commissioning guidelines, fats and sats
TRANSCRIPT
© Falcon Global Ltd. 2000 - 2019
Learning Objectives 1
After this module, you will have an understanding of
the need for acceptance testing, whether at the
vendor facility in the case of a Factory Acceptance
Test (FAT), or a Site Acceptance Test (SAT) on arrival
at the final destination.
Phase 2 - ImplementationCommissioning Guidelines, FATs and SATs
© Falcon Global Ltd. 2000 - 2019
Phase 2 - ImplementationCommissioning Guidelines
FATs and SATs
Learning Objectives 2
You will also gain an appreciation of the risk-based
approach to determine the selection of equipment
for FAT and SAT.
Additionally, the importance of knowing what
equipment has (or is due to) undergo FAT / SAT will
be emphasized and techniques for mitigating
impact to the project schedule.
© Falcon Global Ltd. 2000 - 2019
Learning Objectives 2
You will also gain an appreciation of the risk-based
approach to determine the selection of equipment
for FAT and SAT.
Additionally, the importance of knowing what
equipment has (or is due to) undergo FAT / SAT will
be emphasized and techniques for mitigating
impact to the project schedule.
Phase 2 - ImplementationCommissioning Guidelines, FATs and SATs
© Falcon Global Ltd. 2000 - 2019
Phase 2 - ImplementationCommissioning Guidelines
As an illustration of the work processes and way in which Zenator
(SCDB) can really streamline and transform the Commissioning &
Handover processes the following guidelines and flow diagrams are
included.
The embedded files contain Commissioning Guidelines and work flow
diagrams from a real project recently completed in Kazakhstan where
Zenator was very successfully deployed.
TIP
These guidelines are a great example of communicating the Systems
Completion with the role of the SCDB in the process to final
Handover in clear language to all Stakeholders.
Use these guidelines and modify to suit your project.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCommissioning Guidelines
Factory Acceptance Testing
FAT
As Commissioning Manager, ensure you know about and your
relevant Commissioning Engineers participate in, all Factory
Acceptance Testing (FATs). It is just as vital to know what is to be
Factory Acceptance Tested as knowing what has not been Factory
Acceptance Tested.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCommissioning Guidelines
Factory Acceptance Testing
FAT
Participating in and witnessing a FAT will give the Commissioning
Engineer invaluable first-hand knowledge of how a specialist item
is intended to operate and be integrated with connecting Systems
and controls. Being present at a FAT, he / she will help:
• Document the tests, checks and procedures
• Record all punch list items (PLIs)
• Review Supplier / Vendor documentation, particularly
Operations & Maintenance Manuals and audit during the FAT
for completeness and accuracy.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCommissioning Guidelines
Factory Acceptance Testing
FAT
Use SCDB from the start of the FAT process to plan, track and
report the entire FAT program.
Deploying Walkdown Capture with Zenator (SCDB) to record and
clear Punch List Items (PLIs) will save significant management
manhours.
If a specialist item, such as major long-lead item, packaged
equipment, module, pre-assembled unit, vendor skid is not to be
Factory Acceptance Tested, find out why. It could be an omission.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCommissioning Guidelines
Factory Acceptance Testing
FAT
If deliberate and not an omission:
• Find out who from the project team is participating in and
witnessing the Quality checks being carried out;
• Ensure you receive documentation for each package or
specialist item that has not had a FAT;
• Put a flag on these items for future reference as these
packages or specialist items could be a source of problems
when they arrive on site.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCommissioning Guidelines
Site Acceptance Testing
SAT
Is usually performed on sensitive and / or high value equipment
that previously had a FAT, on delivery to the site location. The test
should be included in the original Purchase Order and is
particularly important in the case of:
• Situations where the condition of the equipment is likely to be
significantly different to that on completion of the FAT, eg,
transportation over long distances by air, land or sea
• Depending on the equipment and perceived risk, the scope
and reporting of SAT could be more than, similar to or less
than the requirements for FAT.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPreservations
Learning Objective
At the conclusion of this module you will have
learned the fundamental principles of the need for
Preservation and the risks if this importance is not
put into practice.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPreservations
Preservation activities are vitally important, recurring
checks carried out on costly, often sensitive
equipment, to:
1. maintain warranty in accordance with the
vendor’s instructions;
2. avoid risk of contamination or corrosion;
3. maintain workability;
4. maintain a controlled environment.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPreservations
Preservations start from the time of delivery and
recur at regular intervals. Develop a Preservations
program and assign a Preservations Supervisor /
Engineer, ideally from within Operations or
Maintenance to perform the work.
A Preservations program is confined to following
package vendor recommendations.
Remain aware of your environment and any
changing conditions.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPreservations
As part of your Risk Assessment, be aware of where
Commissionable Items are being stored following
delivery, exposed to the elements in an outside
compound, in a warehouse or climate-controlled
environment.
If Commissionable Items are stored on shelves in a
warehouse, Preservations will still be needed.
The Preservations Engineer must be vigilant and
keep a close eye on storage and handling.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPreservations
• May not only be needed until the
Commissionable Items are installed and
Commissioned, but if something changes to
the project and mothballing is needed;
• Are not restricted to high value or sensitive
equipment. Refer to Case Study 1 on page 57.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPreservations
Use the Preservations functionality in SCDB to
control, schedule, manage and report all work
pertaining to these recurring P Checksheets, (aka
PITRs, or P ITRs).
From Reports Plus you can get a complete
Preservations History across the project.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPreservations
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures
Learning Objective
After completing this module, you will have learned
about Cleaning and Drying techniques, evaluate
where these should be deployed and be able to
make a comparison of respective strengths and
weaknesses.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopDay 3
Cleaning and Drying
Procedures
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 1
Next to Preservations, the internal cleanliness and dryness of Systems, specifically
piping and vessels, are the biggest ticket items to affect Commissioning & Start Up,
hence will impact the overall project schedule.
