clyde waterfront - clydeside/dalmuir study
DESCRIPTION
Glasgow and Clyde Valley Green Network PartnershipTRANSCRIPT
final draft report prepared by erz Limited
issued March 2011
client group:
West Dunbartonshire Council
Clyde Waterfront Partnership
Glasgow & Clyde Valley Green Network Partnership
clydeside / dalmuirclyde waterfront green network strategy
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
executive summary
introduction
1.0 analysis
2.0 area wide strategy
3.0 area specific proposals
4.0 outline costs
5.0 action plan
list of consultees
p. 5
p. 6
p. 7
p. 17
p. 19
p. 30
p. 45
p. 48
contents:
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
5
executive summary:
The study includes a focused analysis of the immediate study area and identifies the key gaps in the green network and the opportunities that exist to form the missing links.
The breaks in the network are well recognised and have been the subject of previous study work.
A review of historic plans of the urban structure highlight prec-edents for linkages from the urban area to the waterfront.
Proposals have been developed to form the missing links and to deliver a coherent, legible network that realises continuous ac-cess along the Clyde waterfront and links to the Forth and Clyde canal route and further north to Dalmuir park.
The proposals include works that can (subject to funding) be directly implemented and others where delivery may be longer term and subject to redevelopment of particular sites.
Perhaps the core project identified is that focused on Clydeside Community Park and the Golden Jubilee Hospital site. This project forms missing links, but also redefines and brings into active use the expansive under used area of the existing park and hospital grounds.
This rejuvenation and expansion of the existing currently isolat-ed public park to form part of a wider, connected, green net-work delivers significant benefits on both a wider network and neighbourhood level.
Outline costs are provided for all of the proposed works.
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
6
erz Limited were appointed by the Glasgow and Clyde Valley Green Network Partnership, on behalf of the wider client group, to undertake the study focused on Clydeside Community Park as a priority project within the Clyde Waterfront Green Network, in December 2010.
The client group is comprised of the Glasgow and Clyde Valley Green Network Partnership, the Clyde Waterfront Partnership and West Dunbartonshire Council.
erz Limited have led the study, with support from Applied Ecology Limited and Armour construction consultants.
Applied Ecology Limited undertook an ecological scoping of the study area to highlight relevant issues and to inform the proposals. The ecological scoping report was completed in February 2011.
Armour construction consultants prepared outline costings for the proposals, which are included toward the end of this report.
Work on the study began in mid December 2010 and the first draft report was issued in mid March 2011. The final draft report was issued at the end of March 2011.
erz Limited21 James Morrison StreetGlasgowG1 5PETel: 0141-552 0888www.erzstudio.co.uk
introduction:
Geographic Analysis and Strategy Proposals
1.0 analysis
2.0 area wide strategy
3.0 area specific proposals
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
8
1.0 analysis: urban structure
a. urban structure:
- the urban structure in the study area is dominated by broadly east-west orientated transport routes: rail, road and canal. The Forth & Clyde canal towpath offers the main spine of the existing path network. The east- west transport routes however present barriers to north- south movement.
core paths
public buildings
retail / commercial
industrial / infrastructure
Dalmuir rail station
0m 100m 200m 500m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
9
b. existing open space:- The existing open space in the study area currently takes the form of a series of isolated/distinct spaces, with limited off street linkages. There is also extensive un- used or underused space, including: vacant/derelict space along the southern edge of the canal and the Golden Jubilee hospital grounds which currently have no formalised public acess.
1.0 analysis: existing open space
1.
2.
3.
Golden Jubilee hospital grounds (currently no formalised access)
vacant/ derilict space
Dalmuir allotment site
Dalmuir park - (1)
Clydeside Community Park (Beardmore Park) - (2)
‘Clyde Gate’ public plaza - (3)
0m 100m 200m 500m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
10
1.0 analysis: existing network analysis
c. existing network analysis:
- There are significant and obvious missing links in the current green network. Notably the Clyde waterfront route is blocked by lack of access through the hospital site and there are missing north-south links through Clydeside Community park & along the Duntocher Burn.
1.
2.
3.
3.
Forth and Clyde canal towpath
Clyde waterfront walkway
on street links
(1)) - missing link thro’ hospital grounds
(2) - missing link thro’ Clydeside Community Park (river to canal)
(3) - missing link along Duntocher Burn (canal to park and canal to river)
0m 100m 200m 500m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
11
d. historic plan 1857:- A review of historic mapped information for the study area reveals that the original 'street' link from Dalmuir to the Clyde (Dalmuir Shore) ran to the immediate eastern edge of the current Clydeside Community park.
1.0 analysis: historic plan 1857
original street access to Clyde (‘Dalmuir Shore’) - (1)
1.
old quay
current extent of Clydeside Community Park
0m 100m 200m 500m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
12
1.0 analysis: historic plan 1958
e. historic plan 1958:
- Industrial development along the waterfront interupted the original street access to the Clyde waterfront. This route is still evident however in the line of the dock formed in this area (which was infilled and underlies the current Clydeside Community park and western edge of the hospital site).
1.
2.
current extent of Clydeside Community Park
original street access to Clyde interupted by industrial development
0m 100m 200m 500m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
13
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
14
1.0 analysis: Clydeside Community Park:
f. Clydeside community park:
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
15
g. Duntocher Burn & waterfront:
1.0 : analysis: Duntocher Burn & waterfront:
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
16
2.0 area wide strategy: concept / links
a. concept/links:
- The missing links in the network are clearly identified. The historic axial route along the eastern edge of Clydeside Community park offers a clarity of approach to the link between the Clyde waterfront and the canal.
(1) - public waterfront route thro’ hospital site(2) - reinstate historic axial route from canal to waterfront thro’ expanded park(3) - community green space at canal node(4) - off-street route along Duntocher Burn from canal to Dalmuir park(5) - Duntocher Burn link to waterfront
1.
2.
3.
4.
5.
0m 100m 200m 500m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
17
b. overview:
2.0 : area wide strategy: overview
0m 100m 200m 500m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
18
3.0 area specific proposals: Golden Jubilee Hospital waterfront
a. Golden Jubilee Hospital waterfront:
- The waterfront route through the hospital site depends on the formation of 2 missing links: 1. the route to the perimeter of the helipad in the eastern portion of the site and 2. the short link to tie in to the existing route to the west. The mid section of the route already exists in the form of the existing hospital path network.
1. ‘Clyde Gate’ public plaza2. new public footpath formed around helipad (forms link to east)3. existing waterfront path within hospital grounds4. new public footpath link and fence removal (forms link to west)5. Clydeside Community Park
1.
2.
3.
4.
5.
2.
0m 100m50m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
19
b. Clydeside Community Park:- The main axial route is proposed following the historic waterfront link. This strongly expressed feature forms a legible route and stitches the currently incoherent site together. It is proposed that the current park is extended and enhanced.
3.0 area specific proposals: Clydeside Community Park
main axial route: re-establishment of historic waterfront link - (1)enhanced public realm space at waterfront node - (2)
enhanced park waterfront & facilities (play, pitches etc.) - (3)expanded woodland belt - (4)
wildflower meadow - (5)
community woodland - (6)community growing space - (7)
signage/markers - (8)architectural opportunity for axial landmark building - (9)
1.
2.
3.
4.
5.
6.
3.
8.
7.
9.
