chapter 2 public private partnership financing and...
TRANSCRIPT
CHAPTER 2
PUBLIC PRIVATE PARTNERSHIP FINANCING AND CONSTRAINTS
FACED BY PPP
India‘s global competitiveness remains constrained and is adversely affected by
lack of infrastructure, which is critical for improved productivity across all sectors
of the economy. However, achieving the investment targeted for the Eleventh Plan
presents many distinct challenges. These relate not only to scarcity of financial
resources but also to lack of capacity within the government to implement these
ambitious programmes.
In India, government budgetary resources are increasingly constrained in financing
infrastructure projects. In this scenario, Public Private Partnerships (PPP) has
emerged as a viable option for financing infrastructure needs. The trends in PPP
financing highlight several issues with implications for financing the large-scale
PPP program envisaged by Indian government. PPPs have relied heavily on
commercial banks for their debt financing, and it is unclear how sustainable this
dependence will be. Long-term financing exposes the banks to the risk of asset-
liability mismatch. An active bond market can increase the flow of long-term funds
and reduce reliance on banks.
Public Private Partnerships in India face barriers posed by the absence of a
sufficiently sophisticated financial sector, fiscal barriers, red tape and procedural
inefficiencies that have contributed to project delays and discouraged private
investors, and constraints arising from the absence of adequate infrastructure
regulation that aggravates risks and uncertainties for investors. Uttar Pradesh has
lined up many projects for private investment under the Public Private Partnership
mode. These projects have either been launched or awaiting the nod and are spread
over all major sectors like power, transport, education, tourism, infrastructure,
urban development and health.
This chapter discusses infrastructure investment needs of India and how these
needs are fulfilled by PPP financing. It discusses the recent trends and financing
options in PPP financing in India. It further discusses the various environmental
constraints faced by PPP in India and Uttar Pradesh. Finally, it sheds light on
current status of PPP projects in Uttar Pradesh in various sectors.
2.1 PPP Financing
Historically, funding for capital investment in infrastructure has largely depended
on government sources, namely; budgetary allocation, debt against government
guarantees, mandatory financing by institutions or local government funding.
However, Indian government is unable to mobilize the required financial resources
to cope with the rising demand for roads, electricity supply, water supply, etc.
While the infrastructure gap is rising, government budgetary resources are
increasingly constrained in financing this deficit. Rising costs of maintaining and
operating existing assets, inability to increase revenue and cut costs and waste, and
rising constraints on budgets and borrowing, do not allow governments to make the
required investments in upgrading or rehabilitating the existing infrastructure or
creating new infrastructure. In this scenario, Public Private Partnerships (PPP) has
emerged as a viable option for financing infrastructure needs.
2.1.1 Recent trends in PPP financing:
In recent years the role of senior debt has grown while the share of equity has
declined, leading to rising debt-equity ratios. One explanation for this trend is that
commercial banks have become more comfortable with PPPs, particularly in the
road sector, and are therefore willing to have senior debt make up a larger share of
project financing.
There is also evidence suggesting that projects with viability gap grants have
higher gearing than those without them. While the evidence is inconclusive, there
are some indications that lenders and developers view grants as substituting for the
equity infusion needed during construction. The few projects involving a negative
grant—a payment by the PPP to the government—also have a higher ratio of
senior debt to equity, suggesting that these payments are being financed by debt
borrowed by the PPP project.
In India the typical concession terms encourage the use of debt over equity. For
example, in the highway sector, the contracting agency must compensate the
contractor if the contract ends early, even if the termination is due to a breach of
the contractor‘s own obligations or an event of force majeure. In these cases the
compensation is partial, with lenders typically being repaid in full or in large part
while shareholders get nothing. Linking termination payments to debt, while
common around the world, can encourage higher gearing, which in turn may
increase projects‘ financial vulnerability.
Some countries put limits on the ratio of debt to equity. But restricting an
investor‘s ability to choose its capital structure can increase the cost of capital,
prevent companies from reaping tax advantages associated with particular types of
financing, and impose a monitoring burden on the government. Alternatively, India
could consider a different basis for termination payments, reducing the incentive to
use debt embedded in the termination clauses of its model concessions.
Debt financing has become more competitive
The debt financing of PPP projects is on the strength of concessionary agreements.
Since the land and other fixed assets cannot be secured in BOT or BOOT type
projects, the security of revenues and clauses like ‗step-in clause‘ for lenders if the
borrower defaults in concession agreements, form the basis for lending. In the
power sector, power purchase agreements, which are irrevocable, between the
private producer and public sector have formed the basis for lending.
For national highways, annuity payment agreements with national agency, NHAI,
has been the basis for lending. Within the urban sector, however, problems are
evident as lenders have been wary about lending to urban PPP projects. The
problems reside around the low financial strength of urban local bodies and
political resistance to reforms, resulting in ambiguity as to whether the security of
revenue streams for urban projects is through annuity payments or the collection of
user charges. The nature of private players in PPP projects also plays an important
role in their ability to secure funding. Sectors like road, power, ports and airports
comprise large scale projects which have been able to attract large national and
international companies (in terms of their financial net worth). These companies
have the ability to raise commercial debt on the basis of their balance sheet. As a
result, commercial debt for PPP projects is not purely project finance but on the
basis of strengths of balance sheet of borrowers and financial viability of the
project.
Bank lending in India for PPP projects is primarily short term (3–7 years), on a
variable rate basis, with the typical debt to equity ratio a 70:30 arrangement.
Significantly, long term finance for PPP projects, and in general for infrastructure
projects, for longer tenure is not available as institutions like insurance companies
and pension funds do not lend to project companies setting up Greenfield
infrastructure projects. The debt raised through bond markets is another possibility
for PPP projects, but the bond market in general (even for corporate bonds) is in
nascent stages of development in India. Some urban municipal bodies with high
financial strength have attempted to raise debt by issuing general revenue bonds
(tenor 7–15 years) but these are very few. For small and medium municipalities,
pooled fund mechanisms have also been attempted, however their relative success
has been limited as a number of issues from the perspective of investors have
hampered the development of municipal bonds/pooled funds.
Despite some volatility, average spreads on debt to PPP projects have declined
significantly in recent years (Figure 2.1). This does not reflect trends in Indian
corporate bond spreads, which increased in 2006 and 2007. While many factors
may be involved, the decline in spreads is probably due to the financial markets‘
growing acceptance and understanding of PPPs as more projects have come on line
and provided an operational track record, particularly in the road sector. On the
negative side, the tenor of debt has increased little, averaging around 14–15 years
in the past few years. In addition, loans in India have shown a trend toward shorter
reset periods. Although the loans are long term, rates are reset at predefined
intervals. PPP projects generally do not have revenues that are linked to interest
rates. There are concerns that higher rates could affect some projects, particularly
those with higher gearing.
Figure 2.1: Debt-equity ratio of PPP projects in India
Source: PricewaterhouseCoopers, 2007
Figure 2.2 below highlights the distribution and scale of PPP finance in India
between 2005 and 2010. In 2005 PPP finance was equitable between equity and
multilateral and government support (US$0.1bn) with debt finance marginally
higher (US$0.3bn) giving a total of US$0.4bn of PPP finance within infrastructure.
Of this US$0.4bn, debt finance comprised 61% of the total PPP investment based
on two deals reaching financial closure. In 2006 PPP project based finance
witnessed an increase in debt finance by 100% (US$0.3bn to US$0.6bn) increasing
the overall level of debt based finance to 80% of PPP market share. This was
primarily due to the increase in the number of deals and the overall reduction in the
average deal size in the market. Between 2006 and 2007 the PPP market exhibited
a substantial increase of debt structured finance of circa 150% from US$0.6bn to
US$1.5bn comprising 77% of total PPP finance. Significantly in this period the
number of deals decreased illustrating an average deal size of US$0.5bn.A slight
shift in PPP finance occurred between 2007 and 2008 as debt finance marginally
grew by US$ 0.2bn (13.33%) however equity finance increased from US$ 0.3bn in
2007 to US$ 1.0bn in 2008 reducing debt as a percentage of total PPP finance to
63%.
Figure 2.2: India PPP Project Finance
Source: Infrastructure Journal Online (Accessed 15th December 2010)
In 2009 debt structured finance continued to increase (US$ 2.3bn) in line with the
amplification in the number of PPP deals in the market, which reached a peak of
eight. Total PPP finance in 2009 reached US$3.2bn. There was a marginal drop in
equity finance from the previous year however this remained at US$0.9bn, leaving
debt finance as 73% of total finance. PPP finance for 2010 displays a severe
contraction in both debt finance which decreased by US$2.0bn (86.96%) from the
previous year and equity finance of US$0.8bn (88.89%) and the large increase in
debt percentage of total PPP finance to 79%. The substantial decrease in the PPP
finance in 2010 is reflective of the number of deals in the PPP market and the
reduction in the average deal size. In 2009 the total PPP finance in the market was
US$ 3.2bn, comprising eight deals of which the average deal size was US$0.4bn.
However, in 2010 PPP finance totalled US$0.4bn comprising only two deals
averaged at US$0.2bn, bringing the PPP market back to 2005 levels. Significantly,
excluding a capital injection of US$0.1bn in 2007 M&G finance has not been a key
source of funding for PPP projects in India to date.
High equity returns expected
In a survey conducted by PricewaterhouseCoopers in 2007, developers were asked
to state their expected equity returns. Among these, more than 70 percent sought
returns exceeding 16 percent. Analysis suggests, as would be predicted, that
projects with higher gearing had higher expected rates of return. Calculations
indicate that the asset beta for these projects was around 0.6–0.75, depending on
the assumed equity risk premium. This is somewhat higher than other estimates;
for example, Alexander, Estache, and Oliveri (1999) estimated asset betas for road
projects in Latin America and the Caribbean to be 0.31–0.48. The difference could
reflect the high-powered regulatory regime for Indian road projects—but it is also
consistent with the aggressive bidding for road projects in 2006–07. Negative grant
bids were seen for some projects, driven by huge developer interest in road PPPs.
2.1.2 Financing Options for Public Private Partnerships in India:
Recent efforts to encompass commercial finance have been undertaken in urban
service ventures in an attempt to convert service projects into bankable schemes
using commercial loan finance. Indeed, the extent of this commercialisation varies
across different infrastructure sectors and this poses a challenge for structuring of
PPP financing.
Therefore, to counter this challenge, we structure PPP financing in the light of the
extent to which there is a potential for generation of revenue through user charges,
and the capacity of user charges to provide a return on investment and the level of
public sector equity or subsidy in a project. This has culminated in the emergence
of five core PPP financing structures within urban infrastructure (Figure 2.3).
These structures are explained below:
Figure 2.3: Alternative Financing Options for Public Private Partnerships in
India
Source: Infrastructure Journal Online (Accessed 15th December 2010)
Model A - Full cost recovery through user fees, No government guarantee:
At one end of the spectrum, full cost recovery is viable through user fees without
the requirement for government guarantees or subsidies to incentivise private
sector investment. However, this appears to be a theoretical construct in the Indian
scenario, as there are very few examples of projects where the private entity is able
to retrieve their investment through project cash flows without having to increase
the user fee. Nonetheless, the potential to supplement income through advertising
revenue or lease rentals from commercial space has ensured the viability of some
projects for private sector investment. In such cases, project cash flows from the
user fee in combination with alternative revenue sources to provide the return on
investment have potential for tolling. In the case of most urban sector projects such
as water supply, sanitation, education and healthcare (particularly for poor) full
cost recovery even in combination with project related alternative sources of
revenue is not possible or the revenue risks are too high for the private sector to be
interested. Thus, such projects require government financial assistance in the form
of capital grants or revenue guarantees and annuities or a combination of capital
and revenue support.
