Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur (CG.) Pin-492001
Phone: 91-771-4048788, Fax: 2445857 Website: cserc.gov.in, Email: [email protected]
In the matter of Approval of Capital Investment Plan filed by Chhattisgarh State Power Distribution Company Ltd. for FY2013-14
to FY2015-16.
Petition No. 54 of 2012(M)
M/s Chhattisgarh State Power Distribution
Company Limited ..... Petitioner
Present: Manoj Dey, Chairman
Vinod Shrivastava, Member
ORDER
(Passed on 10.04.2013)
1. Chhattisgarh State Power Distribution Company Limited (herewith called
‘CSPDCL’) is a successor company of Chhattisgarh State Electricity
Board (CSEB) and is a deemed distribution licensee under the provisions
of Electricity Act, 2003 (The Act).
2. Based on the principles contained in Sections 61 and 62 of the
Electricity Act 2003, the National Electricity Policy and the Tariff Policy
notified by the Central Government, the Commission notified the
regulations namely Chhattisgarh State Electricity Regulatory
Commission (Terms and Conditions for determination of tariff according
to Multi-Year Tariff principles and Methodology and Procedure for
determination of Expected revenue from Tariff and Charges)
Regulations, 2012 (herewith referred as ‘MYT Regulations 2012’) on 6th
October 2012.
3. As per Regulation 2.1 (d) of these regulations, the scope of regulations
covers the distribution licensee in the state. Accordingly, CSPDCL is
covered by the said regulations.
4. The Regulations 7 of the MYT Regulations, 2012 relate to filing of
Capital Investment Plan by the entities covered by the MYT Regulations
2012. The relevant portion is reproduced for ready reference.
“7. CAPITAL INVESTMENT PLAN
7.1 The Generating Company, Transmission Licensee, and Distribution Licensee shall file for approval of the Commission a capital investment plan by 31st October 2012. The capital investment plan
should cover the entire Control Period, with details for each year of
the Control Period.
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 2 of 22
7.2 The capital investment plan may be in respect of new generation projects or transmission/distribution schemes (for lines, sub
stations, bays, etc.) for capacity addition/ enhancement or
renovation of existing capacities on completion of life or work required due to change in law, or deferred execution of work
included in original scope or efficiency improvement or such works
of value more than Rs. 1Crore which may be expedient for safe operation of the system.
(a) The capital investment plan shall show separately, on-going
projects that will spill over into the Control Period, and new projects (along with justification) that will commence in the
Control Period but may be completed within or beyond the
Control Period. The capital investment plan shall contain the
scheme details, justification for the work, capitalization schedule, capital structure and cost benefit analysis (where
applicable)....”
5. Accordingly, CSPDCL submitted the instant petition for approval of its
Capital Investment Plan for the control period FY2013-14 to FY 2015-16
on dated 07.12.2012. After due verification, it was registered on
11.12.2012 as petition No 54 of 2012(M).
6. A Technical Validation Session (TVS) on the petition was held on
29.12.2012 in the office of Commission. During the validation session,
the utility was asked to submit clarifications / additional information for
prudent analysis of the proposals mentioned in the petition.
7. During scrutiny certain additional information was felt necessary, the
utility was directed to submit such details and the same have been
taken on record. The Capitalization schedules for each of the scheme
has been estimated based on the status report filed by the utility and
additional information received during TVS.
8. The utility was directed to publish gist of its proposals in the news
papers in the form of a public notice inviting suggestions and objections
on the same. The petition was uploaded on the website of the
Commission and also on the website of the company and made it public.
21 days time was granted for submission of e comments/ suggestions/
objections on the petition.
9. A notice for hearing scheduled on 26.02.2013, in the office of
Commission, was published separately on 19.02.2012 in Navbharat
Bilaspur, Central Chronicle Raipur and Hari-Bhoomi Raipur.
10. Neither any comment from any stakeholder was not received nor was
any objection presented in the hearing.
11. On 5th March 2013, a meeting of State Advisory Committee was
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 3 of 22
convened and a presentation on the Capital Investment Plan filed by
CSPDCL was organized for the stakeholder.
12. Based on the available data and information, the Commission is issuing
this order and approving in-principal the Capital Investment Plan
proposed by the utility with respect to capital expenditure plans to the
extent and as per observations/ directives mentioned in attached
documents.
13. The scheme proposed by the utility can mainly be bifurcated in two
broad category i.e. Govt. Funded scheme and partly / fully CSPDCL
funded schemes.
14. The Govt. funded schemes includes 6 different schemes out of which
four are only State Govt. funded schemes and two are mainly funded by
the Central Govt. with counter funding from State Govt.
15. The fully State Govt. funded schemes are Electrification of Govt. schools
and hospitals, Agricultural pump energization and RE works other then
RGGVY, Mukhyamantri Shahri Vidyutikaran Yojna and other
developmental works funded through Backward Region Growth Fund,
Integrated Action Plan and Pradhikarans (namely Bastar Vikas
Pradhikaran, Surguja Vikas Pradhikaran and Anusuchit jati Vikas
Pradhikaran). The aggregate proposal for the above 4 schemes for the
control period is Rs. 981 Cr. As these schemes are proposed to be fully
funded by way of grant from the State Govt. without any implication on
account of return on equity, interest on loan and depreciation, we do
not intend to deliberate on the schemes in detail. However, it is made
clear that this will not absolve utility from exercising all round prudence
at its own end and bring to the knowledge of the State Govt. (Energy
Department as well as the Finance Department) all the implications of
the schemes. In this context, specific reference is invited to the letter of
the Principal Secretary, Finance, Govt. of Chhattisgarh dated
17.02.2012 addressed to the Secretary Energy, Govt. of Chhattisgarh
with a copy to the Secretary, CSERC, wherein it was desired that if any
capital investment proposed to be made by Power Companies through
grant from Govt. of Chhattisgarh then such proposal shall be submitted
to the Commission only after approval of the State Govt. CSPDCL was
asked to confirm the funding from the State Govt. No specific
confirmation for the plan period has been received, however, CSPDCL
vide its submitted dated 07.03.2013 has confirmed that the actual
execution shall be limited to the grants received from the State Govt.
