coal to methanol senior design project final report
TRANSCRIPT
May 8, 2015
Ed Andjeski and Professor Speidel
Chemical Engineering Department
Drexel University
Philadelphia, PA 19104
Subject: Final Submission for Coal to Methanol Senior Design Project
Dear Mr. Andjeski,
Attached is the final design report on the production of methanol from coal. The pilot plant will
be located in Pittsburg, PA and will produce 835.4 lb/hr of 99.9% pure methanol. Waste
products include sulfur compounds, hydrogen, and unreacted syngas consisting of nitrogen,
methane, and trace amounts of hydrogen. The annual cost of manufacturing is $10.8 million and
the estimate for yearly production revenue is $1.8 million. Economic analysis demonstrates the
project is not feasible on the pilot plant scale.
Sincerely,
Group 3 - Coal to Methanol
Danielle Boccelli, Jacklyn Briguglio, Laura Ferguson, Kyle Mattson, Olivia Mustaro
Coal to Methanol
Danielle Boccelli, Jacklyn Briguglio, Laura Ferguson, Kyle Mattson, Olivia Mustaro
Team 3
Edward Andjeski
May 8, 2015
By signing this document, I acknowledge that work represented here is solely our Teamβs efforts
and no plagiarism has occurred in its preparation.
In partial fulfillment of the requirements for CHE 483: Process Design III, Department of
Chemical and Biological Engineering Drexel University, Philadelphia, PA 19104
CTM i
Drexel University, CHE 483
Completed By: Reviewed By:
Abstract
This coal-to-methanol project creates 99.9% pure methanol using coal as the raw material. Methanol is
a commodity chemical most commonly used as a precursor for the production of formaldehyde, which is
widely used in the construction industry. Energy production from coal has been viewed negatively in
recent years due to its negative impact on the environment compared to most other fuel sources.
Methanol is a cleaner product that has a variety of other uses such as, biodiesel, gasoline blending, and
dimethyl ether (DME) production. The goal of this study is to determine the feasibility of producing
methanol from coal.
Methanol has previously been synthesized using natural gas as the raw material, and this process is laid
out in a similar fashion. Raw coal is pulverized and fed into a gasification reactor, which breaks the coal
down into a gaseous mixture of compounds, called syngas. The syngas leaving the gasification unit
contains sulfur compounds found naturally in coal, which can harm some of the equipment
downstream. These naturally occurring sulfur compounds are stripped from the mixture using an amine
solution and absorption column. The sulfur compounds are then treated off-site. Finally, the clean
syngas mixture, made up of mostly CO and hydrogen, is sent into a synthesis reactor, which uses a
catalyst to produce the methanol. The methanol is then separated from the unreacted gases and stored,
while the waste gases are separated further into a pure hydrogen stream, which is put into a pipeline
and can be sold, and a waste gas stream that is sent to an air treatment plant off-site.
The plant is located in Pittsburgh, Pennsylvania. This was chosen because the grade of coal specified for
this process is a Pittsburgh-based bituminous coal with a high carbon content and fairly low sulfur
content. Having the plant close to the mine will cut down on transportation costs, and all coal will be
brought in by barge. All stream and equipment sizing calculations were done on a basis of 1,000 lb/hr of
coal fed to the process. This scale is small for commodity chemicals, which are usually produced in large
quantities to increase economic margins. The scale studied here is on the order of a pilot plant. This
scale was chosen due to limitations while using Aspen software to simulate the process.
From the 1,000 lb/hr of raw coal being fed to the process, 835.4 lb/hr of methanol is produced. As a
result, the annual revenue from sales after subtracting raw material costs is $1.45 million, and the
annual operating cost is $10.8 million. At this scale, the process is not profitable. One way to create
more revenue would be to increase production rate by at least a factor of ten; this would generate ten
times the amount of revenue if the price of methanol stays constant since it is a linear relationship. This
will also increase operating costs slightly, but they do not increase linearly with production rate since it
will not require ten times the equipment, energy, or labor to run a scaled up process.
CTM ii
Drexel University, CHE 483
Completed By: Reviewed By:
Executive Summary
The project is designed to convert bituminous coal into methanol. Burning coal for energy is on the
decline because it emits more pollutants than other forms of energy. Because of this, coal is a relatively
inexpensive feed (estimated at $0.031/lb). The cost of coal for one year of production at full rates of
1,000 lb/hour of coal into the system is $0.248 MM. Along with coal, steam ($0.015/lb) and oxygen
($0.03/lb) are also fed to the process at about 100 lb/hr each - this costs just over $34,000 per year. The
cost of the catalyst, which has a 5 year lifespan, was also added in to the material costs at $11.26/hr, or
$89,000/year.
Methanol is a cleaner and higher-value product than coal, and can be utilized in many industries. The
price of methanol is estimated at $0.20/lb, which would result in $1.33 MM/year in earnings. In
addition to methanol, the process also produces hydrogen ($0.03/lb), and slag ($0.53/lb), which could
both be sold for a combined total of $0.43 MM/year. The total annual revenue from sales after
subtracting raw material costs is $1.45 MM.
The foundation for the process (input material costs v. output material costs) shows that it is possible to
generate a profit using this process. However, the profit is not feasibly seen using such small scale
operations. This is because the annual cost of operating ($10.8MM/year) is much larger than the
production revenue. Annual revenue would increase linearly as long as the price of the materials are
stable - as production rates increase, earnings will continue to increase at the same rate until the market
is saturated. Manufacturing costs, on the other hand, are likely to increase at a diminishing rate as the
size of the plant increases; a plant running at ten times the scale would not require ten times the labor,
nor would the equipment require ten times the energy to run. Also, capital costs for equipment would
not increase linearly, although it is likely that more pieces of equipment would be needed.
Since the base case for the process was found to be unfeasible, building this plant would result in a net
loss that would increase over time. The capital cost, which was calculated to be $6.30MM, would never
be recovered. The main way this could be remedied, as mentioned previously, is to increase production
rates. Another way to increase process profitability would be to do a waste management study for the
process. Currently, waste treatment accounts for about one half of all manufacturing costs; this is
mainly due to the 1,000 lb/hr of hazardous, sulfur-containing waste coming from the amine
regeneration tower, SR-201. Of this waste stream, 94.4% is water. Clean water is required as makeup to
account for the loss from the tower. If this stream was reduced to 70 lb/hr, waste treatment would be
reduced to $0.44MM per year, resulting in a total yearly cost of manufacturing of $5.93MM; this would
also reduce the amount of pure water needed for the process. Reducing waste, in addition to increasing
production rates, would likely result in a profitable process.
.
CTM 1
Drexel University, CHE 483
Completed By: Reviewed By:
Table of Contents Abstract .......................................................................................................................................................... i
Executive Summary ....................................................................................................................................... ii
Report ........................................................................................................................................................... 3
Introduction .............................................................................................................................................. 3
Process Synthesis Discussion .................................................................................................................... 4
Process Description ................................................................................................................................... 5
Process and Equipment Design Discussion ............................................................................................... 9
Table 1: Equipment Sizing Summary ................................................................................................... 13
Operating Requirements......................................................................................................................... 16
Table 2: Utility Cost Basis ($/BTU) ...................................................................................................... 16
Table 3: Catalyst Requirements .......................................................................................................... 16
Environmental Concerns/Waste Minimization/Sustainability ............................................................... 17
Table 4: Sustainability Metrics ............................................................................................................ 19
Safety Considerations ............................................................................................................................. 21
Economic Feasibility for Base Case ......................................................................................................... 23
Figure 1: Cumulative Cash Flow ($MM) .............................................................................................. 23
Table 5: Economics Summary ............................................................................................................. 24
Table 6: Capital Cost............................................................................................................................ 25
Table 7: Cost of Labor Calculations ..................................................................................................... 26
Table 8: Utility Cost Basis ($/BTU) ...................................................................................................... 27
Table 9: Energy Balance and Utilities .................................................................................................. 28
Table 10: Waste Treatment Cost ........................................................................................................ 29
Table 11: Production Profits ............................................................................................................... 29
Economic Uncertainty and Sensitivity .................................................................................................... 30
Figure 2: Cost of Manufacturing v. Product Sale Price ....................................................................... 30
Process Optimization .............................................................................................................................. 31
Table 12: Gasification Optimization Study .......................................................................................... 31
Table 13: Sulfur Removal Optimization Study .................................................................................... 32
Table 14: Sustainability Metrics Comparison ...................................................................................... 33
Conclusions and Recommendations ....................................................................................................... 34
References .............................................................................................................................................. 35
CTM 2
Drexel University, CHE 483
Completed By: Reviewed By:
Appendix A: Process Design Details ............................................................................................................ 38
A. Process Flow Diagram ......................................................................................................................... 38
Appendix B: Material Balances ................................................................................................................... 39
Table B.1: Process Stream Table ......................................................................................................... 39
Table B.2: Material Balance ................................................................................................................ 40
Appendix C: Figures and Tables .................................................................................................................. 41
Table C.1: Chemical Component Properties Table ............................................................................. 41
Table C.2: Coal Properties ................................................................................................................... 41
Table C.3: Annual Cash Flow Summary ............................................................................................... 42
Table C.4: Material Costs in 2015 ....................................................................................................... 43
Table C.5 Sensitivity Analysis .............................................................................................................. 43
Appendix D: Plot Plan.................................................................................................................................. 44
Figure D.1: Plot Plan ............................................................................................................................ 44
Appendix E: Supporting Documentation .................................................................................................... 44
Report
CTM 3
Drexel University, CHE 483
Completed By: Reviewed By:
Introduction
The purpose of this project is to study the feasibility of operating a coal-to-methanol plant. Methanol is
a commodity chemical, commonly used in the production of formaldehyde, a chemical that is used in
the construction industry to produce adhesives for various construction board products. Demand for
formaldehyde production is heavily dependent on the construction industry, so a slowdown in
construction can reduce formaldehyde demand. The global demand for formaldehyde production from
methanol is expected to increase at a rate of 5% per year through 2018. It is also expected that other
end-uses of methanol will increase, such as demand in the fuel industry for products like biodiesel,
gasoline blending and dimethyl ether (DME) [1].
Methanol is typically produced from natural gas. The natural gas is first separated into a synthetic gas
(syngas) stream consisting of CO, CO2, water, and hydrogen. The second step is the catalytic synthesis of
methanol from the gas stream, which is a highly exothermic reaction. The energy created from the
synthesis is used to generate electricity for other sections of the process as needed [2].
This project will use a similar process, with the exception of using coal as the raw material as opposed to
natural gas. The coal will be gasified and separated into a syngas stream as described previously. The
syngas will then be treated with an amine solution to remove the sulfur compounds created as a result
of the naturally occurring sulfur in coal. Finally, the syngas will be reacted in the presence of a catalyst to
form methanol, then separated from the unreacted gas to obtain a high purity product. The reason for
choosing coal as the raw material is because coal is a dirty fuel source and the goal of the project is to
create a product that is useful and not as harmful to humans and the environment as coal.
CTM 4
Drexel University, CHE 483
Completed By: Reviewed By:
Process Synthesis Discussion
Gasification is the first major step in the process, where coal is broken down from a solid into a mixture
of gaseous compounds, called syngas. The syngas from the gasifier contains sulfur compounds, which
can damage equipment downstream, and therefore, must be removed. There were several alternatives
to using an amine stripper for the H2S treatment. However methyldiethanolamine (MDEA) is the most
effective at removing sulfur compounds for the type of coal used in this process, because it selectively
removes sulfur compounds in the presence of CO and CO2. A plug flow catalyst reactor was found to be
the most effective way of converting the syngas into methanol. This reactor was chosen because it is
most effective in terms of catalyst loading and conversion of syngas to methanol. The plant capacity is
1,000 lb/hr of raw coal entering the process.
For the Shell gasifier used as a basis for this project, the downtime (planned and unplanned) is usually
five weeks out of the year [3]. Based on this, the stream factor will be 0.904. Five weeks should be
ample time for cleaning and maintenance on all other pieces of equipment.
The raw materials required for this process are coal, oxygen, steam, and MDEA. The coal for this process
is a Pittsburgh-based bituminous coal, which has an elemental composition described in the component
property table in Appendix C Table 2. The oxygen needed for the gasification must be as pure as
possible, and this will be purchased from an outside company. An air processing unit was considered as
an alternate, but the capital cost outweighed the cost of buying pure oxygen from a supplier. Steam will
be generated on site. The MDEA required is a 30 mole% solution, which can be purchased in bulk [4].