It is too often the case that Construction hand over to Commissioning, piping
Systems with debris and foreign material. These are recurring problems, from
company to company, country to country indicating a cultural problem in
Construction with respect to Quality.
Therefore the advice is beware – treat all piping Systems that are handed over
to Commissioning with a health warning.
Within the Commissioning Team, the designated Mechanical and Commissioning
Engineers will be responsible for tracking and documenting the internal cleanliness
and dryness of Systems with hydraulic tubing, piping and vessels.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 2
Removal of Equipment and Internals to Facilitate Cleaning
To flush and clean pipework and vessel internals it will be necessary to
remove parts that would otherwise cause a blockage or obstruction.
Temporary spools may be inserted. The key, therefore for the
responsible engineer, is to know:
• What these items are
• When the items were removed and by whom
• Where any temporary items were installed
• Where the items were removed from
• Where the items are stored temporarily
• When the items were reinstated and by whom
Mark-ups of Piping Isometrics and P&IDs will be required.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 3
Items commonly removed are:
• Filters, strainers, candles
• Valve internals, particularly non-return (check) valves
• Orifice plates
• Sensitive internals for temperature, pressure, flow from instrumented
valves
• Vessel baffles and internals
Temporary items commonly installed for Commissioning are:
• Blind flanges, skillets, strainers
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 4
Cleaning Methods
Commonly used are:
• Pneumatic blowing
• Steam blowing
• Flushing
• Chemical cleaning
• Mechanical cleaning, pigging
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 5
Pneumatic Blowing
Usually air or nitrogen are introduced from a high energy source to
remove loose items from piping Systems. Disconnect pipework from
vessels, remove all internals that cause blockage or obstruction. Place
temporary isolation valve at exhaust, build internal pressure and release,
removing debris.
Not to be used for cleaning:
• Vessels
• Tube Heat Exchangers
Important considerations:
• Air velocity of a minimum 200 ft/sec (approx 65 m/sec)
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 6
Pneumatic Blowing (continued)
Advantages Disadvantages
Cost
o Use of air is relatively inexpensive
o Easy to setup and operate
o May not require specialist
contractor
Effectiveness
o Useful only for dust, light debris
o Subjective effectiveness
Damage
o Risk to internal items and
pneumatic instrumentation tubing
Safety
o Restrict access, barriers erected
o Containment at exhaust
Link Facility
1 http://www.youtube.com/wa
tch?v=qJqhgIqzQDU
Dry Fork CFPP, WY pneumatic blow
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 7
Steam Blowing
Used on steam piping services to remove scale and loose items.
Disconnect pipework from vessels, remove all internals that cause
blockage or obstruction. Ensure exhaust is sufficiently anchored. Not to
be used for cleaning vessels. Requires careful calculation to determine
the energy and pressure needed to remove mill scale and debris from
the System internal surfaces and volume.
Important considerations:
• Calculated volume, pressure and duration of Steam Blow
• Beware of condensation traps – these will cause water hammer
• Ensure pipework is adequately supported and anchored
• Effect on other nearby operations and work activities
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 8
Steam Blowing -2
Important considerations (continued):
• Effect on other nearby operations and work activities
• Sufficient structural anchoring at exhaust(s) to contain the kinetic
energy
• Personnel protection – lagging of pipework and hearing protection
• Use of silencers
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 9
Steam Blowing - 3
Advantages Disadvantages
Effectiveness
o Good at removing mill scale and
debris
Effectiveness
o Subjective effectiveness
o Use targets, check for pock marks
Damage
o Risk to internal items
Safety
o Restrict access, barriers erected
o Restricts other work in area
o Lag piping for personnel
protection
o Hearing protection
o Achoring of exhaust
o Relief of steam at exhaust
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 10
Steam Blowing - 4
Link Facility
1 http://www.youtube.com/wa
tch?v=wGXmeb956yY
Plum Point CFPP, AR steam blow
2 http://www.youtube.com/wa
tch?v=YUbyTATgFTU
Plum Point CFPP, AR steam blow
3 http://www.youtube.com/wa
tch?v=aYGWjJACzaI
ISCC SPP, Kuraymat, Egypt
4 https://www.youtube.com/w
atch?v=iDcEnSkrBlU
815MW CFPP, Paiton 3, Surabaya,
Indonesia
5 http://www.youtube.com/wa
tch?v=InmhgwIyDN4
Using silencers
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 11
Flushing
Fresh water is introduced to remove loose items from piping Systems.
Disconnect pipework from vessels, remove all internals that cause
blockage or obstruction. Not to be used for cleaning vessels.
Not to be used on services where water could cause internal corrosion
to pipework.
Important considerations:
• Ensure adequate supply of water
• Water velocities should be at least 12 ft/sec(approx. 3.75 m/sec)
• Ensure pipework is adequately supported for the weight of water
• Use of corrosion inhibitor
• Vent high points to prevent pulling a vacuum
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 12
Flushing - 2
Important considerations (continued):
• Ensure adequacy of plant drainage system to cope with volume of
water and expected contaminants
• Fit temporary strainers - agree removal procedure with Operations
Advantages Disadvantages
Effectiveness
o For removal of loose debris
Cost
o Large volumes of water needed
o Temporary strainers to remove
later
Effectiveness
o Subjective effectiveness
Risks
o Corrosion
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 13
Chemical Cleaning (Pickling)
Used on process piping services to remove scale and debris. Disconnect
pipework from vessels, remove all internals that cause blockage or
obstruction. Not to be used for cleaning vessels. Specialist contractor
required. Careful calculation of volume and concentration of chemical
needed to remove mill scale and debris from internal surfaces.
