city of rainier railroad crossings 1. project # 2 team members psu city of rainier lars gare, city...

37
CITY OF RAINIER CITY OF RAINIER RAILROAD CROSSINGS RAILROAD CROSSINGS 1

Upload: brendan-greene

Post on 03-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

CITY OF RAINIER CITY OF RAINIER

RAILROAD CROSSINGSRAILROAD CROSSINGS

1

Page 2: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Project # 2 Team MembersPSU

City of Rainier• Lars Gare, City Administrator

ODOT Rail• David Lanning, Crossing Safety/Compliance

• Matthew DeGeorge

• Robert Acevedo

• Josh Crain

• Heather Wenstrand

• Jim Harvey

• Chris Penka

 

2

Page 3: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Presentation Outline

• Introduction

• Existing Conditions

• Future Conditions

• Intersection Alternative Designs

• Conclusion

3

Page 4: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Scope

1. To design safe railroad crossings that maximizes the movement of people and goods.

2. Design safe pedestrian crossing across the railroad tracks.

3. To design effective intersection closures that minimizes the impact on traffic and the community.

4

Page 5: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Background• The City of Rainier is on the south bank of the

Columbia River across from Longview, Washington.

• This project is part of the Rainier Waterfront Urban Renewal Plan.

• The closing of the Trojan nuclear power plant set off a decline in the number of businesses in the city.

• The current population is around 2,000 people.

• Freight trains with 110 railcars pass through downtown Rainier along A Street.

5

Page 6: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Project Overview• Project consists of:

– Design closing for 3 crossings– Redesign 4 crossings

• The City of Rainier has no dedicated engineering staff.– Lars Gare, City Administrator

• ODOT Rail has final design approval– Dave Lanning, Crossing Safety/Compliance

6

Page 7: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Existing ConditionsRainier, Oregon

Trains Getting More Frequent and Getting LongerA Street all AccessFoss Trucks Backing in on 6th StDowntown Shops 10 Delivery/Week

7

Page 8: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

“A” Street2nd Street E

1st Street

6th Street E8

Page 9: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

2nd Street West has largest traffic volume Near Post Office

Peak Volume < 300 vph Operating well below capacity No additional studies needed

9

Traffic Conditions

A Street & 2nd St W

10:05 am to 10:20 am

15-Minute Interval Summary10:05 am to 10:20 am

Interval Northbound Southbound Eastbound Westbound PedestriansStart 2nd St W Post Office A Street A Street Interval CrosswalkTime L T R Bikes L T R Bikes L T R Bikes L T R Bikes Total North South East WestTotal

Survey10 X 8 0 1 2 1 0 X 4 9 0 12 7 X 0 54 X 0 X 1

Peak Hour EstimatePHF = 0.75

Interval Northbound Southbound Eastbound Westbound PedestriansStart 2nd St W Post Office A Street A Street Interval CrosswalkTime L T R Bikes L T R Bikes L T R Bikes L T R Bikes Total North South East WestTotal

Survey53 X 43 0 5 11 5 0 X 21 48 0 64 37 X 0 288 X 0 X 5

Wednesday, February 11, 2009 InOut

OutIn

In

Out

Out

In

Peak Hour SummaryPHF = 0.75

96

12343

10169

9569

X

21X

53

X 21 48

X 37 64

5

11

5

X

1

0X

Page 10: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Future Conditions

• Railroad’s Plans-– The “A” Street Streetscape and Railroad

Safety Project is a commercial street reconstruction project aimed at improving rail functionality and providing safety to the surrounding community.

• Street Improvements include;– Separation of heavy rail from other street

network users. Rail curbs, crossing closures and restricted access to A Street.

10

Page 11: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

ODOT’s 3/3/1 Offer to City

• City of Rainier Responsibilities– Select 3 at-grade crossing to close, 4 for upgrade– Must produce all design & engineering plans– City is financially responsible for 1 of the 4 upgrades

• ODOT Rail– Maintains final design approval– Will finance and construct 3 crossing closures and 3

crossing upgrades

11

Page 12: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

• Future Closures– City decided due to usage and location that it would be beneficial to

close the following

• 2nd Street East

• 4th Street East

• 5th Street East

• Future Gated/Controlled– City decided that it would be necessary to allow the following

intersection to remain open however to provide control measures for safety purposes.

• 2nd Street West

• 1st Street

• 3rd Street East

• 6th Street East

12

Page 13: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

13

Page 14: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Intersection Design Alternatives

General closures General closures (3 intersections)(3 intersections)

55thth St E St E

General crossings General crossings (2 intersections)(2 intersections)

44thth St E St E 22ndnd St E St E 33rdrd St E St E 11stst St St

66thth Street E Street E 22ndnd Street W Street W

14

Page 15: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Overall Design

• A Street to become a boulevard/couplet with the train tracks in the middle.

• Current on-street diagonal parking will be replaced with parallel parking.

