Case Study:Masen NOOR Ouarzazate Solar Complex
NOOR OUARZAZATE CSP POWER PLANTS
NOORo IIIUnder construction
150 MW
NOORo IIUnder construction
200 MW
NOOR Iin operation
160 MW
NOOR IV
70 MW
R&D Platform
CSP Parabolic Trough
CSP Parabolic Trough
CSP Tower
Photovoltaic
NOOR OUARZAZATE
COMPLEX,
A GRADUAL
DEPLOYMENT OF
580 MW
Ouarzazate
NOOR OUARZAZATE COMPLEX
4
NOORO I SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (1/3)
Techno. Concentrated Solar Power using parabolic troughs and molten salt Thermal Energy Storage
160 MWe Gross Capacity
3 hours Thermal Energy Storage
Capacity
Storage
Developer
EPC
Price Data
Price per kWh* 0,189 $
Wet coolingCooling
* evaluated peak hour tariff
NOORO I SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (2/3)
NOORO I SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (3/3)
Reflective Area: 1 308 000 m2
Number of loops: 400/STN0
HTF: Dowtherm A
HCE tubes: Schott PTR 70
1 hot Tank & 1 cold Tank
Thermal Capacity: 1269MWth (equivalent to 3 hours of storage)
Tank Dimension: Ø: 46,5 m / H: 14 m
ST Gross Capacity: 160 MW
Water consumption: 1̴ 700 000 m3/yr
Project Area: 458ha
NOORO II SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (1/3)
Techno. Concentrated Solar Power using parabolic trough
200 MW Gross Capacity
> 7 hours
Capacity
Storage
Developer
EPC
Financial Institutions
0,14 $ / kWhTariff*
DryCooling
* evaluated peak hour tariff
NOORO II SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (2/3)
NOORO II SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (3/3)
Reflective Area: 1 779 900 m²
Number of loops: 425/STN2
Solar field Inlet/outlet: 295 °C/ 393°C
1 Loop = 4 SCAs 1 SCA = 12 SCEs
2 hot Tank & 2 cold Tank
Thermal Capacity: 3125MWth (equivalent to 7.3 hours of storage)
Tank Dimension: Ø: 44.1 m / H: 16.6 m
ST Gross Capacity: 200MW
Water consumption: 280 000 m3/yr
Project Area: ~ 600ha
Techno. Concentrated Solar Power using tower
150 MW Gross capacity
> 7 hours
Capacity
Storage
Developer
EPC
Financial Institutions
10
0,15 $ / kWhTariff*
NOORO III SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (1/3)
DryCooling
* evaluated peak hour tariff
NOORO III SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (2/3)
NOORO III SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (3/3)
Reflective Area: 1 321 197 m²
Number of heliostat: 7400 (178m2/Heliostat, 54 facet
HTF: Molten Salt (NaNO3 (60%)/ KNO3 (40%)
Receiver: 660 MWth
1 hot Tank & 1 cold Tank
Thermal Capacity: 2770MWth
Tank Dimension: Ø: 41.3 m / H: 14 m
ST Gross Capacity: 150MW
Water consumption: 155 000 m3/yr
Project Area: ~ 600ha
Tower Height: 247m
Cold: 290 C (to receiver) Hot: 565 C (receiver outlet)
NOOR OUARZAZATE POWER PLANTS
NOORo II NOORo III
Technology
Capacity
Cooling
Thermal Storage
Annual Production
Surface
CSP Parabolic trough
200 MW
Dry
7h to 8h
699 GWh
600 ha
CSP Tower
150 MW
Dry
7h to 8h
515 GWh
580 ha
NOORo I in operation since beginning of - 2016NOORo II and NOORo III under construction-
Start of construction of NOORo IV in - 2017
NOORo I
CSP Parabolic trough
160 MW
Wet
3h
520 GWh
485 ha
NOORo IV
Photovoltaic
70 MW
137 ha
-
-
125 GWh
CONSTRUCTION & START-UP
POWER PLANTS – CONSTRUCTION & START-UP
Masen
Project Company
ONEE
PPA 1
PPA 2
EPC Contract O&M Contract
Independent Engineer
Technical Advisor
Owner Engineer
POWER PLANTS – MASEN ORGANIZATION TEAM
Project Management
Contract Management
Quality Management
Technical Management
HSE Management
- Establishment of a responsibility assignment matrix at the beginning of each project
POWER PLANTS – SCOPE OF INTERVENTION
Independent Engineer Services
Request for Proposals preparation
Evaluation of Technical and Financial Proposals
Certification of Initial and Final Tests
Services Awarding
Technical Advisor Services
Request for Proposals preparation
Evaluation of Technical and Financial Proposals
Support for Design Review
Specific missions for construction activities inspections
Specific Audits and inspections
HSE
Quality Assurance
Specific activities
Payment Milestones approval
Ensure the milestones are reached in order to request for funds
Ensure the appropriate documents are provided
Manage the mission of Lender Technical Advisor
Funds disbursement
POWER PLANTS – SCOPE OF INTERVENTION
Engineering
Selection of drawings for ONEE’s approval
Telecommunication system with the dispatching center
Interfaces with ONEE (Grid operator)
Approval of the Plant’s electrical protection settings
