Clemson University Capital Investment Update March 25, 2016
2
Clemson University Capital Investment Update
Table of Contents
Executive Summary………………………………………..……………………..……………. 3 – 5
Construction Phase…………………………………………………………………………….. 6 – 29
Design Phase………………………………………………………………………………….… 30 – 35
3
CLEMSON UNIVERSITY CAPITAL INVESTMENT UPDATE
EXECUTIVE SUMMARY
This Executive Summary spotlights significant changes in selected permanent improvement projects. More detailed information on current and
potential future projects is in the attached Capital Investment Update.
CONSTRUCTION PHASE
CU-ICAR Advanced Powertrain Testing Lab – Construction work is nearing completion with the facility ready for testing equipment final
installation in early April 2016. Test equipment provided by the Department of Automotive Engineering is scheduled to be ready for research
work by mid-May 2016.
West Campus Energy Plant – Underground site utilities including the sewer, storm water, and water lines under the building have been
completed. Chilled water pipeline has been installed across the intramural field. Cooling Towers have been installed except for the electrical
motors and fans. The chillers have been purchased and have been set in place and work is proceeding to connect the chillers into the system.
CURI Graduate Education Center – The construction of the building accelerated as the main foundations, building structural steel, and post
tensioned floor slabs were completed. The roof structure is complete and the installation of the exterior wall is well underway. Rough-in of
the utilities is underway inside the building along with the interior wall framing in the central utility and service areas.
Advanced Plant Technology Laboratory Renovation – All interior structures, including walls, ceilings, sprinkler system, HVAC ductwork,
electrical and plumbing are being installed at this time. Scheduled completion date is late summer 2016.
Greenwood Genetic Center – Construction work began in September but has been hampered by wet weather. Grading work is complete and
unground utilities are now in place. The floor slab was poured the second week of January and steel erection should begin the first week of
February.
Core Campus Development – Construction continues despite record amounts of rainfall. Whiting-Turner has reaffirmed their commitment to
meet substantial completion. The schedule has been reworked and additional resources have been brought on board. Approximately 400
construction team members are on site representing 18 different trades. Most trades have teams in each of the Buildings working simultaneously.
Littlejohn Coliseum Renovation – Steel erection and cast in place concrete are substantially complete for the project. Lighting trusses have
been installed in the Coliseum and insulated metal panels are beginning to be erected to cover the existing Cor-Ten steel at the roof. At the new
4
Swann Pavilion, the old tunnel off of Avenue of Champions has been closed off completely. The practice court slab has been completed and
the interior metal framing, as well as the brick masonry, are well underway. The Mechanical/Electrical/Plumbing rough-ins are ongoing.
Farm Animal Research Center – Bids are due April 14, 2016, for the construction of a new 29,360 square foot free stall barn at Lamaster Dairy.
Football Operations Facility – Deep foundation installation and soil stabilization work is now complete. Structural steel is now on site and steel
erection began in early March. Underground utility work is nearing completion. The CM at Risk contractor is working to have the GMP
finalized in the third quarter of 2016.
Douthit Hills Student Community Construction – The installation of storm drain, sanitary sewer piping, chilled water piping, curb and gutter
and the telecom duct bank continues, but is nearing completion. The precast for the East Zone (Bridge Housing) is nearing completion. The
installation of roof trusses and decking in the East Zone has begun and roofing will begin shortly. The deep foundations for building H are
approximately 75% complete. Pile caps, spread footings, retaining walls and columns for building H are being installed. In the West Zone the
deep foundations for building B are approximately 50% complete. The foundation for building A has begun. Precast erection in the West Zone
is expected to begin in late April of 2016. The CM at Risk contractor is working to have a GMP in the early second quarter of 2016.
5
DESIGN PHASE
Student Activities Center Renovation – The A/E has completed design documents for the barn structure and is working on the final documents
of the site package. Finalization of details, utility systems, and interior furnishing needs is in progress. The contractor is presently bidding the
renovation work of the barn structure which was put out as an early package in order for work to begin as the site package is being finalized.
Business and Behavioral Sciences Building - Interviews with shortlisted design firms were held on March 10, 2016. The team of LS3P
Associates with LMN Architects was selected as the most qualified firm for this project. Contract negotiations are now underway.
Electrical Distribution System Upgrades and Replacement – The design firm is progressing with design documents. Submission for the final
(phase 2) approval is planned for this summer.
