cirompang
DESCRIPTION
PDD_Cirompang_MHPPTRANSCRIPT
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
1
CLEAN DEVELOPMENT MECHANISM
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)
Version 03 - in effect as of: 22 December 2006
CONTENTS
A. General description of the small scale project activity
B. Application of a baseline and monitoring methodology
C. Duration of the project activity / crediting period
D. Environmental impacts
E. Stakeholders comments
Annexes
Annex 1: Contact information on participants in the proposed small scale project activity
Annex 2: Information regarding public funding
Annex 3: Baseline information
Annex 4: Monitoring Information
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
2
Revision history of this document
Version Number
Date Description and reason of revision
01 21 January
2003
Initial adoption
02 8 July 2005 The Board agreed to revise the CDM SSC PDD to reflect guidance and clarifications provided by the Board since
version 01 of this document.
As a consequence, the guidelines for completing CDM SSC PDD have been revised accordingly to version 2. The latest
version can be found at
.
03 22 December
2006 The Board agreed to revise the CDM project design
document for small-scale activities (CDM-SSC-PDD), taking
into account CDM-PDD and CDM-NM.
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
3
SECTION A. General description of small-scale project activity
A.1 Title of the small-scale project activity:
8MW Cirompang Mini Hydro Power Plants at Bungbulang, Garut, Indonesia.
Version : 3.1 Date : 29/08/2012
A.2. Description of the small-scale project activity:
The project activity hereinafter referred to as Project is a new 8 MW run-of-river hydroelectric power plant being developed by PT. Tirta Gemah Ripah (TGR) in Garut district, West Java Province, Indonesia.
The purpose of the project activity is generation of clean hydroelectric power and delivery to Jamali Grid.
The project will be constructed on Cirompang River.
The project activity is run-off river project which is taking place in the existing reservoir. The PP has
received approval to use the water for power generation. There will be no modification done by PP in
existing reservoir for use of water for power generation.
The project is expected to generate net electricity of 47471 MWh/year and expected to bring about GHG
emission reductions of approximately 33,847 tCO2e annually. Hence project activity would contribute to
reduction of CO2 emissions that in the absence of the project activity would have otherwise happened by
gird connected fossil fuel plants.
The project complies with the sustainable development criterias of the host country in the following manner:
Environment:
The project activity is a run-of-river hydroelectric power plant. It is a well established technology which
utilizes water for energy generation without depleting it or impacting the natural environment. Since the
project activity generates electricity from renewable source, it avoids emission such as SOx , NOx and
other particulates matter which would have been emitted from the fossil fuel fired plants.
Social:
Project will aid development of social infrastructure in the region such as roads and water supply. Project
will create job opportunities during the construction and operation stage.
Economy:
Project activity will create new jobs both skilled and unskilled for local population. This increase in
employment will stimulate local economy.
Technology:
The project will contribute to development of technological capacity building in the country as the project
will be implemented with local engineers as well as local labour who will work on the construction.
A.3. Project participants:
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
4
Name of Party involved (*)
((host) indicates a host Party)
Private and/or public
entity(ies)
Project participants (*)
(as applicable)
Kindly indicate if the party
involved wishes to be
considered as project
participant (yes/no)
Sweden Nordic Environment Finance
Corporation NEFCO in its
capacity as Fund Manager to the
NEFCO Carbon Fund (NeCF) Public Entity
No
Indonesia (Host) PT. Tirta Gemah Ripah (Public
Entity)
No
(*) In accordance with the CDM modalities and procedures, at the time of making the CDM-PDD public
at the stage of validation, a Party involved may or may not have provided its approval. At the time of
requesting registration, the approval by the Party(ies) involved is required.
The carbon purchaser is the Nordic Environment Finance Corporation NEFCO in its capacity as Fund
Manager to the NEFCO Carbon Fund (NeCF)
NEFCO Carbon Fund (NeCF)
NEFCO, the Nordic Environment Finance Corporation, is a multilateral risk capital institution financing
environmental projects in Central and Eastern Europe, with an emphasis on the Russian Federation and
Ukraine. Its purpose is to facilitate the implementation of environmentally beneficial projects in the
neighbouring region, with transboundary effects that also benefit the Nordic region. Today, NEFCO
manages funds in an aggregate of approximately 470 million. NEFCO is located in Helsinki, Finland.
The NEFCO Carbon Fund (NeCF) was established as a Public Private Partnership in April 2008, to
provide financial assistance to projects by purchasing emission reduction credits from projects under the
JI and CDM mechanisms. The NEFCO Carbon Fund (NeCF) has the Danish Energy Agency, DONG
Energy, Eesti Energia, the Industrialization Fund for Developing Countries (Denmark), Ministries of
Environment and Foreign Affairs of Finland, Etel-Pohjanmaan Voima Oy (Finland), Kymppivoima Oy
(Finland), GDF Suez, the Norwegian Finance Ministry and NEFCO itself, as participants in the fund. The
total available resources are ca. 165 million.
NEFCO is the Fund Manager of the NeCF, and has been authorized by the governments investing in the
NeCF to participate on their behalf in actions leading to the generation, transfer and acquisition of CERs
under Article 12 of the Kyoto Protocol
A.4. Technical description of the small-scale project activity:
A.4.1. Location of the small-scale project activity:
A.4.1.1. Host Party(ies):
Country: Indonesia
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
5
A.4.1.2. Region/State/Province etc.:
Province: West Java
A.4.1.3. City/Town/Community etc:
Village: Cihikeu and Bungbulang
Sub District: Bungbulang
District: Garut
A.4.1.4. Details of physical location, including information allowing the
unique identification of this small-scale project activity :
The geographical coordinates of the project site are
o Dam : North Latitude: -7.4505 , East Longitude: +107.6093
o Power House : North Latitude: -7.4762 , East Longitude: +107.6122
.The physical location of plant site is depicted in the map below:
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
6
Figure 1: Location planned in River Cirompang in Countryside Cihikeu & Bubbulang, District
Gaurt
A.4.2. Type and category(ies) and technology/measure of the small-scale project activity:
According to the Appendix B of the simplified modalities and procedures for small-scale CDM project
activities, project activity falls under the Type I Renewable Energy Projects. The project activity exports the generated electricity to the grid and falls in the category I. D -Grid Connected Renewable
Electricity Generation. Following Table details the same :
Term Description
Type Type I, Renewable Energy Projects
Category D, Grid Connected Renewable Electricity Generation
Technology/Measure Renewable energy generation units (hydro) that supply
electricity to a regional grid.
Technology Description:
The project is a runofriver Hydroelectric power plant on Cirompang river with a total installed capacity of 8MW consisting of 4 X 2MW turbines and a net projected output of 47, 471 MWh annually. The
electricity generated will be transmitted to the Jamali grid via 20 kV transmission line. The main
construction structures of the project consist of:
Channel Intake / Weir
Project location
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
7
The water in the river will be diverted by the weir through an opening in the river side (the `intake') into
an open channel.
Line Carrier (headrace) It will channel water from the canal intake (Intake) towards sand trap.
Sand Trap The water drawn from the river usually carries suspension of small particles. This sediment consists of
hard abrasive materials such as sand which can cause significant damage and rapid wear to turbine
runners. To remove this material the water flow will be slowed down in settling basins so that the silt
particles will settle on the basin floor.
Head Pond/Forebay Tank This head pond is not a storage area, it is meant to flood a sufficient area to regulate water current into
Penstock.
Penstock The penstock is like a pipe to convey water from the head pond to the powerhouse.
Power House Here all mechanical equipment such as turbines and generators as well as electrical equipment such
as panels and controllers will be housed.
Turbine and Generator Four 2 MW pelton turbines will be installed. When water flows into the turbine, it turns the blades in the
turbine which spins the generators shaft. Generator will convert the mechanical energy from the turning shaft into electrical energy.
The characteristics of the Turbine used in the project are presented in Table 1 below.
