No. Br. No. Location Wearing Coat (Cum) Completion date

    1 202 557/2-3 1.38 23.04.13

    2 203 557/5-6 1.38 24.04.13

    3 205 557/9-10 1.38 25.04.13

    4 206 557/10-11 1.38 26.04.13

    5 210 559/9-10 1.08 27.04.13

    6 230 565/7-8 6.17 30.04.13

    7 249 572/3-4 1.38 05.05.13

    9 270 577/14-15 8.22 15.05.13

    22.35

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    12/21

    1 199 55613-14 1 x2x 3 RCB 8.000 2 0.30

    2 200 556/14-15 1x1.2x1.2 RCB

    3 201 556/16-17 1x1.2x1.2 RCB

    4 202 557/2-3 1x1.2x1.2 RCB 7.650 1.2 0.40

    5 203 557/5-6 1x1.2x1.2 RCB 7.650 1.2 0.50

    6 204 557/6-7 1x6x2.3 RCB 6.850 6 0.37

    7 205 557/9-10 1x1.2x1.2 RCB 7.650 1.2 0.23

    8 206 557/10-11 1x1.2x1.2 RCB 7.650 1.2 0.33

    9 207 559/3-4 1x6x3.1 RCB 6.850 6 0.40

    10 208 559/6-7 1x6x2.4 RCB 6.850 6 0.50

    11 209 559/8-9 1x4x2.5 RCB 6.850 4 0.57

    12 210 559/9-10 1x1.2x1.2 RCB 7.650 1.2 0.30

    13 211 559/11-12 1x1.2x1.2 RCB 7.650 1.2 0.40

    14 212 559/14-15 1x1.2x1.2 RCB 7.650 1.2 0.57

    15 212A 559/16-17 1x1.2x1.2 RCB 7.650 1.2 0.10

    16 213 559/16-560/1 1x1.2x1.2 RCB 7.650 1.2 0.50

    17 214 560/4-5 1x1.2x1.2 RCB 10.710 1.2 0.53

    18 215 560/5-6 1x1.2x1.2 RCB 9.180 1.2 0.40

    19 216 560/10-11 1x1.2x1.2 RCB 7.650 1.2 0.53

    20 217 561/1-2 1x4.5x3 RCB 6.850 4.5 0.50

    21 218 561/3-4 6x12.2 PSC

    22 219 561/5-6

    23 220 561/11-12 1x1.2x1.2 RCB 9.180 1.2 0.47

    REACH-I MANAMADURAI-THIRUCHCHULI VENT

    Sl. No. BR.No LOCATION PROPOSED SPAN BARREL WRIDTH DEPTH

    Major Bridge

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    13/21

    24 221 562/1-2 1x4x2.4 RCB 6.850 4 0.47

    25 222 562/3-4 1x1.2x1.2 RCB 7.650 1.2 0.50

    26 223 562/6-7 1x1.2x1.2 RCB 7.650 1.2 0.27

    27 224 562/8-9 1x1.2x1.2 RCB 7.650 1.2 0.50

    28 225 563/7-8 1x6x2.2 RCB 6.850 6 0.50

    29 226 563/8-9 1x6x3 RCB 6.850 6 0.67

    30 227 563/10-11 1x4x3 RCB 6.850 4 0.50

    31 228 564/1-2 2x4x1.7 RCB 7.000 4 0.50

    32 229 564/15-565/1 1x1.2x1.2 RCB 7.650 1.2 0.60

    33 230 565/7-8 1x4x1.6 RCB 6.85 4 0.53

    34 231 565/8-9 1x4.5x1.8 RCB 6.850 4.5 0.60

    35 232 565/9-10 1x1.2x1.2 RCB 7.650 1.2 0.27

    36 233 565/13-14 1x1.2x1.2 RCB 7.650 1.2 0.50

    37 234 566/1-2 1x1.2x1.2 RCB 7.650 1.2 0.47

    38 235 566/3-4 1x1.2x1.2 RCB 7.650 1.2 0.50

    39 236 566/3-4 1x1.2x1.2 RCB 7.650 1.2 0.60

    40 237 567/4-5 1x4.5x1.8 RCB 6.850 4.5 0.47

    41 238 568/1-2 1 x4x 2 RCB 6.850 4 0.40

