cirompang

Upload: nangkarak8201

Post on 18-Oct-2015

19 views

Category:

Documents


0 download

DESCRIPTION

PDD_Cirompang_MHPP

TRANSCRIPT

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    1

    CLEAN DEVELOPMENT MECHANISM

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)

    Version 03 - in effect as of: 22 December 2006

    CONTENTS

    A. General description of the small scale project activity

    B. Application of a baseline and monitoring methodology

    C. Duration of the project activity / crediting period

    D. Environmental impacts

    E. Stakeholders comments

    Annexes

    Annex 1: Contact information on participants in the proposed small scale project activity

    Annex 2: Information regarding public funding

    Annex 3: Baseline information

    Annex 4: Monitoring Information

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    2

    Revision history of this document

    Version Number

    Date Description and reason of revision

    01 21 January

    2003

    Initial adoption

    02 8 July 2005 The Board agreed to revise the CDM SSC PDD to reflect guidance and clarifications provided by the Board since

    version 01 of this document.

    As a consequence, the guidelines for completing CDM SSC PDD have been revised accordingly to version 2. The latest

    version can be found at

    .

    03 22 December

    2006 The Board agreed to revise the CDM project design

    document for small-scale activities (CDM-SSC-PDD), taking

    into account CDM-PDD and CDM-NM.

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    3

    SECTION A. General description of small-scale project activity

    A.1 Title of the small-scale project activity:

    8MW Cirompang Mini Hydro Power Plants at Bungbulang, Garut, Indonesia.

    Version : 3.1 Date : 29/08/2012

    A.2. Description of the small-scale project activity:

    The project activity hereinafter referred to as Project is a new 8 MW run-of-river hydroelectric power plant being developed by PT. Tirta Gemah Ripah (TGR) in Garut district, West Java Province, Indonesia.

    The purpose of the project activity is generation of clean hydroelectric power and delivery to Jamali Grid.

    The project will be constructed on Cirompang River.

    The project activity is run-off river project which is taking place in the existing reservoir. The PP has

    received approval to use the water for power generation. There will be no modification done by PP in

    existing reservoir for use of water for power generation.

    The project is expected to generate net electricity of 47471 MWh/year and expected to bring about GHG

    emission reductions of approximately 33,847 tCO2e annually. Hence project activity would contribute to

    reduction of CO2 emissions that in the absence of the project activity would have otherwise happened by

    gird connected fossil fuel plants.

    The project complies with the sustainable development criterias of the host country in the following manner:

    Environment:

    The project activity is a run-of-river hydroelectric power plant. It is a well established technology which

    utilizes water for energy generation without depleting it or impacting the natural environment. Since the

    project activity generates electricity from renewable source, it avoids emission such as SOx , NOx and

    other particulates matter which would have been emitted from the fossil fuel fired plants.

    Social:

    Project will aid development of social infrastructure in the region such as roads and water supply. Project

    will create job opportunities during the construction and operation stage.

    Economy:

    Project activity will create new jobs both skilled and unskilled for local population. This increase in

    employment will stimulate local economy.

    Technology:

    The project will contribute to development of technological capacity building in the country as the project

    will be implemented with local engineers as well as local labour who will work on the construction.

    A.3. Project participants:

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    4

    Name of Party involved (*)

    ((host) indicates a host Party)

    Private and/or public

    entity(ies)

    Project participants (*)

    (as applicable)

    Kindly indicate if the party

    involved wishes to be

    considered as project

    participant (yes/no)

    Sweden Nordic Environment Finance

    Corporation NEFCO in its

    capacity as Fund Manager to the

    NEFCO Carbon Fund (NeCF) Public Entity

    No

    Indonesia (Host) PT. Tirta Gemah Ripah (Public

    Entity)

    No

    (*) In accordance with the CDM modalities and procedures, at the time of making the CDM-PDD public

    at the stage of validation, a Party involved may or may not have provided its approval. At the time of

    requesting registration, the approval by the Party(ies) involved is required.

    The carbon purchaser is the Nordic Environment Finance Corporation NEFCO in its capacity as Fund

    Manager to the NEFCO Carbon Fund (NeCF)

    NEFCO Carbon Fund (NeCF)

    NEFCO, the Nordic Environment Finance Corporation, is a multilateral risk capital institution financing

    environmental projects in Central and Eastern Europe, with an emphasis on the Russian Federation and

    Ukraine. Its purpose is to facilitate the implementation of environmentally beneficial projects in the

    neighbouring region, with transboundary effects that also benefit the Nordic region. Today, NEFCO

    manages funds in an aggregate of approximately 470 million. NEFCO is located in Helsinki, Finland.

    The NEFCO Carbon Fund (NeCF) was established as a Public Private Partnership in April 2008, to

    provide financial assistance to projects by purchasing emission reduction credits from projects under the

    JI and CDM mechanisms. The NEFCO Carbon Fund (NeCF) has the Danish Energy Agency, DONG

    Energy, Eesti Energia, the Industrialization Fund for Developing Countries (Denmark), Ministries of

    Environment and Foreign Affairs of Finland, Etel-Pohjanmaan Voima Oy (Finland), Kymppivoima Oy

    (Finland), GDF Suez, the Norwegian Finance Ministry and NEFCO itself, as participants in the fund. The

    total available resources are ca. 165 million.

    NEFCO is the Fund Manager of the NeCF, and has been authorized by the governments investing in the

    NeCF to participate on their behalf in actions leading to the generation, transfer and acquisition of CERs

    under Article 12 of the Kyoto Protocol

    A.4. Technical description of the small-scale project activity:

    A.4.1. Location of the small-scale project activity:

    A.4.1.1. Host Party(ies):

    Country: Indonesia

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    5

    A.4.1.2. Region/State/Province etc.:

    Province: West Java

    A.4.1.3. City/Town/Community etc:

    Village: Cihikeu and Bungbulang

    Sub District: Bungbulang

    District: Garut

    A.4.1.4. Details of physical location, including information allowing the

    unique identification of this small-scale project activity :

    The geographical coordinates of the project site are

    o Dam : North Latitude: -7.4505 , East Longitude: +107.6093

    o Power House : North Latitude: -7.4762 , East Longitude: +107.6122

    .The physical location of plant site is depicted in the map below:

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    6

    Figure 1: Location planned in River Cirompang in Countryside Cihikeu & Bubbulang, District

    Gaurt

    A.4.2. Type and category(ies) and technology/measure of the small-scale project activity:

    According to the Appendix B of the simplified modalities and procedures for small-scale CDM project

    activities, project activity falls under the Type I Renewable Energy Projects. The project activity exports the generated electricity to the grid and falls in the category I. D -Grid Connected Renewable

    Electricity Generation. Following Table details the same :

    Term Description

    Type Type I, Renewable Energy Projects

    Category D, Grid Connected Renewable Electricity Generation

    Technology/Measure Renewable energy generation units (hydro) that supply

    electricity to a regional grid.

    Technology Description:

    The project is a runofriver Hydroelectric power plant on Cirompang river with a total installed capacity of 8MW consisting of 4 X 2MW turbines and a net projected output of 47, 471 MWh annually. The

    electricity generated will be transmitted to the Jamali grid via 20 kV transmission line. The main

    construction structures of the project consist of:

    Channel Intake / Weir

    Project location

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    7

    The water in the river will be diverted by the weir through an opening in the river side (the `intake') into

    an open channel.

    Line Carrier (headrace) It will channel water from the canal intake (Intake) towards sand trap.

    Sand Trap The water drawn from the river usually carries suspension of small particles. This sediment consists of

    hard abrasive materials such as sand which can cause significant damage and rapid wear to turbine

    runners. To remove this material the water flow will be slowed down in settling basins so that the silt

    particles will settle on the basin floor.

    Head Pond/Forebay Tank This head pond is not a storage area, it is meant to flood a sufficient area to regulate water current into

    Penstock.

    Penstock The penstock is like a pipe to convey water from the head pond to the powerhouse.

    Power House Here all mechanical equipment such as turbines and generators as well as electrical equipment such

    as panels and controllers will be housed.

    Turbine and Generator Four 2 MW pelton turbines will be installed. When water flows into the turbine, it turns the blades in the

    turbine which spins the generators shaft. Generator will convert the mechanical energy from the turning shaft into electrical energy.

    The characteristics of the Turbine used in the project are presented in Table 1 below.

