changes to part i & part viii related to structures specifications and... · part viii related...
TRANSCRIPT
Modify the architecture for Part VIII to
bring together related specifications and
accommodate future technologies and
specifications.
Section 104.05, Guarantee and Warranty of
Contractor’s Work
Guarantee period changed 1 year => 3 years, except for projects on
NHS routes, which will remain at 1 year
Guarantee and Warranty begin at final acceptance of the work
Renamed Section 105.02 Plans and Submittals
Standardized the submittal process, Section 105.02.2
Defined Submittal – Detailed drawings and documents provided by
the Contractor as required by the contract
Submittal process
Record – Once received by Project Engineer work can proceed
Review – Submittal goes through the review process until submittal acceptance
and then work may proceed
Set minimum submittal review periods for bidding purposes
Section 105.14, Load Restrictions
Contractor’s Responsibility
Responsible for evaluation of the structure with respect to his
construction activities and imposed loads, including the live load
identified on the plans.
Department’s Responsibility
Responsible for analyzing special permit loads requesting to transit
the construction site. Contractor required to provide construction
loads so the Department can perform the analysis.
Renamed and expanded Section 105.19, Bidder
Inquiries, Contractor Request, and Proposals
Defined different types of communications
Bidder Inquires – Falcon
RFI – Request for Information
To be used for plan and specification clarification only.
Value Engineering Proposal
To be used for proposals that reduce project cost and provide cost
savings shared with the Department
Contractor Proposal
New Proposal Type – cost increase or decrease
Usually at Contractor’s expense
Documents changes in the contract
Examples – bent redesigns, precast bottom forms, material
substitution, construction sequence requiring structural review, top
down construction, cofferdam redesign, Huey P. Long Big Lift, etc.
Contractor and VE Proposals
Contractor cannot base bid on proposal
Must satisfy all design criteria and not impair the essential functions
and characteristics of the project, as determined by the Department
No modification will be permitted which alters the nature of the
project or which is not an integral part of the project objective
Formally documents changes to the contract
The Department has the right to say “No”
801 General Requirements
802 Structural Excavation, Backfill and Earth Retaining Systems
803 Drilled Shafts
804 Piles
805 Structural Concrete
806 Deformed Reinforcing Steel
807 Structural Metals
808 Steel Grid Flooring
809 Welding
810 Bridge Railings, Hand Railings, Permanent Roadway
Barriers, and Pier Protection Systems
811 Painting and Protective Coatings
812 Treated Timber
813 Concrete Approach Slabs
814 Bearings
815 Joints
816 Bridge Drainage Systems
817 Temporary Works
818 Marine Pier Protection
820 Movable Bridge
821 Mechanical Systems
822 Electrical systems
823 Facilities
829 Instrumentation and Evaluation
830 Repair and Rehabilitation
New or repurposed
sections
Modified the architecture and completely re-wrote
Part VIII
Reorganized Part VIII in general construction sequence
Consolidated submittal requirements within sub-
sections when possible
Incorporated existing NS special provisions and
supplemental specifications when possible
Established Format for Submittals
Works in concert with Part 1
Modernized submittal review process (Electronic)
Established improved procedures for project documentation
Established requirements for structural submittals
Provides additional requirements to Part I with respect to structures
Combined Section 803 Sheet Piles with 802 Structural
Excavation and Backfill and added earth retaining
systems
Clearly Defined Types of Sheet Piles
Permanent Sheeting – designed by EOR – paid / SqFt
Temporary Sheeting – designed by EOR – paid / SqFt
Removed when no longer needed