Important considerations:
• Calculated volume and concentration of caustic chemical needed
• Chemical storage and disposal of spent fluid with contaminants
• Ensure pipework is adequately supported
• Ensure adequacy of plant drainage system to cope with volume of
spent chemical and expected contaminants
• Fit temporary strainers - agree removal procedure with Operations
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 14
Chemical Cleaning - 2
Advantages Disadvantages
Effectiveness
o Very effective for removal of scale
o Measurable effectiveness
Cost
o Specialist contractor needed
o Temporary strainers to remove
later
Safety
o Restrict access, barriers required
o Storage and disposal of spent
chemical
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 14
Chemical Cleaning - 2
Link Facility
1 http://www.youtube.com/wa
tch?v=rRSlMiHdQhs
Mechanical Pigging v Chemical Cleaning
For guidance on Chemical Cleaning Specifications, refer to the embedded file from Jacobs:
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 15
Pipeline Pigging
Pigging is the method of choice for cleaning pipelines. Specialist
contractor usually required.
Important considerations:
• Decision on “piggable” lines made in Design Phase
• Launcher and Receiver are expensive additions if not part of original
design – considerable real estate required
• Length of pipeline and energy source (air or nitrogen usually) needed
to push pig through and not get stuck
• Type of pig and degree of measurement needed
• Adequacy of drainage system at Receiver end to cope with volume of
contaminated fluid pushed through pipeline
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 16
Pipeline Pigging - 2
Advantages Disadvantages
Effectiveness
o Very effective for removal of scale
o Measurable effectiveness
Cost
o Specialist contractor needed
Safety
o Restrict access, barriers required
o Drainage implications at reception
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 17
Pipeline Pigging - 3
For further information on this topic, refer to the embedded files on
pipeline Pigging and Cleaning services from a specialist contractor:
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 18
Pipeline Pigging - 4
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 19
Pipeline Pigging
Link Facility
1 http://www.youtube.com/wa
tch?v=ROrQc1T114w
Removing a Pig
2 http://www.youtube.com/wa
tch?v=XT1cOip53R4
Intelligent Mechanical Pigging
3 http://www.youtube.com/wa
tch?v=o2L6jvMaycY
Pipeline Drying - launching a foam pig
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 19
Mechanical Cleaning
Mechanical Cleaning is often the only effective method for cleaning large
vessels and columns. Be realistic about how long this may take, how
much it will cost and the many safety considerations to ensure a safe
working environment. A specialist contractor or painting contractor is
sometimes used, well-trained and expert in the use of various
mechanical cleaning methods:
• Retro Jet, currently the method of choice
• Needle Gun, Shot Blast, Wire Brush - using breathing apparatus when
working in confined spaces.
Important considerations:
• Safety – confined space, vessel entry
• Removal of all debris
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 20
Mechanical Cleaning - 2
Advantages Disadvantages
Effectiveness
o Effective for removal of rust, scale
o Measurable effectiveness
Cost
o Specialist contractor needed
o Manhour intensive, slow
Safety
o Restrict access, barriers required
o Confined space, vessel entry
Risk
o Residual contamination if all dust
and debris not fully removed
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 21
Mechanical Cleaning - 3
Link Facility
1 CSU - Movie Clips\High Pressure Water jet Cleaner for 5 to 12
in. Pipe Cleaning.mp4
Retro Jet Cleaning #1
2 CSU - Movie Clips\High Pressure Water Jetting.mp4 Retro Jet Cleaning #2
3 CSU - Movie Clips\HP Water Jetting Unit in Action.mp4 Retro Jet Cleaning #3
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 22
Drying Methods
For operational reasons to avoid contamination, slugging and corrosion,
most commissioned Systems are required to be clean and dry. Dryness
required for a particular System is achieved by degree.
• Nitrogen Blowing, suitable for initial drying, may leave piping damp
internally
• Vacuum Drying, suitable for pipelines, to remove all moisture
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 22
Drying Methods - 2
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 23
Drying Methods - 3
Refer to the embedded file for details of pigging and vacuum drying of
gas pipelines:
See this embedded file for details of how this company commissioned
and started up one of its pipelines:
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 24
Nitrogen Drying
Nitrogen has a low dew point and is therefore suitable as the drying
medium of choice in colder climates and subsea pipelines.
The gas is introduced from a high energy source to remove water
slugging and debris in piping and pipeline Systems.
Disconnect pipework from vessels, remove all internals that cause
blockage or obstruction.
Place temporary isolation valve at exhaust, build internal pressure and
release, removing debris.
Not to be used for cleaning:
• Vessels
• Tube Heat Exchangers
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 25
Nitrogen Drying - 2
Important considerations:
• Nitrogen velocity of a minimum 200 ft/sec (approx 65 m/sec)
• Allow adequate purge duration, say 12 hours
• Sample test for dew point temperature (DPT) at System low points
As a guide:
• Continue purge if DPT higher than -30 deg C
• Stop purge and reinstate when DPT is lower than -30 deg C
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 26
Nitrogen Drying - 3
Advantages Disadvantages
Effectiveness
o Very effective for removal of water,
debris
o Measurable effectiveness
Cost
o Shipment, storage of N2 is expensive
o Requires operation by trained users
o Specialist contractor required
Safety
o Restrict access, barriers required
o Containment at exhaust
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 27
Vacuum Drying
Vacuum drying is particularly effective for piping Systems and subsea gas
pipelines that have been previously flushed to remove loose debris, but
where no moisture can be tolerated.
After flushing, specifically sized vacuum pumps are introduced by a
specialist contractor to remove any remaining water from piping and
pipeline Systems.
Remove sensitive instrumentation.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 28
Vacuum Drying
Based on the application of Combined General Gas Law (Avogadro, Gay-
Lussac, Charles, Boyle-Marriotte's Law)
As the volume of air is reduced, the pressure drops, also the boiling
point of any liquid present in the system also drops.
At an absolute pressure of about 2 kPa, water boils at the ambient
external temperature of pipe.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 29
Vacuum Drying
The vacuum drying process must be followed very carefully.