    Table 1: Key Turbine Characteristics

    Item Parameter Type/value/Unit

    Turbines

    Type Pelton

    Efficiency at Peak 75%

    Efficiency at Design Flow 75%

    Turbine Speed 1000 m3/s

    Manufacturer Jyoti Ltd , Vadodara,

    India

    Technology Pelton

    Generator Key characteristics:

    Parameter Unit

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    8

    Number 4

    Type Synchronous, vertical axis, 3 phases

    Rated capacity 2000 kW

    Rated frequency 50 Hz

    Rated power factor 0.8

    Transmission Lines The power generated will be transmitted to the Grid via 20 KV transmission lines.

    The Table 2 below highlights Project key Technical Design data and parameters

    Table 2: Key Technical Design Data and Parameters

    Design Data /Parameters Unit Quantity

    Total Installed Capacity MW 8

    Installed Capacity of each

    Unit

    MW 2

    Annual Operating hours hours 8760

    Capacity Factor % 68.77

    Gross Head m 142

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    9

    Figure 2: Typical Scheme of run-off river system

    In case of emergency, the diesel generators will be used.

    Technology transfer and know-how

    The installation and commissioning services are from Indonesia only.

    The technology employed by the project proponent does not result in GHG emissions and the project does

    not cause any negative impacts on the environment. The technology used does not pose any threat to the

    environment in comparison to fossil fuel-fired power plants. Therefore the technology is environmentally

    safe and sound.

    A.4.3 Estimated amount of emission reductions over the chosen crediting period:

    Year

    Estimation of annual

    emission reductions in tonnes

    of CO2e

    Year 1 (01/03/2013- 28/02/2014) 33,847

    Year 2 (01/03/2014-28/02/2015) 33,847

    Year 3 (01/03/2015 -29/02/2016) 33,847

    Year 4 (01/03/2016 28/02/2017) 33,847

    Year 5 (01/03/2017 28/02/2018) 33,847

    Year 6 (01/03/2018 28/02/2019) 33,847

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    10

    Year 7 (01/03/2019 29/02/2020) 33,847

    Year 8 (01/03/2020 28/02/2021) 33,847

    Year 9 (01/03/2021 28/02/2022) 33,847

    Year 10 (01/03/2022 28/02/2023) 33,847

    Total estimated reductions (tonnes

    of CO2e) 338,470

    Total number of crediting years 10

    Annual average of the estimated

    reductions over the crediting

    period (tCO2e)

    33,847

    A.4.4. Public funding of the small-scale project activity:

    The project will not receive any public funding from Parties included in Annex I of the UNFCCC.

    A.4.5. Confirmation that the small-scale project activity is not a debundled component of a

    large scale project activity:

    According to paragraph 2 of Appendix C1 of the Simplified Modalities and Procedures for Small-Scale

    CDM project Activities, the following results into debundling of large CDM project:

    A proposed small-scale project activity shall be deemed to be a debundled component of a large project activity if there is a registered small-scale CDM project activity or an application to register another

    small-scale CDM project activity:

    With the same project participants; In the same project category and technology/measure; Registered within the previous 2 years; and Whose project boundary is within 1 km of the project boundary of the proposed small-scale activity at the closest point.

    The project activity is not a de-bundled component of a large project activity as there is no small scale

    CDM project activity or an application to register another small-scale CDM project activity by Project

    Proponent (PP) in the same project category and technology in the last two years within 1 km of the

    project boundary of the proposed small scale project activity.

    SECTION B. Application of a baseline and monitoring methodology

    B.1. Title and reference of the approved baseline and monitoring methodology applied to the

    small-scale project activity:

    The project activity uses the following approved baseline and monitoring methodology available at the

    UNFCC website2is a small scale project activity and conforms to Appendix B of the simplified modalities

    and procedures for small-scale CDM project activities.

    1 http://cdm.unfccc.int/EB/Meetings/007/eb7ra07.pdf

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    11

    Title Reference Version

    Grid connected renewable electricity generation AMS-I D Version 17

    Guidance on the Assessment of Investment

    Analysis

    EB 62 Annex 5 Version 5

    Guideline to small-scale CDM Methodologies

    (Indicative Simplified Baseline and Monitoring

    Methodologies for selected Small Scale CDM

    Project Activity Categories)

    EB 61 Annex 21 Version 17

    Tool to calculate the emission Factor for an

    electricity system EB 63 Annex 19 Version 2.2.1

    Tool to calculate project or leakage CO2 emission

    from fossil fuel consumption

    EB 41, Annex 11 Version 2

    B.2 Justification of the choice of the project category:

    Applicability of AMS I. D:

    The project activity utilizes the hydro power for electricity generation, which falls into the category of

    renewable energy. The capacity of the proposed project activity is 8 MW which is below 15 MW, the

    eligibility limit of 15 MW for a small-scale CDM project activity applies only to the renewable

    component. The project activity is in line with the approved methodology AMS. I. D Version 17; specific

    features of proposed project and applicability of methodology are discussed below:

    Applicability Criteria with AMS-I.D. Project Applicability

    1 This methodology comprises renewable energy generation

    units, such as photovoltaic, hydro, tidal/wave, wind,

    geothermal and renewable biomass:3

    (a) Supplying electricity to a national or a regional grid; or

    (b) Supplying electricity to an identified consumer facility via national/regional grid

    through a contractual arrangement such as

    wheeling.

    The project activity involves a

    renewable energy generation unit

    specifically a hydro power unit that

    displaces electricity from Jamali

    Grid, an electricity distribution

    system supplied by fossil-fuel fired

    generating units. Thus the project

    activity complies with the

    applicability criteria.

    2

    http://cdm.unfccc.int/methodologies/DB/RSCTZ8SKT4F7N1CFDXCSA7BDQ7FU1X

    3 Refer to EB 23, annex 18 or the definition of renewable biomass.

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    12

    2 Illustration of respective situations under which each of the

    methodology (i.e. AMS-I.D, AMS-I.F and AMS-I.A4) applies

    is included in Table 2.

    Project type AMS-

    I.A

    AMS-

    I.D

    AMS-

    I.F

    1 Project supplies electricity to

    a national/regional grid

    2 Project displaces grid

    electricity consumption (e.g.

    grid import) and/or captive

    fossil fuel electricity

    generation at the user end

    (excess electricity may be

    supplied to a grid)

    3 Project supplies electricity to

    an identified consumer

    facility via national/regional

    grid (through a contractual

    arrangement such as

    wheeling)

    4 Project supplies electricity to

    a mini grid5 system where in

    the baseline all generators

    use exclusively fuel oil

    and/or diesel fuel

    5 Project supplies electricity to

    household users (included in

    the project boundary) located

    in off grid areas

    The project supplies electricity to

    Jamali grid. The grid is owned by

    PT Perusahaan Listrik Negara

    (PLN), a state owned electricity

    company of Indonesia. Thus the

    project complies with the

    applicability criteria of AMS I.D

    3 This methodology is applicable to project activities that (a)

    install a new power plant at a site where there was no

    renewable energy power plant operating prior to the

    implementation of the project activity (Greenfield plant); (b)

    involve a capacity addition6; (c) involve a retrofit

    7 of (an)

    The project activity shall install a

    new power plant at a site where

    there was no renewable energy

    power plant operating prior to the

    implementation of the project

    4 AMS-I.D Grid connected renewable electricity generation, AMS-I.F Renewable electricity generation for

    captive use and mini-grid and AMS-I.A Electricity generation by the user

    5 The sum of installed capacities of all generators connected to the mini-grid is equal to or less than 15 MW.

    6 A capacity addition is an increase in the installed power generation capacity of an existing power plant through: (i)

    the installation of a new power plant besides the existing power plant/units, or (ii) the installation of new power

    units, additional to the existing power plant/units. The existing power plant/units continue to operate after the

    implementation of the project activity.

    7 Retrofit (or Rehabilitation or Refurbishment). It involves an investment to repair or modify an existing power

    plant/unit, with the purpose to increase the efficiency, performance or power generation capacity of the plant,

    without adding new power plants or units, or to resume the operation of closed (mothballed) power plants. A retrofit

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    13

    existing plant(s); or (d) involve a replacement8 of (an) existing

    plant(s).

    activity (Greenfield plant). Thus the

    Project Activity complies with the

    applicability criteria (a)

    4 Hydro power plants with reservoirs that satisfy at least one of

    the following conditions are eligible to apply this

    methodology:

    The project activity is implemented in an existing reservoir with no change in the volume of reservoir;

    The project activity is implemented in an existing reservoir, where the volume of reservoir is increased

    and the power density of the project activity, as per

    definitions given in the Project Emissions section, is

    greater than 4 W/m2;

    The project activity results in new reservoirs and the power density of the power plant, as per definitions

    given in the Project Emissions section, is greater than

    4 W/m2.

    The project activity is a run off-river and it is implemented in an

    existing reservoir. There will be no

    change in the volume of the

    reservoir. So the proposed project

    activity is implemented in the

    existing reservoir with no change in

    the volume of reservoir. Hence this

    condition is applicable to the

    project activity.

