caribbean cement_pdd 2007 12 21

Upload: nuno-ferreira

Post on 03-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    1/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 1

    CLEAN DEVELOPMENT MECHANISM

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD)Version 03 - in effect as of: 28 July 2006

    CONTENTS

    A. General description of project activity

    B. Application of a baseline and monitoring methodology

    C. Duration of the project activity / crediting period

    D. Environmental impacts

    E. Stakeholders comments

    Annexes

    Annex 1: Contact information on participants in the project activity

    Annex 2: Information regarding public funding

    Annex 3: Baseline information

    Annex 4: Monitoring plan

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    2/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 2

    SECTION A. General description of project activity

    A.1 Title of the project activity:

    Title: Blend increasing in the cement production of Caribbean Cement Company Ltd.

    Version number of the document: 01

    Date of the document: 19/December/2007

    A.2. Description of the project activity:

    Project Activity

    Caribbean Cement Company Ltd (hereinafter referred as CCCL) (Figure 1) is the sole manufacturer of

    cement in Jamaica, operating a dual process cement manufacturing plant, utilizing both the wet and dry

    process technologies to produce the Ordinary Portland Cement (OPC).

    Concerned about the sustainable development of the country, CCCL has embarked in an Expansion and

    Modernization Programme, to expand the production capacity to meet market demand increase (domestic

    market is conservatively forecast to grow by approximately 4% per annum), and in the same time, reduce

    environmental impact, improving gaseous emissions control, implementing more energy efficient

    technologies to reduce electricity and fossil fuel consumption, bringing the plant in line with the best

    industry technologies and standards.

    The purpose of the project activity involves the use of pozzolan, an alternative raw material, as

    substitute of clinker. Pozzolan is derived from material present in volcanic ash and is indigenous to the

    region where the plant is located, because of the presence of active volcanoes in some of the neighbouring

    islands. Pozzolan was found in a footprint of the existing gypsum quarry, so will not result in new area

    degradation.

    The company now supplies a local market in the region of 1 million tonnes of cement. In February

    2005, the company initiated a

    conversion of the local market from a

    predominantly OPC - Type 1, to a

    blended cement - Type 1P market. The

    average clinker content in cement has

    reduced by approximately 15%. Thisresults in a reduction in the specific

    energy and power consumptions to

    produce cement. It also results in a

    proportional reduction in the emission

    of carbon dioxide, which is produced in

    the production of clinker.

    Greenhouse gases emissions are

    reduced as a result of the decrease on

    emissions during the calcinations of

    limestone and due to the reduction of Fi ure 1 Caribbean Cement Com an Ltd. Plant

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    3/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 3

    fossil fuels consumption in the kiln.

    The manufacture of blended cements with high contents of pozzolan and relatively high strengths maycause difficult problems, which may increase when the grindability of the components is very different

    and the moisture content of the pozzolan is high.1.

    Initially, several search and development were done to assure the blended cement quality, inclusive

    working together to the Bureau Jamaica Standard, to develop the technical standard for the pozzolan

    blended cement as this is the first time blended cement is produced in Jamaica. Although new to Jamaica,

    the Pozzolan process is currently used by many cement manufacturers worldwide, particularly those in

    Europe. Due to poor awareness levels on use and preparation of Carib Plus for building and other benefits,

    the product acceptability levels of Carib Plus with higher additive % were very low in the beginning.

    In 2010 is planned the substitution of Kiln #3 that operates in wet process by a new Kiln #5 that will

    operates in dry process, which is more efficient. Cement Mill #4 will be upgraded and Cement Mill #3

    will be replaced by Mill #5. Although theses substitutions will result in energy saving in the clinker andcement process, CO2 emission reductions resulting from these savings will not be claimed in this project

    activity, as stated by methodology ACM0005.

    Cement Production Process

    Cement is made by heating limestone with small quantities of other materials, such as clay, to 1,450C

    in a kiln. The resulting hard substance, called clinker, is then ground into a powder, in cement mills, with

    a small amount of gypsum to make the Ordinary Portland Cement (OPC), the first produced type of

    cement. Other materials can be used in substitution of clinker in the grinding phase of the fabrication,

    producing the so-called blended cement. Pozzolan is one of these alternative materials, resulting in the

    production of the Blended Type 1 Cement, known as Carib Cement Plus.