Vacuum pump speed must be maintained to prevent air being evacuated
too quickly, in which case any free water or moisture present will not
evaporate as intended, but cool and freeze.
The pipeline appears to be dry, but after putting into operation ice
gradually melts and the problems with water appears again.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 30
Vacuum Drying
Therefore it is necessary to carefully follow the drying process, including
controlled dwell time when vacuum pumping stops allowing free water
to vaporize in the pipe. Dwell or Rest periods are calculated, determined
by the internal volume of the pipeline and ambient temperature and are
designed to prevent the residual free water from freezing. Dwell times
significantly prolong the drying time.
Refer to the graph on Slide 216 of a Typical Vacuum Drying Operation.
Vacuum drying makes the first gas admittance into the pipes much easier.
The gas is flowing into a vacuum, therefore the pipeline has been
deaerated as there is no risk of forming an explosive mixture.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 31
Vacuum Drying
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 32
Vacuum Drying - 2
Outline procedure:
• After depressurising, any pressure increase indicates a leak
• Find and seal any leaks before continuing the vacuum test
• Monitor vacuum pump exhaust and oil filter for any emulsion,
indicating moisture is present
• When vacuum has been pulled, pump disconnected and pressure
reading stable for duration specified in the test procedure, release to
atmospheric pressure and fill System with a blanket of nitrogen
• Reinstate and proceed with commissioning
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 33
Vacuum Drying - 3
Advantages Disadvantages
Effectiveness
o Very effective for complete removal of
water
o Measurable effectiveness
Cost
o Requires operation by trained users
o Specialist contractor and equipment
required
Safety
o Restrict access, barriers required
o Containment at exhaust
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCleaning and Drying Procedures - 30
Tip
Use or modify the A ITR and B ITR Checksheets supplied with SCDB to
record, track, and report progress in the sequence of activities to
achieve the internal cleanliness and dryness of tubing, piping and vessels.
New Checksheets or Commissioning Procedures should be rendered
compatible with SCDB. Referencing the project’s new Checksheets or
Commissioning Procedures within SCDB will enable the tracking,
controlling and reporting of progress, all intermediate and impacting
activities, such as Punch Listing and Management of Change.
For a reliable audit trail, use or modify the Isolations (Isolation removed)
feature in SCDB to record, track, and report the removal of internals, or
installation of spools, for temporary purposes.
Attach scanned copies of the marked-up Piping Isometrics and P&IDs in
SCDB.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCommissioning Procedures - 01
System and Plant Commissioning
1 http://www.youtube.com/wa
tch?v=0DuURyTtESw
Dry Fork CFPP, WY Scrubber
2 http://www.youtube.com/wa
tch?v=Eg7yvX2M6VY
Ante Creek Gas Plant Commissioning
3
4
5
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet & Certificates Types, Which Ones to Use /
TTM / Maintainable Tags / Punch List & PLI Types
Learning Objectives 1
After this module, the student will have learned the
types of Checksheet (ITR) used and the relevant
part of API RP 1 FSC, the dependent relationship
and hierarchy of certain Checksheets, how to define
Tag Types, what a Tag Type Matrix is, how to create
one for a project, and how to choose the correct
Checksheets for the project.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet & Certificates Types, Which Ones to Use /
TTM / Maintainable Tags / Punch List & PLI Types
Learning Objectives 2
The student will understand that a Gap Analysis is
needed to determine which Tag Types do not have
Checksheets and how to go about filling the gaps by
creating them. The student will have learned the
types of Certificate and Notice used, the dependent
relationship and hierarchy of Certificate, the need to
understand the Contract requirements, incorporate
any Contract Exhibits in SCDB and how to choose
the correct Certificates for the project.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet & Certificates Types, Which Ones to Use /
TTM / Maintainable Tags / Punch List & PLI Types
Learning Objectives 3
The student will understand that a Gap Analysis is
needed to determine which Certificates are needed
and how to go about filling the gaps by creating
them. On completing this module, the student will
know the distinction between Commissionable and
Non-Commissionable Tags and be aware of the two
categories Commissionable Tags come under;
Maintainable and Non-Maintainable.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet & Certificates Types, Which Ones to Use /
TTM / Maintainable Tags / Punch List & PLI Types
Learning Objectives 4
The student will be aware that Maintainable Tags
can be further distinguished as Production or Safety
Critical, be aware of the Tag Types in these
categories, know how these are treated differently
and why. After this module the student will know
the purpose of Punch Listing, the priority treatment
of PLI Categories to achieve System Completion,
how PLIs are recorded, reported and cleared, with
techniques for managing these processes.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones To Use
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopDistribution of Tags in a Typical Project
Tags
Non-Commissionable Commissionable
Areas / Structural
A ITRs only
Architectural, Civil, Structural
Non Maintainable
Maintainable
A & B ITRs
Safety Critical
Production Critical
Other
95%
+/-1%
5%
+/-1%
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopMaintainable and Non-Maintainable Tags
Tags in the Project
From a commissioning perspective, the project is comprised of
two types:
• Commissionable Tags
• Non-Commissionable Tags
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopMaintainable and Non-Maintainable Tags
Commissionable Items
Referred to in this course and across the industry as Tagged
Items, or simply, Tags are two broad component types:
• Maintainable Items
• Non-Maintainable Items
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopMaintainable Tags
Maintainable Items
There are two special types of tags, which by
definition are Maintainable Items:
• Safety Critical and
• Production Critical.
It follows that if an item is Safety Critical or
Production Critical, then it must be Maintainable..
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopMaintainable Tags
Maintainable Items
The ratio of Maintainable Items to Non-
Maintainable Items on a Project is likely to be 5:95.
