case #2hi-ho yoyo
DESCRIPTION
Case analysisTRANSCRIPT
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
Hi-Ho Yo Yo, Inc.
It was a little 9:00 on a Monday morning when Jeff Baker walked into your office with a box of
donuts.
“I’ve been talking with Anne about a problem we have with short-term capacity in our pad
printing operations. You know, that’s where we print our logo on the Custom lines of yo-yos.
We have received more orders to pad printing in a way that will enable us to meet out due date
commitments in the best way possible. Would you have time to look on the order list (attached)
and see what kind of schedule we should follow to do that? By the way, you have established
quite a reputation in your short stay here. You have a talent for really explaining why your
recommendations are the best approach in a way that all of us “over-the-hill” managers can
understand. Please be sure to do that for me too. I want to understand why your recommendation
is the best schedule and what the trade-offs are for other possible schedules – and none of that
philosophical college mumbo-jumbo. Remember, I came up through the ranks. I don’t have one
of those sheepskins on my wall,” he says with a laugh.
Since the schedule was back to normal after that MRP (Material requirements planning) report
you did for Anne, you agreed to look at the information. After that compliment, how could you
say no? “Try to get back to me within a couple of days,” Jeff said as he left your office.
After a few minutes with your old operations management text, you call the production control
office to confirm the pad printing schedule. They confirm that pad printing runs one eight-hour
shift per day. They tell you that due to a make-up day for flooding in June, pad printing will be
running 23 days in July, beginning Friday, July 1 (they will work three Saturdays on July 9, 16,
1
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
and 23, and take a one-day holiday for July 4). You thank them for the information and then you
begin to develop your plan.
Even though Jeff lacks a college degree, from what you have seen, he is very sharp. And
obviously he knows good work when he sees it since he liked, and apparently understood, your
past work. You resolve to cover all the bases but in a way that it as clear as possible.
PAD PRINTING ORDER LIST
Job Date Order
Received
Set-up Time Production Time Due Date
A 6/4 2 hrs 6 days 11 July
B 6/7 4 hrs 2 days 8 July
C 6/12 2 hrs 8 days 25 July
D 6/14 4 hrs 3 days 19 July
E 6/15 4 hrs 9 days 29 July
Note: Setup time is to set up the pad printer at the start of the job. Setup includes thoroughly
cleaning the printing heads and ink reservoirs, installing the new pad(s) and ink supply, and
carefully aligning the machine. Setup at the beginning of a new day with the same job is
insignificant.
Examine the following rules and write a report to Jeff Baker summarizing your findings and
advise him on which rule to use. Rules: FCFS, SPT, DD and CR.
2
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
CHAPTER I
Time Context
Hi-Ho YoYo, Incorporation is an organization that customizes logos for yoyos. Currently
they are beginning to see an issue with rising orders and they wish to continue to meet there
order process deadlines. These are ordered on June but then they will only start on July due to a
make-up day for flooding. So Mr. Jeff asked for what is the scheduling to be followed in order
to meet the constraints. Several rules will be evaluated in order to determine the best method of
inventory scheduling. The four rules to evaluate are: First Come, First Serve (FCFS), Shortest
Processing Time (SPT), Earliest Due Date (DD), and Critical Ratio (CR) methods.
CHAPTER II
Viewpoint
Job sequencing is an important task to determine, because it is either going to slow down
the production process or speed it up. An Operations Manager should determine the best method
based off the needs of the organization, which in this case will require that all jobs are completed
prior to their due dates. In this sense, having a job done before the due date is a priority rule of
the organization. According to the book, Operations Management, “Priority rules are simple
heuristics used to select the order in which the jobs will be processed.” (Stevenson) Job
processing times and due dates are very important pieces of information when applying these
rules. If the sequencing rule takes in account when applying theses similar setups to other jobs,
then this setup will lead to reduced setup times, which will save the organization time and
money. Being able to control time, as far as controlling overtime within the production plant,
3
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
will go far in enabling an organization to save by eliminating overtime paid to employees. Not to
mention the customers will be satisfied to receive a product on schedule as well.
