cob specification no. 16-11002-c city of berkeley … · and pathway renovations city of berkeley...

5
WILLARD PARK PLAY AREA AND PATHWAY RENOVATIONS CITY OF BERKELEY COB SPECIFICATION No. 16-11002-C 2730 HILLEGASS AVENUE BERKELEY, CA 94705 T1 TITLE SHEET D1 DEMOLITION & SITE PREPARATION PLAN L1 LAYOUT & GRADING PLAN L2 DETAILS: SITE WORK L3 DETAILS: PLAY AREA SHEET INDEX STANDARD PLANS & SPECIFICATIONS: CONSTRUCT IN ACCORDANCE WITH THESE PLANS, CITY STANDARD PLANS & THE PROJECT SPECIFICATIONS, SUBJECT TO INSPECTION & APPROVAL OF THE ENGINEER. NOTWITHSTANDING THE PRESENCE OF THE CITY INSPECTOR, EITHER FULL OR PART-TIME, THE CONTRACTOR IS NOT RELIEVED OF THE RESPONSIBILITY OF PERFORMING THE WORK IN ACCORDANCE WITH THESE DOCUMENTS. LICENSING: PRIME CONTRACTOR SHALL POSSESS A VALID CALIFORNIA 'A' OR 'C-27' LICENSE AT THE TIME THIS CONTRACT IS AWARDED. ATTENTION IS DIRECTED TO THE PROVISIONS OF CALIFORNIA BUSINESS & PROFESSIONS CODE - DIVISION 3, CHAPTER 9, CONCERNING CONTRACTOR LICENSING. VERIFICATION OF EXISTING CONDITIONS: ALL EXISTING CONDITIONS, ELEVATIONS, DIMENSIONS & CONSTRUCTION IN THE FIELD PRIOR TO BID. IF ANY DISCREPANCIES ARE NOTED, THE CONTRACTOR SHALL NOTIFY THE ENGINEER IMMEDIATELY FOR DIRECTION. NOTICE TO PROCEED: CONTRACTOR SHALL NOT COMMENCE WORK UNTIL AFTER A PRE-CONSTRUCTION MEETING HAS BEEN HELD WITH THE CITY & AFTER A NOTICE TO PROCEED HAS BEEN ISSUED BY THE CITY. SAFETY: CONTRACTOR SHALL PROVIDE ALL SIGNS, BARRICADES OR OTHER DEVICES NECESSARY TO PROVIDE FOR PUBLIC & WORKER SAFETY. COMPLY WITH THE RULES & REGULATIONS OF THE STATE CONSTRUCTION SAFETY ORDERS & CAL OSHA. CONTRACTOR SHALL POST ON JOB SITE THE EMERGENCY TELEPHONE NUMBERS FOR PUBLIC WORKS, AMBULANCE, POLICE & FIRE DEPARTMENTS. EXISTING UTILITIES, UNDERGROUND FACILITIES & SITE IMPROVEMENTS: LOCATIONS & ELEVATIONS OF ALL EXISTING UTILITIES (UNDERGROUND & OVERHEAD) & SITE IMPROVEMENTS, IF SHOWN ON THE PLANS, ARE APPROXIMATE ONLY. CONTRACTOR SHALL FIELD VERIFY THE EXACT DEPTH OF BURIAL & HORIZONTAL LOCATION OF UTILITY LINES AS NECESSARY. PRIOR TO PERFORMING UNDERGROUND CONSTRUCTION, THE CONTRACTOR SHALL MAKE THE NECESSARY PROBES TO IDENTIFY AREAS OF POSSIBLE CONFLICT WITH PROPOSED CONSTRUCTION AS NEEDED. CONTRACTOR SHALL EXCAVATE TO DETERMINE TYPES, EXTENT, SIZE & DEPTHS OF UNDERGROUND UTILITIES. COORDINATE WORK TO AVOID CONFLICTS BETWEEN PROPOSED IMPROVEMENTS & EXISTING UNDERGROUND FACILITIES, SEWER LATERALS, STORM DRAINS & WATER MAINS. PROTECT EXISTING UTILITIES & SITE IMPROVEMENTS FROM DAMAGE. CONTRACTOR TO TAKE SPECIAL PRECAUTIONS WHEN WORKING NEAR HIGH RISK UTILITIES. CONTRACTOR SHALL COORDINATE ALL NECESSARY UTILITY RELOCATIONS & ADJUSTMENTS WITH THE APPROPRIATE UTILITY COMPANIES. ADJUST UTILITY BOXES TO GRADE AS NOTED. UTILITY REPAIR: CONTRACTOR SHALL REPAIR ANY DAMAGE OR INTERRUPTION OF UTILITIES, WATER LINES OR IRRIGATION