Contractor Sheeting – designed by Contractor – no direct
payment
Removed when no longer needed
Added Section on MSE Walls
814 Drilled Shaft Foundations => 803 Drilled Shafts
Places all foundation element specifications near the front of Part VIII
Adopted and modified Dan Brown Specification from
NHI Drilled Shaft Course
Aligned with AASHTO LRFD Bridge Construction
Specification and AASHTO LRFD Bridge Design
Specification
Require a Drilled Shaft Installation Plan
Require a Drilled Shaft Preconstruction Conference
Opened up testing methods
Integrity Testing
(CSL) Cross Hole Sonic Log Testing
NDT (Future Technologies)
Standardized items for Load Test
Static Load Test
High-Strain Dynamic Test
Force Pulse (Rapid) Test
Bi-Directional Load Cell Test (O-Cell)
Non-Destructive Test
Technique Shaft replaces Trial Shaft
Separated payment for Integrity Test and Load Test
from Test Shaft and Production Shafts
Require a Pile Installation Plan
Now the Contractor is required to perform Drivability Analysis
(WEAP) to assist in sizing pile hammers and develop pile driving
criteria
Static Load Test – ASTM-1143, Procedure A: Quick Test
Dynamic Monitoring renamed “Dynamic Monitoring
Assistance”
Standard Item “Dynamic Monitoring Instrumentation”
Pile Construction Log – Contractor fully documents
each pile driven. The Department witnesses and
performs QA
Pile Penetration Requirements – Practical Refusal
broadly defined as a rate of 20 blows per inch at
maximum stroke, for 3 consecutive inches
Separated payment for the test and the test pile or
indicator pile
Added an item for CPT Assistance
Incorporated specifications for Construction Site
Survey & Vibration Monitoring
Class Design Strengths (psi)
A1 4,000
A2 6,000
A3 8,500
Mass(A1) 4,000
Mass(A2) 6,000
Mass(A3) 8,500
P1 6,000
P2 8,500
P3 10,000
S 4,000
M 3,000
R 1,800
Reorganized to sequence of construction
Surface resistivity – acceptance and payment schedule New research data allow us to reduce the requirements and still meet
projected design life
Precast Prestressed Concrete Strength Requirements
Test cylinders for acceptance testing
Cure cylinders by either Match Cure or Thermocouple Control Cure
Updated curing and curing methods
Minimum cure time 7 days
Minimum cure time for decks 14 days
Minimum cure time for precast concrete 3 days
Better defined Curing Day
Curing day is defined as 24 hours in which the temperature is above
50°F and if binary or ternary mixes used, 55°F. Colder days may be
counted if accepted methods are used to maintain the specified
minimum air temperature adjacent to concrete.
Redefined concrete surface finishes
All concrete receives a Class 1 Ordinary Finish
Pay Items for Class 2 Rubbed and Class 3 Special Finishes (SqFt) when
specified in the plans.
Plans need to specify application locations and itemize quantity.
Established a new section on “Precast Concrete” Conventionally Reinforced Precast
Prestressed Precast
Eliminated Epoxy Reinforcing Steel
No longer used in new bridge construction in Louisiana
Added standard pay items for:
Stainless Steel
Galvanized Steel
Mechanical Splices
Improved Structural Metals specifications to reflect
best industry practices
Removed Metric Bolts
Renamed 807.04 Fabrication Requirements and moved
certification of shops to beginning of section
Updated AISC shop certification to current practice
Eliminated pay unit of “Pounds”
Moved Anchor Bolts from 805 to 807
Stainless Steel is default anchor bolt system (ASTM F593, Group 2,
Alloy 316)
Added Payment and Installation Methods
Placed DTI installation method first to indicate
preference and added Installation Requirements
Eliminated “Lock Pin-Collar Fasteners”
Eliminated punching holes full size
Cleaned up Rotational Capacity Testing Specifications
Eliminated welding on Eyebars
Moved Section 815 Welding => 809 Welding to be
close to Section 807 Structural Metals
Consolidated Sections
Updated to include current shop practices
Welder IDs
Edge Blocks – removed and rely on AWS Bridge Welding Code.