Table 1: Key Turbine Characteristics
Item Parameter Type/value/Unit
Turbines
Type Pelton
Efficiency at Peak 75%
Efficiency at Design Flow 75%
Turbine Speed 1000 m3/s
Manufacturer Jyoti Ltd , Vadodara,
India
Technology Pelton
Generator Key characteristics:
Parameter Unit
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
8
Number 4
Type Synchronous, vertical axis, 3 phases
Rated capacity 2000 kW
Rated frequency 50 Hz
Rated power factor 0.8
Transmission Lines The power generated will be transmitted to the Grid via 20 KV transmission lines.
The Table 2 below highlights Project key Technical Design data and parameters
Table 2: Key Technical Design Data and Parameters
Design Data /Parameters Unit Quantity
Total Installed Capacity MW 8
Installed Capacity of each
Unit
MW 2
Annual Operating hours hours 8760
Capacity Factor % 68.77
Gross Head m 142
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
9
Figure 2: Typical Scheme of run-off river system
In case of emergency, the diesel generators will be used.
Technology transfer and know-how
The installation and commissioning services are from Indonesia only.
The technology employed by the project proponent does not result in GHG emissions and the project does
not cause any negative impacts on the environment. The technology used does not pose any threat to the
environment in comparison to fossil fuel-fired power plants. Therefore the technology is environmentally
safe and sound.
A.4.3 Estimated amount of emission reductions over the chosen crediting period:
Year
Estimation of annual
emission reductions in tonnes
of CO2e
Year 1 (01/03/2013- 28/02/2014) 33,847
Year 2 (01/03/2014-28/02/2015) 33,847
Year 3 (01/03/2015 -29/02/2016) 33,847
Year 4 (01/03/2016 28/02/2017) 33,847
Year 5 (01/03/2017 28/02/2018) 33,847
Year 6 (01/03/2018 28/02/2019) 33,847
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
10
Year 7 (01/03/2019 29/02/2020) 33,847
Year 8 (01/03/2020 28/02/2021) 33,847
Year 9 (01/03/2021 28/02/2022) 33,847
Year 10 (01/03/2022 28/02/2023) 33,847
Total estimated reductions (tonnes
of CO2e) 338,470
Total number of crediting years 10
Annual average of the estimated
reductions over the crediting
period (tCO2e)
33,847
A.4.4. Public funding of the small-scale project activity:
The project will not receive any public funding from Parties included in Annex I of the UNFCCC.
A.4.5. Confirmation that the small-scale project activity is not a debundled component of a
large scale project activity:
According to paragraph 2 of Appendix C1 of the Simplified Modalities and Procedures for Small-Scale
CDM project Activities, the following results into debundling of large CDM project:
A proposed small-scale project activity shall be deemed to be a debundled component of a large project activity if there is a registered small-scale CDM project activity or an application to register another
small-scale CDM project activity:
With the same project participants; In the same project category and technology/measure; Registered within the previous 2 years; and Whose project boundary is within 1 km of the project boundary of the proposed small-scale activity at the closest point.
The project activity is not a de-bundled component of a large project activity as there is no small scale
CDM project activity or an application to register another small-scale CDM project activity by Project
Proponent (PP) in the same project category and technology in the last two years within 1 km of the
project boundary of the proposed small scale project activity.
SECTION B. Application of a baseline and monitoring methodology
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
small-scale project activity:
The project activity uses the following approved baseline and monitoring methodology available at the
UNFCC website2is a small scale project activity and conforms to Appendix B of the simplified modalities
and procedures for small-scale CDM project activities.
1 http://cdm.unfccc.int/EB/Meetings/007/eb7ra07.pdf
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
11
Title Reference Version
Grid connected renewable electricity generation AMS-I D Version 17
Guidance on the Assessment of Investment
Analysis
EB 62 Annex 5 Version 5
Guideline to small-scale CDM Methodologies
(Indicative Simplified Baseline and Monitoring
Methodologies for selected Small Scale CDM
Project Activity Categories)
EB 61 Annex 21 Version 17
Tool to calculate the emission Factor for an
electricity system EB 63 Annex 19 Version 2.2.1
Tool to calculate project or leakage CO2 emission
from fossil fuel consumption
EB 41, Annex 11 Version 2
B.2 Justification of the choice of the project category:
Applicability of AMS I. D:
The project activity utilizes the hydro power for electricity generation, which falls into the category of
renewable energy. The capacity of the proposed project activity is 8 MW which is below 15 MW, the
eligibility limit of 15 MW for a small-scale CDM project activity applies only to the renewable
component. The project activity is in line with the approved methodology AMS. I. D Version 17; specific
features of proposed project and applicability of methodology are discussed below:
Applicability Criteria with AMS-I.D. Project Applicability
1 This methodology comprises renewable energy generation
units, such as photovoltaic, hydro, tidal/wave, wind,
geothermal and renewable biomass:3
(a) Supplying electricity to a national or a regional grid; or
(b) Supplying electricity to an identified consumer facility via national/regional grid
through a contractual arrangement such as
wheeling.
The project activity involves a
renewable energy generation unit
specifically a hydro power unit that
displaces electricity from Jamali
Grid, an electricity distribution
system supplied by fossil-fuel fired
generating units. Thus the project
activity complies with the
applicability criteria.
2
http://cdm.unfccc.int/methodologies/DB/RSCTZ8SKT4F7N1CFDXCSA7BDQ7FU1X
3 Refer to EB 23, annex 18 or the definition of renewable biomass.
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
12
2 Illustration of respective situations under which each of the
methodology (i.e. AMS-I.D, AMS-I.F and AMS-I.A4) applies
is included in Table 2.
Project type AMS-
I.A
AMS-
I.D
AMS-
I.F
1 Project supplies electricity to
a national/regional grid
2 Project displaces grid
electricity consumption (e.g.
grid import) and/or captive
fossil fuel electricity
generation at the user end
(excess electricity may be
supplied to a grid)
3 Project supplies electricity to
an identified consumer
facility via national/regional
grid (through a contractual
arrangement such as
wheeling)
4 Project supplies electricity to
a mini grid5 system where in
the baseline all generators
use exclusively fuel oil
and/or diesel fuel
5 Project supplies electricity to
household users (included in
the project boundary) located
in off grid areas
The project supplies electricity to
Jamali grid. The grid is owned by
PT Perusahaan Listrik Negara
(PLN), a state owned electricity
company of Indonesia. Thus the
project complies with the
applicability criteria of AMS I.D
3 This methodology is applicable to project activities that (a)
install a new power plant at a site where there was no
renewable energy power plant operating prior to the
implementation of the project activity (Greenfield plant); (b)
involve a capacity addition6; (c) involve a retrofit
7 of (an)
The project activity shall install a
new power plant at a site where
there was no renewable energy
power plant operating prior to the
implementation of the project
4 AMS-I.D Grid connected renewable electricity generation, AMS-I.F Renewable electricity generation for
captive use and mini-grid and AMS-I.A Electricity generation by the user
5 The sum of installed capacities of all generators connected to the mini-grid is equal to or less than 15 MW.
6 A capacity addition is an increase in the installed power generation capacity of an existing power plant through: (i)
the installation of a new power plant besides the existing power plant/units, or (ii) the installation of new power
units, additional to the existing power plant/units. The existing power plant/units continue to operate after the
implementation of the project activity.
7 Retrofit (or Rehabilitation or Refurbishment). It involves an investment to repair or modify an existing power
plant/unit, with the purpose to increase the efficiency, performance or power generation capacity of the plant,
without adding new power plants or units, or to resume the operation of closed (mothballed) power plants. A retrofit
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
13
existing plant(s); or (d) involve a replacement8 of (an) existing
plant(s).
activity (Greenfield plant). Thus the
Project Activity complies with the
applicability criteria (a)
4 Hydro power plants with reservoirs that satisfy at least one of
the following conditions are eligible to apply this
methodology:
The project activity is implemented in an existing reservoir with no change in the volume of reservoir;
The project activity is implemented in an existing reservoir, where the volume of reservoir is increased
and the power density of the project activity, as per
definitions given in the Project Emissions section, is
greater than 4 W/m2;
The project activity results in new reservoirs and the power density of the power plant, as per definitions
given in the Project Emissions section, is greater than
4 W/m2.
The project activity is a run off-river and it is implemented in an
existing reservoir. There will be no
change in the volume of the
reservoir. So the proposed project
activity is implemented in the
existing reservoir with no change in
the volume of reservoir. Hence this
condition is applicable to the
project activity.