CHAPTER III
Statement of the Problem
Sequencing is concerned with determining the order in which jobs are processed. Not
only must the order be determined for processing jobs at work centres but also for work
processed at individual work stations. When work centres are heavily loaded and lengthy jobs
are involved, the situation can become complicated. In this case study, the main problem needed
to address is how to meet the constraints such as due dates, delays, etc. and to satisfy the clients’
wants despite of the increasing orders. The company experienced a delay due to a make-up day
for flooding in the month of June which moves the production date of the order to July. In the
month of July, it is stated in the given case that there are 3 Saturdays (July 9, 16 and 23) that the
labours will continue working and they will have a holiday (July 4) aside from the weekends. So
given the constraints, how will be the operation manager will choose the best scheduling on the
given methods (First Come, First Serve (FCFS), Shortest Processing Time (SPT), Earliest Due
Date (DD), and Critical Ratio (CR) methods). In addition, Mr Jeff also wants to have an
understanding about the scheduling methods to be used in order for him to understand the
process.
4
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
CHAPTER IV
Objectives
Job sequencing rules are used to determine the priority for processing jobs. They are
applied to tackle scheduling problems that generally lead to inefficient performance in
processing job orders. Of central importance is job flow time, which is the amount of time a job
spends in a shop from order placement to its completion and release. The average turnaround
time on job orders is its mean job flow time, which is one way of measuring a job shop's
performance. The main objective in this case study is to find the best rule to be followed in order
to solve the existing problem. The following are the other objectives to be met:
Defining the order in which jobs at a work centre will be administered.
Sequencing decision to be made in order to meet all the due dates and satisfy the needs of
the clients.
Educating staff in order to give then understanding about choosing the best schedule to be
made.
Meeting due dates of customers or downstream operations.
Minimalizing the flow time (the time a job spends in the process).
Reducing work-in-process inventory.
Lessening idle time of machines or workers.
5
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
CHAPTER V
Areas of Consideration/Analysis
Scheduling relates to establishing both the timing and use of resources within an
organization. Under the operations function, scheduling relates to use of equipment and facilities,
the scheduling of human activities, and receipt of materials. In this case, there are facts given that
will help in order to end up into a decision of what method to be used.
“I’ve been talking with Anne about a problem we have with short-term capacity in our
pad printing operations. You know, that’s where we print our logo on the Custom lines of yo-yos.
We have received more orders to pad printing in a way that will enable us to meet out due date
commitments in the best way possible. Would you have time to look on the order list (attached)
and see what kind of schedule we should follow to do that?”
In the paragraph above, it was clearly stated the problem of the Hi-ho Yoyo
Incorporation. Their orders are increasing and they must find a way in order to meet due dates.
“After a few minutes with your old operations management text, you call the production
control office to confirm the pad printing schedule. They confirm that pad printing runs one
eight-hour shift per day. They tell you that due to a make-up day for flooding in June, pad
printing will be running 23 days in July, beginning Friday, July 1 (they will work three
Saturdays on July 9, 16, and 23, and take a one-day holiday for July 4). You thank them for the
information and then you begin to develop your plan.”
Moreover, this information was given by production call office in order to create a plan
and find a solution for the problem. The company needs to meet the orders within twenty-three
(23) days in the month of July; twenty three days only because it was stated that the workers will
have one holiday in addition to their weekends. But then, there are three Saturday that they will
6
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
work. Each day the labourers will work for 8 hours. Given below is the illustration of the
working calendar of the company:
JULY
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31
“Note: Setup time is to set up the pad printer at the start of the job. Setup includes thoroughly
cleaning the printing heads and ink reservoirs, installing the new pad(s) and ink supply, and
carefully aligning the machine. Setup at the beginning of a new day with the same job is
insignificant.”
In addition to the given table, the setup time is noted and the information about it is
given. Because of this, this will be added to the processing time.
7
Yellow Working Days
Pink Weekends
Red Holiday
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
CHAPTER VI
Alternative Course of action
According to Stevenson, priority rules are simple heuristics used to select the order in which
jobs will be processed. In this case study, there are four rules given to be analysed in order to
resolve the current problem. The following are the rules:
1. First Come First Serve (FCFS):
This is a service policy that is based on attaining the customers or clients, in order to their onset
or demand. It means that, the one who comes earlier would be given priority in the sequence of
their arrival. FCFS discipline of service delivery does not take any other parameter into
consideration like quantity, monetary value of the order, etc. If we select this method of delivery
to our clients, we are bound to release the order in the sequence of date.