0m 50m 100m 200m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
20
3.0 area specific proposals: Clydeside Community Park - phase 1
c. Clydeside: phase 1
- It is proposed that the first phase of implementation work should be focused on delivering the main axial route and associated features, including the waterfront node and community growing space.
(1) - main axial route: re-establishment of historic waterfront link(2) - enhanced public realm space at waterfront node(3) - community growing space
1.
2.
3.
architectural oppertunity
double avenue tree planting
paths
raised beds
shelter / storage / rain water collection
secure fence
enhanced public realm space
road crossing
signage / markers
potential future pavillion building
0m 50m 100m 200m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
21
d. Clydeside - phase 2:- The next phase of implementation works focus on connecting path links and wider tree/woodland structure planting.
3.0 area specific proposals: Clydeside Community Park - phase 2
1. expanded woodland belt2. path links across parkland3. community woodland4. community orchard5. signage / markers
1.
2.
3.
4.
5.
fruit trees / community orchard
woodland creation
removal of existing brick wall
removal ofexisting boundary fence
0m 50m 100m 200m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
22
3.0 area specific proposals: Clydeside Community Park - phases 3 & 4
e. Clydeside - phases 3 & 4:
- It is proposed that phase 3 of implementation works is focused on enhancement of the waterfront and facilities within the expanded Clydeside community park. The final phase of works are focused on extending the park space north to meet the canal. This will require acquisition and site clearance works.
1. enhanced park waterfront 2. enhanced park facilities (play, pitches etc.)3. extension of park to canal (acquisition & clearance)
1.
2.
3.
enhanced park facilities facilities
developed edge to waterfront
suggested housing layout
area for park extension
signage / markers
0m 50m 100m 200m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
23
f. Clydeside Community Park:- full scheme
3.0 area specific proposals: Clydeside Community Park
0m 50m 100m 200m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
24
3.0 area specific proposals: Clydeside Community Park - sections
g. Clydeside - sections:
- The sections clearly demonstrate the change in scale and character that results from the proposed interventions. A more human scale is brought to both the parkland and the hospital grounds/parking area.
Clydeside Community Park / Golden Jubilee Hospital: existing section:
Clydeside Community Park / Golden Jubilee Hospital: proposed section:
Clydeside Community Park open grassland within hospital site hospital car park
expanded tree belt planting improved park space hospital car parkmain axial route
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
25
h. Clydeside Community Park:
3.0 area specific proposals: Clydeside Community Park - sections
Clydeside Community Park: main axial route - proposed section:
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
26
3.0 area specific proposals: Duntocher Burn link (north)
g. Duntocher Burn link (north):- This section of the Duntocher Burn link is compromised by east-west transport routes and development surrounding the burn. The southern portion of this route is accordingly identified as a longer term aspirational link subject to redevelopment of the adjacent school site.
1. existing sign posted on street route2. proposed signage/markers3. aspirational off-street link along Duntocher burn: delivered thro’ future redevelopment4. proposed light controlled pedestrian crossing (subject to 3)5. resurfacing of path route along Duntocher burn & new access from main road6. resurfacing & wider environmental improvements to route parallel to rail line7. improvements / redevelopment of underpass
1.
2.
3.
4.
5.6.
7.
0m 50m 100m 200m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
27
h. Duntocher Burn link (south)- The section of the Duntocher Burn link between the canal and the river is fairly consistent along its length. The formalised path route being located to the west side of the burn running closely parallel to the perimeter fence of the adjacent storage site.
3.0 area specific proposals: Duntocher Burn link (south)
1. proposed signage/marker2. path formalised: 3m wide gravel path3. management & interplanting of existing tree/scrub vegetation4. retained edge & handrail at constricted section5. tie into extension of waterfront route
1.
2.
3.4.
5.
0m 50m 100m 200m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
28
a. secure perimeter fence (expamet or similar)b. communal fruit growing bedsc. meeting/storage buildingd. main entrancee. vehicular service access & secondary entrance
3.0 area specific proposals: canal / Duntocher Burn node
i. canal / Duntocher Burn node:
- The vacant/dis-used open space between the Duntocher Burn and the recently constructed flats on the south side of the canal offers a great opportunity to introduce new community facilities (growing space proposed), to enhance habitat around the burn and to emphasise the route to the waterfront along Beardmore Way.
1.
2.
4.
3.
1. proposed community woodland2. formalised path link to river3. proposed community growing/allotment site (enclosed)4. management & inter-planting of woodland along derelict rail line
e.
d.
c.
b.a.
a.a.
20 no. 15m x 10m allotment plots
community orchard
axial route aligned with Beardmore way
grass slope and hedgerow
community woodland
management & planting of woodland around Duntocher Burn
signage / marker for waterfront route
bulk storage
0m 50m 100m 200m
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
29
j. clyde walkway - west:- to the west of the meeting of the Duntocher Burn link and the Clyde waterfront, the path route will continue. Although not within the scope of this study, the plan above identifies an indicative route to the west and associated costs are included in the outline costing later in the document, to help inform decision making.
3.0 area specific proposals: Clyde walkway west
1.
2.
canal towpath
local parks
potential clyde walkway
link thru' Clydeside Community Park
Duntocher burn link (south)
Duntocher burn link (north)
Titan Crane Clydebank - (1)
Erskine bridge + historic ferry slip road - (2)
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
30
Outline Costings
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
31
outline costings: Hospital Link ( helipad area)Option 1
Alterations
Removal of existing fence including removal off site
generally 1.00 item @ 150.00 150.00
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 906.00 m2 @ 6.50 5,889.00
extra; breaking out existing hard
pavings 192.00 m2 @ 5.00 960.00
Marshalls or equal paving on and including 50 thick
dry mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 906.00 m2 @ 75.00 67,950.00
Marshalls or equal kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 568.00 m @ 25.00 14,200.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,428.00 nr @ 2.00 2,856.00
Post and wire fence to beech hedge 204.00 m @ 6.00 1,224.00
Mulching; 50 thick
generally 102.00 m2 @ 2.00 204.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 25,000.00 25,000.00
118,433.00£
Option 1
Alterations
Removal of existing fence including removal off site
generally 1.00 item @ 150.00 150.00
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 906.00 m2 @ 6.50 5,889.00
extra; breaking out existing hard
pavings 192.00 m2 @ 5.00 960.00
Marshalls or equal paving on and including 50 thick
dry mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 906.00 m2 @ 75.00 67,950.00
Marshalls or equal kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 568.00 m @ 25.00 14,200.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,428.00 nr @ 2.00 2,856.00
Post and wire fence to beech hedge 204.00 m @ 6.00 1,224.00
Mulching; 50 thick
generally 102.00 m2 @ 2.00 204.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 25,000.00 25,000.00
118,433.00£
Option 2
Alterations
Removal of existing fence including removal off site
