certification process of storage tank.pdf
TRANSCRIPT
-
8/10/2019 Certification process of storage tank.pdf
1/32
resen e y ser em z
Industry and Certification Division
1
-
8/10/2019 Certification process of storage tank.pdf
2/32
WHO WE ARE
T RK LOYDU is an independent, impartial
classification, cer ca on, an
conformity assesment organization.
With its Marine and Industry Divisions provides wide range of services;
Classification and statutory surveys of new building and existing ships, and certification of marine materials and products.
Third party inspections, CE marking in pressure vessels, system certifications, type approvals are some of the businesses amongst the others.
-
8/10/2019 Certification process of storage tank.pdf
3/32
PHASES TO CERTIFICATION;
APPROVAL OF PROJECTS AND
INSPECTION OF FABRICATION
AND FINAL TESTSQUALIFYING OF
WELDING PROCEDURES AND
-
8/10/2019 Certification process of storage tank.pdf
4/32
APPROVAL OF PROJECTS AND CALCULATIONS ARE EXECUTED ACCORDING TO API 650, 653
We also use COADE software to verify the calculations and design,
o ana yse e s ruc ure we use program.
4
-
8/10/2019 Certification process of storage tank.pdf
5/32
BEFORE CONSTRUCTION OF A TANK IN THE WORKSHOP AND IN THE PLANT
EXAMINATION OF
QUALITY PLAN (ITP)
IS AN ESSENTIAL STEP NOT TO BE OVERLOOKED.
5
-
8/10/2019 Certification process of storage tank.pdf
6/32
QUALIFICATION OF WELDING PROCEDURES
Welding procedure qualification records must meet the requirements of Section IX of
the ASME Code.
Either AWS D1.1 or AWS D1.6 are also acceptable for ladder and platform assemblies, handrails, stairways, and other miscellaneous assemblies, but not their attachments to
.
6
-
8/10/2019 Certification process of storage tank.pdf
7/32
QUALIFICATION OF WELDERS
The welders and welding operators must be qualified in accordance with Section IX of
the ASME Code.
7
-
8/10/2019 Certification process of storage tank.pdf
8/32
INSPECTION OF MATERIALS;
STEEL PLATES
PROFILES
FLANGES etc.
8
-
8/10/2019 Certification process of storage tank.pdf
9/32
MARKING
To enable the various fabricated components to be assembled together correctly on site, each part has to be marked with a unique numbering
system.
Hard stamping may be used as well, but except for the plates less than 6 mm thick.
Marking also provides traceability of each piece of material.
9
-
8/10/2019 Certification process of storage tank.pdf
10/32
AFTER FORMING OF SHELL PLATES
RADIUS OF EACH PLATE MUST BE CHECKED
NOT TO SPEND MUCH TIME DURING THIS STEP, A PREFORMED PATTERN MODEL
MADE OF THIN METAL SHEET CAN BE USED.
PRIMER SHOULD BE APPLIED BEFORE TRANSPORTING THE SHEETS TO PLANT , AND INCASE OF NOT TO AFFECT THE QUALITY OF WELDS, ALL WELD FACES SHOULD BE
.
INCASE ANY DEFORMATION MAY OCCUR DURING TRANSPORT AND STACKING,
10
-
8/10/2019 Certification process of storage tank.pdf
11/32
CONCRETE RINGWALL, AND BOTTOM SURFACE ARE MEASURED BY MEANS OF TOTAL STATION DEVICE.
ANCHORS ARE CHECKED ,MATERIAL TYPELOCATION
Tensile test is required for each party of steel rods used in the concrete
11
-
8/10/2019 Certification process of storage tank.pdf
12/32
BOTTOM PLATES ARE SETTLED ACCORDING TO PLATE ORIENTATION SCHEME IN THE APPROVED PROJECT.
BOTTOM PLATES ARE WELDED AFTER CONSTRUCTING OF COARSES
LAP WELDED BOTTOM PLATES UNDER TANK
SHELL
1
-
8/10/2019 Certification process of storage tank.pdf
13/32
TWO TYPES OF TANK FLOORING ARE;
BOTTOM DOWN: Generally, bottom down is design for cone roof tanks. Centreof the flooring is installed with drain pit. Water in the tank is accumulated in the pit (lowest point of the bottom plate/floor).
BOTTOM UP:Generally, this type of design is used for floating roof tanks, 3 to 4 collector pits are installed, close to the shell plate. Each of the pit is provided with a water draw off line.
A slo e of 1:120 is suitable
13
-
8/10/2019 Certification process of storage tank.pdf
14/32
The erection procedure shall include the following steps:
(a) a hole shall be cut in the bottom plate or a sump shall be placed in the foundation before bottom placement;
(b) a neat excavation shall be made to conform to theshape of the drawoff sump, the sump shall be put in place, and the foundation shall be compacted around the sump
(c) the sump shall be welded to the bottom.