2. Shortest Processing Time (SPT):
This process of scheduling is used for completion of work within the due date. This method
emphasizes on processing with the job which takes the least time. The division of the work is
done on the basis of input, processing time and the due date for the completion of assignment.
The flow time is calculated for the each part of the job, using the processing time, which helps in
determination of the overall time for the completion of work. This method is useful in single
machine environment.
3. Due Date Scheduling Technique (DD):
This technique of scheduling can be used with the reference of time either forward or backward.
When forward scheduling is used, it started with the date from which job order starts. It
calculates the period of time, from the day on which first operation was performed to all the
subsequent operation till the completion of the work. It determines the earliest time on which the
8
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
work can be completed. When the technique of back scheduling is used for calculating the period
of time of the completion of work, the resources are allocated in reverse order keeping in mind
the deadline of the completion of work and come to the date on which must start the operation,
so that the work can be completed within the due date.
4. Critical Ratio:
Critical Ratio is an index number computed by dividing the time remaining until due date by the
work time remaining. As opposed to priority rules, critical ratio is dynamic and easily updated. It
tends to perform better than FCFS, EDD, and SPT on the average job lateness (delays) criterion.
The critical ratio gives priority to jobs that must be done to keep shipping on schedule. It is used
in conjunction with MRP systems and has broad industrial application. The critical ratio is
measure of urgency of any order compared to the other orders for the same facility. The ratio is
based on when the completed order is required and how much time is required to complete.
These rules assume that setup time and setup costs are independent of the processing
sequence. However, this is not always the case. Jobs that require similar setups can reduce setup
times if sequenced back to back. In addition to this assumption, the priority rules also assume
that setup time and processing times are deterministic and not variable, there will be no
interruptions in processing, the set of jobs is known, no new jobs arrive after processing begins,
and no jobs are cancelled.
9
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
CHAPTER VII
Recommendation
Comparing the four methods, SPT is recommended to be used by the company because it
reduces average flow time for jobs. Since there are constraints such as they have to meet all the
orders within 23 days and the working hours is eight (8) hours per day, using this method they
will finished all the orders at the shortest period of time. Also, the flow time is calculated for the
every part of the job, using the processing time, which helps in getting whole time for the
completion of work.
In First come/first served method (FC/FS) it could not be applied because in this rule,
jobs are processed in the order in which they arrive. The orders must be finished in a shortest
period of time and not on how when the order arrived since they did not started the production on
June (arrival of orders) due to a problem. They started on July and this will not follow the rule.
Next, under Earliest due date method (EDD), it places the highest priority on processing
jobs with the earliest due dates. Job shop quality performance can be measured by the number of
late jobs, the average tardiness across late jobs or the average tardiness across all jobs. This
seems to work well if the firm performance is judged by job lateness. If this will be used, the
process will follow a track based on due dates of the orders and maybe it will not meet the time
constraints given.
Lastly the critical ratio method (CR), in this rule one must calculate a priority index using
the formula (due date–now)/ (lead time remaining). This rule is widely used in practice. However
in this rule, the sequencing of the jobs is done first by getting the critical ratio of each job then
selecting the lowest among them. Then it is repeated eliminating the job with the lowest CR
point until one job is left.
10
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
By choosing Shortest processing time (SPT), the job with the shortest processing time
requirement goes first. This rule tends to reduce work-in-process inventory, average throughput
time, and average job lateness. So this is the most appropriate rule to be used in order to meet the
limitations.
CHAPTER VIII
Conclusion/Detailed action Plan
A report about the choosing the Short Processing Time method must be made and this
will be used for the production. It must in detailed information so that the schedule will be
followed. Other points to implement:
Align demand and delivery;
Increase flexibility and reduce response/lead times at key points in the supply
chain;
Enable lean operations: reduce inventories and costs while meeting delivery
commitments.
Cost reduction can be achieved by a schedule that considers all rules and
constraints. Ignoring a rule/constraint usually results in increased cost due to
reduced productivity, higher inventory, increased offline work, overtime etc.