SYSTEMS WITHIN 48 HOURS OF THE TIME OF DAMAGE. TRAFFIC CONTROL: CONFORM TO SPECIFICATIONS. COORDINATION: GENERAL CONTRACTOR IS RESPONSIBLE FOR COORDINATING ALL OF THE WORK PERFORMED BY HIS SUBCONTRACTORS WITHOUT EXCEPTION. DUST CONTROL & POLLUTION PREVENTION: CONFORM TO SPECIFICATIONS. ANY OPERATIONS THAT CREATE DUST MUST BE STOPPED IMMEDIATELY & REMEDIAL ACTIONS TAKEN. SUBSEQUENTLY, CONTRACTOR SHALL REMOVE MUD TRACKS FROM STREETS OR ADJACENT PROPERTIES & SWEEP STREETS, AS DIRECTED BY THE CITY ENGINEER. LAYOUT APPROVAL: EXACT FIELD LOCATION FOR NEW IMPROVEMENTS SHALL BE APPROVED BY THE ENGINEER BEFORE CONSTRUCTION. MATCHING EXISTING CONDITIONS: CONTRACTOR IS RESPONSIBLE FOR MATCHING EXISTING WALKS, ADJACENT PAVING, SURROUNDING LANDSCAPE & OTHER IMPROVEMENTS WITH A SMOOTH TRANSITION IN PAVING & GRADING, ETC., & TO AVOID ANY ABRUPT OR APPARENT CHANGES IN GRADES OR CROSS SLOPES, LOW SPOTS OR HAZARDOUS CONDITIONS. WHERE PAVEMENT IS TO BE EXTENDED, THE EXISTING EDGE OF PAVEMENT TO BE REMOVED MUST BE NEATLY SAWCUT OR REMOVED TO AN EXPANSION JOINT. FIELD CHANGES: CONTRACTOR SHALL NOTIFY CITY'S REPRESENTATIVE IMMEDIATELY UPON DISCOVERY OF ANY POTENTIAL FIELD CHANGES. CONTRACTOR SHALL BE RESPONSIBLE FOR ANY FIELD CHANGES MADE WITHOUT WRITTEN AUTHORIZATION FROM THE CITY. HAULING: WHEN HAULING ANY EARTH, SAND, GRAVEL, STONE, DEBRIS, PAPER, OR ANY OTHER SUBSTANCE OVER ANY PUBLIC STREET OR PUBLIC PLACE, NO PERSON SHALL ALLOW MATERIAL TO BLOW OR SPILL OVER & UPON SAID PUBLIC, ADJACENT OR PRIVATE PROPERTY. SITE RESTORATION: CONTRACTOR SHALL REPLACE OR RESTORE TO PRE-CONSTRUCTION CONDITION ALL PAVING, UTILITIES, SERVICES, IRRIGATION, LANDSCAPE MATERIALS, PAVEMENT DELINEATION & OTHER IMPROVEMENTS, THAT ARE NOT TO BE REMOVED BUT ARE DAMAGED DURING CONSTRUCTION AT NO ADDITIONAL EXPENSE TO THE CITY. EXISTING PLANT MATERIAL TO REMAIN: CONTRACTOR IS RESPONSIBLE FOR REPLACING ALL LANDSCAPE DAMAGED DURING CONSTRUCTION. A. EXCAVATION UNDER TREE DRIPLINES: TAKE PRECAUTION WHEN EXCAVATING UNDER TREE DRIPLINES. HAND EXCAVATION ONLY IS ALLOWED WITHIN THE DRIPLINE. B. ROOT CUTTING: THIS WORK SHALL BE DONE UNDER DIRECTION OF CITY APPROVED CERTIFIED ARBORIST HIRED BY THE CONTRACTOR. ROOTS LARGER THAN 2" ENCOUNTERED WITHIN THE TOP 3' OF EXCAVATION SHALL BE HAND DUG & PROTECTED. CLEAN-UP: CLEAN CITY STREETS AS OFTEN AS REQUIRED TO REMOVE ANY ACCUMULATION OF MUD & DEBRIS RESULTING FROM THE CONSTRUCTION. REMOVE OIL TRACKS FROM STRIPING, SIDEWALK & PAVEMENT DELINEATORS ON ADJOINING STREETS WITHIN 48 HOURS. PHOTOGRAPHY: CITY WILL RESERVE THE RIGHT TO TAKE PHOTOGRAPHS & VIDEOS DURING THE COURSE OF CONSTRUCTION. 1. GENERAL NOTES 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. VICINITY MAP LANDSCAPE ARCHITECT McARDLE DESIGN 3400 MT. DIABLO BLVD. SUITE 207 LAFAYETTE, CA 94549 925.283.5520 [email protected] CONTACT: KAREN McARDLE PROJECT TEAM