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 4 of 22
Further, a copy of the petition was also forwarded to the Govt. of
Chhattisgarh (Finance Department as well as Energy Department) on
13.02.2013; however, no comments have been received from either of
the departments.
In light of the above, we refrain from scrutiny of the schemes
and leave it to the utility to take up these schemes with the State Govt.
Even at the risk of repetition, we reiterate that any asset created under
these schemes shall not qualify for consideration in GFA (to the extent it
relates to regulatory accounts) and no consequential impact on the
financial cost component shall lie in the tariff.
16. Out of the other two Govt. funded schemes, the first one is Rajiv Gandhi
Grameen Vidyutikaran Yojna (RGGVY). The scheme was introduced by
the Govt. of India in April, 2005. As per this scheme, all the villages/
hamlets have to be electrified and electricity access has to be given to
rural households, including free of cost connections to the BPL families.
CSPDCL has submitted that under this scheme, 90% of the project cost
is released as advance, which is convertible into grant after fulfilment of
certain mandatory conditions, whereas the balance 10% amount is
given by the respective State Government.
CSPDCL has further submitted that the RGGVY has preset conditions for
implementation which are enumerated below;
(a) Preparation of district wise detailed project reports for execution on
turn-key basis.
(b) Involvement of central public sector undertaking of power ministry
in implementation of some project.
(c) Certification of electrified village by the concerned Gram
Panchayat.
(d) Deployment of franchisee for the management of rural distribution
for better consumer service and reduction in loss.
(e) Undertaking by State for supply of electricity with minimum daily
supply of 6 to 8 hours of electricity in the RGGVY network.
(f) Making provision of requisite revenue subsidy by the State.
(g) Determination of Bulk Supply Tariff (BST) for franchisee in a
manner that ensure commercial viability.
As per CSPDCL submission, in Chhattisgarh, RGGVY is applicable in all
the 27 districts, thereby covering all the villages in the state. It however
excludes those villages which are already been electrified using solar
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 5 of 22
power or the villages that fall within forest area. Under RGGVY, the GOI
has sanctioned funds totalling Rs 1336 crore for various projects across
the state of Chhattisgarh. Of the sanctioned amount, nearly Rs 679
crore was spent until 31.08.2012, of which Rs 417 crore was spent
during the control period FY11-FY13.
In the instant plan CSPDCL has proposed to incur an expenditure
of Rs. 600 crores during FY 2013-14 to FY 2015-16. The scheme wise
investment plan as submitted by CSPDCL is reproduced below:-
Sl. No. Particulars 2013-14 2014-15 2015-16
Target PHY FIN PHY FIN PHY FIN
1 UE & DE Villages 255 - 192 - 192 -
2 Villages for intensive
electrification 104 - 77 - 77 -
3 33 KV line (Km.) 131.2 4.9 98.4 3.6 98.4 3.6
4
33/11 KV S/s
i) New (Nos.) 2 2.5 1 1.3 1 1.3
ii) Addl. (Nos.) 2 1.5 1 0.8 1 0.8
iii) Aug. (Nos.) - - - - - -
5 11 KV line (Km.) 3,680.2 65.5 2,760.2 49.1 2,760.2 49.1
6
Single Phase
Distribution
Transformer 2,496 20.0 1,871 15.0 1,871 15.0
7
Three Phase
Distribution
Transformer 216 3.7 162 2.7 162 2.7
8 LT Line (Km.) 2,486.8 67.9 1,865.1 50.9 1,865.1 50.9
9 Service connections
(BPL) 89,724 19.7 67,294 14.8 67,294 14.8
10 Other schemes
(under preparation) 64.4 - 61.8 - 11.8
Total 250.0 200.0 150.0
Being a Govt. funded scheme with the aim of socio-economic
development of the rural areas, we do not intent to deliberate on the
ratio or nitty-gritty of the schemes. However, as stated in the earlier
para and previous orders too, it is made amply clear that responsibility
of fulfillment of mandatory conditions for conversion of advance (loan
from REC) into grant lies wholly and squarely on CSPDCL and in no case
loading on ARR / tariff shall be allowed on capitalization of the aforesaid
expenditure. We also direct CSPDCL to bring the conditionality attached
to the scheme, to the notice of Govt. of Chhattisgarh so that at a later
date complications may not be faced. Further, without entering into
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 6 of 22
details we have some prima-facie observations on the plan submitted
by CSPDCL. We advise the utility to revisit the plan in light of these
observations:-
(a) The proposed plan includes proposals of Rs. 138 crores (64.4 Cr.
for FY 13-14, Rs. 61.8 Cr. For FY 14-15 and Rs. 11.8 Cr. For FY 15-
16) under the head “Other Schemes (under preparation)”. We fail
to understand that how the schemes which are still under
preparation can be included in a capital plan. It is a settled
principle that to qualify as a capital expenditure, the work has to be
clearly indentified after ascertaining the feasibility and execution
plan. In our opinion, the sub head may not qualify for consideration
in the plan.
(b) As per the performance report the amount spent in the previous
control period was Rs. 416.6 crores, in comparison to the same the
target for the instant control period appears to be quite ambitious.
Further, the phasing also indicates much higher level of target in
the first year of control period (Rs. 250 crores) than the last year
of the control period (Rs. 150 crores). We observe that normally
execution in the later years is faster than the initial years.
Accordingly, CSPDCL may review the plan and targets for FY 2013-
14 and FY 2015-16 may be swapped.
CSPDCL is also directed to bring the above observations to the notice of
the State Govt.
17. The other Govt. funded scheme is Re-structured Accelerated Power
Development and Reform Programme (R-APDRP). The Government of
India approved the R-APDRP during XI Plan as a central sector scheme.
The key objective of this scheme is stated to expedite the reform
process in the distribution segment. The objectives are as follows:
� Improving financial viability of state power utilities
� Reduction of AT & C losses
� Improving customer satisfaction
� Increasing reliability and quality of power supply
CSPDCL has submitted that R-APDRP is being implemented under the
aegis of Ministry of Power (MoP), Government of India. The program
focuses on establishment of reliable and automated system for
sustained collection of accurate base line data, adoption of IT in the
area of energy accounting and reduction of AT&C loss. All the 22
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 7 of 22
towns/cities of Chhattisgarh, with population more than 30,000 (as per
census 2001), have been covered under this scheme.
