chapter 8 rehabilitation and retrofitting of existing bridges
TRANSCRIPT
CHAPTER 8
REHABILITATION AND RETROFITTING OF
EXISTING BRIDGES
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-1
8. REHABILITATION AND RETROFITTING OF EXISTING
BRIDGES
8.1 Background
8.1.1 General
Having examined the survey results described in the previous chapter, it can be said that the
deteriorations of Kanchpur Bridge, Meghna Bridge and Gumti Bridge were only a result of
normal aging except those of the expansion joints in all the bridges and the hinges in Megna
Bridge and Gumti Bridge.
The reasons for the damages on the hinges and expansion joints in Meghna Bridge and Gumti
Bridge were described in the last clause of this chapter. It is considered the reasons for the
damages on the expansion joints in Kanchpur Bridge were the same as the other two bridges;
Heavily overloaded trucks,
Inappropriale maintenance.
8.1.2 Additional Information
RHD, consulting BUET, has requested the Army to execute emergency repair works such as;
for Meghna Bridge
Protection of P7 or P8 against the river bed scouring,
Replacement of the expansion joints, 9 nos.,
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-2
Repair of the hinges involving 36 pot bearings,
for Gumti Bridge
Replacement of the expansion joints, 15 nos.,
Repair of the hinges involving 60 pot bearings.
The budget for the works planned is considered to be 1.5 billion BDT.
On 19 May 2012, RHD, BUET and the Army held a meeting and it was decided that the
works will start after the rainy season has finished, around 3 months later.
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-3
8.2 Configuration of Existing Bridges
8.2.1 Existing Kanchpur Bridge
Basic data of existing Kanchpur Bridge are shown in Table 8.2.1.
Table 8.2.1 Basic Data of Existing Kanchpur Bridge
Bridge Existing Kanchpur Bridge
Consultant Anman and Whitny
Contractor Obayashi Corporation
Period of Construction September 1973 to September 1977
River Lakhya River
Bridge length 396.5 m (4×42.7 m+54.9 m+ 73.2 m+ 54.9 m+ 42.7 m)
Bridge width 14.64 m (12.81 m(road) + 2×0.686 m(sidewalk) + 2×0.229 (Railing)) Pre-stressed concrete I girder, continuous type (54.9 m+ 73.2 m+ 54.9 m)
Superstructure Pre-stressed concrete I girder, simply supported type (42.7 m5 spans)
Abutment Inverted T-type Pier Rigid frame-type
Bridge components
Substructure Foundation
Abutment: Spread foundation Pier: RC open caisson
Construction method Erection by staging
Loads Live load AASHOTO (HS20-44 ASD) (available at the time of construction)
Concrete
Slab: 21 N/mm2 Girder: 35 N/mm2 Abutment and pier: 21 N/mm2 Caisson: 18 N/mm2
Reinforcing bar ASTM A 615, Grade 60 (available at the time of construction)
Materials
Pre-stressing steel SWPR7A 12S12.4 (assumed for restoration design)
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
8-4
φ4550
▽RL+2.000 117472124
9623
-10.000
-20.000
-30.000
20.000
0.000
10.000
▽RL-17.812
▽RL+1.000
▽RL-18.812
1866
12451
2124
14575 1866
2124
15854
13730
▽RL+1.000
▽RL-20.336
▽RL+1.000
▽RL-23.384
1950 14687
16811
2124
12534
15115
2581
2065
▽RL+1.000
▽RL-27.956
12681
15262
2581
▽RL+1.000
▽RL-27.956
2065
16828
14704
2124
▽RL+1.000
1950
▽RL-20.336
P1 P2 P3 P4 P5 P6 P7
2562 2562
2562
2562
4923
4923
2562
19812
19812
φ4550 φ4550
21336 φ4550
24384
1866
φ6510
28956
φ6510
28956
φ4550
21336
42700 42700 42700 42700 54900 73200 54900 42700
396500
4550
13590
4550 4550 4550 6510
15550
6510 4550
42700 42700 42700 42700 54900 73200 54900 42700
396500
15250 42700 15250
P1 P2 P3 P4 P5 P6 P7
PROFILE
PLAN
915
14640
915 12810
CL
915 12810 915
229 14182 229
686 12810 686
14640
915
229
176
8381297
838
176
2286
P3 PIER
GRADIENT
PROPOSED HEIGHT
STATION
DISTANCE
GROUNO HEIGHT
i=3.32%
L= 21.185
3416 1829 1905
9141067
341618291905
1981
13730 15854
143
15550
13590
13590
13590
13590
13590
68323379 3379
6@2135=12810
-SH WL=+5.00 12000
61000(航路)5
700
1388 517
1113 366
A1
A2
A1 A1
A114.431
P1
16.309
P2
18.137
P3
19.416
P4
20.373
P5
21.038
P6
21.185
P7
20.990
A2
19.467
CROSS SECTION
SECTION
(PC I GIRDER)
i=L=
M FFM F
F F MFF
To Dhaka
To Chittagong
Figure 8.2.1 General View of Existing Kanchpur Bridge
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-5
8.2.2 Existing Meghna Bridge
Basic data of existing Meghna Bridge are shown in Table 8.2.2.
Table 8.2.2 Basic Data of Existing Meghna Bridge
Bridge Existing Meghna Bridge
Consultant Pacific Consultants International in consortium with Nippon Koei Co., Ltd.
Contractor Obayashi Corporation
Period of Construction March 1987 to February 1991
River Meghna River
Bridge length 930 m (48.5 m+ 9x87.0 m+ 48.5 m+ 2x25.0 m)
Bridge width 9.2 m (7.2 m(road) + 2×1.0 m(Sidewalk +Railing)) Pre-stressed concrete box girder, continuous rigid frame type (48.5 m+ 9×87.0 m+ 48.5 m)
Superstructure Pre-stressed concrete T girder, simply supported type (2×25.0 m)
Abutment Inverted T-type Pier Columnar type
Bridge components
Substructure Foundation
Abutment: RC pile (φ1500) Pier: RC pile (φ1500)
Construction method Balanced cantilever erection
Live load AASHOTO HS20-44 ASD
Seismic load Horizontal load coefficient taken as 0.05 g
Wind load Without live load (V=140 MPH): 0.479 T/m2 With live load (V=100 MPH): 0.244 T/m2
Loads
Thermal force Temperature range: 26 °C±17 °C
Concrete
Cylinder compressive strength at 28 days Pier, Abutment, Pile cap: 240 kgf/cm2 PC box girder, PC- T beam, PC slab: 350 kgf/cm2 RC pile: 300 kgf/cm2
Reinforcing bar Tensile strength: 4,950 kgf/cm2 Yield stress: 4,250 kgf/cm2
Materials
Prestressing steel
SWPR7A (12T12.4) SWPR19 (1T19.3) SWPR19 (1T21.8) SBPR 95/110 (φ32)
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
8-6
1500 4000 1500
2000
5200
2000
▽RL-52.000
RL 0.000
300
(RL±0)
RL+10.000
RL+20.000
RL+30.000
RL+40.000
RL-10.000
RL-20.000
RL-40.000
RL-30.000
RL-60.000
RL-50.000
CAST-IN-SITU RC PILEφ1.5m N=4 L=48.0m
9200
9200
7000
11000
8000
4000 2022
M
48500
11000
1500
2X4000
=8000 1500
1500
11000
15002X4000
=8000
2700
750
5000
750
3200
1500
2X4000
=8000
1500
11000
1500
11000
1500
2X4000
=8000
87000
750
6000
750
A1 P1 P2
▽RL-52.900
A1
P1
17433
14933
500
▽RL+12.433
5922
2700
100 11000 100
CAST-IN-SITU RC PILEφ1.5m N=9 L=48.0m
24543
▽RL-53.400
φ1.5m N=9 L=44.0mCAST-IN-SITU RC PILES
P2
2000
1500
45711000457
5922
▽RL+15.043
3200
▽RL-5.000
▽RL-9.500
500
3500
3500
P3
3200
1500
1500
2X4000
=8000 1500
11000
1500
2X4000
=8000
11000
7505000
750
87000
3200
P3
▽RL-52.400
CAST-IN-SITU RC PILE
457 45711000
φ1.5m N=9 L=43.0m
5922
▽RL-9.500
1500
27153
3500
2000 50024653
▽RL+17.653
P4
3200
1500
1500
11000
1500
2X4000
=8000
15007505000
750
11000
2X4000
=8000
87000
φ1.5m N=9 L=43.0mCAST-IN-SITU RC PILES
27063
29763 3200
P4
▽RL-52.400
11000 457457
500
2200
1500 ▽RL-9.500
3500
5922
▽RL+20.263
P5
3200
1500
1500
11000
2X4000
=8000
1500
11000
1500
2X4000
=8000
7505000
750
87000
29194
31894
P5
▽RL-52.400
φ1.5m N=9 L=43.0m
▽RL-9.500
CAST-IN-SITU RC PILES
11000 457457
500
2200
1500
3200
▽RL+23.000
5922
3500
15004000
4000 1500
▽RL+22.394
4750 4750
P6
1500
3200
2X4000
=8000
11000
1500
750
5000
750
87000
3200
31894
29194
457
▽RL-54.400
457 11000
1500
2200 500
P6
5922
▽RL+22.394
3500
RL 0.000
RL +5.000
75000
▽SHW▽RL+5.900
100 7000 100
930000
930000
48500 87000 87000 87000 87000 87000
4844060
48000420
43440 120 43440 43420 160 43420 43420 160 43420 43420 160 43420 43420 160 43420
2022
2022
2022 2022
2022
18
19
20
21
22
23
24
25
26
27
28
15.850
GRADIENT
PROPOSED HEIGHT
GROUND HEIGHT
ELEVATION OF BOTTOM
FACE OF PILE CAP
DISTANCE
18 19 20 21 22 23 24 25 26 27 28
17.350
18.850
20.350
21.850
23.350
24.850
26.350
27.756
28.506
28.506
RL-5.500
+18.500
P6
RL-9.500
28.376
RL-7.000
+31.500
P5
RL-9.500
28.316
RL-8.255
+44.500
P4RL-9.500
26.185
RL-8.255
+7.500
RL-9.500
23.575
P3
RL-5.500
+20.500
P2
RL-9.500
20.965
18.355
RL-0.500
+33.500
RL-5.000
P1
RL+4.300
RL+5.900
+35.000
A1
16.900
+25.000
28.600
31.100
27.100
i=3.000%
PROFILE
PLAN
(航路) 18000
P6P5P4P3P2P1
A1
To Dhaka
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
8-7
11000
φ1.5m N=9 L=43.0m
L-9.500
CAST-IN-SITU RC PILES
L+23.000
P6
1500
2X4000
=8000
11000
1500
1500
3200
2X4000
=8000
11000
1500
750
5000
750
87000
3200
31894
29194
457
▽RL-9.500
▽RL-54.400
457 11000
1500
2200500
P6
CAST-IN-SITU RC PILEφ1.5m N=9 L=45.0m
5922
▽RL+22.394
3500
RL 0.000
RL +5.000
75000
W
P7
3200
1500
7505000750
1500
11000
2X4000
=8000
1500
1500
11000
2X4000
=8000
87000
3200
P7
▽RL-54.400
11000457 457
CAST-IN-SITU RC PILEφ1.5m N=9 L=45.0m
▽RL-9.500
5922
1500
29763
3500
2200500
27063
▽RL+20.263
750
5000
750
P8
1500
3200
1500
1500
2X4000
=8000
11000
1500
2X4000
=8000
11000
87000
3200
▽RL-9.500
▽RL-50.400
P8
φ1.5m N=9 L=41.0mCAST-IN-SITU RC PILE
5922
27153
24653
500
1500
2000
3500
457 11000 457
▽RL+17.653
P9
3200
1500
1500
11000
2X4000
=8000
1500
1500
11000
2X4000
=8000
7505000750
87000
22043
24543
3200
▽RL-52.400
2000
1500
P9
457457 11000
▽RL-9.500
500
3500
5922
φ1.5m N=9 L=43.0mCAST-IN-SITU RC PILE
▽RL+15.043
RL 0.000
P10
2700
1500
2X4000
=8000
11000
1500
87000
11000
15002X4000
=8000
1500
5000
750
780
17433
14933
▽RL-5.000
100 11000 100
P10
5922
▽RL+12.433
3500
2700
CAST-IN-SITU RC PILEφ1.5m N=9 L=40.0m
▽RL-44.900
500
485002000
2501500 250
7000
1500 4000 1500
7000
1500
40001500
P11
1007000100
P11
2422
1140
▽RL-0.500
10700
14700
500
1500
▽RL-35.500
1500
10001000
M F
1500
100 7000
P12
▽RL-0.5001500
1000
1000
500
15080
11080
M F
100
P12
15001500 4000
7000
CAST-IN-SITURC PILEφ1.5m N=4 L=35m
▽RL-38.000
8000
4000
M
CAST-IN-SITU RC PILEφ1.5m N=4 L=44.0m
▽RL+5.900
7000
4000 1500
A2
1500
i=12.0
25000 25000
930000
930000
87000 87000 87000 87000 87000 48500 25000 25000
0 160 43420 43420 160 43420 43420 160 43420 43420 160 43420 43440 120 43440 48470 60 24950 40 24960 40
350242403503602424035047048000
2022
2022
2022
2022
2022
1472
28
29
31
30
32
33
34
35
36
37
28
29
30
31
32
33
34
35
36
37
28.506
27.756
26.350
24
23.350
21.850
20.350
18.850
17.350
15.850
A2
+15.000
RL+5.900RL+3.100
15.400
+40.000
RL-0.500RL+3.500
16.150
P12
RL+3.500
RL-0.500
+15.000
P11
16.900
18.355
+16.500
RL-5.000RL-0.500
P10
RL-6.000
RL-9.500
+29.500
P9
20.965
RL-7.000
RL-9.500
+42.500
P8
23.575
RL-6.000
+5.500
RL-9.500
26.185
P7
RL-5.500
+18.500
P6
RL-9.500
28.376
+25.000
28.600
31.100
27.100
i=3.000%
i=12.0
100 7000 100
A2
PROFILE
PLAN
(航路) 18000
A2P12P11P10
P9P8P7P6
To Chittagong
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-8
Figure 8.2.2 General View of Existing Meghna Bridge
PIERP12
800 7200
9200
11200
2@4000=8000
2150
9200
580
0
250
1800
3500
800
1950150
9200
1108
0
1508
0
▽RL-0.500
Φ1,5m,LENGTH:P12=35mCAST-IN-SITU R.C.PILE
500
150
0
100
200
▽RL+14.580
192
100
0100
0
4000
4000
7000
▽RL+5.100
5001000
1500
▽RL+0.620
▽RL+3.500
1000
1500
500
72001000
1200
135
0▽RL+6.990
1000
1600
▽RL-5.000
SHW▽RL+5.100
HWL▽RL+6.990
▽RL-2.500
▽RL+0.628
288
030
06498
LENGTH=55.0m,NOS=4CAST-IN-SITU R.C.PILE Φ1,500
1500
100
11178
200
▽RL+5.900
11000
9200
5200
ABUTMENT
2000
100
A1
100
2000
9200
7200
▽RL+16.900
1000
▽RL+17.078
1000 200
2550
1200
1350
1500
1050
100
9200
8800 200
800
150
900
i 2%
300
120
800
i 1%
300
7200
350
PC T GIRDER
4X1850=7400
150 1500
500
AT PIER
900200
600
AT CENTER
ASPHALT CONCRETE PAVEMENT
200
CL
ADJUSTING CONCREETE
1200
250
200
5000 1950 150
14933
1743
3
2000
200
100
1600
P1 PIER
CAST-IN-SITU R.C.PILEΦ1,5m,LENGTH:48m
500
6700 2150
▽RL+0.880
5800
1200
200800
▽RL+12.433
PC BOY GIRDERAT PIER AT ABUTMENT
1200
2300
250
250
300
2.0%
800
2.0%
300 50
300
70
7200
1300
140
60
100
600
5001000100
800
100
1950
400
300
100
500
750
600300
550
ASPHALT CONCRETE PAVEMENT
ADJUSTING CONCREETE
LC
200
CROSS SECTION
SECTION
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-9
8.2.3 Existing Gumti Bridge
Basic data of existing Gumti Bridge are shown in Table 8.2.3.