    5 If the new unit has both renewable and non-renewable

    components (e.g., a wind/diesel unit), the eligibility limit of

    15 MW for a small-scale CDM project activity applies only to

    the renewable component. If the new unit co-fires fossil fuel9,

    the capacity of the entire unit shall not exceed the limit of

    15 MW.

    The project activity has no non

    renewable component and has

    100% renewable component

    (Hydro). The capacity of the

    proposed project is 8 MW which is

    lower than 15 MW, limit set for

    small scale project activity. Hence

    this condition is applicable.

    6 Combined heat and power (co-generation) systems are not

    eligible under this category.

    There is no Combined heat and

    power (co-generation) in the project

    activity. Thus the project activity

    complies with the applicability

    criteria.

    7 In the case of project activities that involve the addition of

    renewable energy generation units at an existing renewable

    power generation facility, the added capacity of the units

    The project activity does not that

    involve the addition of renewable

    energy generation units at an

    existing renewable power

    restores the installed power generation capacity to or above its original level. Retrofits shall only include measures

    that involve capital investments and not regular maintenance or housekeeping measures.

    8 Replacement. It involves investment in a new power plant or unit that replaces one or several existing unit(s) at the

    existing power plant. The installed capacity of the new plant or unit is equal to or higher than the plant or unit that

    was replaced.

    9 A co-fired system uses both fossil and renewable fuels.

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    14

    added by the project should be lower than 15 MW and should

    be physically distinct10

    from the existing units. generation facility. Hence this

    condition is not applicable to the

    project activity.

    8 In the case of retrofit or replacement, to qualify as a small-

    scale project, the total output of the retrofitted or replacement

    unit shall not exceed the limit of 15 MW.

    The project activity does not seek

    to any retrofit or replacement.

    Hence this condition is not

    applicable to the project activity.

    Summary: It can be concluded based from the above discussion that the project activity meets the

    applicability criteria of approved small scale methodologies AMS I.D

    B.3. Description of the project boundary:

    According to the paragraph 9 of the small scale methodology AMS-I.D. Version 17 The spatial extent of the project boundary includes the project power plant and all power plants connected physically

    to the electricity system11

    that the CDM project power plant is connected to. For the project activity, the generated electricity of the project will be delivered to the Jamali Grid, and the auxiliary internal power

    consumption of hydropower plants is also contained in the project boundary. Also in case of emergency,

    the diesel generators will be used and it comes under project boundary. A general schematic view of the

    boundaries is shown in figure below.

    10 Physically distinct units are those that are capable of generating electricity without the operation of existing units,

    and that do not directly affect the mechanical, thermal, or electrical characteristics of the existing facility. For

    example, the addition of a steam turbine to an existing combustion turbine to create a combined cycle unit would not

    be considered physically distinct.

    11 Refer to the latest approved version of the Tool to calculate the emission factor for an electricity system for definition of an electricity system.

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    15

    Table 3 below Summary of gases and sources included in the project boundary, and justification

    explanation where gases and sources are not included:

    Scenario Source Gas Included/

    Excluded

    Justification/Explanation

    Baseline

    scenario

    Electricity

    Delivered to the

    grid by the

    CO2 Included Main Emission Source.

    N2O Excluded Not Significant. Excluded for simplification and

    conservativeness.

    Existing reservoir

    Tunnel

    Penstock

    Power house

    Transformer

    Jamali Grid

    Diesel Generator (In case of

    emergency, it will be used)

    Project boundary

    CO2 emission

    from diesel

    generator

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    16

    project activity

    that otherwise

    would have

    been generated

    by the operation

    of grid

    connected

    power plants

    and by the

    addition of new

    generation

    sources.

    CH4 Excluded Not Significant. Excluded for simplification and

    conservativeness.

    Project

    activity

    Emissions

    associated with

    the operation of

    the project

    CO2 Included Emission from the diesel generator.

    N2O Excluded Not Significant. Excluded for simplification and

    conservativeness.

    CH4 Excluded Not Significant. Excluded for simplification and

    conservativeness.

    B.4. Description of baseline and its development:

    Baseline Scenario:

    As per applicable methodology AMS I. D version 17, EB 61 paragraph 10 : the baseline scenario is that

    the electricity delivered to the grid by the project activity would have otherwise been generated by the

    operation of grid-connected power plants and by the addition of new generation sources into the grid.

    Hence in the project scenario the electricity delivered to the Jamali grid by the project activity would have

    otherwise been generated by the operation of grid connected power plants and by the addition of new

    generation sources into the grid.

    Data used to determine the baseline emissions:

    The Emission Factor is calculated in a transparent and conservative manner as follows:

    A combined margin (CM), consisting of the combination of operating margin (OM) and build margin

    (BM) according to the procedures prescribed in the Tool to calculate the Emission Factor for an electricity system, version 2.2.1, EB 63 Annex 19.

    The Directorate General Electricity and Energy Utilization (DJLPE, Direktorat Jenderal Listrik dan

    Pemanfaatan Energi), a government institution has issued an official baseline emission factor for the

    Jamali grid which is available from.

    http://pasarkarbon.dnpi.go.id/web/index.php/komnasmpb/read/20/faktor-emisi-jaringan-listrik-jawa-

    madura-bali-jamali-2010-.html

    The calculation method opted for expost grid emission factor is as per Tool to calculate the Emission Factor for an electricity system, version 2.2.1, EB 63 Annex 19 is presented in Annex 3 of the PDD.

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    17

    The parameters considered in the baseline calculation as presented in table below:

    Parameter Unit Description Source of data to

    be used

    EGBL,y MWh Net electricity supplied to the grid Electricity meter

    EFgrid,CM,y tCO2/MWh Combined margin CO2 emission factor

    for grid connected power generation in

    year y

    As published by

    Host Country

    DNA

    EFgrid,BM,y tCO2/MWh Build margin CO2 emission factor for

    grid connected power generation in year

    As published by

    Host Country

    DNA

    EFgrid,OM,y tCO2/MWh Operating margin CO2 emission factor

    for grid connected power generation in

    year

    As published by

    Host Country

    DNA

    B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below

    those that would have occurred in the absence of the registered small-scale CDM project activity:

    The project activity is additional as per the options provided under Non-binding best practice examples to demonstrate additionality for SSC project activities.

    According to the Non-binding best practice examples to demonstrate additionality for SSC project

    activities (EB 35, Annex 34):

    a. Project participants shall provide an explanation to show that the project activity would not have occurred anyway due to at least one of the following barriers: Investment barrier: a financially

    more viable alternative to the project activity would have led to higher emissions;

    b. Access-to-finance barrier: the project activity could not access appropriate capital without

    consideration of the CDM revenues

    c. Technological barrier: a less technologically advanced alternative to the project activity involves lower risks due to the performance uncertainty or low market share of the new technology

    adopted for the project activity and so would have led to higher emissions

    d. Barrier due to prevailing practice: prevailing practice or existing regulatory or policy requirements would have led to implementation of a technology with higher emissions

    e. Other barriers: without the project activity, for another specific reason identified by the project participant, such as institutional barriers or limited information, managerial resources,

    organizational capacity, financial resources, or capacity to absorb new technologies, emissions

    would have been higher.

    Among the multiple barriers identified in the implementation of the project activity, the investment

    barrier analysis is used to demonstrate the financial non-viability of the project activity in a conservative

    and transparent manner. The project activity involves high investment cost. The returns generated from

    the project activity are low and hence the CDM funds are considered essential for improving the returns

    generated from the project.

    Investment barrier

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    18

    The investment barrier has been demonstrated in accordance with the Non-binding best practice examples

    to demonstrate additionality for SSC project activities provided by CDM EB in its 35th Meeting (Annex

    34), which states under investment barrier, Best practice examples include but are not limited to, the application of investment comparison analysis using a relevant financial indicator, application of a

    benchmark analysis or a simple cost analysis (where CDM is the only revenue stream such as end-use

    energy efficiency).

    From the above three best practice options under Investment Barrier, the project proponent has chosen to

    demonstrate additionality using benchmark analysis because the baseline scenario for the project activity

    is be the electricity import from Jamali grid, for which no investment is required by the Project

    Participant. Hence, benchmark approach is best suited approach for PP. This is based on the reference to

    the Guidance 19 of Annex 5 of EB 62, "The benchmark approach is therefore suited to circumstances

    where the baseline does not require investment or is outside the direct control of the project developer,

    i.e. cases where the choice of the developer is to invest or not to invest." This analysis has been selected

    and conducted in accordance with the Guidance on the Assessment of Investment Analysis (Version 05) (EB-62, Annex 5). As per the guidance, the most suitable financial indicator for the project activity is

    determined to be the project IRR

    Selection of Benchmark:

    In accordance with the EB Guidance on the assessment of investment analysis (EB-62, Annex 05) Local commercial lending rates or weighted average costs of capital (WACC) are appropriate benchmarks for a project IRR.