6
Clemson University Capital Investment Update
Construction Phase
CONSTRUCTION PHASE
A Quarterly Update of the Most Significant Current Projects
Listed in order of Projected Substantial Completion Date
Minority Business Enterprise (MBE) is a business which is at least 51% owned, operated, and controlled on a daily basis by American citizens who
are either women or of an ethnic minority classification.
(% value = MBE participation value/total contract amount)
7
CU-ICAR ADVANCED POWERTRAIN TESTING LAB – H12-9911
Project Budget: $2,300,000.00 (Final/Phase 2)
Source of Funds: Maintenance and Stewardship Funds
Project Manager: Mike Davis
Description: This project will renovate an existing 1,800 square foot testing lab in the Campbell Center at CU-ICAR in Greenville, SC. The space
will be renovated to construct one (1) test cell for automotive powertrain testing equipment with space to allow for a second test cell in
the future. One (1) dynamometer is planned for the initial test cell with significant support equipment provided in a new equipment
mezzanine and an equipment service yard. A new power service from Duke Energy will be part of the project.
A/E: Peritus Engineers
Contractor: Affiliated Construction Group (CM@R)
MBE: 0.0 % (to date)
Schedule: Final design: March 2015
Notice to proceed: August 2015
Substantial Completion date: April 2016
Status: Construction work is nearing completion with the contractor scheduled to complete their activities by early April 2016. This will allow
for the final installation phase of the test equipment, which is provided independent of the Capital Project by the Department of
Automotive Engineering. Installation, start-up, and initial commissioning of this equipment is expected to take approximately one (1)
month. The lab is scheduled to be ready for research work by mid-May 2016.
8
9
WEST CAMPUS ENERGY PLANT CONSTRUCTION – H12-9915
Project Budget: $10,465,000.00 (Final/Phase 2)
Source of Funds: Maintenance & Stewardship Funds
Project Manager: Sam Zanca
Description: Construct a new district energy plant on Clemson’s West Campus that will add approximately 3,000 refrigeration tons to the University’s
current plant capacity of 11,000 refrigeration tons. The facility will primarily be a chilled water facility with underground utility piping
including high efficiency electric centrifugal chillers, evaporative cooling tower additions, energy optimized controls, and variable speed
electric centrifugal pumps. The new energy facility will be located near Littlejohn Coliseum on the corner of Centennial Boulevard and
Highway 93.
A/E: Trane US, Inc. (Design-Build Contractor)
Contractor: Trane US, Inc. (Design-Build Contractor)
MBE: 0.5% (to date)
Schedule: Final Approval: December 9, 2014
Final Design: October 5, 2015
Notice to proceed: July 14, 2015
Substantial Completion: May 10, 2016
Status: Underground site utilities including the sewer, storm water, and water lines under the building have been completed. Chilled water
pipeline has been installed across the intramural field. Cooling towers have been installed except for the electrical motors and fans. The
chillers have been set in place and work is proceeding to connect the chillers into the system. Building roofing, structural steel, siding
and masonry work is nearing completion. Mechanical, plumbing and electrical rough in is nearing completion. Chilled water piping is
now being installed and connections made to the chillers. Control systems installation will start at the end of March 2016. Electrical
power and transformers are scheduled to be installed early April 2016. Plans for commissioning of the facility are now being developed.
10
11
CURI GRADUATE EDUCATION CENTER and LASCH LAB RENOVATIONS – H12-9864-PG
Project Budget: $23,520,000.00 (Final/Phase 2)
Source of Funds: Research University Infrastructure Bonds, Operating Revenue, Private Gifts,
Federal Economic Development Administration Grant
Project Manager: Jim Tuten
Description: This project will construct a 70,000 to 75,000 square foot Graduate Education Center (GEC) at the Clemson University Restoration
Institute (CURI) in North Charleston on the old Charleston Naval Base. The facility will support the undergraduate and graduate
education activities for proposed programs in energy systems, water ecology, logistics, advanced materials manufacturing, workforce
development, and K-12 STEM education. These programs will be focused on building public/private partnerships with industry. The
GEC will also serve as Clemson University’s continuing education facility in the low country of South Carolina and will provide shell
space for industry partners in a variety of office-type settings. Clemson students, faculty, and staff will engage in academic activities in
the GEC. The CURI campus management staff will be located in the building. The facility will include offices, classrooms, conference
rooms, café, gallery space, electrical laboratories, and a green roof. The building will seek USGBC LEED silver certification.