5 If the new unit has both renewable and non-renewable
components (e.g., a wind/diesel unit), the eligibility limit of
15 MW for a small-scale CDM project activity applies only to
the renewable component. If the new unit co-fires fossil fuel9,
the capacity of the entire unit shall not exceed the limit of
15 MW.
The project activity has no non
renewable component and has
100% renewable component
(Hydro). The capacity of the
proposed project is 8 MW which is
lower than 15 MW, limit set for
small scale project activity. Hence
this condition is applicable.
6 Combined heat and power (co-generation) systems are not
eligible under this category.
There is no Combined heat and
power (co-generation) in the project
activity. Thus the project activity
complies with the applicability
criteria.
7 In the case of project activities that involve the addition of
renewable energy generation units at an existing renewable
power generation facility, the added capacity of the units
The project activity does not that
involve the addition of renewable
energy generation units at an
existing renewable power
restores the installed power generation capacity to or above its original level. Retrofits shall only include measures
that involve capital investments and not regular maintenance or housekeeping measures.
8 Replacement. It involves investment in a new power plant or unit that replaces one or several existing unit(s) at the
existing power plant. The installed capacity of the new plant or unit is equal to or higher than the plant or unit that
was replaced.
9 A co-fired system uses both fossil and renewable fuels.
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
14
added by the project should be lower than 15 MW and should
be physically distinct10
from the existing units. generation facility. Hence this
condition is not applicable to the
project activity.
8 In the case of retrofit or replacement, to qualify as a small-
scale project, the total output of the retrofitted or replacement
unit shall not exceed the limit of 15 MW.
The project activity does not seek
to any retrofit or replacement.
Hence this condition is not
applicable to the project activity.
Summary: It can be concluded based from the above discussion that the project activity meets the
applicability criteria of approved small scale methodologies AMS I.D
B.3. Description of the project boundary:
According to the paragraph 9 of the small scale methodology AMS-I.D. Version 17 The spatial extent of the project boundary includes the project power plant and all power plants connected physically
to the electricity system11
that the CDM project power plant is connected to. For the project activity, the generated electricity of the project will be delivered to the Jamali Grid, and the auxiliary internal power
consumption of hydropower plants is also contained in the project boundary. Also in case of emergency,
the diesel generators will be used and it comes under project boundary. A general schematic view of the
boundaries is shown in figure below.
10 Physically distinct units are those that are capable of generating electricity without the operation of existing units,
and that do not directly affect the mechanical, thermal, or electrical characteristics of the existing facility. For
example, the addition of a steam turbine to an existing combustion turbine to create a combined cycle unit would not
be considered physically distinct.
11 Refer to the latest approved version of the Tool to calculate the emission factor for an electricity system for definition of an electricity system.
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
15
Table 3 below Summary of gases and sources included in the project boundary, and justification
explanation where gases and sources are not included:
Scenario Source Gas Included/
Excluded
Justification/Explanation
Baseline
scenario
Electricity
Delivered to the
grid by the
CO2 Included Main Emission Source.
N2O Excluded Not Significant. Excluded for simplification and
conservativeness.
Existing reservoir
Tunnel
Penstock
Power house
Transformer
Jamali Grid
Diesel Generator (In case of
emergency, it will be used)
Project boundary
CO2 emission
from diesel
generator
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
16
project activity
that otherwise
would have
been generated
by the operation
of grid
connected
power plants
and by the
addition of new
generation
sources.
CH4 Excluded Not Significant. Excluded for simplification and
conservativeness.
Project
activity
Emissions
associated with
the operation of
the project
CO2 Included Emission from the diesel generator.
N2O Excluded Not Significant. Excluded for simplification and
conservativeness.
CH4 Excluded Not Significant. Excluded for simplification and
conservativeness.
B.4. Description of baseline and its development:
Baseline Scenario:
As per applicable methodology AMS I. D version 17, EB 61 paragraph 10 : the baseline scenario is that
the electricity delivered to the grid by the project activity would have otherwise been generated by the
operation of grid-connected power plants and by the addition of new generation sources into the grid.
Hence in the project scenario the electricity delivered to the Jamali grid by the project activity would have
otherwise been generated by the operation of grid connected power plants and by the addition of new
generation sources into the grid.
Data used to determine the baseline emissions:
The Emission Factor is calculated in a transparent and conservative manner as follows:
A combined margin (CM), consisting of the combination of operating margin (OM) and build margin
(BM) according to the procedures prescribed in the Tool to calculate the Emission Factor for an electricity system, version 2.2.1, EB 63 Annex 19.
The Directorate General Electricity and Energy Utilization (DJLPE, Direktorat Jenderal Listrik dan
Pemanfaatan Energi), a government institution has issued an official baseline emission factor for the
Jamali grid which is available from.
http://pasarkarbon.dnpi.go.id/web/index.php/komnasmpb/read/20/faktor-emisi-jaringan-listrik-jawa-
madura-bali-jamali-2010-.html
The calculation method opted for expost grid emission factor is as per Tool to calculate the Emission Factor for an electricity system, version 2.2.1, EB 63 Annex 19 is presented in Annex 3 of the PDD.
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
17
The parameters considered in the baseline calculation as presented in table below:
Parameter Unit Description Source of data to
be used
EGBL,y MWh Net electricity supplied to the grid Electricity meter
EFgrid,CM,y tCO2/MWh Combined margin CO2 emission factor
for grid connected power generation in
year y
As published by
Host Country
DNA
EFgrid,BM,y tCO2/MWh Build margin CO2 emission factor for
grid connected power generation in year
As published by
Host Country
DNA
EFgrid,OM,y tCO2/MWh Operating margin CO2 emission factor
for grid connected power generation in
year
As published by
Host Country
DNA
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered small-scale CDM project activity:
The project activity is additional as per the options provided under Non-binding best practice examples to demonstrate additionality for SSC project activities.
According to the Non-binding best practice examples to demonstrate additionality for SSC project
activities (EB 35, Annex 34):
a. Project participants shall provide an explanation to show that the project activity would not have occurred anyway due to at least one of the following barriers: Investment barrier: a financially
more viable alternative to the project activity would have led to higher emissions;
b. Access-to-finance barrier: the project activity could not access appropriate capital without
consideration of the CDM revenues
c. Technological barrier: a less technologically advanced alternative to the project activity involves lower risks due to the performance uncertainty or low market share of the new technology
adopted for the project activity and so would have led to higher emissions
d. Barrier due to prevailing practice: prevailing practice or existing regulatory or policy requirements would have led to implementation of a technology with higher emissions
e. Other barriers: without the project activity, for another specific reason identified by the project participant, such as institutional barriers or limited information, managerial resources,
organizational capacity, financial resources, or capacity to absorb new technologies, emissions
would have been higher.
Among the multiple barriers identified in the implementation of the project activity, the investment
barrier analysis is used to demonstrate the financial non-viability of the project activity in a conservative
and transparent manner. The project activity involves high investment cost. The returns generated from
the project activity are low and hence the CDM funds are considered essential for improving the returns
generated from the project.
Investment barrier
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
18
The investment barrier has been demonstrated in accordance with the Non-binding best practice examples
to demonstrate additionality for SSC project activities provided by CDM EB in its 35th Meeting (Annex
34), which states under investment barrier, Best practice examples include but are not limited to, the application of investment comparison analysis using a relevant financial indicator, application of a
benchmark analysis or a simple cost analysis (where CDM is the only revenue stream such as end-use
energy efficiency).
From the above three best practice options under Investment Barrier, the project proponent has chosen to
demonstrate additionality using benchmark analysis because the baseline scenario for the project activity
is be the electricity import from Jamali grid, for which no investment is required by the Project
Participant. Hence, benchmark approach is best suited approach for PP. This is based on the reference to
the Guidance 19 of Annex 5 of EB 62, "The benchmark approach is therefore suited to circumstances
where the baseline does not require investment or is outside the direct control of the project developer,
i.e. cases where the choice of the developer is to invest or not to invest." This analysis has been selected
and conducted in accordance with the Guidance on the Assessment of Investment Analysis (Version 05) (EB-62, Annex 5). As per the guidance, the most suitable financial indicator for the project activity is
determined to be the project IRR
Selection of Benchmark:
In accordance with the EB Guidance on the assessment of investment analysis (EB-62, Annex 05) Local commercial lending rates or weighted average costs of capital (WACC) are appropriate benchmarks for a project IRR.