Significantly, there are no clear distinctions between the form of infrastructure
being procured and the financial PPP model being adopted. The approach is
heterogeneous and determined at project level reflecting the nature of the project,
the capital requirements and the revenue potential. Consequently, public
transportation initiatives encompassing modest capital requirements and the ability
to charge user fees and generate revenues from commercial rents or advertisements
have successfully attracted private funding. Within these approaches the private
sector is responsible for construction, with the return on investment through the
additional fee supplemented by advertising revenue, and rental revenue from
commercial property developed alongside the key infrastructure. Projects located
centrally where land values and commercial lease rentals are high, present
substantial opportunities for using the commercial potential of alternative land use
(such as retail, office) to pay for project cost.
Model B - Combination of user fees and government capital grant:
Within more capital intensive projects, there is a need for capital and operating
subsidies and a supporting regulatory environment in order to attract private sector
funds, as tariffs are often not sufficient to maintain operational costs, let alone
capital costs as evidenced in both MRTS and BRTS schemes. In both schemes, the
public purse has been needed to fund the entire capital cost and a portion of the
operating cost to make these projects attractive to the private sector. They do
however have the capacity to acquire additional sources of revenue including
advertisement revenue and a lease income from commercial properties. The Indore
City Bus Service which became operational in 2006 is an example of public sector
provision of capital infrastructure and private sector provision of assets, which it
fully operates.
Model C - Joint Venture with User fees with or without Capital grant:
In contrast, the airport express link project of Delhi Metro provides a good PPP
model for a capital intensive mass transportation projects. The Delhi Metro Rail
Corporation (DMRC) is in line to build the fixed infrastructure, with the private
sector entity providing the rolling stock and operating the system for a 30 year
period. Paradoxically, the capital cost of the fixed infrastructure and the rolling
stock almost equates on the Delhi Metro project.
Model D - User fee with minimum revenue guarantees:
In this approach the user charges (fare-box revenue) and advertisement revenues
cover the project‘s capital and O&M costs. However, the problem is that only the
commercially lucrative routes have been bid out posing significant challenges, as
this requires a complete system, in that all the routes (even the commercially
unviable) need to be operational in order for it to function efficiently and
effectively. This model does have the capability of generating private sector
interest through investment or direct subsidy. Private investment in financially
non-lucrative routes can be incentivised by bundling these routes with financially
lucrative routes, as limited restrictions placed on the upside revenue potential
coupled with minimum revenue guarantees would provide additional incentives.
Alternatively, the public sector can provide a direct subsidy to the private sector
operators plying on these routes. In the context of urban roads, difficulties in
identifying end-users make imposition of user charges difficult within PPP models.
Model E - Funding through shadow user fee or Annuity scheme:
The toll-based PPP model which is very popular for inter-state roads and highways
in India is difficult to apply to the urban road setting. Therefore, where tolling is
not possible or is insufficient to cover the investment, annuity structures or shadow
user charges offer more viability as these payments to the private sector are
conditioned on performance. For most city roads, PPP take the form where the
private sector bears the construction cost and operational risk but the revenue risk
lies with the public sector (for example Thiruvananthapuram city roads).
Furthermore, highly capital-intensive tariff water and sanitation projects are
insufficient to cover the cost of investment, and comprise limited potential to
generate revenue from other sources. To enhance development, the unbundling of
the ‗value chain‘ presents improved operational efficiency for delivery of WSS
services requiring relatively low capital investment from the private sector, whilst
having the potential to be paid for through tariffs from users or annuity payment by
the public sector. A number of such projects have materialised recently in WSS
sector in India where depending on the project and the extent of the possibility of
unbundling of various activities involved in water and sanitation, a variety of PPP
models are structured based on a combination of capital grant/subsidies, user
charges and government guarantees to enable raising capital from the market by
the Urban Local Bodies (ULBs).
2.1.3 Lessons for going forward:
The trends in PPP financing highlight several issues with implications for
financing the large-scale PPP program envisaged by Indian government. PPPs have
relied heavily on commercial banks for their debt financing, and it is unclear how
sustainable—or how desirable—this dependence will be. Long-term financing
exposes the banks to the risk of asset-liability mismatch: the main source of funds
for Indian banks is savings deposits and term deposits, whose maturity profile
ranges from less than six months to five years. Over much of the period developers
were comfortable with shorter reset periods, perhaps because this had been a
period of declining or low rates. But as interest rates began to increase, concerns
arose about the impact on PPPs, because the concession contracts have no
provisions for passing on higher interest charges. Continued increases in rates as
well as a tightening of credit could have adverse effects on some projects.
An active bond market can increase the flow of long-term funds and reduce
reliance on banks. The Indian corporate bond market, though one of the largest in
Asia, is still at an early stage of development, and its growth is hampered by
institutional, legal, and regulatory constraints that make bonds a more expensive
way of financing debt. These problems, as well as potential solutions, are
highlighted by the Patil Committee (2005), established by the government.
Following the suggestions of the committee, the government has set up reporting
and trading platforms for corporate bonds. Many other important suggestions still
await implementation. But implementing bond market reforms is a difficult
challenge in the best of times, and in the light of the current global financial crisis
the government would have to explore other innovative ways to ensure adequate
flows of (private) financing to infrastructure PPPs.
On the equity side, participation by foreign players, particularly strategic investors,
has been low even though PPP projects are allowed to have 100 percent foreign
direct investment. Foreign direct investment accounted for only 11 percent ($322
million) of the total investment. The port sector had the largest share (51 percent)
of this foreign investment, followed by airports (32 percent) and roads (16
percent). Only nine projects were reported to have strategic investor participation:
four in ports, three in airports, and one each in water supply and railways. Few
pure equity providers are willing to invest directly in special-purpose vehicles
because many concession agreements put restrictions on the sale of developers‘
equity. Encouraging pure equity providers to do so will require more liberal norms
allowing them to participate at the time of bidding or to enter later with a majority
stake.
2.2 Constraints Faced by Public Private Partnerships in India and Uttar
Pradesh
2.2.1 Environmental constraints faced by PPPs:
Public Private Partnership entails compromise and a change in the usual way of
doing things, therefore it is only natural that certain barriers will exist. It is
important to recognize these likely impediments and to build in strategies to cope
with them in order for the partnership to function effectively. This should be done
early in the process to allow time to implement the necessary changes.
The evidence from developing countries indicates that actual or perceived rise in
tariffs, macroeconomic fluctuations in currency or purchasing power, inadequate
regulatory and institutional environments, societal discontent against the private
sector and political reneging are some of the key reasons for the failure of PPP
projects (Harris, 2003; Gomez-Ibanez et al, 2004; Vernon, 1971).
Public Private Partnerships in India face barriers posed by the absence of a
sufficiently sophisticated financial sector, fiscal barriers, red tape and procedural
inefficiencies that have contributed to project delays and discouraged private
investors, and constraints arising from the absence of adequate infrastructure
regulation that aggravates risks and uncertainties for investors.
PPP carries investments and costs; it must be thoroughly efficient and managed in
terms of planning, monitoring, and acceptance of loss of some control. Private and
public sectors often have different goals, and organizational philosophies and
cultures.
The environmental constraints faced by PPPs in India and specially, Uttar Pradesh
are described under the following headings:
1. Political and bureaucratic constraints
2. Legal and regulatory constraints
3. Financial constraints
4. PPP policy framework constraints
5. Social constraints
These constraints are described below in detail:
2.2.1.1 Political and bureaucratic constraints:
Political and bureaucratic constraints, such as fragmented decision making due to
the involvement of multiple public agencies, the prevalent emphasis on
administrative procedures (rather than on strategies and results) that stem from the
traditional, lengthy tendering process (normally split in three or four phases, from
planning to final operation) are major hurdles to PPP implementation.
Progress in PPP development has been limited due to the frequent political
reluctance (often originated in public opinion) to give up control of infrastructure
assets which had been in public hands for a long period of time. Perhaps the
primary constraint to the development of a Public Private Partnership is the lack of
political will. Often the situation related to service provision to the poor citizens is
complex and the proportion of the population that this disadvantaged group
comprises could be too low to provide sufficient political motivation – either to
take the poor into consideration in the first place, or to redesign the contract later
on.
In addition, governments or coalitions in several states such as Tamil Nadu, Kerala
and West Bengal that have representations from left-wing factions are often
strongly opposed to the entry of the private sector to provide essential services. A
lack of support from the political machinery is therefore also a reason for the lack
of PPPs at the state levels.
Often political limitations exist on the development of more pro-poor attitudes
within urban governments. These constraints include: the complex political
struggles that often take place between national and local government; overlapping
responsibilities between different authorities or agencies; and unrealistic
expectations about what local authorities can actually do with their very limited
technical and institutional capacity.
The political and bureaucratic constraints faced by PPP are:
(i) Multiple clearances:
Infrastructure projects require multiple clearances at centre, state and local levels.
This is a time consuming process not only due to the sheer number of approvals
but also because clearances are sequential, and not concurrent. For example, when
Sify was setting up internet cafes in different states, it involved over 50 different
clearances.
According to most developers and financiers, the time taken to obtain all the
requisite approvals for an infrastructure project can vary between a low of 18
months to as much as four to five years. For example, it took more than two years
for the Gujarat Pipavav port project to receive the necessary clearances after
achieving financial closure on the project. Delays like these in getting government
approvals, places India very unfavorably compared to China and South-East Asia.
In spite of the theoretical concept of a single window clearance in many states,
when most projects apply for approvals at the state-level, these have to go through
multiple clearances from local panchayats, municipalities, forest, environment
board etc. which cause huge delays in completion. In many cases, the concession
agreements entered into by individual departments do not have pre-approved
clearances from the Finance Department, leading to further delays. The lack of a
‗single window system‘ to obtain project clearances considerably increases the
transaction costs of a project and often necessitates the exchange of bribes in order
for the project to move forward. Although these institutional arrangements differ
from project to project, the overall effect is to hamper the participation of the
private sector.
(ii) Lack of coordination between government ministries /departments:
Most infrastructure projects involve dealing with multiple ministries. One of the
key reasons for projects not taking off at the pre-financing stage is that the actions
and policies of different ministries are not coordinated and are often at variance
with each other. This is particularly true for the power sector, where even if the
developer obtains the requisite permission for setting-up of a generation facility, he
finds it difficult to start operations because of lack of clearance for fuel supply,
which involves some two other ministries. Similar problems exist regarding the
Ministry of Environment. There are no IIGs except in power. The recently set up
IIG for power has proved to be an effective way to expedite PPP investments in the
sector. Such groups have not been formed for other sectors, and their absence has
impeded the developers‘ ability to achieve financial closure and complete the
necessary formalities on time.
(iii) Lack of effective political commitment to eradicate public sector
corruption:
In most of the states, reaction to corruption is resignation and acceptance. This
makes it very difficult to find those who are willing to investigate corruption, and
especially difficult to punish it when it is found. This kind of reluctant attitude acts
as a deterrent to private sector to invest and participate in Public Private
Partnership projects in India. A strong commitment and lack of acceptance of
corruption is necessary in order to fight it.
(iv) Problems in contract negotiations and delays in the award of contracts:
This is pervasive across all infrastructure sectors. For instance, it took Kakinada
port four years to achieve financial closure. In the power sector, four gas-based
power projects30, which had achieved financial closure in early 2004 with an
investment of over Rs.50 billion, are today on the verge of closing down due to
flawed fuel supply contracts. While the gas supplier Gas Authority of India
Limited (GAIL) has said that it has no gas to offer to these plants, project sponsors
find it impossible to penalize GAIL due to one-sided fuel supply contract that they
were forced into. Even a well run, relatively efficient organization like the NHAI is
now causing delays. To give an example, the bids for the first lot of NHDP III
projects were received in March 2004; not one of these has been awarded till date.