The methanol product will have a purity of 99.9% by weight. The following assumptions were made in
designing this process:
β All stream and sizing calculations were done on the basis of 1,000 lb/hr of coal coming into the
process, with an additional 100 lb/hr each of oxygen and steam.
β The oxygen feed is pure oxygen.
β The MDEA is in a 30 mole% solution in water and has a total flow rate of 10,000 lb/hr.
β The coal is pulverized to 12 microns before it enters the gasification reactor.
β All initial economic calculations were done in terms of 2015 dollars, and then adjusted using an
inflation rate of 2.0% when analyzing the life of the project.
β The water flows for the utilities are approximated on a basis of 1,000 lb of steam or cooling
water per process piece for the water intensity portion of the sustainability metrics.
β The catalyst activity and lifespan of 3-5 years are approximated based on data found in
literature.
β The only reaction taking place inside the methanol reactor is the synthesis of methanol from
carbon monoxide.
β An air treatment plant is adjacent to the facility.
CTM 5
Drexel University, CHE 483
Completed By: Reviewed By:
Process Description
Please refer to drawing D-004 in Appendix A, the block flow diagram for the coal to methanol process
for an overall process description. Please refer to drawing D-001 for the gasification section, drawing D-
002 for the sulfur removal section, and drawing D-003 for the methanol reaction and separation
sections. A detailed stream table can be found in Appendix B Table 1.
The main feed into the process is pulverized coal; coal is received from a local Pittsburgh coal mine by
barge, where it is taken off the barge by conveyor CV-101 and sent into a pulverizer, CR-101. The
pulverizer crushes the coal to a 12 micron particle size. The coal then is fed through a filter, FT-101, to
sort out any large pieces that may disrupt the process, and in line 1003 is transported into the
pulverized coal holding tank, T-101. The coal in the tank is at ground level; using screw conveyer CV-103
and elevator, EV-102, the coal is elevated to the correct height, where it flows through another screw
conveyor, CV-106, in line 1006 which feeds the pulverized coal into the gasification reactor, R-101A/B.
The total feed rate of coal into the process is 1,000 lb/hr. Oxygen and steam are also fed into the
reactor. Oxygen, coming in in line 1009, is fed at a rate of 100 lb/hr at 500 Β°F and 350 psi. Steam, line
1007, is fed at 101 lb/hr at 350 psi and 1,000 Β°F. The total feed rate into the reactor is 1,200 lb/hr.
The gasification reaction between coal, steam, and oxygen occurs in the gasification R-101A/B. The
equations below show the chemistry of the reaction.
3πΆ + π2 + π»2π β π»2 + 3πΆπ
The carbon in the coal reacts with steam and oxygen in R-101A/B to produce syngas; syngas is a mixture
of carbon monoxide, carbon dioxide, hydrogen, water, and other organic compounds. Due to the
kinetics of the reaction, the syngas mixture is mostly carbon monoxide and hydrogen, and lower
concentrations of other components. This syngas mixture leaves R-101A/B at 1,200 lb/hr, 2900 Β°F and
350 psi in line 1015. Since this reaction takes place at high temperatures and pressures, the gasification
vessel is constructed of stainless steel with thick refractory lining. The reactor also has water-filled
membranes lining the walls; these membranes get coated with slag as the reaction takes place and
allow the slag to flow downwards, along the walls to the bottom of the reactor to be recovered. [5] The
slag leaves through line 1014, is slag. Slag is a glass-like product that results from the burning of metals
and coal at high temperatures.
From the gasification reactor, the syngas needs to be cooled with heat exchangers, and decompressed
with a turbine, then the sulfur impurities must be removed. First, the effluent syngas from R-101A/B is
put through a series of heat exchangers, HX-101A-C, to remove excess heat. The first heat exchanger in
the train, HX-101A reduces the temperature of the syngas from 2900 Β°F to 1,000 Β°F using high pressure
steam; the syngas leaves the exchanger in line 1018 at 1,000 Β°F. The next exchanger, HX-101B, uses low
pressure steam to cool the syngas further, to 330 Β°F on the outlet in line 1021. The final heat exchanger,
CTM 6
Drexel University, CHE 483
Completed By: Reviewed By:
HX-101C, cools the syngas to 120 Β°F using cooling water. The syngas leaves H-101A-C in line 1101 at 120
Β°F, 350 psi, and at the same flow rate as the feed to the exchanger, 1,200 lb/hr.
The Pittsburgh coal used in the process contains 3.86% sulfur, 2.23 % pyritic and 1.63% organic; sulfur
reacts in the gasification reactor to form hydrogen sulfide (H2S) carbon disulfide (CS2) and carbonyl
sulfide (COS). These sulfur compounds need to be removed for both safety and environmental reasons.
Hydrogen sulfide is toxic to humans at low concentrations and is harmful to the environment and
corrosive to steel, so it needs to be removed from the process as early as possible.
The sulfur removal tower, AB-201, removes the sulfur compounds through absorption with the amine
compound methyldiethanolamine, or MDEA. MDEA removes sulfur compounds, specifically hydrogen
sulfide, in the presence of carbon dioxide. A 30 mole% solution of MDEA in water is sufficient for the
level of sulfur removal required. First, P-201 pressurizes the ambient pressure MDEA to 350 psi, and is
fed at 10,000 lb/hr via line 1102 into heat exchanger HX-201 to heat it to the absorption temperature
from 70 Β°F to 80 Β°F in line 1105 using steam. The steam in line 1103 is 1,000 lb/hr at 307 Β°F and 75 psi
and leaves the exchanger in line 1104 at 224 Β°F at the absorption column feed pressure and flow rate.
In the tower, 10,000 lb/hr of the liquid MDEA solution, in line 1105, is fed above the top tray, tray
number 1, at 350 psi and 80 Β°F, and 1,201 lb/hr of the sour syngas, in line 1101 is fed above the bottom
tray, tray number 20, at 350 psi and 120 Β°F. The absorption of sulfur compounds into the amine solution
is a pseudo reaction, and the chemistry is shown below:
Two streams exit the sulfur removal tower, AB-201: a rich amine stream, line 1108, that contains the
MDEA along with the sulfur impurities, and a sweet gas stream, line 1106, that contains only syngas. The
rich amine stream flows at 10,057 lb/hr, at 89 Β°F and 350 psi. The sweet gas stream is 1,049 lb/hr, and is
at 80 Β°F and 350 psi.
The rich amine in line 1108 is then sent to a steam stripper, SR-201, to remove the sulfur compounds
present in the amine; steam will be used, via a reboiler, to strip the sulfur compounds, forcing the H2S
and other compounds out of the amine solution. First, the pressure of the rich amine stream is let down
using a pressure changing valve, V-201, from 350 psi to 22.7 psi in line 1109. Line 1109 then enters a
feed-effluent exchanger to heat the amine to the temperature needed to strip out the sulfur
compounds. The rich amine leaves the exchanger, HX-202, in line 1110 at 175 Β°F, 22.7 psi, and at 10,000
lb/hr. The stripper operates at 22.7 psi and 215 Β°F. The amine boils in the tower and the sulfur
CTM 7
Drexel University, CHE 483
Completed By: Reviewed By:
compounds separate and leave the stripper in the overhead gas stream 1119; line 1119 is 210 Β°F, 14.7
psi, and 1,000 lb/hr. The gaseous sulfur compound stream, in line 1119, will be separated and sent to a
sulfur treatment plant to recover elemental sulfur. The other stream leaving SR-201 is the lean MDEA
stream in line 1114; this stream consists of only MDEA and water. First, it is cooled in the feed-effluent
heat exchanger and then pumped and recycled back to the absorber tower AB-201 in line 1113; line
1113 is 123 Β°F, 350 psi, and 10,000 lb/hr. Regenerating and recycling the amine will reduce cost, as less
fresh amine will need to be fed into the process once the recycle occurs.
After the sweet syngas leaves the sulfur absorber section through line 1106, it passes to a knock-out
drum, KO-201, to remove any water that is present in the gas. Water containing some impurities will
leave the process in line 1121 at 80 Β°F and 350 psi, at 5 lb/hr. This water does potentially contain
impurities, so it will be sent to a water treatment facility to be treated and then returned to a local
water source.
Line 1201 leaving KO-201, contains dry syngas at 1,044 lb/hr, 80 Β°F and 350 psi. First, the gas is
compressed to 750 psi, then heated to 482 Β°F, which are the conditions under which the reaction takes
place. The syngas leaving the knockout drum goes into CP-301, the syngas compressor, which is driven
by turbine TB-301 using waste steam from HX-101A. The syngas leaving the compressor leaves in line
1202 at 261 Β°F, 725 psi, and at 1,044 lb/hr. Next, the syngas is heated to reaction temperature in heat
exchanger HX-301; this heat exchanger uses steam to heat the syngas. The syngas leaves the heat
exchanger in line 1210 at 330 Β°F and 725 psi, at 1,044 lb/hr. This resulting syngas is fed directly into the
methanol reactor, R-301A/B.
The syngas to methanol reaction takes place in reactor R-301A/B. In the reactor, carbon monoxide
reacts with hydrogen to form methanol in the presence of a copper/zinc/alumina catalyst. The reaction
takes place at 482 Β°F and 725 psi in and reaction chemistry is shown below.
πΆπ + 2π»2 β πΆπ»3ππ»
A copper/zinc/alumina catalyst is used to drive the reaction. The reactor is a plug flow reactor, with the
flow occurring vertically through the reactor with tubes between the beds to provide cooling on the
tube side. The catalyst used in the reaction becomes inactive above temperatures of 570 Β°F, so it is
important to have proper heat removal to avoid catalyst deactivation.
The syngas mixture in line 1210 enters reactor R-301A/B, where it is converted to methanol. Then,
methanol and unreacted gas leave the reactor in line 1211, which is 1,113 lb/hr of total flow, at a
pressure of 725 psi and 482 Β°F. The methanol contains a lot of impurities, so the final product has to be
purified before sale.
In order to do this, the reactor effluent must be cooled below the boiling point of methanol (148 Β°F).
Line 1211 enters the methanol heat exchanger, HX-302, which is cooled using cooling water, from the
CTM 8
Drexel University, CHE 483
Completed By: Reviewed By:
reaction temperature, and leaves in line 1205 at 102 Β°F and 725 psi. Line 1215 thus contains liquid
methanol and impurities; it flows into the methanol flash drum, FD-301, where the liquid methanol and
unreacted gas separate.
Two streams exit the methanol flash drum, FD-301: line 1216, and line 1217, which is 825 lb/hr of pure
methanol product. Line 1216 contains some methanol and unreacted gases; 137 lb/hr of this gas is
hydrogen and 9.5 lb/hr of methanol in the stream, both of which can be sold. To separate the methanol
and unreacted gases first, line 1217 is sent to a membrane filter, F-301, that selectively separates out
the hydrogen from the rest of the components of the stream. Leaving F-301 are two streams. Line 1221
contains 137 lb/hr of pure hydrogen at 80 Β°F and 725 psi, which is sold to a customer. Line 1218 contains
a mixture of methanol and unreacted gas. Line 1218 is fed to a flash drum, FD-302, that will further
separate the unreacted gas from the methanol. Line 1219 leaving FD-302 is a pure methanol steam at 80
Β°F, 725 psi, and 9.5 lb/hr; this stream combines with line 1217 to form line 1220. The other line leaving
FD-302 is line 1222, which is waste gas. This 71 lb/hr of waste gas can either be sent to a flare, or sent to
reactor R-301A/B to remove heat and control reaction temperature.
Line 1220 is the combined methanol product; 835.9 lb/hr of 99.98% pure methanol at 80 Β°F and 725 psi.
This methanol is sent to storage tanks, where it is held until final sale.
CTM 9
Drexel University, CHE 483
Completed By: Reviewed By:
Process and Equipment Design Discussion
R-101 Gasification Reactor
Pulverized coal with a 12 micron particle size is gasified using Shell Gasification technology, chosen for
its low maintenance costs, which are due to the robustness of the membrane wall gasifier and long
lifetime of coal burners [6]. The dried, pulverized coal is fed to the gasifier at a rate of 1,000 lb/hr. The
gasification reactor is 3.63 feet in diameter and 8 feet in length. Pre-heated oxygen (100 lb/hr at 500 Β°F
and 350 psi) and steam (101 lb/hr at 1,000 Β°F and 350 psi) are mixed and fed to the injector. Coal reacts
with oxygen and water to produce syngas at an operating temperature of 2,900 Β°F and pressure 350 psi.