    In line with the Guidelines on the Assessment of Investment Analysis, EB62 - Weighted average cost of

    capital (WACC) is an appropriate benchmark for project IRR. Steps to calculate WACC are detailed

    below:

    WACC = E *Re + D*Rd*(1-Tc)

    V V

    where:

    WACC: Weighted average cost of capital (%)

    E/V : Percentage of financing that is equity (%).

    D/V: Percentage of financing that is by debt (%).

    Re : Cost of equity

    Rd: Cost of debt

    Tc: Tax rate

    Cost of equity is calculated using CAPM Model as detailed below:

    Re = krf + Rp *

    where:

    krf : Risk free rate

    Rp : Market Risk Premium

    : Beta of industry

    Applicable data used to calculate WACC at the time of decision making is listed in table below:

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    19

    Parameter Value Source

    E/V 30% Based on the FSR which provides the typical debt/equity finance

    structure observed in the hydro power sector of Indonesia, which

    is line with the para 18 of the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5

    D/V 70% Based on the FSR which provides the typical debt/equity finance

    structure observed in the hydro power sector of Indonesia, which

    is line with the para 18 of the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.

    Re 53.96% Calculated based on the formula : Re = krf + Rp *

    Rd 13.00% Based on the Feasibility Study Report which provides the lending

    rate observed for debt financing which is in line with the

    Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.

    Tc 28% Government Regulation No.17, Year 2000, Clausal No.17, which

    is in line with the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.

    krf 8.71% http://www.idx.co.id/Portals/0/StaticData/Publication/BondBook/

    FileDownload/INDONESIA%20BOND%20MARKET%20DIRE

    CTORY%202011.pdf

    Bonds published in the year 2010 which have a maturity period of

    10 or more which is in line with the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.

    Rp 17.69% Calculated (Market return krf). The market return is calculated based on the Jakarta Composite Index (JCI). The krf is calculated

    as explained above, which are in line with the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.

    2.56 Calculated. http://www.stern.nyu.edu/~adamodar/pc/archives/totalbeta09.xls

    The beta value for electrical utility central of 0.95 (The unlevered

    beta) is chosen in the benchmark evaluation. The unlevered beta

    value is then levered with the D/E ratio 70:30 and the tax rate

    28% to get the levered beta 2.56. using the formula

    BL=BU*(1+(1-Tc)*(D/E))

    BL = Levered beta ;

    BU =Unlevered beta

    Tc= Tax rate

    D/E = Debt: Equity ratio

    WACC 22.74% Calculated based on the formula WACC = E/V *Re +

    D/V*Rd*(1-Tc)

    Beta:

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    20

    The Beta value has been calculated based on sector information as compiled by a finance professor of

    Stern School of Business, New York University. Due to the lack of publicly available information in the

    host country, the project participant chose the Beta of the electricity generating companies listed in the

    website.

    The beta value for electrical utility central of 0.95 (The unlevered beta) is chosen in the benchmark

    evaluation. This electrical utility (central) has minimum beta value, compared to other two listed

    electrical utility and this is conservative. The unlevered beta value is then levered with the D/E ratio

    70:30 and the tax rate 28% to get the levered beta 2.56.

    Debt: Equity ratio:

    As per para 18 of the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5, If the benchmark is based on parameters that are standard in the market, then the typical debt/equity finance structure observed in the sector of the country should be used..

    In line with guideline, PP has considered Debt: Equity ratio of 70:30 based on the FSR which provides

    the typical debt/equity finance structure observed in the hydro power sector of Indonesia and the same is

    considered in the benchmark evaluation of the project activity.

    Market return:

    The market return is calculated based on the Jakarta Composite Index (JCI) and was used in the Capital

    Asset Pricing Model (CAPM) to calculate the cost of equity. The compounded return for the market is

    calculated over a time period of 5 years (Dec 2005- Dec 2010) to determine the market return.

    Risk free return:

    The risk free rate is determined as an average of 3 government bond rates from Indonesia issued for a

    period of more than 10 years and published in the year 2010. The risk free rate is the rate of return on an

    asset that is theoretically free of any risk. When doing investment analysis on longer term projects or valuation, the risk free rate should be the long term government bond rate (Estimating Risk Free Rates by Dr. Aswath Damodaran of Stern School of Business, New York University page 6)12. Hence bonds having a maturity period of 10 years or more are considered for risk free rate calculation.

    Project IRR (which is post tax ) is calculated based on following information:

    Parameter Value Unit Source

    Installed Capacity 8 MW Feasibility Study Report

    Total Investment 139757 IDR(million) Feasibility Study Report

    Annual O& M cost 3257 IDR(million) Feasibility Study Report

    Annual Net electricity exported to grid 47,471 MWh Calculated

    Electricity Tariff 656 IDR Feasibility Study Report

    12

    http://jft-newspaper.aub.edu.lb/reserve/data/fina306-ai-project-reading/riskfree.pdf

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    21

    Income tax 28 % Indonesia Government

    Regulation No.17 Year

    2000, clausal No.17

    Project Lifetime 20 years Feasibility Study report

    Using above data Project IRR without CDM is calculated as below:

    Above table shows that Post tax Project IRR without CDM is below the benchmark. The CDM revenue

    helps improve the project IRR significantly.

    Sensitivity Analysis:

    Sub-step 2d: Sensitivity analysis

    As per paragraph 20 of Guidelines on the assessment of investment analysis (EB 62, Annex 5); Only variables, including the initial investment cost, that constitute more than 20% of either total project costs

    or total project revenues should be subjected to reasonable variation (all parameters varied need not

    necessarily be subjected to both negative and positive variations of the same magnitude), and the results

    of this variation should be presented in the PDD and be reproducible in the associated spreadsheets.

    Where a DOE considers that a variable which constitute less than 20% has a material impact on the

    analysis they shall raise a corrective action request to include this variable in the sensitivity analysis.

    As per para 21 of the Guidelines on the assessment of investment analysis (EB 62, Annex 5); The DOE should assess in detail whether the range of variations is reasonable in the project context. Past

    trends may be a guide to determine the reasonable range. As a general point of departure variations in

    the sensitivity analysis should at least cover a range of +10% and 10%, unless this is not deemed

    appropriate in the context of the specific project circumstances. In cases where a scenario will result in

    the project activity passing the benchmark or becoming the most financially attractive alternative the

    DOE shall provide an assessment of the probability of the occurrence of this scenario in comparison to

    the likelihood of the assumptions in the presented investment analysis, taking into consideration

    correlations between the variables as well as the specific socio-economic and policy context of the project

    activity.

    In line with the above guidance para 20 and 21 of EB62, Annex 5, following critical parameters have

    been identified for conducting the Sensitivity analysis:

    Plant load Factor (PLF) which constitutes 22% of total project cost

    Operation and Maintenance cost which constitutes 18% of total project revenue.

    Tariff rate which constitutes 22% of total project cost

    Total project cost.

    In line with paragraph 21 of EB62, annex 5, all the above parameters have been varied by at least 10%.

    The results of the sensitivity analysis are reflected below:

    Project IRR Value Benchmark

    (WACC)

    Without CDM 14.51% 22.74%

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    22

    Particulars IRR with varied parameters (%)

    -10.00% 0.00% 10.00%

    IRR with variation in project investment 16.13% 14.51% 13.15%

    IRR with variation in tariff 12.76% 14.51% 16.19%

    IRR with variation in PLF 12.76% 14.51% 16.19%

    IRR with variation in O&M expenses 14.76% 14.51% 14.27%

    Plant load factor:

    The Project IRR crosses the benchmark at PLF of 104.46 % which is not a likely to happen. The capacity

    factor determined in the FSR according to historical hydrological data from 1997 to 2006 shows a value

    lesser than 104.46%. Hence achieving a PLF value of 104.46% is not possible.

    Operation and Maintenance cost:

    The Project IRR crosses the benchmark when O&M cost is decreased to -9588 Million IDR. However,

    such a situation is not possible as O&M cost usually increases year on year basis. There will not be a

    situation of decrease in O & M cost. Hence, such a scenario of decreasing of -9588 Million IDR is not

    possible.