Upload: others

Post on 31-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: COB SPECIFICATION No. 16-11002-C CITY OF BERKELEY … · and pathway renovations city of berkeley cob specification no. 16-11002-c 2730 hillegass avenue berkeley, ca 94705 t1title

WILLARD PARK PLAY AREA

AND PATHWAY RENOVATIONS

CITY OF BERKELEY

COB SPECIFICATION No. 16-11002-C

2730 HILLEGASS AVENUE

BERKELEY, CA 94705

T1 TITLE SHEET

D1 DEMOLITION & SITE PREPARATION PLAN

L1 LAYOUT & GRADING PLAN

L2 DETAILS: SITE WORK

L3 DETAILS: PLAY AREA

SHEET INDEX

STANDARD PLANS & SPECIFICATIONS: CONSTRUCT IN ACCORDANCE WITH THESE PLANS, CITY STANDARD PLANS & THE PROJECT

SPECIFICATIONS, SUBJECT TO INSPECTION & APPROVAL OF THE ENGINEER.

NOTWITHSTANDING THE PRESENCE OF THE CITY INSPECTOR, EITHER FULL OR PART-TIME, THE CONTRACTOR IS NOT RELIEVED OF

THE RESPONSIBILITY OF PERFORMING THE WORK IN ACCORDANCE WITH THESE DOCUMENTS.

LICENSING: PRIME CONTRACTOR SHALL POSSESS A VALID CALIFORNIA 'A' OR 'C-27' LICENSE AT THE TIME THIS CONTRACT IS

AWARDED. ATTENTION IS DIRECTED TO THE PROVISIONS OF CALIFORNIA BUSINESS & PROFESSIONS CODE - DIVISION 3,

CHAPTER 9, CONCERNING CONTRACTOR LICENSING.

VERIFICATION OF EXISTING CONDITIONS: ALL EXISTING CONDITIONS, ELEVATIONS, DIMENSIONS & CONSTRUCTION IN THE FIELD

PRIOR TO BID. IF ANY DISCREPANCIES ARE NOTED, THE CONTRACTOR SHALL NOTIFY THE ENGINEER IMMEDIATELY FOR DIRECTION.

NOTICE TO PROCEED: CONTRACTOR SHALL NOT COMMENCE WORK UNTIL AFTER A PRE-CONSTRUCTION MEETING HAS BEEN HELD

WITH THE CITY & AFTER A NOTICE TO PROCEED HAS BEEN ISSUED BY THE CITY.

SAFETY: CONTRACTOR SHALL PROVIDE ALL SIGNS, BARRICADES OR OTHER DEVICES NECESSARY TO PROVIDE FOR PUBLIC &

WORKER SAFETY. COMPLY WITH THE RULES & REGULATIONS OF THE STATE CONSTRUCTION SAFETY ORDERS & CAL OSHA.

CONTRACTOR SHALL POST ON JOB SITE THE EMERGENCY TELEPHONE NUMBERS FOR PUBLIC WORKS, AMBULANCE, POLICE & FIRE

DEPARTMENTS.