Only a very small proportion of Tags on the Project
will be Maintainable, roughly 5%, +/-1%
Safety Critical and Production Critical Items are a
subset of the Maintainable Items.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopMaintainable Tags
Safety Critical and Production Critical Tags
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopNon-Commissionable Tags
Non-Commissionable Items
Usually Civil & Structural works, such as:
• Buildings, Structure, Fabric and Cladding
• Foundations, Roads, Drainage ditches
• Lighting standards
• Stairs, Ladders, Walkways, Access Platforms.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPunch Listing & Types of PLI
An essential part in the process of being able to
bring complex projects to acceptable completion is
the role played by Punch Listing.
All snags and incomplete items are recorded as
Punch List Items (PLIs).
Over the life of the project, each System will get
walked many times by formal teams comprising
Owner and Contractor as the overall completion is
progressively achieved.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPunch Listing & Types of PLI
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones To Use
Checksheets for FAT and SAT
Equipment - E ITR
Vendor - V ITR
Used for specialist equipment
Produced by the equipment manufacturer, involving more
detailed, sometimes very specific checks to be carried out.
E ITR and V ITR may first appear during FAT and SAT.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones To Use
Area Checksheets (Non-Commissionable)
Area ITRs - A Checksheet, with no B Checksheet to follow
Relate to Architectural, Civil and Structural discipline
Includes Foundations, Pads, Piles, Roads, Drainage Ditches,
Buildings, Fabric Cladding, Steel Structures, Ladders and
Walkways
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones To Use
One to One and One to Many Checksheets
A considerable amount of management time can be
consumed by signing high volumes of relatively low level
documents.
© Falcon Global Ltd. 2000 - 2019
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones To Use
One to One and One to Many Checksheets
To overcome this, and by mutual agreement, Contractors and
Operators may recognize Tagged Items as suitable candidates for
collecting together on a Bulk ITR.
Bulk ITRs, types A and B, are a special type of one to many
Checksheet, somewhat similar to the Checksheets for Electrical
Circuits, Instrument Loops and Piping Test Packs
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones To Use
Bulk Checksheets
Used for multiple instances of the same Tag Type
Can be checked by the same Inspectors during the same visit
Low Voltage Cables - Electrical, Instrument or Telecomms
Junction Boxes - Electrical, Instrument or Telecomms
Instruments - of same Tag Type in same room or enclosure
Pressure Vessels - of same Tag Type in same area
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones To Use
Bulk Checksheets
In SCDB the same approach is followed so that Power Users can
quickly setup Bulk A ITRs or Bulk B ITRs for:
• Logical groupings of equipment
• Where both parties have agreed Bulk ITRs can be applied.
• The benefit is to the project by:
• saving management time
• but not compromising quality or integrity.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
Test Packs, Loops and Circuits (TLC)
Electrical Circuit, Instrument Loops and Piping Test Pack have a
special type of one-to-many Checksheet that enable verification
checks to be performed on multiple Tagged Items of the
same Tag Type(s) (in the case of Piping Test Packs and Electrical
Circuits) or of the Instrument Tags that form a Loop.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
Test Packs, Loops and Circuits (TLC)
Obtain agreement between Contractor and Customer on the size
and formation of logical groupings of equipment.
Creating Electrical Circuit ITRs, Instrument Loop ITRs
and Piping Test Pack ITRs in SCDB is a very similar process to
creating Bulk ITRs.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
Preservation Checksheets
Preservation ITRs (P ITRs) are also status-sensitive with a unique
icon to differentiate these recurring activities from other
Checksheet activities, which are typically one-time events.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
Rules for Successful use of TLCB ITRs
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
Rules for Successful use of TLCB ITRs
Apply the Trust / Competency – Deployment model
Ensure the Contractor and Customer work closely to agree the
size and composition of the logical groupings to be applied to
Bulks, Circuits, Loops and Test Packs.
Keep deployment of Bulks, Circuits, Loops and Test Packs
proportional to the level of trust
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
Trust / Competency – Deployment model
Establish rules that determine a “logical grouping”:
Tagged Items that have in common
• Tag Type
• Checksheets requiring responses: Yes / No; Initial; PLI
• Location, Room, Module, Building
• All verification checks can be completed by the same
Engineers / Technicians during the same visit
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
Trust / Competency – Deployment model
Establish rules that determine a “logical grouping”:
Two examples of historical abuses:
• Attempting to put all instruments of all types on Bulk
Checksheets
• Attempting to put every motor on the same Bulk Checksheet
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
In Zenator (SCDB), there are the following Checksheet types:
Single Checksheets, one to one relationship of one Checksheet to one
Tagged Item
Bulk Checksheets, one to many relationship of one Checksheet to many
Tagged Items
Electrical Circuits, one to many relationship of one Checksheet to many
Electrical Tags within the Circuit
Instrument Loop, one to many relationship of one Checksheet to many
Instrument Tags within the Loop
Piping Test Packs, one to many relationship of one Checksheet to many
Piping Tags within the Test Pack
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopChecksheet Types, Which Ones to Use
For guidance on Checksheet types, definitions of the stages to
Final Acceptance and general guidance, refer to the embedded
file:
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopGap Analysis – Which Checksheets to Use
Compare Checksheets to Tag Types
The list of Tag Types will come from the engineering deliverables,
including but are not limited to:
• Equipment List
• Piping Line List
• Cable Schedule
• Instrument Index
• Instrument Loop List
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopGap Analysis – Which Checksheets to Use
More Checksheets than Tag Types
An overage of Checksheets to Tag Types is a good place to be,
because then the project has more than are needed and can
remove those that are surplus to requirements.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopGap Analysis – Which Checksheets to Use
More Tag Types than Checksheets
In the situation where the number of Tag Types is greater than
the number of Checksheets, two things will need to occur:
1. Logically rationalize the Tag Types, where possible, so that
several Tag Types can be adequately covered by a single
Checksheet. This situation often arises with Instrumentation
Tags. Many Instrumentation Tag Types, such as Transmitters,
Transducers, Transponders, Flow, Temperature, Pressure
measurement devices can legitimately be covered by a single
Checksheet for installation and another for calibration.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopGap Analysis – Which Checksheets to Use
More Tag Types than Checksheets
If number of Tag Types is greater than number of Checksheets:
2. Create new Checksheets to fill the gaps:
a. With special items, get the vendor to prepare an initial
draft of scope, then customize a Checksheet template;
b. Discipline engineers in the Commissioning Team prepare
the scope, then customize an existing Checksheet template;
c. Choose an existing template closest in scope to the missing
Checksheet, then modify and “save as” new template.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopTag Type Matrix
In parallel with choosing the Checksheets required for the project
and the Gap Analysis is completing the Tag Type Matrix (TTM).