This project will also renovate portions of the Warren G. Lasch Conservation Laboratory (Lasch Lab) which is home to the Hunley
submarine restoration work. Renovations will focus primarily on converting the Hunley tank to a caustic system to allow for better
preservation of this historic Civil War era artifact. The caustic system will include new piping and support equipment for the tank along
with upgraded control systems. Climate controlled storage facilities for the Hunley artifacts will be provided along with finish upgrades
to the Lasch Lab entry lobby.
A/E: Graduate Education Center – LS3P Architects
Lasch Lab Renovations – RMF Engineering
Contractor: Graduate Education Center – Choate Construction Company
MBE: 18.9 % (to date)
Lasch Lab Renovations - IPW Construction Group - $971,575.00
MBE: 0.0 %
Schedule: Final design: March 2015
Notice to proceed: March 2015
Substantial Completion: June 2016
Status: Graduate Education Center: The construction of the building accelerated as the main foundations, building structural steel, and post
tensioned floor slabs were completed. The roof structure is complete and the installation of the exterior wall is well underway. Rough-
in of the utilities is underway inside the building along with the interior wall framing in the central utility and service areas. Significant
portions of the HVAC mechanical and plumbing systems are in place. Work on the Digital Production Arts upfit is being integrated
into the flow of building completion. The project is on schedule for a summer milestone of substantial completion.
Lasch Lab Renovation: Substantial completion was reached on May 25, 2014.
12
13
ADVANCED PLANT TECHNOLOGY LAB – P20-9546
Project Budget: $7,000,000.00 (Final/Phase 2)
Source of Funds: State Appropriations and Capital Reserve Fund
Project Manager: Al Cope
Description: This project encompasses the renovation of laboratory space and the upgrade of mechanical, electrical, and plumbing systems at the
Pee Dee Research and Education Center (REC) in Florence, S.C. This Center houses the Advanced Plant Technology Program and
Laboratory which provides critical research needed for a successful agriculture-based biotechnology industry in South Carolina.
The critical components of the renovation include new mechanical, electrical, and plumbing systems. Many of the proposed design
decisions are also contingent on a new sprinkler system and a new water line to replace an existing PVC main.
The vision for the renovated center and laboratory includes the creation of permeable spaces that foster interaction and team-based
work and hybrid, flexible spaces capable of accommodating visitors, emerging technologies, and corporate partnerships. The proposed
renovation will not only refresh aging systems in the building, but will provide additional office and laboratory space through better
utilization of existing space.
A/E: Goodwyn Mills Cawood Architects, Greenville, SC
Contractor: Rodgers Builders, Greenville, SC
MBE: TBD (Rodgers Builders is a woman-owned firm)
Schedule: Final design: October 2015
Notice to proceed: August 2015
Substantial Completion date: July 2016
Status: Final GMP has been approved at $5,969,226.00. Renovation of the Pitner Center has begun. All interior structures, including walls,
ceilings, sprinkler system, HVAC ductwork, electrical and plumbing are being installed at this time. The scheduled completion date is
late summer 2016.
14
15
GREENWOOD GENETICS CENTER CONSTRUCTION – H12-9910
Project Budget: $6,500,000.00 (Final/Phase 2)
Source of Funds: Research University Infrastructure Bonds, Private Gifts
Project Manager: Paul Borick
Description: This project will construct a 17,000 square foot research and education center in Greenwood, SC. This is a collaborative project in
conjunction with the Greenwood Genetic Center. The facility will allow expansion of the existing doctoral program in human
genetics to include a nationally competitive research and development team and enhance the existing research capabilities of the J.C.
Self Research Institute of Human Genetics.
A/E: Moss and Associates (Design-Build contract)
Contractor: Moss and Associates
MBE: 12% (to date)
Schedule: Final Approval: May 8, 2013
Notice to proceed: September 15, 2015
Substantial Completion: July 2016
Status: Steel erection is now complete and the building is being dried in. Exterior wall sheathing is now in place and interior metal stud
partition work is underway. Roof installation is almost complete. Exterior masonry work began the 2nd week of March.
16
CORE CAMPUS DEVELOPMENT – H12-9906
Project Budget: $96,000,000.00 (Final/Phase 2)
Source of Funds: Revenue Bonds
Project Manager: Tommi Jones
Description: This project is a 260,000 square foot, mixed-use facility that will include student housing and dining facilities. In keeping with the
housing master plan, there are approximately 700 beds in the residential portion of the project, comprising approximately 179,000
square feet of the facility. The dining portion includes an approximately 76,000 square feet dining facility, convenience store, retail
restaurant, and appropriate administrative support spaces. Academically-oriented space in the facility will be approximately 5,000
square feet and will include shared-use seminar and meeting space for faculty and students. This core campus project will replace the
Johnstone complex in the heart of the Clemson's campus.
