    Flexible budgets

    Chapter 13

    Dr. Pinar Guven-Uslu

    Norwich Business School, UEA

  • 8/7/2019 Chapter13Handout

    2/16

    S tatic Budgets and Performance Reports

    S tatic budgets areprepared for a single,

    planned level of activity.

    Performance evaluation isdifficult when actual

    activity differs from theplanned level of activity.

    .

  • 8/7/2019 Chapter13Handout

    3/16

    Static ActualBudget Results Variances

    Machine hours 10,000 8,000Variable costs

    Ind irect labour 40,000 34,000Indirect materials 30,000 25,500Power 5,000 3,800

    Fixed costsDepreciation 12,000 12,000Insurance 2,000 2,050

    Total overhead costs 89,000 77,350

    S tatic Budgets and Performance Reports

    CheeseCo

  • 8/7/2019 Chapter13Handout

    4/16

    S tatic Budgets and Performance Reports

    The relevant question is . . .

    How much of the favourable cost

    variance is due to lower activity, and howmuch is due to good cost control?

  • 8/7/2019 Chapter13Handout

    5/16

    Flexible Budgets

    Improve performance evaluation.

    May be prepared for any activitylevel in the relevant range.

    Show revenues and expensesthat should have occurred at theactual level of activity.

    Reveal variances due to good costcontrol or lack of cost control.

  • 8/7/2019 Chapter13Handout

    6/16

    Preparing a Flexible Budget

    Total variable costs change

    in direct proportion tochanges in activity.

    Total fixed costs remainunchanged within the

    relevant range. F ixed

    To a budget we need t o kno w that:

  • 8/7/2019 Chapter13Handout

    7/16

    Preparing a Flexible Budget

  • 8/7/2019 Chapter13Handout

    8/16

    Cost Total Flexible BudgetsFormula Fixed 8,000 10,000 12,000Per Hour Cost Hours Hours Hours

    Machine hours 8,000 10,000 12,000

    Variable costsIndirect labour 32,000Indirect material 24,000Power 4,000

    Total variable cost

    Fixed costsDepreciation Insurance

    Total fixed costTotal overhead costs

    Preparing a Flexible Budget

    Fixed costs areexpressed as atotal amount.

    Variable costs are expressed asa constant amount per hour.

    Calculate these amounts

    CheeseCo

  • 8/7/2019 Chapter13Handout

    9/16

    Flexible Budget

    Performance Report

  • 8/7/2019 Chapter13Handout

    10/16

    Cost TotalFormula Fixed Flexible ActualPer Hour Costs Budget Results Variances

    Machine hours 8,000 8,000 0

    Variable costsIndirect labour 4.00 32,000 34,000Indirect material 3.00 24,000 25,500Power 0.50 4,000 3,800

    Total variable costs 7.50 60,000 63,300

    Fixed ExpensesDepreciation 12,000 12,000 12,000Insurance 2,000 2,000 2,050

    Total fixed costs 14,000 14,050Total overhead costs 74,000 77,350

    Flexible BudgetPerformance Report

    CheeseCo

    Flexible budget isprepared for the

    same activity level(8,000 hours) as

    actually achieved.

    Calculate thevariances

  • 8/7/2019 Chapter13Handout

    11/16

    Cost TotalFormula Fixed Flexible ActualPer Hour Costs Budget Results Variances

    Machine hours 8,000 8,000 0

    Variable costsIndirect labour 4.00 32,000 34,000Indirect material 3.00 24,000 25,500Power 0.50 4,000 3,800

    Total variable costs 7.50 60,000 63,300

    Fixed ExpensesDepreciation 12,000 12,000 12,000Insurance 2,000 2,000 2,050

    Total fixed costs 14,000 14,050Total overhead costs 74,000 77,350

    Flexible BudgetPerformance Report

    CheeseCoFlexible budget isprepared for the

    same activity level(8,000 hours) as

    actually achieved.

  • 8/7/2019 Chapter13Handout

    12/16

    Flexible BudgetPerformance Report

  • 8/7/2019 Chapter13Handout

    13/16

    Static ActualBudget Results Variances

    Machine hours 10,000 8,000 2,000 UVariable costs

    Indirect labour 40,000 34,000 6,000 FIndirect materials 30,000 25,500 4,500 FPower 5,000 3,800 1,200 F

    Fixed costsDepreciation 12,000 12,000 0Insurance 2,000 2,050 50 U

    Total overhead costs 89,000 77,350 11,650 F

    S tatic Budgets and PerformanceHow much of the 11,650 is due to activityand how much is due to cost control?

  • 8/7/2019 Chapter13Handout

    14/16

    Flexible Budget

    Performance Report

    Calculate total overhead variance. How much isdue to change in activity and how much is due

    to change in planned costs?

    Overhead Variance Analysis

    tatic ActualOverhead Overhead

    udget at atHours Hours

    Flexible

    budget

  • 8/7/2019 Chapter13Handout

    15/16

    Flexible Budget

    Performance Report

    Difference between original static budgetand actual overhead = 11,650 F.

    Overhead Variance Analysis

    tatic ActualOverhead Overhead

    udget at at10,000 ours ,000 ours

    ,000 , 50

    Lets place

    the flexiblebudget for ,000 hours

    here.

  • 8/7/2019 Chapter13Handout

    16/16

    Flexible Budget Performance Report

    W hat causesthe cost

    control variance?

    There are two primaryreasons for unfavourablevariable overhead variances:

    1. Spending too much for resources.

    2. Using the resourcesinefficiently .