15

Page 16: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

16

Page 17: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

General Closure – Option 1

• “Right in, right out”• Access from cross streets maintained• Minimal signage

17

Page 18: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

General Closure – Option 1

• “Right in, right out”• Access from cross streets maintained• Minimal signage

2 Conflict Points

18

Page 19: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

General Closure – Option 2

• Permanently close cross streets• Install barricade to dead end street

19

Page 20: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

General Closure – Option 2

• Permanently close cross streets• Install barricade to dead end street

0 Conflict Points

20

Page 21: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Closed Intersections – Cost EstimateOption 1 – Right In, Right Out Option 2 – Closed Cross

Streets

3 Sign Installations $900 1 Sign Installation $300

Striping Striping

64 Feet Permanent Barricade

$7,680 32 Feet PermanentBarricade

$3,840

1 Pavement Arrow $1,620 240 Ft2 Asphalt Removal, New Sidewalk

$?

Total Cost $14,496 Total Cost $?

21

Page 22: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

General Crossing – Gated, Signed

• Install two grade crossing controls at bulb outs

22

Page 23: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

General Crossing – Gated, Signed

• Install two grade crossing controls at bulb outs

16 Conflict Points

23

Page 24: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

3rd St E / 1st St Crossings – Cost EstimateOption 1 – Non-signalized Option 2 – Signalized

10 Sign Installations $3,000 8 Sign Installations $2,400

2 RXR Pavement Markings $1,800 2 RXR Pavement Markings $1,800

2 Railroad gates $240,000 2 Railroad Gates $240,000

Signalize Intersection (4 Mast Arms)

$160,000

Total Cost $391,680 Total Cost $643,840

24

Page 25: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

2nd St W – Option 1 • Left Turn Pocket• Install two grade crossing controls at curb bulb outs

25

Page 26: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

2nd St W – Option 1 • Left Turn Pocket• Install two grade crossing controls at curb bulb outs

7 Conflict Points

26

Page 27: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

2nd St W – Option 2 • No Left Turn Pocket• Install two grade crossing controls at curb bulb outs

27

Page 28: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

2nd St W – Option 2 • No Left Turn Pocket• Install two grade crossing controls at curb bulb outs

28

8 Conflict Points

Page 29: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

2nd St W Crossings – Cost EstimateOption 1 – Non-signalized Option 2 – Signalized

10 Sign Installations $3,000 8 Sign Installations $2,400

2 RXR Pavement Markings $1,800 2 RXR Pavement Markings $1,800

2 Railroad gates $240,000 2 Railroad Gates $240,000

(Left Turn Pocket) ($2,500) Signalize Intersection (4 Mast Arms)

$160,000

Total Cost $391,680($293,29

3)

Total Cost $643,840

29

Page 30: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

6th St E – Option 1 • Uncontrolled Crossing • Signing and Striping Only• 150-feet of Open Track

30

Page 31: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

6th St E – Option 1 • Uncontrolled Crossing • Signing and Striping Only• 150-feet of Open Track

31

4 Conflict Points

Page 32: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

6th St E – Option 2 • Uncontrolled Crossing • Signing and Striping Only• 100-feet of Open Track

32

Page 33: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

6th St E – Option 2 • Uncontrolled Crossing • Signing and Striping Only• 100-feet of Open Track

33

4 Conflict Points

Page 34: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

6th St E – Cost Estimate

Option 1 – 150 feet open track Option 2 – 100 feet open track

9 Sign Installations $2,700 9 Sign Installations $2,700

660 Feet Striping $660 460 Feet Striping $460

3 Pavement Arrows,1 RXR Pavement Marking

$1,620 3 Pavement Arrows,1 RXR Pavement Marking

$1,620

(1 Train Warning Light) $50,000 (1 Train Warning Light) $50,000

Total Cost(with warning light)

$4,980($54,980)

Total Cost(with warning light)

$4,780($54,780)

34

Page 35: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Intersection Cost Estimates

35

Lowest Cost Highest Cost

2nd Street West $2,700 2nd Street West $2,700

1st Street $660 1st Street $460

2nd Street East $1,620 2nd Street East $1,620

3rd Street East 3rd Street East

4th Street East $1,620 4th Street East $1,620

5th Street East 5th Street East

6th Street East $4,780 6th Street East $54,980

Subtotal $7,968 Subtotal $7,648

Page 36: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

Total Cost Estimate

36

Undefined costs: ROW, Curb, ADA, Removal

Lowest Cost Highest Cost

Intersection Subtotals $2,700 Intersection Subtotals $2,700

Mobilization (10%) $498 Mobilization (10%) $478

Temporary Traffic Control (5%)

$249 Temporary Traffic Control (5%)

$239

Overhead & Profit (15%) $747 Overhead & Profit (15%) $717

Contingency (30%) $1,494 Contingency (30%) $1,434

Total Cost $7,968 Total Cost $7,648

Page 37: CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members PSU City of Rainier Lars Gare, City Administrator ODOT Rail David Lanning, Crossing Safety/Compliance

The Next Phase

• Week 1 - Design 3 intersection closures

• Week 2 & 3 - Design the general railroad crossings. Intersections 1st and 3rd St E

• Week 4 & 5 - Design 2nd St W (Post Office)

• Week 6 & 7 - Design 6th St E (Foss)

• Week 8 - Overall review and finalize designs

• Week 9 & 10 – Presentation preperation37