case study: masen noor ouarzazate solar complexcmimarseille.org › menacspkip › wp-content ›...

27
25/07/2017 Case Study: Masen NOOR Ouarzazate Solar Complex

Upload: others

Post on 03-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

25/07/2017

Case Study:Masen NOOR Ouarzazate Solar Complex

Page 2: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOOR OUARZAZATE CSP POWER PLANTS

Page 3: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORo IIIUnder construction

150 MW

NOORo IIUnder construction

200 MW

NOOR Iin operation

160 MW

NOOR IV

70 MW

R&D Platform

CSP Parabolic Trough

CSP Parabolic Trough

CSP Tower

Photovoltaic

NOOR OUARZAZATE

COMPLEX,

A GRADUAL

DEPLOYMENT OF

580 MW

Ouarzazate

NOOR OUARZAZATE COMPLEX

Page 4: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

4

NOORO I SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (1/3)

Techno. Concentrated Solar Power using parabolic troughs and molten salt Thermal Energy Storage

160 MWe Gross Capacity

3 hours Thermal Energy Storage

Capacity

Storage

Developer

EPC

Price Data

Price per kWh* 0,189 $

Wet coolingCooling

* evaluated peak hour tariff

Page 5: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORO I SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (2/3)

Page 6: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORO I SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (3/3)

Reflective Area: 1 308 000 m2

Number of loops: 400/STN0

HTF: Dowtherm A

HCE tubes: Schott PTR 70

1 hot Tank & 1 cold Tank

Thermal Capacity: 1269MWth (equivalent to 3 hours of storage)

Tank Dimension: Ø: 46,5 m / H: 14 m

ST Gross Capacity: 160 MW

Water consumption: 1̴ 700 000 m3/yr

Project Area: 458ha

Page 7: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORO II SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (1/3)

Techno. Concentrated Solar Power using parabolic trough

200 MW Gross Capacity

> 7 hours

Capacity

Storage

Developer

EPC

Financial Institutions

0,14 $ / kWhTariff*

DryCooling

* evaluated peak hour tariff

Page 8: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORO II SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (2/3)

Page 9: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORO II SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (3/3)

Reflective Area: 1 779 900 m²

Number of loops: 425/STN2

Solar field Inlet/outlet: 295 °C/ 393°C

1 Loop = 4 SCAs 1 SCA = 12 SCEs

2 hot Tank & 2 cold Tank

Thermal Capacity: 3125MWth (equivalent to 7.3 hours of storage)

Tank Dimension: Ø: 44.1 m / H: 16.6 m

ST Gross Capacity: 200MW

Water consumption: 280 000 m3/yr

Project Area: ~ 600ha

Page 10: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

Techno. Concentrated Solar Power using tower

150 MW Gross capacity

> 7 hours

Capacity

Storage

Developer

EPC

Financial Institutions

10

0,15 $ / kWhTariff*

NOORO III SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (1/3)

DryCooling

* evaluated peak hour tariff

Page 11: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORO III SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (2/3)

Page 12: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORO III SOLAR PLANT MAIN TECHNICAL CHARACTERISTICS (3/3)

Reflective Area: 1 321 197 m²

Number of heliostat: 7400 (178m2/Heliostat, 54 facet

HTF: Molten Salt (NaNO3 (60%)/ KNO3 (40%)

Receiver: 660 MWth

1 hot Tank & 1 cold Tank

Thermal Capacity: 2770MWth

Tank Dimension: Ø: 41.3 m / H: 14 m

ST Gross Capacity: 150MW

Water consumption: 155 000 m3/yr

Project Area: ~ 600ha

Tower Height: 247m

Cold: 290 C (to receiver) Hot: 565 C (receiver outlet)

Page 13: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOOR OUARZAZATE POWER PLANTS

NOORo II NOORo III

Technology

Capacity

Cooling

Thermal Storage

Annual Production

Surface

CSP Parabolic trough

200 MW

Dry

7h to 8h

699 GWh

600 ha

CSP Tower

150 MW

Dry

7h to 8h

515 GWh

580 ha

NOORo I in operation since beginning of - 2016NOORo II and NOORo III under construction-

Start of construction of NOORo IV in - 2017

NOORo I

CSP Parabolic trough

160 MW

Wet

3h

520 GWh

485 ha

NOORo IV

Photovoltaic

70 MW

137 ha

-

-

125 GWh

Page 14: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

CONSTRUCTION & START-UP

Page 15: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

POWER PLANTS – CONSTRUCTION & START-UP

Masen

Project Company

ONEE

PPA 1

PPA 2

EPC Contract O&M Contract

Independent Engineer

Technical Advisor

Owner Engineer

Page 16: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

POWER PLANTS – MASEN ORGANIZATION TEAM

Project Management

Contract Management

Quality Management

Technical Management

HSE Management

- Establishment of a responsibility assignment matrix at the beginning of each project

Page 17: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

POWER PLANTS – SCOPE OF INTERVENTION

Independent Engineer Services

Request for Proposals preparation

Evaluation of Technical and Financial Proposals

Certification of Initial and Final Tests

Services Awarding

Technical Advisor Services

Request for Proposals preparation

Evaluation of Technical and Financial Proposals

Support for Design Review

Specific missions for construction activities inspections

Specific Audits and inspections

HSE

Quality Assurance

Specific activities

Payment Milestones approval

Ensure the milestones are reached in order to request for funds

Ensure the appropriate documents are provided

Manage the mission of Lender Technical Advisor

Funds disbursement

Page 18: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

POWER PLANTS – SCOPE OF INTERVENTION

Engineering

Selection of drawings for ONEE’s approval

Telecommunication system with the dispatching center

Interfaces with ONEE (Grid operator)