The scheme has two components, one is part-A for establishing
information technology based energy accounting and audit system
leading to verifiable base-line AT&C loss levels in the project areas and
the other is part-B for investments in strengthening of the distribution
network leading to reduction in loss levels.
18. For part-A of the scheme, 100% of the project cost is provided as
normal loan from the government on which interest is payable.
Subsequently 100% of the loan amount of Part A as well as the interest
amount can be converted into grant on completion of the project. The
maximum period for completion of works under this Part has been fixed
as 3 years from the date of sanction of DPR or 18 months from the date
of issue of LOI for appointment of ITIA/SIA, whichever is earlier.
Under Part–A following activities have been proposed by CSPDCL:-
i. Establishment of enabling IT Infrastructure to establish base
line data and verify AT&C loss figures of all the 22 towns for
which 20 DPRs have been prepared/ sanctioned
ii. Installation of Supervisory Control and Data Acquisition /
Distribution Management System (SCADA/DMS) applicable for
the towns having population more than 4 lakh and annual input
energy more than 350MU. For this work, 2 towns namely Raipur
and Durg-Bhilai-Charoda complex have been selected and the
DPRs prepared and sanctioned.
CSPDCL has informed that the time limit of 3 years for execution of
project for conversion of loan into grant has expired on 03.09.2012. It
has also submitted copies of its representations and correspondence
done by the State Govt. with Ministry of Power, Govt. of India regarding
request for extension of time period for implementation of Part-A
activities.
We note that these project reports were prepared by CSPDCL and
vetted by the State Govt. and the Central Govt. The Commission has
made it clear at time and again that even if the loan from the Govt. is
not converted into grant for any reason whatsoever, the investment
shall not qualify for consideration in the ARR / Tariff determination
process. It may be in the utility’s own interest to ensure proper
pursuance and to make it clear to the State Govt. that if the eventuality
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 8 of 22
of non conversion of loan into grant arises then the State Govt. support
will be needed to meet the liability of loan repayment.
The R-APDRP part-A plan is indicated to have two components - SCADA
and IT Project (details not submitted by CSPDCL). At this juncture, we
wish to advise that implementation of SCADA in the two cities namely
Raipur and Durg-Bhilai-Charoda complex is very ambitious plan which
needs to be reviewed looking to the practical constraints. It is true that
funding is to be provided by the Central / State Govt. and there may
not be any direct loading on the consumers per se. However, it is only
one side of the coin. We observe that the SCADA has two components -
one is Supervisory Control and other is Data Acquisition System (DAS).
Implementation of DAS may be needed for monitoring purposes and
may not call for big investment on the system side as well as
infrastructure side, however, implementation of Supervisory Control
involve a very high cost of the system automation which may be much
higher than the cost of SCADA itself. One need not to be an expert of
rocket science to appreciate that to implement supervisory control all
the 33/11 kV S/s in the two towns will have to be completely
refurbished. All isolators will have to be replaced by new motorized
isolators and many of the panels/equipments would have to be
replaced. Further, it is a material fact that as on this date none of the
switch yard of any of the power station of CSPGCL or EHT S/s of
CSPTCL is operating through supervisory control system. Also SCADA is
installed in the SLDC, since so many years, however, the operational
execution of the supervisory control system could not be implemented
till date. Under such a situation implementation of supervisory control
system in 33/11 KV S/s and maintenance of the same on a long run
seems to be a remote feasibility. Further, it is ironical that in the instant
plan nothing has been mention regarding the expenditure which will be
needed for renovation of the 33/11 KV S/s in the two cities. Obviously
such renovation will not get support from the Central Govt. under R-
APDRP scheme and the cost will lie on the consumer without any
significant return from such investment. Even on the IT front, where it
is stated that the complete cost is met by Govt. funding, we have
noticed that investment on civil works has been shown for installation of
SCADA system which is proposed to be financed through debt & equity,
for which a claim may arise to qualify for ROE, interest and depreciation
in the tariff computation.
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 9 of 22
In light of the above observations and looking to the fact that ultimately
it is public money which is going to be put on stake, we are constrained
to direct CSPDCL that if possible the plan may be reviewed and DAS
may be considered instead of SCADA. It is also directed that the views
of the Commission shall also be brought to the knowledge of State
Govt. which is the prime stakeholder and sole shareholder of the utility.
19. Part-B of R-APDRP is intended for improvement, strengthening and
augmentation of the distribution network system to reduce AT & C loss
up to 15%. 19 DPRs of 21 towns of Chhattisgarh State are stated to
have been sanctioned by MoP/GoI. The maximum period for completion
of works under this part has been fixed as 5 years from the date of
sanction of the project DPR. 25% for the Part-B projects shall be
provided as normal loan by the government on which interest is
payable. 50% of project cost and interest can be converted in to grant
on achieving the target of 15% loss on a sustained basis for 5 years in
the project area.
On the funding part, CSPDCL has informed that GOI vide two separate
letters, sent in July 2011 and February 2012, approved a total amount
of Rs 710 crore, covering 16 towns in the state of Chhattisgarh. A
corresponding loan amount of Rs 177 crore, at the rate of 25% of the
project cost, was also sanctioned by GOI. Momentum on the
implementation of R-APDRP projects is stated to have gathered pace in
the current financial year.
Following the ratio adopted in the previous paras, we do not intend to
interfere in the Govt. funded schemes, however, there are few
observations which we wish to put on record in the wider public
interest:
� From the performance review, it appears that the previous control
period target was Rs. 135 crores, the project was sanctioned to the
tune of Rs. 710 crores and the loan of Rs. 177.6 crores was also
sanctioned yet the amount spent in the control period FY 11-13 (up
to 31.08.2012) was only Rs. 0.7 crore. As the scheme is stated to
be focused on reduction of AT&C loss up to 15%, it is imperative
that faster implementation may be in the wider interest of the
utility and community both. The target proposed for the control
period is Rs. 596.6 crores (Rs. 365.4 Crs. for FY 13-14 Rs. 131.1
Cr. For FY 14-15 and Rs. 100 Crs. For FY 15-16). Utility would do
well if the schemes are prioritized and monitored closely to achieve
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 10 of 22
the targeted loss reduction. The balance costing (50%) will qualify
for consideration in tariff only when the desired reduction in loss is
achieved.