The TTM is an important summary level document defining the
choice of Checksheets to be used to complete each Tag Type.
For many experienced Contractors the TTM is formalized in their
work practices and routines. It is the way they do things. By
Discipline, Supervisors know that from project to project, certain
Checksheets are used to complete certain Tag Types.
On a new project, the Commissioning Manager will either need to
create the TTM from scratch, if one does not exist, or use a TTM
from a previous project.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopTag Type Matrix
When the TTM has been setup, importing it to Zenator is easy.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopTag Type Matrix
TTM in Reports Plus
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopTag Type Matrix
TTM format from Reports Plus
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCertificate Types, Which Ones to Use
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopCertificate Types, Which Ones to Use
Model the Contract requirements in SCDB
Decide which Certificate templates to use
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopGap Analysis – Which Certificates to Use
Compare Certificates to Templates
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopGap Analysis – Which Certificates to Use
Compare Certificates to Templates Supplied
More Certificates than Templates
Create new Certificates to meet Contract requirements
a. Use the Certificates contained in the Contract as Exhibits
and render these compatible with SCDB;
b. Ensure the sequence in the Contract matches that in the
Completions Pyramid and API RP 1FSC;
More Templates than Certificates
Select / customize the Templates required to meet requirements:
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPunch Listing & Types of PLI
Punch List Item Categories
Category A - must be completed before Tag or System is
Mechanically Complete
Category B – can carry over through Static Commissioning but
must be completed before System is Dynamically Commissioned
Category C - must be completed before Start-Up &
Performance Testing is complete
Category D – can be completed at discretion of Operations.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPunch Listing & Types of PLI
When Punch Listing is Performed
Ad-hoc inspections
During completion of A ITR and B ITR Checksheet activities
During a formal System walkdown by Construction,
Commissioning and Operations.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPunch Listing & Types of PLI
Centralize the Punch List 1
Punch List Items can originate in 3rd party
databases, but control and good order
All Punch Listing must be contained in a single
database, for which the Commissioning Manager is
the custodian.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPunch Listing & Types of PLI
Centralize the Punch List 2
Use the functionality in Zenator (SCDB) with
Walkdown Capture to Record and Clear Punch List
Items (PLIs) at every stage in the project life cycle,
until Final Handover to Operations, the ultimate
End-User.
Track and monitor PLIs in Zenator, see reports in
Reports Plus.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPunch Listing & Types of PLI
Recording and Clearing Punch List Items 1
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopManaging PLIs in SCDB
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopManaging PLIs in SCDB
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopLeak Detection
Refer also to Nitrogen-Helium Leak Detection on pages 77-83.
Following Flushing, and closely linked to the Cleaning and Drying
processes discussed earlier is Leak Detection. This occurs after
the Handover from Construction to Commissioning, following
completion of all remaining Category A PLIs in that System.
The purpose of Leak Detection is to discover all leaks within the
System, therefore it necessarily means all items removed during
the Construction tests will have been reinstated, temporary spool
pieces removed and the permanent valves or other equipment
finally installed.
Discuss leak rates
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopLeak Detection
Test pressures, test media and test duration will be stated in the
B ITR Checksheet template, specifically modified to match the
parameters for the System being tested.
At specification changes in the System, where operating pressures
change, isolate the higher pressure parts and progress to
establish the integrity of that part of the System operating at the
lowest pressure.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopLeak Detection
Progress the System test on the higher pressure parts of the
System until the System has been completely tested.
A great deal of visual inspection will be needed by the
Commissioning Team to check for leaks.
With pneumatic testing, test joints with soapy water.
For N2-He leak testing, a specialist subcontractor will test joints
using a mass spectrometer with laboratory for results analysis.
Particular attention will be paid to tests at the specification
changes, to ensure integrity of the joint.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopLeak Detection
Considerations for leak detection are:
• Service Test, with an inert utility, usually air, water or
occasionally nitrogen
• Test pressures are set in the B ITR procedure, for example
at x% of Design Pressure for n hours
• Pipework is adequately supported for the weight of water
• Vents are at high points, drains are at low points
• Relief valves installed
Add leak rates
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopLeak Detection
Considerations for leak detection are:
• Supply of water arranged
• Work Permit obtained based on the procedure contained
in the B ITR
• Test rig, pumps, hoses, test gauges and recorders all ready
• Area is cordoned off with barriers
• Safe disposal of test media arranged
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopLeak Detection
Considerations for leak detection are:
• If successful, with no PLIs to carry forward:
• All Checksheets, procedures and Certificates are
signed off
• The System is physically tagged as “Live”
• If unsuccessful, with PLIs to carry forward:
• PLIs are recorded, any materials needed are sourced
• Work continues on the System until it can pass the
leak test
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
Hydraulic systems are extremely sensitive to contamination, so
achieving the required standard of cleanliness is paramount.
Anecdotally, it is reckoned that perhaps 75% of the downtime
with hydraulic systems can be attributed to contamination.
Cleanliness is important because these are critical systems in the
operation and control of the facility.
For an oil of a given kinematic viscosity, at a temperature of
around 40o to 65o C and at a velocity higher than that at normal
operation to ensure turbulent flow, as calculated in the flushing
procedure, oil is flushed and filtered through the hydraulic
systems, until the required standards are attained.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
In theory, this can be performed either by Construction or
Commissioning – see recommendations below - but it will be
necessary and will take time, running into several weeks on most
projects.
