D14-RP - P
OC1
220kV BUS SECTION
ABB
REF615
CT Ratio 3000:1
IEC - Normal Inverse
Pickup = 1.2 (0.3 - 5 xCT Sec)
Time Dial = 0.49
3x = 3.09 s, 5x = 2.1 s, 8x = 1.62 s
D05-RP - P
OC1
120MVA T/F
ABB
REF615
CT Ratio 600:1
IEC - Normal Inverse
Pickup = 0.8 (0.3 - 5 xCT Sec)
Time Dial = 0.31
3x = 1.95 s, 5x = 1.33 s, 8x = 1.02 s
Inst = 6 (0.5 - 35 xCT Sec)
Time Delay = 0.1 s
10K.5 1 10 100 1K3 5 30 50 300 500 3K 5K
Amps X 100 BB-1A (Nom. kV=220, Plot Ref. kV=220)
10K.5 1 10 100 1K3 5 30 50 300 500 3K 5K
Amps X 100 BB-1A (Nom. kV=220, Plot Ref. kV=220)
1K
.01
.1
1
10
100
.03
.05
.3
.5
3
5
30
50
300
500
Seconds
1K
.01
.1
1
10
100
.03
.05
.3
.5
3
5
30
50
300
500
Seconds
ETAP Star 12.5.0C
N7733- ZAKHER GRID CASE1.2
Project: 220/33/11kV Zakher Grid
Location: Zakher Area of Al Ain
Contract: N7733
Engineer: JM
Filename: C:\ETAP 1250\N7733\N7733.OTI
Date: 18-01-2016
SN: LARSENTRN2
Rev: Base
Fault: Phase
Circuit: 120MVA T/F, 220KV B/S