2.2.1.2 Legal and regulatory environment:
Enabling legislation must be in place before PPP programmes can be embarked on
in a country. The government has to demonstrate a clear, long-term political
commitment to the use of PPP. Such commitment may manifest itself in a variety
of practical ways. PPP inevitably involve highly complex commercial and financial
structures. This is attributable to, firstly, the many stakeholders involved and,
secondly, the wide range of risks associated with the project which has to be
allocated properly. A third factor is the long-term nature of PPP schemes, which
means the arrangements must be flexible and responsive to circumstances
changing over time. To meet these requirements will necessitate the existence of a
reliable and well-developed legal framework.
Various aspects of the broader legal and regulatory environment for services can
act as significant barriers to the PPP, like the presence of vague responsibilities
among (independent) regulatory agencies and ministerial, unclear regulatory
procedures, the lack of a dispute-resolution framework. In addition, accounting
laws and practices, laws governing construction contracts, public works laws and
conventions and so on may be inappropriate for private sector participation.
Therefore, before a particular partnership opportunity for the implementation of a
project is approved, the service must be examined in detail to ensure that there are
no legislative or regulatory barriers to the PPP. If this step is ignored, significant
investment in time and money can be spent developing a partnership only to find
that it cannot proceed in the current environment.
The following are the legal and regulatory barriers faced by infrastructure players:
(i) Lack of a clearly defined legal basis for private sector participation in
PPP:
The legal framework for PPP in India lacks a clearly defined basis for private
sector participation. In this case, individual sector legislation may have to be
modified. For example, some countries do not allow private provision of
telecommunications, or of water, etc. The target sectors chosen for PPP need to
have explicit legal provision enabling private participation.
Several PPP proposals for projects at the state level face roadblocks due to the lack
of enabling PPP legislation. In some cases, the existing legislations mandate that
only the public sector be allowed to provide a given set of infrastructure services.
Even when there is no explicit law that prevents the private sector from
participating in infrastructure, the lack of enabling legislation on PPPs also implies
that state government officials and bureaucrats who encourage private sector
participation are doing so at their own discretion due to their own personal beliefs
of the advantages of partnering with the private sector. This in turn leaves such
personnel open to investigation from anti-corruption agencies, which acts as a
further deterrent towards soliciting involvement from the private sector. On the
other hand the presence of pro-PPP legislation would provide considerable
reassurance and recourse to the public officials.
Some states have framed policies for PPPs, but unless these policies are enshrined
as laws, they always run the risk of being re-written by succeeding governments.
Furthermore when legislation is enacted, it is enacted in a piecemeal manner, to
accommodate a particular project. This then leads to several legislations that need
to be enacted periodically across other sectors. A more holistic approach that
anticipates concerns across sectors and can lead to the enactment of broader
legislation could therefore be an asset. The institutional bottlenecks outlined above
result in a considerable increase in transaction costs to plan, approve and execute
PPP projects which in turn leads to extended delays, changes in project viability
and in some cases, project cancellations.
(ii) Restriction on participation of foreign investors in PPP projects:
Even though Indian regulatory framework enables private sector companies to
provide basic services, it limits foreign participation in such efforts. These
limitations include limitations on land ownership and other natural resource use,
greater restrictions on employment and special requirements such as technology
transfer. Openness to foreign participation usually accompanies a policy emphasis
on effectiveness of private participation. Many countries like Australia and United
Kingdom have signed treaties concerning the treatment of foreign investors,
providing a more predictable and secure environment for these investors. These
kinds of treaties are not present in Indian context.
(iii) High customs duties on infrastructure equipment:
While there are import duty concessions available to imports used for
infrastructure development, such as in the case of mega power projects, certain
telecom equipment etc., these are largely selective in nature. For instance, while
equipment for mega-power projects can be imported against zero or low duties, the
same facility is not available for capital goods used in roads. It has been suggested
that the government creates a masterlist of all key capital goods and machinery
used for roads, power, ports, airports, telecom and water supply and distribution,
and make these available at zero duty. In large measure, this is what China has
done in the recent past, which has significantly reduced its cost of setting up
infrastructure.
(iv) Section 10(23G) of the Income Tax Act:
This clause exempts tax on income from dividends, interest and long term capital
gains from any investment made in an enterprise engaged in the business of
developing, maintaining and operating an infrastructure facility — and has been of
great help in facilitating infrastructure investments. However, three issues still
cause problems.
(a) First, the borrowing infrastructure company needs to get annual approval and
certification of its ―infrastructure status‖ from the Central Board of Direct Taxes
(CBDT) before the lender can claim the fiscal benefits under this section. The
process is not automatic and often takes considerable time — which has on several
occasions led to delays in getting the concessions.
(b) Second, there is an issue of escalation. In essence, if the surplus of an
infrastructure SPV that falls under section 10(23G)is reinvested in another
infrastructure SPV —both of which belong to the same umbrella company —
could the latter also obtain the fiscal benefits under this provision? As of now, the
opinion runs counter to this. According to this view, an enterprise qualifies for the
benefits under section10 (23G) if it is wholly engaged in the business of
developing, maintaining and operating any infrastructure facilities. The catch lies
in the word ―wholly‖. This apparently precludes any infrastructure enterprise to
invest or lend its investible surplus in another infrastructure entity — for that
would be an act of financing, and not amount to developing, maintaining or
operating of infrastructure. Thus, according to this interpretation, it will not get the
benefits of section 10(23G). This problem can be resolved by either eliminating the
word ―wholly‖ or substituting it with ―substantially‖.
(c) Third, the benefits of section 10(23G) do not flow down to retail investors. Had
that been possible, the tax benefits of this provision could have been leveraged to
create more dedicated infrastructure mutual funds where the retail investors would
have been additionally attracted by the tax incentive.
(v) Tax holidays under section 80IA:
Section 80IA of the Income Tax Act relates to infrastructure projects and provides
for 100 percent tax deduction on profits for 10 years and 50 percent for the next
five. There are two issues with this seemingly beneficial provision.
First, most infrastructure projects, especially those in roads, power and ports, take
up to 7-8 years before starting to show profits. Therefore, providing for a 100
percent tax holiday over the first 10 years does not actually amount to a serious
fiscal incentive.
Second, even this limited fiscal incentive is overridden by the Minimum Alternate
Tax (MAT), which is levied at 7.5 percent on book profits. Consequently, the fiscal
benefits from section 80IA get significantly diluted at the ground level.
(vi) Priority sector status:
At present, the RBI rules state that 40 percent of a domestic scheduled commercial
bank‘s loans and advances (and 32 percent of a foreign bank‘s)should be directed
to the so-called ‗priority sectors‘, which comprise agriculture, small scale
industries, khadi and village industries and a classified list of other small scale
businesses. Infrastructure sectors fall outside the definition of priority sector. It has
been argued by several banks that, given the critical importance of infrastructure, it
too should be considered as a priority sector.
(vii) ‘Statutory Liquidity Ratio (SLR) and Cash Reserve Ratio (CRR)
requirements on infrastructure bonds:
At present, scheduled commercial banks are required to maintain with RBI on a
fortnightly basis an average cash balance or CRR amounting to a certain percent of
the total of the Net Demand and Time Liabilities (NDTL) in India. SLR is peculiar
to India, which mandates that scheduled commercial banks must keep a certain
percent of their total demand and time liabilities in India in cash, gold or approved
government securities. The reason for both is to maintain a safe liquidity in
banking system, although the SLR requirement makes it easier for the central
government to pre-empt depositors‘ funds. It has been suggested by many banks
that since 15-20 year AAA rated infrastructure bonds are of long maturity and
carry no short term liquidity risks, liabilities on account of the sale of such
instruments should be considered outside the purview of SLR and CRR.
2.2.1.3 Financial constraints
Financial constraints measure the ability to find funding for PPP projects through a
variety of mechanisms. They include indicators that measure the overall strength
and capacity of the financial system. Handling finances domestically will be
greatly facilitated if the country has a well developed banking system, with a
variety of financial products and instruments intermediating between depositors
and borrowers. Financial regulation is critical to a financial system, partly to avoid
illegal behavior and partly to help manage corporate and systemic risk. Having an
effective financial regulatory regime in place reduces risk for the PPP firm and the
government. The following constraints need special attention:
(i) Under developed Pension and Insurance markets:
It is widely accepted that insurance companies and pension funds are ideal
candidates for supplying long tenor financing given the long tenor nature (15 years
or more) of their liabilities. But with a few notable exceptions, in recent times,
most insurance companies and pension funds have not focused on funding
infrastructure.
Among the various term-lending institutions, LIC (the largest insurance company
in India that is also state-owned) has emerged as the biggest player, with its
disbursements for infrastructure projects exceeding the combined disbursements of
IDBI, IFCI, IDFC, IIBI and SIDBI. However, most of the involvement of the state-
owned insurance companies, including LIC, is in infrastructure projects of the
central and state governments‘ SOEs backed by government guarantees. These are
often not based on credibility or the detailed economics of the project. In fact, in
the past, state governments have raised funds from the insurance SOEs ostensibly
for financing infrastructure, which have then been diverted to the state‘s
consolidated finances. Commercial banks have only been marginal players in terms
of their share of infrastructure financing in the recent past, though this segment has
registered strong growth in the last two years.
Within the sectors, FIs have a much higher appetite to lend for power projects than
others. Power generation accounts for 62 percent of the value of infrastructure
loans sanctioned and 55 percent of disbursals. Telecommunication comes second,
accounting for 20 percent of total infrastructure sanctions, and 24 percent of
disbursals.
(ii) An underdeveloped corporate bond market and the lack of longer term
financing:
Most infrastructure projects fructify into profit making entities 10 to 15 years after
the initial investment and hence require longer tenor financing (with long drawn
out repayments) to ensure financial viability of the project. The availability of a
developed bond market is an important backbone to project financing for
infrastructure as it increases the prospects for project finance banks to eventually
off-load their assets, and for project companies to lock in fixed interest rates at
lower margin when the project has stabilized after a few years of operation.
Moreover, functional bond markets are important for funding existing
infrastructure utilities/companies, as well as certain types of projects with no or
low construction risk and an established revenue pattern. Unfortunately, India still
does not have a wide or deep enough corporate bond market for such paper.
According to the estimates of the Bank for International Settlement (BIS), the size
of India‘s corporate bond market was 0.3 percent of nominal GDP in December
2003—much lower than that of Malaysia (43.3 percent) or South Korea (27.7
percent). Trading on the Indian corporate bond market is limited.
The lack of size and depth in India‘s corporate bond market may be attributed to
three broad sets of issues viz., development of government securities market, lack
of market infrastructure and innovations in the corporate debt market and
regulatory issues.
(iii) Constraints to equity and quasi-equity financing:
Raising adequate equity finance tends to be the most challenging aspect of
infrastructure project financing, as equity typically shoulders the greatest level of
operational, financial and market risk. Equity can be provided by project sponsors
(those who have an operational interest in the contract) or financial investors (those
who have only an investment interest). In India, as in many other countries, the
early phase of private financing of infrastructure has shown a predominance of
sponsor equity. But the ability of sponsors to raise equity from the primary market
remains limited. First, infrastructure companies or project sponsors typically have
much higher gearing than other corporate, which makes them unattractive
candidates in the securities market. Second, not only are the projects operationally
complex but also, they involve complexities in terms of contracts, legal structures,
right of first charge on assets etc. Consequently, investors, especially retail
investors, find it difficult to understand the true risks involved — and are wary of
investing in such issues.
In the longer-term, equity finance from financial investors – including private
equity funds such as venture capital funds and other institutional investors such as
dedicated infrastructure funds sponsored by a consortium of insurance companies,
pension funds, Government sponsored funds, commercial banks, development
banks, private fund managers and other privately-held companies, can prove to be
critical.
However, at present, equity financing and quasi-financing by financial investors is
constrained by the following factors:
(a) Limited exit options constrain equity participation: The best route for
financial investors to exit from an infrastructure project is to sell their stake to the
sponsors, through a ‗put option‘, which involves an upfront agreement between the
financial investor and sponsor, including agreement on the minimum price at
which the financial investor could sell the equity stake to the sponsor at a future
date. However, in India, the regulations do not allow such agreements to be
reached upfront between financial investors and sponsors of an unlisted company.