In line with the Guidelines on the Assessment of Investment Analysis, EB62 - Weighted average cost of
capital (WACC) is an appropriate benchmark for project IRR. Steps to calculate WACC are detailed
below:
WACC = E *Re + D*Rd*(1-Tc)
V V
where:
WACC: Weighted average cost of capital (%)
E/V : Percentage of financing that is equity (%).
D/V: Percentage of financing that is by debt (%).
Re : Cost of equity
Rd: Cost of debt
Tc: Tax rate
Cost of equity is calculated using CAPM Model as detailed below:
Re = krf + Rp *
where:
krf : Risk free rate
Rp : Market Risk Premium
: Beta of industry
Applicable data used to calculate WACC at the time of decision making is listed in table below:
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
19
Parameter Value Source
E/V 30% Based on the FSR which provides the typical debt/equity finance
structure observed in the hydro power sector of Indonesia, which
is line with the para 18 of the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5
D/V 70% Based on the FSR which provides the typical debt/equity finance
structure observed in the hydro power sector of Indonesia, which
is line with the para 18 of the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.
Re 53.96% Calculated based on the formula : Re = krf + Rp *
Rd 13.00% Based on the Feasibility Study Report which provides the lending
rate observed for debt financing which is in line with the
Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.
Tc 28% Government Regulation No.17, Year 2000, Clausal No.17, which
is in line with the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.
krf 8.71% http://www.idx.co.id/Portals/0/StaticData/Publication/BondBook/
FileDownload/INDONESIA%20BOND%20MARKET%20DIRE
CTORY%202011.pdf
Bonds published in the year 2010 which have a maturity period of
10 or more which is in line with the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.
Rp 17.69% Calculated (Market return krf). The market return is calculated based on the Jakarta Composite Index (JCI). The krf is calculated
as explained above, which are in line with the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5.
2.56 Calculated. http://www.stern.nyu.edu/~adamodar/pc/archives/totalbeta09.xls
The beta value for electrical utility central of 0.95 (The unlevered
beta) is chosen in the benchmark evaluation. The unlevered beta
value is then levered with the D/E ratio 70:30 and the tax rate
28% to get the levered beta 2.56. using the formula
BL=BU*(1+(1-Tc)*(D/E))
BL = Levered beta ;
BU =Unlevered beta
Tc= Tax rate
D/E = Debt: Equity ratio
WACC 22.74% Calculated based on the formula WACC = E/V *Re +
D/V*Rd*(1-Tc)
Beta:
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
20
The Beta value has been calculated based on sector information as compiled by a finance professor of
Stern School of Business, New York University. Due to the lack of publicly available information in the
host country, the project participant chose the Beta of the electricity generating companies listed in the
website.
The beta value for electrical utility central of 0.95 (The unlevered beta) is chosen in the benchmark
evaluation. This electrical utility (central) has minimum beta value, compared to other two listed
electrical utility and this is conservative. The unlevered beta value is then levered with the D/E ratio
70:30 and the tax rate 28% to get the levered beta 2.56.
Debt: Equity ratio:
As per para 18 of the Guidance on the Assessment of Investment Analysis, Version 05, EB 62, Annex 5, If the benchmark is based on parameters that are standard in the market, then the typical debt/equity finance structure observed in the sector of the country should be used..
In line with guideline, PP has considered Debt: Equity ratio of 70:30 based on the FSR which provides
the typical debt/equity finance structure observed in the hydro power sector of Indonesia and the same is
considered in the benchmark evaluation of the project activity.
Market return:
The market return is calculated based on the Jakarta Composite Index (JCI) and was used in the Capital
Asset Pricing Model (CAPM) to calculate the cost of equity. The compounded return for the market is
calculated over a time period of 5 years (Dec 2005- Dec 2010) to determine the market return.
Risk free return:
The risk free rate is determined as an average of 3 government bond rates from Indonesia issued for a
period of more than 10 years and published in the year 2010. The risk free rate is the rate of return on an
asset that is theoretically free of any risk. When doing investment analysis on longer term projects or valuation, the risk free rate should be the long term government bond rate (Estimating Risk Free Rates by Dr. Aswath Damodaran of Stern School of Business, New York University page 6)12. Hence bonds having a maturity period of 10 years or more are considered for risk free rate calculation.
Project IRR (which is post tax ) is calculated based on following information:
Parameter Value Unit Source
Installed Capacity 8 MW Feasibility Study Report
Total Investment 139757 IDR(million) Feasibility Study Report
Annual O& M cost 3257 IDR(million) Feasibility Study Report
Annual Net electricity exported to grid 47,471 MWh Calculated
Electricity Tariff 656 IDR Feasibility Study Report
12
http://jft-newspaper.aub.edu.lb/reserve/data/fina306-ai-project-reading/riskfree.pdf
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
21
Income tax 28 % Indonesia Government
Regulation No.17 Year
2000, clausal No.17
Project Lifetime 20 years Feasibility Study report
Using above data Project IRR without CDM is calculated as below:
Above table shows that Post tax Project IRR without CDM is below the benchmark. The CDM revenue
helps improve the project IRR significantly.
Sensitivity Analysis:
Sub-step 2d: Sensitivity analysis
As per paragraph 20 of Guidelines on the assessment of investment analysis (EB 62, Annex 5); Only variables, including the initial investment cost, that constitute more than 20% of either total project costs
or total project revenues should be subjected to reasonable variation (all parameters varied need not
necessarily be subjected to both negative and positive variations of the same magnitude), and the results
of this variation should be presented in the PDD and be reproducible in the associated spreadsheets.
Where a DOE considers that a variable which constitute less than 20% has a material impact on the
analysis they shall raise a corrective action request to include this variable in the sensitivity analysis.
As per para 21 of the Guidelines on the assessment of investment analysis (EB 62, Annex 5); The DOE should assess in detail whether the range of variations is reasonable in the project context. Past
trends may be a guide to determine the reasonable range. As a general point of departure variations in
the sensitivity analysis should at least cover a range of +10% and 10%, unless this is not deemed
appropriate in the context of the specific project circumstances. In cases where a scenario will result in
the project activity passing the benchmark or becoming the most financially attractive alternative the
DOE shall provide an assessment of the probability of the occurrence of this scenario in comparison to
the likelihood of the assumptions in the presented investment analysis, taking into consideration
correlations between the variables as well as the specific socio-economic and policy context of the project
activity.
In line with the above guidance para 20 and 21 of EB62, Annex 5, following critical parameters have
been identified for conducting the Sensitivity analysis:
Plant load Factor (PLF) which constitutes 22% of total project cost
Operation and Maintenance cost which constitutes 18% of total project revenue.
Tariff rate which constitutes 22% of total project cost
Total project cost.
In line with paragraph 21 of EB62, annex 5, all the above parameters have been varied by at least 10%.
The results of the sensitivity analysis are reflected below:
Project IRR Value Benchmark
(WACC)
Without CDM 14.51% 22.74%
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
22
Particulars IRR with varied parameters (%)
-10.00% 0.00% 10.00%
IRR with variation in project investment 16.13% 14.51% 13.15%
IRR with variation in tariff 12.76% 14.51% 16.19%
IRR with variation in PLF 12.76% 14.51% 16.19%
IRR with variation in O&M expenses 14.76% 14.51% 14.27%
Plant load factor:
The Project IRR crosses the benchmark at PLF of 104.46 % which is not a likely to happen. The capacity
factor determined in the FSR according to historical hydrological data from 1997 to 2006 shows a value
lesser than 104.46%. Hence achieving a PLF value of 104.46% is not possible.