    Pozzolan will be used in the project activity as clinker substitute. It is used in the grinding phase of

    cement production chain, i.e. pozzolan replaces clinker in the cement mills avoiding, then, clinkerproduction in the kilns.

    It is important to highlight that the cement industry plays a significant role in Climate Change2. First

    because the cement manufacture is an energy intensive process, demanding large amounts of fuel and

    electricity in the whole process chain. In addition, the chemical process of producing clinker (calcination

    of limestone) produces non-renewable CO2. These two factors results in that the cement industry is

    responsible for a significant portion of global man-made CO2 emissions. It is estimated that 50% of the

    cement industry GHG emissions derive from the chemical process, and 40% from burning fuel. The

    remainder is split between electricity and transport uses.

    Company History

    CCCL was incorporated in 1947, and the first bag of cement was delivered in 1952. The company has

    transitioned from private ownership in the 1950s, to the state acquiring controlling interest in the 1970s,to Scancem and later to Cemex operating the plant under management contracts in the 1990s, and finally,

    to the divestment of the Governments interest to Trinidad Cement Limited in 1999.

    CCCL is the sole manufacturer of cement in Jamaica and was the sole supplier until as recently as 1999.

    The size of the cement market has grown substantially over the last 10 years: demand has increased by

    1 Baragano Coronas, J. R.; Rey y Vazquez de la Torre, P.; Difficulties in the manufacture of cements with grinding

    additives; Spain, 1986 in Portland Cement Association: www.cement.org

    2World Business Council for Sustainability Development. Cement Sustainability Initiative Progress Report. June

    2005.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    4/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 4

    52% or 5.1% per annum. The domestic market is conservatively forecast to grow by approximately 4%

    per annum from 862,289 tonnes in 2004 to 1,291,167 tonnes in 2010.CCCL presently holds the dominant share of the domestic market and is developing and implementing

    strategies to meet this increasing demand and to provide even better service to the construction industry.

    The modernization and expansion of the existing plant is necessary in order to meet the growing demand

    for cement in Jamaica as well as the need to reduce fuel consumption, improve production efficiencies

    and environmental performance.

    Concurrent with the developments in Jamaica and the wider business world, the company has gone

    through several changes. In addition to the changes in ownership and leadership, the company has had

    three major plant expansions to meet increasing consumption.

    The company has embarked on an Expansion and Modernization Programme, which involves the

    retiring of obsolete technology and expensive operating units. Caribbean Cement Company Ltd. willinstall and commission new plants to increase capacity, continue to meet market demand, reduce

    operating costs and improve environmental performance.

    The project activity contributes to sustainable development in the following manners:

    - The project activity helps mitigating Climate Change because of the significant reductions ofdirect and indirect greenhouse gases emissions.

    - Project activity contributes to the reduction of energy consumption in the cement manufacturechain and consequently to the conservation of energy resources. The increase in the use of

    pozzolan in place of clinker reduces energy demand in cement manufacture and mining of

    limestone. Both import of grid energy and fossil fuel consumption are reduced. This is an

    improvement in the usage of a commodity that is supplied by the power utility in the case of grid

    energy, and supplied internally in the case of fossil fuel;- The reduction of fossil fuel consumption also results in the reduction of local air pollution;

    - Energy consumption is reduced also during cement milling process because of the fact thatpozzolan is easier to grind than clinker;

    - The reduced use of clinker helps in the conservation of non-renewable reserves of limestone.

    - The substitution on part of limestone mining to pozzolan mining, reduces noise and vibrationpollution as the limestone mining requires the blasting of dynamite, and pozzolan mining does

    not.

    - The limestone quarry is located riverside, causing water pollution from the mining activities. Onthe other hand the pozzolan quarry is located far from waterfront, decreasing water pollution

    There is only one registered CDM project in Jamaica. The acceptation of the CCCL project will attract

    new players in the country. In entire Caribbean, composed by 13 independent countries and 11 territories

    there are only 2 (two) CDM registered projects. Both of Wind Farm, one in Dominican Republic and one

    in Jamaica. The CCCL project if registered as CDM, could stimulate other countries in the Caribbean

    region and the Central America to manufacture blended cements, or improve the share of additives,

    leading to benefits explained above.