    42 239 568/2-3 1x4x2.3 RCB 6.850 4 0.50

    43 240 568/7-8 4x12.2 PSC

    44 241 568/8-9 1x4.5x2.6 6.850 4.57 0.27

    45 242 569/3-4 1x1.2x1.2 RCB 9.180 1.2 0.50

    46 243 569/5-6 1x1.2x1.2 RCB 10.710 1.2 0.20

    47 244 569/6-7 1x1.2x1.2 RCB 10.710 1.2 0.27

    48 245 569/7-8 1x2.5x2.6 RCB 6.850 2.5 0.33

    49 246 569/8-9 1x4.5x4.4 RCB 6.850 4.5 0.40

    50 247 569/14-15 1x1.2x1.2 RCB 9.180 1.2 0.27

    51 248 570/14-15 1 x4x 1.9 RCB 6.850 4 0.20

    Major Bridge

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    14/21

    52 249 572/3-4 1x1.2x1.2 RCB 7.650 1.2 0.17

    53 250 572/13-14 1x 6x 3 RCB 6.850 6 0.10

    54 251 572/14-15 1x6x5.3 RCB 6.850 6 0.37

    55 252 573/3-5 9x12.2 PSC

    56 252 A 573/5-6

    57 253 573/8-9 1x1.2x1.2 RCB 10.710 1.2 0.23

    58 254 573/9-10 1x1.2x1.2 RCB 9.180 1.2 0.10

    59 255 573/11-12 1x1.2x1.2 RCB 7.650 1.2 0.17

    60 256 573/14-15 1x1.2x1.2 RCB 7.650 1.2 0.17

    61 257 574/2-3 1x1.2x1.2 RCB 7.650 1.2 0.38

    62 258 574/4-5 1x1.2x1.2 RCB 7.650 1.2 0.20

    63 259 574/5-6 1x6x2.3 RCB 6.850 6 0.27

    64 260 574/12-13 1x1.2x1.2 RCB 7.650 1.2 0.27

    65 261 575/5-6 1x4.5x3 RCB 6.850 4.5 0.53

    66 262 575/15-576/1 1x1.2x1.2 RCB 7.650 1.2 0.27

    67 263 575/15-576/1

    68 264 576/7-8 1x1.2x1.2 RCB 32.130 1.2 0.20

    69 265 576/10-11 1x2x2.3 RCB 32.325 2 0.17

    70 266 577/6-7 1x4.5x3.4 RCB 6.850 4.5 0.17

    71 267 577/9-10 1x1.2x1.2 RCB 10.710 1.2 0.33

    72 268 577/12-13 1x1.2x1.2 RCB 9.180 1.2 0.23

    73 269 577/12-13 1x2.5x2.8 RCB 6.850 2.5 0.30

    74 270 577/14-15 2x4x2.1 RCB 6.850 4 0.17

    75 271 577/16-578/1 1x2x1.2 RCB 6.850 2 0.50

    76 272 579/7-8 1x3x1.2 RCB 6.850 3 0.40

    77 273 580/3-4 1x4.5x1.4 RCB 6.850 4.5 0.37

    78 274 580/13-14 1x1.2x1.2 RCB 7.650 1.2 0.20

    79 275 581/2-3 1x1.2x1.2 RCB 7.650 1.2 0.43

    Major Bridge

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    15/21

    80 276 581/5-6 1x1.2x1.2 RCB 7.650 1.2 0.50

    81 277 581/7-8 1x1.2x1.2 RCB 7.650 1.2 0.43

    82 278 581/13-14 1x1.2x1.2 RCB 7.650 1.2 0.47

    83 279 581/15-582/1 1x4.5x1.6 RCB 6.850 4.5 0.37

    84 280 582/8-9 1x1.2x1.2 RCB 7.650 1.2 0.43

    85 281 582/10-11 1x1.2x1.2 RCB 7.650 1.2 0.40

    86 282 583/11-12

    87 283 583/12-13 1x1.2x1.2 RCB 9.180 1.2 0.38

    88 284 583/12-13 1x1.2x1.2 RCB 9.180 1.2 0.47

    89 285 583/14-15 1x1.2x1.2 RCB 10.710 1.2 0.50

    90 286 584/1-2 1x1.2x1.2 RCB 10.710 1.2 0.37

    91 287 584/4-5 1x6x2.3 RCB 13.760 6 0.24