Operation and Maintenance cost:
The Project IRR crosses the benchmark when O&M cost is decreased to -9588 Million IDR. However,
such a situation is not possible as O&M cost usually increases year on year basis. There will not be a
situation of decrease in O & M cost. Hence, such a scenario of decreasing of -9588 Million IDR is not
possible.
Tariff rate:
The Project IRR crosses the benchmark at tariff of 996 IDR/kWh which is not realistic, as the PP signed
long term power purchase agreement for the period of 15 years at the rate of 656 IDR/kWh. As per PPA
Article 10, para 1, page 14 the tariff rate is as per the data by Minister of Energy and Mineral Resources
No. 31 of 2009, which is fixed for 15 years (as per article 3 para 1,page 7) from the date of
commissioning of the project. & Article 3, Para 2 page 7, states that The life of the agreement referred to in paragraph (1) of this Article 3, may extended the lifetime of power plant with the written approval of
THE PARTIES the lifetime of the project can be extended over to 15 years which is mentioned in para 1 by the parties PP and PLN with the written approval. Hence the PP may extend the PPA after 15 years
and so the tariff may also be remains same. Thus the situation is not likely to happen.
Project cost:
The Project IRR crosses the benchmark when the project cost is decreased to 87828 Million IDR.
However it is not possible as PP has already placed purchase orders for 80% of the total project cost.
Hence such a situation is not possible.
Conclusion:
Thus, the financial analysis shows that the project activity is not the most financially attractive, and the
sensitivity analysis shows that it is unlikely to be financially attractive compared to the benchmark under
reasonable variations of the relevant parameters.
Early Consideration of CDM:
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
23
As per the Guidelines on the Demonstration and Assessment of Prior Consideration of the CDM13, version 04, EB 62 (Annex13) , For Project activities with a start date on or after August 2008 the project participant must inform a Host party DNA and the UNFCCC Secretariat in writing of the
commencement of the project activity and of their intension to seek CDM Status. Such Notification must
be made within six months of the project activity starting date
The start date for the project activity is 04/08/2011 when the EPC contract for the project activity was
signed. The prior CDM consideration notification was sent to UNFCCC and Host party DNA on
09th March 2011 and 8
th March 2011 respectively. The same is reflected on UNFCCC website. This
confirms that the project proponent has seriously considered CDM benefits for the proposed project
activity.
The chronology of the events is presented below:
S.No Events Date
1 Board decision to processs the clearance for the 8 MW project activity 23rd
June 2010
2 PPA between PT. PLN (Persero) and PT. Tirta Gemah Ripah for Mini
Hydro Power Plant Total Capacity 2000 kW.
28th June 2010
3 Investment Approval from the Regent of Garut for Cirompang Mini
Hydro Power Plant with capacity 8.000 kW.
23rd July 2010
4 Recommendation on Cirompang MHPs Use of Land Allocation Permit, from the Office of Housing, Spatial Planning, and Settlements,
Garut regency.
26th July 2010
5 Recommendation letter document of Environmental Management
Effort & Environmental Monitoring Effort for Cirompang MHP 8 MW
construction.
2nd Sep 2010.
6 Feasibility study report Nov 2010
7 Board resolution to undertake the project activity under CDM 10th Dec 2010
8 CDM Advisory services agreement between PP and consultant. 2nd March 2011
9 CDM prior intimation to UNFCCC and DNA To UNFCCC - 9th
March 2011
To DNA 8th March 2011
10 Stakeholder consultation meeting 15th April 2011
11 EPC contract between PT. Hutama Karya (Persero) and PT. Tirta
Gemah Ripah
4th Aug 2011
12 The Agreement between PT. TGR with GP3A Daerah Irigasi
Cirompang (affiliation of farmers using Cirompang water) regarding
the Use of Dams, Irrigation Channels, and Tunnels for the Cirompang
Mini Hydro Power Investment Project.
11th Aug 2011
13 PPA between PT. PLN (Persero) and PT. Tirta Gemah Ripah for Mini
Hydro Power Plant Total Capacity 8000 kW
21st Nov 2011
13
http://cdm.unfccc.int/Reference/Guidclarif/reg/reg_guid04.pdf
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
24
B.6. Emission reductions:
B.6.1. Explanation of methodological choices:
Baseline Emissions
As per paragraph 11 of the methodology AMS-I.D., Version 17, the baseline emissions are calculated as
the product of electrical energy baseline yBLEG , expressed in MWh of electricity produced by the
renewable generating unit multiplied by the grid emission factor.
ygridCOyBLy EFEGBE ,,, 2*
Where:
yBE Baseline Emissions in year y (t CO2)
yBLEG , Quantity of net electricity supplied to the grid as a result of the implementation of
the CDM project activity in year y (MWh)
ygridCOEF ,,2 CO2 emission factor of the grid in year y (t CO2/MWh)
The Emission Factor is calculated in a transparent and conservative manner as follows:
A combined margin (CM), consisting of the combination of operating margin (OM) and build margin
(BM) according to the procedures prescribed in the Tool to calculate the Emission Factor for an electricity system, version 2.2.1, EB 63 Annex 19.
The Directorate General Electricity and Energy Utilization (DJLPE, Direktorat Jenderal Listrik dan
Pemanfaatan Energi), a government institution has issued an official baseline emission factor for the
Jamali grid which is available from.
http://pasarkarbon.dnpi.go.id/web/index.php/komnasmpb/read/20/faktor-emisi-jaringan-listrik-jawa-
madura-bali-jamali-2010-.html
The calculation method opted for expost grid emission factor is as per Tool to calculate the Emission Factor for an electricity system, version 2.2.1, EB 63 Annex 19 is presented in Annex 3 of the PDD.
Project Emissions:
As per paragraph 20 of approved methodology AMS-I.D. (Version-17, EB- 61), emissions from water
reservoir of hydro power plants qualify as project emissions.
The project emission for the project activity will be
PEy = PEHP,y + PEFF,y
Where:
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
25
PEHP,y - Emission from reservoir:
PEFF,y - Emission from fossil fuel consumption in year y. It is the emission from diesel generator which
will be used in emergency purposes and it is calculated by Tool to calculate project or leakage CO2 emission from fossil fuel consumption.
PEHP,y - Emission from reservoir:
The proposed project activity is implemented in the existing reservoir with no change in the volume of
reservoir. Therefore, project activity not shall account for CH4 and CO2 emissions from the reservoir. So
PEHP,y = 0.
PEFF,y - Emission from diesel generator backup:
The project emission includes the proponent of emission from diesel generator which will be used in
emergency purposes and it is calculated by Tool to calculate project or leakage CO2 emission from fossil fuel consumption.
The following formula is applied according to the Tool to calculate project or leakage CO2 emission from fossil fuel consumption:
Emission from the operation of a backup system in process j during the year y is calculated as follows:
PEFC,j,y = FCi,j y COEFi,y COEFi,y = NCVi,y EFCO2,i,y
Where:
PEFC,j,y Are the CO2 emissions from fossil fuel combustion in process j during the year y
FCi,j y Is the quantity of fuel type i combusted in process j during the year y (mass or volume
unit/year)
COEFi,y Is the CO2 emission coefficient of fuel type i in year y (tCO2/mass or volume unit)
NCVi,y Is the weighted average net calorific value of the fuel type i in year y
EFCO2,i,y Is the weighted average CO2 emission factor of fuel type i in year y (tCO2/GJ)
i Are the fuel types combusted in process j during the year y
PEy = 0.
Leakage Emissions:
As per paragraph 22 of the approved methodology AMS-I.D. (Version-17, EB-61), if the energy
generating equipment is transferred from another activity, leakage is to be considered. The leakage
emissions may be considered as zero as no such equipment shall be transferred from another project
activity. Hence LEy = 0
Emission Reductions
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
26
As per paragraph 23 of the approved methodology AMS-I.D. (Version-17, EB-61), Emission reductions
are calculated as follows:
yyyy LEPEBEER
Where:
yER Emission reductions in year y (tCO2/y)
yBE Baseline Emissions in year y (tCO2/y)
yPE Project emissions in year y (tCO2/y)
yLE Leakage emissions in year y (tCO2/y)
B.6.2. Data and parameters that are available at validation:
Data / Parameter: Grid Emission Factor
Data unit: tCO2e/MWh
Description: CO2 emission factor of the grid in year y
Source of data used: Emission Factor for Jamali Grid
Value applied: 0.713
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
The value is published by host country DNA
Any comment: The value is expost and hence it is to be monitored during the crediting period
Data / Parameter: Installed Capacity of the project activity
Data unit: MW
Description: The installed capacity of the project activity
Source of data used: Feasibility Study report
Value applied: 8
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
The data is from Feasibility Study Report.