    Additionally, the incomes from the CDM will indirectly support and stimulate Caribbean Cement

    Company Ltd. in keeping and improving its social and environmental programs already developed with

    the local community and employees at several locations. Information is available at the company website:

    http://www.caribcement.com/community/

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    5/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 5

    A.3. Project participants:

    >>

    Table 1 - Parties involved in the project activity

    Name of Party involved (*)

    ((host) indicates host

    Party)

    Private and/or public entity(ies)

    project participants (*)

    (as applicable)

    Kindly indicate if the Party

    involved wishes to be considered

    as project participant (Yes/No)

    Jamaica (host)

    Caribbean Cement Company

    Limited

    (private entity)

    BrazilEcoinvest Carbon SA

    (private entity)

    NO

    (*) In accordance with the CDM modalities and procedures, at the time of making the CDM-PDD public at the stage

    of validation, a Party involved may or may not have provided its approval. At the time of requesting registration, the

    approval by the Party(ies) involved is required.

    Note: When the PDD is filled in support of a proposed new methodology (forms CDM-NBM and CDM-NMM), at

    least the host Party(ies) and any known project participant (e.g. those proposing a new methodology) shall be

    identified.

    A.4. Technical description of the project activity:

    A.4.1. Location of the project activity:

    >>

    A.4.1.1. Host Party(ies):

    >>Jamaica

    A.4.1.2. Region/State/Province etc.:

    >>Saint Andrew

    A.4.1.3. City/Town/Community etc:

    >>Kingston, Kingston Harbour

    A.4.1.4. Detail of physical location, including information allowing the

    unique identification of this project activity (maximum one page):

    The project activity encompasses the cement manufacturing plant located in Kingston, Jamaica.

    Kingston is the capital of Jamaica, with 652,000 inhabitants, and is located on the southeastern coast of

    the island country.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    6/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 6

    Project boundary encompasses the cement manufacturing plant and new additive (pozzolan) source

    located 12km away from cement plant, , as well as the pozzolan transportation route.The CCCCL facility is located on the south coast of Jamaica, in Kingston Harbour. It lies within the

    Kingston Metropolitan Area (KMA), with the Liguanea Plains, Kingston, Long Mountain to the west.

    The Blue Mountains, to the north, Harbour View and St Thomas to the east and Kinsgton Harbour, the

    Palisades and the Norman Manley International Airport to the south.

    Figure 2: Map showing the location of the city of Kingston in Jamaica, and CCCL plant.

    (References: 1. Wikipedia, 2. CCCL internal document, 3. Google Maps 2007)

    Address and Geographical Coordinates:CCCL Plant: PO Box 448, Rockfort, Kingston 2.

    17o 5748 N, 76o 4352 W.

    Pozzolan Quarry: Bito/Jacksonville District, Saint Andrew Parishi

    17o

    5656.8 N, 76o

    3929.8 W.

    In Jamaican JAD69 coordinates: 286200E, 144400N

    A.4.2. Category(ies) of project activity:

    >>

    The project activity pertains to Sectoral Scope 4 (Manufacturing industries).

    2

    3

    1

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    7/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 7

    A.4.3. Technology to be employed by the project activity:

    >>

    Pozzolan Blended Cement

    Since the beginning of the Christian era, the Italians have successfully employed pozzolan cement,

    made by grinding 2 to 4 parts of a pozzolan with 1 part of hydrate lime. A pozzolan is a material which is

    not cementitious in itself but which becomes so upon admixture with lime. The early strength of a

    pozzolan cement is lower than that of Ordinary Portland cement, but within a year the strengths are equal.

    The advantage of this cement is that it resists the corrosive action of saline solutions and seawater much

    better than does Ordinary Portland cement. (ref3).

    Greater Resistance to Alkali Attack and greater resistance to Chloride Penetration: This property makes

    Carib Cement Plus ideal for the tropical market and suitable for structures erected near the sea. Concrete

    made with Carib Cement Plus offers greater protection to reinforced steel from Chloride attack.