generally 1.00 item @ 150.00 150.00
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 906.00 m2 @ 6.50 5,889.00
extra; breaking out existing hard
pavings 192.00 m2 @ 5.00 960.00
Natural stone paving on and including 50 thick dry
mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 906.00 m2 @ 225.00 203,850.00
Natural stone stone kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 568.00 m @ 50.00 28,400.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,428.00 nr @ 2.00 2,856.00
Post and wire fence to beech hedge 204.00 m @ 6.00 1,224.00
Mulching; 50 thick
generally 102.00 m2 @ 2.00 204.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 30,000.00 30,000.00
273,533.00£
Option 2
Alterations
Removal of existing fence including removal off site
generally 1.00 item @ 150.00 150.00
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 906.00 m2 @ 6.50 5,889.00
extra; breaking out existing hard
pavings 192.00 m2 @ 5.00 960.00
Natural stone paving on and including 50 thick dry
mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 906.00 m2 @ 225.00 203,850.00
Natural stone stone kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 568.00 m @ 50.00 28,400.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,428.00 nr @ 2.00 2,856.00
Post and wire fence to beech hedge 204.00 m @ 6.00 1,224.00
Mulching; 50 thick
generally 102.00 m2 @ 2.00 204.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 30,000.00 30,000.00
273,533.00£
Option 2
Alterations
Removal of existing fence including removal off site
generally 1.00 item @ 150.00 150.00
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 906.00 m2 @ 6.50 5,889.00
extra; breaking out existing hard
pavings 192.00 m2 @ 5.00 960.00
Natural stone paving on and including 50 thick dry
mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 906.00 m2 @ 225.00 203,850.00
Natural stone stone kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 568.00 m @ 50.00 28,400.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,428.00 nr @ 2.00 2,856.00
Post and wire fence to beech hedge 204.00 m @ 6.00 1,224.00
Mulching; 50 thick
generally 102.00 m2 @ 2.00 204.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 30,000.00 30,000.00
273,533.00£
As per option 1 with enhanced specification to surfaces:
118,433.00£ SUB TOTAL
273,533.00£ SUB TOTAL
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
32
outline costings: Clydeside Community ParkPhase 1: Option 1
Growing Beds
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,089.00 m2 @ 6.50 7,078.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 637.00 m2 @ 25.00 15,925.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 294.00 m @ 10.00 2,940.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 624.00 m2 @ 200.00 124,800.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 624.00 m2 @ 17.50 10,920.00
Beach hedge 616.00 nr @ 2.00 1,232.00
Post and wire fence to beech hedge 88.00 m @ 6.00 528.00
Mulching; 50 thick
generally 44.00 m2 @ 2.00 88.00
163,511.50£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Fencing
Expamet fast track fencing including associated posts
and foundations
generally 190.00 m @ 100.00 19,000.00
extra over for 1200mm wide gate 1.00 nr @ 750.00 750.00
19,750.00£
Tree Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,698.00 m2 @ 6.50 11,037.00
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 1,698.00 m2 @ 25.00 42,450.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 712.00 m @ 10.00 7,120.00
Street lighting including trench excavation, removal
of material off site, cabling and ducting; setting
columns in concrete foundations
generally 30.00 nr @ 1,500.00 45,000.00
Wildflower/british seed mix; grading and preparing
existing soil
generally 14,520.00 m2 @ 1.00 14,520.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soill inprover;
clean stone drainage layer, stakes etc
generally 146 nr @ 550.00 80,300.00
200,427.00£
Hard Paving Etc
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 1,216.00 m2 @ 6.50 7,904.00
Marshalls or equal paving on and including 50 thick
dry mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 1,216.00 m2 @ 75.00 91,200.00
Marshalls or equal kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 342.00 m @ 25.00 8,550.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
Allowance only for road crossings
generally 1.00 item @ 15,000.00 15,000.00
127,154.00£
Pavilion/Café
Allowance only for the provision of a Pavilion/Café
Building
generally 96.00 m2 @ 750.00 72,000.00
72,000.00£
Phase 1: Option 1
Growing Beds
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,089.00 m2 @ 6.50 7,078.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 637.00 m2 @ 25.00 15,925.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 294.00 m @ 10.00 2,940.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 624.00 m2 @ 200.00 124,800.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 624.00 m2 @ 17.50 10,920.00
Beach hedge 616.00 nr @ 2.00 1,232.00
Post and wire fence to beech hedge 88.00 m @ 6.00 528.00
Mulching; 50 thick
generally 44.00 m2 @ 2.00 88.00
163,511.50£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Fencing
Expamet fast track fencing including associated posts
and foundations
generally 190.00 m @ 100.00 19,000.00
extra over for 1200mm wide gate 1.00 nr @ 750.00 750.00
19,750.00£
Tree Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,698.00 m2 @ 6.50 11,037.00
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 1,698.00 m2 @ 25.00 42,450.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 712.00 m @ 10.00 7,120.00
Street lighting including trench excavation, removal
of material off site, cabling and ducting; setting
columns in concrete foundations
generally 30.00 nr @ 1,500.00 45,000.00
Wildflower/british seed mix; grading and preparing
existing soil
generally 14,520.00 m2 @ 1.00 14,520.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soill inprover;
clean stone drainage layer, stakes etc
generally 146 nr @ 550.00 80,300.00
200,427.00£
Hard Paving Etc
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 1,216.00 m2 @ 6.50 7,904.00
Marshalls or equal paving on and including 50 thick
dry mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 1,216.00 m2 @ 75.00 91,200.00
Marshalls or equal kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 342.00 m @ 25.00 8,550.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
Allowance only for road crossings
generally 1.00 item @ 15,000.00 15,000.00
127,154.00£
Pavilion/Café
Allowance only for the provision of a Pavilion/Café
Building
generally 96.00 m2 @ 750.00 72,000.00
72,000.00£
Phase 1: Option 1
Growing Beds
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,089.00 m2 @ 6.50 7,078.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 637.00 m2 @ 25.00 15,925.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 294.00 m @ 10.00 2,940.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 624.00 m2 @ 200.00 124,800.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 624.00 m2 @ 17.50 10,920.00
Beach hedge 616.00 nr @ 2.00 1,232.00
Post and wire fence to beech hedge 88.00 m @ 6.00 528.00
Mulching; 50 thick
generally 44.00 m2 @ 2.00 88.00
163,511.50£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Fencing
Expamet fast track fencing including associated posts
and foundations
generally 190.00 m @ 100.00 19,000.00
extra over for 1200mm wide gate 1.00 nr @ 750.00 750.00
19,750.00£
Tree Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,698.00 m2 @ 6.50 11,037.00
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 1,698.00 m2 @ 25.00 42,450.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 712.00 m @ 10.00 7,120.00
Street lighting including trench excavation, removal
of material off site, cabling and ducting; setting
columns in concrete foundations
generally 30.00 nr @ 1,500.00 45,000.00
Wildflower/british seed mix; grading and preparing
existing soil
generally 14,520.00 m2 @ 1.00 14,520.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soill inprover;
clean stone drainage layer, stakes etc
generally 146 nr @ 550.00 80,300.00
200,427.00£
Hard Paving Etc
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 1,216.00 m2 @ 6.50 7,904.00
