che 308 - chemical process analysis sessional. a hydrogen peroxide plant is to be set-up at...
TRANSCRIPT
![Page 1: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/1.jpg)
WELCOME
ChE 308 - Chemical Process Analysis Sessional
![Page 2: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/2.jpg)
HYSYS SIMULATION PROJECT
100 MTPD HYDROGEN PEROXIDE (50%) PLANT
![Page 3: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/3.jpg)
A hydrogen peroxide plant is to be set-up at
Gazaria, Munshiganj having a capacity of
100 metric ton of hydrogen per oxide (50 %
w/w) per stream day, corresponding to
33,000 metric ton of hydrogen peroxide(50%
w/w) per year, including all off sites,
auxiliaries, utilities and supporting facilities
using natural gas as feedstock and fuel.
DEFINITION OF THE PLANT
![Page 4: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/4.jpg)
NG from TITAS Gas◦ Methane > 96 % (V/V)◦ Calorific Value > 1000 Btu◦ Pressure > 240 kPa◦ Temperature about 5-15 oC
Air Water
SPECIFICATION OF RAW MATERIALS
![Page 5: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/5.jpg)
![Page 6: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/6.jpg)
H2O2 specification:
H2O2 content 50% Free acid (as H2SO4) 0.040% max. Non-volatile matter 0.080% max. Stability 97.0% min. Freezing point -52.2°C Boiling point 113.8°C Density 1191 kg/m3
SPECIFICATION OF PRODUCT
![Page 7: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/7.jpg)
By Auto-oxidation of alkylanthraquinones By Electrolysis from Ammonium Bisulfate. From Barium Peroxide By oxidization of isopropanol
Auto-oxidation of 2-ethylalkylanthraquinone is selected for this project.
PROCESS SELECTION
![Page 8: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/8.jpg)
Geological Data
Location
The site for the plant is selected on the bank of river Meghna at Baluakandi under Gazaria upzilla in Munshiganj district.
Load bearing capacity: The soil has a bearing capacity of 0.38 ton/ft2
required piling is used. Corrosive tendency: Non Corrosive
DESIGN BASIS
![Page 9: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/9.jpg)
Climatic condition
Dry bulb temperature (maximum) 35 oC (summer) Dry bulb temperature (maximum) 26 oC (winter)
Wet bulb temperature (maximum) 29 oC (summer) Wet bulb temperature (maximum) 22 oC (winter)
DESIGN BASIS (Contd.)
![Page 10: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/10.jpg)
Meteorological condition
Average monthly Temperature 35oC (max.) Average Temperature 30oC Average annual rainfall 2850 mm Wind flow
Direction = South to NorthVelocity = 52 mile/h
DESIGN BASIS (Contd.)
![Page 11: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/11.jpg)
Utility Electric Power
◦ Voltage 380/220 V◦ Frequency 50 Hz◦ Phase 3 phases
Cooling Water Inlet Outlet
Temperature < 30 oC 38 oCPressure 0.5 MPa 0.2 MPaTurbidity ≤ 50 mg/lChlorine < 5 ppm
PH 6.5 – 8
DESIGN BASIS (Contd.)
![Page 12: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/12.jpg)
Four main stages involved:
1. Hydrogen Generation ( Reformer)
2. Hydrogenation
3. Oxidation
4. Extraction and Purification
PROCESS INVOLVED
![Page 13: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/13.jpg)
A. Reformer: CH4+H2O = CO+3H2 - Q
CO + H2O = CO2+H2 + Q
B. Hydrogenation And Oxidation tower:
REACTIONS INVOLVED
![Page 14: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/14.jpg)
PROCESS BLOCK DIAGRAM
REFORMERREFORMERPRESSURE
SWINGADSORBER
PRESSURE SWING
ADSORBERHYDROGENATION
TOWER
HYDROGENATION TOWER
OXYDATIONTOWER
OXYDATIONTOWER
EXTRACTIONTOWER
EXTRACTIONTOWER
SEPARATORSEPARATOR
DSVDSV
PURIFICATIONTOWER
PURIFICATIONTOWER
H2O2
STORAGETANK
H2O2
STORAGETANK
Tail Gas
SEPARATOR
SEPARATOR
NG
Steam Tall Gas
Water
WSMake
Up
DRYING TOWER
Air
Tail Gas
Water
WS STORAGE
TANK
![Page 15: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/15.jpg)
PROCESS FLOW DIAGRAM
![Page 16: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/16.jpg)
![Page 17: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/17.jpg)
![Page 18: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/18.jpg)
Natural Gas Knock Out Drum Feed Gas Compressor Desulfurization Vessel Desulfurization Vessel Water Tank BFW Pump Stack Heat Exchanger Waste Heat Boiler Reformed Gas Cooler Raw Gas Separator Pressure Swing Adsorber Induced Draft Fan Reformer
EQUIPMENT LIST
![Page 19: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/19.jpg)
Static Mixer Hydrogenation Tower Working Solution Pump Working Solution Storage Tank Hydrogenated Solution Storage Tank Hydrogenated Solution Pump Hydrogenated Solution Cooler Air Compressor Oxidation Tower Oxidation Solution Separator Tail Gas Condenser Oxidation Solution Cooler Wet Gas Separator
EQUIPMENT LIST (Contd.)
![Page 20: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/20.jpg)
Extraction Column Working Solution Separator Recycled Working Solution Pump Extraction Water Pump Recycled Working Solution Heater Purification Column Hydrogen Peroxide Storage Tank
EQUIPMENT LIST (Contd.)
![Page 21: ChE 308 - Chemical Process Analysis Sessional. A hydrogen peroxide plant is to be set-up at Gazaria, Munshiganj having a capacity of 100 metric ton](https://reader030.vdocuments.site/reader030/viewer/2022032702/56649cc25503460f949896d6/html5/thumbnails/21.jpg)