FY09 Tactical Plan for Wide Area Networking (doc #2876)
• Relevant Strategic Plan(s):
– Strategic Plan for Wide Area Networking (doc #2811)
– Strategic Plan for Data Movement & Storage (doc #2812)
– Strategic Plan for Scientific Facilities (doc #2788)
– Computing Division Strategic Plan (doc #2784)
• Tactical Plan Leader: Phil DeMar• Organizational Unit home: CD/SCF/DMS/WAN
CD FY09 Tactical Plan Review 2
FY09 Tactical Plan: Strategies
– Network designs or configurations will be kept as simple as requirements allow.
– Network infrastructure capacity will be kept well ahead of current & projected near term requirements.
– High capacity, high density network switch fabric will be deployed to the extent practicable.
– Network infrastructure will be maintained at the forward edge of established network technology
– Reliability of network infrastructure will be maximized. Redundancy will be the cornerstone of reliability.
CD FY09 Tactical Plan Review 3
– Operate the Laboratory’s off-site network facilities at the highest level of reliability & performance
– Enhance and maintain the CMS Tier-1 network
– Enhance & configure Laboratory’s wide-area network & MAN infrastructure
– Facilitate optimal network performance capabilities of the Laboratory wide area systems
– Upgrade the wide-area network infrastructure to meet needs of Laboratory experiments & collaborations
FY09 Tactical Plan: Goals
FY09 Tactical Plan: Goals (II)
– Evaluate, and deploy as appropriate new and advanced wide-area network technologies
– Engage in and publish research investigations
– Harden / complete the Lambda Station project
FY09 Tactical Plan: Objectives
– Facilitate reliable end-to-end data circuit service
– Develop and deploy advanced active & passive network monitoring capabilities over offsite data paths
– Enhance the reliability & monitoring of the MAN
– Upgrade the CMS Tier-1 network with very high performance central 10GE aggregation device
– Provide addtl 10GE offsite network path capabilities
– Upgrade offsite backup path to 10GE
– Initiate deployment of a 2nd offsite network hub in WH
– Deploy redundant supervisor on border routers
CD FY09 Tactical Plan Review 6
V = vital priorityH = high priorityM = medium priority
{H}
{H}
{V}
{H}
{V}
{V}
{V}
{V}
– Increase CMS Tier-1’s off-site bandwidth as needed
– Enhance structured performance analysis methodology
– Guide remote sites in improving data transfer rates
– Develop IPv6 test bed to production quality facility
– Deploy a 10GE network connection with ANL
– Connect to the Global Lambda Integrated Facility
– Participate in tests of network speeds beyond 10Gb/s
FY09 Tactical Plan: Objectives (II)V = highest priorityH = high priorityM = medium priority
{M}
{M}
{M}
{M}
{H}
{H}
{H}
– Refresh FAPL/Gridworks cluster with state-of-the-technology systems
– Develop network-based traffic analysis as initiator of dynamic circuits
– Design next-generation Lambda Station product
FY09 Tactical Plan: Objectives (III)V = highest priorityH = high priorityM = medium priority
{M}
{M}
{M}
FY09 Tactical Plan: Past Action Items
– Wide Area Networks initial review – Matt Crawford; Nov. 7, 2007• Re-evaluate budget cuts associated with storage disk space for flow analysis data
from border router.
» Resolved. Space provided on BlueARC• May need to re-visit the budget for making the backup border router to be fully
configured to match the primary border router
FY09 project– Wide Area Networks mid-year review– Phil DeMar; June 3, 2008
• 15.1: Andrey's effort - reporting against CMS-T1 but not actually getting charged as expected to CMS-T1. Jon and Phil agree this is a problem, needs to be resolved with Mike Smith.