Marshalls or equal paving on and including 50 thick
dry mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 1,216.00 m2 @ 75.00 91,200.00
Marshalls or equal kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 342.00 m @ 25.00 8,550.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
Allowance only for road crossings
generally 1.00 item @ 15,000.00 15,000.00
127,154.00£
Pavilion/Café
Allowance only for the provision of a Pavilion/Café
Building
generally 96.00 m2 @ 750.00 72,000.00
72,000.00£
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
33
outline costings: Clydeside Community Park
Phase 1: Option 1
Growing Beds
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,089.00 m2 @ 6.50 7,078.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 637.00 m2 @ 25.00 15,925.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 294.00 m @ 10.00 2,940.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 624.00 m2 @ 200.00 124,800.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 624.00 m2 @ 17.50 10,920.00
Beach hedge 616.00 nr @ 2.00 1,232.00
Post and wire fence to beech hedge 88.00 m @ 6.00 528.00
Mulching; 50 thick
generally 44.00 m2 @ 2.00 88.00
163,511.50£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Fencing
Expamet fast track fencing including associated posts
and foundations
generally 190.00 m @ 100.00 19,000.00
extra over for 1200mm wide gate 1.00 nr @ 750.00 750.00
19,750.00£
Tree Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,698.00 m2 @ 6.50 11,037.00
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 1,698.00 m2 @ 25.00 42,450.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 712.00 m @ 10.00 7,120.00
Street lighting including trench excavation, removal
of material off site, cabling and ducting; setting
columns in concrete foundations
generally 30.00 nr @ 1,500.00 45,000.00
Wildflower/british seed mix; grading and preparing
existing soil
generally 14,520.00 m2 @ 1.00 14,520.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soill inprover;
clean stone drainage layer, stakes etc
generally 146 nr @ 550.00 80,300.00
200,427.00£
Hard Paving Etc
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 1,216.00 m2 @ 6.50 7,904.00
Marshalls or equal paving on and including 50 thick
dry mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 1,216.00 m2 @ 75.00 91,200.00
Marshalls or equal kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 342.00 m @ 25.00 8,550.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
Allowance only for road crossings
generally 1.00 item @ 15,000.00 15,000.00
127,154.00£
Pavilion/Café
Allowance only for the provision of a Pavilion/Café
Building
generally 96.00 m2 @ 750.00 72,000.00
72,000.00£
Phase 1: Option 2
Growing Beds
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 3,520.00 m2 @ 6.50 22,880.00
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 637.00 m2 @ 25.00 15,925.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 294.00 m @ 10.00 2,940.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 624.00 m2 @ 200.00 124,800.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 624.00 m2 @ 17.50 10,920.00
Beach hedge 616.00 nr @ 2.00 1,232.00
Post and wire fence to beech hedge 88.00 m @ 6.00 528.00
Mulching; 50 thick
generally 44.00 m2 @ 2.00 88.00
179,313.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Fencing
Expamet fast track fencing including associated posts
and foundations
generally 190.00 m @ 100.00 19,000.00
extra over for 1200mm wide gate 1.00 nr @ 750.00 750.00
19,750.00£
Tree Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,698.00 m2 @ 6.50 11,037.00
80 thick tarmacadam footpath on and including 150
thick type 1
generally 1,698.00 m2 @ 35.00 59,430.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 712.00 m @ 20.00 14,240.00
Street lighting including trench excavation, removal
of material off site, cabling and ducting; setting
columns in concrete foundations
generally 30.00 nr @ 1,500.00 45,000.00
Wildflower/british seed mix; grading and preparing
existing soil
generally 1,246.00 m2 @ 1.00 1,246.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soill inprover;
clean stone drainage layer, stakes etc
generally 146 nr @ 550.00 80,300.00
211,253.00£
Hard Paving Etc
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 1,216.00 m2 @ 6.50 7,904.00
Natural stone paving on and including 50 thick dry
mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 1,216.00 m2 @ 225.00 273,600.00
Natural stone stone kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 342.00 m @ 50.00 17,100.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
Allowance only for road crossings
generally 1.00 item @ 15,000.00 15,000.00
318,104.00£
Pavilion/Café
Allowance only for the provision of a Pavilion/Café
Building
generally 96.00 m2 @ 750.00 72,000.00
72,000.00£
Phase 1: Option 2
Growing Beds
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 3,520.00 m2 @ 6.50 22,880.00
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 637.00 m2 @ 25.00 15,925.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 294.00 m @ 10.00 2,940.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 624.00 m2 @ 200.00 124,800.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 624.00 m2 @ 17.50 10,920.00
Beach hedge 616.00 nr @ 2.00 1,232.00
Post and wire fence to beech hedge 88.00 m @ 6.00 528.00
Mulching; 50 thick
generally 44.00 m2 @ 2.00 88.00
179,313.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Fencing
Expamet fast track fencing including associated posts
and foundations
generally 190.00 m @ 100.00 19,000.00
extra over for 1200mm wide gate 1.00 nr @ 750.00 750.00
19,750.00£
Tree Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,698.00 m2 @ 6.50 11,037.00
80 thick tarmacadam footpath on and including 150
thick type 1
generally 1,698.00 m2 @ 35.00 59,430.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 712.00 m @ 20.00 14,240.00
Street lighting including trench excavation, removal
of material off site, cabling and ducting; setting
columns in concrete foundations
generally 30.00 nr @ 1,500.00 45,000.00
Wildflower/british seed mix; grading and preparing
existing soil
generally 1,246.00 m2 @ 1.00 1,246.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soill inprover;
clean stone drainage layer, stakes etc
generally 146 nr @ 550.00 80,300.00
211,253.00£
Hard Paving Etc
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 1,216.00 m2 @ 6.50 7,904.00
Natural stone paving on and including 50 thick dry
mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 1,216.00 m2 @ 225.00 273,600.00
Natural stone stone kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 342.00 m @ 50.00 17,100.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
Allowance only for road crossings
generally 1.00 item @ 15,000.00 15,000.00
318,104.00£
Pavilion/Café
Allowance only for the provision of a Pavilion/Café
Building
generally 96.00 m2 @ 750.00 72,000.00
72,000.00£
As per option 1 with enhanced specification to surfaces:
Pavilion/Café
Allowance only for the provision of a Pavilion/Café
Building
generally 96.00 m2 @ 750.00 72,000.00
72,000.00£
800,420.00£
Pavilion/Café
Allowance only for the provision of a Pavilion/Café
Building
generally 96.00 m2 @ 750.00 72,000.00
72,000.00£
601,842.50£
Improved Park Facility
Provision of sports pitches or play including suitable
lighting, fencing and play equipment etc
1.00 item @ 750,000.00 750,000.00
750,000.00£
SUB TOTAL 923,588.00£
Improved Park Facility
Provision of sports pitches or play including suitable
lighting, fencing and play equipment etc
1.00 item @ 750,000.00 750,000.00
750,000.00£
SUB TOTAL 923,588.00£
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
34
outline costings: Clydeside Community ParkPhase 2: Option 1
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 798.00 m2 @ 6.50 5,187.00
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on regulating type 1
generally 798.00 m2 @ 25.00 19,950.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 540.00 m @ 10.00 5,400.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
35,037.00£
Orchard Area
Wildflower/british seed mix; grading and preparing