Table 8.2.3 Basic Data of Existing Gumti Bridge
Bridge Existing Gumti Bridge
Consultant Pacific Consultants International in consortium with Nippon Koei Co., Ltd.
Contractor Obayashi Corporation
Period of construction March 1992 to February 1996
River Meghna River and Gumti River
Overall length 1410 m (52.5 m + 15x87.0 m + 52.5 m)
Overall width 9.2 m (7.2 m (road) + 2×1.0 m (Sidewalk +Railing)
Superstructure Pre-stressed concrete box girder, continuous rigid frame type
Abutment Inverted T-type Pier Columnar type
Bridge components
Substructure Foundation
Abutment: RC pile (φ1500) Pier: RC pile (φ1500)
Construction method Balanced cantilever erection
Live load AASHOTO HS20-44 ASD
Seismic load Horizontal load coefficient taken as 0.05
Wind load Without live load (V=150 MPH): 0.513 T/m2 With live load (V=100 MPH): 0.244 T/ m2
Loads
Thermal force Temperature range: 26 °C±17 °C
Concrete
Cylinder compressive strength at 28 days Pier, Abutment, Pile cap: 240 kgf/cm2 PC box girder, PC T beam, PC slab: 350 kgf/cm2 RC pile: 300kgf/cm2
Reinforcing bar Tensile strength: 4,950 kgf/cm2 Yield stress: 3,000 kgf/cm2 Allowable stress: 2,100kgf/cm2
Materials
Prestressing steel
SWPR7A (12T12.4) SWPR19 (1T19.3) SWPR19 (1T21.8) SBPR 95/110 (φ32).
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
8-10
9000
7200
300
A1
▽RL-62.195
M
2422
▽RL+3.705
φ1.5m N=5 L=66.0mCAST IN SITU RC PILE
-70.000
-50.000
-60.000
-30.000
-40.000
-20.000
-10.000
10.000
0.000
20.000
N
1500
7500
22501500
14
1500
A1
9200
1500
3100
3100
1500
2250
52500
10500
1500
3750
3750
1500
10500
15003750
3750 1500
4900
15001500 3750
10500
15003750 3750
1500
10500
4900
3750
87000
10500
SEAL CONCRETE
φ1.5m N=8 L=63.0mCAST IN SITU RC PILE
▽RL-2.500 12358
8358
2500
1500
5922
▽RL-65.400
P1
P1 P2
16957
20957
15002500▽RL-8.500
10500
φ1.5m N=8 L=59.5m
▽RL-67.900
CAST IN SITU RC PILE
5922P2
N
3750
4900
10500
37501500 1500
P3
10500
1500
3750
3750
1500
87000
10500
▽RL-8.500
22903
18903
CAST IN SITU RC PILEφ1.5m N=8 L=65.0m
▽RL-73.400
15002500
5922P3
15001500 3750
10500
P4
15003750 3750
1500
10500
4900
3750
87000
φ1.5m N=8 L=64.5mCAST IN SITU RC PILE
19828
23828
▽RL-8.500
▽RL-72.900
2500
1500
10500
5922P4
24100
20100
φ1.5m N=8 L=68.5mCAST IN SITU RC PILE
▽RL-76.900
10500
▽RL-8.500
15002500
5922
P5
10500
37501500 1500
P5
3750
4900
10500
1500
3750
3750
1500
87000
MG 9
15001500 3750
10500
15003750 3750
1500
10500
P6
4900
3750
87000
20361
24361
▽RL-74.400
2500
1500▽RL-8.500
10500
5922
P6
φ1.5m N=8 L=66.0mCAST IN SITU RC PILE
5922
▽RL-70.900
10500
▽RL-6.500
22622
2500
1500
φ1.5m N=8 L=64.5mCAST IN SITU RC PILE
18622
P7
P7
4900
375015003750
10500
1500
1500
15003750 3750
10500
87000
P8
1500
1500
10500
3750 15003750
4900
10500
3750
3750
1500
87000
5922
▽RL-2.500
▽RL-70.400
CAST IN SITU RC PILEφ1.5m N=8 L=68.0m
18380
2500
1000
10500
14880
P8
▽RL-2.500
1500
87000
1410000
DL=-80.000
52500 87000 87000 87000 87000 87000 87000 87000 87000
BRIDGE LENGTH L=1410000m
52440
60 420 52020
43440 120 43440 43440 120 43440 43440 120 43440 43440 120 86880 120 43440 43440 120 43440 43440 120 43440 43440 120 43440
1900 1900
1900
1900
1900
1900
1900
1900
DISTANCE
GROUNO HEIGHT
PROPOSED HEIGHT
STATION
GRADIENT
14
10.905
13.905
A1
+10
12.705
14.280
15.405
18.133
19.036
19.601
19.841
19.991
20.141
20.291
20.441
20.591
20.741
20.865
20.915
i=600
i=600
VCL = 200 R = 7400 VCL = 200 15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
700.000
2.25
12.405
2.62
750.000
760.000
i=3.0%
L=416.660
800.000
2.15
P1
812.500
5.60
5.60
2.40
-2.50
-4.80
-5.80
-5.80
-5.60
850.000
P2
899.500
900.000
-5.60
16.879
16.893
950.000
-5.60
-6.00
P3
986.500
18.825
-6.00
19.500
1000.000
1050.000
1073.500
P4
19.750
-6.00
1100.000
-6.00
-5.80
1150.000
-5.70
1160.500
P5
20.022
-5.30
-5.00
1200.000
-4.80
1250.000
1247.500
P6
20.283
-4.65
-4.40
1300.000
-3.60
1350.000
-2.60
1334.500
20.544
-3.10
P7
1400.000
-0.40
1421.500
P8
20.802
-0.20
1450.000
1.99
2.34
L=522.000
i=3.0%
2.95
2.67
3.31
1500.000
MEGHNA RIVER
N N N N N
N N N
PROFILE
PLAN
(航路)75000
7500
To Dhaka
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
8-11
CAST IN SITU RC PILEφ1.5m N=8
5922
▽RL-72.400
10500
15025
0014994
17644
▽RL-2.500
P9
P9
4900
375015003750
10500
1500
1500
15003750 37
50
1050
0
70.0m75.0m
CHAR LAND
N=4 L=70.0m
N=4 L=75.0m
▽RL-77.400
5922
▽RL-69.900
1753
0
14880
15025
00
φ1.5m N=8 L=67.5mCAST IN SITU RC PILE
10500
-SH WL =+5.25
▽RL-2.500
P10
P10
1050
0
1500
1500
10500
3750 15003750
4900
3750
3750
1500
87000
P11
15003750 37
50
1500
1500
1050
0
4900
37503750
10500
1500
87000
5922
14622
1812
2
2500
1000
10500
▽RL-2.500
▽RL-67.400
φ1.5m N=8 L=65.0mCAST IN SITU RC PILE
P11
5922
▽RL-67.400
▽RL-2.500
1000
10500
φ1.5m N=8 L=65.0mCAST IN SITU RC PILE
17861
14361
2500
P12
P12
1500
10500
37503750
4900
1500
1500
1050
0
3750
3750
1500
87000
P13
1500
1500
4900
37503750
10500
1500
15003750 37
50
1050
0
87000
5922
▽RL-67.400
CAST IN SITU RC PILEφ1.5m N=8 L=63.0m
10500
1500
1610
0
20100
2500
▽RL-4.500
P13
5922
21828
φ1.5m N=8 L=62.0mCAST IN SITU RC PILE
▽RL-68.400
1500
2500
10500
▽RL-6.500
17828
P14
P14
1500
10500
37503750
4900
1500
1500
1050
0
3750
3750
1500
87000
5922
▽RL-66.900
1690
3
20903
2500
1500▽RL-6.500
10500
φ1.5m N=8 L=60.5mCAST IN SITU RC PILE
P15
P15
15003750 37
50
1050
0
1500
1500
4900
37503750
10500
1500
87000
GUMTI RIVER
P16
10500
▽RL-4.500
5922
▽RL-68.900
16951
1500
2500
φ1.5m N=8 L=64.5mCAST IN SITU RC PILE
12951
1500
10500
37503750
4900
P16
1500
1500
1050
0
3750
3750
1500
87000 52500
9200
1500
3100
3100
1500
150022502250
7500
1500
A2
300
7500
1500
1100
0
9200
▽RL-61.585
CAST IN SITU RC PILEφ1.5m N=5 L=66.0m
M
▽RL+4.315
1900
87000 87000 87000 87000 87000 87000 87000 52500
00m
43440 43440 120 43440 43440 120 43440 43440 120 43440 43440 120 43440 43440 120 43440 43440 120 43440 43440 120 43440 52500
1900
1900
1900
1900
1900
1900
1900
20.915
20.891
20.462
20.791
VCL = 200 R = 34000 VCL = 200 R = 7400
30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
2.67
3.31
1500
.000
1508
.500
P920.916
3.10
21.066
2.25
2.28
2.79
2.66
1550
.000
1.93
2.23
1.17
1600
.000
1595
.500
P10
20.802
1.75
1.78
2.17
1650
.000
1700
.000
20.492
2.23
2.69
1682
.500
P11
20.544
2.65
2.58
3.12
1750
.000
20.342
2.79
1769
.500
P12
20.283
2.77
i=0.3%L=522.000
2.77
2.84
2.60
1800
.000
20.192
1850
.000
20.042
2.37
1.30
1856
.500
P13
20.022
1.20
1.00
1900
.000
19.892
0.00
-1.10
1943
.500
P14
19.750
-1.20
-1.30
1950
.000
19.716
2000
.000
19.266
-1.20
2030
.500
P15
18.825
-1.30
19.500
2050
.000
18.748
2100
.000
17.352
-1.40
2117
.500
P16
16.879
0.20
0.50
2150
.000
15.915
1.88
2.34
3.54
3.95
2170
.000
15.315
A2+20
2200
.000
14.415
4.10
4.21
4.16
4.06
5.47
2250
.000
12.915
2300
000
11415
i=3.0%L=432.300
4.14
4.08
4.12
5.48
STONE DAUDKANDI
A2
N N N
N N
N N
N
N
ILE
To Chittagong
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-12
Figure 8.2.3 General View of Existing Gumti Bridge
1501950150 1950 5000
ADJUSTING CONCRETE
ASPHALT CONCRETE PAVEMENT
7200
9200
300
800
2.0%
200
CL
1500300
800
250
2.0%
250
2300
200
42250
72300
140050
1800
50
400100
300600
AT ABUTMENT
200
250
250
1900
1400
150
1500300
800
622
500
7250
300
800 7200
50001950150 1950
2.0% 2.0%
AT CENTER
9200
200
CL
ASPHALT CONCRETE PAVEMENT
ADJUSTING CONCRETE
50
150 960 960150
100 400 100 800
300
100
600
100
200
250
250
5800
5300
150
1500300
800
422
300
7250
300
800 7200
500
5000
50
1950150
50
1950
2.0% 2.0%
AT PIER
9200
200
CL
ASPHALT CONCRETE PAVEMENT
ADJUSTING CONCRETE
500
1400
300
100
800
1000
500
600
100
100
110
00
11178
2878
ABUTMENT
1500
6500
300
1500
A1
1500 3100
9200
CAST IN SITU PILEφ1.5m N=6 L=66.0m
▽RL+1.705
10001000
▽RL+12.703
7200
9200
▽RL+12.883
3100
3750 3750
10500
1500 1500
PIERP6
4900
▽RL+20.283
7200
9200
2800
▽S W WL RL+5.250
1000
5800
7000
2800
20361
1500
2500
φ1.5m N=8, L=66.0mCAST IN SITU RC PILE
▽RL-10.00
1000
▽RL+14.361
1500
1000
123
61
CROSS SECTION
1000
9200
72001000
▽RL+14.280
1500
5800
▽RL+8.358
8358
2500
1500
2800 4900 2800
▽RL-4.000
10500
1500 3750 3750 1500
CAST-IN-SITU RC PILEφ1.5m N=8, L=63.0m
7358
1000
▽S W WL RL+5.250
P1 PIER
SECTION
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-13
8.3 Scope of the Retrofitting and Rehabilitation Works
8.3.1 Observation of the Damages
As shown in detail in 2.5.1 the damages to the three bridges have been observerd as follows;
Table 8.3.1 Observation of the Damages (Structures)
Kanchpur Meghna Gumti
Sub-structure Cracks and water leakage Cracks Small dents No rebar deteriorations.