    Clinker Production Process

    CCCL operates a dual process cement manufacturing plant, utilizing both the wet and dry process

    technologies. The dry process, using preheaters and precalciners, is both economically and

    environmentally preferable to the wet process because the energy consumption (3,200 kJ/kg) is

    approximately half of that for the wet process.

    One of the line, Kiln No.3, is a wet process plant. This kiln line consists of: two wet raw mills, Raw

    Mills 2 and 3; slurry basins; slurry pumps; the rotary kiln; an ID fan; and a fabric filter to clean the kiln

    exhaust gases (Figure 3).

    The other line, Kiln No.4, is a dry process line and consists of: a preheater tower; the rotary kiln;preheater ID fan; dry process vertical roller mill; electrostatic precipitator (EP) to clean the exhaust gases;

    and an EP fan (Figure 4).

    A new line, Kiln No.5 will be constructed in the plant footprint decommissioning the Kiln No.3. This

    shift is planned to finish in 2010. The new line system consists in a vertical roller mill, preheater vessels,

    calciner, kiln, and clinker cooler will all use the most recent technology, thus significantly lowering

    operating costs and providing the best environmental performance.

    Wet process

    The critical manufacturing step, called pyroprocessing, takes place in the cement kiln. The prepared

    raw feed is pumped into the kiln where it is exposed to gas temperatures starting at 260C at the elevated

    feed end to over 1,870C near the product discharge end. After tumbling slowly through the kiln,exothermic chemical changes in the burning zone transform the raw materials to cement clinker, a product

    physically resembling grey gravel.

    The production of clinker in a wet kiln requires that the solid material be heated to approximately

    1,400C to 1,482C, while the gaseous material reaches a temperature of greater than 1,870C. Tricalcium

    silicate is the major strength-producing constituent of cement, and its formation begins in the burning

    zone at material temperatures above 1,400C. Other clinker compounds important for the performance of

    Portland cement are formed by reactions that take place in the burning zone.

    3 Austin, G.T.; Shreves Chemical Process Industries, 5 th edition, McGraw-Hill (1984)

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    8/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 8

    Exhaust gases from the kiln are routed to the air pollution control system and then discharged to the

    atmosphere through a stack.

    Figure 3 - Representation of the wet process (Ref: WBCSD, 20064

    )

    Dry Process

    Initially, the crushed raw materials (raw meal feed i.e., limestone, clay, ash, sand, and/or iron ore) enter

    the raw mill to be dried and ground. A fan draws hot combustion gas from the top of the preheater tower

    into the raw mill to evaporate moisture from the raw meal, as it is ground. The prepared raw meal feed is

    transported to a blending silo where it is held pending introduction into the pyroprocess.

    The dry process, by re-use of the hot gases for drying raw materials and with the use of the vertical

    tower for calcining the raw material is very energy efficient. The rapid heating of the raw materials is the

    key to the efficiency of the preheater tower. The entrainment of the raw material in the air stream and

    collection of the solids through the cyclones transfers heat to the raw materials rapidly and efficiently.

    The addition of fuel in the precalciner also prepares the raw material for final chemical transformation inthe rotary kiln.

    4WBCSD, 2006. Formation and Release of POPs in the Cement Industry Second edition, World Business

    Council for Sustainable Development http://www.wbcsdcement.org/.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    9/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 9

    Figure 4 - Representation of the dry process (Ref: WBCSD, 20064)

    Raw materials for both production lines are supplied by limestone and shale quarries operated by

    CCCL. Together, the limestone and two types of shale supply the necessary chemical components for kiln

    feed that will produce high quality clinker and cement chemistry while providing good performance in

    the kilns. These three raw materials are stored in a longitudinal storage and reclaiming facility known as a

    Reclaimer. Raw materials enter the storage hall on one of two conveyor belts, one for limestone, the other

    for the two shales. Each has a movable, overhead tripper that stacks the raw materials into one of four

    bays. A single, portal reclaimer withdraws the raw materials and deposits them on the reclaim belt. From

    the reclaim belt, the raw materials may be directed onto a series of belt conveyors that transports them to

    raw mill feed bins, and from there into either wet raw mills 2 and 3 or dry raw mill 4. Raw mill product

    from the wet raw mills is stored in slurry basins where it is blended and stored for use in kiln system 3.