A/E: Stevens & Wilkinson, Inc. with VMDO Architects and Sasaki Associates, Inc.
S&W Current Contract: $7,832,330.00 (includes 4 amendments)
Contractor: The Whiting-Turner Contracting Company (CM@R)
Current W-T Contract: $82,298,178.00
Change Order #1: $190,712.00 approved on 2/25/16
MBE: 6.16 % (to date)
Schedule: Final Construction Documents: July 24, 2015 (Phase V)
Notice to proceed: August 5, 2014
Substantial Completion date: August 1, 2016
Status: Whiting-Turner continues construction despite record amounts of rainfall which have hindered brick, glazing and roofing activities.
Despite these challenges, they have committed to deliver the project on schedule. The trades working on skin activities are working
12-hour days, 6 days a week to overcome the weather delays. Spray foam insulation and brick veneer activities, window installation,
and roof installation are all ongoing for Buildings A, C & D. Mechanical, electrical, plumbing (MEP), roofing, interior framing, and
exterior framing/sheathing activities are underway in each of the four buildings. Drywall is being installed in all 4 buildings. Painting
and tile installation are in progress in Buildings A & D. Millwork is being delivered to Buildings A & D in March. Storefront and
curtain wall installation continues in Buildings A & D. Permanent power is energized in Building D which will facilitate the elevator
inspection as both elevators are installed in D. All transformers and switches have been set and electrical cables pulled. The elevator
installation continues in Buildings A & C. Kitchen hoods are being installed in Building B in March. To date, 725 tons of construction
debris have been recycled on the job; therefore, the job is tracking an 85% recycled C&D rate. Four Clemson students are currently
interning for Whiting-Turner. Eight new Clemson students have accepted offers for summer internships. During February, the Atelier
InSite CU Public Art group selected Koryn Rolstad to commission art for the Core Campus project. Her work, Illuminated Croma Wind
Trees, will be installed inside the Dining atrium and in the 2 adjacent courtyards.
17
18
19
DEFERRED MAINTENANCE - H12-9898/H12-9909/H12-9913/H12-9924
Project Budget: $17,249,118.00 (Final/Phase 2)
Source of Funds: Capital Reserve Funds
Project Manager: Bret McCarley (construction); Pat Crowther (procurement)
Description: This project will consist of replacing and upgrading portions of the campus-owned 12,470-volt and 4,160-volt distribution systems in
order to address deferred maintenance and reliability issues. The main scope of work will replace electrical switches which are no
longer safe for personnel to operate under load, replace seriously deteriorated overhead and underground power distribution cabling,
and replace building transformers, protective relays, and provide fuse coordination. These are essential steps for the ongoing safety,
compliance, and continuity of the University enterprise. Currently, this project has been broken into eight (8) separate construction
packages dealing with distinct areas of campus and portions of the distribution system.
PACKAGE #1 (The Office of the State Engineer requested that subsequent phases be identified by letter suffixes.)
A/E: Burns & McDonnell
Description The scope of this phase includes various upgrades to portions of the existing 4kV and 12kV electrical distribution system.
Contractor: A. West Enterprise
MBE: 100% (Economically Deprived Woman Owned Small Business)
Contract: Design-Bid-Build $600,338.00
Schedule: Notice to proceed: January 22, 2014
Substantial Completion: October 28, 2014
Status: The construction for this phase of the project is complete and final payment made to the contractor.
PACKAGE B
A/E: Burns & McDonnell
Description: This contract package consists of replacement work and overhead power conversions in the South Ravenel (Y-Beach) area, repairs in
the substation, and incoming utility safety improvements in Long Hall.
Contractor: A. West Enterprise
MBE: 100% (Economically Deprived Woman Owned Small Business)
Contract: Design-Bid-Build $1,197,977.00
Schedule: Notice to proceed: May 2, 2014
Substantial Completion: February 11, 2015
Status: The A/E has declared this phase substantially complete and awaiting completion of punch list items. The contractor has completed
the punch list items. Close-out documents and a final pay application are currently being reviewed for processing.
20
PACKAGE C
A/E: Burns & McDonnell
Description: This contract package consists of building service entrance upgrades, system switch replacements, and loop redundancies for Cooper
Library, Lowry Hall, and the new Fernow Street/Calhoun Street.
Contractor: A. West Enterprise
MBE: 100% (Economically Deprived Woman Owned Small Business)
Contract: Design-Bid-Build $3,096,777.00
Schedule: Notice to proceed: July 3, 2014
Substantial Completion: September 24, 2015 per change orders
Status: The construction for this phase of the project has been declared substantially complete – contractor continues work of resolving
punch list items.