Customer Relationship Management
Dealer Order Management
Material planning
Scheduling of feeder lines
Vendor supply chain management
11
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
Job Date Order Received
Set-up Time Production Time Due Date
A 6/4 2 hrs 6 days 11 JulyB 6/7 4 hrs 2 days 8 JulyC 6/12 2 hrs 8 days 25 JulyD 6/14 4 hrs 3 days 19 JulyE 6/15 4 hrs 9 days 29 July
JobProcessing Time (days)
Flow time Days to Due date
A 6 6 7
B 2 8 5
C 8 16 19
D 3 19 14E 9 28 23Total 28 days 58 days 68 days
Based on the given information and initial table above, each method will be used for the
computation the criteria to be considered in choosing the best technique.
Sequence
Average Flow Time / Average completion time
Average Tardiness / delays
Utilization / Average # of Jobs at Work Center
Make span
Solution using FCFS Method:
12
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
In HOURS:
FCFS Sequencing
Job
Set-up Time (hours)
ProductionTime (hours)
TotalProcessingTime (hours)
Flow Time (hours)
Date Due
Days Due
Hours Due
Hours Tardy
A 2 48 50 50 11-Jul 7 56 0B 4 16 20 70 8-Jul 5 40 30C 2 64 66 136 25-Jul 19 152 0D 4 24 28 164 19-Jul 14 112 52E 4 72 76 240 29-Jul 23 184 56Total 240 660 68 544 138Sequence A, B, C, D, EAverage Flow Time / Average completion time (sum of total flow / no. of jobs)(660 hours / 5 jobs) 132.00Average Tardiness / delays (total delays / no. of jobs)(138 hours / 5 jobs) 27.6Utilization / Average # of Jobs at Work Center (total flow time / total processing time)(660 hours / 240 hours) 240.00Make span 2.75
Job
Set-up Time (days)
Processing Time (days)
Total Time (days)
Flow Time (days)
Date Due
Days Due
Hours Due (8 hours per day only)
Converted into Days
Hours Tardy
A 0.0833 2 2.0833 2.0833 11-Jul 7 56 2.333333333 0B 0.1667 3 3.1667 5.2500 8-Jul 5 40 1.666666667 4C 0.0833 6 6.0833 11.3333 25-Jul 19 152 6.333333333 5D 0.1667 8 8.1667 19.5000 19-Jul 14 112 4.666666667 15E 0.1667 9 9.1667 28.6667 29-Jul 23 184 7.666666667 21Total 28.6667 66.8333 68 544 22.66666667 44
Sequence A, B, C, D, EAverage Flow Time 13.37Average Tardiness 8.833333333Make span 28.67Average # of Jobs at Work Centre 2.33
13
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
Solution using SPT Method:
SPT Sequencing
Job
Set-up Time (hours)
Production Time (hours)
Total ProcessingTime (hours)
Flow Time (hours)
Date Due
Days Due
Hours Due
Hours Tardy
B 4 16 20 20 8-Jul 5 40 0D 4 24 28 48 19-Jul 14 112 0A 2 48 50 98 11-Jul 7 56 42C 2 64 66 164 25-Jul 19 152 12E 4 72 76 240 29-Jul 23 184 56Total 240 570 68 544 110
Sequence B, D, A, C, EAverage Flow Time / Average completion time (sum of total flow / no. of jobs)(570 hours / 5 jobs) 114.00Average Tardiness / delays (total delays / no. of jobs)(110 hours / 5 jobs) 22Utilization / Average # of Jobs at Work Center (total flow time / total processing time)(570 hours / 240 hours)
2.38
Make span 240
Solution using EDD Method:
EDD SEQUENCE
Job
Set-up Time (hours)
Production Time (hours)
Total ProcessingTime (hours)
Flow Time (hours)
Date Due
Days Due
Hours Due
Hours Tardy
B 4 16 20 20 8-Jul 5 40 0A 2 48 50 70 11-Jul 7 56 14D 4 24 28 98 19-Jul 14 112 0C 2 64 66 164 25-Jul 19 152 12E 4 72 76 240 29-Jul 23 184 56Total 240 592 68 82
Sequence B, D, A, C, E
14
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
Average Flow Time / Average completion time (sum of total flow / no. of jobs)(592 hours / 5 jobs)
118.40
Average Tardiness / delays (total delays / no. of jobs)(82 hours / 5 jobs)
16.4