    Raw mill product from Raw Mill No.4 is pneumatically conveyed to a 1200-ton capacity blending silo,

    and then to a 3500-ton capacity kiln feed storage silo for subsequent use in the Kiln No.4 system.

    In order to achieve the objectives of energy conservation, the clinker produced in rotary kiln is cooled

    in a counter current air cooler. Typically, it is also stored for few days before it is ground in cement

    grinding mills along with appropriate quantity of gypsum and other additive materials for production of

    finely pulverized cement with desired fineness.

    Cement Milling

    The Ball / Tube millss are used for clinker grinding in cement plants. Cement mills 3 and 4 are used in

    open circuit and closed circuit modes respectively.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    10/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 10

    Mill 3 will be decommissioned and substituted by new Mill 5, with a more energy efficient technology.

    This shift is planned to finish in 2010.

    Energy

    The company currently uses Bunker C, Coal and Petroleum Coke to fuel the Clinker Manufacturing

    Process. Electrical power is provided by the Jamaica Public Service Company Limited, which is the

    national grid supplier.

    Table 2 Kiln and Mil description

    Line 3 (wet) Line 4 (dry) Line 5 (dry)

    Kiln Supplier Allis Chalmers Allis Chalmers F.L. Smidth

    Maximum Production Capacity

    (tones/day)705 1250 2800

    Diameter (meters) 4 4.26 4.55

    Length (meters) 120 60 54

    Mill Supplier F.L. Smidth Allis Chalmers Loesche

    Power (HP) 2,000 4,500 4,224

    Maximum Production Capacity

    (tones/h)40 for OPC 100 for OPC 110 for Carib Plus

    A.4.4 Estimated amount of emission reductions over the chosen crediting period:

    >>

    The chosen crediting period for this project is the non-renewable crediting period of 10 years. The

    estimated amount of emission reductions of the project can be seen at Table 3.

    Table 3 Estimated emission reductions for the crediting period

    YearsAnnual estimation of

    emission reductions intonnes of CO2

    2008 (from July 1st

    ) 153.490

    2009 187.175

    2010 217.262

    2011 228.712

    2012 237.569

    2013 242.433

    2014 239.114

    2015 235.728

    2016 232.275

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    11/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 11

    2017 228.753

    2018 (until June 30th ) 112.580

    Total Estimated Reductions(tonnes of CO2e)

    2.315.089

    Total number of crediting years 10

    Annual average over thecrediting period of estimatedreductions (tonnes of CO2e)

    231,509

    A.4.5. Public funding of the project activity:>>

    There were no public funding the project activity.

    SECTION B. Application of a baseline and monitoring methodology

    B.1. Title and reference of the approved baseline and monitoring methodology applied to the

    project activity:

    >>

    Main Methodology: ACM 0005 Consolidated Baseline Methodology fro Increasing the Blend in Cement

    Production, version 04, EB35

    Methodological Tool: Tool to calculate the emission factor for an electricity system , version 01,

    EB35

    Tool for the demonstration and assessment of additionality, version 04

    B.2 Justification of the choice of the methodology and why it is applicable to the project

    activity:

    >>

    Methodology for the Blended Cement

    ACM0005 is applicable to projects that increase the share of additives (i.e. reduce the share of clinker) in

    the production of cement types beyond current practices in the country. Additives are defined as materials

    blended with clinker to produce blended cement types and include fly ash, gypsum, slag, etc.

    In the case of Caribbean Cements project, the increase in the share of additives and respective reduction

    in the share of clinker in the production of cement occurs due to the use of pozzolan beyond current

    practices in the country.

    The methodology is applicable to this project activity because it meets the applicability conditions:

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    12/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 12

    - There is no shortage of additives related to the lack of blending materials. Project participantsshould demonstrate that there is no alternative allocation or use for the additional amount of

    additives used in the project activity.