Cracks Water leakage Small dents No rebar deterioration.
Girders & Cross beams
No visible cracks. Rebar exposures Cracks over 0.2 mm Water leakage
Deck slab No visible cracks. A crack over 0.2 mm width with small amount of isolated lime
No visible cracks.
State Normal Normal Normal
Causes of Deterioration
Aging Aging Aging
Table 8.3.2 Observation of the Damages (Accessories)
Kanchpur Meghna Gumti Expansion
joints Damaged. Damaged.
Damaged.
Hinges N/A Damaged.
State Serious Serious Serious
Possible causes of damages
Overloaded trucks Insufficient maintenance
Overloaded trucks Insufficient maintenance
Overloaded trucks Insufficient maintenance
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-14
8.3.2 Scope of the Retrofitting and Rehabilitation Works
From the above mentioned background the scope of the rehabilitation works shall be defined
as the repair works for the damaged expansion joints in Kanchpur Bridge, Meghna Bridge
and Gumti Bridge and the repair works for the damaged hinges in Meghna Bridge and Gumti
Bridge.
The retofitting works shall be defined as the works to renew the bridge structures to conform
to the current bridge design standards and to cope with the current and future scouring
conditions. As mentioned in the previous chapter the changes of the design seismic force
should be reflected in all the bridges and the changes of the live load should be reflected in
Kanchpur Bridge.
The repair works for the damaged hinges shall be connecting two cantilever girders to be
monolithic, eliminating the hinge and expansion joint at each hinge section. As the hinge
section shall remain in every 5 or 6 spans to avoid excessive restraint forces from being
generated by the temperature change, the hinges and expansion joints at such sections shall
be replaced by new ones.
To prevent the bridge from collapsing during earthquake the steel brackets will be attached to
the substructures at the girder ends. At the halving joint of Kanchpur Bridge the girder ends
are connected to each other.
Consequently, the scope of the retrofitting and rehabilitation works for Kanchpur Bridge,
Meghna Bridge and Gumti Bridge are summarized below.
Table 8.3.3 Scope of the Rehabilitation and Retrofitting Works
Kanchpur Meghna Gumti
Repair of cracks/rebar exposures ○ ○ ○
Connecting girders (eliminating hinges/joints) - ○ ○
Center hinge rehabilitation - ○ ○ Repair
Expansion joint replacement ○ ○ ○
Steel brackets on the substructures ○ ○ ○
Fail-safe connection ○ - -
Deck strengthening ○ - -
RC-lining ○ ○ ○ Piers
Diaphragm wall ○ - -
Pile cap integration P1, P3, P5, P6 P1 to P10 P1 to P8
Steel pipe sheet piles P1 to P6 P3 to P10 P1 to P8
Retrofit
Foundations
Bored RC piles - P1, P2 -
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-15
8.4 Loads Applied in the Original Design and to be Applied in the Current Design
The difference between the original design standards and the current design standards is
found to be changes in magnitude of;
Earthquake loads
Live loads
8.4.1 Earthquake Loads
According the existing records (as-built drawings and design calculation report of existing
Meghna and Gumti Bridges), it is found that the seismic acceleration coefficient of 0.05 was
used to calculate the horizontal seismic forces. But, that value according to BNBC (2006) has
been increased to 0.15, which results in increasing the coefficient of response of spectral
acceleration to 0.08~0.33. Therefore, it may necessitate revising the original design of the
existing bridges.
Figure 8.4.1 Seismic Zoning Map of Bangladesh
Legend
Border
River and Lake
Acceleration zone (0.25)
Acceleration zone (0.15)
Kanchpur Bridge
Meghna Bridge
Gumti Bridge
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-16
Due to the change of the seismic acceleration coefficient, the magnitude of the horizontal
seismic force will be increased to 1.6~6.6 times the original seismic force.
Table 8.4.1 Horizontal Seismic Coefficient
Figure 8.4.2 Earthquake Load Application
8.4.2 Live load Combination
As is mentioned in Chapter 6, special consideration will be given to the design of the floor
slab system due to accommodating the heavily loaded trucks. Accordingly, the live load
combination from Japanese standards B-type live load will be followed, while the live load
combination from AASHTO HS20-44 will be followed for girder design.
(1) Slab design
The restoration design by reverse analysis method shall be followed particularly for the
existing Kanchpur Bridge. This is due to lack of information and no as-built drawings
available. The floor slab design is recovered by restoration method applying the AASHTO
ASD based HS20-44 live load. The computed results hereinafter are referred to as the
11200
2@4000=8000
2150
1600
14933
17433
2000
200
100
1600
CAST-IN-SITU R.C.PILEΦ1,5m,LENGTH:48m
500
6700 2150
5800
1200
H Original design standard
H=0.05 V
Current standard
H=0.08~0.33 V
H
Original design standard (1) Current standard (2) (2) / (1)
0.05 0.08~0.33 1.6~6.6
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-17
capacity of the existing Kanchpur Bridge considering the bridge time span from construction.
On the other hand, the results computed with B-type live loads are considered as the
requirements for the exiting bridges. However, the rehabilitation plan along with retrofitting
is finalized based on these two results.
Furthermore, the retrofitting plan for the floor slab system of the existing Meghna and Gumti
Bridges is finalized considering the B-type live loads.
Table 8.4.2 Live Loads for Slab Design
(a) AASHTO HS20-44 truck load (b) JRA B-type truck load
Figure 8.4.3 Truck Live Load Comparison
(2) Girder design
The differences in lane live loads, based on different AASHTO versions, are mainly focused
on their magnitude, which are shown in Table 8.4.3 side by side. The lane load specification
corresponding to AASHTO LRFD HS20-44 will be used for retrofitting of the existing bridge
girders.
Original design standard
(AASHTO HS20-44 ASD) Current standard
(Japanese standard B-type live load)
Truck Wheel Load
72 kN 100 kN
Load applica-
tion
72kNSlab
Transverse direction
100kN
Slab
Transverse direction
Transverse direction
Tire area
Unit: mm
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-18
Table 8.4.3 Live Loads for Girder Design
Figure 8.4.4 Live Loads (AASHTO HS20-44)
※1: Live load for moment calculation
※2: Live load for shear calculation
Original design standard
(AASHTO ASD, HS20-44) Current standard
(AASHTO LRFD, HS20-44)
Live loads Concentrated load: 208 kN ※1 or 302 kN※2
(4 Lanes) Uniform load: 24 kN/m (4 Lanes)
Concentrated load: 845 kN (4 Lanes) Uniform load: 24 kN/m (4 Lanes)
Load applicat-
ion
24kN/ 208kN or 302kN
Girder
Longitudinal direction
24kN/845kN
Girder
Longitudinal direction
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-19
8.5 Kanchpur Bridge
8.5.1 Evaluation and Recommendations for Slab Design
As is also discussed in the previous section, the slab strength of the existing Kanchpur Bridge
shall be assessed by applying the restoration design concept. Then, the strength assessment in
both longitudinal and transverse directions is compared with the allowable stress
recommended by JRA. It can be found that the slab strength retained does not meet the
allowable criteria when subjected to current design standards.
Table 8.5.1 Slab Strength Evaluation
Table 8.5.2 Retrofitting Method for Slabs
Center span Support Center span
- kN・m 13.80 -25.24 8.25 -
Concrete 8.0 N/mm2 4.41 7.12 3.75 OK
Reinforcement 165 N/mm2 128.00 155.30 138.50 OK
- kN・m 19.42 -38.61 13.43 -
Concrete 8.0 N/mm2 6.20 10.88 6.10 OUT
Reinforcement 165 N/mm2 180.10 237.60 225.50 OUT
CheckUnitAllowable
Stress
Stress
Moment
Moment
Original design standard
Current standard
Transversedirection
Longitudinaldirection
D13ctc250 (assumed) D16ctc150 (assumed)
180
30
30
D13ctc250 (assumed) D13ctc150 (assumed)
Transverse direction
◎ △ ◎
△ △ △
Construction period ◎ △ ◎
Legend: ◎excellent, ○good, △poor
1.111.11
Need traffic restriction
(Overlay and waterproof) (waterproof)
A little
(Upward construction)
Weight is increasedGirder, pier and foundation need retrofittingabout slab retrofitting
Weight is increasedGirder, pier and foundation need retrofittingabout slab retrofitting
△
△△
Long
Need scaffolding
Better
Need traffic restriction
○◎
Many
Evaluation
Image
ConstructabilityConstruction
Traffic restriction
Cost
Crack rehabilitation
Feature
Record of usage
C plan:Carbon fiber
Many
Short
Need scaffolding
Best
(Downward construction)
B plan: Overlay method on the under of slabA plan: Overlay method on the top of slab
Better○
(Upward construction)
Need scaffolding
◎
◎
Crack width under 0.2mm shall be coated
Crack width over 0.2mm shall be crack grout△
1.00
No weight increase ◎△
△ △
Crack rehabilitation isn't required ◎△
Short
traffic restriction isn't required◎
Crack width under 0.2mm shall be coated
Crack width over 0.2mm shall be crack grout
△△
Existing slab
Additional slab(100mm)
Pavement
Existing slab
Additional slab(70mm)
Pavement
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-20
8.5.2 Evaluation and Recommendations for PC Girder Design
Based on the original design standards, the arrangement and profile of PC-bars are decided
from the restoration design. Then, the computed results are compared with the results
computed by current design standards specification in Table 8.5.3 - Table 8.5.4. It shows that
the capacity of the PC-girder does not meet the requirements as per current design standards.
Therefore, it requires retrofitting /additional reinforcement. On the other hand, PRC girder
seems to be quite safe under current design standards and thereby, no further retrofitting is
necessary.
Table 8.5.3 Restoration Design of PC Girder Based on Original Design Standards
Table 8.5.4 State of Strength of PC-Girder
Unit Allowable Results Check Remarks
N/mm2 0.00<σ<12.5 3.82 OKN/mm2 -1.35<σ<12.5 1.32 OKN/mm2 -1.35<σ<14.3 1.57 OK
Ultimate moment Mu kNm - 17213 -Moment capacity Mr kNm - 22846 -
Mr/Mu - F>1.0 1.33 OK
N/mm2 σi>-0.9 -0.05 OKN/mm2 σi>-1.85 -0.16 OK
Ultimate share Sh kN - 1299 -Crushing capacity Suc kN - 2405 -
Suc/Sh - F>1.0 1.85 OK
Moment Center span
SWPR7A 12S12.4-6PC bar
From girder end to 4.6m
Compound stress due to
Flexural safety
Live loadDead load
Shear
Diagonal tensile stress due to
Web crushing capacity
Temperature load
Live loadDead load
Moment checkShear check
Unit Allowable Results Check Remarks
N/mm2 0.00<σ<12.5 3.82 OKN/mm2 -1.35<σ<12.5 -1.45 OUTN/mm2 -1.55<σ<14.3 -1.21 OK
Ultimate moment Mu kNm - 20816 -Moment capacity Mr kNm - 22846 -
Mr/Mu - F>1.0 1.10 OK
N/mm2 σi>-0.9 -0.05 OKN/mm2 σi>-1.85 -0.35 OK
Ultimate share Sh kN - 1581 -Crushing capacity Suc kN - 2405 -
Suc/Sh - F>1.0 1.52 OK
From girder end to 4.6mShear
Diagonal tensile stress due to
Web crushing capacity
Dead loadLive load
Center span
Live loadTemperature load
Compound stress due to
Flexural safety
Dead load
PC bar SWPR7A 12S12.4-6
Moment
Moment checkShear check
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-21
Table 8.5.5 State of Strength of PRC-Girder
There are two cantilever sections in the span between pier P5 and P6. It is found from the
survey results that these cantilever sections are not severely damaged and the existing traffic
can easily move over these cantilever sections without any hindrance. Therefore, it is planned
not to rehabilitate and leave them unchanged.