    92 288 584/7-8 5X12.2 PSC

    93 288A 584/8-9 1x1.2x1.2 RCB 13.000 1.2 0.30

    94 289 585/5-6 1x1.2x1.2 RCB 9.180 1.2 0.17

    95 290 585/6-7 1x4.5x3.1 RCB 6.850 4.5 0.43

    96 291 587/1-2 1x1.2x1.2 RCB 7.650 1.2 0.38

    97 292 588/5-6 1x4.5x3.7 RCB 6.850 4.5 0.67

    98 293 588/7-9 11 x12.2 PSC

    Total

    Retained

    Major Bridge

    Major Bridge

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    16/21

    Date of

    completion

    Required

    Labours

    JCB hours

    required

    Date of

    completion

    4.80 Completed 6 Completed

    3.67 Completed 4 Completed

    4.59 Completed 5 Completed

    15.07 Completed 7 Completed

    2.14 Completed 3 Completed

    3.06 Completed 5 Completed

    16.44 Completed 6

    20.55 Completed 4

    15.53 Completed 7

    2.75 Completed 4

    3.67 Completed 5

    5.20 Completed 6

    0.92 Completed 4

    4.59 Completed 5

    6.85 Completed 6

    4.41 Completed 5

    4.90 21.04.13 3 4

    15.41 21.04.13 11 7

    5.14 21.04.13 4 6

    AY DETAILS Date-17-04-13

    CUM Status

    Inside vent way

    cleaning

    Outside vent way

    Cleaning

    onstructed in MNM-RMM GC Project

    Pitching

    work was

    executed by

    other

    agency

    Completed

    Closed Bridge

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    17/21

    12.79 20.04.13 9 7

    4.59 20.04.13 3 5

    2.45 19.04.13 2 5

    4.59 19.04.13 3 5

    20.55 Completed 7

    27.40 Completed 7.5

    13.70 Completed 6

    14.00 Completed 7

    5.51 29.04.13 4 5

    14.61 29.04.13 10 7

    18.50 30.04.13 13 7

    2.45 30.04.13 2 5

    4.59 01.05.13 3 5

    4.28 01.05.13 3 5

    4.59 02.05.13 3 5

    5.51 02.05.13 4 6

    14.39 03.05.13 10 6.5

    10.96 03.05.13 8 5.5

    13.70 04.05.13 10 5.5 04.05.13

    8.35 05.05.13 6 5

    5.51 05.05.13 4 6

    2.57 06.05.13 2 7

    3.43 06.05.13 2 8

    5.71 07.05.13 4 6

    12.33 07.05.13 9 6

    2.94 08.05.13 2 6

    5.48 08.05.13 4 6

    Pitching

    work was

    executed by

    other

    agency

    Completed

    Pitchingwork was

    executed by

    other

    agency

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    18/21

    1.53 09.05.13 1 5 09.05.13

    4.11 09.05.13 3 5 09.05.13

    15.07 10.05.13 11 6 10.05.13

    3.00 Completed 5

    1.10 Completed 5

    1.53 Completed 6

    1.53 Completed 5

    3.52 Completed 5

    1.84 Completed 5

    10.96 Completed 6

    2.45 11.05.13 2 4 11.05.13

    16.44 11.05.13 12 7 11.05.13

