2013 CAPITAL IMPROVEMENT PROGRAM (CIP)CIP UpdateBoard of Education MeetingOctober 28, 2014
CIP IMPLEMENTATION• Program is on schedule• Ongoing meetings with COC
– Held monthly since June 2014– COC Quarterly Report at November 11 Board Meeting
• Ongoing consultation with industry organizations– TEXO, Association of General Contractors– American Subcontractors Association (ASA)– Council of Education Facilities Planners International (CEFPI)
PROGRAM TIMELINE
Phase 1On Target
QT 2 QT3 QT4 QT 2 QT3 QT4 QT1 QT 2 QT3 QT4
Phase 2 September 30, 2014Ahead
Phase 2Phase 1
2017QT 2 QT3 QT4
2015QT1
2014 2016QT1 QT1
Phase 3
CIP STATUSPhase 1&1A: On Schedule
• Completed design and final reviews in preparation for 4th Quarter Procurement
• New schools in design– New Washington Heights ES (anticipated completing re-design by
Mid-November 2014)– New Westpark ES (anticipate completing design February 2015)
Phase 2: On Schedule• Principal Orientation Meetings On-Going• Scope to Budget in Process
Phase 2A: Delayed • Visual & Performing Arts Academy - Site Selection and A/E Selection• STEM Academy – Site Selection and A/E Selection
Phase 3: Scheduled to begin April 2015
CIP STATUSInformation Management
• CIP Website• CIP Monthly Newsletter• CIP Monthly Dashboard• CIP Quarterly Updates
Safety Program• All vendors undergoing safety screening
Risk Management• No claims or legal action reported
CIP PROCUREMENT STATUSArchitect /Engineers under contract
• 25 A/E firms – 28 contracts
Other Consultants under contract • Geotechnical (8)• Materials Testing (3)• Printing (3)• HazMat Consulting (6)• Insurance (1)• Movers (1)• Registered Accessibility Specialists (4)• Roof Consulting (5)• Test and Balance (1)
In Process• HazMat Contractors – November 11• Construction Manager at Risk
CIP EXECUTION STATUS – PRE-DESIGN & DESIGNProgramming• Academic Leadership Coordination
• Universal Pre-K• Athletics• Food Services
Pre-Design• Scope-to-Budget (School Participation and District Sign-Off)
• 35 Projects Complete• 2 in Process
Design Process• 4 Projects in Schematic Design• 1 in Design Development• 27 in Construction Documents
CIP EXECUTION STATUS – CONSTRUCTION
Construction Procurement• BP041 – New Washington Heights
– Bids rejected, Project in re-design
Construction In Progress• BP 053 – Safety & Security (Phase 1)
– Construction is scheduled to be complete by Mid-October 2014
– Projects undergoing certification by City of Fort Worth and FWISD Safety & Security
Construction Complete• BP 032 – YWLA (Phase 2)
CIP HUB & COMMUNITY OUTREACH HUB Participation
• Program Manager• Fees Contracted: 42.9%
• Architects/Engineers• Fees Committed: 35.7%
Training/HUB Events• Ongoing One-on-One Vendor Trainings• Phase 1 Bid Preview (July 17)
Opportunities for all Vendors
CIP FINANCIAL OVERVIEW
CIP Construction/Capital Projects - $357.3M
FWISD District Operations - $30M• Buses/Vehicles – $22M• Furniture, Fixture & Equipment (FF&E) Refresh – $5.5M• Student Uniforms & Instruments – $2.5M
FWISD Division of Technology - $102.6M • Network Electronics - $27.1M• Student Mobile Devices (High Schools) - $15M• Campus Based Computer/Printer Replacement - $60.5M
CIP Construction/Capital Projects - $357,369,165
Total Encumbered To Date: ($27,924,160)
Total Paid To Date: ($15,192,341)
Subtotal: ($43,116,501)
Available Budget as of 9/30/2014: $314,252,664
CIP FINANCIAL OVERVIEW
CIP FINANCIAL OVERVIEW
FWISD District Operations - $30,000,000
Total Encumbered To Date: ($ 4,930,477)
Total Paid To Date: ($ 0)
Subtotal ($ 4,930,477)
Available Budget as of 9/30/2014: $25,069,523
Encumbered amount is the purchase ofClassroom desks and chairs, 50 buses, 26 maintenance
vehicles, and band uniforms and instruments
CIP FINANCIAL OVERVIEW
FWISD Division of Technology - $102,600,000
Total Encumbered To Date: ($16,422,223)
Total Paid To Date: ($ 3,591,457)
Subtotal ($20,013,680)
Available Budget as of 9/30/2014: $ 82,586,320
Campuses $15,020,975• Network Electronics and Wi-Fi $5,560,731• Desktop Computer Refresh $1,742,272• Laptop Computer Refresh $2,240,942• Promethean Projector Refresh $5,161,520• Distance Learning Centers $315,510
Network Operations Center $1,401,248• Network Electronics and Wi-Fi $1,401,248
High School Mobile Device One-to-one• Phase I Schools Devices Have Been Ordered• Training Ongoing at Phase I Campuses• 1:1 Specialists are In Place and Building Teacher Capacity to Support
the Student 1:1 Deployment
TECHNOLOGY OVERVIEW – ROUND 1
Technology Budget $102.6MEncumbered $16,422,223