� On the funding part, it is noted that CSPDCL has to fund 75% of
the project cost. It has proposed to fund this portion through mix
of debt & equity. Debt is indicated to be 95% of such cost. Thus,
effectively only 3.75% of the total project cost shall be funded
through equity. We are of the opinion that high debt may pose
considerable financial strain in the long run due to high DSCR.
Utility may review the funding option.
Utility may take appropriate action in the above context.
20. After the aforesaid discussion on the Govt. funded schemes, now we
turn to the partly or fully CSPDCL funded schemes. These schemes are
broadly categorized in five categories i.e. ST(N) scheme, ND scheme,
loss reduction scheme, proposal for EITC and proposal for civil works.
The combined proposal for all these schemes is Rs. 2608.3 crores.
Before proceeding for scheme wise deliberation, we deem fit to review
the achievements in the last three years vis-a-vis the plan for the next
three years.
Particulars Three years 01/04/08 to
31/03/11
Three Years 01/04/09 to
31/03/12
Three Years 01/04/10 to
31/03/13 (Estimated)
Three Years 01/04/13 to
31/03/16 (Proposal)
Addition in 33 KV Line (KM) 2317 1859 1568 4877
Addition in 11 KV Line (KM) 12317 11657 8392 21058
Addition in LT Line (KM) 27336 24226 17226 14712
Addition in Distribution Transformers (No)
17602 15589 10728 29923
The above table clearly indicates that the physical targets for the plan
period are on a higher side then what has been achieved in the
comparable period for the last three years. It is worthwhile to note that
the above comparison do not include the capital work on loss reduction
programme which is proposed to be taken on a very ambitious scale in
the instant control period. We have also gone through the status report
filed by the utility which compares the achievement in financial terms
for the last control period. The total capital expenditure under all the
schemes put together in the control period FY 11-13 was Rs. 1364.4
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 11 of 22
crores (up to 31.08.2012). The CAPEX plan for the next three years (FY
2013-14 to FY 2015-16) is Rs. 4879.9 crores.
Clearly the proposed plan is not only too ambitious but appears to
outstretch the physical and financial limits of implementation. It is in
this perspective that the schemes have been reviewed and the plan has
been revised to fit into the canvas of feasibility and practicability.
21. Sub Transmission and System Improvement Scheme (ST&SI): It
is stated that addition of new substations is required to cater to the
increasing demand in the state to ensure quality of supply and reduction
of losses. For the last control period, the target approved by the
Commission was of Rs. 240 Crores. Against the same, achievement up
to 31.08.2012 was Rs. 152.3 crores. The utility has attributed the
underperformance to operational challenges it is facing in executing
some of these projects. In physical terms, CSPDCL expressed hope that
by the end of control period it shall be able to complete 129 numbers
33/11 KV S/s. Now for the instant control period, it has set a target of
196 S/s and a total capital expenditure of Rs. 484 crores. No
explanation has been given for the whooping rise in the projected plan
expenditure (more than 3 times of the expenditure up to 31.08.2013).
Cost per S/s also appears to be very high in comparison to the previous
plan.
Looking to the proposed investment in loss reduction scheme,
particularly HVDS scheme in the rural area and R-APDRP part-B in the
urban area, we expect that there should be substantial savings in the
technical losses in the system which in turn will provides some relief in
the requirement for additional investment towards system stability. We
accordingly approve capital expenditure of Rs. 180 crores financial for
the instant control period. The year wise expenditure to be considered is
Rs. 55 crores, Rs. 60 crores, Rs. 65 crores for FY 13-14, FY 14-15 and
FY 15-16 respectively. On the physical front, utility in the additional
submission had submitted list of 67, 65 and 64 numbers S/s which are
proposed for FY 13-14, FY 14-15 and FY 15-16 respectively. However, it
is noted that the list of S/s is circle wise and neither priorities have been
assigned nor any technical parameters have been provided which can
be used for prioritization by the Commission. Therefore, we refrain from
deciding the list of S/s which can be taken up during each year of
control period. The utility is directed to prepare the priority list which
shall be submitted to the Commission at the earliest and in no case
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 12 of 22
later than 30th June, 2013. We also note that the funding has been
indicated at debt equity mix of 90:10, the same may be revisited for the
reasons stated earlier in the order.
22. Normal Development scheme (ND): It is stated that the Normal
development scheme predominantly covers the work required for
extending the power supply to the consumers i.e. releasing of
connections. The scheme also encompasses some quality improvement
initiatives such as distribution system strengthening, installation of
distribution transformers and capacitors to provide quality power supply
to the consumers. The expenditure incurred upto 31.08.2012 was
Rs.283.9 crores and the proposed expenditure is Rs. 550 crores. In
physical terms the comparison is as under:-
S. No Particulars
Achievement
in Control
period FY 11-13
Target for
control period
FY 14-16
1 33K.V. Line (K.m.) 481 870
2 33/11KV S/s 8 32
3 11KV Line (K.m.) 1263 1600
4 L.T.Line K.m. 1269 1900
5
Distribution Transformer
i. New (No’s) 3822 5350
ii.Aug. (Nos.) 928 1450
6
Service Connection
I. Single Phase (Nos.) 244755 420000
ii. Three phase (No’s) 28943 53000
iii. H.T. Connection (Nos.) 416 630
iv. St. Light Point (Nos.) 5208 11800
From the above, it is apparent that plan figures are very high and
unrealistic. With high stress on RAPDRP – part B and loss reduction
scheme normal development work at the cost of utility is expected to be
much lower.
CSPDCL in its own submission has indicated that approximately 40% of
the schemes are funded by the consumer contribution. Accordingly, it is
estimated that out of the Rs. 284 crore expenditure incurred on the
above schemes utility might have to fund Rs. 170 crores from its own
sources.
Looking to the above, we are of the opinion that a total expenditure of
Rs. 340 crores (about 20% higher than achievement in previous control
period) may be sufficient for the normal development schemes in the
instant control period. In the aforesaid capital expenditure utility share
is determined as Rs. 200 crores in the control period and the year wise
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 13 of 22
expenditure in the plan is considered as Rs. 60 crore, Rs. 65 crore and
Rs.75 crore for FY 13-14, FY 14-15 and FY 15-16 respectively. However,
there is no restriction for additional work funded through the consumer
contribution.
