city of rainier railroad crossings 1. project # 2 team members psu city of rainier lars gare, city...
TRANSCRIPT
CITY OF RAINIER CITY OF RAINIER
RAILROAD CROSSINGSRAILROAD CROSSINGS
1
Project # 2 Team MembersPSU
City of Rainier• Lars Gare, City Administrator
ODOT Rail• David Lanning, Crossing Safety/Compliance
• Matthew DeGeorge
• Robert Acevedo
• Josh Crain
• Heather Wenstrand
• Jim Harvey
• Chris Penka
2
Presentation Outline
• Introduction
• Existing Conditions
• Future Conditions
• Intersection Alternative Designs
• Conclusion
3
Scope
1. To design safe railroad crossings that maximizes the movement of people and goods.
2. Design safe pedestrian crossing across the railroad tracks.
3. To design effective intersection closures that minimizes the impact on traffic and the community.
4
Background• The City of Rainier is on the south bank of the
Columbia River across from Longview, Washington.
• This project is part of the Rainier Waterfront Urban Renewal Plan.
• The closing of the Trojan nuclear power plant set off a decline in the number of businesses in the city.
• The current population is around 2,000 people.
• Freight trains with 110 railcars pass through downtown Rainier along A Street.
5
Project Overview• Project consists of:
– Design closing for 3 crossings– Redesign 4 crossings
• The City of Rainier has no dedicated engineering staff.– Lars Gare, City Administrator
• ODOT Rail has final design approval– Dave Lanning, Crossing Safety/Compliance
6
Existing ConditionsRainier, Oregon
Trains Getting More Frequent and Getting LongerA Street all AccessFoss Trucks Backing in on 6th StDowntown Shops 10 Delivery/Week
7
“A” Street2nd Street E
1st Street
6th Street E8
2nd Street West has largest traffic volume Near Post Office
Peak Volume < 300 vph Operating well below capacity No additional studies needed
9
Traffic Conditions
A Street & 2nd St W
10:05 am to 10:20 am
15-Minute Interval Summary10:05 am to 10:20 am
Interval Northbound Southbound Eastbound Westbound PedestriansStart 2nd St W Post Office A Street A Street Interval CrosswalkTime L T R Bikes L T R Bikes L T R Bikes L T R Bikes Total North South East WestTotal
Survey10 X 8 0 1 2 1 0 X 4 9 0 12 7 X 0 54 X 0 X 1
Peak Hour EstimatePHF = 0.75
Interval Northbound Southbound Eastbound Westbound PedestriansStart 2nd St W Post Office A Street A Street Interval CrosswalkTime L T R Bikes L T R Bikes L T R Bikes L T R Bikes Total North South East WestTotal
Survey53 X 43 0 5 11 5 0 X 21 48 0 64 37 X 0 288 X 0 X 5
Wednesday, February 11, 2009 InOut
OutIn
In
Out
Out
In
Peak Hour SummaryPHF = 0.75
96
12343
10169
9569
X
21X
53
X 21 48
X 37 64
5
11
5
X
1
0X
Future Conditions
• Railroad’s Plans-– The “A” Street Streetscape and Railroad
Safety Project is a commercial street reconstruction project aimed at improving rail functionality and providing safety to the surrounding community.
• Street Improvements include;– Separation of heavy rail from other street
network users. Rail curbs, crossing closures and restricted access to A Street.
10
ODOT’s 3/3/1 Offer to City
• City of Rainier Responsibilities– Select 3 at-grade crossing to close, 4 for upgrade– Must produce all design & engineering plans– City is financially responsible for 1 of the 4 upgrades
• ODOT Rail– Maintains final design approval– Will finance and construct 3 crossing closures and 3
crossing upgrades
11
• Future Closures– City decided due to usage and location that it would be beneficial to
close the following
• 2nd Street East
• 4th Street East
• 5th Street East
• Future Gated/Controlled– City decided that it would be necessary to allow the following
intersection to remain open however to provide control measures for safety purposes.
• 2nd Street West
• 1st Street
• 3rd Street East
• 6th Street East
12
13
Intersection Design Alternatives
General closures General closures (3 intersections)(3 intersections)
55thth St E St E
General crossings General crossings (2 intersections)(2 intersections)
44thth St E St E 22ndnd St E St E 33rdrd St E St E 11stst St St
66thth Street E Street E 22ndnd Street W Street W
14
Overall Design
• A Street to become a boulevard/couplet with the train tracks in the middle.
• Current on-street diagonal parking will be replaced with parallel parking.