    Pozzolan use in CCCL has natural source and is derived from material present in volcanic ash

    that is indigenous to the region where the plant is located, because of the presence of active

    volcanoes in some of the neighboring islands. Pozzolan was found in the gypsum quarry owned

    by Jamaica Gypsum and Quarries Limited (JGQ), a CCCL subsidiary company, which supplies

    the company with the gypsum used in the manufacture of its cement Therefore, the shortage of

    pozzolan is unlikely and the alternative allocation for it would be maintain the pozzolan at place,

    without quarrying.

    - ACM0005 is applicable to domestically sold output of the project activity plant and excludesexport of blended cement.

    The production of the blended cement in the project activity is sold domestically; therefore no

    export of blended cement is included. In the event that some part of the production is exported in

    the future, then, this amount shall be discounted from emissions reductions calculations.

    Until now, only the Ordinary Portland Cement, Type 1 is exported.

    - Adequate data are available on cement types in the market.

    According to ACM0005, blended cement type (BC) is defined as distinct products with

    different uses, additives and additive to clinker ratios. In this project activity blended cement type

    is Portland Pozzolan cement.

    Until half of 2006, CCCL was the sole cement seller in Jamaica, producing only Ordinary

    Portland Cement (OPC). In this way, the Bureau of Standards Jamaica (BSJ) has standard only

    for OPC. When CCCL planned to start producing blended cement, CCCL uses the United States

    standard American Society for Testing and Materials (ASTM) C-595 for blended Portland

    cements as reference. CCCL pozzolan cement was approved by BSJ.

    For Ordinary Portland Cement and rapid-hardening, BSJ has the standard JS32 Part 1: 1999

    A Jamaican Standard Specification for Blended Hydraulic Cements is being developed, has

    already been approved by the Standards Council 5, 6, resulting in a draft standard 7.

    The draft standard made available by BSJ to CCCL, classifies the blended cement in 4 (four)

    types as follows:Table 4 Blended Cement Type in Jamaica

    Description Additive Range (%)Portland Blast Furnace Slag Cement 25 70

    Portland Pozzolan Cement 15 - 40

    Slag Modified Portland Cement Less than 25

    Pozzolan Modified Portland Cement. Less than 15

    5 Bureau of Standards Jamaica. Standards Development Work Pogramme. April 2006 September 2006

    6 Ministry of Industry, Technology, Energy and Commerce. Performance of the Bureau of Standards, Jamaica

    (BSJ) for Financial Year 2005/2006 and Focus for Financial Year 2006/2007.June 20, 2006.

    7 Jamaican Standard Specifications for Blended Hydraulic Cements (Final Draft). Bureau of Standards Jamaica.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    13/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 13

    Reference: Jamaican Standard Specifications for Blended Hydraulic Cements. Bureau ofStandards Jamaica (Final Draft)

    For the purposes of this standard, the following definitions and terminology shall apply

    PORTLAND CEMENT CLINKER

    A clinker consisting predominantly of crystalline hydraulic calcium silicates

    PORTLAND CEMENT

    A hydraulic cement made by pulverizing Portland cement clinker, and which usually contains

    calcium sulphate.

    SLAG MODIFIED PORTLAND CEMENT

    An intimate and uniform blend of Portland cement and finely ground granulated blast furnace

    slag in which the slag constituent is kept within certain limits.

    PORTLAND BLAST FURNACE SLAG CEMENT

    A hydraulic cement consisting of an intimately interground mixture of Portland cement or

    portland cement clinker and granulated blast furnace slag with the proportion of the slag

    constituent restricted within certain specified limits.

    POZZOLAN

    A siliceous or siliceous and aluminous material which in itself possesses little or no cementitious

    property but which, in a finely divided form, will react chemically with calcium hydroxide in the

    presence of moisture at ordinary temperatures to produce compounds possessing cementitiousproperties.

    POZZOLAN MODIFIED PORTLAND CEMENT

    An intimate and uniform blend of Portland cement or Portland blast furnace slag cement and a

    finely ground pozzolan in which the pozzolan constituent is kept within certain limits.