Utilization / Average # of Jobs at Work Center (total flow time / total processing time)(592 hours / 240 hours)
2.47
Make span240
Another approach:
Job JOB TIME (Set up and Run Time) (in hours)
Date Order Received
Due Date
Days to Due date
SPTSequence
EDDSequence
A 6 days + .083 days (2 hours) = 6.083 days
6/4 11 July 36 days B B
B 2 days + .17 = 2.17 days 6/7 8 July 30 days D DC 8 days + .083 = 8.083
days6/12 25 July 42 days A A
D 3 days + .17 = 3.17 days 6/14 19 July 34 days C CE 9 days + .17 = 9.17 days 6/15 29 July 43 days E E
CR SequencingTABLE 1
15
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
Job
Set-up Time
(hours)
Production Time (hours)
Total Processing
Time (hours)
Date Due
Days Due
Hours Due
CR Ratio
A 2 48 50 11-Jul 7 56 1.12 LowestB 4 16 20 8-Jul 5 40 2.00C 2 64 66 25-Jul 19 152 2.30D 4 24 28 19-Jul 14 112 4.00E 4 72 76 29-Jul 23 184 2.42
Job CR Ratio ComputationA (56 – 0) / 50B (40 – 0) / 20C (152 – 0) / 66D (112 – 0) / 28E (184 – 0) / 76
CR SequencingTABLE 2 (Hour 48)
A FINISHED (1st)B 4 16 20 8-Jul 5 40 -0.50 LowestC 2 64 66 25-Jul 19 152 1.55D 4 24 28 19-Jul 14 112 2.21E 4 72 76 29-Jul 23 184 1.76
Job CR Ratio ComputationB (40 – 50) / 20C (152 – 50) / 66D (112 – 50) / 28E (184 – 50) / 76
JOB B = The job is on schedule. JOB D = The job is ahead of scheduleJOB C & E = The job is falling behind the schedule. And have some slack.
CR SequencingTABLE 3 (Hour 64)
A FINISHED (1st)B FINISHED (2nd)C 2 64 66 25-Jul 19 152 1.24 LowestD 4 24 28 19-Jul 14 112 1.50E 4 72 76 29-Jul 23 184 1.50
Job CR Ratio ComputationC (152 – 70) / 66D (112 – 70) / 28E (184 – 70) / 76
JOB C = The job is on schedule.JOB D & E = The job is falling behind the schedule.
CR Sequencing
16
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
TABLE 4 (Hour 88)A FINISHED(1st)B FINISHED(2nd)C FINISHED (3rd)D 4 24 28 19-Jul 14 112 -0.86 lowestE 4 72 76 29-Jul 23 184 0.63
Job CR Ratio ComputationD (112 – 136) / 28E (184 – 136) / 76
JOB D= The job is on schedule.JOB E = The job is falling behind the schedule.
CR Sequencing
Job
Set-up Time
(hours)
Processing Time
(hours)
Total Time
(hours)
Flow Time
(hours)Date Due
Days Due
Hours Due
Hours Tardy
A 2 48 50 50 11-Jul 7 56 0B 4 16 20 70 8-Jul 5 40 30C 2 64 66 136 25-Jul 19 152 0D 4 24 28 164 19-Jul 14 112 52E 4 72 76 240 29-Jul 23 184 56Total 240 660 68 138
Sequence B, D, A, C, EAverage Flow Time / Average completion time (sum of total flow / no. of jobs)(660 hours / 5 jobs) 132.00Average Tardiness / delays (total delays / no. of jobs)(138 hours / 5 jobs) 27.6Utilization / Average # of Jobs at Work Center (total flow time / total processing time)(660 hours / 240 hours) 2.75Make span 240
Comparison of Sequencing Rules
17
Hi-Ho Yo Yo, Inc.Case Analysis - FINALS
Rules
Average Flow Time
Utilization/ Average Jobs at Work
CentreAverage
TardinessFCFS 132.00 2.75 27.60 WorstSPT 114.00 2.38 22.00 BestEDD 118.40 2.47 16.40 GoodCR 132.00 2.75 27.60 Worst
In the table above, it is clearly shown what method to be used. Based on the average tardiness column, it clearly presented that SPT got the lowest point followed by EDD and the methods that gain bigger average tardiness is under FCFS and CR method.
Shortest processing time is generally the best technique for minimising job flow and minimising the average number of jobs in the system. Its chief disadvantage is that long-duration jobs may be continuously pushed back in priority in favour of short-duration jobs. Customers may view this dimly, and a periodic adjustment for longer jobs has been made.
18