For one thing, the approval to exercise the ‗put‘ has to be obtained from the
Reserve Bank of India (RBI) at the time of the exercise, and cannot be obtained
up-front. For another, put option agreements with sponsors of unlisted companies
cannot guarantee a minimum price on the sale of shares to the sponsors. The sale
price in such transactions is subject to pricing requirements of the RBI, which
requires an independent valuation to determine a ―fair‖ price for the shares at the
time the option is exercised. This leaves a lot of uncertainty in the minds of
investors and prevents them from negotiating a floor to their return and ensuring a
suitable exit prior to investing.
(b) Additional constraints: Additional constraints to equity investment include a
shallow capital market (albeit continuously improving), and corporate governance
issues (primarily minority shareholder protection rights).
For construction companies and equipment suppliers, revenues from these
activities exceed the returns provided by equity. Many times, this is their primary
motivation for venturing into infrastructure projects, rather than the returns
provided by the project itself. For a financial investor, the only return on equity is
provided by the revenues generated by the project. Therefore, there is a severe
conflict of interest between the project developer and the financial investor. A
project developer may act in a way which maximizes his return from the secondary
activities, at the cost of project revenues. The financial investor, who is in a
minority position in such projects, loses out in such situations.
To improve corporate governance, and to protect minority shareholders rights
infrastructure projects must go for competitive bidding for the EPC contracts,
equipment supply contract, management contract and user contracts. The project
promoters may participate in such bidding processes, but must emerge a winner
from such a process to obtain the contract for providing such services.
(c) Limited mezzanine financing: In the developed world, many infrastructure
projects are part-funded through ‗mezzanine finance‘, which is a hybrid of debt
and equity. Mezzanine finance is debt capital with fixed payment or repayment
requirements, but with the right to convert to an equity interest in a company. It
carries two advantages: first, it attracts investors by offering a rate of return which
is higher than that of senior debt and second, on the balance sheet of a company, it
is treated like quasi-equity, which makes it easier to increase the component of the
usual bank or financial institution loans. Unfortunately, there is no infrastructure
funding entity that has actively explored mezzanine financing in India in any
sizeable amounts. The reasons for this include the following:
First, an impediment to the use of mezzanine financing is the lack of a sufficiently
large and varied pool of infrastructure projects. When projects and financiers are
few and far between, and when modern infrastructure financing is in its nascent
stages, there is a preference for funding institutions to opt for more straightforward
loans than hybrids.
Second, interest rate caps on external commercial borrowing (ECBs) constrain the
use of mezzanine financing by foreign investors. The interest rate caps make no
provision for pricing different debt or quasi-equity instruments commensurately
with the risks associated with them.
Third, regulatory norms and premium pricing are also factors that weigh against
mezzanine financing. The norms for provisioning against Non-Performing Assets
(NPA) do not make a distinction between senior debt and subordinated debt; the
latter deserves more liberal treatment given its quasi-equity nature. Also, sponsors
with projects that are at the margin in terms of profitability find the ‗premium‘
demanded for subordinated debt over senior debt by a host of risk-averse lenders
far too excessive—enough to turn a potentially profitable venture into an unviable
one.
(iv) Restrictions on External Commercial Borrowings (ECBs):
Given the risk aversion and/or relative inexperience of many financial
intermediaries in India in the area of infrastructure financing, external financial
resources (ECBs, mezzanine, equity, etc.) can potentially play an important role in
meeting funding gaps.
Revised ECB guidelines now allow (i) companies to access ECB for undertaking
infrastructure investment activity in India, (ii) borrowings under the approval route
by FIs dealing exclusively with infrastructure.
Despite the welcome increase in ECB for infrastructure, the fact still remains that
external funds are significantly inadequate compared to the needs. This may be
attributed to the following:
(a) One concern raised by investors is the interest rate cap on ECBs. According to
the ECB guidelines, interest rates are capped atLibor+200 basis points for loans
with an average maturity of 3-5 years, and at Libor+350 basis points for loans with
an average maturity of more than five years. It has been argued that, while these
caps may be adequate for ‗normal‘ industrial projects, they are too low to attract
funds for riskier infrastructure projects.
(b) An even greater constraint in utilizing foreign currency loans is the lack of a
sufficiently deep forwards-market in foreign exchange. Infrastructure projects
require long tenor loans, and if financed through foreign currency borrowings these
need to be adequately hedged against currency risks since few infrastructure
projects have forex earnings to serve as a natural hedge. Inability to hedge long
term currency risk in a market which is limited to one year‘s forward cover poses a
big challenge to the use of foreign currency loans in these projects.
(v) Limited use of takeout financing:
Commercial bank funding of infrastructure projects runs the risk of asset-liability
mismatch. An innovative method is to encourage the use of ‗take-out‘ finance.
Here, a bank which is funding an infrastructure project gets into an arrangement
with a financial institution, where the institution commits to buying the bank‘s
loans after a certain period. There are two versions to this arrangement:
unconditional and conditional take-out finance. The unconditional version involves
full or partial credit risk with the institution agreeing to take over the finance from
the original lender. Under conditional take-out finance, the institution commits to
taking over the finance from the lending institution only if it is satisfied with
certain stipulated conditions.
Hence, it is only unconditional takeout financing that helps bank resolve the asset-
liability mismatch since under the conditional takeout financing model, the long-
term risk still remains on the books of the banks until the take out actually
happens. Take-out financing is ideally suited for annuity and BOT type road and
housing projects. While there are some recent examples of institutions like IDFC
and Housing and Urban Development Corporation (HUDCO) trying takeout
financing as a method, this has not found much favor in India.
While unconditional takeout financing is not very common, it can give a fillip to
infrastructure financing by addressing both the unwillingness and the lack of
experience of institutional investors to participate in infrastructure financing. The
main factors limiting the use of takeout financing include the following:
(a) First, the presence of excess liquidity in the system reduces the need for banks
to quickly circulate their funds, and hence, the appetites for instruments like
takeout financing. With limited number of ‗bankable‘ projects in the fray and no
liquidity crunch, banks have no inclination to sell out these good assets from their
portfolio.
(b) Second, high stamp duties reduce the attractiveness of takeout financing and
securitization. Being a state government subject, stamp duties vary considerably
across the country. Excessive rates of stamp duties in some states have stymied the
growth in innovative financial instruments such as take-out financing and also
securitization.
(vi) Restrictive government policies and regulatory guidelines:
The investment guidelines of insurance companies specified by IRDA require them
to invest not less than 15 percent of their investments in infrastructure and social
sectors. It is understood that most of the investments by insurance companies in
infrastructure are made to State-owned specialized FIs such as National Thermal
Power Corporation (NTPC), Power Finance Corporation (PFC) (which have a
AAA rating) as also to housing sector which qualifies under infrastructure
investments. This clearly indicates the low risk-taking outlook of the insurance
companies. The guidelines also lay down a minimum credit rating of ‗AA‘ for
investments in debt paper which would automatically exclude investment by
insurance companies in debt paper of private infrastructure sponsors.
(vii) Poor state government finances:
Nearly all states suffer from serious fiscal imbalances and are ridden with huge
debt obligations. The debt to GDP ratio of states has increased by over 7 percent in
the last five years to 29.1 percent (31 March 2004). In 2003-04 interest payments
on debt accounted for over 25 percent of revenue receipts. Apart from the
increasing level of debt, the outstanding guarantees of state governments have also
recorded a sharp increase from 4.4percent of GDP in March 1996 to 7.5 percent of
GDP, or Rs.1,842 billion. Clearly, in such a situation, states are not the most
bankable business partners for private sector participation in infrastructure.
2.2.1.4 PPP policy framework constraints
An imbalance in the capacities of the public, private and community partners is the
most common limitation on successful PPP arrangements. Capacity deficiencies
affect ongoing partnership arrangements, as well as any reforms that may be
necessary due to lack of confidence. There are important potential constraints
related to project selection and contracting; however, they can be resolved or at
least mitigated through well-specified contract design.
The following issues need special attention:
(i) Lack of clearly allocated authority and responsibility in PPP policy:
In India, there is confusion and tension between different parts of government, who
naturally have very different perspectives. This is a major source of difficulty for
PPP projects. It is important to clearly define the respective authority and
responsibility between central and state government and between central and line
agencies. Full consideration must be given to adequacy of the resources required.
(ii) Predictable staging of project identification, selection and contracting:
In India, the process of identifying projects and moving forward to contract does
not follow a predictable pattern. It is difficult to predict how long it will take to
process a proposal and to finish further steps. The stages do not have well defined
procedures and the workload is not managed by efficient planning and adequate
resources. The government should define ―time bound‖ steps of the authorization
process, so that officials must meet the schedule or account for not meeting the
schedule.
(iii) Policy framework generates commercially viable project proposals:
In India, the private sector does not find many projects lucrative for bidding and
investment. The perspective of the private sector needs to be fully recognized, and
risks should be effectively managed, so that the PPP framework consistently
generates proposals that pay for themselves (with governmental support if justified
by social priorities).
(iv) Competitive tendering process is transparent in practice:
Lack of transparency in tendering is one of the greatest challenges to the PPP
process in India. Less established firms are reluctant to bid, non-competitive efforts
to win bids are encouraged, and quality standards are more difficult to uphold.
Private firms need to be assured that their performance, and the financial
attractiveness of their bid, will be the main factor determining whether they get the
contract. In addition to monitoring the transparency of the selection process,
government needs to vigilantly enforce rules for bidder behaviour, to exclude any
coordination or manipulation of the bidding process.
(i) Lack of tendering and contracting capacity:
Two of the obstacles to the wide adoption of contracting arrangements are lack of
experience in development of contract conditions and lack of data and guidelines
upon which contract specifications should be based. In order to overcome these
difficulties, governments in several countries provide their officers with advice
about different contractual arrangements, such as a list of standard specifications
that should be built into contracts.
The basic principle of PPP – the provision of value for money for public services –
can only be satisfied when a fair and transparent procurement process is in place.
Many government officials have little experience in negotiating and managing
concession contracts, which can lengthen the contract award process and increase
the costs of bidding. Decision-makers might also lack the confidence to renegotiate
the contract such that it meets the redefined objectives of the municipality.
Lack of action on the part of officials might also be attributed to lack of detailed
provision for renegotiation in the contract; imbalance in perceived negotiating
skills; lack of access to ―objective‖ support; and/or fear over the implications of
decisions made. Capacity development in negotiation is essential if the public
sector partner is unwilling to accept the support of skilled specialists.
2.2.1.5 Social constraints:
Social constraints measure the ability to administer PPP projects in a fair and
sustainable way that supports all groups in society. It includes indicators that
measure government success in promoting the PPP concept. Providing basic
services to the marginalized/poor should be one of the central aims of the
government, and should have an active role in the design of new projects and the
choice of projects. If past projects have shown interest in marginalized groups, it
will be easier to assemble systematic information about the possibilities for
effective action.
Social pressures lead to impasses and difficulties in implementing PPP projects. In
some cases, social activists protest against the displacement of poor people,
environmental degradation, loss of jobs and income, inequitable resettlement plans,
distributional inefficiencies that result from the projects and so on. In other cases,
the intended users of the project may resist tariff increases that result through
privatization. In the case of the Coimbatore bypass road, the government of Tamil
Nadu decided to toll a neighbouring bridge and include the toll revenues as part of
the financial equation for the bypass road project. However users of the bridge
were upset at a toll being charged for a facility that they had used for free
previously, and refused to pay. In particular, state-run buses that were subsidized
by their governments lobbied for and won a decision to lower the tariff rates,
which in turn placed enormous pressure on the concessionaire to break-even on
this project. The potential for societal protests and economic weaknesses in project
structuring deters the private sector and further inhibits the use of PPPs at the state
level.