Any comment: NA
B.6.3 Ex-ante calculation of emission reductions:
Ex- ante emissions are calculated as defined in section 6.1 as given below:
Baseline emissions (BE,y):
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
27
As per paragraph 11 of the methodology AMS-I.D, Version 17, the baseline emissions are the product of
electrical energy baseline yBLEG , expressed in MWh of electricity produced by the renewable generating
unit multiplied by the grid emission factor.
ygridCOyBLy EFEGBE ,,, 2*
Where:
yBE = Baseline Emissions in year y; tCO2e
yBLEG , = Quantity of net electricity supplied to the grid as a result of the implementation of the
CDM project activity in year y (MWh)
ygridCOEF ,,2 = CO2 emission factor of the grid in year y (tCO2e/MWh)
Parameter Units Value Remarks
Capacity of each turbine MW 2 FSR
Number of turbines Nos 4 FSR
Total installed capacity MW 8 Calculated
Total number of hours of operation
annually Hours 8760 FSR
Plant load factor % 68.77 FSR
Gross energy generation MWh 48194 Calculated
Auxiliary consumption % 1.5 FSR
MWh 723 Calculated
Net energy generation from the project
activity MWh 47471 Calculated
Grid emission factor tCO2e/MWh 0.713 Calculated
Baseline emissions tCO2e/year 33,847 Calculated
Project Emissions (PEy)
The project emission includes the proponent of emission from diesel generator which will be used in
emergency purposes and it is calculated by Tool to calculate project or leakage CO2 emission from fossil fuel consumption.
The following formula is applied according to the Tool to calculate project or leakage CO2 emission from fossil fuel consumption:
Emission from the operation of a backup system in process j during the year y is calculated as follows:
PEFC,j,y = FCi,j y COEFi,y COEFi,y = NCVi,y EFCO2,i,y
Where:
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
28
Particular Unit Value Remarks
Quantity of diesel consumption in
the project activity Litres/annum 0
Diesel will be consumed only for
emergency cases
Net Calorific Value of diesel TJ/tonne 0.0433
2006 IPCC Guidelines for
National Greenhouse Gas
Inventories, Volume 2, Chapter 1,
Table 1.2, The upper limit value
has been used.
Emission factor of diesel tCO2/TJ 74.8
2006 IPCC Guidelines for
National Greenhouse Gas
Inventories, Volume 2, Chapter 1,
Table 1.4. The upper limit value
has been used.
Density of diesel T/litre 0.8439*1
0^-3
http://v-c-s.org/sites/v-c-
s.org/files/15.%20E-
FFC%20fossil%20fuels.pdf
Project emission due to
consumption of diesel tCO2e/annum 0 Calculated
Hence PEy = 0
Leakage Emissions (LEy)
LEy = 0
Emission Reduction
ERy, = BEy PEy LEy, = 33,847 0 0 = 33,847
B.6.4 Summary of the ex-ante estimation of emission reductions:
Year
Estimation of
project activity
emissions
(tonnes of
CO2e)
Estimation of
baseline
emissions
(tonnes of
CO2e)
Estimation of
leakage
(tonnes of
CO2e)
Estimation of
overall emission
reductions
(tonnes of CO2e)
Year1 (01/03/2013-
28/02/2014) 0 33,847 0 33,847
Year 2 (01/03/2014-
28/02/2015) 0 33,847 0 33,847
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
29
Year 3 (01/03/2015 -
29/02/2016) 0 33,847 0 33,847
Year 4 (01/03/2016 28/02/2017)
0 33,847 0 33,847
Year 5 (01/03/2017 28/02/2018)
0 33,847 0 33,847
Year 6 (01/03/2018 28/02/2019)
0 33,847 0 33,847
Year 7 (01/03/2019 29/02/2020)
0 33,847 0 33,847
Year 8 (01/03/2020 28/02/2021)
0 33,847 0 33,847
Year 9 (01/03/2021 28/02/2022)
0 33,847 0 33,847
Year 10 (01/03/2022
28/02/2023) 0 33,847 0 33,847
Total Emission
Reductions
(tCO2e)
0 338,470 0 338,470
B.7 Application of a monitoring methodology and description of the monitoring plan:
B.7.1 Data and parameters monitored:
Data / Parameter: EGfacility,y= EGBL,y
Data unit: MWh/year
Description: Quantity of net electricity supplied to the grid in year y
Source of data to be
used:
Onsite measurement by Project Developer
Value of data 47,471
Description of
measurement methods
and procedures to be
applied:
Electricity will be measured with an electricity meter and will be recorded on a
monthly basis by Project Developer with the use of Energy Meter (s).
Measured : Continuously
Recorded : Monthly
QA/QC procedures to
be applied:
The meter(s) will be subject to maintenance and calibration according to standard
set by PLN. On site staff will receive training in CDM monitoring and the
maintenance requirements of the electricity meters.
Data measured by the meter(s) will be cross checked using electricity sales
receipts.
The accuracy (class 0.2) of the measurement will be ensured through annually
calibration by a qualified party.
Any comment: Data will be archived at least for two years after the end of the crediting period,
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
30
or the last issuance of CERs, whichever occurs later.
Data / Parameter: ygridCOEF ,,2
Data unit: tCO2e/MWh
Description: CO2 emission factor of the grid in year y
Source of data to be
used:
Emission Factor for Jamali Grid.
Value of data 0.713
Description of
measurement methods
and procedures to be
applied:
The value is published by the host country DNA. However, the calculation
procedure is provided in Annex 3
QA/QC procedures to
be applied:
The data is a published data by host country DNA. Hence QA/QC procedure is
not applicable.
Any comment: Data will be archived at least for two years after the end of the crediting period,
or the last issuance of CERs, whichever occurs later.
Data / Parameter: yiFC ,
Data unit: Litres/annum
Description: Quantity of fossil fuel consumption(diesel) in project activity in a year
Source of data to be
used:
Log book maintained to record onsite consumption of diesel.
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.6
-
Description of
measurement methods
and procedures to be
applied:
The data will be monitored continuously and aggregated monthly.
QA/QC procedures to
be applied:
The diesel consumption quantities can be cross-checked with the records of the
quantity of diesel purchased from the invoices.
Any comment: The data will be archived electronically and the archived data will be kept for 2
years beyond the Crediting Period.
Data / Parameter: yiNCV ,
Data unit: TJ/tonne
Description: Net calorific value of the fossil fuel (i) (diesel) combusted in the project activity
during the year y.
Source of data to be
used:
2006 IPCC Guidelines for National Greenhouse Gas Inventories, Volume
2,Chapter 1, Table 1.2
Value of data applied 0.0433
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
31
for the purpose of
calculating expected
emission reductions in
section B.6
Description of
measurement methods
and procedures to be
applied:
The net calorific value of diesel has been sourced from IPCC 2006 default value
at the upper limit of the uncertainty at a 95% confidence interval and any future
revision of the IPCC guidelines will be taken into account in determining the
same.
QA/QC procedures to
be applied:
Project participants have no control on the parameter. Hence, No QA/QC
procedures are applicable.
Any comment: The data will be archived electronically and the archived data will be kept for 2
years beyond the Crediting Period.
Data / Parameter: diesel
Data unit: T/Litres
Description: Density of fossil fuel diesel combusted in the project activity
Source of data to be
used:
http://v-c-s.org/sites/v-c-s.org/files/15.%20E-FFC%20fossil%20fuels.pdf
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.6
0.8439*10^-3
Description of
measurement methods
and procedures to be
applied:
The value of the density of the diesel has been taken based on regional values
available.
QA/QC procedures to
be applied:
Not applicable.
Any comment: The data will be archived electronically and the archived data will be kept for 2
years beyond the Crediting Period.