    Tariff rate:

    The Project IRR crosses the benchmark at tariff of 996 IDR/kWh which is not realistic, as the PP signed

    long term power purchase agreement for the period of 15 years at the rate of 656 IDR/kWh. As per PPA

    Article 10, para 1, page 14 the tariff rate is as per the data by Minister of Energy and Mineral Resources

    No. 31 of 2009, which is fixed for 15 years (as per article 3 para 1,page 7) from the date of

    commissioning of the project. & Article 3, Para 2 page 7, states that The life of the agreement referred to in paragraph (1) of this Article 3, may extended the lifetime of power plant with the written approval of

    THE PARTIES the lifetime of the project can be extended over to 15 years which is mentioned in para 1 by the parties PP and PLN with the written approval. Hence the PP may extend the PPA after 15 years

    and so the tariff may also be remains same. Thus the situation is not likely to happen.

    Project cost:

    The Project IRR crosses the benchmark when the project cost is decreased to 87828 Million IDR.

    However it is not possible as PP has already placed purchase orders for 80% of the total project cost.

    Hence such a situation is not possible.

    Conclusion:

    Thus, the financial analysis shows that the project activity is not the most financially attractive, and the

    sensitivity analysis shows that it is unlikely to be financially attractive compared to the benchmark under

    reasonable variations of the relevant parameters.

    Early Consideration of CDM:

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    23

    As per the Guidelines on the Demonstration and Assessment of Prior Consideration of the CDM13, version 04, EB 62 (Annex13) , For Project activities with a start date on or after August 2008 the project participant must inform a Host party DNA and the UNFCCC Secretariat in writing of the

    commencement of the project activity and of their intension to seek CDM Status. Such Notification must

    be made within six months of the project activity starting date

    The start date for the project activity is 04/08/2011 when the EPC contract for the project activity was

    signed. The prior CDM consideration notification was sent to UNFCCC and Host party DNA on

    09th March 2011 and 8

    th March 2011 respectively. The same is reflected on UNFCCC website. This

    confirms that the project proponent has seriously considered CDM benefits for the proposed project

    activity.

    The chronology of the events is presented below:

    S.No Events Date

    1 Board decision to processs the clearance for the 8 MW project activity 23rd

    June 2010

    2 PPA between PT. PLN (Persero) and PT. Tirta Gemah Ripah for Mini

    Hydro Power Plant Total Capacity 2000 kW.

    28th June 2010

    3 Investment Approval from the Regent of Garut for Cirompang Mini

    Hydro Power Plant with capacity 8.000 kW.

    23rd July 2010

    4 Recommendation on Cirompang MHPs Use of Land Allocation Permit, from the Office of Housing, Spatial Planning, and Settlements,

    Garut regency.

    26th July 2010

    5 Recommendation letter document of Environmental Management

    Effort & Environmental Monitoring Effort for Cirompang MHP 8 MW

    construction.

    2nd Sep 2010.

    6 Feasibility study report Nov 2010

    7 Board resolution to undertake the project activity under CDM 10th Dec 2010

    8 CDM Advisory services agreement between PP and consultant. 2nd March 2011

    9 CDM prior intimation to UNFCCC and DNA To UNFCCC - 9th

    March 2011

    To DNA 8th March 2011

    10 Stakeholder consultation meeting 15th April 2011

    11 EPC contract between PT. Hutama Karya (Persero) and PT. Tirta

    Gemah Ripah

    4th Aug 2011

    12 The Agreement between PT. TGR with GP3A Daerah Irigasi

    Cirompang (affiliation of farmers using Cirompang water) regarding

    the Use of Dams, Irrigation Channels, and Tunnels for the Cirompang

    Mini Hydro Power Investment Project.

    11th Aug 2011

    13 PPA between PT. PLN (Persero) and PT. Tirta Gemah Ripah for Mini

    Hydro Power Plant Total Capacity 8000 kW

    21st Nov 2011

    13

    http://cdm.unfccc.int/Reference/Guidclarif/reg/reg_guid04.pdf

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    24

    B.6. Emission reductions:

    B.6.1. Explanation of methodological choices:

    Baseline Emissions

    As per paragraph 11 of the methodology AMS-I.D., Version 17, the baseline emissions are calculated as

    the product of electrical energy baseline yBLEG , expressed in MWh of electricity produced by the

    renewable generating unit multiplied by the grid emission factor.

    ygridCOyBLy EFEGBE ,,, 2*

    Where:

    yBE Baseline Emissions in year y (t CO2)

    yBLEG , Quantity of net electricity supplied to the grid as a result of the implementation of

    the CDM project activity in year y (MWh)

    ygridCOEF ,,2 CO2 emission factor of the grid in year y (t CO2/MWh)

    The Emission Factor is calculated in a transparent and conservative manner as follows:

    A combined margin (CM), consisting of the combination of operating margin (OM) and build margin

    (BM) according to the procedures prescribed in the Tool to calculate the Emission Factor for an electricity system, version 2.2.1, EB 63 Annex 19.

    The Directorate General Electricity and Energy Utilization (DJLPE, Direktorat Jenderal Listrik dan

    Pemanfaatan Energi), a government institution has issued an official baseline emission factor for the

    Jamali grid which is available from.

    http://pasarkarbon.dnpi.go.id/web/index.php/komnasmpb/read/20/faktor-emisi-jaringan-listrik-jawa-

    madura-bali-jamali-2010-.html

    The calculation method opted for expost grid emission factor is as per Tool to calculate the Emission Factor for an electricity system, version 2.2.1, EB 63 Annex 19 is presented in Annex 3 of the PDD.

    Project Emissions:

    As per paragraph 20 of approved methodology AMS-I.D. (Version-17, EB- 61), emissions from water

    reservoir of hydro power plants qualify as project emissions.

    The project emission for the project activity will be

    PEy = PEHP,y + PEFF,y

    Where:

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    25

    PEHP,y - Emission from reservoir:

    PEFF,y - Emission from fossil fuel consumption in year y. It is the emission from diesel generator which

    will be used in emergency purposes and it is calculated by Tool to calculate project or leakage CO2 emission from fossil fuel consumption.

    PEHP,y - Emission from reservoir:

    The proposed project activity is implemented in the existing reservoir with no change in the volume of

    reservoir. Therefore, project activity not shall account for CH4 and CO2 emissions from the reservoir. So

    PEHP,y = 0.

    PEFF,y - Emission from diesel generator backup:

    The project emission includes the proponent of emission from diesel generator which will be used in

    emergency purposes and it is calculated by Tool to calculate project or leakage CO2 emission from fossil fuel consumption.

    The following formula is applied according to the Tool to calculate project or leakage CO2 emission from fossil fuel consumption:

    Emission from the operation of a backup system in process j during the year y is calculated as follows:

    PEFC,j,y = FCi,j y COEFi,y COEFi,y = NCVi,y EFCO2,i,y

    Where:

    PEFC,j,y Are the CO2 emissions from fossil fuel combustion in process j during the year y

    FCi,j y Is the quantity of fuel type i combusted in process j during the year y (mass or volume

    unit/year)

    COEFi,y Is the CO2 emission coefficient of fuel type i in year y (tCO2/mass or volume unit)

    NCVi,y Is the weighted average net calorific value of the fuel type i in year y

    EFCO2,i,y Is the weighted average CO2 emission factor of fuel type i in year y (tCO2/GJ)

    i Are the fuel types combusted in process j during the year y

    PEy = 0.

    Leakage Emissions:

    As per paragraph 22 of the approved methodology AMS-I.D. (Version-17, EB-61), if the energy

    generating equipment is transferred from another activity, leakage is to be considered. The leakage

    emissions may be considered as zero as no such equipment shall be transferred from another project

    activity. Hence LEy = 0

    Emission Reductions

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    26

    As per paragraph 23 of the approved methodology AMS-I.D. (Version-17, EB-61), Emission reductions

    are calculated as follows:

    yyyy LEPEBEER

    Where:

    yER Emission reductions in year y (tCO2/y)

    yBE Baseline Emissions in year y (tCO2/y)

    yPE Project emissions in year y (tCO2/y)

    yLE Leakage emissions in year y (tCO2/y)

    B.6.2. Data and parameters that are available at validation:

    Data / Parameter: Grid Emission Factor

    Data unit: tCO2e/MWh

    Description: CO2 emission factor of the grid in year y

    Source of data used: Emission Factor for Jamali Grid

    Value applied: 0.713

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    The value is published by host country DNA

    Any comment: The value is expost and hence it is to be monitored during the crediting period

    Data / Parameter: Installed Capacity of the project activity

    Data unit: MW

    Description: The installed capacity of the project activity

    Source of data used: Feasibility Study report

    Value applied: 8

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    The data is from Feasibility Study Report.