The following social constraints need special attention:
(i) Perception of PPPs as a viable means of providing infrastructure and basic
services:
PPP projects face a lot of opposition and misunderstanding. The public needs to be
educated about the positive aspects and benefits of PPP to improve standard of
living. If PPP firms are already accepted as a possible way to achieving
government aims in infrastructure and basic services, it will greatly simplify the
adoption of new PPP projects.
The local government‘s policy for the provision, financing and cost recovery of
services will be a key factor in assessing whether or not it views public-private
partnerships as an acceptable approach to service delivery.
If, based on the government‘s fundamental values and policies, public-private
partnerships are not seen as a viable or accepted approach to service delivery; it is
clearly not in the community‘s best interest to proceed with individual public-
private partnerships. More commonly, local governments will establish policies
that identify the circumstances (for example, the type of service, or a particular
component of the service system) under which public-private partnerships may be
considered.
(ii) Awareness in public concerning the need for user-pays principle:
Many PPP projects rely on the user-pay principle, which says that additional
services are provided, but for a price. Stakeholders are used to the government
providing services without direct charges and may be resistant to user-pays
programs. Education is required to explain to them that the services could not be
provided unless a fee is charged, and then they are better offered.
(iii) Strategic understanding of public-private partnerships:
The most significant capacity constraint is usually with respect to the strategic
understanding of public-private partnerships. Training in PPPs and exposure to the
development of PPPs is likely to result in a broader understanding of their potential
in terms of social and institutional aspects in the municipal context; such training
will also aid understanding of the implications of long-term partnership
arrangements.
2.2.2 Sector specific constraints faced by PPPs:
The constraints faced by PPP in India vary considerably across sectors. In some
sectors, such as telecom, the obstacles and contradictions during the initial phase of
the1990s are things of the past. Through learning by-doing, the Telecom
Regulatory Authority of India (TRAI) has established itself as an efficient, fair,
expeditious and independent regulator which is respected as a body for creating a
level playing field and fostering the rapid growth of telecom in India. In sharp
contrast, the regulatory environment in power leaves much to be desired; and as
yet there is no independent regulatory institution in place for ports or airports.
Progress in the infrastructure sector during 2010–11 has been lacklustre, both in
terms of physical progress as well as in terms of policy and regulatory
developments. While 2009–10 saw policy and regulatory changes, attempts at
improving the pace of award and execution of infrastructure projects, revival of
investor interest, and more definitive future plans, 2010–11 saw a slackening in the
pace of reforms as well as development activity in almost all the sectors.
The telecom sector was mired in controversies associated with licences and the
process followed for the 2G spectrum which were allotted in 2007–08. The roads
sector saw irregularities and enquiries about the National Highways Authority of
India (NHAI), and slower than expected project award activity. The Government
of India (GoI) revised its target of building roads downwards from 20 km a day to
12–13 km a day. The ports sector did not see significant capacity addition and the
finances of the power distribution utilities worsened, with utilities starting to resort
to higher load shedding to avoid the burden of extra power purchase costs (Power
Finance Corporation Limited 2011) and to prevent their financial position from
worsening further. What stands out in almost all the sectors is the poor level of
monitoring and accountability for completing programmes and projects (Planning
Commission 2010a). Not surprisingly, the World Economic Forum (WEF) in its
Global Competitiveness Report-2010 ranked India‘s basic infrastructure at the 86th
position amongst 139 countries; a fall of 10 places compared to that in 2009. This
fall was largely attributable to the poor quality of roads, ports, and electricity
supply.
To understand the extent of constraints faced by PPP, therefore, one needs to
analyze the different sectors. The significant constraints faced by PPP across
different sectors are given below:
1. Roads
Major constraints in a highway PPP project usually include the acquisition of right-
of way, construction, environmental, Operation and Maintenance (O&M), traffic,
collection of tolls, competing roads, political intervention (policy reversals),
inflation, forex (in cases involving foreign currency financing) and force majeure.
Of these, constraint related to time and cost overruns during the construction phase
as well as traffic volume and user fees (tolls) are of particular significance from the
standpoint of private operators, as they are normally expected to absorb these risks.
By and large, the National Highways Development Program has been a success.
There has been significant learning by both government and the private sector.
Through wide-spread consultation and its own experiences, the NHAI has
stabilized a robust Model Concession Agreement (MCA) for its BOT as well as
annuity projects. Standard bidding documents have also been prepared for the
Pradhan Mantri Gram Sadak Yojana (PMGSY) contracts. Till now, there have
been no major cases of the government reneging on BOT or annuity agreements,
which has served to maintain and enhance the credibility of these contracts -
something that is lacking in the power sector.
Moreover, there has been a clear financial commitment on the part of the
Government of India in the form of setting-up a long-term ring fenced source of
finance, namely the Central Road Fund (CRF). Not only does it secure significant
long-term funds but it also helps project executing agencies such as NHAI to use it
as quasi-equity to leverage market borrowings. Despite its successes, there are
some issues that need to be addressed.
The major one relates to the small size of NHAI projects. The average size of PPP
projects (BOT, annuity and through pure contracting SPVs) is 44.6 km; that of
BOT projects is 50.4 km; and of annuity-based projects is 59.4 km. This piece-
meal approach adopted by NHAI towards awarding contracts has three negative
consequences:
(i) Entry of smaller players: First, it encourages the entry of smaller players with
limited technical and financial abilities in the bidding process — often leading to
as many as 30 bids in response to a single tender floated by NHAI. Though this
could be construed as healthy competition, it has sometimes resulted in the
selection of firms with unrealistically low bids, who later have not been able to
deliver.
(ii) Higher per unit capital cost: Smaller projects inflict higher per unit capital costs
to the contractors. As the size of the project increases the per unit cost of
mobilizing requisite physical and financial capital goes down more than
proportionally. Scaling-up project sizes will incentivize bigger domestic and
foreign players to make competitive bids and also make it economic for them to
source the requisite capital in a timely manner.
(iii) Non-lucrative for large players: Small project sizes have discouraged large
players, who can access both capital and expertise and deploy these more
effectively than fragmented operators. Diseconomies of scale have also prevented
more widespread use of annuity and BOT. Although the thrust of the NHAI‘s
NHDP program is to encourage private sector involvement in road creation,
operation and maintenance, in reality more than 80 percent of the Golden
Quadrilateral (GQ) has been completed through EPC contracts, i.e. civil works
implemented through contracts on a cash payment basis. Till date, only 9 BOT and
8 Annuity based schemes have materialized under GQ program, and none in the
NS-EW project.
The other regulatory issue relates to the Central Road Fund. Although the CRF is
ring-fenced in the technical sense of the word, the timing and quantum of
allocations to the CRF from the Consolidated Fund of India are still dependent
upon the central government. For a program as important as improvement and
modernization of roads, it is more advisable to have a statutorily independent body
administering the CRF.
2. Power
Nearly 60% of India‘s population in rural areas does not have access to electricity.
TATA Power is considering 4–5 options for addressing rural electrification needs
in a sustainable manner. For sustainable operations and supply of power in rural
areas, transparent and targeted subsidy delivery mechanisms need to be developed
so as to ensure the financial viability of the distribution business.
More than any other sector, the power sector suffers from a wholly inadequate and
non-credible regulatory regime at both the central and state government levels.
Given below are some key deficiencies:
(i) State Electricity Regulatory Commissions (SERCs) do not act in a
predictable and consistent manner in most states: The State Electricity Boards
(SEBs) have been unbundled into three distinct entities: generation, transmission
and distribution. Also in theory, with the enactment of the Electricity Act, 2003,
these entities are supposed to be monitored and regulated by independent SERCs.
However, in practice, no investor can be sure if the regulator will adjust prices, or
when, or the extent to which non-action (or injurious action) will be defended on
the grounds that social factors (especially, ―affordability‖) need to be taken into
account. Unpredictable behavior of the SERCs relates in large part to their lack of
autonomy and the fact that they are under pressure from many directions. Most, if
not all, SERC members in any state are former employees of the SEBs that they
are now expected to regulate. Moreover, the funding of SERCs comes from the
state government. Consequently, the stage gets set for serious regulatory capture by
both the state government and its SEB. In most cases, SERCs are weakened from
inception, which allows large state utilities to remain unresponsive to their
regulations.
It should be pointed out however, that the above-mentioned issues stem
predominantly from a fundamental structural flaw in the current operational and
regulatory structure of the power sector. Since the reforms in the sector have
progressed only to the extent of unbundling and establishing regulatory bodies
without actually changing ownership, the effectiveness of the regulator to regulate
the utility (which is another arm of the government) is obviously limited. The
policy maker, the regulator and the utility are all different parts of the government.
In this scenario, at the very least, there needs to be operational autonomy for the
utilities and functional and financial autonomy for the SERCs.
(ii) Access charges: The Electricity Act, 2003, which is supposed to be
adopted by all states, provides for non-discriminatory open access to transmission
and distribution lines. There are serious regulatory concerns about state owned
transmission companies stifling competition by levying prohibitively high access
charges between private sector generating companies and end-consumers. This has
often been cited as one of the major regulatory risks that could prevent an active
private sector market for the wheeling of power.
(iii) Credibility of fuel supply agreements: Every power generation
project is based upon fuel supply agreements — be it for coal or gas.
Unfortunately, neither source of fuel falls within the domain of the Ministry of
Power, and there have been serious delays in power projects because the promised
fuel supply agreement has not materialized. Moreover, fuel that is promised to be
supplied often does not arrive on time. In September 2004, one of the bigger units
of NTPC had to be shut down for five and a half days because of coal shortages.
The shortage of gas has also been quite severe in the past, which has adversely
affected the Plant Load Factor (PLF) of many plants. For example, it is estimated
that around 1,600MW of gas-based power capacity in the private sector is not
being made operational on account of fuel shortage. The Ministry of Power
estimates that but for the fuel shortages, the growth in actual generation for the first
nine months of FY06 would have been five percentage points higher. Fuel supply
poses serious concern with new plants, which even after achieving financial
closure are not able to move on to the construction phase because of their inability
to garner requisite fuel supply.
(iv) State government guarantees: Some observers believe that guarantees
could play an important role in catalyzing private investment in the power sector.
Unfortunately, the financial credibility of most state government guarantees is
clearly suspect in light of the weak fiscal position of states. By March 2004,
outstanding guarantees of all state governments were as high as Rs.1,842 billion or
7.5 percent of GDP. In addition to this, the estimated commercial losses of the
SEBs in 2005-06 were approximately Rs.226 billion (excluding subsidies). Such
financial penury does not augur well for PPPs in power. Other observers, however,
argue that in states where the fiscal situation is relatively better, state government
guarantees in fact create the wrong incentives. In Rajasthan, for example, the
state‘s transmission company can borrow (essentially, to cover losses in the
distribution sector) from commercial banks and issue bonds at surprisingly good
interest rates, despite annual financial losses of over Rs.2000 crore, as long as it
has a state guarantee. Its ability to borrow at tenors of up to 15 years may be a
factor in delaying more fundamental reform of pricing and creates an uneven
playing field against private operators who do not enjoy similar government
guarantees.
(v) Slow operationalization of the Electricity Act, 2003: Without doubt, the
Electricity Act, 2003, is good in theory. However, progress by states to frame the
rules to operationalize the Act has been slow. Consequently, it does not serve as a
guidepost for structuring projects and making investment decisions.
3. Ports
The ports sector in India has seen substantial entry by the private sector. The
introduction of the private sector has resulted in greater efficiencies as well as
competition for services. According to an estimate, by 2011–12, India requires to
step up its ports capacity to 800 million tonnes, which requires additional
investment of about US$11 billion.