B.7.2 Description of the monitoring plan:
Parties involved in monitoring
This section details the steps taken to monitor the greenhouse gas emissions reductions on a regular basis.
The Monitoring set up for this project has been developed to ensure that from the start, the Project is well
organised in terms of the collection and archiving of complete and reliable data.
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
32
The monitoring of this type of project consists of metering the electricity generated by the renewable
technology. Below is the description of monitoring procedures for data measurement, quality assurance
and quality control.
PLN, as the state-owned company that own the Grid to which the Project Developer send its electricity to,
is responsible in maintaining the electricity generation in the Grid as well as the system of metering to
measure the transferred electricity into the Grid. The monitoring plan of the project will follow PLN
system on measuring the electricity sent to the Grid.
Metering of Electricity Supplied to the Grid
The main electricity meter for establishing the electricity delivered to the grid will be installed at the
project site using a Metering System that is approved by PLN. This electricity meter provides the main
data for CER measurement, thus it will be the key part of the verification process. To check the amount of
electricity delivered to the grid, official data will be used.
In case of emergency purposes, the diesel generators will be used.
Quality Control and Quality Assurance
Quality control and quality assurance procedures will guarantee the quality of data collected. The
electricity meter(s) will undergo periodic calibration once in a year throughout the lifetime of the Project
Activity. Inspection will also be done as requested by PLN subject to manufacturer standards. Moreover,
meter(s) are maintained by qualified spare parts. Documents of these procedures will be available during
the verification.
Data Collection and Archiving:
The monthly data of electricity generation is collected in electronic form. However, the data in electronic
form is archived throughout the life time of the project. The electricity records are maintained regularly
by the team at the site. The archived data will be kept for 2 years beyond the Crediting Period.
The following chart shows the data flow for the monitored data for the project acticity.
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
33
The table below shows the roles and responsibilities and the information flow for the project activity data.
Personnel Responsiblity
Power plant Shift Incharge Monitoring the plant parameters including
the monitoring parameters as described in
the PDD.
Collecting the data recorded in log sheets
of respective sections and prepares the
consolidated report on electricity
generation.
Power plant Operators
Responsible for the overall plant
performance and electricity generation of
the power plant.
Cross check and sign the daily plant
operation reports regularly.
Should look after the periodical tests of the
monitoring equipments as per the
monitoring plan.
Responsible for the storage and archiving
of information in good condition.
Power plant Manager Responsible for the total monitoring plan.
Examining the reports generated by Power
President PT TGR
CDM Manager
Power plant
Manager
Power plant
operators
Power plant Shift -
In charge
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
34
Plant operators with reference to the
monthly electricity generated; net
electricity exported to grid and annual
emission reduction calculations as per the
monitoring plan.
CDM Manager Responsible for overall CDM activities and
proper monitoring of data as mentioned in
monitoring plan.
He will be reporting to Director to look
after the CDM validation / verification
process for the project activity.
President PT TGR President will review the reports regularly
and take necessary corrective action
conforming to CDM.
Emergency procedures:
A back up meter will be installed in the power house and equipped with UPS (Uninterruptible Power
Supply). In the situation of the main meter has problem, the back up meter will maintain the metering
process. To ensure that the data is recorded correctly, the shift engineer will read the meter in power
house and record it in the log book.
B.8 Date of completion of the application of the baseline and monitoring methodology and the
name of the responsible person(s)/entity(ies)
Date of completion of the application of the baseline and monitoring methodology: 14/07/2011
Name of the entity determine the baseline:
Mr.Johan Romadhon, CEO, PT Tirta Gemah Ripah.
PT. Tirta Gemah Ripah. (Project Participant as mentioned in Annex 1)
SECTION C. Duration of the project activity / crediting period
C.1 Duration of the project activity:
C.1.1. Starting date of the project activity:
04/08/2011 (Signing of EPC contract).
C.1.2. Expected operational lifetime of the project activity:
20 years
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
35
C.2 Choice of the crediting period and related information:
Project Activity will use Fixed Crediting Period.
C.2.1. Renewable crediting period
C.2.1.1. Starting date of the first crediting period:
NA
C.2.1.2. Length of the first crediting period:
NA
C.2.2. Fixed crediting period:
C.2.2.1. Starting date:
01/03/2013 or registration date. (Whichever occurs later)
C.2.2.2. Length:
10 years
SECTION D. Environmental impacts
D.1. If required by the host Party, documentation on the analysis of the environmental impacts
of the project activity:
Based on the letter issued by the Department of Mining and Energy ,Directorate General of Electricity
and Energy Development, the project activity does not required to have an Environment Impact
Assessment (AMDAL) however it is still required to submit an Environment Management (UKL) and
Environment Planning(UPL) Procedure to be approved and fulfilled. The same has been approved for the
project activity by Badan Pengelolaan Lingkungan Hidup, Pemerintaah Kabupaten Garut (Local
Government Environment Department) .The project activity will also need to comply with the procedure
by submitting a periodic report.
Table 5: Summary of Environment Management Procedure Findings
Activity Impacts Parameters Environmental Management
Efforts
Pre-construction
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
36
Field Survey
Land
Procurement and
Acquisition
Public
Perception
Public
Perception
Normal daily activities (does not cause
fears and anxieties among the
residents)
Appropriate reimbursement (of the
lands owned by the residents)
Mutual agreements with local
agencies (lands owned by Perhutani)
Socializing the PLTMH
development project to the
community,
Discussion and coordination to set
the reimbursement price for land
acquisition.
Discussion and coordination with
local agencies associated with the
use of lands owned by the residents.
Construction
Workforce
Recruitment and
Layoffs
Public
Perception
Job
Opportunities
Increased
Income
Complaints of the residents
The number of workers recruited from
local residents
Complaints of the residents
The number of workers recruited from
local residents
Wage satisfaction
Prioritizing the local workforce in
recruitment
Inform the workers that the jobs for
construction period will be
temporary (during construction
period)
Prioritizing the local workforce in
recruitment
Providing the appropriate and
adequate wages
Land Clearing
and Maturation
Degradation of
Water Quality
and
disturbance to
water biota
Loss of
vegetations
Landslide
Water quality standard (PP. no 82
Year 2001 or West-Java Governor
Decision no. 38/1991 )
The magnitude of lost vegetations
(area of cleared space)
Complaints from the residents about
the risk of landslide
Disturbance to environmental function
and stability.
The logging will be carried out
selectively (only as necessary)
The arrangement of execution time
(not during rains)
Digging of pile will be carried out
as necessary and carefully.
Digging and hoarding will be
carried out as necessary and
carefully
Activities will not be conducted
during heavy rainfalls period
Constructing a landslide retainer,
especially in places with high risk
of landslide
Planting vegetations to strengthen
the cliff, this eventually is expected
to prevent landslide.
Construction of
Main Facilities
and
Infrastructure
Landslide and
Degradation of
water quality
Perception and
Complaints of
Complaints from the residents about
the risk of landslide
Disturbance to environmental function
and stability.
Digging and hoarding will be
carried out as necessary and
carefully
Activities will not be conducted
during heavy rainfalls period
Constructing a landslide retainer,
especially in places with high risk
of landslide
Planting vegetations to strengthen
the cliff, this eventually is expected
to prevent landslide.
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
37
the
Community
(to the
installation of
transmission
network)
The willingness of residents to allow
electrical poles installed in their land
No request for reimbursement.
Inform the residents about the
benefits of transmission network
installations.
Operations
Recruitment of
Workers
Job
opportunities
Increased
Income
The number of workers recruited from
local residents
Adequate wages and satisfaction with
the wage earned
Prioritizing the local workforce in
recruitment.
Inform them that the jobs for
construction period will be
temporary and limited to a few
workers.
Providing adequate and appropriate
wages to the workers.
Operations and
Management of
Pembangkit
Listrik Tenaga
Mikro Hidro
(PLTMH) and
Maintenance of
PLTMH
facilities
Facilities
provided to the
community
(electricity)
Nuisance
Landslide
Public
perceptions
Improvement
of Water
Quality
Accidents and
Safety Issues
Addition of Electrical Capacity
Noise Standards (kepMenLH No Kep-
48/MenLH/11/1996)
Complaints from the residents about
the risk of landslide.