The gasifier is lined with refractory material and equipped with an inner membrane wall consisting of
circulating water/steam-filled tubes. During operation, ash is converted into molten slag which flows
down the reactor where it solidifies and is removed [7].
HX-101 A/B/C Syngas Heat Exchangers
The hot syngas must be cooled from 2,900 Β°F before entering the sulfur removal unit that operates at
120 Β°F. This is done using three heat exchangers in series at 350 psi. The first exchanger has an area of
69.3 ft2 and uses high-pressure steam to reduce the temperature to 1,000 Β°F, the second has an area of
40.75 ft2 and uses low-pressure steam to reduce the temperature to 330 Β°F, and the third has an area of
34.5 ft2 and uses cooling water to reduce the temperature to 120 Β°F.
AB-201 Sulfur Absorption Column
Sulfur compounds must be removed from the syngas before methanol synthesis is attempted to avoid
poisoning the Cu/ZnO/Al2O3 catalyst in the methanol reactor. A sulfur removal unit operating at 350 psi
removes sulfur by absorbing it into a 30% methyldiethanolamine (MDEA) solution. MDEA selectively
absorbs H2S in the presence of CO2 at temperatures below 135 Β°F.
Lean MDEA solution is heated to 80 Β°F and fed at 10,000 lb/hr to the top tray of the column while the
sour syngas at 120 Β°F is fed at 1,107 lb/hr to the bottom tray. Sulfur is absorbed into the MDEA solution
as it passes over the sour syngas in the 0.93 foot diameter and 21 foot tall column. The rich MDEA
solution exits the bottom of the column at 10,057 lb/hr to a steam stripper that removes sulfur
compounds so the MDEA can be recycled. Sweet syngas exits the top of the column at 1,049 lb/hr.
SR-201 Steam Stripper
A stripper is required to remove the sulfur compounds present in the rich amine stream. Steam is used
to strip the sulfur compounds, forcing the H2S and other compounds out of the amine solution. The
stripper is 0.93 feet in diameter and 12 feet tall. The gaseous sulfur compound stream is sent to a sulfur
treatment plant to recover elemental sulfur and the lean MDEA is recycled back to the absorption
column.
KO-201 Water Knock Out Drum
CTM 10
Drexel University, CHE 483
Completed By: Reviewed By:
Excess water must be removed from the syngas to avoid catalyst deactivation in the methanol reactor. A
water knockout drum 1.84 feet in diameter and 5.53 feet in height is used to remove approximately
5lb/hr of water from the sulfur-free syngas. Dry syngas exits the drum at 1,044 lb/hr.
TB-301 Syngas Turbine
A 75 HP turbine is driven by the superheated steam produced in HX-101A at a flow rate of 9,041,724
lb/hr. The turbine drives the compressor, CP-301.
CP-301 Syngas Compressor
A 75 HP compressor is required to raise the pressure of the syngas leaving the sulfur absorption unit
from 350 psi to 725 psi before the syngas enters the methanol reactor. The temperature of the stream
leaving the compressor increases to 261 Β°F with compression.
HX-301 Methanol Reactor Heat Exchanger
A 3.34 ft2 steam heat exchanger is required to preheat the feed to the methanol reactor. Syngas enters
the heat exchanger at 261 Β°F and leaves at 330 Β°F.
R-301 Methanol Reactor
An Imperial Chemical Industries (ICI) low pressure reactor that operates at 482 Β°F and 725 psi is used to
react hydrogen and carbon monoxide to form methanol. It is modeled in Aspen as an adiabatic, shell
and tube, plug flow reactor using kinetic data deduced from the Langmuir-Hinshelwood rate equation
[7]:
To accommodate a feed of 1,000 lb/hr of pulverized coal, the reactor must be 10.23 feet in diameter
and 18 feet in length for a total reactor volume of 1,480 cubic feet.
The ICI reactor consists of 2,094 vertical tubes packed with catalyst that are surrounded by boiling
water. Catalyst is charged through manholes at the top of the reactor and gravity discharge of spent
catalyst permits rapid preparations for maintenance and recharging [8]. The total tube volume of 822 ft3
requires 33,876 lb of catalyst. Catalyst addition and withdrawal occurs during manufacturing downtime
[9].
A low-pressure Cu/ZnO/Al2O3 pellet catalyst, chosen for its high selectivity, stability and activity, is used
to drive the reaction of carbon monoxide and hydrogen to methanol [10]. The catalyst forms methanol
from carbon monoxide only at low levels of carbon dioxide, making it a good choice for the process since
the feed to the reactor is has trace levels of carbon dioxide. The proportions of the copper, zinc, and
alumina elements are >55% by weight, 21-25% by weight, and 8-10 % by weight, respectively, with a
standard size of 6 x 4 mm and optimal operating temperature and pressure ranges of 390-590 F and
CTM 11
Drexel University, CHE 483
Completed By: Reviewed By:
570-1175 psi. The most active catalysts have a high copper content while the Al2O3 interacts with the
supporting ZnO to improve methanol selectivity by reducing the potential for dimethyl ether formation
[11]. Catalyst poisoning can result from exposure to sulfur, halogens, and phosphorus containing
compounds from biomass and nickel carbonyls from reactor equipment. Poisoning by these compounds
results in site blocking or sintering, which yields decreased activity [12]. Commercial methanol synthesis
catalysts have lifetimes on the order of 3-5 years under normal operating conditions [11].
HX-302 Methanol Heat Exchanger
A 41.4 ft2 heat exchanger is required to cool the 1,044 lb/hr of methanol reactor effluent from 482 Β°F to
102 Β°F. The heat exchanger uses cooling water at 1,000 lb/hr. The effluent must be cooled to below the
boiling point of methanol (148 Β°F) to allow separation of the methanol and unreacted syngas in FD-301.
FD-301 Methanol Flash Drum
A flash drum 2.34 feet in diameter and 7 feet tall is required to separate the product methanol from the
unreacted gas. The drum operates at 725 psi and 80 Β°F allowing unreacted syngas to leave the top of the
drum at 218 lb/hr and 99.9% pure methanol to leave the bottom at 825.9 lb/hr.
The unreacted gas leaving the top of the drum passes through a hydrogen membrane filter, F-301. Pure
hydrogen leaves the filter at 137 lb/hr and is transported to the neighboring air plant through a
hydrogen pipeline.
FD-302 Waste Gas Recycle Flash Drum
A flash drum 0.75 feet in diameter and 2.2 feet tall is required to further separate and purify the
methanol from the filtered unreacted gas stream leaving F-301. 9.5 lb/hr of methanol leaves the bottom
of the drum and is combined with the product methanol stream, while the remaining unreacted gas at
71.3 lb/hr is returned the air plant for further processing.
Overall, 1,000 lb/hr of pulverized coal, 101 lb/hr of steam, and 100 lb/hr of oxygen results in a yield of
835.9 lb/hr of 99.9% pure methanol. Process byproducts include slag from the gasifier, sulfur
compounds stripped from the MDEA solution, water removed via knock-out drum, and unreacted waste
syngas from the flash drums. Once cooled, slag is can be marketed as a by-product for multiple
advantageous uses, which negates the need for long-term disposal plans. The profit costs and avoidance
of disposal costs combine to improve the economics of the disposition of slag [13]. Sulfur compounds
removed from the amine solution are hazardous to human health and the environment. Hydrogen
sulfide (H2S), carbon disulfide (CS2), and carbonyl sulfide (COS) will be reacted to form elemental sulfur
in an off-site sulfur treatment plant. The water removed from the knock out drum following the sulfur
removal unit contains traces of potentially harmful chemicals so it will be sent off-site to be treated by a
wastewater company before being released to the municipality.
In addition to the manufacturing area, a maintenance shop, central control room, and office space with
personnel facilities, such as a locker room and break room, are included in the plant. The maintenance
CTM 12
Drexel University, CHE 483
Completed By: Reviewed By:
shop will host the mechanics, welders, pipe fitters, etc. necessary for the process. A plot plan showing
the arrangement of the processing units and buildings within the plant is displayed in Appendix D.
Process equipment was sized using the simulation results in Aspen. Sample calculations can be found in
the calculations section and tabulated equipment sizes and specifications are summarized in Table 1 on
the next page.
CTM 13
Drexel University, CHE 483
Completed By: Reviewed By:
Table 1: Equipment Sizing Summary
Compressors MOC Compressor Type Power (HP) #Spares
CP-301 SS/SS Rotary 90 1
Drums MOC Height (ft) Diameter (ft) Pressure (psi)
FD-301 SS/SS 7 2.3 725
FD-302 SS/SS 2.3 0.8 725
KO-201 SS/SS 6 2 350
Exchangers MOC Type Pressure (psi) Area (ft2)
HX-101A T/T Double Pipe 350 20
HX-101B SS/SS Double Pipe 350 6
HX-101C SS/SS Double Pipe 350 19
HX-201 SS/SS Double Pipe 350 50
HX-202 SS/SS Multiple Pipe 350 170
HX-301 SS/SS Double Pipe 725 4
HX-302 SS/SS Double Pipe 725 41
Filters MOC Type Pressure (psi)
F-301 SS/SS Membrane 725
Miscellaneous MOC Type Length Power (HP)
CR-101 SS/SS 100 Mesh 60
CV-101 SS/SS Screw Conveyor 16 5
CV-102 SS/SS Screw Conveyor 16 5
CV-103 SS/SS Screw Conveyor 16 5
CV-106 SS/SS Screw Conveyor 16 5
BV-101 SS/SS Belt Conveyor 70 15
EV-101 SS/SS Elevator 50 15
EV-102 SS/SS Elevator 50 15
Pumps MOC Type Power (HP) Pressure Out (psi)
P-201 SS/SS Centrifugal 17 407
P-202 SS/SS Centrifugal 2 407
P-203 SS/SS Centrifugal 0.5 61
Reactors MOC Type Volume (ft3) # Spares
R-101 A/B SS/SS Combustion 100 1
R-301 A/B SS/SS Shell and Tube 1480 1
Storage Tanks MOC Type Volume (ft3)
T-101 SS/SS Fixed Roof 3900
T-401 SS/SS Fixed Roof 6684
T-402 SS/SS Fixed Roof 6684
T-403 SS/SS Fixed Roof 6684
Towers MOC Height (ft) Diameter (ft) # Trays
AB-201 SS/SS 21 1 21
SR-201 SS/SS 12 1 12
Turbines MOC Type Power (HP) # Spares
TB-301 SS/SS Axial 90 1
CTM 14
Drexel University, CHE 483
Completed By: Reviewed By:
Process Control Systems
A programmable logic controller (PLC) is used to control the flow rates of the four inlet streams entering
the gasification reactor (R-101). The PLC is connected to two flow controllers placed on the valves of the
inlet steam and oxygen streams. It is also connected to a speed controller attached to the motor of CV-
106, the screw conveyer entering the R-101. Additionally, the PLC is connected to a flow controller for
the inert nitrogen stream, which pressurizes the conveyer entering the reactor. The PLC adjusts the flow
rates of each stream to ensure that the correct ratio of pulverized coal, oxygen, and steam enters the
reactor at the required pressure.
A temperature controller is placed on the valve controlling the flow of an additional steam inlet stream
that is at a lower temperature than the steam reacting with the coal. The additional steam is used to
cool the reactor, since the reactions are exothermic, and the amount of steam required is based on the
temperature of the reactor. If the temperature in the reactor is too high, the additional steam will cool it
down. This temperature controller is vital for the safety of the process, since the gasification reactor is
already subject to high temperatures.
A level controller is placed on the valve controlling the flow of recycle amine from the stripper (SR-201)
to the absorber (AB-201). This will measure the liquid level inside the stripper column. If there is too
much liquid inside the stripper, then the valve will open further and allow more amine to be recycled to
the absorber. This control scheme will help prevent flooding inside the stripper.
A pressure controller is used on the knockout drum (KO-201) directly after the sulfur absorber. This
controller determines how far to open the valve that controls the flow of sulfur-free syngas to the
methanol synthesis section of the process. Higher pressure will result in more syngas flowing from the
knockout drum to the methanol synthesis section.