8.5.3 Evaluation and Recommendations for Pier Design
In order to assess the state of strength of the bridge piers, the pier P5 is analyzed with the
seismic loading specified by the original and current design standards. From the computed
results, it can be seen that pier P5 does not meet the requirements for its resistance capacity.
Therefore, it will lose its resistance capacity when subjected to strong earthquake excitation.
Table 8.5.6 State of Strength of Pier P5
It is necessary to increase the strength of the existing bridge piers so that they can withstand
strong seismic excitation. Accordingly, the JICA study team adopted three plans;
ReinforcementUnit Results Check
Compound stress Live load N/mm2 -1.45 -N 99180 -
N/mm2 200.00 -mm2 495.90 -mm2 506.80 -
F>1.0 - 1.02 OK
Tensile force
Available reinforcementReinforcement requiredAllowable tensile stress
SD390-4
600
150 150 150 150
69 210 43 210 69
250
240
90
120
120
120
50
180
PC鋼材 6-12φ12.4
D13
PC bar
Moment kNm 18420 17434 OUT
Shear kN 1290 1838 OK0.081.89
Longitudinaldirection
CheckCapacityDemandSpectral
accelerationcoefficient
Periodictime
Unit
1600
838
16762057
3429 3429
2057
1676
143
12534
15115
2438
15550
68584346 4346
1573572
12534
15115
2581
2065
4923
φ6510
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-22
A-plan: RC-lining + Wall
B-plan: Steel plate lining
C-Plan: Polymer mortar lining
A comparative study of the four plans with their construction cost is shown in Table 8.4.7.
From this comparison, the JICA study team recommends that the A-plan (RC-lining + Wall)
is most preferable for seismic retrofitting of the existing Kanchpur Bridge piers. This is due
to the least construction cost.
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
8-23
Table 8.5.7 Seismic Retrofitting of Existing Bridge Piers
Record of usage ◎ ○ △
△ △ △
Construction period △ ◎ △
Painting ◎ △ ◎
Inspection ◎ △ ◎
Legend: ◎excellent, ○good, △poor
△
◎
(No space in the wall)
Poor Poor
(No space in the wall)
Poor
Structural performance
Constructability
Maintenance
Long
Extra provision No need protection from heavier floating bodies
Many
◎
△(No space in the wall)
Need cofferdam
Need No need
Need cofferdam
Short
Cost ◎ △1.491.261.00
Evaluation
A plan: RC lining + Wall
Easy
◎
Image
Landscape △
B plan: Steel plate lining C plan: polymer mortar lining
◎ △
△Need protection from heavier floating bodies◎No need protection from heavier floating bodies
DifficultConstruction
No need
Need cofferdam
Easy
△
Few
○
○
Not so many
Difficult
Long
Easy
Easy
Effect on acquaticenvironment
Good ◎ ◎Good ◎ Good
Anchor
14324
1600
838
1758 3429 3429 1758
2145
1253
4
2565
2065
250
250
1573572
286 2502145
250
250 286
250
Existing pier
100 150
a part
A-A
250
100 150
286
A A
a
500
Wall
Anchor
Existing pier
a part
14324
1600
838
1758 3429 3429 1758
2145
1511
5
2137
2065
36
36
1573572
41 362145
36
36 41
A-A
36
306
41
36
30 6
Steel
Less-shrinkage
Concrete
A A
a
36
500
Wall
mortar t=30mm
Anchor
Existing pier
a part
14324
1600
838
1758 3429 3429 1758
2145
1511
5
2181
2065
5858
1573572
66 582145
58
58 66
A-A
58
66
58
58
A A
a
500
Wall
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-24
8.5.4 Evaluation and Recommendations for Foundation Design
As per the original design standards, the capacity of the existing bridge pier foundation is
assessed by applying the restoration design concept. Then, the computed results are compared
with the results computed by the current design specifications in Table 8.5.8. The current
design specifications consider the seismic force as per BNBC along with the higher scouring
level that is expected. It shows that the capacity of the foundation corresponding to pier P5
does not meet the requirements as per current design standards. Therefore, it requires
retrofitting /additional reinforcement.
Table 8.5.8 State of Strength of Foundation Corresponding to Pier P5
Displacement mm 29 50 OK
Subgrade shearing action kN 7707 8292 OK
Displacement mm 92 50 OUT
Subgrade shearing action kN 7967 5860 OUT
OUT637833kN/m2Subgrade reactionin axial direction
Subgrade reactionin axial direction
Longitudinal direction
Transverse direction
OUT7341894kN/m2
0.151.89
0.150.89
Demand Capacity CheckUnitPeriodic
time
Spectralaccelerationcoefficient
11150
2070
15550
6510
1740
1740
4350 3430 3430 4350
Caisson foundation(φ15.550mx6.510m L=28.956m)
1570570
15120
28960
▽RL+1.000
Design scouring depth RL=-15.00
H.W.L ▽RL+5.000
3000
Projected length 16000
4000
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-25
Based on the above results, it is necessary to increase the strength of the foundation for the
existing bridge piers so that they can withstand strong seismic excitation. Accordingly, the
JICA study team has adopted two plans;
A-plan: Steel Pipe Sheet Pile
B-plan: Additional RC-Pile
A comparative study of the two alternative plans highlighting their construction cost and
scouring effect on the river bed is shown in Table 8.5.9. From this comparison, the JICA
study team recommends that the A-plan (Steel Pipe Sheet Pile) is the most preferable option
for retrofitting of the existing Kanchpur Bridge pier foundations. This is due to the least
construction cost and small scouring effect on the river bed.
Table 8.5.9 Foundation Retrofitting
SP
Plan A: SPSP Plan B: RC pile
Image
Foundation size Small Large
Not requiredCofferdam
Evaluation ◎
Cost 1.921.00
RL=+16.115
15120
1322 436
14640
28960
Dc1
Dm2
As
▽RL+1.000
800
S.H.W.L ▽RL+5.08
Protected height 19010
4500
13990
4648
18400
15300
2.0%
16200
2.0%
155504545 1500 7000 1500
10000
14324
1000 1596
H.H.W.L ▽RL+6.37
Retrofitted wall1000 4858 1000
Scouring RL=-18.01
9950
3000
Supporting layer
New bridgeExisting bridge
P5
RC LINING
500
River bed
34940
14640
11150
2065
15550
9980
4540
13730
3000
Retrofitted wall
10000 2720
4120
4110
11230
56205620
2120
2360
6510
2360
11230
2360
2360
1000
17320
Steel pipe sheet pile
φ1000 L=37.5
3000
6510
5×3750=18750
21750
9×3750=33750
1500
1500
1500 1500
36750
15550
10000
10980
99207400
£
7620
7620
17320 8450
CAST-IN-SITU R.C.PILE
Φ1,5m,n=52,LENGTH:30.5m
1500
36750
18400
15300
2.0%
3100 3100
2.0%
2060 10000
▽RL-2.000
H.H.W.L ▽RL+6.37
Supporting layer
P5
S.H.W.L ▽RL+5.08
500
River bed
1600
838
4346 3429 3429 4346
1676 2057 3429 3429 1790 1943
143
Caisson
φ15.550mx6.510m L=28.956m
1573 572
4350 3430 3430 4350
Caisson
(φ15.550mx6.510m L=28.956m)
14620
14640
Dc1
Dm2
▽RL+1.000
Scouring RL=-18.01
800
3000
Protected height 16510
3500
13990
4650
RC LINING
New bridgeExisting bridge
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-26
8.5.5 Evaluation and Recommendations for Work to prevent the Bridge from collapsing
The end of the girder must be constructed in a way of preventing bridge from collapsing. The
following are options for such prevention works. In the case of the halving joints section C
plan will be recommended.
A plan: Steel brackets
Steel brackets are attached to the pedestal so as to ensure the foolproof length for
preventing the girder’s falling off the pedestal
B plan: Additional pedestal
Pedestal is extended so as to ensure the foolproof length for preventing the girder’s falling
off the pedestal
C plan: Fail-safe connection
Ends of the adjacent girders are connected by PC bars for preventing the girder’s falling
off the pedestal
Table 8.5.10 Prevention Work above the Substructure to prevent bridge collapse
◎ ◎ ◎
○ ○ ○
△ △ △
Legend: ◎excellent, ○good, △poor
△
Nomal Nomal
△Not good Not goodNot good
Nomal
Need scaffolding
△
△
△
Nomal ○
1.62○
○
Connect the ends of the adjacent girders byPC bars so as to prevent the girder's fallingoff if the end of the girder deviates from thepedestal
C plan: Fail-safe connection
Many
Evaluation
Image
Aesthetic appearance
Cost
Maintenance
Structure
Record of usage
Constructability
B plan: Additional pedestalA plan: Steel brackets
Attach the steel bracket to the pedestal so asto ensure the foolproof length of the end ofthe girder against the girder's falling off thepedestal
Extend the pedestal so as to ensure thefoolproof length of the end of the girderagainst the girders falling off the pedestal
Many Many
○◎
Need scaffolding
Nomal
Need scaffolding
Nomal
◎1.00 1.07
○
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-27
8.6 Meghna Bridge
8.6.1 Evaluation and Recommendations for Girder Design
The JICA study team assumed that the reduction in the number of expansion joints and
hinged shoes will increase the servicability of the existing bridges and reduce the maintenace
cost in the future. This can be achieved by connecting the simply supported girders into the
continuous girder at hinged sections. The computed results are shown in Figure 8.6.1.
Figure 8.6.1 Concept of Continuity in Meghna Bridge Girder
In order to reduce the number of expansion joints and hinges in the floor slab, the existing
cantilever box girder system is being planned to be continuous with a rigid frame at the
hinged sections. The lengths of the two continuous sections for Meghna Bridge are shown in
Figure 8.6.1. The lengths of the continuous sections is determined to meet the requirements
that the stress due to change of temperature shall be less than the stress generated from
horizontal earthquake excitation.
PC-continuous box girder (5.5-span) PC-continuous box girder (5.5-span)
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-28
In order to rehabilitate the central hinges of Meghna and Gumti bridges, the JICA Study
Team has considered three plans;
A plan: Entire change
B plan: Additional hinge
C plan: Partly change
Meghna bridge has one joint for this rehabilitation and the Gumti bridge has two joint for this
rehabilitation. Among the three plans, C plan is more preferable. This is due to the fact that it
is possible to manufacture and procure.
Table 8.6.1 Retrofitting by Center Hinge
Legend: ◎excellent, ○good, △poor
Image
Procurement
Evaluation
Impossible to manufacture Impossible to manufacture
◎△△
C plan: Partly changeB plan: Addition at hingeA plan: Entire change
Possible to manufacture
All change
Change
Additional
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-29
8.6.2 Evaluation and Recommendations for Pier Design
In order to assess the state of strength of the bridge pier, pier P8 is analyzed with the seismic
loading specified in the original and current design standards. From the computed results, it
can be seen that pier P8 does not meet the requirements for its resistance capacity. This state
of strength is similar to Kanchpur Bridge. Therefore, the Meghna Bridge pier will lose its
resistance capacity when subjected to strong earthquake excitation.
Table 8.6.2 Strength Check for Pier P8
Moment kNm 140042 97856 OUT
Shear kN 12691 9923 OUT0.170.6
Longitudinaldirection
UnitPeriodic
time
Spectralaccelerationcoefficient
Demand Capacity Check
750
5000
750
1500
3200
1500
1500
2X4000
=8000
11000
1500
2X4000
=8000
11000
11200
2@4000=8000
2150
1600
24653
27153
2000
200100
1600
CAST-IN-SITU R.C.PILEΦ1,5m,LENGTH:41m
500
6700 21505800
1200
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-30
Similar to Kanchpur Bridge, three of four plans are also considered for retrofitting of Meghna
Bridge pier.
A-plan: RC-lining
B-plan: Steel plate lining
C-Plan: Polymer mortar lining
A comparative study of the three plans with their construction cost is shown in Table 8.6.3.
From this comparison, the JICA study team recommends that the A-plan (RC-lining) is most
preferable for seismic retrofitting of the existing Meghna Bridge piers. This is due to the least
construction cost.
Table 8.6.3 Retrofitting by Pier
Record of usage ◎ ○ △
◎ ◎ ◎
Painting ◎ △ ◎
◎ ◎ ◎
Legend: ◎excellent, ○good, △poor
◎Effect on acquaticenvironment
Good ◎ Good
△◎◎Extre provisionNo need protection from heavierfloating bodies
Need protection from heavier floatingbodies
No need protection from heavierfloating bodies
Easy ◎ ◎
△
C plan: Polymer mortar lining
Difficult △
Inspection
B plan: Steel sheet liningA plan: RC lining
Structual performance
Need cofferdam
Evaluation
Cost △
Constructability
Maintenance
No need
Easy
Good Good
Construction
Construction period
△△◎
○◎
Need cofferdam
Easy
Need cofferdam
LongLong ◎△
◎◎ △ EasyDifficult
Image
Landscape
No needNeed
Many Not so many Few
Short
1.00 1.84 2.34
Good
◎ Good
24653
500
5000
5800
750 750
6500276 276
5000750276
867 5318
3200
250
250
750 276
867
Anchor
250
Existing pier
100 150
A-A
a partA A
a
250
100 150
276
mortar t=30mm
8
24653
500
5000
5800
750 750
650042 42
500075042
768 5048
3200
38
38
750 42
768
A-A
A A
a
30
42
Anchor
38
Existing pier
30 8
Steel
Less-shrinkage
Concrete
a part
Existing pier
24653
500
5000
5800
750 750
6500276 276
500075087
787 5100
3200
79
79
750 87
787
A-A
A A
a
79
87
Anchor
79
a part
79
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-31
8.6.3 Evaluation and Recommendations for Foundation Design
Following a method similar to that stated above for Kanchpur Bridge, the capacity of the
Meghna Bridge foundations is verified under load specifications by current design standards.