PACKAGE D
A/E: Design South
Description: This phase of the project is for the replacement of the emergency power systems at the Wastewater Treatment Plant.
Contractor: Quality Electric Company
MBE: 0%
Contract: Design-Bid-Build $395,000.00
Schedule: Notice to proceed: April 29, 2014
Substantial Completion: February 1, 2015 (achieved)
Status: Construction has been completed on this phase of the project and final payment made to the contractor.
PACKAGE F
A/E: Burns & McDonnell
Description: The scope of this phase consists of the installation of various sections of concrete encased electrical ductbank that will be used in
other construction packages of this overall project.
Contractor: M.C. Dean Construction, Inc.
MBE: 0% (to date)
Contract: Design-Bid-Build $447,380.00
Schedule: Notice to proceed: September 3, 2014
Substantial Completion: December 10, 2014 (achieved)
Status: The construction for this phase of the project has been completed and final payment made to the contractor.
21
DEFERRED MAINTENANCE 2012 PACKAGE A
A/E: HiLine Engineering (dba GDS Associates)
Description: The scope of this phase consists of major load balancing to the 12,470 volt feeder on Williamson Road and extension to the
conversion of Athletic and Calhoun Fields (Bottoms) from 4kV to 12kV.
Contractor: H.R. Allen, Inc.
MBE: 0%
Contract: Design-Bid-Build $1,932,300.00
Schedule: Notice to proceed: 10/13/2014.
Substantial Completion: 6/17/2015 (original) + 51 days (CO #1) = 8/7/2015 (pending)
Status: The contract for this phase of the project has been awarded and construction has been completed –there were some liquidated
damages assessed due to the failure to achieve substantial completion prior to contract completion date. Punch list items have been
completed and close-out documents and final pay application are being reviewed for processing.
DEFERRED MAINTENANCE 2012 PACKAGE B
A/E: Burns and McDonnell
Description: The scope of this phase consists of the installation of various sections of concrete encased electrical ductbank that will be used in
other construction packages of this overall project.
Contractor: A. West Enterprise
MBE: 100% (Economically Deprived Woman Owned Small Business)
Contract: Design-Bid-Build: $1,077,123.00
Schedule: Notice to proceed: 4/1/2015
Substantial Completion: 9/8/2015 - pending per inspection by A/E
Status: This phase of the project has been declared substantially complete. The contractor is currently completing punch list items and
assembling the close-out documents and final pay application.
2013-14 MAINTENANCE NEEDS – PACKAGE A
A/E: Burns and McDonnell
Description: The scope of this phase consists of the conversion of power from 4kV to 12kV for the Shoebox dormitories, and provide power to the
new Core Campus development. An alternate pricing package was also requested for this phase. Alternate Number One will provide
conversion from 4kV to 12kV for the fraternity quad, Tennis /Soccer Area, and intramural fields along SC Route 93.
Contractor: A. West Enterprise.
MBE: 100% (Economically Deprived Woman Owned Small Business)
Contract: Design-Bid-Build: $1,692,304.00
Schedule: Notice to proceed: 7/24/2015
Substantial Completion: 2/6/2016 (Base Bid); 5/16/2016 (Alternate No. One)
Status: The construction contract for this phase of the project has been awarded and construction is in progress.
22
2013-14 MAINTENANCE NEEDS – PACKAGE B
A/E: Burns and McDonnell
Description: The scope of this phase consists of the upgrade of the electrical distribution system to serve the new Energy Facility, Football
Operations, and renovated Littlejohn.
Contractor: A West Enterprise
MBE: 100% (Economically Deprived Woman Owned Small Business)
Contract: Design-Bid-Build: $797,123.00
Schedule: Notice to proceed: 2/24/2016
Substantial Completion: 9/14/2016
Status: The contractor is currently procuring material and mobilizing to begin construction.
23
LITTLEJOHN COLISEUM RENOVATION – H12-9914
Project Budget: $63,500,000.00 (Final/Phase 2)
Source of Funds: Revenue bonds
Project Manager: Bill Muth
Description: A comprehensive renovation of the nearly 50-year old Littlejohn Coliseum will include an upgraded playing arena and seating bowl
(with 8,500 seats), increased premium level seating, and an NCAA regulation practice facility. Men’s and women’s coaches offices,
weight rooms, locker rooms, recruitment gathering spaces, and video editing/theater areas will also be included in the upgraded practice
facility. A large significant transformation to the exterior will be made reflecting a new state-of-the-art facility. A large ceremonial
entry way and two additional enhanced functional entry ways on the south corners will be added.