Disturbance to environmental function
and stability.
Satisfaction of community
Quality standards of River Water (PP
no. 82 Year 2001 or West-Java
Governor Decision No.38/1991).
Success of reforestation.
Number of Reported Accidents
Optimizing the operations
Placing the turbine in closed space
Constructing a landslide retainer,
especially in places with high risk
of landslide
Planting vegetations to strengthen
the cliff, this eventually is expected
to prevent landslide.
Inviting community participation in
managing PLTMH
Coordinating with local authorities
and agencies in managing PLTMH
If the mud precipitates in the
tranquilizing pool, it will not be
thrown directly to the river, but
removed from the pool to other
area.
The clearance of water entering the
turbine (by installing trash
trapper/trap).
Keeping the hygiene
Conducting reforestation in the
open activity locations due to
PLTMH development activities
Developing clear work instructions
which are obeyed by all workers.
Installing warning/notification
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
38
Environmental
Security
New Business
Opportunities
(because the
availability of
electricity)
Number of disturbances to the
PLTMH facilities.
Disruptions of the forest areas
surrounding the location.
Improvement of local economy
board.
Creating boundary or setting up
fences for important and accident-
prone facilities.
Providing the workers with personal
protective equipment and first aid
kit.
Coordinating with local agencies.
Keeping the environmental
securities together with the
community and local government
agencies.
Organizing community
development activities in
Bungbuland and Cihikeu villages.
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
The project is expected to deliver an overall positive sustainable impact and development on the local and
global environment All negative environmental impacts are subjected to observation and management as
described above.
SECTION E. Stakeholders comments
E.1. Brief description how comments by local stakeholders have been invited and compiled:
The project developer conducted a stakeholders consultation meeting at their project site with the local village people residing in and around the vicinity of this project activity in order to view the concerns of
the local stakeholders and their opinion about the proposed project activity on 15/04/2011. Some of the
key local stakeholders were also invited by an invitation letter14
. The local population and regulatory
authorities participated in that meeting. An advertisement was also published to inform local people
regarding the project activity in daily newspaper i.e. Radar Garut on 4 April 2011.
Mr. Herman Rachmat (General Manager TGR) briefed the attendees about the project and the agenda of
the stakeholder meeting and introduced the global warming and the climate change.
Mr.Yulianto (Project Director TGR) introduced the company/project to the audience and also presented a brief overview of the hydro power business.
After this brief introduction of company, climate change, Kyoto Protocol and CDM, he explained to the
attendees the purpose of the stakeholder consultation meeting as to seek the concern, opinion and
suggestion of the stakeholders.
14 Copy of invitation letters shall be provided at the time of validation
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
39
Subsequently, project promoter invited the stakeholders to ask for their queries and suggestions. The
questions and responses to their query are given in the next section.
E.2. Summary of the comments received:
People participated with great enthusiasm and raised a few questions, which were answered to in an
appropriate manner by the project developer. Summary of these comments is given as follows;
Mr.Ayi Saripudin (Cibungbulang Head of Sub-districts Secretary) Opening Statement:
We would like to thank PT. Gemah Ripah for its contribution to the Bungbulang Sub-district by
developing the Cirompang Mini Hydro Power Plant (MHPP), hereafter referred as MHPP. We also fully
support the CDM project, a global/international scale program, which allows us to contribute to save the
environment.
Mr.Burhanudin Apip (Head of Local Environmental Management Council)
Opening Statement:
We support the development of Cirompang MHPP, because Garut Regency still lacks electricity. In
addition, 18500 houses in our regency are still not connected to the electrical network. Therefore, we
support the development of Cirompang MHPP.
Mr. M.Mahfudin (GP3A of Mitra Cai)
Question: We fully support the development of Cirompang MHPP and CDM proposal, and according to
the agreement between TGR and Mitra Cai, we hope that the rice fields will continue to be irrigated and
we hope that TGR will conduct reforestation in the area surrounding the project location.
Answer: TGR will neither destroy the existing channels nor use the old tunnels, but we will construct
new channels and tunnels. Therefore, the irrigation will not be disturbed during the construction period.
In accordance to the agreement between TGR Mitra Cai, the water will be prioritized to irrigate the rice fields up to 800 L/seconds, and the rest will be allocated to MMPH.
Mr. Ridwan Taufik (Sabareuma Environmental Activist)
We support the Development of Cirompang MMPH, because it represents clean, environmentally friendly
energy.What are the advantages of CDM to the community and environment?
Answers:
To supply the electricity to Garut Regency
To preserve the environment because PLTM is free of pollution.
To provide jobs to the members of Bungbulang community according to their skill set.
To assist in increasing the CSR activities to the community surrounding the project.
Mr.Tjahya (Head of Intellegence, Bungbulang Police Department)
In principle, we support the continuation of the Cirompang MHPP project.We request a coordination
between TGR, Muspika of the Sub-district, and police department for the safety and continuity of the
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
40
project. The police department is ready to help the project in preventing any provocation, in order to aid
safe and continuous development of PLTMH.
Mr. Aos Suryana (Water and Mining Resources Agency)
At the location of Cirompang irrigation grounds belonging to SDAP, above the bridge to be exact, there is
an area of around 2-3 Hectares, which can be utilized for reforestation. We hope that from the CDM
project, the TGR can participate in restoring the area for greener purposes
The meeting was concluded with vote of thanks by Mr. Herman Rachmat from TGR. In general, all
participants in the forum supported the implementation of proposed project.
E.3. Report on how due account was taken of any comments received:
No negative comments have been received on the Project.
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
41
Annex 1
CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY
Organisation: Nordic Environment Finance Corporation NEFCO in its capacity as Fund
Manager to the NEFCO Carbon Fund (NeCF)
Street/P.O.Box: Fabianinkatu 34, P.O. Box 249
Building:
City: Helsinki
State/Region:
Postal code: FI-00171
Country: Finland
Phone: +358 10 6180 644
Fax: +358 9 630 976
E-mail:
URL: www.nefco.org/cff
Represented by: Ash Sharma
Title: Vice President,
Head, Carbon Finance and Funds Unit
Salutation: Mr.
Last name: Sharma
Middle name:
First name: Ash
Department:
Phone (direct): + 358 10 6180 644
Fax (direct): +358 9 630 976
Mobile: +358 10 6180 644
Personal e-mail: [email protected]
Organization: PT. Tirta Gemah Ripah
Street/P.O.Box: Jl. Tubagus Ismail Depan No. IA
Building:
City: Bandung
State/Region: West Java
Postfix/ZIP: 40134
Country: Indonesia
Telephone: +62-222535852/+62-8112209514
FAX: +62-222535851
E-Mail:
URL: -
Represented by: Mr Johan Romadhon
Title: CEO
Salutation: Mr
Last Name: Romadhon
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
42
Middle Name:
First Name: Johan
Department: -
Mobile: +62-8112209514
Direct FAX: +62-222535851
Direct tel: +62-222535852/+62-8112209514
Personal E-Mail: [email protected]
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
43
Annex 2
INFORMATION REGARDING PUBLIC FUNDING
No public funding is involved in this project activity
-
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
44
Annex 3
BASELINE INFORMATION
Calculation of Grid Emission Factor
The Board decision on CDM consideration for the project activity is in Dec 2010. The emission factor
value considered for Emission factor calculation in the PDD is based on the data published in the year 2010
by the Indonesian DNA in its website stating Emission factor for electricity system of the Java-Madura-
Bali (Jamali) based on the 2010 update which in turn refers the documents No: 2478/21/600.4/2011 dated
31st Mar 2011 and document No: B-48/DNPI/05/2011 dated 5th May 2011 which gives 0.713 tCO2e/MWh
as value, which is the recent data available before webhosting of the PDD for GSP during 09 Dec 11 - 07
Jan 12.
The expost grid emission factor has been estimated using the following six steps of according to Tool to
calculate the emission factor for an electricity system (Version -02.2.1, EB- 63, Annex 19):
Step 1: Identify the relevant sy