A flow controller is placed on the valve which controls the amount of sulfur going to the sulfur
treatment plant from the condenser (CD-201) attached to the stripper column. The controller will adjust
the valve depending on how much amine is being recycled into the stripper and how much sulfur is
being stripped from the amine. This will help prevent buildup of both sulfur and amine in the stripper.
A pressure controller is used on the compressor at the beginning of the methanol synthesis section of
the process (CP-301). The controller is also connected to the valve controlling the superheated steam
that drives the adjacent turbine (TB-301), which is being supplied by HX-101A. Additional steam will be
supplied to the turbine, which will provide more energy to the compressor in order to increase the
pressure of the syngas going into the methanol reactor (R-301). The compressor will pressurize the
syngas to 725 psi, which is the operating pressure of the methanol reactor.
A temperature controller is placed on HX-301, which is directly before the methanol reactor. The
exchanger will provide any additional heat that is needed using steam, since the methanol reaction must
CTM 15
Drexel University, CHE 483
Completed By: Reviewed By:
take place at 482β. The compressor will heat up the syngas while pressurizing it, so the amount of
additional heat needed will vary. The amount of steam needed will be determined using the
temperature controller.
A temperature and pressure controller is placed on the valve controlling the amount of steam going into
HX-302, which cools the stream leaving the methanol reactor. The steam flow rate will be adjusted
depending on how much cooling is required going from the methanol reactor to the first flash drum
separator (FD-301). The flash drum operates below the boiling point of methanol, so the waste gases
will go out the top and the methanol product will come out the bottom stream.
An additional temperature and pressure controller is placed on the valve that controls the amount of
boiler water going into R-301. The optimal temperature range for the catalyst is 390β-590β, and the
reaction occurring in R-301 is exothermic. Therefore, the cooling water will ensure that the temperature
of the reactor stays within the range where the catalyst is most effective. The amount of water needed
will depend on the temperature and pressure of the reactor, which will both increase as the reaction
goes to completion.
A pressure controller is placed on the valve controlling the flow of waste gas to the offsite air treatment
plant. If the pressure becomes too high leaving the second flash drum (FD-302) then a portion of the gas
will be redirected to the emergency flare. This will prevent buildup of pressure inside the flash drum and
will only be used in emergency situations.
CTM 16
Drexel University, CHE 483
Completed By: Reviewed By:
Operating Requirements
The plant will operate 47 weeks out of the year, 24 hours per day, with 5 weeks of down time. Planned
downtime was based off of Shell Coal Gasification Process (SCGP) plants in China, which typically
operate more than 300 days per year [3].
Utilities
Utilities consist of high pressure steam, low pressure steam, cooling water, and electricity. The cost per
BTU basis for each utility is summarized in the table below. The cost of utilities was calculated to be
$74.98 per hour.
Table 2: Utility Cost Basis ($/BTU)
Cooling Water 4.04E-07
fired heater 90% efficient 1.41E-05
HP Steam 2.02E-05
LP Steam 1.52E-05
Electric 1.92E-05
Labor Requirements
A total of 28 operating personnel will be employed at the plant and 6 employees are required per shift,
two for the gasification unit, two for the sulfur removal unit, and two for the methanol production unit.
Waste Streams
Waste treatment costs include disposal of sulfur-containing compounds from the sulfur removal unit
(hazardous), unreacted syngas from the flash drum (non-hazardous), and waste water from the knock-
out drum.
Catalyst Requirements
The catalyst requirements for the process are the Cu/ZnO/Al2O3 catalyst used in the methanol synthesis
reactor. The catalyst was assumed to have a lifetime of 3-5 years.
Table 3: Catalyst Requirements
# Tubes 2,094
Tube length 16 ft
Tube diameter 0.41 ft
Tube volume 822 ft3
Amount of cat 33,876.74 lb
CTM 17
Drexel University, CHE 483
Completed By: Reviewed By:
Environmental Concerns/Waste Minimization/Sustainability
This process creates several waste streams that contain hazardous products. The primary product,
methanol, is also a hazardous material.
Slag is a glass-like byproduct that is created when coal is heated at high temperatures. In this process,
Pittsburgh coal is heated to 2,900 Β°F in order to gasify it, and the metal compounds in the coal are
burned, creating slag. The molten slag flows out of the reactor, wand is pumped into a quenching tank
where it will solidify. These solid masses of slag will be pulverized to a standard particle size and sold.
Gasification slag is especially useful in industry due to its leachability characteristics, and can be sold to
various markets for use in asphalt, Portland cement, construction structural backfill, and many other
applications [13] [14]. The amount of slag produced cannot be minimized, so safety precautions are put
in place to ensure it is safely contained. Since the main concern with the slag is the high temperature, it
will be contained in insulated lines that keep the temperature under control and reduce the risk for
fires.
Hydrogen sulfide (H2S), carbon disulfide (CS2), and carbonyl sulfide (COS) are all created in the
gasification process. These compounds are dangerous and harmful to the environment. All of these
sulfur compounds leave the process directly in the waste stream coming from the amine regenerator.
This stream will be reclaimed and sent to a sulfur plant, which will react these compounds to form
elemental sulfur.
H2S is a combustible sulfur compound that is extremely hazardous to human health. It is characterized
by its rotten-egg odor at very low concentrations, however, it is not detectable by odor at toxic
concentrations (which are relatively moderate). Exposure to low concentrations of H2S has been linked
to human health effects, such as eye, skin, and respiratory irritation. Hydrogen sulfide is also corrosive
to metals. There need to be several lines of defense against H2S releases. First, all pieces of equipment
that are in H2S service need to be made of stainless steel to avoid corrosion; there also needs to be signs
in the area warning of H2S presence. Additionally, all personnel who work in areas where H2S can be
present must wear personal H2S monitors to ensure they are not exposed without their knowledge [15]
[16].
COS is a colorless, flammable gas identifiable by its unpleasant odor. When COS is in the presence of
humidity (as would be likely if a release occurred), it decomposes to carbon dioxide and hydrogen
sulfide. It is important to avoid the release of COS because if it does not decompose, it can cause serious
health effects to humans, such as convulsions and respiratory paralysis. Releases of COS will not cause
significant environmental effects [17].
CS2 is a colorless, volatile liquid. In humans and animals, CS2 is absorbed by the lungs and can result in
local irritation and pharyngitis and central nervous system effects; long term exposure results in
CTM 18
Drexel University, CHE 483
Completed By: Reviewed By:
neurological and cardiovascular effects. CS2 will evaporate from water and soil into the atmosphere,
and does not cause significant environmental effects [18].
There is no way, unfortunately, to reduce the production of sulfur compounds in the syngas; the sulfur
compounds are formed by the sulfur present in the coal, so the only possible way to reduce the
production of sulfur compounds would be to choose a different coal for feed stock that contained less
sulfur. The coal chosen is the best for the application, so it will not be changed to reduce the sulfur
compounds. Instead, there will be extra safety precautions taken to ensure proper handling of these
materials.
The sulfur gases will be sent to a sulfur plant, which will be purchased as a βstockβ unit, which will be
purchased as a fully functional unit on which no extra design is required, and placed on the plant
grounds close to the sulfur removal unit. The sulfur plant will process the sulfur gas in clause units and
produce an end product of elemental sulfur; this elemental sulfur will be sold as an additive to concrete
or sulfur enhanced fertilizers [19].
Syngas is reacted in the methanol reactor to form methanol, but there is some unreacted gas in the
product stream. This gas is recovered from the methanol and recycled into the reactor feed, to increase
total conversion and to decrease the waste stream amount. However, there are some components that
do not react in this gas stream, so there is a purge to avoid buildup of inert gases in the system. The
purge stream contains some greenhouse gases, such as carbon dioxide, and other dangerous gases like,
nitrogen. It is imperative that this gas stream is not released directly to the atmosphere, as it will give off
toxic emissions. The purge gas will first be sent through a carbon dioxide sequestering system to recover
carbon dioxide left in the stream. These units are produced and created by other companies, so it will be
purchased as a functioning unit and fit into the process; no design is needed in this section, as it is a
"stock" unit and will be purchased as a fully functional unit. Next, the purge gases will be sent to a flare
before releasing to the atmosphere to reduce toxic emissions [20].
Water is removed from this process after the sulfur removal step; this water must be treated as waste
water because it can contain traces of other harmful chemicals, and has the potential to be hazardous.
The waste water stream will be sent off-site to be treated by a local industrial waste water treatment
facility, such as a close-by refinery or chemical plant; the waste will not be able to be treated in a
municipal water treatment facility due to its contamination with amine and other compounds. This
water has the potential to contaminate groundwater under unusual circumstances, such as a line leak,
so there will be secondary containment around the waste water streams and holding tanks to avoid this
hazard. The amount of water created in the gasification step is minimized by carefully maintaining a
ratio coal:steam:oxygen ratio of 10:1:1. This reduces the amount of water formed while ensuring a
syngas composition high in hydrogen and carbon monoxide.
CTM 19
Drexel University, CHE 483
Completed By: Reviewed By:
There are many potential pollutants and hazardous chemicals present in this process, but the hazards
can be avoided by extra equipment and containment measures that reduce the chance of
environmental releases.
Table 4: Sustainability Metrics
Metric
Material Intensity 43.7 % (kg/kg)
Energy Intensity 43.37 MJ/kg
Water Intensity 12,105.88 kg/kg
Toxic Emissions 1.32 kg/kg
Greenhouse Gases 1.42 kg/kg
The first metric calculated was the Material Intensity, which investigates the amount of raw materials
the process uses and how it relates to the amount of product produced, in this case, methanol. Overall,
43.7% of our inputs are not manufactured into the final product. Of this 43.7% is either excess gas that is
being used elsewhere or is a waste product that must be removed from the process.
πππ‘πππππ πΌππ‘πππ ππ‘π¦ =πππ π ππ π ππ€ πππ‘ππππππ β πππ π ππ πππππ’ππ‘π
ππ’π‘ππ’π‘π
The second metric studied was the energy intensity. This metric examines amount of energy the process
needs to create a kilogram of methanol produced. Hot streams within the plant were used in heat
exchangers to recycle energy and help reduce the overall energy consumption.
πΈπππππ¦ πΌππ‘πππ ππ‘π¦ = πππ‘ πΉππ’π πΈπππππ¦ πΆπππ π’πππ (ππ½)
ππ’π‘ππ’π‘π
Water Intensity addresses the amount of fresh water used in the process. The fresh water accounts for
steam, cooling water, and general utilities water along with the water that goes into the process for the
gasification reaction. This number is very large due to the large amount of cooling that takes place after
the gasification reaction. There is also a constant loss of sulfur-containing water in the amine stripper
requiring constant renewal of that water.
πππ‘ππ πΌππ‘πππ ππ‘π¦ = πππ π ππ πΉπππ β πππ‘ππ πΆπππ π’πππ (ππ)
ππ’π‘ππ’π‘π
The metric for Toxic Releases measures the amount of toxic chemicals according to Environmental
Protection Agency's Toxic Release Inventory Chemical List for 2014. In this specific process, the
chemicals that are accounted for under the list are water (because it contains trace other chemicals and
has to be treated like toxic waste), carbonyl sulfide, hydrogen sulfide, carbon disulfide, ammonia, and
slag. The releases are combated by water treatment and the sulfur removal process.
CTM 20
Drexel University, CHE 483
Completed By: Reviewed By:
πππ₯ππ π πππππ π = πππ π ππ πππ₯ππ πππππ’π‘πππ‘π ππ πΈπππ π ππππ πππ πππ π‘π (ππ)
ππ’π‘ππ’π‘π
The final metric reviewed is Greenhouse Gas emissions which takes any emissions that are considered to
be greenhouse gases and relates them to carbon dioxide. The chemicals considered were carbon
dioxide, carbon monoxide, methane, and nitrogen dioxide. This section also takes into account the
carbon emissions from powering the plant.
πΊππππβππ’π π πΊππ ππ =πΆπ2 πΈππ’ππ£πππππ‘ ππππ πΉπ’ππ, πΈπππ π ππππ , πππ πππ π‘π (ππ)
ππ’π‘ππ’π‘π
CTM 21
Drexel University, CHE 483
Completed By: Reviewed By:
Safety Considerations
Within the gasification process, the temperature and pressure reach conditions that cause the coal to
partially combust. The coal increases the risk of explosion so it is crucial to ensure the oxygen level does
not exceed the flammable limit. The particle size of coal also creates an inhalation hazard. Workers in
this area should have inhalation PPE, such as respirators, to prevent exposure to coal dust [21].