23. Loss Reduction including HVDS and feeder separation Schemes:
It is stated that loss reduction schemes target reduction in the overall
technical & commercial losses (T&C losses) in the distribution system.
T&C losses can be broken up in two categories: 1) Technical loss and 2)
Commercial loss. CSPDCL plans reduction in the technical losses by
investing in the revamp of LT distribution systems, replacement of
conductors, implementation of HVDS system, etc. At the same time, the
company plans to reduce commercial losses by laying AB Cables in theft
prone areas, setting up pole mounted metering boxes at consumer
premise, installing Automated Meter Reading system, etc.
We appreciate the move towards loss reduction programme, on a long
run basis. This is an investment which is going to benefit the utility and
community both. The reduction of commercial losses will lessen the
burden on the honest consumer and the reduction in technical losses
will not only decrease the power purchase cost but will also assist in
reducing the capital investment needs on the infrastructure
development in the Generation, Transmission and Distribution functions.
On a hind sight, it also implies arresting the carbon foot prints and
environment degradation which has become a major challenge to the
mankind. As per additional submission made by CSPDCL on 08.03.2013
the pilot project on 2 feeders at O&M Division Kawardha has yielded
very good result and the distribution losses which were 57.13% at the
end of year 2009-10 has now come down to 38.78% at the end of
2011-12. We also notice that the HVDS scheme offers significant
opportunity in financial terms as these schemes have shorter payback
period in comparison to the other capital investment opportunity. As
such, they can be easily financed through banks also.
In the last control period the target was Rs. 261.4 crores with Rs. 130
crores for HVDS scheme and balance Rs. 131.4 crores for another loss
reduction schemes. Against the above target, expenditure up to
31.08.2012 was Rs. 5.6 crores on HVDS schemes and Rs. 97.5 crores
on non HVDS schemes. In the instant control period proposal has been
submitted for Rs. 1250 crores (About Rs. 1000 crores for HVDS
schemes and Rs. 250 crores for non HVDS scheme). Regarding the
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 14 of 22
proposal for the instant control period, discrepancy was noted in the
figures quoted in the different tables. Therefore, clarification was sought
from CSPDCL, the utility has submitted the revised figures vide its
additional submission dated 08.03.2013. We have relied on the details
submitted through additional submission. During analysis, we have noted
that the cost benefit analysis submitted for the HVDS scheme suffers from
some infirmity regarding calculation of expected input units after
implementation of the scheme. We have revised the calculations. We also
noted that CSPDCL has relied on computation of payback period by
multiplying the saving in input units with the average cost of supply (taken
as Rs. 4.02 per unit). In our opinion due to reduction in losses the savings
cannot be calculated in terms of average cost of supply. The savings
depend upon the nature of the loss being arrested. In case of reduction in
technical losses, the input unit requirement goes down and in such case
after adjusting for distribution losses at 33 and 11 KV and transmission
losses in the EHT grid, the saving should be computed in terms of
reduction in power purchase cost. On the other hand, in case of reduction
in commercial losses the savings occur in terms of higher sold units
keeping the input unit constant. In such case, additional sold units should
be multiplied with the average billing rate (ABR) of LT consumers to work
out the gain through implementation of the scheme. As the breakup of
technical and commercial losses is not readily available, we have worked
out the savings and corresponding payback from both the perspective for
prioritizing the divisions where this scheme offers higher potential. The list
of divisions with number of feeders and estimated cost, arranged in the
sequence of their tentative payback period is annexed with the order as A-I
& A-II. Based on the data submitted by the utility, and following the saving
in input unit methodology (as adopted by CSPDCL) it appears (from A-I)
that Ambikapur, Bilaspur (O&M) and Champa Division offer the best three
payback period of about one year followed by Raigarh I and Raigarh II with
payback period of about 2 years. Kanker, Pendra Road, Shakti and Mungeli
offer a payback period of 2-3 years and Akaltara, Saraipali, Dhamtari,
Mahasamund and Kawardha offer a payback period of 4 to 5 years.
We are of the view that in the first year i.e. FY 13-14, 73 feeders of the top
three Divisions may be taken up for conversion to HVDS system with a cost
of Rs. 116.07 crores. In the next year, 90 feeders of next two divisions
with a cost of Rs. 143.08 crores may be taken up, followed by conversion
of 146 feeders of next four divisions with a cost of Rs. 232.14 crores. Thus
the total investment on the HVDS in the control period is expected to be
Rs. 491.29 crores. We also approve investment of Rs. 158.71 crores on
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 15 of 22
non HVDS loss reduction schemes (a substantial increase of more than
50% from the achievement till 31.08.2012). Thus the total capital
investment considered for the control period on the loss reduction scheme
stands at Rs. 650 crores. As financing of the normal development works
may not have debt component (due to practical difficulty in preparation of
DPR and bankability of such project), if needed, the debt equity ratio for
the loss reduction schemes may be considered at higher value of 90:10 so
as to ease the equity infusion requirement. The year wise expenditure
considered in the plan period is as under:
Particulars FY 13-14 F5 14-15 FY 15-16 Control Period Total
HVDS Scheme 116.07 143.08 232.14 491.29
Non HVDS Schemes 63.93 56.92 37.86 158.71
Total 180.00 200.00 270.00 650.00
It is further made clear that unlike other schemes, the investment
considered for loss reduction schemes is not the sealing limit, rather it
is minimum desired level. If feasible, utility may take up additional work
too, however, generally pay back priority should be followed.
24. Investment Plan for Energy Info Tech Centre (EITC): CSPDCL has
proposed an investment of Rs. 189 crores on EITC during the control
period. The investment has been categorized in the three major heads
i.e. SAP & hardware (Rs. 48 crores), Network & Security (Rs. 38 crores)
and other IT projects & miscellaneous (Rs. 103 crores).