A/E: LS3P Architects with AECOM
Contractor: Turner Construction Company
MBE: 8.2% (to date)
Schedule: Final Approval: April 18, 2015
Notice to proceed: May 11, 2015
Substantial Completion: October 2016
Status: The GMP for construction was set at $53,415,000.00. The project is on schedule and within budget.
Coliseum – The concrete seating risers in the lower bowl have been completed and the four new super vomitories, which dramatically
enhance the openness of the space, have been completed. New court lighting trusses have been erected to the roof structure and the
event court slab has been prepared for the wood court floor. The installation of the new scoreboard is schedule in April, followed by
court flooring and the new seating. At the exterior, steel framing for the new insulated metal panels to cover the existing Cor-Ten steel
roof girders has been completed and the metal panels are beginning to be erected.
Swann Pavilion – The steel erection and cast in place concrete work are substantially complete except for miscellaneous slabs and ramps.
The existing truck tunnel has now been permanently closed from the Avenue of Champions and the resulting slab on grade in the practice
court has been poured to complete that floor. Metal stud framing for interior partitions is substantially complete and these partitions are
being one-sided with drywall to allow MEP rough-in to continue. Roofing at the Pavilion is well underway, as is the brick masonry.
Installation of the metal panels on the practice court will begin in early April.
24
25
FARM ANIMAL RESEARCH CENTER – P20-9545
Project Budget: $3,600,000.00 (Final/Phase 2)
Source of Funds: State Appropriated Funds
Project Manager: Channon Chambers
Description: This project involves the renovation of several small animal facilities at both the LaMaster Dairy Center and the Simpson Experiment
Station. The renovations will facilitate research for sheep, steers, and cows. The project has been organized as ten (10) smaller
construction components.
A/E: CDA Architects, Summit Engineering, RMF Engineering, Land Planning Associates
Contractor: J. Davis Construction, Inc., Westminster, SC, J&M Construction, Anderson, SC
MBE: 0.0%
Contract: Design-Bid-Build - $348,674.75 (Sheep Barn); $296,588.45 (Forage Research)
Schedule: Notice to proceed: September 2013 (Sheep Barn); August 2014 (Forage Research)
Substantial Completion: May 2014 (Sheep Barn); January 2015 (Forage Research)
Status: Bids are due April 14, 2016, for the construction of a new 29,360 square foot free stall barn at Lamaster Dairy.
.
26
FOOTBALL OPERATIONS FACILITY – H12-9922
Project Budget: $55,000,000.00 (Final/Phase 2)
Source of Funds: Private Gifts - Athletics
Project Manager: Paul Borick
Description: This project is to construct an approximately 142,000 square foot facility which will house all football operational functions. The facility
will include coaches’ offices, team meeting rooms, recruiting areas, student-athlete/coaches locker rooms, a weight room, equipment
room, dining areas, and related spaces. The facility will be constructed on the southwest side of the indoor practice facility adjacent to
the outdoor practice fields and will bring all football activity into close proximity. Football operations facilities are a major component
of competitiveness in the conferences in which Clemson competes for student athletes. Major reasons for Clemson’s lack of
competitiveness in these areas are attributable to the lack of non-contiguous football facilities, exclusive training and rehab space for
football, food service, and condensed weight room space. Current facilities are not sufficient in square footage and an additional 45%
increase in square footage would place the University more in line with comparable football facilities across the nation. It is equally
important that the location of the building be adjacent to the current indoor and outdoor football practice facilities. Further, NCAA
governance changes continue to affect both staff sizes and additional programming that the University can provide to its student athletes.
This new building will allow the Athletic Department to better serve the needs of its student athletes now and will provide needed space
in the future as additional governance changes take place.
A/E: Goodwyn Mills Cawood with HOK
Contractor: DPR Construction + Sherman Construction
MBE: 4% (to date)
Schedule: Final Approval: November 10, 2015
Notice to proceed: December 2015
Substantial Completion: February 2017 (estimated)
Status: Goodwyn Mills Cawood/HOK issued a CD review set of documents on 3/15/16. OSE is now reviewing these documents and DPR +
Sherman is issuing these documents to subcontractors for final pricing.