    PORTLAND POZZOLAN CEMENT

    A hydraulic cement consisting of an intimate and uniform blend of Portland cement or Portland

    blast furnace slag cement and a fine pozzolan in which the proportion of the pozzolan constituent

    is kept within specified limits

    B.3. Description of the sources and gases included in the project boundary

    The project boundary includes the cement production plant, any onsite power generation, and the power

    generation in the grid. Three emission sources are considered:

    - Direct emissions at the cement plant due to fuel combustion for firing the kiln and on-sitegeneration of electricity.

    - Direct emissions due to calcination of limestone.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    14/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 14

    - Indirect emissions from fossil fuel combustion in power plants in the grid due to electricity use at

    the cement plant for: crushing and grinding the raw materials used for clinker production; drivingthe kiln and kiln fans; finish grinding of cement; and processing of additives.

    Figure 5 Project Activity Boundary

    Any transport related emissions for the delivery of additional additives will be included in the emissions

    related to the project activity as leakage.

    Emissions reductions from transport of raw materials for clinker production are not taken into account as

    a conservative simplification.

    Only CO2 is considered in the calculations because changes in CH4 and N2O emissions from combustion

    processes and calcination are considered to be negligible and excluded because the differences in the

    baseline and project activity are not substantial. This assumption is conservative and in accordance with

    ACM0005.

    Source Gas Included? Justification/Explanation

    el Calcination of CO2 Yes Main source of emissions.

    RAW MATERIAL

    SUPPLY

    Quarrying,Transport

    RAW MATERIAL

    SUPPLY

    Quarrying,Transport

    FUELS

    PREPARATION

    Crushing,Grinding, Drying

    FUELS

    PREPARATION

    Crushing,Grinding, Drying

    PYRO-

    PROCESSING

    Calcinations,Clinkering, Cooling

    PYRO-

    PROCESSING

    Calcinations,Clinkering, Cooling

    CEMENT

    GRINDING

    Clinker

    Electricity from Grid

    Bagging &Transport

    TRANSPORT

    PREPARATION

    (Drying, Crushing)

    FUEL

    FIRING

    ADDITIVES

    QUARRYING

    PREPARATION

    Crushing, drying,grinding,

    homogenizing

    PREPARATION

    Crushing, drying,grinding,

    homogenizing

    Project Boundary

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    15/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 15

    CH4 No Excluded. This is conservative.limestone

    N2O No Excluded. This is conservative.

    CO2 Yes

    Main source of emissions. Fuel firing in the clinker

    production kiln and fuel consumption in the additive

    transport.

    CH4 NoExcluded. Emissions are considered negligible. This is

    conservative.

    Fossil Fuel

    combustion

    N2O NoExcluded. Emissions are considered negligible. This is

    conservative.

    CO2 YesMay be an important emission source in cement

    production process as well as additives transport.

    CH4 No Excluded. This is conservative.

    Grid Electricity

    Consumption

    N2O No Excluded. This is conservative.

    CO2 Yes Main source of emissions.

    CH4 No Excluded. This is conservative.Calcination of

    limestoneN2O No Excluded. This is conservative.

    CO2 Yes

    Main source of emissions. Fuel firing in the clinker

    production kiln and fuel consumption in the additive

    transport.

    CH4 NoExcluded. Emissions are considered negligible. This is

    conservative.

    Fossil Fuel

    combustion

    N2O NoExcluded. Emissions are considered negligible. This is

    conservative.

    CO2 YesMay be an important emission source in cement

    production process as well as additives transport.

    CH4 No Excluded. This is conservative.

    Proje

    ctActivity

    Grid Electricity

    Consumption

    N2O No Excluded. This is conservative.

    B.4. Description of how the baseline scenario is identified and description of the identified

    baseline scenario:

    Identification of the baseline scenario

    The baseline scenario is the most plausible scenario among all realistic and credible alternative

    production scenarios for the relevant cement type that are consistent with current rules and regulations.

    Project proponents identify the baseline scenario in Section B.5 through the use of Step 3 Barrier

    Analysis of the latest approved version of the Tool for the determination and assessment of

    additionality.