Since reactor the gasification reactor receives a pure oxygen feed, it is important to ensure the oxygen
does not combust before entering the vessel. To combat this risk, oxygen will not be stored on site and
instead will be made at a separate plant then transported via pipeline on site. Oxygen is fed at the exact
rate it needs to be consumed, so that there is no accumulation of unreacted oxygen in the system. The
pipeline that feeds the oxygen will be fitted with explosion arrestors to prevent an explosion from
flowing back to the production plant; explosion arrestors are pieces of equipment that are composed of
smaller pipes, similar to the design of a heat exchanger, filled with mesh to help dissipate the flame
front and stop the explosion from propagating. Oxygen level sensors around the reactor ensure the air
around the reactor does not become oxygen rich.
The waste stream exiting leaving the gasifier contains molten slag, which contains many heavy metal
materials that need to be treated. A water bath below the gasifier collects the molten slag where it cools
it to a solid. Once the slag solidifies, it can be transported without releasing these dangerous materials.
The gasifier outlet stream contains carbon monoxide, carbon dioxide, water, hydrogen gas, and sulfur
compounds. Hydrogen gas makes up most of the syngas, creating a safety risk since hydrogen is highly
combustible in the presence of oxygen [22]. To prevent hydrogen leaks in this pipeline, there will be
limited welds in the pipeline, as well as sensors to monitor the hydrogen gas and carbon monoxide
concentration in the space surrounding the pipeline. To prevent fires, the surrounding pipeline will be
monitored for hydrogen leaks using hydrogen sensors. Carbon monoxide is an odorless and colorless
toxic gas, so sensors are needed to ensure the safety of the operators in the area around the process.
Carbon dioxide also has associated health risks at low concentrations so monitors will also need to be
installed. Since carbon dioxide is also an environmental risk, its treatment is also talked about in the
environmental section of this report.
The sulfur components that exit the gasifier are removed through an amine absorption column. In order
to avoid release of the sulfur compounds, limited welds between the gasifier and the sulfur removal
system. Sulfur is extremely corrosive and needs to be removed as soon as possible from the system to
reduce risk. Besides being corrosive, the biggest risk of the sulfur compounds is the toxicity of H2S. The
sulfur present in the coal forms H2S in the gasification reactor; H2S is extremely toxic at low
concentrations that are not detectable by odor. This area will need to be monitored with H2S sensors,
have posted signs warning of the possibility of H2S presence in the air, and the required PPE in this area
will include personal H2S sensors. The sulfur compounds are absorbed into the amine when the two
come into contact. The rich amine, containing the sulfur compounds, is then stripped with steam,
CTM 22
Drexel University, CHE 483
Completed By: Reviewed By:
leaving a stream of purely sulfur compounds. This stream will be sent to a sulfur plant to treat the gas
and produce elemental sulfur. Leaving the sulfur removal process, all that remains in the syngas is
carbon monoxide, carbon dioxide, water, which is removed immediately using a knock-out drum, and
hydrogen gas.
Methanol is created from the syngas in the methanol reactor unit. Methanol is a relatively harmless
chemical but it poses an explosion hazard, and it must be stored at away from potential spark sources
and at ambient temperatures. Methanol can easily flash if near an open flame. Methanol is a problem
when a large spill occurs overwhelming the surrounding area. Methanol easily breaks down in the
environment making it relatively benign environmentally, but is still a safety hazard.
Water and steam are used throughout the process as reactants and as a form of temperature control.
The water that is removed from the process will need to be treated in a wastewater treatment area to
remove any trace sulfur compounds, amines, or heavy metals. Waste water monitoring sensors will
allow for excess sulfur or heavy metal concentrations to be detected before they reach wastewater
treatment and allow for the plant to avoid fines associated with water treatment and impurities.
All the pieces of equipment that are needed to ensure the safety of the process will need to be put on a
maintenance schedule; a maintenance calendar prevents the plant from using emergency equipment to
continue production. When installed, the equipment will be evaluated for its criticality and proper
maintenance procedures will be attached to the appropriate equipment pieces.
CTM 23
Drexel University, CHE 483
Completed By: Reviewed By:
Economic Feasibility for Base Case
To determine if the plant would be profitable to build, the payout period, which is the number of years it
takes to turn a profit, is calculated by finding the time it takes for the plant to have a positive cumulative
cash flow. Cumulative cash flow is the total revenue generated by the products (methanol, hydrogen,
and slag), minus all of the costs of production, which include: capital costs (land, equipment, and startup
MDEA cost); manufacturing costs such as labor, utilities, waste treatment, and raw materials; taxes; and
depreciation. The tax rate and inflation rate were assumed to be 39.0% and 2.0% respectively, and
depreciation was assumed to be linear over an 11-year period, with a salvage rate of 10% of the initial
investment. The economic analysis covers a span of 17 years, from 2015-2031.
The grassroots capital cost of the project is $6.30 MM, and the yearly cost of manufacturing is $10.82
MM (2015); the breakdown for which can be seen in Table 5. The plant profits $1.76 MM per year
(2015) from sales. This means that at the current rates, the project would never be able to turn a profit.
The economic calculations include two years for construction, during which there is no revenue. A
cumulative cash flow diagram over the span of the project is shown below (Figure 1), and an exhaustive
account of the cash flow over time can be seen in Table C.3 of Appendix C.
Figure 1: Cumulative Cash Flow ($MM)
CTM 24
Drexel University, CHE 483
Completed By: Reviewed By:
Table 5: Economics Summary
Cost $/year
Capital Cost* $6,304,280
Cost of Labor $1,481,200
Cost of Utilities $581,271
Cost of Waste Treatment $4,423,270
Cost of Raw Materials $371,996
Cost of Manufacturing $10,833,336
Revenue ($/yr) $1,758,647
Payout Period (yr) N/A
*Total Capital Cost, not on yearly basis
Capital Cost All prices for equipment were based on the sizing information listed in Table 6 and were calculated using
CapCost, with the exception of the equipment listed in the Miscellaneous section of the table. The
equipment in the Miscellaneous section were not available in CapCost, and are based off of supplier
estimates found on J&M Industrialβs website. The total bare module cost for the equipment is $3.36
MM, and the total grassroots cost is $5.35 MM. Grassroots cost can be estimated as 1.6 times the bare
module cost [25].
In addition to equipment cost, the cost of land, and the cost of MDEA needed at start-up were also
added to the total capital cost. Land cost was estimated at $600,000, and the cost of MDEA was at
$9,000. Additional MDEA needed during production to make up for loss is accounted for in the raw
material costs.
CTM 25
Drexel University, CHE 483
Completed By: Reviewed By:
Table 6: Capital Cost
Compressors MOC Compressor Type Power (HP) #Spares Purchase Cost Bare Module Cost Grass Roots Cost
CP-301 SS/SS Rotary 90 1 $79,900 $402,000 $571,000
Drums MOC Height (ft) Diameter (ft) Pressure (psi) Purchase Cost Bare Module Cost Grass Roots Cost
FD-301 SS/SS 7 2.3 725 $3,630 $89,700 $108,000
FD-302 SS/SS 2.3 0.8 725 $2,470 $29,400 $36,000
KO-201 SS/SS 6 2 350 $4,540 $42,000 $606,000
Exchangers MOC Type Pressure (psi) Area (ft2) Purchase Cost Bare Module Cost Grass Roots Cost
HX-101A T/T Double Pipe 350 20 $3,270 $63,400 $80,000
HX-101B SS/SS Double Pipe 350 6 $2,780 $16,600 $24,200
HX-101C SS/SS Double Pipe 350 19 $3,230 $19,300 $28,100
HX-201 SS/SS Double Pipe 350 50 $4,040 $24,100 $35,100
HX-202 SS/SS Multiple Pipe 350 170 $7,090 $42,300 $61,600
HX-301 SS/SS Double Pipe 725 4 $2,780 $17,100 $24,800
HX-302 SS/SS Double Pipe 725 41 $3,870 $23,800 $34,500
Filters MOC Type Pressure (psi) Purchase Cost Bare Module Cost Grass Roots Cost
F-301 SS/SS Membrane 725 $190,000 $284,000 $430,000
Miscellaneous MOC Type Length Power (HP) Purchase Cost Bare Module Cost Grass Roots Cost
CR-101 SS/SS 100 60 $9,500 $9,500 $16,000
CV-101 SS/SS Screw Conveyor 16 5 $10,000 $10,000 $16,800
CV-102 SS/SS Screw Conveyor 16 5 $10,000 $10,000 $16,800
CV-103 SS/SS Screw Conveyor 16 5 $10,000 $10,000 $16,800
CV-106 SS/SS Screw Conveyor 16 5 $10,000 $10,000 $16,800
BV-101 SS/SS Belt Conveyor 70 15 $8,200 $8,200 $13,800
EV-101 SS/SS Elevator 50 15 $5,800 $5,800 $9,740
EV-102 SS/SS Elevator 50 15 $5,800 $5,800 $9,740
Pumps MOC Type Power (HP) Press,out (psi) Purchase Cost Bare Module Cost Grass Roots Cost
P-201 SS/SS Centrifugal 17 407 $10,900 $70,700 $101,000
P-202 SS/SS Centrifugal 2 407 $6,370 $41,400 $59,200
P-203 SS/SS Centrifugal 0.5 61 $6,170 $30,700 $46,200
Reactors MOC Type Volume (ft3) #Spares Purchase Cost Bare Module Cost Grass Roots Cost
R-101 A/B SS/SS Combustion 100 1 $186,900 $280,200 $424,000
R-301 A/B SS/SS Shell and Tube 1480 1 $85,400 $128,000 $194,000
Storage Tanks MOC Type Volume (ft3) Purchase Cost Bare Module Cost Grass Roots Cost
T-101 SS/SS Fixed Roof 3900 $55,300 $60,800 $102,000
TS-401 SS/SS Fixed Roof 6684 $62,500 $68,700 $115,000
TS-402 SS/SS Fixed Roof 6684 $62,500 $68,700 $115,000
TS-403 SS/SS Fixed Roof 6684 $62,500 $68,700 $115,000
Towers MOC Height (ft) Diameter (ft) # Trays Purchase Cost Bare Module Cost Grass Roots Cost
AB-201 SS/SS 21 1 21 $31,000 $414,000 $511,000
SR-201 SS/SS 12 1 12 $17,500 $46,400 $67,100
Turbines MOC Type Power (HP) #Spares Purchase Cost Bare Module Cost Grass Roots Cost
TB-301 SS/SS Axial 90 1 $189,000 $1,160,000 $1,690,000
Total $1,152,940 $3,561,300 $5,695,280
CTM 26
Drexel University, CHE 483
Completed By: Reviewed By:
Cost of Manufacturing The total cost of manufacturing (COM) was calculated using the equation below [25]:
πΆππ = 0.028 β πΆπππ + 2.73 β πΆππΏ + 1.23 β (πΆπ + πΆππ + πΆπ π)
In this equation, Ccap is the total capital cost, and COL, CU, CWT, and CRM are the costs of operating labor,
utilities, waste treatment, and raw materials, respectively. All of these costs were calculated for 2015,
and were adjusted by the inflation rate when looking at the profitability of the plant over its lifetime.
Cost of Operating Labor To calculate the cost of labor, the number of operators per shift (Nop/shift in Table 7) had to be
calculated using the equation below [25]:
πππ/π βπππ‘ = β6.29 + 31.7 β π2 + 0.23 β πππ
P, which the number of processing steps involving particulate solids, is 1 (for the handling of pulverized
coal). Nnp, the number of nonparticulate processing steps, is fifteen (two columns, two flash drum, two
reactors, one compressor, one turbine, and seven heat exchangers). Assuming the plant needs 6
operators per shift, and 4.5 operators for every one operator per shift, the total number of operators
came out to 28. Multiplying this by an average salary of $52,900 resulted in the total operating cost of
$1.48 MM per year (2015).