existing soil
generally 1,216.00 m2 @ 1.00 1,216.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 42 nr @ 500.00 21,000.00
22,216.00£
Comminity Woodland
General site clearance, removing debris etc
generally 6,840.00 m2 @ 0.50 3,420.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,840.00 m2 @ 8.00 54,720.00
Dense mix of shrubs, whips etc
generally 6,840.00 m2 @ 15.00 102,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 684.00 nr @ 550.00 376,200.00
Post and wire fence to perimeter inlcuding posts in
and including concrete foundations
generally 445.00 m @ 12.00 5,340.00
extra; 1200 wide gate 1.00 nr @ 150.00 150.00
542,430.00£
Expanded Tree Belt
General site clearance, removing debris etc
generally 6,660.00 m2 @ 0.50 3,330.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,660.00 m2 @ 8.00 53,280.00
Dense mix of shrubs, whips etc
generally 6,660.00 m2 @ 15.00 99,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 666.00 nr @ 550.00 366,300.00
522,810.00£
Existing Roads, Roundabout and Bridge
Allowance only for improvement works to existing
roads, roundabout and bridge parapet
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Phase 2: Option 1
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 798.00 m2 @ 6.50 5,187.00
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on regulating type 1
generally 798.00 m2 @ 25.00 19,950.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 540.00 m @ 10.00 5,400.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
35,037.00£
Orchard Area
Wildflower/british seed mix; grading and preparing
existing soil
generally 1,216.00 m2 @ 1.00 1,216.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 42 nr @ 500.00 21,000.00
22,216.00£
Comminity Woodland
General site clearance, removing debris etc
generally 6,840.00 m2 @ 0.50 3,420.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,840.00 m2 @ 8.00 54,720.00
Dense mix of shrubs, whips etc
generally 6,840.00 m2 @ 15.00 102,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 684.00 nr @ 550.00 376,200.00
Post and wire fence to perimeter inlcuding posts in
and including concrete foundations
generally 445.00 m @ 12.00 5,340.00
extra; 1200 wide gate 1.00 nr @ 150.00 150.00
542,430.00£
Expanded Tree Belt
General site clearance, removing debris etc
generally 6,660.00 m2 @ 0.50 3,330.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,660.00 m2 @ 8.00 53,280.00
Dense mix of shrubs, whips etc
generally 6,660.00 m2 @ 15.00 99,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 666.00 nr @ 550.00 366,300.00
522,810.00£
Existing Roads, Roundabout and Bridge
Allowance only for improvement works to existing
roads, roundabout and bridge parapet
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Phase 2: Option 1
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 798.00 m2 @ 6.50 5,187.00
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on regulating type 1
generally 798.00 m2 @ 25.00 19,950.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 540.00 m @ 10.00 5,400.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
35,037.00£
Orchard Area
Wildflower/british seed mix; grading and preparing
existing soil
generally 1,216.00 m2 @ 1.00 1,216.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 42 nr @ 500.00 21,000.00
22,216.00£
Comminity Woodland
General site clearance, removing debris etc
generally 6,840.00 m2 @ 0.50 3,420.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,840.00 m2 @ 8.00 54,720.00
Dense mix of shrubs, whips etc
generally 6,840.00 m2 @ 15.00 102,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 684.00 nr @ 550.00 376,200.00
Post and wire fence to perimeter inlcuding posts in
and including concrete foundations
generally 445.00 m @ 12.00 5,340.00
extra; 1200 wide gate 1.00 nr @ 150.00 150.00
542,430.00£
Expanded Tree Belt
General site clearance, removing debris etc
generally 6,660.00 m2 @ 0.50 3,330.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,660.00 m2 @ 8.00 53,280.00
Dense mix of shrubs, whips etc
generally 6,660.00 m2 @ 15.00 99,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 666.00 nr @ 550.00 366,300.00
522,810.00£
Existing Roads, Roundabout and Bridge
Allowance only for improvement works to existing
roads, roundabout and bridge parapet
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Existing Roads, Roundabout and Bridge
Allowance only for improvement works to existing
roads, roundabout and bridge parapet
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Phase 2 1,132,493.00£
Improved Park Facility
Provision of sports pitches or play including suitable
lighting, fencing and play equipment etc
1.00 item @ 750,000.00 750,000.00
750,000.00£
SUB TOTAL 923,588.00£
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
35
outline costings: Clydeside Community ParkPhase 2: Option 2
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 798.00 m2 @ 6.50 5,187.00
80 thick tarmacadam footpath on and including 150
thick type 1
generally 798.00 m2 @ 35.00 27,930.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 540.00 m @ 20.00 10,800.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
48,417.00£
Orchard Area
Wildflower/british seed mix; grading and preparing
existing soil
generally 1,216.00 m2 @ 1.00 1,216.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 42 nr @ 500.00 21,000.00
22,216.00£
Comminity Woodland
General site clearance, removing debris etc
generally 6,840.00 m2 @ 0.50 3,420.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,840.00 m2 @ 8.00 54,720.00
Dense mix of shrubs, whips etc
generally 6,840.00 m2 @ 15.00 102,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 684.00 nr @ 550.00 376,200.00
Post and wire fence to perimeter inlcuding posts in
and including concrete foundations
generally 445.00 m @ 12.00 5,340.00
extra; 1200 wide gate 1.00 nr @ 150.00 150.00
542,430.00£
Expanded Tree Belt
General site clearance, removing debris etc
generally 6,660.00 m2 @ 0.50 3,330.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,660.00 m2 @ 8.00 53,280.00
Dense mix of shrubs, whips etc
generally 6,660.00 m2 @ 15.00 99,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 666.00 nr @ 550.00 366,300.00
522,810.00£
Existing Roads, Roundabout and Bridge
Allowance only for improvement works to existing
roads, roundabout and bridge parapet
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Phase 2: Option 2
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 798.00 m2 @ 6.50 5,187.00
80 thick tarmacadam footpath on and including 150
thick type 1
generally 798.00 m2 @ 35.00 27,930.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 540.00 m @ 20.00 10,800.00
Allowance only for signage
generally 3.00 nr @ 1,500.00 4,500.00
48,417.00£
Orchard Area
Wildflower/british seed mix; grading and preparing
existing soil
generally 1,216.00 m2 @ 1.00 1,216.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 42 nr @ 500.00 21,000.00
22,216.00£
Comminity Woodland
General site clearance, removing debris etc
generally 6,840.00 m2 @ 0.50 3,420.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,840.00 m2 @ 8.00 54,720.00
Dense mix of shrubs, whips etc
generally 6,840.00 m2 @ 15.00 102,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 684.00 nr @ 550.00 376,200.00
Post and wire fence to perimeter inlcuding posts in
and including concrete foundations
generally 445.00 m @ 12.00 5,340.00
extra; 1200 wide gate 1.00 nr @ 150.00 150.00
542,430.00£
Expanded Tree Belt
General site clearance, removing debris etc
generally 6,660.00 m2 @ 0.50 3,330.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,660.00 m2 @ 8.00 53,280.00
Dense mix of shrubs, whips etc
generally 6,660.00 m2 @ 15.00 99,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 666.00 nr @ 550.00 366,300.00
522,810.00£
Existing Roads, Roundabout and Bridge
Allowance only for improvement works to existing
roads, roundabout and bridge parapet
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
As per option 1 with enhanced specification to surfaces:
Phase 3: Option 1
Wildflower Meadow
Strip existing grass surface and form mounds
generally 9,888.00 m2 @ 5.00 49,440.00