    2.45 12.05.13 2 5 12.05.13

    7.71 12.05.13 6 6.5 12.05.13

    10.78 12.05.13 8 6 12.05.13

    5.14 13.05.13 4 5 13.05.13

    4.28 13.05.13 3 5 13.05.13

    2.57 13.05.13 2 5 13.05.13

    5.14 14.05.13 4 5 14.05.13

    4.57 14.05.13 3 5 14.05.13

    6.85

    8.22

    11.30 15.03.13 8 6 15.03.13

    1.84 16.05.13 1 6 16.05.13

    3.98 16.05.13 3 5 16.05.13

    Completed

    Closed Bridge

    Closed Bridge

    Completed

    Completed

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    19/21

    4.59 16.05.13 3 5 16.05.13

    3.98 17.05.13 3 5 17.05.13

    4.28 17.05.13 3 5 17.05.13

    11.30 18.05.13 8 6 18.05.13

    3.98 19.05.13 3 6 19.05.13

    3.67 19.05.13 3 5 19.05.13

    4.22 19.05.13 3 0 19.05.13

    5.14

    6.43

    4.71

    19.81

    4.68 20.05.13 3 20.05.13

    1.84 20.05.13 1 20.05.13

    13.36

    3.52 20.05.13 3 20.05.13

    20.55

    634.31 244 416.5

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    20/21

    Date of

    completion

    Required

    Labours

    JCB hours

    required

    Date of

    completion

    1 293 A, RUB 589/3-4

    2 294 589/11-12 1X2.0X1.230 2 0.45 27.00 completed completed 22.04.13

    3 296 590/14-15 2X6.0X2.318.350 12.000 0.300 66.06 26.04.13

    4 297 590/14-15 1X1.2X1.27.680 1.200 0.20 1.84 27.04.13

    5 298 591/5-6 1X1.2X1.29.180 1.200 0.150 1.65 27.04.13

    6 299 591/10-11 1X6.0X2.36.850 6.000 0.200 8.22 28.04.13

    7 300 591/12-13 1X1.2X1.27.650 1.200 0.300 2.75 28.04.13

    8 301 592/2-3 1X4.0X1.8 6.850 4.000 0.250 6.85 29.04.13

    9 302 592/15-593/115.000 2.000 0.300 9.00 30.04.13

    10 303 593/7-8 1X4.5X3.46.850 4.500 0.300 9.25 02.05.13

    11 304 594/2-3 1X1.2X1.29.180 1.200 0.100 1.10 02.05.13

    12 305 15-595/1 1X1.2X1.212.240 1.200 0.200 2.94 03.05.13

    13 306 595/1-2 1X1.2X1.29.180 1.200 0.300 3.30 03.05.13

    14 307 595/2-3 1X1.2X1.26.850 1.200 0.00 Completed

    15 308 595/3-4 1X1.2X1.220.000 1.200 0.300 7.20 04.05.13

    16 309 595/5-6 1X1.2X1.212.240 1.200 0.300 4.41 04.05.13

    17 310 595/8-9 1X1.2X1.220.000 1.200 0.100 2.40 05.05.13

    18 311 595/11-12 1X1.2X1.210.710 1.200 0.300 3.86 05.05.13

    19 312 595/12-13 1X1.2X1.29.180 1.200 0.300 3.30 06.05.13

    20 313 2X4.0X3.36.850 4.000 0.00 Completed

    21 31416.000 2.000 0.350 11.20 07.05.13

    22 315 596/9-1016.000 2.000 0.350 11.20 07.05.13

    23 316 597/1-2 1X1.2X1.2 12.240 1.200 0.350 5.14 08.05.13

    24 317 597/4-5 1X1.2X1.212.240 1.200 0.500 7.34 08.05.13