There are various standards in use in the hydraulic industry, of
which ISO 4406:1999, NAS1638 and SAE AS 4059 are probably
the most common.
These standards relate to the size and quantity of particles
passing filters of decreasing size. Liquid Particle Counters are
used to determine the quality of the liquid passing through them.
The size and number of particles can determine if the liquid is
clean enough to be used for the designed application.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
Each project will specify the degree of cleanliness to be attained.
The Commissioning Manager needs to decide early on, by whom
and when hot oil flushing will be performed, and plan accordingly.
The objective is to attain the required cleanliness standards in the
least time and at the least expense;
Considerations are:
• Where in the project schedule to fit hot oil flushing
• Extent of Lube Oil and hydraulic systems on the project
• Quantity of oil needed to attain the required standard
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
Further considerations are:
• Equipment needed
• Hire a specialist contractor and attendance on site
• Bed space
• Budget
The advice is to schedule the work as a Static Commissioning
activity, within the scope of B ITRs, and hire a specialist
contractor who will provide the personnel, pumps, hoses,
laboratory with measuring equipment and the cleaning fluid.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
All A ITRs for Hydraulic and Lube Oil Systems are complete, with
no outstanding Category A PLIs or MOCs.
All B ITRs for Leak Testing Hydraulic and Lube Oil Systems are
complete and Category A PLIs or MOCs
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
The fluid sample size used to determine cleanliness is proportional
to the total volume of fluid in the System.
When the required cleanliness standard is attained for the System,
Commissioning retains custody until Handover to Operations.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
Refer to the embedded files:
POCKET_BOOK_EN_St
andard.pdf
GE_Cleanliness_Requi
rements.pdf
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
Notes on varying cleanliness standards:
Commonly quoted: NAS 1638 Class 6; ISO 4406: Class 17/15/12
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
Kinematic Viscosity v Temperature:
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHot Oil Flushing
Hydraulic Systems / Lube Oil Systems
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Learning Objective
After completing this module, the student will have an
understanding that the Pre-Start-Up Safety Review originates in
the OSHA regulations concerning process safety with the
sequence of activities leading to a successful PSSR that should
ensure a safe Start Up of the facility.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Process safety management of highly
hazardous chemicals
In accordance with CFR 1910.119 (OSHA regulation 3132) for
process safety management (PSM), the Owner or Operator shall
follow established procedures and observe specific requirements
leading to the Start-Up of a plant or facility.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Process Safety Management today
• Many developments since OSHA 3132 in 2000
• Reactive models with lagging indicators proven insufficient
• Positive ROI for good PSM, examples from IOGP and et al
• Use Proactive indicators and metrics
• Asset Integrity = Process Safety
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Risk Management - Swiss Cheese Model
https://www.aiche.org/resources/publications/cep/2017/september/plug-holes-swiss-cheese-model
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Risk Management – Barrier Analysis
https://www.aiche.org/resources/publications/cep/2016/december/use-bow-tie-diagram-help-reduce-process-safety-risks
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Table 1 OSHA PSM Regulation
The employer shall perform a pre-startup safety review (PSSR) for new
facilities and for modified facilities when the modification is significant
enough to require a change in the process safety information.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Table 1 OSHA PSM Regulation (Cont’d)
The pre-startup safety review shall confirm that prior to the
introduction of highly hazardous chemicals to a process:
(i) Construction and equipment is in accordance with design
specifications;
(ii) Safety, operating, maintenance, and emergency procedures are in
place and are adequate;
(iii) For new facilities, a process hazard analysis has been performed
and recommendations have been resolved or implemented before
Start-Up; and modified facilities meet the requirements contained in
management of change, paragraph (l) [of this regulation].
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Table 2 OSHA PSM Guidance
For new processes, the employer will find a Process Hazard Analysis
(PHA) helpful in improving the design and construction of the process
from a reliability and quality point of view.
The safe operation of the new process will be enhanced by making use
of the PHA recommendations before final installations are completed.
P&IDs are to be completed along with having the operating procedures
in place and the operating staff trained to run the process before
startup.
The initial startup procedures and normal operating procedures need
to be fully evaluated as part of the pre-startup review to assure a safe
transfer into the normal operating mode for meeting the process
parameters.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Table 2 OSHA PSM Guidance (Cont’d)
For existing processes that have been shutdown for turnaround, or
modification, etc., the employer must assure that any changes other
than “replacement in kind” made to the process during shutdown go
through the management of change procedures.
P&IDs will need to be updated as necessary, as well as operating
procedures and instructions. If the changes made to the process during
shutdown are significant and impact the training program, then
operating personnel as well as employees engaged in routine and non-
routine work in the process area may need some refresher or
additional training in light of the changes. Any incident investigation
recommendations, compliance audits or PHA recommendations need to
be reviewed as well to see what impacts they may have on the process
before beginning the startup.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Discussion of the Regulation
The first paragraph of the regulation states that a PSSR is needed
whenever Process Safety Information (PSI) is changed.
In effect, this requirement is such that virtually all changes will have to
be reviewed in a PSSR.
There are very few changes that do not require some information
changes to do with topics such as safe limits, engineering drawings and
equipment lists.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Discussion of the Regulation (Cont’d)
(i) Construction and Equipment
Paragraph (i) of the standard requires that construction and equipment
is in accordance with design specifications.
PSSR team members can carry out spot-checks of the installed piping
and equipment, and compare it with the piping lists and equipment
data sheets.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Discussion of the Regulation (Cont’d)
(ii) Procedures
Paragraph (ii) requires that the facility’s procedures reflect the manner
in which the facility is to be operated after the process changes have
been made.
The PSSR should check that safety, operating and emergency
procedures for the new operation have been written down, and that
they accurately describe what has to done.