    Any comment: NA

    B.6.3 Ex-ante calculation of emission reductions:

    Ex- ante emissions are calculated as defined in section 6.1 as given below:

    Baseline emissions (BE,y):

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    27

    As per paragraph 11 of the methodology AMS-I.D, Version 17, the baseline emissions are the product of

    electrical energy baseline yBLEG , expressed in MWh of electricity produced by the renewable generating

    unit multiplied by the grid emission factor.

    ygridCOyBLy EFEGBE ,,, 2*

    Where:

    yBE = Baseline Emissions in year y; tCO2e

    yBLEG , = Quantity of net electricity supplied to the grid as a result of the implementation of the

    CDM project activity in year y (MWh)

    ygridCOEF ,,2 = CO2 emission factor of the grid in year y (tCO2e/MWh)

    Parameter Units Value Remarks

    Capacity of each turbine MW 2 FSR

    Number of turbines Nos 4 FSR

    Total installed capacity MW 8 Calculated

    Total number of hours of operation

    annually Hours 8760 FSR

    Plant load factor % 68.77 FSR

    Gross energy generation MWh 48194 Calculated

    Auxiliary consumption % 1.5 FSR

    MWh 723 Calculated

    Net energy generation from the project

    activity MWh 47471 Calculated

    Grid emission factor tCO2e/MWh 0.713 Calculated

    Baseline emissions tCO2e/year 33,847 Calculated

    Project Emissions (PEy)

    The project emission includes the proponent of emission from diesel generator which will be used in

    emergency purposes and it is calculated by Tool to calculate project or leakage CO2 emission from fossil fuel consumption.

    The following formula is applied according to the Tool to calculate project or leakage CO2 emission from fossil fuel consumption:

    Emission from the operation of a backup system in process j during the year y is calculated as follows:

    PEFC,j,y = FCi,j y COEFi,y COEFi,y = NCVi,y EFCO2,i,y

    Where:

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    28

    Particular Unit Value Remarks

    Quantity of diesel consumption in

    the project activity Litres/annum 0

    Diesel will be consumed only for

    emergency cases

    Net Calorific Value of diesel TJ/tonne 0.0433

    2006 IPCC Guidelines for

    National Greenhouse Gas

    Inventories, Volume 2, Chapter 1,

    Table 1.2, The upper limit value

    has been used.

    Emission factor of diesel tCO2/TJ 74.8

    2006 IPCC Guidelines for

    National Greenhouse Gas

    Inventories, Volume 2, Chapter 1,

    Table 1.4. The upper limit value

    has been used.

    Density of diesel T/litre 0.8439*1

    0^-3

    http://v-c-s.org/sites/v-c-

    s.org/files/15.%20E-

    FFC%20fossil%20fuels.pdf

    Project emission due to

    consumption of diesel tCO2e/annum 0 Calculated

    Hence PEy = 0

    Leakage Emissions (LEy)

    LEy = 0

    Emission Reduction

    ERy, = BEy PEy LEy, = 33,847 0 0 = 33,847

    B.6.4 Summary of the ex-ante estimation of emission reductions:

    Year

    Estimation of

    project activity

    emissions

    (tonnes of

    CO2e)

    Estimation of

    baseline

    emissions

    (tonnes of

    CO2e)

    Estimation of

    leakage

    (tonnes of

    CO2e)

    Estimation of

    overall emission

    reductions

    (tonnes of CO2e)

    Year1 (01/03/2013-

    28/02/2014) 0 33,847 0 33,847

    Year 2 (01/03/2014-

    28/02/2015) 0 33,847 0 33,847

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    29

    Year 3 (01/03/2015 -

    29/02/2016) 0 33,847 0 33,847

    Year 4 (01/03/2016 28/02/2017)

    0 33,847 0 33,847

    Year 5 (01/03/2017 28/02/2018)

    0 33,847 0 33,847

    Year 6 (01/03/2018 28/02/2019)

    0 33,847 0 33,847

    Year 7 (01/03/2019 29/02/2020)

    0 33,847 0 33,847

    Year 8 (01/03/2020 28/02/2021)

    0 33,847 0 33,847

    Year 9 (01/03/2021 28/02/2022)

    0 33,847 0 33,847

    Year 10 (01/03/2022

    28/02/2023) 0 33,847 0 33,847

    Total Emission

    Reductions

    (tCO2e)

    0 338,470 0 338,470

    B.7 Application of a monitoring methodology and description of the monitoring plan:

    B.7.1 Data and parameters monitored:

    Data / Parameter: EGfacility,y= EGBL,y

    Data unit: MWh/year

    Description: Quantity of net electricity supplied to the grid in year y

    Source of data to be

    used:

    Onsite measurement by Project Developer

    Value of data 47,471

    Description of

    measurement methods

    and procedures to be

    applied:

    Electricity will be measured with an electricity meter and will be recorded on a

    monthly basis by Project Developer with the use of Energy Meter (s).

    Measured : Continuously

    Recorded : Monthly

    QA/QC procedures to

    be applied:

    The meter(s) will be subject to maintenance and calibration according to standard

    set by PLN. On site staff will receive training in CDM monitoring and the

    maintenance requirements of the electricity meters.

    Data measured by the meter(s) will be cross checked using electricity sales

    receipts.

    The accuracy (class 0.2) of the measurement will be ensured through annually

    calibration by a qualified party.

    Any comment: Data will be archived at least for two years after the end of the crediting period,

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    30

    or the last issuance of CERs, whichever occurs later.

    Data / Parameter: ygridCOEF ,,2

    Data unit: tCO2e/MWh

    Description: CO2 emission factor of the grid in year y

    Source of data to be

    used:

    Emission Factor for Jamali Grid.

    Value of data 0.713

    Description of

    measurement methods

    and procedures to be

    applied:

    The value is published by the host country DNA. However, the calculation

    procedure is provided in Annex 3

    QA/QC procedures to

    be applied:

    The data is a published data by host country DNA. Hence QA/QC procedure is

    not applicable.

    Any comment: Data will be archived at least for two years after the end of the crediting period,

    or the last issuance of CERs, whichever occurs later.

    Data / Parameter: yiFC ,

    Data unit: Litres/annum

    Description: Quantity of fossil fuel consumption(diesel) in project activity in a year

    Source of data to be

    used:

    Log book maintained to record onsite consumption of diesel.

    Value of data applied

    for the purpose of

    calculating expected

    emission reductions in

    section B.6

    -

    Description of

    measurement methods

    and procedures to be

    applied:

    The data will be monitored continuously and aggregated monthly.

    QA/QC procedures to

    be applied:

    The diesel consumption quantities can be cross-checked with the records of the

    quantity of diesel purchased from the invoices.

    Any comment: The data will be archived electronically and the archived data will be kept for 2

    years beyond the Crediting Period.

    Data / Parameter: yiNCV ,

    Data unit: TJ/tonne

    Description: Net calorific value of the fossil fuel (i) (diesel) combusted in the project activity

    during the year y.

    Source of data to be

    used:

    2006 IPCC Guidelines for National Greenhouse Gas Inventories, Volume

    2,Chapter 1, Table 1.2

    Value of data applied 0.0433

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    31

    for the purpose of

    calculating expected

    emission reductions in

    section B.6

    Description of

    measurement methods

    and procedures to be

    applied:

    The net calorific value of diesel has been sourced from IPCC 2006 default value

    at the upper limit of the uncertainty at a 95% confidence interval and any future

    revision of the IPCC guidelines will be taken into account in determining the

    same.

    QA/QC procedures to

    be applied:

    Project participants have no control on the parameter. Hence, No QA/QC

    procedures are applicable.

    Any comment: The data will be archived electronically and the archived data will be kept for 2

    years beyond the Crediting Period.

    Data / Parameter: diesel

    Data unit: T/Litres

    Description: Density of fossil fuel diesel combusted in the project activity

    Source of data to be

    used:

    http://v-c-s.org/sites/v-c-s.org/files/15.%20E-FFC%20fossil%20fuels.pdf

    Value of data applied

    for the purpose of

    calculating expected

    emission reductions in

    section B.6

    0.8439*10^-3

    Description of

    measurement methods

    and procedures to be

    applied:

    The value of the density of the diesel has been taken based on regional values

    available.

    QA/QC procedures to

    be applied:

    Not applicable.

    Any comment: The data will be archived electronically and the archived data will be kept for 2

    years beyond the Crediting Period.

    B.7.2 Description of the monitoring plan:

    Parties involved in monitoring

    This section details the steps taken to monitor the greenhouse gas emissions reductions on a regular basis.

    The Monitoring set up for this project has been developed to ensure that from the start, the Project is well

    organised in terms of the collection and archiving of complete and reliable data.