14
-
8/10/2019 Certification process of storage tank.pdf
15/32
ADJUSTMENT OF FIRST COURSE
UPRIGHTNESS, ROUNDNESS AND DIAMETER OF THE COURSE IS MEASURED MIN.AT 8 POINTS.
IT IS CONSIDERED THAT THE WELD SEAMS OF BOTTOM PLATES AND VERTICALSEAMS OF THE COARSE ARE NOT TO BE INTERSECT EACHOTHER
15
-
8/10/2019 Certification process of storage tank.pdf
16/32
ADJUSTMENT OF SECOND COURSE
UPRIGHTNESS, AND ROUNDNESS OF THE SHELL IS MEASURED MIN. AT 8 POINTS.
THEN VERTICAL WELDS ARE EXECUTED OF THE FIRST COURSE.
16
-
8/10/2019 Certification process of storage tank.pdf
17/32
, . .
THEN, VERTICAL
AND
CIRCUMFERENTIAL
WELDS
OF
THE
SECOND
COURSE
ARE
SUCH PRINCIPLE IS FOLLOWED FOR THE OTHER COURSES.
17
-
8/10/2019 Certification process of storage tank.pdf
18/32
FOURTH
THIRD
FIRST
SECOND
COURSE
18
-
8/10/2019 Certification process of storage tank.pdf
19/32
TYPICAL ANCHORAGE
19
-
8/10/2019 Certification process of storage tank.pdf
20/32
TYPICAL ANCHORAGE
20
-
8/10/2019 Certification process of storage tank.pdf
21/32
, . THEN VACUUM TEST IS PERFORMED.
Vacuum testing is performed using a testing boxapproximately 150 mm (6 in.) wide by 750 mm (30 in.) long with a clear window in the top, which provides proper visibility to view the area under inspection.
Durin testin , illumination shall be ade uate for proper evaluation and interpretation of the
test.
The open bottom shall be sealed against the . ,
valves, lighting and gauges, shall be provided as required.
A soap film solution or commercial, leak detection solution, applicable to the conditions, shall be used.
21
-
8/10/2019 Certification process of storage tank.pdf
22/32
22
-
8/10/2019 Certification process of storage tank.pdf
23/32
23
-
8/10/2019 Certification process of storage tank.pdf
24/32
plates to shell plates.
method , or alternatively, by agreement between the purchaser and the manufacturer, using the ultrasonic method. In addition to the radiographic or ultrasonic examination these welds are also visuall examined.
In general, radiographic inspection is required for shell butt welds, annular plate butt welds, and flush type connections with butt welds.
24
-
8/10/2019 Certification process of storage tank.pdf
25/32
TESTING OF THE SHELL
After the entire tank and roof structure is completed, the shell is tested by one of the following methods:
1 If water is available for testing the shell, the tank shall be filled with water as follows:
ito the maximum design liquid level; iifor a tank with a tight roof, to 50 mm above the weld connecting the roof plate or compression bar to the top angle or shell
2 If
sufficient
water
to
fill
the
tank
is
not
available,
the
tank may
be
tested
by painting
a o e o n s on e ns e w a g y pene ra ng o
25
-
8/10/2019 Certification process of storage tank.pdf
26/32
FIRE PROTECTION
Fire protection system shall be established according to the NFPA standards.
This s stem is ins ected durin manufacturin of the installation and after that
functions, and performance are examined.
System shall include;Foam based extinguishing,Water coolingMonitorsDike protection
26
-
8/10/2019 Certification process of storage tank.pdf
27/32
FIRE PROTECTION
For the cooling water rates the standards do not provide cogruent values.They only prescribe minimum water flow rates
API 2030 : 4.1 liters per minute per square meterNFPA 15 : 10.5 liters / min.m 2IP 19 : 2 liters / min.m 2
To be on the safe side for exposure protection we recommend and apply NFPA rate.
27
-
8/10/2019 Certification process of storage tank.pdf
28/32
CATHODIC PROTECTION
Both sacrificial anode system or impressed current system are acceptable.
The main standard for this ste is API 651.
28
-
8/10/2019 Certification process of storage tank.pdf
29/32
EARTHING
To minimize the accumulation of electrostatic charge and prevent sparks, all metal parts of the storage installation must be bonded together and earthed.
Maximum resistance to earth of 10 ohms is recommended.
29
-
8/10/2019 Certification process of storage tank.pdf
30/32
After completing all structure of the tank, for the surfaces of the weld seams
First, shotblasting then
primer paint should be applied before whole tank is painted.
30
-
8/10/2019 Certification process of storage tank.pdf
31/32
, .
31
-
8/10/2019 Certification process of storage tank.pdf
32/32
32