wildflower/british seed mix; grading and preparing
existing soil
generally 6,138.00 m2 @ 1.00 6,138.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 240.00 m2 @ 200.00 48,000.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 240.00 m2 @ 17.50 4,200.00
107,778.00£
Riverside Area
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 440.00 m2 @ 6.50 2,860.00
extra; breaking out existing hard
pavings 440.00 m2 @ 5.00 2,200.00
Marshalls or equal paving on and including 50 thick
dry mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 440.00 m2 @ 75.00 33,000.00
Marshalls or equal kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 110.00 m @ 25.00 2,750.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 25,000.00 25,000.00
65,810.00£
Improved Park Facility
Provision of sports pitches including suitable
lighting, fencing and play equipment etc
sports pitches 2.00 item @ 500,000.00 1,000,000.00
play area 2.00 item @ 150,000.00 300,000.00
1,300,000.00£
Phase 3: Option 1
Wildflower Meadow
Strip existing grass surface and form mounds
generally 9,888.00 m2 @ 5.00 49,440.00
wildflower/british seed mix; grading and preparing
existing soil
generally 6,138.00 m2 @ 1.00 6,138.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 240.00 m2 @ 200.00 48,000.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 240.00 m2 @ 17.50 4,200.00
107,778.00£
Riverside Area
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 440.00 m2 @ 6.50 2,860.00
extra; breaking out existing hard
pavings 440.00 m2 @ 5.00 2,200.00
Marshalls or equal paving on and including 50 thick
dry mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 440.00 m2 @ 75.00 33,000.00
Marshalls or equal kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 110.00 m @ 25.00 2,750.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 25,000.00 25,000.00
65,810.00£
Improved Park Facility
Provision of sports pitches including suitable
lighting, fencing and play equipment etc
sports pitches 2.00 item @ 500,000.00 1,000,000.00
play area 2.00 item @ 150,000.00 300,000.00
1,300,000.00£
Existing Roads, Roundabout and Bridge
Allowance only for improvement works to existing
roads, roundabout and bridge parapet
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Phase 3
1,145,873.00£
Option 1
Improved Park Facility
Provision of sports pitches or play including suitable
lighting, fencing and play equipment etc
1.00 item @ 750,000.00 750,000.00
750,000.00£
SUB TOTAL 923,588.00£
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
36
outline costings: Clydeside Community ParkPhase 3: Option 2
Wildflower Meadow
Strip existing grass surface and form mounds
generally 9,888.00 m2 @ 5.00 49,440.00
wildflower/british seed mix; grading and preparing
existing soil
generally 6,138.00 m2 @ 1.00 6,138.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 240.00 m2 @ 200.00 48,000.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 240.00 m2 @ 17.50 4,200.00
107,778.00£
Riverside Area
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 440.00 m2 @ 6.50 2,860.00
extra; breaking out existing hard
pavings 440.00 m2 @ 5.00 2,200.00
Natural stone paving on and including 50 thick dry
mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 440.00 m2 @ 225.00 99,000.00
Natural stone stone kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 110.00 m @ 50.00 5,500.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 30,000.00 30,000.00
139,560.00£
Improved Park Facility
Provision of sports pitches including suitable
lighting, fencing and play equipment etc
sports pitches 2.00 item @ 500,000.00 1,000,000.00
play area 2.00 item @ 150,000.00 300,000.00
1,300,000.00£
Phase 3: Option 2
Wildflower Meadow
Strip existing grass surface and form mounds
generally 9,888.00 m2 @ 5.00 49,440.00
wildflower/british seed mix; grading and preparing
existing soil
generally 6,138.00 m2 @ 1.00 6,138.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 240.00 m2 @ 200.00 48,000.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 240.00 m2 @ 17.50 4,200.00
107,778.00£
Riverside Area
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 440.00 m2 @ 6.50 2,860.00
extra; breaking out existing hard
pavings 440.00 m2 @ 5.00 2,200.00
Natural stone paving on and including 50 thick dry
mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 440.00 m2 @ 225.00 99,000.00
Natural stone stone kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 110.00 m @ 50.00 5,500.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 30,000.00 30,000.00
139,560.00£
Improved Park Facility
Provision of sports pitches including suitable
lighting, fencing and play equipment etc
sports pitches 2.00 item @ 500,000.00 1,000,000.00
play area 2.00 item @ 150,000.00 300,000.00
1,300,000.00£
Phase 3: Option 1
Wildflower Meadow
Strip existing grass surface and form mounds
generally 9,888.00 m2 @ 5.00 49,440.00
wildflower/british seed mix; grading and preparing
existing soil
generally 6,138.00 m2 @ 1.00 6,138.00
Raised planters; 100 x 100 heartwood larch timber;
geotextile membrane and imported topsoil on clean
broken stone base; overall approx 750mm high
generally 240.00 m2 @ 200.00 48,000.00
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
To raised planters 240.00 m2 @ 17.50 4,200.00
107,778.00£
Riverside Area
Footpaths
Excavating and removal of material off site; approx
250mm deep; compacting bottom of excavation
generally 440.00 m2 @ 6.50 2,860.00
extra; breaking out existing hard
pavings 440.00 m2 @ 5.00 2,200.00
Marshalls or equal paving on and including 50 thick
dry mortar bed on 150 thick blinded type 1 base;
including all necessary excavations, preparation etc
generally 440.00 m2 @ 75.00 33,000.00
Marshalls or equal kerbs on and including
foundations and suitable haunching; forming neat
edge to existing surfaces as required
generally 110.00 m @ 25.00 2,750.00
Allowance only for signage, street lighting and
furniture
generally 1.00 item @ 25,000.00 25,000.00
65,810.00£
Improved Park Facility
Provision of sports pitches including suitable
lighting, fencing and play equipment etc
sports pitches 2.00 item @ 500,000.00 1,000,000.00
play area 2.00 item @ 150,000.00 300,000.00
1,300,000.00£
Continued
As per option 1 with enhanced specification to surfaces:Improved Park Facility
Provision of sports pitches or play including suitable
lighting, fencing and play equipment etc
1.00 item @ 750,000.00 750,000.00
750,000.00£
SUB TOTAL 923,588.00£
SUB TOTAL 997,338.00£
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
37
outline costings: Clydeside Community ParkPhase 4
Site Clearance
Demolition of existing buildings; removal of material
off site; grubbing up foundations; filling voids with
well compacted type 1
allowance only 1.00 item @ 25,000.00 25,000.00
Preparing existing ground; breaking up and
removing hard pavings; removing trees and shrubs
rotivating, weeding and preparing for future use
generally 11,232.00 m2 @ 20.00 224,640.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 11,232.00 m2 @ 8.00 89,856.00
wildflower/british seed mix; grading and preparing
new topsoil
generally 11,232.00 m2 @ 1.00 11,232.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 562.00 nr @ 550.00 309,100.00
659,828.00£
Phase 4
Site Clearance
Demolition of existing buildings; removal of material
off site; grubbing up foundations; filling voids with
well compacted type 1
allowance only 1.00 item @ 25,000.00 25,000.00
Preparing existing ground; breaking up and
removing hard pavings; removing trees and shrubs
rotivating, weeding and preparing for future use
generally 11,232.00 m2 @ 20.00 224,640.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 11,232.00 m2 @ 8.00 89,856.00
wildflower/british seed mix; grading and preparing
new topsoil
generally 11,232.00 m2 @ 1.00 11,232.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 562.00 nr @ 550.00 309,100.00
SUB TOTAL 659,828.00£
Phase 4
Site Clearance
Demolition of existing buildings; removal of material
off site; grubbing up foundations; filling voids with
well compacted type 1
allowance only 1.00 item @ 25,000.00 25,000.00
Preparing existing ground; breaking up and
removing hard pavings; removing trees and shrubs