We have gone through the justification given for each of the scheme
and based on the deliberations and past experience, decide as under:-
24.1 SAP & Hardware
(a) SAP licenses: we appreciate that with the growth of
computerization, additional licenses may be required. However, the
increase in number of licensees is to be planed carefully based on
the “need to know principle” and budgeting should be done in a
progressive manner. Accordingly, we allow capital expenditure of
Rs. 2 crores, Rs 3 crores and Rs. 4 crores in the year FY 13-14, FY
14-15 and FY 15-16 respectively.
(b) SAP Additional modules: Three additional modules namely
Employees Self Services (ESS), Quality Management (QM) and
Sales and Distribution (SD) have been proposed at a total cost of
Rs. 10 crores. However, we note that the benefit of existing
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 16 of 22
modules is yet to be reaped fully. Further the additional modules
are not of urgent nature and may wait for some time. Accordingly,
we direct the proposal to be differed.
(c) SAP Functional Upgradation: It is proposed in name of ensuring
better productivity, ease in supervision, material management,
customer relationship management, upgradation of ERP software
and hardware. Total investment of Rs. 8 crores has been proposed.
After deliberations, we allow CAPEX of Rs. 1 crores, Rs 1 crores and
Rs. 2 crores in the year FY 13-14, FY 14-15 and FY 15-16
respectively.
(d) Hardware Upgradation: CSPDCL has proposed to invest Rs. 18
crores during the control period on hardware upgradation. We
understand that in the IT field upgradation is needed from time to
time, however, the proposal given by the utility is on very high
side. The investment is allowed at Rs. 2 crores, Rs 4 crores and Rs.
4 crores in the year FY 13-14, FY 14-15 and FY 15-16 respectively.
Thus the total investment on SAP & Hardware is allowed at Rs. 24
crores.
24.2 Network & Security
(a) Network & Security augmentation: Need of network security is
well recognized, however, it is noted that with the change in
technology, the augmentation of network security is no more one-
off capital investment. The system augmentation to meet the
challenges posed by the hackers, viruses and other internal &
external threats is now an embedded part of network management.
Thus, such investment is not a capital expenditure rather it is a
routine operation and maintenance expenditure. As such, we are
unable to consider the proposed investment as capital investment,
however, at the same time, we direct the utility that all the steps to
ensure proper security of the network should be taken with due
earnest. If needed, utility may ask for accommodation in the O&M
charges based on the actual expenditure incurred on network
security in the last three years.
(b) IT & Cyber Security: This is proposed as one time investment
and the same is allowed as proposed.
(c) ISO 27001 Compliance & ITIL Framework: Based on the
discussions, the investment on the proposal is now being allowed
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 17 of 22
but differed to the year 2015-16.
(d) DR set-up for existing Systems: The need for data recovery set
up is appreciated, accordingly, we concur with the proposal.
(e) OFC Connectivity in 3 Towns: We don’t find enough force in the
proposal, as such, the proposal is turned down.
(f) IPv6 Deployment: This is stated to be a mandatory requirement
and as such, the same is allowed as proposed.
Thus the total investment on network & security is allowed at Rs.13
crores.
24.3 Other IT Project & Miscellaneous
(a) R-APDRP modules roll-out in non R-APDRP Towns : CSPDCL
has proposed to extend R-APDRP modules to non APDRP towns
also. Such extension will involve GIS mapping and establishment of
base line data. We note that rolling out of RAPDRP modules to non
RAPDRP is not going to yield any worthwhile return. The experience
foretells that even GIS mapping becomes useless if the data is not
updated and maintained frequently. In the present scheme of
things the data gathered from rolling out of such modules may be
worthless by the time implementation becomes due. Utility would
do better to focus on the RAPDRP part itself where it has to achieve
a loss reduction level of 15% in 22 towns. Diversion of resources is
not expected to bring in any commercial benefit to the utility or to
the society. We are of the conscious opinion that a capital
investment should be well focused, targeted and able to bring in
identifiable and measureable benefits. The proposal is turned down
on merits.
(b) Smart Grid Implementation: Smart grid implementation is a
fairly new concept and at present this is being experimented in the
States/Metros which are reeling under severe power shortages.
Chhattisgarh do not fall in this category. We will do better to wait
for the results of experiences at other places and as such, the
scheme is differed.
(c) PCs, Printers & Scanners: It is stated that the procurement of
these equipments for the utility has been consolidated under this
head and no separate capital proposal is being included under any
other scheme. We principally agree with the need for purchase of
new machines, accordingly, we allow provision of Rs. 2 crore for
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 18 of 22
each year of the control period. However, utility is directed to
ensure that in case of replacements, capitalization of such
investment should be accompanied with the decapitalization on the
same account.
(d) System Software & S/w development: CSPDCL submitted that
new system software will be required for running in-house
applications developed for intra-departmental working. The capital
expenditure is allowed @ Rs. 1 Cr/year during the control period.
(e) IT Building along with System Shifting: The need for separate
IT building is agreeable, however, the proposal seems to be on
higher side, as such, an investment of Rs. 5 Cr is allowed during
control period.
The total investment on other IT project is allowed as Rs.14 Cr.
Thus total investment on EITC is approved for Rs. 50 Cr. during the
control period. The year wise break up is tabulated are as under :-
SN DETAILS 2013-14 2014-15 2015-16 Total
1 SAP & Hardware
A SAP License 2 3 4 9
B SAP Additional Modules 0
C SAP Functional Upgradation 1 1 2 4
D Hardware Upgradation 2 4 4 10
Subtotal SAP & Hardware 5 8 10 23
2 Network & Security 0
A Network &Security Upgradation 0 0 0 0
B IT & Cyber Security 1 1
C ISO 27001 Compliance & ITIL Framework 2 2
D DR Setup for Existing Framework 5 5
E OFC Connectivity in 3 Towns 0
F IPv6 Development 5 5
Subtotal Network & Security 1 5 7 13
3 Other IT Project & Miscellaneous
A R-APDRP module roll-out in non R-APDRP Town 0
B Smart Grid Implementation 0
C PCs, Printers & Scanners 2 2 2 6
D System Software & S/w development 1 1 1 3
E IT Building along with System Shifting 1 4 0 5
Sub Total Other IT Project & Miscellaneous 4 7 3 14
EITC Total 10 20 20 50
It is advised that funding arrangement may be revisited at debt equity
ratio of 80:20, as the mix proposed in plan seems highly optimistic.