15
16
General Closure – Option 1
• “Right in, right out”• Access from cross streets maintained• Minimal signage
17
General Closure – Option 1
• “Right in, right out”• Access from cross streets maintained• Minimal signage
2 Conflict Points
18
General Closure – Option 2
• Permanently close cross streets• Install barricade to dead end street
19
General Closure – Option 2
• Permanently close cross streets• Install barricade to dead end street
0 Conflict Points
20
Closed Intersections – Cost EstimateOption 1 – Right In, Right Out Option 2 – Closed Cross
Streets
3 Sign Installations $900 1 Sign Installation $300
Striping Striping
64 Feet Permanent Barricade
$7,680 32 Feet PermanentBarricade
$3,840
1 Pavement Arrow $1,620 240 Ft2 Asphalt Removal, New Sidewalk
$?
Total Cost $14,496 Total Cost $?
21
General Crossing – Gated, Signed
• Install two grade crossing controls at bulb outs
22
General Crossing – Gated, Signed
• Install two grade crossing controls at bulb outs
16 Conflict Points
23
3rd St E / 1st St Crossings – Cost EstimateOption 1 – Non-signalized Option 2 – Signalized
10 Sign Installations $3,000 8 Sign Installations $2,400
2 RXR Pavement Markings $1,800 2 RXR Pavement Markings $1,800
2 Railroad gates $240,000 2 Railroad Gates $240,000
Signalize Intersection (4 Mast Arms)
$160,000
Total Cost $391,680 Total Cost $643,840
24
2nd St W – Option 1 • Left Turn Pocket• Install two grade crossing controls at curb bulb outs
25
2nd St W – Option 1 • Left Turn Pocket• Install two grade crossing controls at curb bulb outs
7 Conflict Points
26
2nd St W – Option 2 • No Left Turn Pocket• Install two grade crossing controls at curb bulb outs
27
2nd St W – Option 2 • No Left Turn Pocket• Install two grade crossing controls at curb bulb outs
28
8 Conflict Points
2nd St W Crossings – Cost EstimateOption 1 – Non-signalized Option 2 – Signalized
10 Sign Installations $3,000 8 Sign Installations $2,400
2 RXR Pavement Markings $1,800 2 RXR Pavement Markings $1,800
2 Railroad gates $240,000 2 Railroad Gates $240,000
(Left Turn Pocket) ($2,500) Signalize Intersection (4 Mast Arms)
$160,000
Total Cost $391,680($293,29
3)
Total Cost $643,840
29
6th St E – Option 1 • Uncontrolled Crossing • Signing and Striping Only• 150-feet of Open Track
30
6th St E – Option 1 • Uncontrolled Crossing • Signing and Striping Only• 150-feet of Open Track
31
4 Conflict Points
6th St E – Option 2 • Uncontrolled Crossing • Signing and Striping Only• 100-feet of Open Track
32
6th St E – Option 2 • Uncontrolled Crossing • Signing and Striping Only• 100-feet of Open Track
33
4 Conflict Points
6th St E – Cost Estimate
Option 1 – 150 feet open track Option 2 – 100 feet open track
9 Sign Installations $2,700 9 Sign Installations $2,700
660 Feet Striping $660 460 Feet Striping $460
3 Pavement Arrows,1 RXR Pavement Marking
$1,620 3 Pavement Arrows,1 RXR Pavement Marking
$1,620
(1 Train Warning Light) $50,000 (1 Train Warning Light) $50,000
Total Cost(with warning light)
$4,980($54,980)
Total Cost(with warning light)
$4,780($54,780)
34
Intersection Cost Estimates
35
Lowest Cost Highest Cost
2nd Street West $2,700 2nd Street West $2,700
1st Street $660 1st Street $460
2nd Street East $1,620 2nd Street East $1,620
3rd Street East 3rd Street East
4th Street East $1,620 4th Street East $1,620
5th Street East 5th Street East
6th Street East $4,780 6th Street East $54,980
Subtotal $7,968 Subtotal $7,648
Total Cost Estimate
36
Undefined costs: ROW, Curb, ADA, Removal
Lowest Cost Highest Cost
Intersection Subtotals $2,700 Intersection Subtotals $2,700
Mobilization (10%) $498 Mobilization (10%) $478
Temporary Traffic Control (5%)
$249 Temporary Traffic Control (5%)
$239
Overhead & Profit (15%) $747 Overhead & Profit (15%) $717
Contingency (30%) $1,494 Contingency (30%) $1,434
Total Cost $7,968 Total Cost $7,648
The Next Phase
• Week 1 - Design 3 intersection closures
• Week 2 & 3 - Design the general railroad crossings. Intersections 1st and 3rd St E
• Week 4 & 5 - Design 2nd St W (Post Office)
• Week 6 & 7 - Design 6th St E (Foss)
• Week 8 - Overall review and finalize designs
• Week 9 & 10 – Presentation preperation37