The current design specification considers the seismic force as per BNBC along with the
higher scouring level that is expected. The decision is similar to Kanchpur Bridge. The
capacity of the foundation corresponding to pier P8 does not meet the requirements and
requires retrofitting /additional reinforcement.
Table 8.6.4 Strength Check for Foundation of Pier P8
Similarly, two retrofitting plans are also considered for Meghna Bridge foundation.
A-plan: Steel Pipe Sheet Pile
B-plan: Additional RC-Pile
mm 65 15 OUT
Max kN 29149 26733 OUT
Min kN -21582 -21432 OUT
Moment Mmax kNm 71482 1920 OUT
mm 27 15 OUT
Max kN 16862 26733 OK
Min kN -6136 -21432 OK
Moment Mmax kNm 29740 1920 OUT
Longitudinal direction
Displacement
0.8 0.27
Axial force 0.330.6
Displacement
Transverse direction
Axial force
Capacity CheckUnitPeriodic
time
Spectralaccelerationcoefficient
Demand
3200
6500
11000
2@4000=8000
11000
2@4000=8000
11000
2@4000=8000
2150
▽RL-9.500
▽RL+5.00
24650
27150
2000
1500
1500
CAST-IN-SITU R.C.PILE
Φ1,5m,LENGTH:48m
500
5000
2250
5800
11910
750 750
6500
▽RL-33.00 Design scouring depth
Ds2
As
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-32
A comparative study of the two alternative plans highlighting with their construction cost and
scouring effect on the river bed was carried out as already seen in Table 7.3.1. From this
comparison, the JICA study team recommends that the A-plan (Steel Pipe Sheet Pile) is the
most preferable option for retrofitting of the existing Meghna Bridge pier foundations. This is
due to the least construction cost and small scouring effect on the river bed.
The comparison shown in Table 7.3.1 as described above was for the severe scouring zone.
In the cases of the shallow and medium scouring zones results of the comparison are as
shown in Table 8.6.5 and Table 8.6.6 Retrofitting the foundation, respectively. The piled
foundation is advantageous in the shallow scouring zone.
Table 8.6.5 Retrofitting the foundation
1.00 0.66
Plan A: SPSP Plan B: RC pile
Small
Image
Evaluation ◎
Cost
Cofferdam Not required SP
Foundation size Small
1500
800
3950
17750
2.0%2.0%
23100
517
1000 13600 10001075 1075
S.H.W.L ▽RL+5.05
H.H.W.L ▽RL+6.31
3846
Existing bridgeNew bridge
2250 6500 2250
15600
14600
Ac
Dc
Ds2
▽RL+20.965
As
Scouring ▽RL-4.60
22043
6500
1475
CAST-IN-SITU RC PILEφ1500 L=44.00m n=9
3993011550
41950
Supporting layer
3000
1500
500
Steel pipe sheet pile
L=57.00m n=88
φ1000 SKY490 t=16mm
(Navigation clearance n=20)
2500
1500
▽RL-11.00
11550
500
500
74875368
Design level
57000
9200
11000
2@4000=80001500
▽RL-9.500
7505000750
3700
14600
3000
250
3725
7297
24956 74877487
14974
9200
6978
1987
1987
(Existing bridge width)
39930
11000
11000
Steel pipe sheet pile
φ1000 L=57.00m n=88
SKY490 t=16mm
Navigation clearance
n=20
9200
11000
2@4000=80001500
▽RL-9.500
1500
800
3950
17750
2.0%2.0%
23100
517
1000 13600 10001075 1075
S.H.W.L ▽RL+5.05
H.H.W.L ▽RL+6.31
3846
Existing bridgeNew bridge
2250 6500 2250
15600
50014600
Ac
Dc
Ds2
▽RL+20.965
As
Scouring ▽RL-4.60
43900
22043
6500
2500
1500
▽RL-11.00
500
11550
11550
3000
1500
Supporting layer
1475
CAST-IN-SITU RC PILE
φ1500 L=44.00m n=9
CAST-IN-SITU RC PILEφ1500 L=44.00m n=12
27575
Design level
2700
7505000750
3000
372514600500 2250
250
7300 7300 3725 3250 3250 2250
5987 8288
13788 13788
1500
4000
4000
1500
11000
500
7800
2@4000=8000
27575
1500 3@4200=12600 1500
1100016575
3975
5500
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-33
Table 8.6.6 Retrofitting the foundation
Evaluation ◎
Cost 1.00 1.07
Foundation size Small Large
Image
Plan A: SPSP Plan B: RC pile
Cofferdam Not required SP
11000
2@4000=80001500
▽RL-9.500
1500
800
650
17750
2.0%2.0%
468
1000 13600 10001075 1075
H.H.W.L ▽RL+6.31
3846
Existing bridgeNew bridge
2250 6500 2250
15600
5343 14600
Ac
Dc
Ds2
▽RL+28.316
As
2919430500
2700
1500
▽RL-11.00
11550
300
Protected height 5400
Scouring ▽RL-14.90
11550
35550
Supporting layer
3000
1500
1475
39930
7512
CAST-IN-SIUT RC PILE
φ1500 L=43.00m n=9
S.H.W.L ▽RL+5.05500
500
φ1000 SKY490 t=16mm
6500
(Navigation clearance n=20)
56000
9200
11000
2@4000=80001500
▽RL-9.500
2700
1500
800
1500
17750
2.0%2.0%
468
1000 13600 10001075 1075
S.H.W.L ▽RL+5.05
H.H.W.L ▽RL+6.31
3846
Existing bridgeNew bridge
2250 6500 2250
▽RL-11.00
15600
14600
Protected height 5400
Ac
Dc
Ds2
▽RL+28.316
As
River bed
Scouring ▽RL-14.90
11050
37500
30000
Supporting layer
29194
11050
33500
800
3500
1500
37502675 1475
CAST=IN-SIUT RC PILE
φ1500 L=43.00m n=9
6500
CAST=IN-SIUT RC PILEφ1500 L=43.00m n=36
Steel pipe sheet pile
L=56.00m n=88
9200
7505000750
3700
14600
3000
250
3725
7297
24956 74877487
14974
9200
6978
1987
1987
(Existing bridge width)
39930
11000
11000
Steel pipe sheet pile
φ1000 L=56.00m n=88
SKY490 t=16mm
Navigation clearance
n=20
7505000750
3700
14600
3000
2@4000=8000 3750
33500
3750
250
2675 3725
2675 7300 3449 3526 57247300 3526
1500 5@3750=18750 1500
6775 7500
16750 16750
6000
9975 9250
1500
3750
4000
4000
3750
18500
1500
11000
3750
11000 375018750
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-34
8.6.4 Evaluation and Recommendations for Work to prevent Bridge collapse
The work to prevent bridge collapse that was already explained for Kanchpur Bridge in
subsection 8.5.5 will also be used for Meghna Bridge.
8.7 Gumti Bridge
8.7.1 Evaluation and Recommendations for Girder Design
Similar to Meghna Bridge, the number of expansion joints and hinged shoes will be
decreased in order to increase the serviceability of the existing bridges and reduce the
maintenance cost in the future. This can be achieved by connecting the simply supported
girders to become a continuous girder at the hinged sections. The computed results are shown
in Figure 8.7.1
Figure 8.7.1 Concept of Continuity in Gumti Bridge Girder
The concept to determine the length of the continuous section of Gumti Bridge is the same as
that used for Meghna Bridge. The existing cantilever system will be rehabilitated and
converted into three continuous box sections so that the number of expansion joints and
hinged shoes will be decreased and thereby increase its serviceability. The lengths of the
three continuous sections for Gumti Bridge are shown in Figure 8.7.1.
PC-continuous box girder (5.5-span) PC-continuous box girder (5.5-span)PC-continuous box girder (6-span)
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-35
Meghna bridge has one joint for this rehabilitation and the Gumti bridge has two joint for this
rehabilitation.
Table 8.7.1 Retrofitting Center Hinge
Legend: ◎excellent, ○good, △poor
A plan: Entire change B plan: Addition at hinge C plan: Partly change
Image
Procurement Impossible to manufacture Impossible to manufacture Possible to manufacture
Evaluation △ △ ◎
All change
Change
AdditionaAll change
Change
Additional
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-36
8.7.2 Evaluation and Recommendations for Pier Design
In order to assess the state of the strength of the bridge piers, pier P6 is analyzed with the
seismic loading specified in the original and current design standards. From the computed
results, it can be seen that pier P6 does not meet the requirements for its resistance capacity.
This state of strength is similar to Kanchpur and Meghna Bridges. Therefore, the Gumti
Bridge piers will lose their resistance capacity when subjected to strong earthquake excitation.
Table 8.7.2 Strength Check for Pier P6
Moment kNm 140042 98221 OUT
Shear kN 12691 8587 OUT
Demand Capacity Check
0.170.6Longitudinal
direction
UnitPeriodic
time
Spectralaccelerationcoefficient
2800
▽S W WL RL+5.250
1000
5800
7000
2800
20361
1500
2500
φ1.5m N=8, L=66.0mCAST IN SITU RC PILE
▽RL-10.00
1000▽RL+14.361
1500
1000
12361
10500
2@3750=7500
?4900
10500
3750 3750
10500
1500 1500
4900
▽RL+20.283
7200
9200
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-37
Similar to Meghna Bridge, three plans are also considered for retrofitting of Gumti Bridge
piers.
A-plan: RC-lining
B-plan: Steel plate lining
C-Plan: Polymer mortar lining
A comparative study among the three plans with their construction cost is shown in Table
8.7.3. From this comparison, the JICA study team recommends that the A-plan (RC-lining) is
the most preferable for seismic retrofitting of existing Meghna Bridge piers. This is due to the
least construction cost, which is the same reason considered for Meghna Bridge.
Table 8.7.3 Retrofitting Piers
Record of usage ◎ ○ △
◎ ◎ ◎
Painting ◎ △ ◎
◎ ◎ ◎
Legend: ◎excellent, ○good, △poor
◎Effect on acquaticenvironment
Good ◎ Good
△◎◎Extre provisionNo need protection from heavier floatingbodies
NeedNo need
Easy ◎ ◎
△
C plan: polymer mortar casting reinforcement
Difficult △
Inspection
B plan: Steel casting reinforcementA plan: RC casting reinforcement
Structural performance
Need cofferdam
Evaluation
Cost △
Constructability
Maintenance
No need
Easy
Good Good
Construction
Construction period
△△◎
○◎
Need cofferdam
Easy
Need cofferdam
LongLong ◎△
◎◎ △ EasyDifficult
Image
Landscape
No needNeed
Many Not so many Few
Short
1.00 2.04 2.43
Good
◎ Good
4900
5800
20361
1000
19361
250 250
4900250 250
Anchor
250
Existing pier
250
100150
100 150
A A
A-A
a part
a
39
Existing pier
39
309
30 99 30 94900
5800
20361
1000
19361
30
490039 39
Anchor
A A
a
A-A
a part
Steel
Less-shrinkage
Concrete
mortar t=30mm
4900
5800
20361
1000
19361
82 82
490082 82
Anchor
82
Existing pier
82A A
A-A
a part
a
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-38
8.7.3 Evaluation and Recommendations for Foundation Design
Following a method similar to that stated above for Kanchpur and Meghna Bridges, the
capacity of Gumti Bridge foundations is verified under load specifications in the current
design standards. The current design specifications consider the seismic force as per BNBC
along with the higher scouring level that is expected. The computed result shows a similar
tendency that has been verified for Kanchpur and Meghna Bridges. The capacity of the
foundation corresponding to pier P6 does not meet the demand requirements and requires
retrofitting /additional reinforcement.
Table 8.7.4 Strength Check for Foundation of Pier P6
Similarly, two retrofitting plans are also considered for Meghna Bridge foundation.
A-plan: Steel Pipe Sheet Pile
B-plan: Additional RC-Pile
mm 53 15 OUT
Max kN 24327 43479 OK
Min kN -15814 -38177 OK
Moment Mmax kNm 40441 8400 OUT
mm 22 15 OUT
Max kN 15256 43479 OK
Min kN -3438 -38177 OK
Moment Mmax kNm 16826 4130 OUT
Demand
Displacement
Capacity CheckUnit
Longitudinal direction
Axial force
Naturalperiods
Spectralaccelerationcoefficient
0.6 0.33
Displacement
0.270.8
Transverse direction
Axial force
10500
2@3750=7500
2@3750=7500
Φ4900
10500
37503750
10500
15001500
Φ4900
9200
2800
▽S W WL RL+5.250
5800
7000
2800
20360
1500
2500
φ1.5m N=8, L=66.0m
CAST IN SITU RC PILE
1000
12360
11914
▽RL-20.00 Design scouring depth
▽RL-8.500
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-39
A comparative study of the two alternative plans highlighting their construction cost and
scouring effect on the river bed is shown in Table 8.7.5. From this comparison, the JICA
study team recommends that the A-plan (Steel Pipe Sheet Pile) is the most preferable option
for retrofitting of existing Gumti Bridge pier foundation. This is due to the least construction
cost and small scouring effect on the river bed.