On the efficiency front, although berth productivity has improved substantially
since the advent of private participation — from 20 moves per hour in the 90‘s to
70–80 moves per hour — it is far below the global benchmarks. The government
should not view private participation in ports as a revenue earning opportunity, and
instead should opt for models that would result in efficient services for the end-
users of ports.
While there is a Tariff Authority for Major Ports (TAMP) which regulates and
supervises tariffs of private sector service providers, it is not a regulator in the
wider sense of the term.
4. Airports
The rapid growth in airline services began several years ago, with the result that
the infrastructure in the metro and major non-metro airports is under considerable
strain. The recent Delhi and Mumbai airport deals had created a very high visibility
internationally for the Government‘s airport reform process.
The development of physical infrastructure in the Airways sector is inadequate to
sustain the growth momentum. Progress on existing projects has been slow and has
been substantially costlier than initial estimates. The latter is true for privatized
airports as well as airports being developed by the Airports Authority of India
(AAI). Of the 35 non-metro airports identified for modernization in June 2006,
work has been completed at 20 with another 10 under progress and the remaining
5in the planning stages.
The development of sectoral regulatory frameworks is required along with striking
a balance between competition and regulation so as to meet consumer demands
and expand infrastructure.
Airports have yet to have an independent regulator, although this was an important
recommendation of the Naresh Chandra Committee.
5. Railways
The recent turnaround achieved by Indian Railways was based on a strategy
founded on a clear understanding that the railways is not a natural monopoly, its
cost structures are highly rigid, its main competitive advantage is economies of
scale, and it needs to blend both social and commercial objectives. For instance,
Indian Railways faces competition from road transport in general, and from low-
cost airlines in the premium passenger services segment. The key for business
growth, hence, lies in offering a compelling value — a value superior to the one
offered by the other modes of transport — to the railway users.
In a similar vein, a closer examination of its cost structures reveals that, at the
current level of tariffs, its train operations would break even with 20 coaches,
whereas it has been operating trains, on an average, with only 14 coaches. Armed
with this understanding, Indian Railways is gradually shifting to 24-coach trains so
that it can make profits without altering tariffs. Already, Indian Railways has
invested Rs. 400 crore in increasing the length of both passenger platforms and
sidings at goods terminals, and earned over Rs. 6,000 crore by hauling longer and
heavier trains. As part of its efforts to blend social and commercial objectives,
Indian Railways is pursuing the ―fortune at the bottom of the pyramid‖ through
initiatives such as Garib Raths, fully air-conditioned trains at tariffs that are less
than 40% of the existing fares.
As a result, Indian Railways has succeeded in increasing its internal revenue
generation from US$ 0.5 billion in 2000–01 to US$ 4.5 billion in 2006–07. During
the same period, it managed to bring the operating ratio — expenses divided by
traffic earnings— down from 98% to 78%.
However, Indian Railways has refused to have a regulator despite the
recommendation of the Rakesh Mohan Expert Group. In Railways, the lack of a
regulator has allowed the Container Corporation of India (CONCOR), a subsidiary
of Indian Railways, to exercise complete monopoly rights of managing and linking
up inland container depots (ICDs) with container freight stations (CFSs) at ports, to
the detriment of port-side container terminals although this monopoly is now being
ended by allowing private sector to offer linkages to ICDs. The lack of
independent regulators in these critical sectors creates problems for future
deregulation, and fails to provide comfort to potential investors in terms of
predictability and stability.
6. Telecom
The telecom sector made commendable progress during 2010–11 on physical
parameters. With 811.59 million connections at the end of Fiver Year 2010–11
(Telecom Regulatory Authority of India 2011a), the Indian telecom network
became the second largest wireless network in the world after China.
On the policy and regulatory front, the sector was embroiled in controversies on
issues relating to the allotment of new unified access services (UAS) licences and
the 2G spectrum in 2007–08. A report of the Comptroller and Auditor General
(CAG) of India concluded that the government exchequer incurred a loss of
between Rs 67,364–176,645 crore on account of such allotment. The UAS licences
had been issued at a price discovered in 2001 when the market was at a nascent
stage of development as opposed to an appropriate market price in 2008 when the
sector had undergone substantial transformation and manifold growth. Moreover,
the licences were issued on a single day. These actions prompted questions
regarding transparency in the licence allocation process and the failure in
maximizing revenue generation for the government from the allocation of
spectrum. Another controversy in the sector was related to spectrum hoarding and
exaggeration of subscriber numbers to garner additional spectrum.
These controversies coupled with the other pressing issues facing the sector (such
as availability of spectrum, impending strategy for penetration of broadband, and
security issues regarding telecom equipment procurement, messenger services, and
subscriber verification) are acting as barriers to Public Private Partnership Projects
in the telecom sector.
2.3 Public Private Partnerships (PPPs) in Uttar Pradesh
2.3.1 Status of Public Private Partnership projects in Uttar Pradesh
According to World Bank Report (2006), across states and central agencies, the
leading users of PPPs by number of projects have been Madhya Pradesh and
Maharashtra, with 21 and 14 awarded projects respectively, all in the roads sector,
and the National Highways Authority of India (NHAI), with 16 projects. The other
states or central agencies that have been important users of PPPs are Gujarat (9
projects) and Tamil Nadu (7), Karnataka (4) and Ministry of Shipping, Road
Transport and Highways (MOSRTH) (4).
However, looking at a breakdown by estimated project size, we see that MP
becomes significantly less prominent due to the large number of relatively small-
sized projects in its portfolio, falling to 3 percent of total project costs. Gujarat
accounts for 48 percent of total project costs due to its four large port projects.
NHAI (17%) and MOSRTH (12%) are the other significant players. Karnataka
accounts for 7 percent of total project costs given that its one awarded PPP project,
the Bangalore-Mysore road corridor (currently under construction) had a reported
project cost of Rs 22.5 billion.
If we look at the World Bank report (2006), we find that Uttar Pradesh constituted
only 2% of the total PPP projects in India worth Rs.4.074 bn. This is a very
pathetic situation and the state government needs to take serious measures to
attract private investment in infrastructure projects.
The figure 2.4 and figure 2.5 below shows the status of Uttar Pradesh in Public
private partnership projects with rest of the country:
Figure 2.4: Number of PPP projects across states and central agencies
(Total = 86 projects)
Source: PricewaterhouseCoopers Report, 2006
Figure 2.5: PPP projects across states and central agencies according to
project size (Total= Rs. 339.5 billion)
Source: PricewaterhouseCoopers Report, 2006
At the end of year 2009, Uttar Pradesh had lined up Rs 125,000 crore projects for
private investment under the public-private partnership mode. These projects have
either been launched or awaiting the nod and are spread over all major sectors like
power, transport, education, tourism, infrastructure, urban development and health.
Major projects include Greater Noida-Ballia Ganga Expressway, Noida-Agra
Yamuna Expressway, power plants in Allahabad, Fatehpur, Anpara and Lalitpur,
proposed international airport at Kushinagar and setting up of super specialty
hospitals in seven towns/cities.
However, in Uttar Pradesh, there is no specialized institutions and legal framework
like other states. The project development responsibility is with state level
government agencies and departments. After realizing that private investment is
necessary for the development of Uttar Pradesh, the government machinery has
offered tax, fee and levy exemptions for setting up industry to make it an attractive
investment destination. However, the response from private players is slow
because of lack of confidence among investors and constant complaints regarding
obstructions and delays while executing projects in the Uttar Pradesh. During a
survey to find the reason for the low level of interest among investors in the state,
it was found that the risk of their money getting stuck up was the major deterrent
for the private sector.
2.3.2 Public Private Partnership projects in Uttar Pradesh in various sectors:
1. EXPRESSWAYS:
(i) Yamuna Expressway
The project was inaugurated by Chief Minister Akhilesh Yadav on 9th August,
2012. This 165 km long 6-lane access controlled concrete pavement expressway
between Greater Noida and Agra has opened new avenues of development for the
towns of the area through which it is passing. It provides hassle free connectivity
with major towns of the area i.e. Aligarh, Hathras and Mathura. Adequate
provision of interchanges shall facilitate the exit and entrance from the expressway
to/from other important roads. The travel time on the expressway shall be less than
2 hours from Greater Noida to Agra.
The project has been completed under Public Private Partnership (PPP) model. The
players in this project are Yamuna Expressway Industrial Development Authority
(Government agency) and Jaypee Infratech Pvt. Ltd. (Private company). The
estimated cost of the project is Rs.10,374 crores. The construction work of the
expressway has been completed. The construction work of all 3 Toll Plazas is in
progress. Overall progress of the project has been registered at 93.46% in
February, 2013.
(ii) Ganga Expressway
The Ganga Expressway project was launched by Uttar Pradesh Chief Minister
Mayawati after coming to power in 2007. The 1047 km long 8-lane access
controlled Ganga Expressway costs Rs.30,000 crores and is proposed to run from
Greater Noida to Ballia. This Expressway has been planned along the river Ganga
and has been designed as a flood control embankment. The Ganga Expressway is
expected to considerably reduce the travel time across the state. When completed,
it would be amongst the biggest infrastructure projects implemented through PPP
mode in the country. The Expressway will pass through Districts Gautam Budh
Nagar, Bulandshahr, Aligarh, Badaun, Kanshiram Nagar, Farrukhabad,
Shahjahanpur, Hardoi, Unnao, Raebareli, Pratapgarh, Allahabad, Sant Ravidas
Nagar, Mirzapur, Varanasi, Ghazipur and Ballia. Links from Fatehgarh, Lucknow
and Mirzapur are to be constructed to provide access from these districts to the
Expressway. Toll free service road shall also be constructed along the Expressway
for the convenience of local people.
The construction of the expressway is going to be done under a Public Private
Partnership (PPP) model. The state government of Uttar Pradesh accepted bids
from various infrastructure companies. A total of 18 developers submitted proposal
to build the expressway. Some of the companies which submitted the bids included
DLF Universal, GMR Group, Jaypee Group, Larsen & Toubro, Omaxe-GVK-
Nagarjuna, Reliance Energy, Unitech Group. The Uttar Pradesh government
awarded the Ganga Expressway contract to Jaypee Infratech Pvt. Ltd. According to
the contract, Jaypee will build the expressway at no cost to public finance, in
exchange for the right to maintain, operate and collect tolls on the expressway for a
35-year period and right to procure and develop a few land parcels for commercial
activity along the 1047 kilometer expressway. The construction was anticipated to
be started by April 2008. However, a series of land acquisition issues, legal
challenges and judicial motions have prevented construction work on the Ganga
Expressway.
To address the land acquisition issues, the government of Uttar Pradesh announced
a revised land acquisition policy in June 2011. This policy is part of what the state
government calls ―Karar Niyamavali,‖ the guiding policy for land acquisition by
the government from the citizens of its state. This policy‘s section 6 provides
certain protections to any farmer whose land has been fraudulently transacted. The
rules require that any fraudulent transaction be considered for appeal and
cancelled. The farmer whose land has been fraudulently transacted has a right to
compensation and damages from the state government whenever fraud is
discovered and reported.
Construction work on Ganga Expressway has not yet started because of a stay
order from the High Court of Uttar Pradesh. The order instructed that the state and
the concessionaire complete a full environmental study and obtain permission from
the central government before embarking on the construction. The concessionaire
completed the study and submitted its proposal with Ministry of Environment and
Forests in New Delhi, in April 2011, to obtain environmental clearances, as
required by recently enacted Indian environmental laws. However, the proposal
has been rejected by the Ministry. It has directed that UPEIDA being project
promoter, is required to file application for clearance. UPEIDA is in the process of
submitting application for obtaining NOC to Ministry of Environment and Forests.
The future of this project is uncertain.