EXISTING UTILITIES, UNDERGROUND FACILITIES & SITE IMPROVEMENTS: LOCATIONS & ELEVATIONS OF ALL EXISTING UTILITIES

(UNDERGROUND & OVERHEAD) & SITE IMPROVEMENTS, IF SHOWN ON THE PLANS, ARE APPROXIMATE ONLY. CONTRACTOR SHALL

FIELD VERIFY THE EXACT DEPTH OF BURIAL & HORIZONTAL LOCATION OF UTILITY LINES AS NECESSARY.

PRIOR TO PERFORMING UNDERGROUND CONSTRUCTION, THE CONTRACTOR SHALL MAKE THE NECESSARY PROBES TO IDENTIFY

AREAS OF POSSIBLE CONFLICT WITH PROPOSED CONSTRUCTION AS NEEDED. CONTRACTOR SHALL EXCAVATE TO DETERMINE

TYPES, EXTENT, SIZE & DEPTHS OF UNDERGROUND UTILITIES. COORDINATE WORK TO AVOID CONFLICTS BETWEEN PROPOSED

IMPROVEMENTS & EXISTING UNDERGROUND FACILITIES, SEWER LATERALS, STORM DRAINS & WATER MAINS.

PROTECT EXISTING UTILITIES & SITE IMPROVEMENTS FROM DAMAGE. CONTRACTOR TO TAKE SPECIAL PRECAUTIONS WHEN

WORKING NEAR HIGH RISK UTILITIES. CONTRACTOR SHALL COORDINATE ALL NECESSARY UTILITY RELOCATIONS & ADJUSTMENTS

WITH THE APPROPRIATE UTILITY COMPANIES. ADJUST UTILITY BOXES TO GRADE AS NOTED.

UTILITY REPAIR: CONTRACTOR SHALL REPAIR ANY DAMAGE OR INTERRUPTION OF UTILITIES, WATER LINES OR IRRIGATION

SYSTEMS WITHIN 48 HOURS OF THE TIME OF DAMAGE.

TRAFFIC CONTROL: CONFORM TO SPECIFICATIONS.

COORDINATION: GENERAL CONTRACTOR IS RESPONSIBLE FOR COORDINATING ALL OF THE WORK PERFORMED BY HIS

SUBCONTRACTORS WITHOUT EXCEPTION.

DUST CONTROL & POLLUTION PREVENTION: CONFORM TO SPECIFICATIONS. ANY OPERATIONS THAT CREATE DUST MUST BE

STOPPED IMMEDIATELY & REMEDIAL ACTIONS TAKEN. SUBSEQUENTLY, CONTRACTOR SHALL REMOVE MUD TRACKS FROM STREETS

OR ADJACENT PROPERTIES & SWEEP STREETS, AS DIRECTED BY THE CITY ENGINEER.

LAYOUT APPROVAL: EXACT FIELD LOCATION FOR NEW IMPROVEMENTS SHALL BE APPROVED BY THE ENGINEER BEFORE

CONSTRUCTION.

MATCHING EXISTING CONDITIONS: CONTRACTOR IS RESPONSIBLE FOR MATCHING EXISTING WALKS, ADJACENT PAVING,

SURROUNDING LANDSCAPE & OTHER IMPROVEMENTS WITH A SMOOTH TRANSITION IN PAVING & GRADING, ETC., & TO AVOID ANY

ABRUPT OR APPARENT CHANGES IN GRADES OR CROSS SLOPES, LOW SPOTS OR HAZARDOUS CONDITIONS. WHERE PAVEMENT IS

TO BE EXTENDED, THE EXISTING EDGE OF PAVEMENT TO BE REMOVED MUST BE NEATLY SAWCUT OR REMOVED TO AN EXPANSION

JOINT.

FIELD CHANGES: CONTRACTOR SHALL NOTIFY CITY'S REPRESENTATIVE IMMEDIATELY UPON DISCOVERY OF ANY POTENTIAL FIELD

CHANGES. CONTRACTOR SHALL BE RESPONSIBLE FOR ANY FIELD CHANGES MADE WITHOUT WRITTEN AUTHORIZATION FROM THE

CITY.

HAULING: WHEN HAULING ANY EARTH, SAND, GRAVEL, STONE, DEBRIS, PAPER, OR ANY OTHER SUBSTANCE OVER ANY PUBLIC

STREET OR PUBLIC PLACE, NO PERSON SHALL ALLOW MATERIAL TO BLOW OR SPILL OVER & UPON SAID PUBLIC, ADJACENT OR

PRIVATE PROPERTY.