Table 8.7.5 Retrofitting the Foundations
Image
B plan: Additonal RC pileA plan: Steel pipe sheet pile
◎
1.481.00
Cofferdam
Foudation size Large
SP
Small
Not required
Evaluation
Cost
φ1.5m N=8, L=66.0m
CAST IN SITU RC PILE
▽RL-10.00
▽RL+14.361
▽RL-8.500
5922
20400
15600
4000
S.H.W.L ▽RL+5.14
▽RL-72.10
800 17750
Φ4900
9200
2800
5800
7000
2800
20360
1000
12360
Clearance 8220
9640
Projected length 85504000
PIERP6
New BridgeExisting Bridge
▽RL-17.05 Design scouring depth
56350
1500 3750 3750 1500
10500
11910
φ1.5m N=54, L=65.0m
CAST IN SITU RC PILE
4900 4525 14600
7500 6775
6550 2425
2500
33000
9@5000=300001500
25500
1500
6@3750=22500
1500
1500
φ1.5m N=8, L=66.0m
CAST IN SITU RC PILE
▽RL-10.00
▽RL+14.361
▽RL-8.500
5922
21400
15600
3000
S.H.W.L ▽RL+5.14
▽RL-72.10
▽RL-5.50
800 17750
Φ4900
9200
2800
5800
7000
2800
20360
1000
12360
Clearance 8220
10640
Projected length 8550
3000
PIERP6
New BridgeExisting Bridge
▽RL-17.05 Design scouring depth
50450
1500 3750 3750 1500
10500
11910
14600
7300
249607490 7490
14970
9200
6980
39930
10500
10500
C L
2500
Φ4900
φ1000 L=73.5mSteel pipe sheet pile
Clearance
Existing Bridge New Bridge
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-40
8.7.4 Evaluation and Recommendations for Work to Prevent Bridge Collapse
The work to prevent bridge collapse that was already explained for Kanchpur Bridge in
subsection 8.5.5 will also be used for Gumti Bridge.
8.8 Consideration of Damages on Meghna Bridge and Gumti Bridges
8.8.1 General
Meghna Bridge and Gumti Bridge are multi span continuous prestressed concrete rigid frame
bridges having, in the middle of each span between piers, hinges and expansion joints where
no bending moments occur. The hinges are fixed in the vertical direction to transmit the
shearing forces between the cantilevers projecting from the piers whereas they are free in the
horizontal direction to eliminate restraint forces due to creep, shrinkage and temperature
change in the structures and thus greatly reduce the sizes of the substructures / foundations.
8.8.2 What Happened to the Hinges and Expansion Joints
(1) Damages to the hinges
It has been observed that the hinges lost their proper function to transmit the shearing forces
between the cantilevers projecting from the piers, generating noises and unfavorable impact
forces on the expansion joints when vehicles move from one cantilever to the other cantilever.
Recent investigations showed the deteriorated rubber plates in the hinges as below.
Rubber plate (Originally 20 mm thick)
Damaged rubber plate (Thickness 0 to 8 mm)
Damaged rubber plate (Plan view)
Figure 8.8.1 Deterioration in Hinges
(2) Damages to the expansion joints
As shown on the right in Figure 8.8.1 the expansion joints also deteriorated as a result of
unfavorable impact forces acting frequently on them caused by the loss of proper function of
the hinges.
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-41
Plane touch type
Line touch type
Figure 8.8.2 Deterioration in Expansion Joints
8.8.3 Possible Causes of the Damages
(1) Possible causes of the damages to the hinges
Historically, the common types of hinges used to be the line touch type shown in Figure 8.8.3.
As this type is vulnerable to abrasion from the steel components in the contact points due to
the horizontal movement, there were many cases where the line touch type was replaced by
the plane touch type shown in Figure 8.8.3 as the repair works.
Conceptual drawing of the hinge Mechanism of the hinge
Figure 8.8.3 Types of Hinges
Stainless steel plate
R i
Movement
Tightly contained rubber Bearing
Movement
Rotation
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-42
As can be seen in the figure, the plane touch type has improved resistance to abrasion due to
horizontal movement. On the other hand, it should be noted that the plane touch type may
have less capacity to accommodate the rotation than the line touch type.
When used for the repair works of an existing bridge where the creep deflection has finished
and the rotation of the hinge will be relatively small because it is generated mainly by the live
loads, adopting the plane touch type will cause no major problems due to the rotation.
In the case of a newly constructed bridge, however, a pre-camber is prescribed in the girder to
accommodate the creep deflection and as a result of it a considerable amount of rotation will
be generated between at the time of completion and at the time of reaching the permanent
condition―the creep is finished. See Figure 8.8.4.
Pre-camber = creep deflection = profile at the time of closure – planned permanent profile
Figure 8.8.4 Creep Deflection of the Bridge Girders
Meghna Bridge and Gumti Bridge adopted the plane touch type of hinges as shown in Figure
8.8.5. There could have been a possibility that the rubber plates in the hinges had a distorted
deformation due to the rotation caused by the creep deflection with an amount exceeding the
planned value, since the actual magnitude of the creep could have been larger than the
planned depending on various conditions such as not only the actual mix proportion and
characteristics of the materials used for the concrete but also the climate or environmental
conditions. If that was the case then the rubber plates which had already been stressed some
amount could have been excessively stressed when they were subjected to the live loading
effects.
Figure 8.8.5 Hinge of Gumti Bridge
According to the current observations, strict control of the axle load of the trucks, with a limit
of 20 tons, has just recently become effective at the entrance to the toll gate of Meghna
Precamber Profile at the time of closure
Planned permanent profile
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
8-43
Bridge. It was observed before then that a number of trucks with remodeled suspension and
tires which appeared to carry an axle load well over 20 tons, namely 30 or even 40 tons were
passing over the roads and bridges.
In this way Meghna Bridge and Gumti Bridge have been often occupied by trucks heavily
overloaded in comparison with the design truck so as to further increase the excessive
stresses in the rubber plates.
Consequently, complex factors as described above may have hastened deterioration of the
rubber plates in the hinges, gaps between the female (concaved) parts and the male (convex)
parts having been formed accordingly.
(2) Possible causes of the damages in the expansion joints
Following the above consideration, it can be said that;
Once a gap was formed in the hinges, unfavorable impact forces were generated when
the vehicles move from one cantilever to the other cantilever over an expansion joint,
which would be rapidly deteriorated, since such impact forces were considerably larger
than the forces envisaged in the design.
The heavily overloaded trucks further increased the unfavorable impact forces, which
again further deteriorated the expansion joints.
The type of the expansion joint adopted, consisting of steel and rubber, would have
been appropriate if the gap in the hinge was not formed and the trucks moving over it
were not overloaded. But in the case of a gap having been formed for reasons described
above, this type would be much more vulnerable than a type like the steel finger joint.
In addition, it can be said that inappropriate maintenance, which might have not been done in
a timely manner, spurred the deterioration of the expansion joints. It looks from the
observation of the image on the right that the fixing bolts, crucial components, might have
not been adequately taken care of.
8.8.4 Conclusions
(1) Possible causes of the damages to the hinges and expansion joints
It can be said that the damages to the hinges and expansion joints on Meghna Bridge and
Gumti Bridge have been caused by;
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
8-44
Creep deflection of the girder which may have been unexpectedly larger than the
planned,
Heavily overloaded trucks,
Inappropriate maintenance, which might not have been done in a timely manner.
(2) Appropriateness of the design and construction
As described in Figure 8.8.4 the adoption of a structural system with the hinges in the mid
span eliminated restraint forces due to creep, shrinkage and temperature change in the
structures and thus greatly reduced the sizes of the substructures / foundations. Adoption of
the continuous girder with sliding bearings on the piers to eliminate the restraint forces would
have greatly increased the cost because of the expensive bearings. Adoption of the continuous
girders with neither the mid span hinges nor the sliding bearings on the piers would have also
increased the cost because of the increased substructures / foundations due to the restraint
forces. Consequently it can be said the design was the most appropriate at the time.
From the viewpoint of constructability, there have been no particular observations showing
any sign of faulty construction.
CHAPTER 9
OUTLINE OF THE DESIGN
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-1
9. OUTLINE OF THE DESIGN
9.1 Road
9.1.1 Geometric Design
(1) Design Principles
The following design principles were considered for setting alignment.
Compliance with the required parameters of the adopted design speed
Balancing the size and length of curves
Balancing the horizontal, vertical and cross-sectional parameters
Method of construction
Constraints due to natural conditions such as terrain, geological features and existing
property
The horizontal alignment is finalized considering mobility, safety and comfort which are
derived from balanced design parameters. In addition to the above, the following conditions
are taken into account for the vertical alignment design.
Start point and end point of the horizontal alignment follow the existing NH-1 center
line.
New alignment is next to and parallel to the existing road and bridges, therefore, the
new vertical alignment is set to almost the same level as the existing to secure adequate
navigation clearance under the bridge section.
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-2
(2) Geometric Design Outline
The application of the design parameters are shown in Table 9.1.1.
Table 9.1.1 Geometric Design Outline
Parameters Unit Applied Kanchpur Meghna Gumti
Length m
STA 0+0.0 -
STA 1+100.0 Road L=703,5
(Bridge L=396.5 m)
STA 0+0.0 -
STA 1+800.0 Road L=870
(Bridge L=930.0 m)
STA 0+0.0 -
STA 2+420.0 Road L=1010.0
(Bridge L=1410.0 m) Maximum Slope Height
m 12.6 10.5 6.3
Design Speed km/h 80 80
Lane Width m 3.65 3.65
Outer Shoulder m 1.8 1.8
Inner Shoulder m 0.3 0.3
Cross fall of Travel Way
% 3.0 3.0
Maximum Super Elevation
% 7.0 7.0 7.0 7.0
Minimum R. of Horizontal Curve
m 250 340 390 350
Maximum Gradients
% 5.0 4.5 3.0 3.0
Minimum Vertical Curve K Value
m 35 37 35 74
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-3
9.1.2 Pavement Design
(1) Introduction
Pavement design is carried out based on the consideration of the constraints of the three
bridge sites.
(2) Equivalent Single Axle Load (ESAL) Calculations
For pavement design, all heavy commercial vehicles are expressed in the terms of the
equivalent number of standard axles that they represent. 8,160 kg is taken for a standard axle.
Based on axle load studies previously undertaken in Bangladesh, the following equivalence
factors have been determined.
Table 9.1.2 Vehicle Equivalent Factor
The cumulative ESAL for design is calculated using the following equation;
ESAL = Traffic volume of vehicle type for 20 years x DDF x LDF x VEF
DDF: Directional Distribution Factor = 0.5
LDF: Lane Distribution Factor = 0.7 for 3-lanes, 0.6 for 4-lanes
VEF: Vehicle Equivalent Factor
Table 9.1.3 Summary of ESAL
Section 10 years (million)
20 years (million)
Kanchpur site 102 207
Meghna, Gumti site 97 229
(3) Flexible Pavement Design
Flexible Pavement Design is carried out by two methods namely;
Vehicle Category Equivalence Factor
Large Truck 4.8
Medium Truck 4.62
Small Truck 1.0
Large Bus 1.0
Mini Bus 0.5
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-4
AASHTO Guide for the Design of Pavement Structures
RHD’s Pavement Design Manual
(4) AASHTO Design Method
The AASHTO method for the design of pavement structure is based on the consideration that
a pavement life is a function of;
Traffic loading
Pavement strength
Pavement serviceability
Sub-grade strength
The relationship between the above factors can be mathematically represented as;
Log ESAL = Z.S. + f1 (SN) – 0.20 + f (P0 – P1) / f2 (SN) + f (MR)
Where
ESAL: Cumulative Equivalent Single Axle Loads
Z.S.: Adjustment factor to offset unreliability of traffic volumes and serviceability
SN: Structural Number
P0: Initial Serviceability
P1: terminal serviceability
MR: resilient modulus of sub-grade
SN: a1D1 + a2D2m2 + a3D3m3
a: layer coefficient
D: layer thickness in inches
m: drainage coefficient of base and sub-base
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-5
The structural number (SN) is represented by the sum total of the multiplication of the layer
coefficient, the thickness in inches, and drainage coefficient of each layer in the pavement
structure.
The AASHTO equation can be solved by mean of a nomograph include in the AASHTO
Guide for Design of Pavement method that involves certain input variables, which are as
follows;
Traffic or Cumulative Equivalent Single Loads (ESAL)
Reliability (R)
Standard Deviation (S0)
Resilient Modulus of Subgrade (MR)
△Loss in Serviceability ( PSI)
Structural Layer Coefficients
1) Design Life
Design life is the number of years reckoned from the completion of pavement construction
and application of traffic load until the time when major maintenance is required so that it can
continue to carry traffic satisfactorily for a further period. A design life of 20 years is adopted
for this project and is recommended in general as per Pavement Design Guide (RHD). For
comparison of design life between 20 years and 10 years refer to Appendix 8.
2) Design CBR
A CBR value of 5 % is recommended in general as per the Pavement Design Guide (RHD).
The CBR values at the site surveyed range from 4 to 8 and the average CBR at the site is
beyond 5 %.
The soil parameter used in the AASHTO Guide for Pavement Design is the Modulus of
Resilience (MR). Therefore the design CBR needs to be converted into the corresponding MR
value. There is a widely used correlation for CBR and MR up to 10. The correlation is below.