Table 7: Cost of Labor Calculations
Nnp 15
N_op/shift 6
N_op 28
Salary $52,900
Cost of Labor $1,481,200
CTM 27
Drexel University, CHE 483
Completed By: Reviewed By:
Cost of Utilities
The cost of utilities was estimated for most pieces of equipment using the heat duties for the equipment
from the Aspen models. This does not include pumps, and the items in the Miscellaneous section of the
capital cost table, which were calculated by converting the horsepower of the motor to BTU/hour, and
using this number to estimate electricity cost. Using these energies, utility costs for each piece of
equipment were calculated by multiplying the amount of energy needed by the cost of the basis utility
(electric, cooling water, etc.). Both heat duties and utility costs per hour of operation are listed in Table
9, and the price per BTU of energy for each basis utility (which come from Analysis, Synthesis, and
Design of Chemical Processes [25], and are adjusted to 2015 prices for inflation) are listed in Table 8.
Total cost per year for utilities $0.58 MM. This estimate only accounts for the utilities needed to run the
process, and does not account for auxiliary on-site buildings.
Table 8: Utility Cost Basis ($/BTU)
Cooling Water 4.04E-07
HP Steam 2.02E-05
LP Steam 1.52E-05
Electric 1.92E-05
CTM 28
Drexel University, CHE 483
Completed By: Reviewed By:
Table 9: Energy Balance and Utilities
Equipment Energy
In Energy
Out
HP Steam Cost
LP Steam Cost
Cooling Water Cost Electric
BTU/h BTU/h $/h $/h $/h $/h
AB-201 - - - - - -
BV-101 38,167 - - - - $0.73
CP-301 228,999 - $4.64 - - -
CR-101 152,666 - - - - $2.93
CV-101 12,722 - - - - $0.24
CV-102 12,722 - - - - $0.24
CV-103 12,722 - - - - $0.24
CV-106 12,722 - - - - $0.24
EV-101 38,167 - - - - $0.73
EV-102 38,167 - - - - $0.73
F-301 - 5,169 - - $0.10
FD-301 - 32,349 - - $0.01 -
FD-302 964 - - $0.02 - -
HX-101A - 2,998,346 $60.70 - - -
HX-101B - 212,383 - $5.31 - -
HX-101C - 262,355 - - $0.11 -
HX-201 84,819 - - - - -
HX-202 - - - - - -
HX-301 - - - - - -
HX-302 - 750,602 - - - -
KO-201 - - - - - -
P-201 43,510 - - - - $0.84
P-202 8,899 - - - - $0.17
P-203 1,272 - - - - $0.02
R-101A/B - - - - - -
R-301A/B - - - - - -
SR-201 - - - - - -
T-101 - - - - - -
T-401 - 228,999 - - - -
T-402 686,517 4,490,204 - - - -
T-403 - - - -
TB-301 - 228,999 -$4.64 - - -
Total $60.70 $5.33 $0.12 $7.24 $73.39
CTM 29
Drexel University, CHE 483
Completed By: Reviewed By:
Cost of Waste Treatment The cost of waste treatment was estimated by analyzing the streams exiting the process that do not
contain sellable product, which include: the sulfur waste stream (hazardous, 1115), the water stream
from the knock-out drum (waste water, 1121), and the waste gas stream after the separations (non-
hazardous, 1222). The cost of treating of these streams was based on information from Analysis,
Synthesis, and Design of Chemical Processes [25], and adjusted to account for inflation. The total waste
treatment cost per year is $4.42 MM, a breakdown for which can be seen in Table 10.
Table 10: Waste Treatment Cost
lb/h $/lb $/h
Disposal, hazardous 1,000.00 0.54 $540.90
Disposal, nonhazardous 71.73 0.02 $17.59
Water Treatment 4.00 0.000020 $0.0001
Total $558.49
Cost of Raw Materials The cost of raw materials was estimated by finding the price per pound of the raw material, and
multiplying by the total number of hours in operation. A few different sources were needed in order to
find prices for all of the materials. Table C.4 of Appendix C lists the price of the material as found in the
sources, a conversion of the found value to a per pound basis, and a final price in 2015 dollars. These
prices are then multiplied by the total amount of material required to get a total raw material cost of
$0.37 MM per year. (Table 11) Total revenue from the product streams is $1.76 MM per year.
The cost of catalyst is also included in these calculations. Since the catalyst has to be changed out every
five years or so, the cost of the total amount of catalyst needed in the methanol reactor is divided over
this time period to come up with a per hour cost.
Table 11: Production Profits
Unit Price Amount In Amount Out Total Profit
Material $/lb lb/h lb/h $/h
Coal $0.031 1,000 - (31.38)
Oxygen $0.03 100 - (2.80)
Steam* $0.015 101 - (1.54)
MDEA $0.897 0.00025 - (0.00)
Methanol $0.20 - 835.13 168.09
Slag $0.53 - 94.40 50.33
Hydrogen $0.03 - 137.20 3.63
Catalyst $11.65 0.967 - (11.26)
Total Hourly Production Profit $183
Total Yearly Production Profit $1,447,078
CTM 30
Drexel University, CHE 483
Completed By: Reviewed By:
Economic Uncertainty and Sensitivity
The project is not feasible because of the high operating costs, and pilot plant size of the process. Since
the base case for the project is not feasible, a sensitivity study was done to see how the price paid for
the products would have to change in order for the process to turn a profit over the life of the project.
This was done by varying sale price of the products (the initial cost of products, $0.21/lb, was found by
taking a weighted average of the prices of the three sellable products), and calculating the cost of
manufacturing that would result in a DCFROR of 0. This would mean, that although no profits were
earned, the project would at least break even.
Figure 2 shows a graph of cost of manufacturing v. sale price of the products, and Table C.5 of Appendix
C shows the data points that were plotted in this graph. In order for the process to break even at its
current operating costs, the price of the products would have to rise 750%, to $1.79/lb.
Figure 2: Cost of Manufacturing v. Product Sale Price
One of the major issues for the process is the cost of waste treatment. The sulfur removal section of the
plant produces about 1000 lb/hour of hazardous waste. That stream alone costs $4.28MM per year to
treat. The majority of this steam (94.4%) is water lost from the amine; clean water is later added back to
the process to account for this loss. If water loss was reduced, waste treatment costs for the year could
be reduced to $0.44MM per year, resulting in a total yearly cost of manufacturing of $5.93MM. This
would still be more than the plant makes in material revenue for the year, however, it would reduce the
break-even price of products to just over $1/lb ($1.004). This is still a 377% increase from where the
current prices are, but that is far less than the 750% increases needed for the base case cost of
manufacturing. Moreover, this decrease, coupled with an increase in production rates, would likely
make the process profitable overall.
The process produces materials that are of a higher value than the raw materials that go into it. Since
annual revenue would likely increase linearly, while manufacturing costs are likely to increase at a
decreasing rate as the size of the plant increases, it is probably that higher production rates would make
this process feasible.
CTM 31
Drexel University, CHE 483
Completed By: Reviewed By:
Process Optimization
The original process model had room for improvement. The process was on a small, pilot-plant scale;
commodity chemicals such as methanol are usually produced in large quantities to maximize profits. The
process also had multiple, large pressure changes throughout the different sections of the process;
these pressure changes necessitated extra equipment that increased capital and utility cost for the
process. There was also an undesirable mixture of syngas; the syngas contained carbon dioxide as well
as carbon monoxide, where it is most desirable in this process to only have carbon monoxide. These
shortcomings of the process decrease profitability and were analyzed to see if improvements and
process optimizations could be made.
Two process optimizations were done to improve the process performance and to save money on utility
and operation costs. The first was an optimization of the gasification reactor to increase the amount of
carbon monoxide produced and decrease the amounts of carbon dioxide produced. Carbon monoxide is
the desired reactant in the methanol reactor since it reacts with hydrogen in the presence of the catalyst
to form methanol. This reaction is efficient and produces the desired product with no by-products.
Carbon dioxide reacts undesirably to form methanol and water which are very difficult to separate, as
they have an azeotrope. The minimization of carbon dioxide, and consequently water, in the process
helps to simplify the separation of the methanol product and ensure a high product quality. Pinch point
analysis was done on the gasification Aspen file in order to find the correct ratio of feed components
and the correct temperature and pressure to create the desired syngas stream. The feed rate of steam
and water, the reaction temperature, and the reaction pressure were varied to find what resulted in the
most desirable syngas mixture. The table below shows the results.
Table 12: Gasification Optimization Study
Water Flow Oxygen Flow Temperature Pressure CO2 CH4 CO H2 O2 H2S
lb/hr lb/hr F psi lb/h lb/h lb/h lb/h lb/h lb/h
101 100 2,600 725 3.48 35.25 759.65 257.94 trace 61.67
51 100 2,600 725 1.53 67.97 703.76 245.52 trace 61.94
201 100 2,600 725 13.89 9.49 798.01 268.13 trace 61.99
101 50 2,600 725 1.40 73.02 695.04 249.91 trace 61.96
101 200 2,600 725 16.17 7.96 799.21 256.21 trace 61.96
101 100 2,500 725 5.00 42.91 745.32 255.11 trace 61.98
101 100 2,700 725 2.44 29.62 770.13 260.02 trace 61.94
101 100 2,600 350 1.39 22.24 783.66 262.79 trace 61.90
101 100 2,600 600 2.79 30.92 767.65 259.55 trace 61.95
101 100 2,900 350 0.39 16.52 794.18 264.91 trace 61.65
CTM 32
Drexel University, CHE 483
Completed By: Reviewed By:
It was found that feeding steam and water at 100 lb/hr into the reactor at 2,900 Β°F and 350 psi produces
a syngas stream with minimal carbon dioxide and maximum carbon monoxide; the carbon monoxide
content in the stream is 794 lb/hr while carbon dioxide is only 0.39 lb/hr. This ratio allows for full
conversion of the carbon monoxide into methanol with almost no production of water. The resultant
methanol stream can be purified to 99.98% methanol.
The second process optimization done was to increase the pressure of the sulfur removal section to
reduce the pressure changes throughout the process. Initially, the absorber column (AB-201) in the
sulfur removal section operated at atmospheric pressure. This meant that the system pressure, which
was 350 psi in the gasification section, would go from 350 psi to 14.7 psi, then back up to 725 psi in the
methanol section. To facilitate these pressure changes, there was a turbine to reduce the pressure from
350 psi to 14.7 psi before the sulfur removal section, and a compressor to increase the pressure after
the sulfur removal section from 14.7 psi to 725 psi. Compressors and turbines are both expensive pieces
of equipment that require a lot of utilities to operate; increasing the pressure would reduce the need for
this equipment. Pinch point analysis was used to understand how the increase in pressure would affect
the removal of sulfur. The pressure of the absorber column was incrementally stepped up to find the
optimum pressure for sulfur removal. The table below shows the results.
Table 13: Sulfur Removal Optimization Study
AB-201 Pressure Turbine Size H2S in Sweet Gas
psi HP lb/hr
14.7 102.8 7.51E-05
20 96.5 5.50E-05
50 74 3.03E-05
100 52.3 2.48E-05
200 25.8 2.27E-05
300 7.54 2.86E-05
350 0 2.25E-05
The removal of sulfur increased with increasing pressure, so it was decided to operate the sulfur
removal section at 350 psi. This removed the need for pressure reduction before the unit, and
minimized the size of the compressor needed to increase the system pressure before the methanol
reactor.
Unfortunately, the process could not be scaled up to a large-scale, commodity chemical sized operation
due to limitations of the Aspen software. Upon attempts to scale the process up by five and ten times,
the Aspen files would not converge to a solution; the software was unable to adequately scale up the
process. It is understood that this process is currently modeled as a pilot-sized plant and it is difficult to
CTM 33
Drexel University, CHE 483
Completed By: Reviewed By:
calculate how profitable the process would be if it were scaled up without a properly functioning model
in Aspen, as scaling is not linear, so there is no accurate way to predict the profits of the plant.
Table 14: Sustainability Metrics Comparison
Metric Previous Metrics Current Metrics
Material Intensity 58.80 % (kg/kg) 43.70 % (kg/kg)
Energy Intensity 116.51 MJ/kg 43.37 MJ/kg
Water Intensity 49.06 kg/kg 12,105.88 kg/kg
Toxic Emissions 0.33 kg/kg 1.32 kg/kg
Greenhouse Gases 2.15 kg/kg 1.42 kg/kg
Overall, the material, energy, and greenhouse gas sustainability metrics have improved due to the
optimization. The metric that changed the most drastically is the water intensity due to the changes in
the sulfur removal section. The amount of water needed to ensure proper removal of sulfur was not
correctly accounted for in the Interim report, and fixing this problems has caused it to increase greatly.