Deep foundation installation and soil stabilization work are now complete. Structural steel is on site and steel erection began in early
March. Underground utility work is nearing completion. The CM at Risk contractor is working to have the GMP finalized in the third
quarter of 2016. Value engineering has been ongoing for several weeks and the project is now within 5% of targeted estimates. VE
efforts will continue until budget issues are resolved. The project is still tracking for a February 2017 completion date and this schedule
will be confirmed in June of 2016 once the building is under roof and the majority of the subcontractor packages have been procured.
27
28
DOUTHIT HILLS STUDENT COMMUNITY CONSTRUCTION - H12-9899/H12-9918
Project Budget: $212,652,000.00 (Final/Phase 2)
Source of Funds: Revenue Bonds, Dining Improvement Funds, Bookstore Improvement Funds, Institution Bonds
Project Manager: Mike Parker
Description: This project will construct a student community on a 52-acre site at the entrance to the Clemson campus. The student community will
include apartment-style housing facilities of approximately 980 beds designated primarily for upper division students, residence halls
with approximately 782 beds designated for Bridge-to-Clemson students, and a central hub including a new approximately 400-seat
dining facility and spaces for retail operations, food service venues, and student services amenities. The project will include parking to
accommodate residents, visitors, and customers. Water and electrical infrastructure will be needed due to the nature of the site and
facilities to be constructed, including a new energy plant. The buildings in this project will achieve a minimum of U.S. Green Building
Council (USGBC) LEED Silver Rating.
A/E: The Boudreaux Group with Clark-Nexsen and Ayers Saint Gross
Contractor: Holder Construction Company (CM@R)
MBE: 1.13 % (to date)
Schedule: Final Approval: August 2014
Final design: November 2015
Notice to proceed: December 2014
Substantial Completion date: August 2018
Status: Component Change Order #14 is being processed to bring the total construction contract to $167,402,793.00. The GMP is forthcoming
and is expected in the early second quarter of 2016. It is also expected that the GMP will be on budget. The project is on schedule
despite the extraordinarily wet winter. Site work continues as they work to install the underground utilities. The precast erection is
nearing completion in the East Zone (Bridge Housing). Roof trusses and decking has begun in the East Zone and roofing will begin
shortly. The deep foundations for building H are approximately 75% complete. Pile caps, spread footings, retaining walls and columns
are being installed for building H. In the West Zone the deep foundations for building B are approximately 50% complete. The
foundation for building A has begun. Precast erection in the West Zone is expected to begin in late April of 2016.
29
30
Clemson University Capital Investment Update
Design Phase
DESIGN PHASE
Listed in order of projected construction start
(% value = MBE participation value/total contract amount)
31
STUDENT ACTIVITIES CENTER RENOVATION – H12-9917
Project Budget: $3,000,000.00 (Final/Phase 2)
Source of Funds: Private, Dining Improvement Funds
Project Manager: Kevin McDonough
Description: A 7,000 square foot vacated central campus agriculture building, formerly known as the Sheep Barn, which is currently used for material
storage, will be renovated into a student activity center. Due to an open floor plan, the renovated facility will include large meeting and
lecture rooms and spaces for student and academic-related functions. The renovation will include making structural improvements to
the facility, adding mechanical and electrical systems, and upgrading the building envelope to provide a comfortable, energy efficient
environment. Care will be taken to preserve the character of the facility and maintain its status on the National Register of Historic
Place.
A/E: Lord Aeck Sargent Architects
Contractor: Hood Construction, Inc. (CM@R)
MBE: 0% (to date)
Schedule: Final Approval: September 4, 2015
Final Design: January (barn) & March (site) 2016
Notice to proceed: To be determined
Substantial Completion: October 2016
Status: The A/E has completed design documents for the barn structure and is working on the final documents of the site package. Finalization
of details, utility systems, and interior furnishing needs is in progress. The contractor is presently bidding the renovation work of the
barn structure which was put out as an early package in order for work to begin as the site package is being finalized.
32
CENTRAL ENERGY FACILITY BOILER REPLACEMENT– H12-9920
Project Budget: $3,260,284.00 (Final/Phase 2)
Source of Funds: Maintenance & Stewardship Funds, FY 14-15 Lottery funds
Project Manager: Tom Minor
Description: This Project is to replace the boiler in the Central Energy Facility. The Central Energy Facility is the central boiler stream plant that
provides thermal energy to heat more than 80 buildings on the main campus. This project is essential to enhancing plant reliability,
providing redundancy, and reducing the University’s carbon footprint, as well as improving energy efficiency and meeting EPA
emissions regulations. The work will include replacing the existing 1964 coal-fired boiler with a high-efficient boiler fueled primarily
by natural gas with fuel oil backup, and removing the fuel (coal) conveyance, storage, and ash handling systems which were installed
during the original plant construction in 1948.