MR=1500*CBR
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-6
3) Thickness Design
Design Parameters
20 years ESAL = 229 Million
Modulus of Resilience (MR) = 12000 Psi
Reliability (R) = 95 %
Standard Deviation (So) = 0.45
Initial Serviceability Index (Po) = 4.2
Terminal Serviceability Index (Pt) = 2.5
Design Thickness
Bituminous Wearing Course 5 cm
Bituminous Binder Course 20 cm
Aggregate Base Course 35 cm
Aggregate Subbase 40 cm
For detailed calculations, refer to Appendix 8.
(5) RHD Design Manual
The subject design guide is a simplified version of various international standards with due
modifications keeping in view local conditions and practices. The thickness design shown in
the table provides variable thicknesses of bituminous pavement, base and subbase for discrete
ranges of ESAL from 3-4 million to 60-80 million. The target ESAL is beyond the range of
ESAL value in the RHD Design Manual, therefore pavement thickness is adopted from the
AASHTO Design Method.
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-7
9.1.3 D
rawing
Figure 9.1.1 Plan and Typical Cross Section at Kanchpur
Project area L=1100m
Approach Road L=327.0m Approach Road L=376.5m Bridge L=396.5m
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-8
Figure 9.1.2 Plan and Typical Cross Section at Meghna
Project area L=1800m
Approach Road L=438m Bridge L=930.0m Approach Road L=m432.0
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-9
Figure 9.1.3 Plan and Typical Cross Section at Gumti
Project area L=2420m
Approach Road L=695.0m Bridge L=1410.0m
Approach Road L=315.0m
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-10
9.2 The 2nd Bridges
As per the clarification letter No.35.033.014.00.00.007.2012 -161 issued by Ministry of
Communication (MoC) of Bangladesh on 13th August 2012, the type of the 2nd Bridges would
be ‘Steel Narrow Box Girder Bridge’. The reason behind this bridge type selection is its
relatively least construction cost, least construction period and constructability. The Steel box
girders have been chosen for the superstructure of the 2nd bridges; therefore the span for the
2nd Kanchpur Bridge will be larger than that of the existing one. But, for the 2nd Meghna and
2nd Gumti Bridges, the span allocation is kept the same as the existing one. This is because
the same span allocation will ensure the same number of foundations for the 2nd and existing
bridges. Therefore, it will be easier to unify the new foundations with the adjacent existing
foundations, which will secure the least construction cost and minimize the scouring in the
riverbed.
(1) Superstructure design
For the superstructure, steel narrow box girders is chosen in order to reduce the
superstructure weight and increase the earthquake resistance capacity of the bridges.
(2) Foundation design
In order to determine the foundation type for the 2nd bridges, the following factors are taken
into consideration.
-Design scouring level is revised in consideration of new research results and a river study.
-Cost factor
Cast-in-place RC pile foundation and Steel Pipe Sheet Pile (SPSP) foundation are taken into
consideration and they are compared with respect to the cost aspect. These factors are studied
for the respective 2nd Bridges and the computed results are shown in the following sections.
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-11
9.2.1 The 2nd Kanchpur Bridge
(1) Design Scouring Level
Using the bathymetric survey results, the scouring level along the river cross-section at the
bridge center line is estimated and graphically shown as blue line in Figure 9.2.1. This figure
also shows the design scouring level at each respective pier. The design scouring levels (red
line) are categorized as follows;
Shallow scouring: RL= - 1.4m
Severe scouring: RL= - 18.0 m
It can be observed that piers P1, P2 and P3 are located in shallow scouring zones (RL=-1.4m),
whereas piers P4, P5 and P6 are located in severe scouring zones (RL=-18.0m). The
foundation type for each pier is examined in accordance with the design local scouring level.
Design Scouring Level
Estimated Scouring Level
RL=-1.39m RL=-18.01m
P1 P3 P5 P6 P7P2 P4
Figure 9.2.1 Riverbed Scouring and Design Scouring Level for the 2nd Kanchpur Bridge
(2) Foundation type selection
It can be seen from Figure 9.2.1 that the foundations of piers P4, P5 and P6 of 2nd and the
existing bridges are located in severe scouring zones. A cast-in-place RC pile foundation and
Steel Pipe Sheet Pile (SPSP) foundation are examined considering the severe scouring level
(RL=-18.0m) parameter and then, their construction cost is compared as already seen in
Table 8.5.9. It can be found that the construction of SPSP foundation in a severe scouring
zone is cost effective. Moreover, implementing SPSP technology is a countermeasure to
scouring.
It is also decided that the foundations for piers P1, P2 and P3, which are located in areas with
shallow riverbed scouring should also be SPSP type. This is just to maintain conformity with
the existing caisson foundation that needs to be retrofitted. Therefore, for the 2nd Kanchpur
Bridge, the foundation of piers P1-to-P6 will be the SPSP type and their foundations will be
unified with those of the adjacent existing foundations. On the other hand, the foundation of
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-12
pier P7 only will be a cast-in-place RC pile type which is designed as a single type
foundation that means that there will be no interference with the existing foundation.
(3) Results of the Study
The general outline of the design is summarized in Table 9.2.1. Consequently, the general
view of the 2nd Kanchpur Bridge is schematically shown in Figure 9.2.2.
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-13
Table 9.2.1 Outline of Design (The 2nd Kanchpur Bridge)
Bridge type Continuous steel narrow box girder
Configuration of bridge superstructure
Bridge length = 396.5 m Girder length = 396.0m Span = 41.6 m + 85.4 m + 97.6 m + 73.2 m + 54.9 m + 41.6 m
Number of lanes 4-lanes
Cross section
18.4 m (1.1 m (sidewalk ) + 14.6 m (road) + 2.7 m (sidewalk))
18400
CL
7300 500 2000 2001100 7300
2700 6500 6500 2700
2.0%1.0%
100
3300
1200
250
80
Superstructure 3-box girders (1.2 m x 3.3 m) with PC floor slab (t=25 cm)
Abutment Inverted T-type
Number: 2 Height: 7.5 m
Piers Columnar type
Number: 5 Height: 10.64 m - 15.55 m
Abutment Cast-in-place RC pile (φ1.5 m): A1&A2; n=6, L=36.0 m
Cast-in-place RC pile (φ1.5 m): P7; n=8, L=18.0 m
Bridge components Substructure
Foundation Piers
SPSP (φ1.0 m) P1 to P5; max 34.94 m x 11.23 m (including existing)
min 33.7 m x 8.74 m (including existing) L = 33.0 m
Live load JRA B-type (only for floor slab system) AASHTO HS20-44 (for girder and substructure)
Seismic load 2/3
1.22.5sm
m
ZSC Z
T ; where Z=0.15 and S=1.5
Wind load 3.0 kN/m2
Loads
Thermal force Temperature range: +10 oc to +50 °c
Specification
Steel Grade-SM490A (JIS)
u = 490 MPa, y = 315 MPa
PC steel bar Grade-SWPR7BL (JIS)
u = 1,850 MPa, y = 1,600 MPa Superstructure
Concrete (Precast)
JIS
c = 50 MPa
Concrete (cast-in-place)
RHD
c = 25 MPa
Rebar Grade-60 (ASTM)
u : 620 MPa, y : 420 MPa
Construction materials
Substructure
SPSP
SKY400 and SKY490 (JIS)
u = 400 MPa and 490 MPa
y = 235 MPa and 315 MPa
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-14
Figure 9.2.2 General View of Kanchpur Bridge
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-15
Figure 9.2.3 CG of Completed the 2nd Kanchpur Bridge (Dhaka side)
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-16
9.2.2 The 2nd Meghna Bridge
(1) Design Scouring Level
Using the bathymetric survey results, the scouring level along the river cross-section is
estimated and graphically shown as blue line in Figure 9.2.4. This figure also shows the
design scouring level for each respective pier. The design scouring levels (red line) are
categorized as follows;
Shallow scouring : RL=-4.6 m
Medium scouring : RL=-14.90 m
Severe scouring : RL=-26.2 m
It can be observed that piers P1 and P2 are in shallow scouring zones (RL = -4.6 m), whereas
piers P3-P5 are in medium scouring zones (RL = -14.90) and P6-P11 are in severe scouring
(RL = -26.2 m) zones. The foundation type for each pier is examined in accordance with
these three categorized design scouring levels.
23
Design Scouring Level
Estimated Scouring Level
RL=-4.6m RL=-14.90m
RL=-26.19m
P1 P2 P3 P4 P5
P6 P7 P8 P9 P10P12
P11
Figure 9.2.4 Riverbed Scouring and Design Scouring Level for the 2nd Meghna Bridge
(2) Foundation type selection
1) In case of shallow scouring
The foundation of pier P2 (new bridge) is close and parallel to that of P2 (existing bridge).
Their foundations will be combined so as to secure the least construction cost. It is also
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-17
observed from Figure 9.2.4 that they are located in a shallow scouring zone. A cast-in-place
RC pile foundation and Steel Pipe Sheet Pile (SPSP) foundation are examined considering
the shallow scouring zone (RL = -4.6 m) and then, their construction costs are compared as
already seen in Table 8.6.5. The construction of cast-in-place RC pile foundation in a shallow
scouring zone is cost effective.
2) In case of medium and severe scouring
It can be observed from Figure 9.2.4 that the foundations of pier P5 (2nd and existing bridges)
are located in a medium scouring zone. A cast-in-place RC pile foundation and Steel Pipe
Sheet Pile (SPSP) foundation are also examined considering the medium scouring level
(RL=14.90 m) and then, their construction costs are compared as already seen in Table 8.6.6.
From this comparison, it can be seen that the construction of an SPSP foundation in a
medium scouring zone is cost effective. This is because no temporary cofferdam is required
to construct an SPSP foundation and thereby it secures the least construction cost.
The foundation selected for a medium scouring zone is the SPSP type, therefore, the
foundation for a severe scouring zone undoubtedly will be evaluated as an SPSP type.
Therefore, no additional comparison between the said foundations in severe scouring zones
needs to be shown.
(3) Remarks on foundation type
From the above results, it can be concluded that where the riverbed scouring level is medium
to severe, the SPSP type foundation will be economical and additionally it will act as a
scouring countermeasure. On the other hand, where the riverbed scouring level is shallow, a
cast-in-place RC pile foundation will be cost effective.
(4) Results of the Study
The general outline of the design and the obtained output results are summarized in Table
9.2.2. Consequently, the general view of the 2nd Meghna Bridge is schematically shown in
Figure 9.2.5.
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-18
Table 9.2.2 Outline of Design (The 2nd Meghna Bridge)
Bridge type Continuous steel narrow box girder
Configuration of bridge superstructure
Bridge length= 930.0 m Girder length= 929.1 m Span= 47.4 m [email protected] m + 73.5 m + 23.9 m
Number of lanes 4-lanes
Cross section
17.75 m (1.1 m (sidewalk) + 15.55 m (road) + 1.1 m (sidewalk))
17750
CL
11001100
2675 6200 6200 2675
100
3310
1200
240
65010950 3950
2.0% 2.0%
80
Superstructure 3-box girders (1.2 m x 3.31 m) with PC floor slab (t=24 cm)
Abutment Inverted T-type
Number: 2 Height: 8.0 m - 9.5 m
Pier Columnar type
Number: 11 Height: 9.9 m - 30.44 m
Abutment Cast-in-place RC pile (φ1.5 m): A1&A2; n=6, L=48.0 m
Cast-in-place RC pile (φ1.5 m): P1,P2&P12; n=6-12, L=35.0 m-44.0 m
Bridge components Substructure
Foundation Pier SPSP (φ1.0 m)
P3-P10; 39.93 m x 14.97 m (including existing) L = 42.65 - 44.15 m
Live load JRA B-type (only for floor slab system) AASHTO HS20-44 (for girder and substructure)
Seismic load 2/3
1.22.5sm
m
ZSC Z
T ; where Z=0.15 and S=1.5
Wind load 3.0 kN/m2
Loads
Thermal force Temperature range: +10 oc to +50 °c Specification
Steel Grade-SM490A (JIS)
u = 490 MPa, y = 315 MPa
PC steel bar Grade-SWPR7BL (JIS)
u = 1,850 MPa, y = 1,600 MPa Superstructure
Concrete (Precast)
JIS
c = 50 MPa
Concrete (cast-in-situ)
RHD
c = 25 MPa
Rebar Grade-60 (ASTM)
u : 620 MPa, y : 420 MPa
Construction Materials
Substructure
SPSP
SKY400 and SKY490 (JIS)
u = 400 MPa and 490 MPa
y = 235 MPa and 315 MPa
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-19
Figure 9.2.5 General V
iew of M
eghna Bridge
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-20
Figure 9.2.6 CG
of Com
pleted the 2nd M
eghna Bridge (C
hittagong side)
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-21
9.2.3 The 2nd Gumti Bridge
(1) Design Scouring Level
Using the bathymetric survey results, the scouring level along the river cross-section is
estimated and graphically shown as blue line in Figure 9.2.7. This figure also shows the
design scouring level (red line) for each respective pier. The design scouring levels are
categorized as follows;
Shallow scouring : RL= -0.7 mto -2.8 m
Severe scouring : RL= -17.1 m
It can be observed that the piers P1-P8 are in severe scouring zones (RL = -17.1 m), whereas
piers P9-P16 are located in shallow scouring zones (RL = -0.7 to -2.8 m). The foundation
type for each pier is examined in accordance with these two categorized scouring levels.