The problem with this large amount of water is that it contains sulfur and must be treated as toxic
waste. The sulfur impurities in the water can also explain why the toxic emissions metric has also
increased, as the sulfur compounds are toxic. With the optimization, all of the sulfur, along with other
toxic chemicals, are being removed and are accounted for in the toxic emissions metric.
CTM 34
Drexel University, CHE 483
Completed By: Reviewed By:
Conclusions and Recommendations
This feasibility study describes a process that uses bituminous coal as a raw material to create methanol.
On the basis of 1,000 lb/hr of coal processed, methanol is produced at a rate of 835 lb/hr with a purity
of 99.9% by weight. The grassroots capital cost is estimated to be $8.6 million. The yearly cost of
operation is estimated at $10.8 million, and the plant creates an annual revenue of $1.45 million. It can
be seen here that the plant is not profitable at the current capacity.
While not profitable, the methanol production process operates successfully and the technology could
be applied as a cleaner coal-to-fuel process.
There are a few ways to improve upon the profitability of the plant, the first being increasing the
production rate. If the plant were to be scaled up by at least a factor of ten, then the amount of revenue
generated would be ten-fold of what is currently being made, if methanol prices stay stable. However,
the cost of manufacturing would not increase ten-fold since it is not a linear relationship. A plant that is
ten times the size of the current capacity will not need ten times the labor required to run. Additionally,
the equipment would not need to be ten times as large if the process were scaled up, and would not
need ten times the amount of energy to run. Capital costs would also not increase linearly with scale up,
however it will still increase due to larger and more pieces of equipment. Finally, reducing waste is
another way to lower the cost of manufacturing. Currently, waste treatment of the sulfur compounds
accounts for about half of the total manufacturing costs. If the waste streams were decreased then the
cost of manufacturing would decrease, resulting in a higher possibility of the process becoming
profitable.
The result of this feasibility study is that this process as designed is not profitable and would result in a
net loss that increases over time. Increasing the plant production rate would increase product revenue
linearly while the equipment, energy, and labor costs would increase at a lower rate. Reducing waste
streams would also cut back the manufacturing costs significantly. It is for these reasons that most
commodity chemicals are produced on a much larger scale, because the economic margins increase as
the production rate increases, therefore is advantageous to manufacture as much product as possible.
CTM 35
Drexel University, CHE 483
Completed By: Reviewed By:
References
[1] Ihs.com, 'Methanol - Chemical Economics Handbook (CEH) | IHS', 2015. [Online]. Available: https://www.ihs.com/products/methanol-chemical-economics-handbook.html. [Accessed: 08- Mar- 2015].
[2] Methanol.org, 'How is Methanol Made? - Methanol Institute', 2015. [Online]. Available: http://www.methanol.org/methanol-basics/overview/how-is-methanol-made-.aspx. [Accessed: 08- Mar- 2015].
[3] CORNERSTONE MAG, 'The Shell Coal Gasification Process for Reliable Chemicals, Power, and Liquids Production', 2014. [Online]. Available: http://cornerstonemag.net/the-shell-coal-gasification-process-for-reliable-chemicals-power-and-liquids-production/. [Accessed: 08- Mar- 2015].
[4] Zauba.com, 'Export Data and Price of methyldiethanolamine bulk | Zauba', 2015. [Online]. Available: https://www.zauba.com/export-METHYLDIETHANOLAMINE+BULK-hs-code.html. [Accessed: 08- Mar- 2015].
[5] 2015. [Online]. Available: http://denr.sd.gov/Hyperion/Air/Ref/10%20Year%20Operating%20Experience%20Presentation.pdf. [Accessed: 08- Mar- 2015].
[6] 'Shell Coal Gasification Technology', 2015. [Online]. Available: http://w3.wtb.tue.nl/fileadmin/wtb/ct-pdfs/Energy_from_Biomass/Lecture_2011_gastcollege_Shell.pdf. [Accessed: 08- Mar- 2015].
[7] Netl.doe.gov, 'shell | netl.doe.gov', 2015. [Online]. Available: http://www.netl.doe.gov/research/coal/energy-systems/gasification/gasifipedia/shell. [Accessed: 08- Mar- 2015].
[8] K. Obareti, 'Kinetic Modelling and Reactor Design Methanol Synthesis 2013', ResearchGate, 2013. [Online]. Available: http://www.researchgate.net/publication/267777098_Kinetic_Modelling_and_Reactor_Design_Methanol_Synthesis_2013. [Accessed: 08- Mar- 2015].
[9] Google Books, 'Catalyst Deactivation 1991', 2015. [Online]. Available: https://books.google.com/books?id=773W71zqcQYC&pg=PA355&lpg=PA355&dq=catalyst+deactivation+in+methanol+reactor&source=bl&ots=DJmtwlNvA5&sig=NNS1nxiobGwilhY2BgIH6Ry7eMw&hl=en&sa=X&ei=CZDzVL2fNOmRsQTYqoKIBA&ved=0CCgQ6AEwAjgK#v=onepage&q=catalyst%20deactivation%20in%20methanol%20reactor&f=false. [Accessed: 08- Mar- 2015].
[10] Scholarworks.sjsu.edu, 2015. [Online]. Available: http://scholarworks.sjsu.edu/cgi/viewcontent.cgi?article=7695&context=etd_theses&sei-
CTM 36
Drexel University, CHE 483
Completed By: Reviewed By:
redir=1&referer=http%3A%2F%2Fwww.google.com%2Furl%3Fq%3Dhttp%253A%252F%252Fscholarworks.sjsu.edu%252Fcgi%252Fviewcontent.cgi%253Farticle%253D7695%2526context%253Detd_theses%26sa%3DD%26sntz%3D1%26usg%3DAFQjCNHZa9YidL7cJJZgUBnnkoSnAyCHVA#search=%22http%3A%2F%2Fscholarworks.sjsu.edu%2Fcgi%2Fviewcontent.cgi%3Farticle%3D7695%26context%3Detd_theses%22. [Accessed: 08- Mar- 2015].
[11] P. Spath and D. Dayton, 'Technical and Economic Assessment of Synthesis Gas to Fuels and Chemicals with Emphasis on the Potential for Biomass-Derived Syngas', 2015. [Online]. Available: http://www.nrel.gov/docs/fy04osti/34929.pdf. [Accessed: 08- Mar- 2015].
[12] M. Rep, R. Cornelissen and S. Clevers, 'Clean Hydrogen-rich Synthesis Gas', 2015. [Online]. Available: http://lnu.se/polopoly_fs/1.37212!Methanol%20Catalyst%20Poisons%20-%20A%20Literature%20Study%20(CCS).pdf. [Accessed: 08- Mar- 2015].
[13] Netl.doe.gov, 'slag-utilization | netl.doe.gov', 2015. [Online]. Available: http://www.netl.doe.gov/research/Coal/energy-systems/gasification/gasifipedia/slag-utilization. [Accessed: 08- Mar- 2015].
[14] Wikipedia, 'Slag', 2015. [Online]. Available: http://en.wikipedia.org/wiki/Slag. [Accessed: 08- Mar- 2015]. [15] Pubchem.ncbi.nlm.nih.gov, 'hydrogen sulfide | H2S - PubChem', 2015. [Online]. Available: http://pubchem.ncbi.nlm.nih.gov/compound/402?from=summary#section=2D-Structure. [Accessed: 08- Mar- 2015].
[16] Wikipedia, 'Hydrogen sulfide', 2015. [Online]. Available: http://en.wikipedia.org/wiki/Hydrogen_sulfide. [Accessed: 08- Mar- 2015].
[17] [2] Epa.gov, 2015. [Online]. Available: http://www.epa.gov/chemfact/s_carbns.txt. [Accessed: 08- Mar- 2015].
[18] Epa.gov, 2015. [Online]. Available: http://www.epa.gov/chemfact/s_carbds.txt. [Accessed: 08- Mar- 2015].
[19] Hydrocarbon Engineering, 2015. [Online]. Available: http://sulvaris.com/wp-content/uploads/2013/01/Cope-Calm-Before-The-Storm.pdf. [Accessed: 08- Mar- 2015].
[20] Wikipedia, 'Gas flare', 2015. [Online]. Available: http://en.wikipedia.org/wiki/Gas_flare. [Accessed: 08- Mar- 2015].
[21] 'Recommended Health and Safety Guidelines for Coal Gasification Pilot Plants', 2015. [Online]. Available: http://nepis.epa.gov/Exe/ZyPDF.cgi/9100Q6H7.PDF?Dockey=9100Q6H7.PDF. [Accessed: 08- Mar- 2015].
CTM 37
Drexel University, CHE 483
Completed By: Reviewed By:
[22] 'Hydrogen Safety', 2015. [Online]. Available: http://www.arhab.org/pdfs/h2_safety_fsheet.pdf. [Accessed: 08- Mar- 2015]. [23] Eia.gov, 'Coal News and Markets - Energy Information Administration', 2015. [Online]. Available: http://www.eia.gov/coal/news_markets/index.cfm. [Accessed: 08- Mar- 2015].
[24] S. Katell and P. Wellman, 'An Evaluation of Tonnage Oxygen Plants', Bureau of Mines US Department of the Interior, 2015.
[25] Turton, Richard; Baille, Richard; Whiting, Wallace; Shaelwitz, Joseph. Analysis, Synthesis, and Design of Chemical Processes, 3rd Edition. Upper Saddle River, NJ. PTR. [Print]
[26] Zauba.com, 'Export Data and Price of methyldiethanolamine bulk | Zauba', 2015. [Online]. Available: https://www.zauba.com/export-METHYLDIETHANOLAMINE+BULK-hs-code.html. [Accessed: 08- Mar- 2015].
[27] Methanex.com, βBusiness Pricingβ, 2015. [Online]. Available: https://www.methanex.com/our-business/pricing/. [Accessed: 08- April- 2015].
[28] Grainger.com, 'GRAINGER APPROVED Blast Media,Coal Slag,20/40 Grit - Pneumatic Blasting Media - 6YY28|6YY28 - Grainger Industrial Supply', 2015. [Online]. Available: http://www.grainger.com/product/GRAINGER-APPROVED-Blast-Media-6YY28. [Accessed: 08- Mar- 2015]. [29] Icis.com, 'Chemicals A-Z', 2015. [Online]. Available: http://www.icis.com/resources/news/2005/12/08/190713/chemical-profile-hydrogen/ [Accessed: 08- Mar- 2015]. [30] April 2015 Quote from Haldor Topsoe Inc.