Resolved. New activity for charge-back being set up
• 15.2: WAN Operations, Support, & Maintenance erroneously listed under Site Networking. Mike Smith knows about and will fix
Fixed
CD FY09 Tactical Plan Review 9
Service: Advanced WAN Infrastructure
CD FY09 Tactical Plan Review 10
• Offsite configurations & infrastructure enhancements for WAN data movement
• Goals:
1. Facilitate reliable end-to-end (E2E) data circuit service• Ongoing goal – highest priority
2. Deploy perfSonar-based E2E active monitoring capabilities• New goal – high priority
• Key Metrics:
1. Aggregate off-site bandwidth capacity
2. # of E2E circuits, their uptime & utilization – need to develop E2E monitoring capabilities
3. # of PerfSonar-monitored remote sites• Milestones:
1. Active PerfSonar monitoring to all Tier-2 sites - April ‘09
Service: Network / Performance Improvement
CD FY09 Tactical Plan Review 11
• Support for optimization of offsite data movement
• Goals:
1. Enhance structured performance methodology• Ongoing goal – high priority
2. Coordinate & assist remote sites in improving data transfer rates• Ongoing goal – high priority
• Key Metrics:– Quantified performance improvements for CMS Tier-2 & Tier-3 sites
• Milestones:– Incorporation of content management capability in methodology - April ‘09
Services: (1) Network Operational Support & Maint. (2) Network Operations / MAN
CD FY09 Tactical Plan Review 12
• (1) Operation & support of WAN network infrastructure
• (2) Operation & support of Chicago MAN
• Goals:
1. Facilitate very high performance, highly reliable WAN network service• Ongoing goal – highest priority
2. Provide expeditious troubleshooting support for WAN-related network problems
• Ongoing goal – highest priority
3. Enhance reliability & monitoring capabilities of Chicago MAN• Ongoing goal – high priority
• Key Metrics:
1. Uptime of perimeter routers
2. MAN channel uptime• Milestones:
---
Service: Network-CMS-WAN
CD FY09 Tactical Plan Review 13
• Planning, deployment, & support of CMS Tier-1 network infrastructure
• Goals:
1. Upgrade the Tier-1 infrastructure to be based on a very high performance 10GE aggregation device
• New goal – highest priority
2. Increase CMS onsite & offsite bandwidth capacity to meet the Tier-1’s needs
• Ongoing goal – high priority
• Key Metrics:– Uptime of CMS Tier-1 network devices– Measured data traffic levels, internal & offsite
• Milestones:– Upgrade of CMS Tier-1 network to new core device - September ‘09
Project: Network Upgrades
CD FY09 Tactical Plan Review 14
• Testing & deployment of advanced network technologies• Goals:
1. Upgrade backup offsite path to 10GE• Ongoing goal – highest priority
2. Develop 2nd offsite hub in WH• New goal – high priority
3. Deploy redundant supervisors on border & E2E circuit routers• New goal – high priority
4. Additional 10GE offsite channel capacity, as needed• Ongoing goal – high priority
• Key Milestones:
1. Backup border router upgraded with new supervisor – Nov ‘09
2. 2nd Ciena hub deployed in WH - July ‘09
3. Border & E2E routers upgraded with BXL supervisors – Feb ‘09
• Issues and Risks: 1. Could be delayed, but would seriously impact long term strategic directions
Project: Network Investigations
CD FY09 Tactical Plan Review 15
• Testing & deployment of advanced network technologies• Goals:
1. Develop production-quality IPv6 network test bed• Ongoing goal – medium priority
2. Deploy 10GE network connection to ANL• New goal – medium priority
3. Connect R&D test network to Global Lambda Integrated Facility• Ongoing goal – medium priority
4. Participate in wide-area network technologies beyond 10GE• New goal – medium priority
• Key Milestones:
1. Full-function IPv6 test bed with DHCPv6 - July ‘09
2. 10GE connection between FNAL & ANL R&D LANs - Sept. ’09
3. Attachment to GLIF GOLE – Dec. ’08
• Issues and Risks: 1. Could be delayed, but would impact long term strategic directions
Project: (1) SciDAC Lambda Station (2) Lambda Station FTWatch
CD FY09 Tactical Plan Review 16
• (1) Alternate wide-area network path selection service• (2) Flow-based traffic analysis initiator of Lambda Station services• Goals:
1. Hardened Lambda Station distribution package w/ config tools• Ongoing goal – high priority
2. Develop generic flow record analysis algorithms for FTWatch• New goal – medium priority
3. Design next-generation Lambda Station product• New goal – medium priority
• Key Milestones:
1. Complete Lambda Station project - Early-as-possible ’09
• Issues and Risks: 1. Scripting help (PERL) needed to help finish project2. Funding spend-down for Lambda Station proving to be difficult 3. Ongoing support effort also a concern
CD FY09 Tactical Plan Review 17
FY09 Resource Request, Preliminary Allocation
Level 0 Activity: Wide-Area Networking
• Medium priority projects would be first to be scaled back or deferred– Largely effort expenditures; would try for some forward progress
– 100GE test bed & IPv6 initiatives have R&E leadership aspects
• Network upgrades could also be deferred– Would impact strategic direction on reliability & resilience
– Backup 10GE path already delayed one year and overdue
• Lambda Station effort will end this FY– Can not be deferred, only stopped
• High priority WAN & CMS Tier-1 services remain essential– Must receive required effort, at expense of projects, upgrades, &
technology investigations
Impact of Partial Allocation