chuck lemon 2-14-07

Upload: tarek

Post on 04-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Chuck Lemon 2-14-07

    1/19

    Tower Crane Safety Regulations

    Chuck Lemon

    Division of OccupationalSafety & Health

  • 8/13/2019 Chuck Lemon 2-14-07

    2/19

    Current

    Regulations that cover Tower Cranes

    WAC 296155525 ANSI B30.31990

    OSHA 29 CFR 1926550 Subpart N

  • 8/13/2019 Chuck Lemon 2-14-07

    3/19

    Upcoming New Regulations

    WAC 296880 (this number could change)

    Available on L&Is Website

    ASME B30.32004 (effective now, not

    adopted in rule)

    OSHAs New Crane Rule (C-DAC)

    Available in OSHAs Website

  • 8/13/2019 Chuck Lemon 2-14-07

    4/19

    What the current rules say

    WAC 296

    525

    (2)(a) Operate all cranes per manufacturers

    specifications (2)(d) Designate a competent person to

    inspect all machinery and equipment prior to

    use and periodically during use to make sure

    it is safe.

  • 8/13/2019 Chuck Lemon 2-14-07

    5/19

    What the current rules say

    WAC 296

    525 (cont.)

    (2)(e) Have a competent person, or a

    government or private agency recognized byL&I perform a thorough annual inspection of

    the hoisting equipment and maintain a

    permanent record of these inspections.

    (2)(f) A tag line must be used on all loadsthat swing freely. Tag lines must be held by

    experienced persons.

  • 8/13/2019 Chuck Lemon 2-14-07

    6/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(a) Tower Cranes must be erected,

    jumped and dismantled under the immediatesupervision of a competent person.

    (5)(b) Tower cranes must be erected,

    maintained, and used per the manufacturers

    specifications. All modifications must beapproved by the manufacturer and

    engineered by a PE.

  • 8/13/2019 Chuck Lemon 2-14-07

    7/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(c) A professional engineer must certify that the

    crane foundations and underlying soil are adequate

    support for the tower crane.

    (5)(e) Prior to installing a climbing tower crane within

    an existing building or new construction, a structural

    engineer must certify that the building is designed to

    withstand the torque & floor loading created by thecrane to be installed.

  • 8/13/2019 Chuck Lemon 2-14-07

    8/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(f) Tower cranes erected on new

    foundations must be tested per ANSI B30.3-1990 Chapter 3-1.

    This test would include all functional motions,

    limiting devices, and brakes for operation.

    Limiting devices must be checked for propersetting.

  • 8/13/2019 Chuck Lemon 2-14-07

    9/19

    What the current rules say

    WAC 296

    525 (cont.)

    The functional tests must include slewing,

    trolleying, and hoisting with frequent stops,starts, and reversals.

    The functional motion test should continue

    for 15 minutes during which all controls,

    drives, and braking means engaged shallhave functioned correctly.

  • 8/13/2019 Chuck Lemon 2-14-07

    10/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(f)(i) Load test not less than 110% capacity for 15

    minutes at the maximum radius. Results of test must

    be within the manufacturers specifications.

    (5)(f)(ii) A record of each test must be made and

    signed by the person responsible for conducting the

    test. This record must be maintained at the

    construction site and made part of the firmspermanent equipment records.

  • 8/13/2019 Chuck Lemon 2-14-07

    11/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(j) Limit switches must be installed and keptproperly adjusted. Limit switches must provide the

    following functions: (i) Safely limit the travel of the trolley to prevent it from

    hitting the outer end of the jib.

    (ii) Limit the upward travel of the load block to limit two-blocking

    (iii) Lower over travel limiting devices must be provided forall load hoists where hook area is not visible to the operator

    (iv) Limit the load being lifted in a manner whereby no morethan 110% of the maximum rated load can be lifted ormoved.

  • 8/13/2019 Chuck Lemon 2-14-07

    12/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(k) Only use tower cranes for the proper handling

    of freely suspended loads, they are not to be used

    for pulling vehicles, removing pilings, pull away loadswhich are attached to the ground or walls.

    (5)(p) Tower cranes must have a a functional

    slewing brake. When crane is out of operation, the

    jib/boom must be pointed downwind and the slewingbrake released so it can weathervane.

  • 8/13/2019 Chuck Lemon 2-14-07

    13/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(q) Tower cranes must have a functional

    braking system on the trolley. An automaticbrake or device must be installed which will

    immediately stop and lock the trolley in the

    event that the trolley rope breaks.

    (5)(r) All electrical equipment must begrounded and protection must be provided

    against lightning.

  • 8/13/2019 Chuck Lemon 2-14-07

    14/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(t) All brakes must automatically set in

    event of power failure. (5)(u) Climbing jack systems must be

    equipped with over-pressure relief valves,

    direct-reading gauges, and pilot-operated

    hydraulic check valves. These must be ableto prevent jack from retracting should a

    hydraulic line or fitting rupture or fail.

  • 8/13/2019 Chuck Lemon 2-14-07

    15/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(v) During periods of high winds or

    weather affecting visibility, i.e., fog, etc. onlyhandle loads that are consistent with good

    safety practices. The practices must be

    agreed upon by the operator and the person

    in charge of the construction job, with dueconsideration given to the manufacturers

    recommendations.

  • 8/13/2019 Chuck Lemon 2-14-07

    16/19

    What the current rules say

    WAC 296

    525 (cont.)

    (5)(x) Tower cranes must be inspected & maintained

    per the manufacturers recommendations or more

    frequently if reason to suspect a possible defect orweakening of any portion of the structure or

    equipment.

    (5)(y) Guy wires, wedges, braces or other supports

    must be inspected at the beginning and midpoint ofeach work shift to ensure they are functioning as

    intended.

  • 8/13/2019 Chuck Lemon 2-14-07

    17/19

    What the current rules say

    WAC 296

    525 (cont.)

    (6)(b) Tower cranes must not be erected or

    raised when the wind velocity at the worksiteexceeds 20 MPH or as specified by the

    manufacturer.

    (6)(c) Tower crane operators must be trained

    and experienced in tower crane operations. (6)(f) Buffers must be provided at both ends

    of travel of the trolley.

  • 8/13/2019 Chuck Lemon 2-14-07

    18/19

    What the current rules say

    WAC 296

    525 (cont.)

    (6)(h) All hammerhead tower cranes must meet

    the requirements for design, construction,installation, testing, maintenance, inspection, and

    operation as prescribed by the manufacturer.

  • 8/13/2019 Chuck Lemon 2-14-07

    19/19

    Questions?

    Contact information:

    Chuck Lemon (360) 902-4669

    [email protected]

    mailto:[email protected]:[email protected]