SITE RESTORATION: CONTRACTOR SHALL REPLACE OR RESTORE TO PRE-CONSTRUCTION CONDITION ALL PAVING, UTILITIES,

SERVICES, IRRIGATION, LANDSCAPE MATERIALS, PAVEMENT DELINEATION & OTHER IMPROVEMENTS, THAT ARE NOT TO BE

REMOVED BUT ARE DAMAGED DURING CONSTRUCTION AT NO ADDITIONAL EXPENSE TO THE CITY.

EXISTING PLANT MATERIAL TO REMAIN: CONTRACTOR IS RESPONSIBLE FOR REPLACING ALL LANDSCAPE DAMAGED DURING

CONSTRUCTION.

A. EXCAVATION UNDER TREE DRIPLINES: TAKE PRECAUTION WHEN EXCAVATING UNDER TREE DRIPLINES. HAND EXCAVATION

ONLY IS ALLOWED WITHIN THE DRIPLINE.

B. ROOT CUTTING: THIS WORK SHALL BE DONE UNDER DIRECTION OF CITY APPROVED CERTIFIED ARBORIST HIRED BY THE

CONTRACTOR. ROOTS LARGER THAN 2" ENCOUNTERED WITHIN THE TOP 3' OF EXCAVATION SHALL BE HAND DUG &

PROTECTED.

CLEAN-UP: CLEAN CITY STREETS AS OFTEN AS REQUIRED TO REMOVE ANY ACCUMULATION OF MUD & DEBRIS RESULTING FROM

THE CONSTRUCTION. REMOVE OIL TRACKS FROM STRIPING, SIDEWALK & PAVEMENT DELINEATORS ON ADJOINING STREETS WITHIN

48 HOURS.

PHOTOGRAPHY: CITY WILL RESERVE THE RIGHT TO TAKE PHOTOGRAPHS & VIDEOS DURING THE COURSE OF CONSTRUCTION.

1.

GENERAL NOTES

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

VICINITY MAP

LANDSCAPE ARCHITECT

McARDLE DESIGN

3400 MT. DIABLO BLVD. SUITE 207

LAFAYETTE, CA 94549

925.283.5520

[email protected]

CONTACT: KAREN McARDLE

PROJECT TEAM

Page 2: COB SPECIFICATION No. 16-11002-C CITY OF BERKELEY … · and pathway renovations city of berkeley cob specification no. 16-11002-c 2730 hillegass avenue berkeley, ca 94705 t1title

TENNIS

COURT

D4

L4

E6

E7

E8

L5

G2

L6

D5

L10

SF

DF3

C1

SF

L9

C1

SF

SURFACE B

SURFACE A

SWING 2

SWING 1

SURFACE B

EQUIP 1

SURFACE C

C2

DF2

SF

CONSTRUCTION

FENCE

CONSTRUCTION

FENCE

SURFACE B

SURFACE D

SURFACE D

RELOCATE

BENCH

SF

T

DERBY STREET

TENNIS

COURT

D1

B1

SF

D2

E1

L1

B2

C1

E2

L2

G1

SF

L8

E3

E4

L3

I1E5

D3

D4

I2

D7

I3

I4

D6

DF1

C1

E9

C2

E10E11E12

L7

C2

W

CONSTRUCTION

FENCE

CONSTRUCTION PROTECTION FENCING: SECURE WORK AREA WITH TEMPORARY

6' HEIGHT CHAIN LINK FENCE AS DIRECTED BY CITY, SEE SPECIFICATIONS.

MATERIAL STORAGE: NO STOCKPILING OF MATERIAL ON SITE UNLESS

APPROVED BY THE CITY.

DRAIN INLETS: ADJUST ALL DRAIN INLETS WITHIN PROJECT PAVING AREA AS

REQUIRED TO MEET FLUSH WITH PROPOSED GRADES. PROVIDE NEW CONC.

COLLAR AS REQUIRED.

UTILITY BOXES: ADJUST ALL UTILITY BOXES WITHIN PROJECT PAVING AREA AS

REQUIRED TO MEET FLUSH WITH PROPOSED GRADES. REPLACE ALL DAMAGED

UTILITY BOXES AND/OR LIDS, MATCH EXISTING.

1.