25. Investment Plan for Civil Construction Work: CSPDCL has
proposed investment in civil construction work for- zone office building
(New / Renovation old building), control rooms in S/s of SCADA
building, Residential quarters for employees, Lineman Training Centre,
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 19 of 22
Executive Hostel, Central Training Institute, Distribution Centre building,
Control Room building at 33/11 KV Substation, Administrative Office
building for EDs/CEs for Raipur & Durg, Cement Concrete road /
Culverts / Drains in the S/s, Welfare Centre building, Customers Care
Centre, Hospital building and Area Stores shed, Area fencing / boundary
wall, etc. Total investment of Rs. 135 crores is projected during the
control period. It is stated that loan shall be arranged from M/s HUDCO
at a debt equity mix of 80:20.
We have gone through the proposal. In the main petition list of works to
be taken was not provided. On query, CSPDCL has submitted the same
in its additional submission. However, it is noted that priority of the
works has not been mentioned and variety of works ranging from
erection of chain link mash, boundary wall, culverts, mooram road
control room for panels, offices for JE/AE/EE at zone/division offices /
sub stations have been mentioned in bulk. It is also noted that in
previous business plan no such approval was sought. As per normal
practice the works related to boundary wall, fencing, culvert, road, etc.
should be part of the estimate for the building / substation itself.
Normally they are envisaged as a separate asset, however, from the
submissions made it appear that in some cases, particularly the old
substations, there are cases where such works were not executed and
as such they pose severe problem in efficient and smooth O&M.
As such, we agree for completion of such works. These works along with
renovation of Control rooms (including upgradation of control rooms for
installation of R-APDRP panels) and fencing may be taken up on the first
priority. Scheme also includes proposals for construction of residential
quarters for the employees. We also agree with the proposal for
Executive Hostel and Training Centre. Instead of erection of new
lineman training centre, the centre at Gudihari can be renovated. Need
based renovation of O&M offices, where required.
We are of the view that except for remote places, where arranging
accommodation is extremely difficult, construction of quarters by the
utility is not an attractive option. From the employee point of view also
it results in additional tax liability on deemed income.
We have also noted that a proposal has been submitted regarding
extension of EITC building, but EITC has proposed a new building for
integration of its functions. Thus the proposal from civil department is
duplication in contradiction
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 20 of 22
In view of the above, we are pruning up the capital expenditure for civil
works during the control period to Rs. 36 crore for the control period.
The investment is allowed at Rs. 10 crores, Rs 12 crores and Rs. 14
crores in the year FY 13-14, FY 14-15 and FY 15-16 respectively.
In absence of marked priority, we refrain from deciding the list of
schemes. CSPDCL should prioritize the works itself and submit the list of
works to be taken up during each year of control period as per CAPEX
allowed by 30th June 2013.
26. Capitalization plan :
In an ideal condition the capitalization for any scheme is considered in
the year in which the last trench of capital investment is made.
However, the capital investments estimated sometimes fail to fructify in
time for various reasons, as such, looking to the past trend, we are
inclined to consider 70% of the ideal value for consideration in the ARR
/ tariff computation on front end basis. The same shall be revisited and
adjusted as per actual at the time of trueup. The summary of the year
wise capital expenses and capitalization considered for ARR is tabulated
here as under:-
Particulars 2013-14 2014-15 2015-16 Total
ST (N) Schemes 55 60 65 180
ND Scheme (CSPDCL Share) 60 65 75 200
Loss Reduction Scheme 180 200 270 650
EITC SAP & IT Project 10 20 20 50
Civil Works 10 12 14 36
Total Capex (CSPDCL) 315 357 444 1116
Capitalization @ 70% of Capex 221 250 311 781
The actual capitalization shall be accounted and adjusted at the time of
true up when realistic values will be available. We are of the view that
except for the schemes allowed by Commission normally no expense
may qualify for additional capitalization at the time of tariff
determination / true up. For works approved in the previous orders, it is
noted that at the time of ARR / Tariff estimation, capitalisation of such
schemes was considered, now the same shall be revisited during the
true up. For the purpose of ARR, subject to appropriate check, GFA as in
provisional accounts for FY 2011-12 shall be considered. Such check
may include (but not limited to) scheme-wise comparison of actual
capitalisation vis-a-vis the approved plan. Additional capitalisation for
FY 2012-13 shall be revisited as per status considered in this order.
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 21 of 22
However, on receipt of any new information the extent of loading of
capitalization in ARR / Tariff determination may be reviewed
appropriately.
We feel it imperative to stress that on completion of the schemes, at
the time of true up of ARR of respective years, CSPDCL shall be under
obligation to provide, details of actual expenses incurred and capitalized
on each of scheme. It must be understood, loud and clear, that If the
utility fails to provide such details at the time of true up, the additional
GFA to such extent, may not qualify for consideration in computation of
ARR and tariff and the cost and consequences shall rest wholly and
squarely on the utility itself.
27. General observations:
27.1 As stated in the previous orders and provided in the regulations too,
we reiterate, that in case of emergency situations, causing threat to
life and property, work may be taken up by the utility on its own.
However, in such cases the petition for expost facto approval should
be submitted at the first available opportunity with due justification.
The Commission, subject to its satisfaction with exigency stated and
prudent scrutiny of cost, may accord approval for such additional
capitalization.
27.2 Further, it may be noted that the authorities can not be allowed to
take shelter of regulatory process to run away from their functional
responsibility. It must be understood loud and clear that the
responsibility of detailed budgeting, financial planning and
administrative/technical approval of various proposals rests unfettered
on the management of the utility. The tariff order or business plan
order should not be construed or projected as a substitute for detail
financial budgeting or planning.
27.3 Last but not the least, the approval of the schemes does not imply that
Commission has given any blanket approval for capitalization of such
expenses. It must be borne by all and one, that all the approvals
granted by the Commission are only in-principle approvals and such
approval / concurrence by the Commission does not in any way
absolve or dilute the responsibility and liability of the competent
authorities to adhere to prudence check on technical requirement and
detailed specifications. Similarly canons of financial propriety shall
have to be applied with undiminished force and vigor. Regulatory
process only ensures test on some broad parameters. Executive
Capital Investment Plan Order (for CSPDCL) FY 2013-14 to FY 2015-16
CSERC Page 22 of 22
authorities must do their duty of exercising prudence check, un-
trembled by the consideration that such costs or proposals have
passed the test of regulatory scrutiny. If at any point of time,
Commission comes to know about any irregularity, then such costs
shall not be considered for capitalization ‘ab-initio’.