Approval of the Plant’s electrical protection settings

List of prerequisites before first energization

List of prerequisites before first synchronization

Approval of agreed manufacturers

Factory Acceptance Tests

Logistics and Procurement

Factory inspections

Support for the delivery of permits and authorizations

Design Review

Ensure compliance with the contractual documents

Interfaces with Masen common infrastructures

Review of design plans and drawings including the specification of equipment

Review of O&M Manuals

Page 19: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

POWER PLANTS – SCOPE OF INTERVENTION

Construction & Commissioning

Commissioning procedures analysis

Follow-up of commissioning progressCommissioning Management

Analysis of Project scheduling

Certification by the Independent Engineer

Construction Management

Ensure compliance with the contractual documents

Follow-up of construction progress

Analysis of Project scheduling

Follow-up of Industrial Integration

Integration of the Plant with Masen Infrastructures

Follow-up of employment statisticsHSE

ManagementQuality

Assurance

Initial Performance Tests

Final Performance Tests

Acceptance Tests

Certification by the Independent Engineer

Performance Tests procedures analysis

Witness and Approval of Performance Tests results

Page 20: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

LESSONS LEARNED

Page 21: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORo I – DUST IMPACT ON PRODUCTION

➢ Mirrors cleanliness impact directly the performance of the plant➢ 2 additional cleaning trucks have been procured in beginning of 2017➢ Mirrors cleanness factor is expected to be higher after the completion of NOORo II & NOORo III

construction

Page 22: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORo I - ACTUAL PRODUCTION VS EXPECTED PRODUCTION S2 2016

Overall the production during this semester was good. However it was impacted by following:➢ the cleanliness factor affected by ongoing works in the complex and weather conditions➢ Learning curve of the Operator (NOMAC) especially during cloudy days

41,916

32,672 31,040

24,291 24,658 25,697

47,539

37,440 35,049 28,945

26,924 28,293

ACTUAL PRODUCTION VS EXPECTED PRODUCTION

Actual generation (MWh) Expected generation* (MWh)

SeptemberJuly August Octobre November December

*Expected generation is calculated using the Performance Model with reference data and the weather data musured on site

Page 23: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORo I – RATIO PEAK GENERATION S2 2016

23

8,231 4,760 6,524 4,807

8,342 9,506

33,685

27,912 24,516

19,484 16,316 16,191

July August September October November December

Peak Hours generation (MWh) Off-Peak Hours generation (MWh)

25 697 MWh

41 916 MWh

32 672 MWh 31 040 MWh

24 291 MWh 24 658 MWh

20%15%

21% 20%

34% 37%

July August September October November December

Ratio Peak generation

2nd semester2016 (MWh)

Peakgeneration

42 170

Off-Peakgeneration

138 105

Ratio Peak 23,5%

Very good production during peak hours thanks to the progress made by the O&M team

Page 24: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

NOORo I – PLANTS CONSUMPTION (JANUARY – APRIL 2017)

Page 25: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

COOLING SYSTEM DESIGN

Wet Cooling System Dry Cooling System

NOORo I: 160 MW

Annual water consumption:1 750 000 m3

NOORo II: 200 MWAnnual water consumption:

288 000 m3

NOORo III: 150 MWAnnual water consumption:

155 000 m3

Page 26: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

Main heavy equipment requiring transport ‒authorization:

HEAVY EQUIPMENT TRANSPORTATION

DIFFICULTIES IN THE DELIVERY OF HEAVY EQUIPMENT SELECTED ROUTING FOR TRANSPORTATION

o HTF / SALT Heat exchangers: 6 x 362 To Generator : 237 To HP turbine: 134 To Pre-heaters 2x92 To Evaporators 2x146 To Reheaters 2x92 T o Main Transformer 130 To Condenser 140 To HTF heaters: 2 x 90 T

Assessment to be conducted at the beginning of the project:➢ Selection of the routing during the bidding process➢ Coordination with the involved authorities in order to define any necessary reinforcement works

Page 27: Case Study: Masen NOOR Ouarzazate Solar Complexcmimarseille.org › menacspkip › wp-content › uploads › ...Technology Capacity Cooling Thermal Storage Annual Production Surface

% industrialintegration 0%

34,7%

30%

Committed % industrial integration over the period

34,7%

EPC Committed expenses EPC expenses

% total industrial integration 34,7 %

EPC Committed expenses with local companies

Total EPC budgeted costs for the project

/5 581 Mdh

EPC expenses with local companies

Total EPC budgeted costs for the project

/5 581 Mdh

Expenses split by main EPC works (paid to local companies)Committed expenses split by main EPC works (committed by local companies)

1 940 Mdh 1 940 Mdh

22%

8%

10%33%

27%

Solar field collectors (mirrorssupports)

Salts and water tanks andreservoirs

Piping and cables

Piling and civil works

Mechanical and electricalerection

23%

7%

10%34%

26%

Solar field collectors (mirrorssupports)

Salts and water tanks andreservoirs

Piping and cables

Piling and civil works

Mechanical and electricalerection

27

NOORo I - INDUSTRIAL INTEGRATION