This paragraph does not mention training, but it can be assumed that
operators and maintenance workers must be trained in the use of the
new procedures.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Discussion of the Regulation (Cont’d)
(iii) New / Modified Facilities
The regulation requires that new facilities conduct a PHA.
The PSSR team should check that the PHA was in fact carried out, and
that its recommendations were either resolved or implemented.
During the pressure of construction, there is sometimes a tendency to
postpone some of the PHA recommendations until ‘there is sufficient
time’.
The PSSR should check that the recommendations have been closed
out properly.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Fishbone Diagrams
According to Wikipedia, Ishikawa diagrams (also called fishbone diagrams,
herringbone diagrams, cause-and-effect diagrams, or Fishikawa) are causal
diagrams created by Kaoru Ishikawa (1968) that show the causes of a specific
event.[1][2] Common uses of the Ishikawa diagram are product design and
quality defect prevention to identify potential factors causing an overall effect.
Each cause or reason for imperfection is a source of variation. Causes are
usually grouped into major categories to identify these sources of variation. The
categories typically include:
People: Anyone involved with the process
Methods: How the process is performed and the specific requirements for
doing it, such as policies, procedures, rules, regulations and laws
Machines: Equipment, computers, tools required to accomplish the job
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Fishbone Diagrams (cont’d)
Materials: Raw materials, parts, pens, paper, etc. used to produce the final
product
Measurements: Data generated from the process that are used to evaluate
its quality
Environment: The conditions, such as location, time, temperature, and culture
in which the process operates.
Refer to the embedded
Fishbone Diagram from a
recently completed major oil
& gas production facilities
project.
Refer to the embedded
PSSR Checklist from
AICE.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopProcess Safety Management and PSSR
Management of Change and Audits
The way in which PSSR, MOCs and audits link to one another is
demonstrated in Figure 1.
Figure 1 - PSSR / MOC / Audit
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopLessons Learned [Practices Worth Replicating]
Make Lessons Learned become Best Practices
Now, and at key stages in the life cycle of a project we have the
opportunity for capturing the lessons to be learned and enabling them
to become best practices.
Document and embed the ideas that follow in the learning
organization through training, modified work practices, processes and
procedures.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopTurnover Completion Packages
aka Commissioning Dossiers or Workpacks
Learning Objective
On completing this module, the student will again be reminded of
the importance of having excellent relations with Operations and
being able to make timely contributions to the PSM and PSSR,
achieved by delivering on the well thought-through agreements
made with Operations during Step 4 of the Simplified
Commissioning Logic, while the project was early in Detailed
Engineering.
These concern the timing of TCCC around agreed battery limits
and contents of TCPs.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopTurnover Completion Packages
aka Commissioning Dossiers or Workpacks
API RP 1FSC, 1st Edition, Annex A – Courtesy of API
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopTurnover Completion Packages
aka Commissioning Dossiers or Workpacks
API RP 1FSC, 1st Edition, Annex A – Courtesy of API (Cont’d)
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopHandover to Operations
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopReady for Initial Start-Up (RFISU)
Guidelines on Timing and Scope
• RFISU of a defined portion of the Facility is when the
agreed target status has been demonstrated for all
material items, and can be safely energized.
• The defined portion is an ‘operable entity’ of the Facility.
• Successful testing prior to RFISU is a good indicator that
reliable and continuous Initial Start-up operations may be
productively commenced
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPre Start-Up Safety Review (PSSR)
Guidelines on Timing and Scope
• Focus on high energy processing or critical equipment
within the boundaries of a pre-defined plant area, or
within the boundaries of the whole facility
• Prior to initial start-up of unit / facility on process
hydrocarbons or hazardous chemicals, or critical Utilities
before Initial Start-Up
• Not greater than 90 days from start-up date
• Not less than 35 days from start-up
• Formal process carried out by external auditors
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPre Start-Up Safety Review (PSSR)
Guidelines on Timing and Scope
– Facilities are constructed as per design
– In compliance with Operations philosophy
– Asset integrity is verified and can be demonstrated
– Vendor support is identified and scheduled
– Operations staff are sufficiently trained and competent
– OMS is operable and ready for steady-state operations
– Commissioning ‘prerequisites’ are in place
– Project assurance is in place
– HSE Management System is in place
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopPre Start-Up Safety Review (PSSR)
Checklist Guidelines
Reproduced with grateful thanks to AICE:
Performance Monitoring
Reproduced with grateful thanks to Chevron Corporation:
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopStart-Up on Paper (SUOP)
Guidelines on Timing and Scope
• Risk assessment, preparation and familiarization
• All personnel required for SU must be involved in Start-
Up On Paper (SUOP) as it ensures
– Start-Up/Ramp-Up (SURU) procedure for Initial Start-Up is
fully understood
– Requirements in event of an emergency are known
– Roles and Responsibilities are identified
– Interfaces are known and the communication protocol for
Start-Up is fully understood.
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopStart-Up on Paper (SUOP)
Guidelines on Timing and Scope
• Commissioning issue the RFSU Certificate to Operations
for TCCC
• All ESD/PSD testing has been completed before Start-Up
– A full ESD test will be carried out post Initial Start-Up
• To accept TCCC, the Operator shall:
– review all Systems status until assured that integrity criteria
has been demonstrated and required test criteria verified
– verify any necessary approvals have been received
– ensure remaining PLIs / Exceptions are agreed in terms of
scope, cost and schedule
© Falcon Global Ltd. 2000 - 2019
Commissioning & Start Up WorkshopStart-Up on Paper (SUOP)
Guidelines on Timing and Scope
• Commissioning and Operations agree Systems are at
RFSU status, initial start-up procedure can commence
• Large projects with multiple Production Units, or phased
introduction of hydrocarbons, verification of the RFSU
status will be required and included in the Final
Acceptance Certificate (FAC) documentation.