rotivating, weeding and preparing for future use
generally 11,232.00 m2 @ 20.00 224,640.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 11,232.00 m2 @ 8.00 89,856.00
wildflower/british seed mix; grading and preparing
new topsoil
generally 11,232.00 m2 @ 1.00 11,232.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 562.00 nr @ 550.00 309,100.00
SUB TOTAL 659,828.00£
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
38
outline costings: canal allotment / Duntocher burn nodeOption 1
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 345.00 m2 @ 25.00 8,625.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 230.00 m @ 10.00 2,300.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
331,212.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 171.00 m2 @ 25.00 4,275.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 114.00 m @ 10.00 1,140.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
501,982.50£
Option 1
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 345.00 m2 @ 25.00 8,625.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 230.00 m @ 10.00 2,300.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
331,212.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 171.00 m2 @ 25.00 4,275.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 114.00 m @ 10.00 1,140.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
501,982.50£
Option 1
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 345.00 m2 @ 25.00 8,625.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 230.00 m @ 10.00 2,300.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
331,212.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 171.00 m2 @ 25.00 4,275.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 114.00 m @ 10.00 1,140.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
501,982.50£
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
39
outline costings: canal allotment / Duntocher burn node
Option 1
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 345.00 m2 @ 25.00 8,625.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 230.00 m @ 10.00 2,300.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
331,212.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 171.00 m2 @ 25.00 4,275.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 114.00 m @ 10.00 1,140.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
501,982.50£
Option 1
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 345.00 m2 @ 25.00 8,625.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 230.00 m @ 10.00 2,300.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
331,212.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 171.00 m2 @ 25.00 4,275.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 114.00 m @ 10.00 1,140.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
501,982.50£
Option 1
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 345.00 m2 @ 25.00 8,625.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 230.00 m @ 10.00 2,300.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
331,212.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 171.00 m2 @ 25.00 4,275.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 114.00 m @ 10.00 1,140.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
501,982.50£
Continued
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
40
outline costings: canal allotment / Duntocher burn node
Option 1
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 345.00 m2 @ 25.00 8,625.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 230.00 m @ 10.00 2,300.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
331,212.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 171.00 m2 @ 25.00 4,275.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 114.00 m @ 10.00 1,140.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
501,982.50£
Option 1
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 345.00 m2 @ 25.00 8,625.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 230.00 m @ 10.00 2,300.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
331,212.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 171.00 m2 @ 25.00 4,275.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 114.00 m @ 10.00 1,140.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
501,982.50£
Continued Option 2
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
80 thick tarmacadam footpath on and including 150
thick type 1
generally 345.00 m2 @ 35.00 12,075.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 230.00 m @ 20.00 4,600.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
336,962.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
80 thick tarmacadam footpath on and including 150
thick type 1
generally 171.00 m2 @ 35.00 5,985.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 114.00 m @ 20.00 2,280.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
504,832.50£
Option 2
Site Clearance
Preparing existing surfaces; removing debris;
scraping back and removing areas of spoil;
preparing to receive the works
generally 22,525.00 m2 @ 0.50 11,262.50
11,262.50£
Earthworks
Allowance only for earthworks to tree avenue area
generally 1.00 item @ 10,000.00 10,000.00
10,000.00£
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 2,845.00 m2 @ 6.50 18,492.50
75 thick Raisby golden gravel or equal and approved
on and including Terram 1000, on 150 thick type 1
generally 2,845.00 m2 @ 25.00 71,125.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 794.00 m @ 10.00 7,940.00
97,557.50£
Growing Beds
Growing beds; 300 thick well fertilized top soil bed
generally 3,822.00 m2 @ 8.00 30,576.00
Larch edging; 300 x 50; pegged at 300 centres with
75 x 75 x 600 softwood pegs
generally 1,246.00 m @ 20.00 24,920.00
55,496.00£
Grass Seeding
wildflower/british seed mix; grading and preparing
existing soil
generally 4,894.00 m2 @ 1.00 4,894.00
4,894.00£
Tree Planting
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
Orchard Area 42 nr @ 450.00 18,900.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
General Area 26 nr @ 500.00 13,000.00
31,900.00£
Shrubs/Hedges
Shrub planting; forming pit; removal of excavated
material; imported top soil and granular soil improver
Beach hedge 1,176.00 nr @ 2.00 2,352.00
Post and wire fence to beech hedge 168.00 m @ 6.00 1,008.00
Mulching; 50 thick
generally 84.00 m2 @ 2.00 168.00
3,528.00£
Fencing
Fencing; 2.4m high metal fencing with paint finish
generally 390 m @ 75.00 29,250.00
extra; access gate; 1200 wide 2 nr @ 500.00 1,000.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
31,250.00£
Signage
Allowance only for signage
generally 2.00 nr @ 1,500.00 3,000.00
3,000.00£
Shelters, Storage Etc
Bulk storage containers; 100 x 50 heartwood larch
cladding
allowance only 1.00 item @ 1,000.00 1,000.00
Composting toilet; Natsol or equal and approved;
forming void and including soakaway pit etc as
required
generally 1.00 nr @ 7,000.00 7,000.00
Shelters; 100 x 100 heartwood larch; metal profile roof
with hessian sheet and broken slate covered roof
allowance only 1.00 item @ 1,500.00 1,500.00
Lockable metal tool store
allowance only 1.00 item @ 2,500.00 2,500.00
Water storage barrels including interconnecting
pipework; 500 litre capacity each barrel
generally 20.00 nr @ 100.00 2,000.00
Provision of stand pipe and underground mains water
supply
allowance only 1.00 item @ 5,000.00 5,000.00
19,000.00£
Community Woodland
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 345.00 m2 @ 6.50 2,242.50
80 thick tarmacadam footpath on and including 150
thick type 1
generally 345.00 m2 @ 35.00 12,075.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 230.00 m @ 20.00 4,600.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 3,840.00 m2 @ 8.00 30,720.00
Dense mix of shrubs, whips etc
generally 3,840.00 m2 @ 15.00 57,600.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 384.00 nr @ 550.00 211,200.00
Fencing; 2.4m high metal fencing with paint finish
generally 227 m @ 75.00 17,025.00
extra; access gate; 1200 wide 1 nr @ 500.00 500.00
extra; double access gate; 2400 wide 1 nr @ 1,000.00 1,000.00
336,962.50£
Burn Side Habitat Planting
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 171.00 m2 @ 6.50 1,111.50