Reduced the number of copies of reports
Specified non-destructive testing for aluminum
Required steel pipe and tubular section testing to
comply with AWS D 1.5
Consolidated Bridge Railing, Hand Railing and
Permanent Roadway Barriers
Moved Section 733 Roadway Barriers => Section 810
Incorporated NS-800-0026 Hand Railing
Temporary concrete barriers are still provided as per
section 713.06
New: Temporary concrete barriers provided by the Contractor will
become property of the Contractor
Improved and incorporated existing Cleaning and
Painting Supplemental Specification
Covers painting new and existing steel
List Zinc Paint System first to show preference as
primary paint system
Eliminated Water Borne Paint as a system
Added more enforcement
Provided a submittal section
Better defined the “Stripe Coat” and specified the
application sequence and requirements
Provided caulking to seal the perimeter of all faying
surfaces, cracks, crevices, joints, gaps less than ½ inch,
and skip welded joints
Better defined the section on “Protection of the
Environment, Public, and Workers”
Require stenciling the date of construction, coating
manufacturer, and type of paint system at specified
locations on structure
Moved the Containment System to new Section 817
Temporary Works
Improved section on galvanizing and metalizing
Reorganized the section
Added a section for use of High Early Strength (HES)
Concrete
Changed the unit of payment to SqFt
New section Accommodates addition of future technologies and specifications
Added a Submittal Section
All bearings and bearing assemblies (pay items)
Contractor designed bearings Disc bearings
Pot bearings
Other bearings
Moved Joints from Section 805 => New 815 Joints Accommodates addition of future technologies and specifications
Joints Unsealed expansion joints
Sealed expansion joints
Joint Seals Preformed neoprene seal
Preformed silicone seal
Poured seal
New section Accommodates addition of future technologies and specifications
Incorporated NS-800-0060 Deck Drainage System
New Section
Described Temporary Works and design requirements Based on AASHTO LRFD Bridge Construction Specifications
Based on Contractor’s means and methods
Established reviews and responsibilities Designed by EOR
Temporary Detour Bridge, Temporary Sheeting
Designed by Contractor
Construction Access Bridge, Contractor Sheeting, Falsework and
formwork, Cofferdams, Water Control Systems, Cleaning and Painting
Containment Systems, etc.
New section Accommodates addition of future technologies and specifications
Incorporated NS items
Added materials Ultra-High Molecular Weight Polyethylene (UHMW-PE) Panels
Plastic Composite Marine Timbers (PCMT)
Extruded Rubber Fender Elements
Molded Rubber Fender Elements
Moved Section 809 => Section 820 Movable Bridges Allows for addition of Sections 821 Mechanical Systems, Section 822
Electrical Systems, and Section 823 Facilities in sequence
Added Definitions
Added requirements for a “System Integrator”
Requires the contractor to coordinate between all mechanical,
electrical, architectural, and structural components.
Submittals are all processed through the System Integrator to make
sure all components are compatible and work properly
Provides construction sequence information for various
types of movable bridges construction
Field testing requirements
Requirements for mechanical inspections during
construction
Added tolerances for vertical lift bridge towers.
Added standard item for “Temporary Operation and
Maintenance of Movable Span”
Added a 5% Retainage on all mechanical, electrical,
and facility items until acceptance of all O&M Manuals
New Section – many of the plan notes of the past have
been incorporated
Added Definitions specific to mechanical systems
New submittal section and definition of processes,
works in concert with Part I and Section 801
Moved counterweight ropes from Part X to Section 821,
because they are a fabricated item
FACILITIES:
Added Definitions
General Information concerning Mechanical Systems
Added Code Requirements
Added requirements for plumbing systems for
buildings: Material Specifications
Plumbing Specialties
Pressure Testing and Sterilization of Piping Systems
Added requirements for outdoor mechanical
equipment
Heating, Ventilating and Air Conditioning (HVAC)
Systems for Buildings including: Material Specifications
Testing, Adjusting and Balancing Information
Moved Section 730 => Part VIII Structures Section
Primary use is Movable Bridges, Facilities, Roadway
Lighting, and ITS
Organizational changes
Added definitions specific to this section
Better Defined Responsibilities / Expectations
New Section – incorporated many of the plan notes.
Consist mainly of exterior items of Bridge Operator’s
House.
May be used to construct other types building projects
throughout the state.
This Section consist of the following:
General Information concerning Facilities
Code Requirements
Requirements for building architectural components Foundations
Roofing Systems
Storefront Systems
Doors, Louvers, etc.
New section Accommodates addition of future technologies and specifications
Performing more bridge evaluation through
instrumentation and proof loading
Section reference for non standard items during
development of new technologies
New section Accommodates addition of future technologies and specifications
Rolled up existing non standard items
Section reference for non standard items during
development of new technologies
Some of the items covered: Bridge Superstructure Repair
Bridge Substructure repair
Tunnel Repair
Girder Strengthening
Structural concrete patching
Span movement (SPMT, etc.)
Structure jacking
Epoxy Injection
Bolt-rivet replacement (Structural steel)