List of prerequisites before first energization
List of prerequisites before first synchronization
Approval of agreed manufacturers
Factory Acceptance Tests
Logistics and Procurement
Factory inspections
Support for the delivery of permits and authorizations
Design Review
Ensure compliance with the contractual documents
Interfaces with Masen common infrastructures
Review of design plans and drawings including the specification of equipment
Review of O&M Manuals
POWER PLANTS – SCOPE OF INTERVENTION
Construction & Commissioning
Commissioning procedures analysis
Follow-up of commissioning progressCommissioning Management
Analysis of Project scheduling
Certification by the Independent Engineer
Construction Management
Ensure compliance with the contractual documents
Follow-up of construction progress
Analysis of Project scheduling
Follow-up of Industrial Integration
Integration of the Plant with Masen Infrastructures
Follow-up of employment statisticsHSE
ManagementQuality
Assurance
Initial Performance Tests
Final Performance Tests
Acceptance Tests
Certification by the Independent Engineer
Performance Tests procedures analysis
Witness and Approval of Performance Tests results
LESSONS LEARNED
NOORo I – DUST IMPACT ON PRODUCTION
➢ Mirrors cleanliness impact directly the performance of the plant➢ 2 additional cleaning trucks have been procured in beginning of 2017➢ Mirrors cleanness factor is expected to be higher after the completion of NOORo II & NOORo III
construction
NOORo I - ACTUAL PRODUCTION VS EXPECTED PRODUCTION S2 2016
Overall the production during this semester was good. However it was impacted by following:➢ the cleanliness factor affected by ongoing works in the complex and weather conditions➢ Learning curve of the Operator (NOMAC) especially during cloudy days
41,916
32,672 31,040
24,291 24,658 25,697
47,539
37,440 35,049 28,945
26,924 28,293
ACTUAL PRODUCTION VS EXPECTED PRODUCTION
Actual generation (MWh) Expected generation* (MWh)
SeptemberJuly August Octobre November December
*Expected generation is calculated using the Performance Model with reference data and the weather data musured on site
NOORo I – RATIO PEAK GENERATION S2 2016
23
8,231 4,760 6,524 4,807
8,342 9,506
33,685
27,912 24,516
19,484 16,316 16,191
July August September October November December
Peak Hours generation (MWh) Off-Peak Hours generation (MWh)
25 697 MWh
41 916 MWh
32 672 MWh 31 040 MWh
24 291 MWh 24 658 MWh
20%15%
21% 20%
34% 37%
July August September October November December
Ratio Peak generation
2nd semester2016 (MWh)
Peakgeneration
42 170
Off-Peakgeneration
138 105
Ratio Peak 23,5%
Very good production during peak hours thanks to the progress made by the O&M team
NOORo I – PLANTS CONSUMPTION (JANUARY – APRIL 2017)
COOLING SYSTEM DESIGN
Wet Cooling System Dry Cooling System
NOORo I: 160 MW
Annual water consumption:1 750 000 m3
NOORo II: 200 MWAnnual water consumption:
288 000 m3
NOORo III: 150 MWAnnual water consumption:
155 000 m3
Main heavy equipment requiring transport ‒authorization:
HEAVY EQUIPMENT TRANSPORTATION
DIFFICULTIES IN THE DELIVERY OF HEAVY EQUIPMENT SELECTED ROUTING FOR TRANSPORTATION
o HTF / SALT Heat exchangers: 6 x 362 To Generator : 237 To HP turbine: 134 To Pre-heaters 2x92 To Evaporators 2x146 To Reheaters 2x92 T o Main Transformer 130 To Condenser 140 To HTF heaters: 2 x 90 T
Assessment to be conducted at the beginning of the project:➢ Selection of the routing during the bidding process➢ Coordination with the involved authorities in order to define any necessary reinforcement works
% industrialintegration 0%
34,7%
30%
Committed % industrial integration over the period
34,7%
EPC Committed expenses EPC expenses
% total industrial integration 34,7 %
EPC Committed expenses with local companies
Total EPC budgeted costs for the project
/5 581 Mdh
EPC expenses with local companies
Total EPC budgeted costs for the project
/5 581 Mdh
Expenses split by main EPC works (paid to local companies)Committed expenses split by main EPC works (committed by local companies)
1 940 Mdh 1 940 Mdh
22%
8%
10%33%
27%
Solar field collectors (mirrorssupports)
Salts and water tanks andreservoirs
Piping and cables
Piling and civil works
Mechanical and electricalerection
23%
7%
10%34%
26%
Solar field collectors (mirrorssupports)
Salts and water tanks andreservoirs
Piping and cables
Piling and civil works
Mechanical and electricalerection
27
NOORo I - INDUSTRIAL INTEGRATION