80 thick tarmacadam footpath on and including 150
thick type 1
generally 171.00 m2 @ 35.00 5,985.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 114.00 m @ 20.00 2,280.00
Imported topsoil; 300 thick including suitable fertiliser;
weeding and preparing for planting
generally 6,352.00 m2 @ 8.00 50,816.00
Dense mix of shrubs, whips etc
generally 6,352.00 m2 @ 15.00 95,280.00
Trees; forming pit; removal of excavated material
off site; imported topsoil and granular soil improver;
clean stone drainage layer, stakes etc
generally 635.20 nr @ 550.00 349,360.00
504,832.50£
As per option 1 with enhanced specification to surfaces:
SUB TOTAL 1,045,587.00£
SUB TOTAL 1,109,683.00£
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
41
Option 1
outline costings: Duntocher Burn linkPark to Canal (north)
Footpath
Allowance only for new footpath including breaking up
existing pavings and tieing in to existing surfaces
generally 530.00 m @ 100.00 53,000.00
extra for additional demolitions etc 1.00 item @ 1,500.00 1,500.00
54,500.00£
Signage
Allowance only for signage
generally 6.00 nr @ 1,500.00 9,000.00
9,000.00£
Park to Canal (north)
Footpath
Allowance only for new footpath including breaking up
existing pavings and tieing in to existing surfaces
generally 530.00 m @ 100.00 53,000.00
extra for additional demolitions etc 1.00 item @ 1,500.00 1,500.00
54,500.00£
Signage
Allowance only for signage
generally 6.00 nr @ 1,500.00 9,000.00
9,000.00£
Canal to Clyde (south)
Option 1
Footpaths
Lifting turf and removing off site; compacting
bottom of excavation
generally 1,720.00 m2 @ 6.50 11,180.00
75 thick bound whin dust or equal and approved on
and including Terram 1000, on regulating type 1
generally 1,720.00 m2 @ 20.00 34,400.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 876.00 m @ 10.00 8,760.00
Pedestrian railing approx 1100mm high; galvanised;
posts at 1800 centres set into concrete foundations
generally 60.00 m @ 75.00 4,500.00
Signage
Allowance only for signage
generally 1.00 nr @ 1,500.00 1,500.00
60,340.00£
Canal to Clyde (south)
Option 1
Footpaths
Lifting turf and removing off site; compacting
bottom of excavation
generally 1,720.00 m2 @ 6.50 11,180.00
75 thick bound whin dust or equal and approved on
and including Terram 1000, on regulating type 1
generally 1,720.00 m2 @ 20.00 34,400.00
Larch edging; 150 x 38; pegged at 500 centres with
50 x 50 x 450 softwood pegs
generally 876.00 m @ 10.00 8,760.00
Pedestrian railing approx 1100mm high; galvanised;
posts at 1800 centres set into concrete foundations
generally 60.00 m @ 75.00 4,500.00
Signage
Allowance only for signage
generally 1.00 nr @ 1,500.00 1,500.00
60,340.00£
SUB TOTAL 63,500.00£
60,340.00£ SUB TOTAL
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
42
outline costings: Duntocher Burn linkCanal to Clyde (south): Option 2
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,720.00 m2 @ 6.50 11,180.00
80 thick tarmacadam footpath on and including 150
thick type 1
generally 1,720.00 m2 @ 35.00 60,200.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 876.00 m @ 20.00 17,520.00
Pedestrian railing approx 1100mm high; galvanised;
posts at 1800 centres set into concrete foundations
generally 60.00 m @ 75.00 4,500.00
Signage
Allowance only for signage
generally 1.00 nr @ 1,500.00 1,500.00
94,900.00£
Canal to Clyde (south): Option 2
Footpaths
Excavating and removal of material off site; approx
225mm deep; compacting bottom of excavation
generally 1,720.00 m2 @ 6.50 11,180.00
80 thick tarmacadam footpath on and including 150
thick type 1
generally 1,720.00 m2 @ 35.00 60,200.00
Concrete heel kerb approx 200 x 50; including
foundations and haunchings
generally 876.00 m @ 20.00 17,520.00
Pedestrian railing approx 1100mm high; galvanised;
posts at 1800 centres set into concrete foundations
generally 60.00 m @ 75.00 4,500.00
Signage
Allowance only for signage
generally 1.00 nr @ 1,500.00 1,500.00
94,900.00£
Clydeside Walkway
Footpath
Allowance only for new footpath
generally 1,496.00 m @ 100.00 149,600.00
149,600.00£
Clydeside Walkway
Footpath
Allowance only for new footpath
generally 1,496.00 m @ 100.00 149,600.00
149,600.00£
94,900.00£ SUB TOTAL
149,600.00£ SUB TOTAL
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
43
outline costings: summary
Exclusions
Road construction in town centre area.
Lighting to commercial/residential area.
Tree surgeon/specialist works to woodland areas.
Site acquisition costs (if necessary).
Professional Fees.
Statutory approval costs.
Fluctuations in labour and material costs beyond the current date.
VAT (where applicable).
Exclusions
Road construction in town centre area.
Lighting to commercial/residential area.
Tree surgeon/specialist works to woodland areas.
Site acquisition costs (if necessary).
Professional Fees.
Statutory approval costs.
Fluctuations in labour and material costs beyond the current date.
VAT (where applicable).
Summary Option 1 Option 2
Hospital Link (Helipad Area) 118,433.00 273,533.00
Clydeside Community Park 601,842.50 819,420.00
Phase 2 1,132,493.00 1,145,873.00
Phase 3 923,588.00 997,338.00
Phase 4 659,828.00 659,828.00
Canal Allotment/Duntocher Burn Node 1,101,083.00 1,109,683.00
Path to Canal 63,500.00 63,500.00
Canal to Clyde 60,340.00 94,900.00
Clydeside Walkway 149,600.00 149,600.00
4,810,707.50 5,313,675.00
Allowance for Preliminaries at 10% 481,070.75 531,367.50
5,291,778.25 5,845,042.50
Allowance for Contingencies at 5% 264,588.91 292,252.13
Total Cost 5,556,367.16£ 6,137,294.63£
Summary Option 1 Option 2
Hospital Link (Helipad Area) 118,433.00 273,533.00
Clydeside Community Park: Phase 1 601,842.50 819,420.00
Phase 2 1,132,493.00 1,145,873.00
Phase 3 923,588.00 997,338.00
Phase 4 659,828.00 659,828.00
Canal Allotment/Duntocher Burn Node 1,101,083.00 1,109,683.00
Path to Canal 63,500.00 63,500.00
Canal to Clyde 60,340.00 94,900.00
Clydeside Walkway 149,600.00 149,600.00
4,810,707.50 5,313,675.00
Allowance for Preliminaries at 10% 481,070.75 531,367.50
5,291,778.25 5,845,042.50
Allowance for Contingencies at 5% 264,588.91 292,252.13
Total Cost 5,556,367.16£ 6,137,294.63£
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
44
Action Plan
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
46
next steps / action plan:
The study provides sufficiently detailed information and associated costings to inform decision making and to form the basis of applications for funding.
Many of the proposals can be delivered through direct implementation subject to budgets being allocated or funding being secured for delivery - there are few barriers evident to progressing the works. Further detailed design development will be required prior to implementation.
Perhaps the most significant 'project' is the forming of links thru' Clydeside Community Park and the Golden Jubilee Hospital grounds. These works will (in all or in part) be subject to detailed dialogue and partnership working with the NHS. Support in principle has to date been stated for opening up the hospital site to public access.
As a key next step, detailed dialogue is required with the relevant respresentatives of the NHS, to discuss the detail of the proposals and the best approach to delivery.
In order to deliver the proposals and indeed to prevent the remaining opportunities to form links being lost to inappropriate development, the proposals outlined in the study require to be formalised within the development control / statutory planning framework.
As each component project is advanced, a process of dialogue with the surrounding community, user groups and other stakeholders will be required to develop and finalise the detailed proposals.
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
47
clyd
esid
e &
dal
mui
r - c
lyde
wat
erfro
nt g
reen
net
wor
k st
rate
gy
48
list of consultees:
Alastair Corbett - Glasgow & Clyde Valley Green Network Partnership
Vikki Kewney - Clyde Waterfront Partnership, Scottish Enterprise
Alastair Gemmell - West Dunbartonshire Council
Donald Petrie - West Dunbartonshire Council
Ian Bain - West Dunbartonshire Council
Davina Lavery - West Dunbartonshire Council
Hugh Moore - Clydebank Re-built