    25 318 597/6-7 1X1.2X1.212.240 1.200 0.500 7.34 09.05.13

    26 319 598/6-7 1X1.2X1.29.180 1.200 0.300 3.30 09.05.13

    27 320 598/14-15 1X2.5X2.06.850 2.500 0.250 4.28 10.05.13

    28 321 599/7-8 1X1.2X1.27.650 1.200 0.300 2.75 10.05.13

    29 322 600/13-14 1X1.2X1.221.420 1.200 0.350 9.00 11.05.13

    30 324 600/15-16 1X4.0X3.06.850 4.000 0.800 21.92 12.05.13

    31 325 602/14-15 1X4.0X3.06.850 4.000 0.200 5.48 12.05.13

    32 326 604/5-6 1X4.5X2.56.850 4.500 0.850 26.20 13.05.13

    33 327 605/2-3 1X4.5X1.66.850 4.500 0.850 26.20 13.05.13

    34 328 608/1-2 1X1.2X1.27.650 1.200 0.250 2.30 14.05.13

    35 329 608/9-10 1X2.0X2.019.000 2.000 0.250 9.50 14.05.13

    36 330 609/5-6 1X1.2X1.219.000 1.200 0.250 5.70 15.05.13

    37 331 611/12-13 1X1.2X1.219.000 1.200 0.250 5.70 15.05.13

    38 333 612/9-10 2X6.0X3.5 6.850 0.00 Completed

    WRIDTH DEPTH CUMLocation

    Pitching work

    was

    executed by

    other agency

    BARREL

    Inside vent way

    cleaning

    Outside vent way

    Cleaning

    MINOR BRIDGES DETAILS

    REACH - II ( THIRUCHULI - VIRUDHNAGAR )

    AS ON : 17.04.13

    SI. NO BR. NOPROPOSED

    SPAN

  • 7/30/2019 Comp Programme Civil 17.04.12 (R1)

    21/21

    Date of

    completion

    Required

    Labours

    JCB hours

    required

    Date of

    completion

    WRIDTH DEPTH CUMLocation BARREL

    Inside vent way

    cleaning

    Outside vent way

    CleaningSI. NO BR. NOPROPOSED

    SPAN

    39 334 612/13-14 1X1.2X1.27.650 1.200 0.300 2.75 16.05.13

    40 335 613/6-7 1X2.0X1.7518.000 2.000 0.300 10.80 16.05.13

    41 336 613/7-8 1X1.2X1.27.650 1.200 0.350 0.30 17.05.13

    42 337 613/10-11 1X1.2X1.27.650 1.200 0.300 2.75 17.05.13

    43 338 613/13-14 1X1.2X1.27.650 1.200 0.250 2.30 17.05.13

    44 339 613/14-15 1X6.0X2.76.850 6.000 0.00 Completed

    45 340 613/15-614/1 1X1.2X1.219.000 1.200 0.450 10.26 18.05.13

    46 341 614/8-9 1X2.0X1.519.000 2.000 0.450 17.10 18.05.13

    47 342 615/15-616/1 1X4.0X1.3

    6.850 4.000 1.000 27.40 19.05.1348 343 617/5-6 1X1.2X1.2

    6.850 1.200 0.300 2.47 19.05.13

    49 344 618/7-8 1X4.0X1.56.850 4.000 1.000 27.40 20.05.13

    50 345 618/8-9 1X4.0X1.510.000 4.000 1.000 40.00 21.05.13

    51 346 618/10-11 1X1.2X1.210.000 1.200 1.000 12.00 22.05.13

    52 347 618/12-13 1X1.2X1.210.000 1.200 0.100 1.20 22.05.13

    53 348 2X4.0X2.59.000 4.000 1.000 36.00 24.05.13

    518.43

    Pitching work

    wasexecuted by

    other agency