DEMOLITION & SITE PREPARATION NOTES

2.

3.

4.

LEGEND

SYMBOL DESCRIPTION TASK

REMOVE (E) A.C. PAVING & BASE MATERIAL. REMOVAL

DEPTH TO ACCOMMODATE PROPOSED GRADING & PAVING.

REMOVE (E) SURFACING MATERIAL. REMOVAL DEPTH

TO ACCOMMODATE PROPOSED GRADING & PAVING.

CONSTRUCTION FENCE. LOCATION TO BE

APPROVED IN FIELD BY CITY'S REPRESENTATIVE

SAWCUT PAVING

D1

MATCHLINE - SEE LOWER LEFT

MATCHLINE - SEE UPPER RIGHT

WILLARD PARK PLAY AREA

AND PATHWAY RENOVATIONS

2730 HILLEGASS AVE., BERKELEY, CA 94705

Page 3: COB SPECIFICATION No. 16-11002-C CITY OF BERKELEY … · and pathway renovations city of berkeley cob specification no. 16-11002-c 2730 hillegass avenue berkeley, ca 94705 t1title

TENNIS

COURT

5%8.1%

2

.2

%

2.2%

RL

7

.

7

%

1

.6

%

FLO

W LIN

E

2.0%

FG 233.32

(FG 233.32)

FG 233.35

(FG 233.35)

FG 233.54

(FG 233.54)

FG 233.49

(FG 233.49)

FG 233.35

FG 233.40

(FG 233.40)

2

.

6

%

FG 233.31

(FG 233.31)

RE 233.23

B

L2

1

.

1

%

1

%

RL

1%

4

.

8

%

A

L2

1

%

1

.

2

%

2

%

1

.

2

%

1%

1

.

1

%

1

%

4" S

D P

IP

E S

=0.005 M

IN

FG 233.34

(FG 233.34)

FG 233.34

(FG 233.34)

9

'-

6

"

C1

C2

RELOCATE

BENCH

B

L3

C

L3

G

L3

EQ

EQEQ

EQ

E

L3

E

L3

F.2

L3

F.1

L3

H

L2

F

L2

DECK MOUNTED

BENCH

SEE NOTE 1,

THIS SHEET

F

L2

EWF PLAY SURFACING

12" MIN. COMPACTED DEPTH

TIMBER EDGING

AT TREE

EWF PLAY SURFACING

6" MIN. COMPACTED DEPTH.

INSTALL FLUSH WITH WOOD CAP

H

L3

E

L3

A

L1

PAINT METAL

RAIL

A

L1

PAINT METAL

RAIL

A

L1

PAINT METAL

BENCH

TENNIS

COURT

R

3

'-

6

"

FG 231.84

(FG 231.84)

4

.

0

%

1

%

2

.2

%

1

.

1

%

2

.3

%

1%

RL

6

.

0

%

6

.4

%

2

.3

%

2

.

3

%

2

.

3

%

2

.3

%

2

.3

%

2

.

3

%

1

.

5

%

1.6%

RL

1

.

1

%

1.1%

1

.

5

%

1

.5

%

RL

1

%

(4.4

%

)

3.3%

1

%

6

.

1

%

5

.

5

%

(1.7%)

1

%

4.2%

1

%1

%

0.002%

0.009%

1.8%

FLO

W LIN

E

FG 232.00

(FG 232.00)

FG 231.68

(FG 231.68)

RE 231.80

(RE 231.79)

(RE 231.81)

FG 231.91

(FG 231.91)

FG 232.01

(FG 232.01)

FG 232.03

(FG 232.03)

FG 231.91

(FG 231.91)

FG 232.07

(FG 232.07)

RE 231.77

(RE 231.62)

FG 233.25

(FG 232.25)

FG 232.10

(FG 232.10)

FG 231.97

(FG 231.72)

FG 232.04

(FG 232.04)

FG 232.18

(FG 232.18)

FG 231.91

(FG 231.89)

FLO

W LIN

E

1.1%

FG 232.37

(FG 232.37)

FG 232.40

(FG 232.40)

FG 232.77

(FG 232.77)

FG 233.24

(FG 233.24)

RE 232.30

(RE 231.75)

FG 233.34

(FG 233.34)

REMOVABLE

BOLLARDS

1.2%

1.8%

1.1%

INFILL COBBLE PAVERS.