CTM 38
Drexel University, CHE 483
Completed By: Reviewed By:
Appendix A: Process Design Details
A. Process Flow Diagram
CTM 39
Drexel University, CHE 483
Completed By: Reviewed By:
Appendix B: Material Balances Table B.1: Process Stream Table
Str
ea
mD
esc
rip
tio
nT
em
pe
ratu
reP
ress
ure
Ma
ss F
low
Str
ea
mD
esc
rip
tio
nT
em
pe
ratu
reP
ress
ure
Ma
ss F
low
Fp
silb
/hF
psi
lb/h
1001
Raw
Coal from
Barg
e70
15
1,0
00
1114
Lean M
DE
A fro
m S
R-2
01
215
14.7
9,0
57
1002
Pulv
erized C
oal from
CR
-101
70
15
1,0
00
1115
H2S
Ric
h G
as fro
m S
R-2
01
210
14.7
3,0
00
1003
Pulv
erized C
oal to
T-1
01
70
15
1,0
00
1116
Cool G
as t
o C
D-2
01
--
3,0
00
1004
Pulv
erized C
oal to
EV
-102
70
15
1,0
00
1117
Coolin
g W
ate
r75
14.7
-
1005
Pulv
erized C
oal F
eed t
o R
-101A
/B70
15
1,0
00
1118
Coolin
g W
ate
r R
etu
rn100
14.7
-
1006
350 p
sig
Ste
am
1,0
00
350
101
1119
Condensed R
eflu
x-
-2,0
00
1007
Ste
am
Feed t
o R
-101A
/B1,0
00
350
100
1120
Coole
d G
as fro
m S
R-2
01
--
1,0
00
1008
Oxygen
500
350
100
1121
H2S
Ric
h G
as t
o S
ulfu
r P
lant
210
14.7
1,0
00
1009
Oxygen F
eed t
o R
-101A
/B500
350
100
1122
Reflu
x t
o S
R-2
01
--
2,0
00
1010
Nitro
gen
70
350
50
1123
SR
-201 C
ool R
eboil
Str
eam
180
37.7
-
1011
Nitro
gen t
o D
rive
CV
-106
70
350
50
1124
SR
-201 H
ot
Reboil
Str
eam
220
37.7
-
1012
Ste
am
435
350
-1125
Low
Pre
ssure
Ste
am
250
16.0
-
1013
Ste
am
to Q
uench R
-101A
/B435
350
-1226
Low
Pre
ssure
Ste
am
Retu
rn230
16.0
-
1014
Sla
g2,9
00
350
94
1127
SR
-101 R
eboil
Retu
rn220
37.7
-
1015
R-1
01A
/B E
ffluent
Syngas
2,9
00
350
1,1
07
1128
Wate
r from
KO
-201
80
350
5
1016
Hig
h P
ressure
Ste
am
490
400
9,0
41,7
24
1201
H2S
-Fre
e,
Wate
r-F
ree S
yngas t
o C
P-3
01
80
350
1,0
44
1017
Superh
eate
d S
team
Retu
rn600
1,5
00
9,0
41,7
24
1202
Com
pre
ssed S
yngas
261
725
1,0
44
1018
HX-1
01A
Effl
uent
Syngas
1,0
00
350
1,1
07
1203
Superh
eate
d S
team
600
1,5
00
9,0
41,7
24
1019
Low
Pre
ssure
Ste
am
250
16
791,1
51
1204
Superh
eate
d S
team
to D
rive
TB
-301
600
1,5
00
9,0
41,7
24
1020
Low
Pre
ssure
Ste
am
Retu
rn300
55
791,1
51
1205
Ste
am
Retu
rn600
--
1021
HX-1
01B
Effl
uent
Syngas
330
350
1,1
07
1206
CP
-301 D
rive
600
--
1022
Coolin
g W
ate
r75
15
15,8
02
1207
Ste
am
505
715
1,0
00
1023
Coolin
g W
ate
r R
etu
rn100
15
15,8
02
1208
Ste
am
to H
X-3
01
505
715
1,0
00
1101
AB
-101 F
eed S
yngas (
H2S
)120
350
1,1
07
1209
Ste
am
Retu
rn370
715
1,0
00
1102
Lean M
DE
A S
upply
70
350
10,0
00
1210
Syngas F
eed t
o R
-301A
/B330
725
1,0
44
1103
Low
Pre
ssure
Ste
am
307
75
1,0
00
1211
R-2
02A
/B E
ffluent
482
725
1,0
44
1104
Low
Pre
ssure
Ste
am
Retu
rn224
75
1,0
00
1212
Coolin
g W
ate
r70
15
1,0
00
1105
Lean M
DE
A F
eed t
o A
B-2
01
80
350
10,0
00
1213
Coolin
g W
ate
r to
HX-3
02
70
15
1,0
00
1106
H2S
-Fre
e S
yngas
80
350
1,0
49
1214
Coolin
g W
ate
r R
etu
rn129
15
1,0
00
1107
H2S
-Fre
e,
Wate
r-F
ree S
yngas
80
350
1,0
44
1215
Cool R
-202A
/B E
ffluent
to F
D-3
01
102
725
1,0
44
1108
Ric
h M
DE
A fro
m A
B-2
01
89
350
10,0
57
1216
Unre
acte
d G
ases fro
m F
D-3
01
80
725
218
1109
Low
Pre
ssure
Ric
h M
DE
A t
o H
X-2
02
89
22.7
10,0
57
1217
Meth
anol P
roduct
from
FD
-301
80
725
825.9
1110
Hot
Ric
h M
DE
A t
o S
R-2
01
175
22.7
10,0
57
1218
Bott
om
s fro
m F
-301
80
725
81
1111
Low
Pre
ssure
Lean M
DE
A215
14.7
10,0
57
1219
Meth
anol P
roduct
from
FD
-302
80
725
9.5
1112
Makeup W
ate
r to
MD
EA
215
14.7
943
1220
Pure
Meth
anol P
roduct
80
725
835.4
1113
Hig
h P
ressure
Recycle
MD
EA
123
350
10,0
00
1221
Pure
Hydro
gen t
o P
ipelin
e80
725
137
1222
Waste
Gas t
o A
ir P
lant
80
725
71
Ta
ble
1:
Pro
ce
ss S
tre
am
Ta
ble
CTM 40
Drexel University, CHE 483
Completed By: Reviewed By:
Table B.2: Material Balance
CTM 41
Drexel University, CHE 483
Completed By: Reviewed By:
Appendix C: Figures and Tables
Table C.1: Chemical Component Properties Table
Component MW NBP,Β°F Freeze Point,
Β°F
Water
solubility
(g/L)
Flash Point,
Β°F Flammability
Safety
Hazards
Ammonia (NH3) 17 -28 -108 31% (w/w) N/A Flammable Toxic by
Inhalation
Carbon Dioxide (CO2) 44 -71 -108 1.45 N/A Non-flammable Greenhouse
Gas
Carbon Disulfide (CS2) 76 115 -169 2.17 -45 Highly Flammable
Skin, Eye,
and
Inhalation
Irritant
Carbon Monoxide (CO) 28 -313 -337 0.028 -312 Highly Flammable Carbon
Monoxide
Poisoning
Carbonyl Sulfide (COS) 60 -58 -218 1.25 N/A Flammable Acute
Toxicity
Elemental C 12 ~8700 ~6300 Insoluble N/A Flammable
Black
Carbon
Irritates
Respiratory
System
Elemental H 1 -423 -435 Insoluble N/A Highly Flammable Asphyxiant
When Pure Elemental O 16 -297 -362 0.015 N/A Non-flammable None
Elemental S 32.1 832 239 Insoluble 168-188 Highly Flammable Irritates
Respiratory
System Hydrogen Disulfide
(H2S) 34.1 -76 -116 4 -116 Highly Flammable
Major Injury
or Death Methane (CH4) 16 -259 -296 0.023 -306 Highly Flammable Asphyxiant
Methanol (MeOH) 32 149 -144 53 Flammable Highly Toxic
Methyl Diethanol Amine
(MDEA) 119 477 -6 Miscible 261
Flammable (with
Aluminum) Skin and Eye
Irritation
Sulfuric Acid (H2SO4) 98.1 639 50 Miscible N/A Non-flammable Highly
Corrosive Water (H20) 18 212 32 - N/A Non-flammable None
Table C.2: Coal Properties
Coal Name Coal Type Moisture and Mineral-Matter Free Basis Moisture-Free Basis
% Carbon % Hydrogen % Nitrogen % Oxygen % Pyritic S % Sulfate S
Pittsburgh (DECS-23) High Volatile A
Bituminous 84.64 5.82 1.54 8.00 2.23 0.01
Coal Name Coal Type
Percentage Moisture Moisture-Free Basis
Received Equilibrium % Ash % Volatile
Matter % Fixed Carbon
Pittsburgh (DECS-23) High Volatile A
Bituminous 2.00 2.50 9.44 39.42 51.14
CTM 42
Drexel University, CHE 483
Completed By: Reviewed By:
Ta
ble C.3: Annual Cash Flow Summary
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
12
34
56
78
910
11
12
13
14
15
16
17
Sa
les,
lb
s (M
M)
6.6
16.6
16.6
16.6
16.6
16.6
16.6
16.6
16.6
16.6
16.6
16.6
16.6
16.6
16.6
1
Pri
ce
, n
et
$/l
b0.2
10.2
10.2
10.2
10.2
10.2
20.2
20.2
30.2
30.2
40.2
40.2
50.2
50.2
60.2
60.2
70.2
7
Re
ve
nu
e (
$M
M)
1.3
91.3
91.4
21.4
51.4
71.5
01.5
31.5
61.6
01.6
31.6
61.6
91.7
31.7
61.8
0
Fix
ed
Co
st (
$M
M)
11.2
611.4
811.7
111.9
512.1
912.4
312.6
812.9
313.1
913.4
513.7
214.0
014.2
814.5
614.8
5
Fix
ed
In
ve
stm
en
t ($
MM
)1.1
34.5
46.3
06.3
06.3
06.3
06.3
06.3
06.3
06.3
06.3
06.3
06.3
06.3
06.3
06.3
06.3
0
De
pre
cia
tio
n0.5
70.5
70.5
70.5
70.5
70.5
70.5
70.5
70.5
70.5
70.5
70.6
3
Gro
ss P
rofi
t-1
0.4
4-1
0.6
7-1
0.8
7-1
1.0
7-1
1.2
8-1
1.5
0-1
1.7
2-1
1.9
4-1
2.1
7-1
2.4
0-1
2.6
4-1
2.3
0-1
2.5
5-1
2.8
0-1
3.6
9
Ta
xe
s (3
9%
)-4
.07
-4.1
6-4
.24
-4.3
2-4
.40
-4.4
8-4
.57
-4.6
6-4
.75
-4.8
4-4
.93
-4.8
0-4
.89
-4.9
9-5
.34
Aft
er
Ta
x P
rofi
t-6
.37
-6.5
1-6
.63
-6.7
6-6
.88
-7.0
1-7
.15
-7.2
8-7
.42
-7.5
6-7
.71
-7.5
1-7
.66
-7.8
1-8
.35
AT
Ca
sh F
low
($M
M)
-1.1
3-3
.40
-7.5
6-5
.93
-6.0
6-6
.18
-6.3
1-6
.44
-6.5
7-6
.71
-6.8
5-6
.99
-7.1
3-7
.51
-7.6
6-7
.81
-7.7
2
Cu
m.
Ca
sh F
low
($M
M)
-1.1
3-4
.54
-12.1
0-1
8.0
3-2
4.0
9-3
0.2
7-3
6.5
8-4
3.0
2-4
9.6
0-5
6.3
1-6
3.1
5-7
0.1
5-7
7.2
8-8
4.7
8-9
2.4
4-1
00.2
5-1
07.9
7
PW
Fa
cto
r0.8
90.8
00.7
10.6
40.5
70.5
10.4
50.4
00.3
60.3
20.2
90.2
60.2
30.2
00.1
80.1
60.1
5
An
nu
al
PW
($M
M)
-1.0
1-2
.71
-5.3
8-3
.77
-3.4
4-3
.13
-2.8
5-2
.60
-2.3
7-2
.16
-1.9
7-1
.79
-1.6
4-1
.54
-1.4
0-1
.27
-1.1
2
Cu
mu
lati
ve
PW
($M
M)
-7.0
0-1
0.0
0-1
5.0
0-1
9.0
0-2
3.0
0-2
6.0
0-2
9.0
0-3
1.0
0-3
4.0
0-3
6.0
0-3
8.0
0-3
9.0
0-4
1.0
0-4
3.0
0-4
4.0
0-4
5.0
0-4
6.0
0
Ta
ble
C.3
: A
nn
ua
l C
ash
Flo
w S
um
ma
ry
CTM 43
Drexel University, CHE 483
Completed By: Reviewed By:
Table C.4: Material Costs in 2015
Material Price Basis Price per lb Year of Data Average Inflation 2015 Price
Coal [23] $62.75 per short ton $0.031 2015 0 $0.031
Oxygen [24] $55.90 per short ton $0.028 2015 0 $0.028
Steam [25] $29.97 per 1,000 kg $0.01359 2008 1.61% $0.015
MDEA [26] $38,823.36 per 19,800 kg $0.89 2014 0.80% $0.90
Methanol [27] $1.33 per gallon $0.20 2015 0.00% $0.20
Slag [28] $42.65 per 80 lb $0.53 2015 0 $0.53
Hydrogen [29] $2.15 per scf $0.02 2005 1.91% $0.03
Catalyst [30] $800.00 per ft3 $11.65 2015 0 $11.65
Table C.5 Sensitivity Analysis
COM Sale Price % Increase, Sale Price
0.983 0.21 0
1.048 0.221 5
1.31 0.263 25
1.638 0.315 50
2.293 0.42 100
3.603 0.63 200
6.224 1.05 400
10.81 1.79 750
14.09 2.31 1000
CTM 44
Drexel University, CHE 483
Completed By: Reviewed By:
Appendix D: Plot Plan
Figure D.1: Plot Plan