A/E: RMF
Contractor: To be determined
Schedule: Final Approval: March 2015
Final Design: July 2015
Notice to proceed: To be determined
Substantial Completion: To be determined
Status: Bids received exceeded available funds. The project is being re-evaluated for scope reductions.
33
ADVANCED TECHNOLOGY EDUCATION CENTER – H12-9921
Project Budget: $210,000.00 (Concept/Phase 1)
Source of Funds: Operating Revenue
Project Manager: Paul Borick
Description: This project is to construct a 24,000 square foot Advanced Technology Education Center (ATEC) that will house Clemson University
Center for Workforce Development (CUCWD). The programs will include the federally funded National Science Foundation and
Department of Labor and Economic Development Administration (EDA) concentrating on advanced manufacturing. The facility will
provide a space for enhancing public-private collaboration in areas of advanced manufacturing and engineering, where students,
industry, state agencies, and educational institutions will have access to digital learning tools, equipment, curriculum, and faculty
expertise that are also integrated into the curricula of the State’s 16 technical colleges. It will also provide incubator space for the
undergraduate students in the College of Engineering and Science entrepreneurial and innovation program to allow them to gain valuable
real world entrepreneurial and startup experience.
A/E: Lord Aeck Sargent Architects
Contractor: Harper Corporation General Contractors
Schedule: Final Approval: To be determined
Final Design: To be determined
Notice to proceed: To be determined
Substantial Completion: To be determined
Status: This project has been placed on hold.
34
ELECTRICAL DISTRIBUTION SYSTEM UPGRADES AND REPLACEMENT – H12-9923
Project Budget: $1,125,000.00 (Concept/Phase 1)
Source of Funds: Maintenance and Stewardship Funds
Project Manager: Bret McCarley (construction); Pat Crowther (procurement)
Description: This project is to upgrade the main campus electrical distribution system which was predominantly constructed in the late-1950’s through
mid-1960’s. The work will include replacing aging electrical distribution infrastructure, creating a redundant loop feed system to
eliminate single point system failure possibilities, adding communication and distribution automation capability to all switches to reduce
outage durations, and developing a central operations location to monitor and control a Distribution Automation System. It will also
include converting remaining exposed overhead electrical facilities to underground, adding metering and controls to equipment in
campus buildings with aging utility transformers and main gear, and making modifications to the campus electrical system. The project
will be multi-year to replace vulnerable sections of the aging electrical infrastructure to improve system reliability in areas which have
higher probability of failure, impacting major academic research and student life activities.
A/E: Jacobs Engineering Group
Contractor: To be determined
Schedule: Final Approval: To be determined
Final Design: To be determined
Notice to proceed: To be determined
Substantial Completion: To be determined
Status: An agreement has been made with Jacobs and they are proceeding with design documents. The project will be pursuing phase 2 approval
this summer.
35
BUSINESS AND BEHAVIORAL SCIENCES BUILDING – H12-9929
Project Budget: $5,000,000.00 (Concept/Phase 1)
Source of Funds: Capital Reserve Fund
Project Manager: Paul Borick
Description: This project is to design and construct an approximately 162,000 square foot building to relocate the College of Business and Behavioral
Science from Sirrine Hall, built in 1938. The existing antiquated academic facility no longer provides adequate space for planned growth
for modern instructional delivery methods. The College of Business and Behavioral Sciences (CBBS) is currently co-located with other
academic programs in Sirrine. The new facility will become the dedicated, recognizable home for all business and related disciplines
within the CBBS, and it will provide space for the college’s administrative offices, outreach centers and research institutes. The new
facility will include a variety of classrooms and learning laboratories, faculty and administrative offices, study and gathering spaces,
student services spaces and common areas that will encourage greater collaboration among students, faculty, staff and business partners.
The new facility will provide an enhanced interface between academics and industry, accommodate growth and provide flexibility to
adapt to advancements in technology and instructional methods. Construction of the new facility will also allow Sirrine Hall to be
utilized as swing space, which will allow for the systematic renovation of other aging campus facilities.
A/E: LS3P Associates with LMN Architects
Contractor: To be determined
MBE: 0% (to date)
Schedule: Final Approval: To be determined
Final Design: To be determined
Notice to proceed: To be determined
Substantial Completion: To be determined
Status: Interviews with shortlisted design firms were held on March 10, 2016. The team of LS3P Associates with LMN Architects was selected
as the most qualified firm for this project. Contract negotiations are now underway.