CONFORM TO EXISTING

PATTERN

D

L2

A

L2

E

L2

F

L2

CURVED

BENCH

G

L2

B

L2

B

L2

5

.

9

%

1.2%

A

L2

2.7%

5

.

8

%

4" S

D P

IP

E S

=0.005 M

IN

C1

C1

C2

C2

DERBY STREET

4

" S

D

P

IP

E

S

=

0

.0

0

5

M

IN

4'-6" 5'-6"2'-6"

2'-6"

C

L2

SEE NOTE 1,

THIS SHEET

SEE NOTE 1, THIS SHEET

2'-6"

EQ

.

EQ

.

C

L

EQ

.

EQ

.

C

L

LEGEND

SYMBOL DESCRIPTION

MATCHLINE - SEE LOWER LEFT

MATCHLINE - SEE UPPER RIGHT

C1

(E) COBBLE PAVERS - TO REMAIN. REINSTALL

ANY DISTURBED PAVERS TO MATCH EXISTING

(E) CURB - TO REMAINC2

(E) FINISH GRADE ELEVATION(FG 232.00)

PROPOSED FINISH GRADE ELEVATIONFG 232.00

(E) RIM ELEVATION(RE)

PROPOSED RIM ELEVATIONRE

PROPOSED INVERT ELEVATIONIE

CONNECT PROPOSED DRAINLINE TO

EXISTING DRAIN INLET. SEE SPECS.

NOTE:

1.

(E) SLOPE

PROPOSED SLOPE1.7%

(1.7%)

A

POWDER-COAT PAINTING

SCALE: NONE

Page 4: COB SPECIFICATION No. 16-11002-C CITY OF BERKELEY … · and pathway renovations city of berkeley cob specification no. 16-11002-c 2730 hillegass avenue berkeley, ca 94705 t1title

CONCRETE PAVING

SCALE: 1 1/2" = 1'-0"

AC PAVING

SCALE: 1" = 1'-0"

WOOD HEADER

SCALE: NONE

DRINKING FOUNTAIN

SCALE: 1"=1'-0"

BENCH

SCALE: AS NOTED

A

CATCH BASIN

SCALE: NONE

C D

E

B

F

REMOVABLE BOLLARD

SCALE: 1"=1'-0"

G

TIMBER EDGING AT TREE

SCALE: AS NOTED

H

COBBLESTONE PAVING

SCALE: 1 1/2"=1'-0"

I

F.1 - CURVED BENCH AT COBBLE SEATING AREA F.2 - RELOCATED BENCH

3/4"=1'-0"1"=1'-0"

Page 5: COB SPECIFICATION No. 16-11002-C CITY OF BERKELEY … · and pathway renovations city of berkeley cob specification no. 16-11002-c 2730 hillegass avenue berkeley, ca 94705 t1title

B

LAYOUT PLAN: PLAY AREA RUBBERIZED SURFACING

G

SCALE: 1"=10'-0"

SAND PLAY

E

PLAY AREA SURFACING:

SCALE: 3/4" = 1'-0"

F

PLAY AREA SURFACING:

POURED-IN-PLACE (P.I.P.) RUBBERIZED SURFACINGENGINEERED WOOD FIBER (EWF)

SCALE: 1 1/2" = 1'-0"

F.2 - SECTION: TRANSITION FROMF.1 - TYPICAL SECTION

P.I.P. TO EWF SURFACING

PLAY EQUIPMENT

SCALE: N.T.S.

DC

SCALE: 1"=10'-0"

LAYOUT PLAN: PLAY EQUIPMENT

R

E

F

E

R

E

N

C

E

L

I

N

E

R

E

F

E

R

E

N

C

E

L

I

N

E

SCALE: 1"=1/2'-0"

I

PLAY EQUIPMENT

FOOTING FOR ACOUSTIC PANELS,

CHITTER CHATTER NOODLE

J

PLAY EQUIPMENT

WEEVOS PLAY STRUCTURE

K

PLAY EQUIPMENT

BALANCE BEAM

A

PLAY AREA SUBGRADE PREPARATION

SCALE: 1"=10'-0"

H

PLAY AREA SURFACING: SAND

SCALE: 1 1/2"=1'-0"