Design Scouring Level
Estimated Scouring Level
P1 P2 P3 P4 P5
P11 P12 P13 P14 P15 P16
P6 P7 P8 P9
P10
RL=-0.69m
RL=-17.05m
RL=-2.75m
Figure 9.2.7 Riverbed Scouring and Design Scouring Level for 2nd Gumti Bridge
(2) Foundation type selection
As is already stated for the 2nd Meghna Bridge, a combined cast-in-place RC pile foundation
will secure least construction cost where the riverbed scouring is shallow, whilst the
combined SPSP foundation is cost effective where the riverbed scouring is severe. The same
results are also observed for the 2nd Gumti Bridge. Therefore, it is decided that the
foundations for piers P1-P8 in severe scouring zones will be designed as SPSP foundations
and that for piers P9-P16 in shallow scouring zones will be designed as cast-in-place RC pile
foundation. The foundations of piers P1-to-P8 of the new bridge will be unified with that of
the corresponding existing pier. But, the remaining foundations will be single type
foundations and there will be no interference with the existing foundations.
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-22
(3) Results of the Study
The general outline of the design and the design outputs are summarized in Table 9.2.3.
Consequently, the general view of 2nd Gumti Bridge is schematically shown in Figure 9.2.8.
Table 9.2.3 Outline of Design (The 2nd Gumti Bridge)
Bridge type Continuous steel narrow box girder
Configuration of bridge superstructure
Bridge length = 1,410 m Girder length = 747.75 m + 660.75 m Span = 51.4 m + [email protected] m + 86.15 m, 86.15 m + [email protected] m + 51.4 m
Number of lanes 4-lanes
Cross section
17.75 m (1.1 m (sidewalk) +15.5 5m (road) + 1.1 m (sidewalk))
17750
CL
1100 1100
2675620062002675
100
3310
1200
240
650 109503950
2.0%2.0%
Superstructure 3-box girders (1.2 m x 3.31 m) with PC floor slab (t=24 cm)
Abutment Inverted T-type
Number: 2 Height: 7.5 m - 9.5 m
Pier Columnar type
Number: 16 Height: 9.6 m - 21.60 m
Abutment Cast-in-place RC pile (φ1.5 m): A1&A2; n=6, L=66.0-m Cast-in-place RC pile (φ1.5 m): P9-P16; n=8, L=62.0 m-
Bridge components Substructure
Foundation Pier SPSP (φ1.0 m)
P1-P8; 34.93 m x 14.97 m (including existing) L=62.0 m - 70.0 m
Live load JRA B-type (only for floor slab system) AASHTO HS20-44 (for girder and substructure)
Seismic load 2/3
1.22.5sm
m
ZSC Z
T ; where Z=0.15 and S=1.5
Wind load 3.0 kN/m2
Loads
Thermal force Temperature range: +10 oc to +50 °c Specification
Steel Grade-SM490A (JIS)
u = 490 MPa, y = 315 MPa
PC steel bar Grade-SWPR7BL (JIS)
u = 1,850 MPa, y = 1,600 MPa Superstructure
Concrete (Precast)
JIS
c = 50 MPa
Concrete (cast-in-situ)
RHD
c = 25 MPa
Rebar Grade-60 (ASTM)
u : 620 MPa, y : 420 MPa
Construction Materials
Substructure
SPSP
SKY400 and SKY490 (JIS)
u = 400 MPa and 490 MPa
y = 235 MPa and 315 MPa
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-23
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-24
Figure 9.2.8 General View of Gumti Bridge
TH
E K
AN
CH
PU
R, M
EG
HN
A, G
UM
TI 2N
D B
RID
GE
S C
ON
ST
RU
CT
ION
A
ND
EX
IST
ING
BR
IDG
ES
RE
HA
BILIT
AT
ION
PR
OJE
CT
F
inal Report
9-25
Figure 9.2.9 CG of Completed the 2nd Gumti Bridge (Dhaka side)
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-26
9.2.4 Bridge Accessories
As the bridges are planned as the steel structure, therefore the bridge accessories should be
considered as water proof at the design stage in order to avoid corrosion in the girders.
(1) Expansion joints
Table 9.2.4 Horizontal Movement of Expansion Joint
Bridge Horizontal movement Type
Kanchpur ±170 mm
Meghna ±400 mm
Gumti ±300 mm
Finger non-drainage type
The expansion joints should be designed as non-drainage type in order to avoid the water
leakage into the end of girder and also near the abutment. The water will be passed through
drainage system from the outside of the girder and from the water tight rubber drain under the
fingers.
The finger type is chosen from the view point of durability against heavy loading trucks. In
that case, the steel finger is more durable than the rubber top expansion joints.
(2) Water drain system
The road surface catchment should be located at the end of surface and the collected water
will directly drop to the river. The pipe end is set 1 m below the girder in order to avoid water
spray back to the girder.
Table 9.2.5 Drainage System (Direct Drop)
Item Material Remarks
Catchment drain Cast Steel Buried in the PC deck
pipe Vinyl chloride pipe
Pipe support Steel Directly fixed to the girder
(3) Bearing shoes
The bearing shoes are rubber bearings for the movement and seismic resistance. The
durability of rubber bearing is secured by a lapping layer over the rubber against ultraviolet
for 100 years. And the rust prevention for bearing accessories should be achieved by metallic
thermal spraying which is expected to be lasting as 100 years.
Table 9.2.6 Bearing Movement
Bridge Movement Maximum Reaction Force
Kanchpur ±170 mm 1250 t
Meghna ±400 mm 1150 t
Gumti ±300 mm 1300 t
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-27
(4) Inspection way
The inspection ways should be made of galvanized steel structure in order to inspect the piers
and the girders at some time intervals.
Type: Girder with railing
Size: Width 60 cm, railing height 120 cm
Material: Galvanized steel
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-28
9.3 Existing Bridges
9.3.1 General
The present conditions observed and investigated have been examined and the latest design
criteria to be conformed to have also been considered. As a result, the existing bridges,
Kanchpur Bridge, Meghna Bridge and Gumti Bridge have been determined to need to be
retrofitted and rehabilitated in the manner described as follows.
9.3.2 Scope of the Retrofitting and Rehabilitation Works
It has been determined that the scope of the rehabilitation works shall be defined as the repair
works for the damaged expansion joints in Kanchpur Bridge, Meghna Bridge and Gumti
Bridge and the repair works for the damaged hinges in Meghna Bridge and Gumti Bridge.
The retrofitting works shall be defined as the works to renew the bridge structures to conform
to the current bridge design standards and to cope with the current and future scouring
conditions. As mentioned in the previous chapter the changes of the design seismic force
should be reflected in all the bridges and the changes of the live load should be reflected in
Kanchpur Bridge.
The repair works for the damaged hinges shall be connecting two cantilever girders to
become monolithic, eliminating the hinge and expansion joint, at each hinge section. As the
hinge section shall remain in every 5 or 6 spans to avoid excessive restraint forces to be
generated by the temperature change, the hinges and expansion joints at such sections shall
be replaced by new ones.
To prevent the bridge from collapsing during earthquake the steel brackets will be attached to
the substructures at the girder ends. At the having joint of Kanchpur Bridge the girder ends
are connected to each other (Fail-safe connection).
Consequently, the scope of the retrofitting and rehabilitation works for Kanchpur Bridge,
Meghna Bridge and Gumti Bridge are summarized below.
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-29
Table 9.3.1 Scope of the Rehabilitation and Retrofitting Works
Kanchpur Meghna Gumti
Repair of cracks/rebar exposures ○ ○ ○
Connecting girders (eliminating hinges/joints)
- ○ ○
Center hinge rehabilitation - ○ ○
Expansion joint replacement ○ ○ ○
Steel brackets on the substructures ○ ○ ○
Fail-safe connection ○ - -
Deck strengthening ○ - -
RC-lining ○ ○ ○ Piers
Diaphragm wall ○ - -
Pile cap integration P1, P3, P5, P6 P1 to P10 P1 to P8
Steel pipe sheet piles P1 to P6 P3 to P10 P1 to P8 Foundations
Bored RC piles - P1, P2 -
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-30
9.3.3 Retrofitting and Rehabilitation Works
(1) Existing Kanchpur Bridge
The general outline of the design and the design outputs are summarized in Table 9.3.2.
Table 9.3.2 Outline of Design (Existing Kanchpur Bridge)
Bridge data Length = 395.6 m : [email protected] m + 54.9 m + 73.2 m + 54.9 m+42.7 mWidth = 14.64 m
Superstructure
Pre-stressed concrete I girder, continuous type (54.9 m + 73.2 m + 54.9 m) Pre-stressed concrete I girder, simply supported type (42.7 m5 spans)
915 12810 915
229 229686 12810 686
14640
915
229
176
838 1297 838
176
2286
6@2135=12810
Abutment Inverted T-type
Pier Rigid frame-type
Bridge components
Substructure
Foundation Abutment: Spread foundation Pier: RC open caisson
Live load JRA B-type (only for floor slab system) AASHTO HS20-44 (for girder and substructure)
Seismic load 2/3
1.22.5sm
m
ZSC Z
T ; where Z=0.15 and S=1.5
Wind load 3.0 kN/m2
Loads
Thermal force Temperature range: 26 17c c
Repair of cracks/rebar exposures
N/A Girder and deck
Deck strengthening Carbon fiber sheet adhering A1 to A2
Expansion joint replacement A1 to P4, P7, A2 Bridge accessories Steel brackets A1 to P4, P7, A2
RC-lining P1 to P7 Pier
Diaphragm wall P1 to P7
Foundation Steel pipe sheet piles P1 to P6
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-31
(2) Existing Meghna Bridge
The general outline of the design and the design outputs are summarized in Table 9.3.3. The
connection of the hinges should be the same as Figure 9.3.1.
Table 9.3.3 Outline of Design (Existing Meghna Bridge)
Bridge data Length = 930 m : 48.5 + [email protected] + 73.5 + 25.0 m Width = 9.2 m
Superstructure
Pre-stressed concrete box girder, continuous rigid frame type (48.5 m + 9*87.0 m + 48.5 m) Pre-stressed concrete T girder, simply supported type (2*25.0 m)
Abutment Inverted T-type Pier Columnar type
Bridge components
Substructure Foundation
Abutment: Cast-in-place RC pile (φ1,500) Pier: Cast-in-place RC pile (φ1,500)
Live load AASHTO HS20-44 (for girder and substructure)
Seismic load 2/3
1.22.5sm
m
ZSC Z
T ; where Z=0.15 and S=1.5
Wind load 3.0 kN/m2 Loads
Thermal force Temperature range: 26 17c c
Repair of cracks/rebar exposures P12 to A2 Girder and deck Connecting girders (eliminating
hinges/joints) All except P5 to P6
Center hinge rehabilitation P5 to P6 Expansion joint replacement A1, P5 to P6, A2 Bridge
accessories Steel brackets A1, A2
Pier RC-lining P1 to P12
RC casting reinforcement P1 to P10
Steel pipe sheet piles P3 to P10 Foundation
Bored RC piles P1,P2
9200
5800
250
1800
3500
800
1950
250
200
5000 1950
2300
250
250
2.0%
800
2.0%
50
300 70
7200
600
5001000
1950
400
500
750
600
550
LC
200
2550 1200
1350
9200
200800
900
2%120
800
2%
7200
350
4X1850=7400
1500
500
900
200
CL
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT Final Report
9-32
STEP-1: Removal of expansion joint in top slab and chip bottom slab.
Weld rebars for connecting to longitudinal rebar in top and bottom slab.
Drill holes for external cables and PC bars.
Arrange steel pipes for external cables and PC bars for connecting.
STEP-2: Cast concrete for connecting.
Having confirmed hardened concrete strength, PC bar to be connected
STEP-3: Arrange and stress the external cables.
Adhere carbon fiber sheets on the bottom slab
Figure 9.3.1 Hinge Connection of Existing Meghna Bridge
STEP-1:
STEP-2:
STEP-3:
THE KANCHPUR, MEGHNA, GUMTI 2ND BRIDGES CONSTRUCTION AND EXISTING BRIDGES REHABILITATION PROJECT
Final Report
9-33
(3) Existing Gumti Bridge
The general outline of the design and the design outputs are summarized in Table 9.3.4. The
connection of the hinges should be the same as Figure 9.3.1.
Table 9.3.4 Outline of Design (Existing Gumti Bridge)
Bridge data Length = 1,410 m: 52.5 + [email protected] + 52.5 m Width = 9.2 m
Superstructure
Pre-stressed concrete box girder, continuous rigid frame type
Abutment Inverted T-type Pier Columnar type
Bridge components
Substructure Foundation
Abutment: Cast-in-place RC pile (φ1,500) Pier: Cast-in-place RC pile (φ1,500)
Live load AASHTO HS20-44 (for girder and substructure)
Seismic load 2/3
1.22.5sm
m
ZSC Z
T ; where Z=0.15 and S=1.5
Wind load 3.0 kN/m2
Loads
Thermal force Temperature range: 26 17c c
Repair of cracks/rebar exposures P5 to P7, around P10 Girder and deck Connecting girders (eliminating
hinge/joints) All except P5 to P6 and P11 to P12
Center hinge rehabilitation P5 to P6, P11 to P12
Expansion joint replacement A1, P5 to P6, P11 to P12, A2 Bridge accessories
Steel brackets A1, A2
Pier RC-lining P1 to P16
RC casting reinforcement P1 to P8
Steel pipe sheet piles P1 to P8 Foundation
Bored RC piles N/A
200
250
250
2300
1800
800
300
7250
800 7200
500
50001950 1950
2.0% 2.0%
9200
200
CL
1000
500
600
600
250
250
5300