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    32

    The monitoring of this type of project consists of metering the electricity generated by the renewable

    technology. Below is the description of monitoring procedures for data measurement, quality assurance

    and quality control.

    PLN, as the state-owned company that own the Grid to which the Project Developer send its electricity to,

    is responsible in maintaining the electricity generation in the Grid as well as the system of metering to

    measure the transferred electricity into the Grid. The monitoring plan of the project will follow PLN

    system on measuring the electricity sent to the Grid.

    Metering of Electricity Supplied to the Grid

    The main electricity meter for establishing the electricity delivered to the grid will be installed at the

    project site using a Metering System that is approved by PLN. This electricity meter provides the main

    data for CER measurement, thus it will be the key part of the verification process. To check the amount of

    electricity delivered to the grid, official data will be used.

    In case of emergency purposes, the diesel generators will be used.

    Quality Control and Quality Assurance

    Quality control and quality assurance procedures will guarantee the quality of data collected. The

    electricity meter(s) will undergo periodic calibration once in a year throughout the lifetime of the Project

    Activity. Inspection will also be done as requested by PLN subject to manufacturer standards. Moreover,

    meter(s) are maintained by qualified spare parts. Documents of these procedures will be available during

    the verification.

    Data Collection and Archiving:

    The monthly data of electricity generation is collected in electronic form. However, the data in electronic

    form is archived throughout the life time of the project. The electricity records are maintained regularly

    by the team at the site. The archived data will be kept for 2 years beyond the Crediting Period.

    The following chart shows the data flow for the monitored data for the project acticity.

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    33

    The table below shows the roles and responsibilities and the information flow for the project activity data.

    Personnel Responsiblity

    Power plant Shift Incharge Monitoring the plant parameters including

    the monitoring parameters as described in

    the PDD.

    Collecting the data recorded in log sheets

    of respective sections and prepares the

    consolidated report on electricity

    generation.

    Power plant Operators

    Responsible for the overall plant

    performance and electricity generation of

    the power plant.

    Cross check and sign the daily plant

    operation reports regularly.

    Should look after the periodical tests of the

    monitoring equipments as per the

    monitoring plan.

    Responsible for the storage and archiving

    of information in good condition.

    Power plant Manager Responsible for the total monitoring plan.

    Examining the reports generated by Power

    President PT TGR

    CDM Manager

    Power plant

    Manager

    Power plant

    operators

    Power plant Shift -

    In charge

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    34

    Plant operators with reference to the

    monthly electricity generated; net

    electricity exported to grid and annual

    emission reduction calculations as per the

    monitoring plan.

    CDM Manager Responsible for overall CDM activities and

    proper monitoring of data as mentioned in

    monitoring plan.

    He will be reporting to Director to look

    after the CDM validation / verification

    process for the project activity.

    President PT TGR President will review the reports regularly

    and take necessary corrective action

    conforming to CDM.

    Emergency procedures:

    A back up meter will be installed in the power house and equipped with UPS (Uninterruptible Power

    Supply). In the situation of the main meter has problem, the back up meter will maintain the metering

    process. To ensure that the data is recorded correctly, the shift engineer will read the meter in power

    house and record it in the log book.

    B.8 Date of completion of the application of the baseline and monitoring methodology and the

    name of the responsible person(s)/entity(ies)

    Date of completion of the application of the baseline and monitoring methodology: 14/07/2011

    Name of the entity determine the baseline:

    Mr.Johan Romadhon, CEO, PT Tirta Gemah Ripah.

    PT. Tirta Gemah Ripah. (Project Participant as mentioned in Annex 1)

    SECTION C. Duration of the project activity / crediting period

    C.1 Duration of the project activity:

    C.1.1. Starting date of the project activity:

    04/08/2011 (Signing of EPC contract).

    C.1.2. Expected operational lifetime of the project activity:

    20 years

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    35

    C.2 Choice of the crediting period and related information:

    Project Activity will use Fixed Crediting Period.

    C.2.1. Renewable crediting period

    C.2.1.1. Starting date of the first crediting period:

    NA

    C.2.1.2. Length of the first crediting period:

    NA

    C.2.2. Fixed crediting period:

    C.2.2.1. Starting date:

    01/03/2013 or registration date. (Whichever occurs later)

    C.2.2.2. Length:

    10 years

    SECTION D. Environmental impacts

    D.1. If required by the host Party, documentation on the analysis of the environmental impacts

    of the project activity:

    Based on the letter issued by the Department of Mining and Energy ,Directorate General of Electricity

    and Energy Development, the project activity does not required to have an Environment Impact

    Assessment (AMDAL) however it is still required to submit an Environment Management (UKL) and

    Environment Planning(UPL) Procedure to be approved and fulfilled. The same has been approved for the

    project activity by Badan Pengelolaan Lingkungan Hidup, Pemerintaah Kabupaten Garut (Local

    Government Environment Department) .The project activity will also need to comply with the procedure

    by submitting a periodic report.

    Table 5: Summary of Environment Management Procedure Findings

    Activity Impacts Parameters Environmental Management

    Efforts

    Pre-construction

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    36

    Field Survey

    Land

    Procurement and

    Acquisition

    Public

    Perception

    Public

    Perception

    Normal daily activities (does not cause

    fears and anxieties among the

    residents)

    Appropriate reimbursement (of the

    lands owned by the residents)

    Mutual agreements with local

    agencies (lands owned by Perhutani)

    Socializing the PLTMH

    development project to the

    community,

    Discussion and coordination to set

    the reimbursement price for land

    acquisition.

    Discussion and coordination with

    local agencies associated with the

    use of lands owned by the residents.

    Construction

    Workforce

    Recruitment and

    Layoffs

    Public

    Perception

    Job

    Opportunities

    Increased

    Income

    Complaints of the residents

    The number of workers recruited from

    local residents

    Complaints of the residents

    The number of workers recruited from

    local residents

    Wage satisfaction

    Prioritizing the local workforce in

    recruitment

    Inform the workers that the jobs for

    construction period will be

    temporary (during construction

    period)

    Prioritizing the local workforce in

    recruitment

    Providing the appropriate and

    adequate wages

    Land Clearing

    and Maturation

    Degradation of

    Water Quality

    and

    disturbance to

    water biota

    Loss of

    vegetations

    Landslide

    Water quality standard (PP. no 82

    Year 2001 or West-Java Governor

    Decision no. 38/1991 )

    The magnitude of lost vegetations

    (area of cleared space)

    Complaints from the residents about

    the risk of landslide

    Disturbance to environmental function

    and stability.

    The logging will be carried out

    selectively (only as necessary)

    The arrangement of execution time

    (not during rains)

    Digging of pile will be carried out

    as necessary and carefully.

    Digging and hoarding will be

    carried out as necessary and

    carefully

    Activities will not be conducted

    during heavy rainfalls period

    Constructing a landslide retainer,

    especially in places with high risk

    of landslide

    Planting vegetations to strengthen

    the cliff, this eventually is expected

    to prevent landslide.

    Construction of

    Main Facilities

    and

    Infrastructure

    Landslide and

    Degradation of

    water quality

    Perception and

    Complaints of

    Complaints from the residents about

    the risk of landslide

    Disturbance to environmental function

    and stability.

    Digging and hoarding will be

    carried out as necessary and

    carefully

    Activities will not be conducted

    during heavy rainfalls period

    Constructing a landslide retainer,

    especially in places with high risk

    of landslide

    Planting vegetations to strengthen

    the cliff, this eventually is expected

    to prevent landslide.

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    37

    the

    Community

    (to the

    installation of

    transmission

    network)

    The willingness of residents to allow

    electrical poles installed in their land

    No request for reimbursement.

    Inform the residents about the

    benefits of transmission network

    installations.

    Operations

    Recruitment of

    Workers

    Job

    opportunities

    Increased

    Income

    The number of workers recruited from

    local residents

    Adequate wages and satisfaction with

    the wage earned

    Prioritizing the local workforce in

    recruitment.

    Inform them that the jobs for

    construction period will be

    temporary and limited to a few

    workers.

    Providing adequate and appropriate

    wages to the workers.

    Operations and

    Management of

    Pembangkit

    Listrik Tenaga

    Mikro Hidro

    (PLTMH) and

    Maintenance of

    PLTMH

    facilities

    Facilities

    provided to the

    community

    (electricity)

    Nuisance

    Landslide

    Public

    perceptions

    Improvement

    of Water

    Quality

    Accidents and

    Safety Issues

    Addition of Electrical Capacity

    Noise Standards (kepMenLH No Kep-

    48/MenLH/11/1996)

    Complaints from the residents about

    the risk of landslide.