(iii) Upper Ganga Canal Expressway
This proposed 148 km long 8-lane access controlled Expressway starting from
Sanouta Bridge in Greater Noida is passing through western Uttar Pradesh and will
connect National Capital Region (NCR) to Uttarakhand border near Purkazi. This
unique multi-dimensional project includes development of Expressway, 7 Hydro
Electric Power Stations (HEPS) and navigation facilities, besides the ancillary
works of rehabilitation of Upper Ganga Canal, construction of service road
and access road, raising of NH bridges and railway bridges and connecting roads
and interchanges. The state government has selected consultant M/s IL & FS IDC.
The project cost of 147.8 km long Expressway and 68.5 km long link Expressway
including 7 hydro electric power stations and navigation facilities has been
estimated approximately Rs.8, 911 crores.
Request For Qualification (RFQ) for selection of Developer was issued on 24th
January 2010. As many as 7 bids were received against the RFQ issued for
selection of Developer. Request For Proposal (RFP) has been issued to 6 short
listed bidders. Bid parameter shall be Highest Negative Grant or Lowest Value of
Land Parcels opted for Development Rights. Due to slow response, the date of
receiving of RFP document has been postponed till further notice.
(iv) Development of 06-Lane Access Controlled Expressway on the Right
Bank of Upper Ganga Canal from Sanouta Bridge (Greater Noida) to
Kanpur-Fatehpur
Uttar Pradesh government has entrusted this project to UPEIDA for the study of
the technical and financial viability of the project, owing and execution. Consultant
for preparation of concept report has been selected.
(v) Agra to Lucknow Green Field Expressway
This 08 lane access controlled Expressway from Agra to Lucknow is to be built on
PPP mode. This green field expressway shall be based on minimum distance
formula having the potential of providing a smooth link from Greater Noida to
Lucknow. Hence the journey time from Greater Noida to Lucknow via Agra
covering about 530 km, which presently consumes around 9 hours would now
drastically be reduced to 5 hours. Likewise the 6 hours journey of 365 km between
Agra and Lucknow would reduce to around 3.30 hours through this proposed
Expressway. UPEIDA has been nominated as nodal agency. The selected
consultant, M/s Redicon (India) Private Ltd. has prepared Concept Report for this
Expressway. The revised E.O.I.-cum- R.F.P. for selection of consultant was issued
on 24.11.2012 and its submission from interested parties is awaited.
(vi) Jhansi-Kanpur-Lucknow-Gorakhpur-Kushi Nagar Expressway
Pre-feasibility study for this project is to be conducted. Vide G.O. no. 695A/77-3-
2008-34M/07TC dated Feb.28.2008 issued by Industrial Development
Department-3, GoUP, UPEIDA has been entrusted the expressway ―Jhansi –
Kanpur – Lucknow – Gorakhpur – Kushinagar (on the bank of river Betwa &
Gaghra) connecting Southern to Eastern boundaries of the State‖ for development
under PPP Model. Concept report/proposed alignment of Expressway is under
preparation/Finalization. Environmental Impact Assessment (EIA) study of the
Expressway is also under progress.
2. TOURISM
(i) Leasing & Management Contract of Tourism Properties
The Department of Tourism, Government of Uttar Pradesh has proposed to
develop the properties through leasing out to private sector parties with the
objective of promoting tourism, providing upgraded facilities to users, better
management and unlocking of the commercial values of properties. Department
has invited Request for Proposal (RFP) for design, finance, development,
construction, up-gradation, maintenance and management of 68 properties through
Private Public Partnership. RFP for selection of developer has been issued on
25.10.2011. Due to slow response, the last date of submission of RFP bid has been
postponed till further order.
(ii) Kushinagar International Airport & Buddhist Circuit
Site survey has been done by Directorate General of Civil Aviation (DGCA), Govt.
of India on 02.09.2009 for granting NOC from Civil Aviation Ministry. RFQ-cum-
RFP being prepared by consultant for selection of developer. Viability Gap
Funding (VGF) proposal is to be sent to Ministry of Finance, GoI for sanction. 32
bids were received against (Expression of Interest) E.O.I. issued on 04.05.2012
after in principal approval for VGF.
(iii) Development of Passenger Ropeways
The Government of Uttar Pradesh has decided to develop Passenger Ropeways at
the following three places through Public Private Partnership mode as an added
attraction to the tourists:
Radha Rani Temple (Ladlee ji Temple) in Barsana, Mathura in Braj Region
From Ashtabhuja to Kalikhoh in Mirzapur in Vindhyachal Region
Devangana in Chitrakut in Buldelkhand Region
M/s UDIC, M/s UDFC, M/s Innovest Dehradun (Consortium) have been selected
as consultant and Letter of Intent (LOI) was issued on 16.08.2012. The Consultant
is required to carry out the entire bidding process management for selection of
developer and also to carry out the preliminary assessment of social and
environment impact assessment etc.
(iv) Development of Waysides Public Amenities
The Government is keen to provide better facilities to road users especially clean
toilets and potable drinking water and also to the tourists. In this context, Director
General, Department of Tourism, Government of Uttar Pradesh has invited
Expression of Interest from Private Sector Parties to develop Waysides Amenities
along the major transport corridors of the State under PPP mode.
The last date of submission of EOI was fixed as 14.08.2012, wherein 75 proposals
were received. Initially, a committee has been constituted for deliberation on 20
proposals.
3. POWER
The PPP projects in Power sector include power generation projects, power
transmission projects and power distribution projects. These are discussed in detail
below:
(i) Generation Projects
The following power generation projects are under PPP
(a) Bara Thermal Power Project
This project has been proposed at Tehsil Bara in Allahabad. The capacity of this
project is 3 x 660 MW. The estimated cost of project is Rs. 11,500 crores. Letter of
intent has been issued and Shell Company is transferred to developer. The
environmental clearance has been obtained and the first unit is expected to
commence operation by July 2014.
(b) Karchana Thermal Power Project
This project has been proposed at Tehsil Karchana in Allahabad. The capacity of
this project is 2 x 660 MW. The estimated cost of project is Rs. Rs. 7,600 crores.
Letter of intent has been issued and Shell Company is transferred to developer. The
environmental clearance has been obtained and the first unit is expected to
commence operation by January 2014.
(c) Jawaharpur Thermal Power
The capacity of this project is 2 x 660 MW. The estimated cost of project is Rs. Rs.
6,600 crores. Jawaharpur Vidyut Utpadan Limited has been incorporated by Uttar
Pradesh Power Corporation Ltd. as SPV (Shell Company). Request For
Qualification (RFQ) is received from 19 bidders out of which 17 bidders have been
shortlisted. Request for Proposal (RFP) has been issued to 17 shortlisted bidders
Power Project.
(d) Yamuna Expressway Thermal Power Project
The capacity of this project is 2000 MW. Yamuna Power Generation Company
(SPV) (A joint venture of Noida Authority, UPPCL, Greater Noida Authority and
Yamuna Expressway Authority) has invited tenders for appointment of consultants
for preparation of Feasibility report and DPR for establishing this thermal power
project in Gautam Budha Nagar/NCR region.
(e) Dopaha Thermal Power Project - 3 x 660 MW
The capacity of this project is 2000 MW. The estimated cost of project is Rs.
10,000 crores. Consultant has been selected for preparation of feasibility report,
DPF and Environment clearance for MOEF.
(ii) Transmission Projects
For strengthening the power transmission network across the State and to enhance
reliability, Govt. of U.P has decided to adopt the PPP mode for execution of the
transmission project. Consultant has been selected. The process of selection of
Developer for two packages for transmission work is in progress. This would be
the first major private participation in transmission. Uttar Pradesh Power
Transmission Corporation Ltd. (UPPTCL) would facilitate acquisition of land
along with various clearances and technical surveys. The details of the projects are
given in Table 2.1 below:
Table 2.1: Power Transmission projects under PPP mode
Packages Particulars
Package-I
Transmission Sub Station (Package-I) - South East
UP Power Transmission Company.
765 KV sub station and related lines.
M/s Isolux consortium selected as Developer. LoI
issued. Bank guarantee deposited.
Signing of Share Purchase Agreement with
Developer is in process.
Package-II
Transmission Sub Station (Package-II) – Western
UP Power Transmission Company.
400 KV sub station and related lines.
M/s Cobra MELI consortium selected as
Developer. LoI issued. Bank guarantee deposited.
Share Purchase Agreement signed with Developer.
Source: http://udyogbandhu.com
(iii) Distribution Projects
UPPCL is implementing Input Based Franchisee models in urban areas. Agra city
has already been handed over to the franchisee (Torrent Power) and for Kanpur
city franchisee has been finalized and the distribution system is yet to be handed
over.
4. TRANSPORT
(i) Engagement of Bus Operators/ Private Investors
This project aims to select private operators / Investors to run the buses on the
roads of State of UP. The Deloitte Touhe Tohmatsu India Pvt. Ltd. is selected as
consultant. The process for preparation/issuance of Request For Qualification
(RFQ) document is delayed due to stay granted by High Court.
(ii) Project for Development of modern bus stations by UPSRTC
The original project of UPSRTC i.e. Modernisation, Redevelopment and
Management of bus stations of UPSRTC under PPP mode was reviewed during
Uttar Pradesh Chief Minister Akhilesh Yadav‘s meeting held on 27.04.2012. In
compliance thereof, UPSRTC has appointed consultant / transaction advisor for
selection of bus stations, who have started study in this regard.
5. UTTAR PRADESH STATE HIGHWAYS AUTHORITY (UPSHA)
The upgradation of State Highways has been proposed under Public Private
Partnership model. The detail of projects along with their present status is given in
Table 2.2 below:
Table 2.2: State Highway projects under PPP mode
S.
N
o
Name of
Roads
Lengt
h in
Km
Estimate
d cost
(Rs. Cr.)
Status
1.
Delhi-
Saharanpur-
Yamunotri
Road (SH57)
206.09 1718.35
M/s SEW - Prasad Consortium
Infrastructure Limited, Hyderabad
selected as a developer. Concession
agreement signed on
01.08.2011.Independent Engineer
selected, agreement signed on
28.02.2012.
2.
Bareilly-
Almora-
Bagheshwar
Road (SH-37)
54 354.07
M/s PNC Infratech Ltd., Agra selected
as developer. Concession agreement
signed on 01.08.2011. Independent
Engineer selected, agreement signed
on 08.02.2012.
3.
Varanasi-
Shaktinagar
Road(SH-5A)
115 1211.96
M/s APCO Chetak - Patel Ltd.,
Lucknow selected as a developer.
Letter of award issued on 15.11.2011.
Concession agreement signed on
08.12.2011. RFQ cum RFP issued on
16.03.2012 for selection of
Independent Engineer. Bids opened on
20.04.2012, 7 bids received which are
under evaluation.
4.
Akbarpur-
Tanda-
Jaunpur-
Mirzapur-
Dudhi Road
(SH-5)
207.47 829
Consultant selected, feasibility report
has been prepared by the consultant is
being examined. Proposal for VGF
under preparation.
5.
Sahjahanpur-
Hardoi-
Lucknow
Road (SH-25)
162 1039.83
Consultant selected, proposal for VGF
submitted to GOI on 31.01.2011. RFQ
issued for selection of developer on
22.11.2011. Bids opened on
28.03.2012. 12 bids received which
are under evaluation.
6. Meerut- 87.155 583.23 M/s Abhijeet Road Ltd. Nagpur
Karnal Road
(SH-82)
selected as developer. Concession
agreement signed on 08.12.2011.
Further RFQ cum RFP for selection of
IE issued on 16.03.2012. Bids opened
on 20.04.2012, 8 bids received, which
are under evaluation.
7.
Gorakhpur-
Maharajganj
Road (SH-81)
53.160 159
Consultant selected, feasibility report
has been prepared by the consultant is
being examined.
8.
Basti-
Mehndwal-
Kaptanganj-
Tamkuhi
Road (SH-64)
166.12 303.05
Consultant selected, feasibility report
has been prepared by the consultant.
Proposal for VGF submitted to GOI
on 20.05.2011. RFQ issued for
selection of developer on 22.11.2011.