28. Commission's Directives
28.1 For government funded schemes, it shall be the responsibility of the
utility to coordinate with the government and execution should be in
accordance to the funding.
28.2 Priority of implementation of the schemes and their completion should
be decided by CSPDCL. For taking up work under different schemes
criterion should be laid out for deciding the priority.
28.3 Effort should be made by CSPDCL for completion of all the schemes
within scheduled period. Specific attention should be paid to the loss
reduction schemes. They will prove to be life line of the distribution
utility in the long run. Circle wise progress of such schemes and the
benefits derived should be submitted to the Commission quarterly.
Other directives such as study of load on existing system and load growth,
prioritization of schemes, swapping of high cost loans, creation and
maintenance of asset register etc. contained in the previous orders, unless
superseded, shall remain in force.
Sd/-
(Vinod Shrivastav) Member
Sd/-
(Manoj Dey) Chairman
Expected Input
(LU)
Saving in Input
(LU)Saving in Cr Rs
Pay back
Period (Yr)
Ambikapur 18 28.62 7,036 3057 56.55% 46.00% 5661 1,375 35 1
Bilaspur (O&M) 36 57.24 6,161 3010 51.14% 34.00% 4561 1,600 40 1
Champa 19 30.21 3,293 1226 62.77% 50.00% 2452 841 21 1
Raigarh I 22 34.98 6,345 4157.1 34.48% 24.00% 5470 875 22 2
Raigarh-II 68 108.1 5,519 2,039 63.10% 43.10% 3583 1,936 49 2
Kanker 22 34.98 2,877 1448.27 49.65% 38.00% 2336 541 14 3
Pendra Road 14 22.26 2,126 1198 43.65% 34.00% 1815 311 8 3
Sakti 60 95.4 3,768 1,420 62.30% 42.30% 2461 1,307 33 3
Mungali 50 79.5 3,513 1,854 47.20% 28.20% 2582 931 24 3
Akaltara 28 68.3 1,893 694 63.40% 38.40% 1127 766 19 4
Saraipali 62 98.4 4,673 2,389 48.87% 25.25% 3197 1,477 37 3
Dhamtari 18 28.6 4,871 3,917 19.60% 15.00% 4608 263 7 4
Mahasamund 65 103.4 4,308 2,890 32.90% 17.00% 3482 826 21 5
Kawardha 77 99.5 3,905 2,401 38.50% 23.00% 3118 787 20 5
Khairagarh 20 31.8 1,221 822 32.70% 20.70% 1037 184 5 7
Raipur(O&M) 65 103.4 5,362 3,997 25.50% 17.00% 4816 546 14 7
Feeders Yrly Invest. Cum. Invest. Yrly Gain Cum. Gain Eff. Power Purchase Rate 2.5
First Year 73 116 116 95 47.58
Second Year 90 143 259 30 157.52
Third Year 146 232 491 55 309.88 1st Year 2nd Yr 3rd Yr
Total 309 491 41% 61% 63%
Recovery of Investment
HVDS cost benefit analysis - Savings on Input Unit (Reduction in Technical losses only)
DivisionHVDS Feeder
Prov. (No.)
Est. cost (Rs
Cr.)
Input units
(LU)Units Solf (LU)
Loss
2011-12
%
Expected loss
after HVDS
%
CSPDCL CIP ORDER 2013- ANNEXURE -I
Calaculated Pay Back
Page 1 of 2
Expct. Sold
Units (LU)Addl Sales (LU)
Gains
(Cr Rs)
Pay back
Period (Yrs)
Ambikapur 18 28.62 7,036 3057 56.55% 46.00% 3799 742 22 1
Raigarh I 22 34.98 6,345 4157.1 34.48% 24.00% 4822 665 19 2
Bilaspur (O&M) 36 57.24 6,161 3010 51.14% 34.00% 4066 1,056 31 2
Champa 19 30.21 3,293 1226 62.77% 50.00% 1647 421 12 2
Saraipali 62 98.4 4,673 2,389 48.87% 25.25% 3493 1,104 32 3
Raigarh-II 68 108.1 5,519 2,039 63.10% 43.10% 3140 1,101 32 3
Kanker 22 34.98 2,877 1448.27 49.65% 38.00% 1783 335 10 4
Pendra Road 14 22.26 2,126 1198 43.65% 34.00% 1403 205 6 4
Mungali 50 79.5 3,513 1,854 47.20% 28.20% 2522 668 19 4
Sakti 60 95.4 3,768 1,420 62.30% 42.30% 2174 754 22 4
Dhamtari 18 28.6 4,871 3,917 19.60% 15.00% 4140 223 6 4
Akaltara 28 68.3 1,893 694 63.40% 38.40% 1166 472 14 5
Mahasamund 65 103.4 4,308 2,890 32.90% 17.00% 3576 686 20 5
Kawardha 77 99.5 3,905 2,401 38.50% 23.00% 3007 606 18 6
Khairagarh 20 31.8 1,221 822 32.70% 20.70% 968 146 4 7
Raipur(O&M) 65 103.4 5,362 3,997 25.50% 17.00% 4450 453 13 8
Plan Feeders Yrly Invest. Cum. Invest. Yrly Gain Cum. Gain 2.900
First Year 76 121 121 71 36
Second Year 81 129 249 44 129
Third Year 154 245 494 67 278 1st Year 2nd Yr 3rd Yr
Total 311 494 30% 52% 56%
HVDS cost benefit analysis - Gains though Addl. Sales (Reduction in Commercial losses only)
DivisionHVDS Feeder
Prov. (No.)
Est. cost
(Rs Cr.)
Input units
(LU)Units Solf (LU)
Loss
2011-12
%
Expected loss
after HVDS
%
Recovery of Investment
Calaculated Pay Back
ABR (LT)
CSPDCL CIP ORDER 2013- ANNEXURE -II
Page 2 of 2