    Disturbance to environmental function

    and stability.

    Satisfaction of community

    Quality standards of River Water (PP

    no. 82 Year 2001 or West-Java

    Governor Decision No.38/1991).

    Success of reforestation.

    Number of Reported Accidents

    Optimizing the operations

    Placing the turbine in closed space

    Constructing a landslide retainer,

    especially in places with high risk

    of landslide

    Planting vegetations to strengthen

    the cliff, this eventually is expected

    to prevent landslide.

    Inviting community participation in

    managing PLTMH

    Coordinating with local authorities

    and agencies in managing PLTMH

    If the mud precipitates in the

    tranquilizing pool, it will not be

    thrown directly to the river, but

    removed from the pool to other

    area.

    The clearance of water entering the

    turbine (by installing trash

    trapper/trap).

    Keeping the hygiene

    Conducting reforestation in the

    open activity locations due to

    PLTMH development activities

    Developing clear work instructions

    which are obeyed by all workers.

    Installing warning/notification

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    38

    Environmental

    Security

    New Business

    Opportunities

    (because the

    availability of

    electricity)

    Number of disturbances to the

    PLTMH facilities.

    Disruptions of the forest areas

    surrounding the location.

    Improvement of local economy

    board.

    Creating boundary or setting up

    fences for important and accident-

    prone facilities.

    Providing the workers with personal

    protective equipment and first aid

    kit.

    Coordinating with local agencies.

    Keeping the environmental

    securities together with the

    community and local government

    agencies.

    Organizing community

    development activities in

    Bungbuland and Cihikeu villages.

    D.2. If environmental impacts are considered significant by the project participants or the host

    Party, please provide conclusions and all references to support documentation of an environmental

    impact assessment undertaken in accordance with the procedures as required by the host Party:

    The project is expected to deliver an overall positive sustainable impact and development on the local and

    global environment All negative environmental impacts are subjected to observation and management as

    described above.

    SECTION E. Stakeholders comments

    E.1. Brief description how comments by local stakeholders have been invited and compiled:

    The project developer conducted a stakeholders consultation meeting at their project site with the local village people residing in and around the vicinity of this project activity in order to view the concerns of

    the local stakeholders and their opinion about the proposed project activity on 15/04/2011. Some of the

    key local stakeholders were also invited by an invitation letter14

    . The local population and regulatory

    authorities participated in that meeting. An advertisement was also published to inform local people

    regarding the project activity in daily newspaper i.e. Radar Garut on 4 April 2011.

    Mr. Herman Rachmat (General Manager TGR) briefed the attendees about the project and the agenda of

    the stakeholder meeting and introduced the global warming and the climate change.

    Mr.Yulianto (Project Director TGR) introduced the company/project to the audience and also presented a brief overview of the hydro power business.

    After this brief introduction of company, climate change, Kyoto Protocol and CDM, he explained to the

    attendees the purpose of the stakeholder consultation meeting as to seek the concern, opinion and

    suggestion of the stakeholders.

    14 Copy of invitation letters shall be provided at the time of validation

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    39

    Subsequently, project promoter invited the stakeholders to ask for their queries and suggestions. The

    questions and responses to their query are given in the next section.

    E.2. Summary of the comments received:

    People participated with great enthusiasm and raised a few questions, which were answered to in an

    appropriate manner by the project developer. Summary of these comments is given as follows;

    Mr.Ayi Saripudin (Cibungbulang Head of Sub-districts Secretary) Opening Statement:

    We would like to thank PT. Gemah Ripah for its contribution to the Bungbulang Sub-district by

    developing the Cirompang Mini Hydro Power Plant (MHPP), hereafter referred as MHPP. We also fully

    support the CDM project, a global/international scale program, which allows us to contribute to save the

    environment.

    Mr.Burhanudin Apip (Head of Local Environmental Management Council)

    Opening Statement:

    We support the development of Cirompang MHPP, because Garut Regency still lacks electricity. In

    addition, 18500 houses in our regency are still not connected to the electrical network. Therefore, we

    support the development of Cirompang MHPP.

    Mr. M.Mahfudin (GP3A of Mitra Cai)

    Question: We fully support the development of Cirompang MHPP and CDM proposal, and according to

    the agreement between TGR and Mitra Cai, we hope that the rice fields will continue to be irrigated and

    we hope that TGR will conduct reforestation in the area surrounding the project location.

    Answer: TGR will neither destroy the existing channels nor use the old tunnels, but we will construct

    new channels and tunnels. Therefore, the irrigation will not be disturbed during the construction period.

    In accordance to the agreement between TGR Mitra Cai, the water will be prioritized to irrigate the rice fields up to 800 L/seconds, and the rest will be allocated to MMPH.

    Mr. Ridwan Taufik (Sabareuma Environmental Activist)

    We support the Development of Cirompang MMPH, because it represents clean, environmentally friendly

    energy.What are the advantages of CDM to the community and environment?

    Answers:

    To supply the electricity to Garut Regency

    To preserve the environment because PLTM is free of pollution.

    To provide jobs to the members of Bungbulang community according to their skill set.

    To assist in increasing the CSR activities to the community surrounding the project.

    Mr.Tjahya (Head of Intellegence, Bungbulang Police Department)

    In principle, we support the continuation of the Cirompang MHPP project.We request a coordination

    between TGR, Muspika of the Sub-district, and police department for the safety and continuity of the

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    40

    project. The police department is ready to help the project in preventing any provocation, in order to aid

    safe and continuous development of PLTMH.

    Mr. Aos Suryana (Water and Mining Resources Agency)

    At the location of Cirompang irrigation grounds belonging to SDAP, above the bridge to be exact, there is

    an area of around 2-3 Hectares, which can be utilized for reforestation. We hope that from the CDM

    project, the TGR can participate in restoring the area for greener purposes

    The meeting was concluded with vote of thanks by Mr. Herman Rachmat from TGR. In general, all

    participants in the forum supported the implementation of proposed project.

    E.3. Report on how due account was taken of any comments received:

    No negative comments have been received on the Project.

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    41

    Annex 1

    CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY

    Organisation: Nordic Environment Finance Corporation NEFCO in its capacity as Fund

    Manager to the NEFCO Carbon Fund (NeCF)

    Street/P.O.Box: Fabianinkatu 34, P.O. Box 249

    Building:

    City: Helsinki

    State/Region:

    Postal code: FI-00171

    Country: Finland

    Phone: +358 10 6180 644

    Fax: +358 9 630 976

    E-mail:

    URL: www.nefco.org/cff

    Represented by: Ash Sharma

    Title: Vice President,

    Head, Carbon Finance and Funds Unit

    Salutation: Mr.

    Last name: Sharma

    Middle name:

    First name: Ash

    Department:

    Phone (direct): + 358 10 6180 644

    Fax (direct): +358 9 630 976

    Mobile: +358 10 6180 644

    Personal e-mail: [email protected]

    Organization: PT. Tirta Gemah Ripah

    Street/P.O.Box: Jl. Tubagus Ismail Depan No. IA

    Building:

    City: Bandung

    State/Region: West Java

    Postfix/ZIP: 40134

    Country: Indonesia

    Telephone: +62-222535852/+62-8112209514

    FAX: +62-222535851

    E-Mail:

    URL: -

    Represented by: Mr Johan Romadhon

    Title: CEO

    Salutation: Mr

    Last Name: Romadhon

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    42

    Middle Name:

    First Name: Johan

    Department: -

    Mobile: +62-8112209514

    Direct FAX: +62-222535851

    Direct tel: +62-222535852/+62-8112209514

    Personal E-Mail: [email protected]

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    43

    Annex 2

    INFORMATION REGARDING PUBLIC FUNDING

    No public funding is involved in this project activity

  • PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    44

    Annex 3

    BASELINE INFORMATION

    Calculation of Grid Emission Factor

    The Board decision on CDM consideration for the project activity is in Dec 2010. The emission factor

    value considered for Emission factor calculation in the PDD is based on the data published in the year 2010

    by the Indonesian DNA in its website stating Emission factor for electricity system of the Java-Madura-

    Bali (Jamali) based on the 2010 update which in turn refers the documents No: 2478/21/600.4/2011 dated

    31st Mar 2011 and document No: B-48/DNPI/05/2011 dated 5th May 2011 which gives 0.713 tCO2e/MWh

    as value, which is the recent data available before webhosting of the PDD for GSP during 09 Dec 11 - 07

    Jan 12.

    The expost grid emission factor has been estimated using the following six steps of according to Tool to

    calculate the emission factor for an electricity system (Version -02.2.1, EB- 63, Annex 19):

    Step 1: Identify the relevant sy