Bids opened on 28.03.2012. 10 bids
received which are under evaluation.
9.
Moradabad-
Chandausi-
Badaun Road
(SH-43)
164.17 656
Consultant selected, feasibility report
has been prepared by the consultant is
being examined. Proposal for VGF
Under preparation.
10.
Farenda-
Naugarh-
Barhni-
Tulsipur-
Balrampur-
Gonda Road
(SH-1-A)
230 690
Consultant selected, feasibility report
has been prepared by the consultant is
being examined. Proposal for VGF
under preparation.
11.
Garh-Meerut-
Baghpat-
Sonipat Road
(SH-14)
90.42 900
Consultant selected, feasibility report
has been prepared by the consultant is
being examined. In the BEC meeting
dated 25.04.2011, it has been decided
that clarification should be shout out
regarding land near Meerut Bye Pass
before releasing the RFQ. Proposal for
VGF under preparation.
12.
Etawah-
Mainpuri
(SH 83)
52.82 370 Consultant selected. Feasibility report
is being prepared by the consultant.
13. Aligarh 38.96 300
Mathura (SH-
80)
Consultant selected. Feasibility report
is being prepared by the consultant.
14. Etah Tundla
(SH-31) 57.16 400
Consultant selected. Feasibility report
is being prepared by the consultant.
15.
Etah
Shikohabad
Marg (SH-85)
52.5 368 Consultant selected. Feasibility report
is being prepared by the consultant.
16.
Varanasi
Bhadohi-
Gopiganj
(SH-87)
60.12 375 Consultant selected. Feasibility report
is being prepared by the consultant.
17.
Tarighat -
Bara Road
(SH-99)
40 280 Consultant selected. Feasibility report
is being prepared by the consultant.
18.
Kalwari-
Barhalganj-
Lal-Ghuthni
(SH-72)
189.82 580 Consultant selected Feasibility report
is being prepared by the consultant.
19.
Muzaffarnaga
r Saharanpur
via Deoband
(SH-59)
52.70 369
M/s Krishna Techno committee (P)
Ltd. has selected as Consultant,
agreement signed on 05.12.2012,
feasibility report is being prepared by
the consultant.
Total 2079.7 11486.49
Source: http://udyogbandhu.com
6. HOUSING & URBAN PLANNING
(i) Inner Ring Road project, Agra
This project has been proposed under Public Private Partnership model. The
consultant and developer for the project are to be selected. Land acquisition is
under process by Agra Development Authority. The last date of submission of bids
for consultant was 12.11.2012. Four bids have been received and they are being
examined.
(ii) Northern Peripheral Road, Ghaziabad
The construction of 4 lane 20 Km. length road starting from Vazirabad (Delhi
Border) to Hapur Road has been proposed under Public Private Partnership model.
The Ghaziabad Development Authority has been nominated as nodal agency for
the project. M/s Feedback Venture & Services Pvt. Ltd. has been selected as
consultant and TEFR is being prepared.
(iii) International Cricket Stadium
The construction of an International Cricket Stadium has been proposed under
Public Private Partnership model. M/s Innovest Advisory Services Pvt. Ltd. and
M/s IDFCUDEC, Gurgaon have been selected as consultant.
7. TECHNICAL EDUCATION
(i) Medical Education Department
The State government has decided to run the two newly established State
Medical Colleges at Azamgarh and Banda and one Para Medical College in Safai
on PPP Model. M/s Crisil Risk and Infrastructure Solution was selected as
consultant. The details are given below:
8. URBAN DEVELOPMENT DEPARTMENT
(i) Solid Waste Management plant Project:
The solid waste management plant has been launched in 26 cities of the state to
provide better amenities in the Urban Areas. The cities are Lucknow, Varanasi,
Allahabad, Meerut, Gorakhpur, Moradabad, Aligarh, Jhansi, Mathura, Agra,
Kanpur, Muzaffar Nagar, Firozabad, Etawah, Rae Bareily, Mirzapur, Loni
(Ghaziabad),Mainpuri, Basti, Barabanki, Kannauj, Ballia, Fatehpur, Badaun,
Sambhal (Moradabad) and Jaunpur. The project comprises of door to door
collection, primary storage, secondary collection, transportation up to processing
State Medical Colleges:
1) Azamgarh – The bids from private players were opened on 07.03.2011, 5 bids
were received. The evaluation is under process.
2) Banda - The bids from private players were opened on 07.03.2011, 6 bids were
received. The evaluation is under process.
Para Medical Colleges:
1) Saifai – Request For Qualification (RFQ) was issued on 15.01.2011. Pre bid
conference was held on 11.02.2011. The bids opening date was 07.03.2011.
No bid has been received so far.
As per decision of BEC held on 11.11.2011 the services of M/s Crisil Risk and
Infrastructure Solution has been terminated. Action for appointment of consultant
is being taken.
plant, installation of processing plant and development of sanitary engineered land
fills. Out of 26 projects, 10 projects viz Kanpur, Kannauj, Muzaffarnagar,
Moradabad, Etawah, Mainpuri, Mathura, Aligarh, Barabanki and Raebareli have
been completed. The plants at Fatehpur, Agra and Allahabad are almost (85-90%)
competed. Speedy land acquisition process / physical work is in progress
in other cities.
(ii) Establishment of New Modern Slaughter House at Meerut, Jhansi and
Moradabad:
To ensure slaughtering under hygienic conditions and to provide healthy meat to
the public, the project for establishing a new slaughter house under PPP mode with
modern mechanised system of slaughtering and handling of slaughtered bye-
products has been undertaken at Meerut, Jhansi and Moradabad. The details are
given below:
(a) New Modern Slaughter House at Meerut:
The estimated cost of the project is Rs. 101.76 crores. M/s Abacus Legal Group,
Delhi has been selected as the consultant. During selection process (2nd time) of
developer, only one bid was received. In the mean time, the decision of High Court
on W/P No. 71568/2010 was released, which was in the favour of bidder from
whom only bid was received earlier. Nagar Nigam, Meerut has refered the matter
to Supreme Court. Subsequently, Chief Minister Akhilesh Yadav has given
instructions, during PPP projects review meeting held on 27.04.2012, to put up a
detailed note before the Chief Secretary for obtaining necessary directions.
(b) New Modern Slaughter House at Jhansi
The estimated cost of the project is Rs. 82 crores. M/s Abacus Legal Group, Delhi
has been selected as consultant. Process for selection of developer started in
December 2010 but it could not be materialised. Now the process is to be started
afresh as per direction given by the government. Accordingly action has to be
taken by Nagar Nigam, Jhansi.
(c) New Modern Slaughter House at Moradabad
The estimated cost of the project is Rs. 55 crores. M/s Abacus Legal Group, Delhi
has been selected as consultant. Process for selection of developer has been
started. The BEC under chairmanship of IIDC on 25.04.12 approved the Request
for Qualification (RFQ) and directed the Nagar Nigam, Moradabad to issue RFQ
for obtaining bids, which is delayed due to local bodies election.
(iii) Operation of city bus service in selected cities
This project relates to Financing, Operations & Maintenance of city bus services in
selected cities of state under JNNURM of Govt. of India. The selected cities are
Lucknow, Kanpur, Meerut, Varanasi, Allahabad, Agra and Mathura. UMTC, New
Delhi has been selected as consultant. The process for selection of developers was
undertaken twice by the department, but it could not be materialized. The project
was put up before Chief Minister Akhilesh Yadav during PPP project review
meeting held on 27.04.2012. It was directed to run the project under PPP. To
implement the scheme under PPP mode, matter is being considered afresh. At
present, the city buses in mission cities are being operated through SPV by
UPSRTC.
(iv) Upgradation, Operation & Maintenance of street lights in city zone
Ghaziabad
The project relates to upgradation, operation and maintenance of street lights in
Ghaziabad city zone by replacing existing lighting system. Besides saving energy
as well revenue, it is also proposed to obtain carbon credits by implementing this
project. M/s Deloitte, New Delhi has been selected as the consultant. Preparation
of Request for Qualification (RFQ) for developers is under process. The project
was put up before Chief Minister Akhilesh Yadav during PPP project review
meeting held on 27.04.2012 and it was directed to undertake the project and also
explore the possibilities of solar energy based lamps.
2.4 References:
1. Alexander, I., Estache, A. and Oliveri, A. (1999), ―A Few Things Transport
Regulators Should Know about Risk and the Cost of Capital.‖ Policy
Research Working Paper 2151, World Bank, Washington, DC.
2. Committee on Infrastructure Financing (2007), ―The Report of the
Committee on InfrastructureFinancing‖, Government of India, New Delhi,
India.
3. Compendium of PPP Projects in Infrastructure, (2007), Secretariat for
Infrastructure, Planning Commission, Government of India.
4. DEA, MoF, GoI (2007), ―Meeting India‘s Infrastructure Needs with Public
Private Partnerships - The International Experience and Perspective‖,
International Conference Report, Ministry of Finance, New Delhi, India.
5. Economic Survey 2007-08, Ministry of Finance, New Delhi.
6. Eleventh Five Year Plan, Volume I, II and III (2007), Planning Commission,
New Delhi.
7. Gomez-Ibanez, J.A., D. Lorrain, M. Osius (2004), The Future of Private
Infrastructure Taubman Center for State and Local Government. Kennedy
School of Government, Cambridge, MA.
8. Harris, C. (2003), ―Private Participation in infrastructure in Developing
Countries - Trends, Impacts and Policy Lesson”, IMF Working Paper, IMF
Institute, 33-65
9. Harris, S., (2004), Public Private Partnership: Delivering Better
Infrastructure Services, World Bank, India-Country Framework Report for
Private Participation in Infrastructure, March 2000, Washington DC.
10. Harris, C. (2008), ―India Leads Developing Nations in Private Sector
Investment.‖ Gridlines series, no. 30, PPIAF, Washington, DC.
11. Infrastructure Development Finance Company Limited. (2006). India
Infrastructure Report 2006. Anupam Rastogi, Ed. New Delhi: Oxford
University Press
12. Kochhar, Kalpana (2008), IMF Asia and Pacific Department, Business
Standard, May 4, 2008.
13. Michael B. Gerrard (2001), Public-Private Partnerships, Finance
and Development, IMF, Vol. 38, No.3, September 2001, Washington.
14. Ministry of Finance (2005), Scheme for support to PPP in Infrastructure,
New Delhi.
15. Mohan Rakesh (2006), Economic reforms in India – where are we and
where do we go? Public Seminar by the Institute of South Asia Studies,
Singapore, November 2006
16. Patil Committee (2005), Report of the High Level Expert Committee on
Corporate Bonds and Securitization, New Delhi: Ministry of Finance.
http://www.sebi.gov.in/debt/expertreport.pdf.
17. PricewaterhouseCoopers (2007), ―Infrastructure Public-Private Partnership
(PPP) Financing in India.‖ Draft report prepared for the World Bank with
support from PPIAF, Washington, DC.
18. Ramamurthi, R. (2003). ―Can governments make credible promises?
Insights from infrastructure projects in emerging economies‖. Journal of
International Management. 9, 253-269
19. Union Budget 2006-07, Ministry of Finance, New Delhi.
20. Vernon, R. (1971), Sovereignty at Bay: The Spread of U.S. Enterprises. New
York: Basic Books.
21. World Bank Report (2006), ―Financing Infrastructure: Addressing
constraints and challenges‖, Finance and Private Sector Development Unit,
South Asia Region
22. World Bank Report (2006), ―India – building capacities for Public Private
Partnership‖, Energy and Infrastructure Unit and Finance and Private Sector
Development Unit, South Asia Region.
23. World Economic Forum, (2010), ―The Global Competitiveness Report‖
24. www.rbi.org.in/scripts/BS_VIEWContent.aspx?ID=1912
25. www.udyogbandhu.com/topics.aspx?mid=Expressways