    Alternative project activities that would take place are as follow:

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    16/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 16

    - Alternative 1: the proposed project activity undertaken without being registered as CDM project

    activity. Production of pozzolan blended cement Carib Plus;- Alternative 2: continuation of the current situation. In this scenario CCCL continues to produce

    only Ordinary Portland cement, and does not use pozzolan or any other additives ;

    - Alternative 3: use of other additives different from natural pozzolan. In this scenario CCCL usesother additives, such as blast furnace slag, fly ash from thermal power plants, in the production of

    blended cement above the benchmark level.

    Section B.5 describes the barriers that alternatives 1 and 3 faces preventing the implementation, resulting

    that Alternative 2 is the most plausible baseline scenario Please, refer to Section B.5 for detailed barrier

    analysis.

    Definition of BBlend,y from benchmark analysis

    The baseline benchmark of share of clinker per tonne of BC, BBlend,y, is defined as the lowest value among

    the following:

    (i) The average (weighted by production) mass percentage of clinker for the 5 highest blendcements brands for the relevant cement type in the region; If region comprises of less than 5

    blend cement brands, the national market should be used as the default region; or

    (ii) The production weighted average mass percentage of clinker in the top 20% (in terms ofshare of additives) of the total production of the blended cement type in the region. If 20%

    falls on part of a plant, that plant is included in the calculations; or(iii) The mass percentage of clinker in the relevant cement type produced in the proposed project

    activity plant before the implementation of the CDM project activity, if applicable (for

    Greenfield project activity this option may be excluded).

    CCCL is the sole cement manufacture as well as the sole seller in Jamaica until half of 2006. Therefore,

    option iii) is used to calculate benchmark share of clinker. The lowest percentage of clinker used over the

    3 most recent years before project implementation is selected and an increasing trend of 2% in the blend

    is incorporated, as indicated in ACM0005 up to the limit of the regulatory/product norm in the national

    market. Jamaican

    According to the Draft Standard for blended cement defined by the Bureau of Standards Jamaica, the

    limit for Portland Pozzolan Cement (Carib Plus) is 40% of pozzolan.

    Project activity started in the beginning of 2005, after decision of the Group Budget Meeting in

    December 2004. Therefore years 2002, 2003 and 2004 are used to define the baseline share of clinker.

    According to ACM0005, at the renewal of the crediting period, the benchmark shall be recalculated. The

    basis (between the 3 options) of the benchmark may change from the option selected during the first

    crediting period.

    Detailed information and calculation can be found in Section B.6.1.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    17/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 17

    B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below

    those that would have occurred in the absence of the registered CDM project activity (assessmentand demonstration of additionality): >>

    The additionality of the project activity is demonstrated and assessed using the Tool for the

    demonstration and assessment of additionality Version 4.

    Step 3 of the Tool is used to identify the most plausible scenario among all realistic and credible

    alternatives(s) to the project activity, i.e. the baseline scenario.

    Step 1. Identification of alternatives to the project activity consistent with current laws and

    regulations

    Sub-step 1a. Define alternatives to the project activity:

    Realistic and credible alternatives are production scenarios for the relevant cement type that are consistent

    with current rules and regulations available to the project participants or similar project developers. They

    include the proposed project activity, the existing practice of cement production and practices in other

    manufacturing plants in the region using similar input/raw materials and facing similar economic, market

    and technical circumstances:

    - Alternative 1: the proposed project activity undertaken without being registered as a CDM projectactivity. In this scenario CCCL uses natural pozzolan in the production of blended cement above

    the benchmark level, as in the project activity;- Alternative 2: continuation of the current situation. In this scenario CCCL does not change its

    production pattern, thus continuing to produce only the Ordinary Portland cement;

    - Alternative 3: use of other additives different from natural pozzolan. In this scenario CCCL usesother additives, such as blast furnace slag, fly ash from thermal power plants, in the production of

    blended cement above the benchmark level.

    Sub-step 1b. Consistency with mandatory laws and regulations:

    As there is no modification in equipments or implementation of new facilities in neither case, all the

    alternatives are in compliance with all applicable legal and regulatory requirements.

    Step 2. Investment analysis

    Investment analysis is not undertaken.

    Step 3. Barrier analysis

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    18/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 18

    As showed below, the proposed project activity faces barriers that prevent the implementation of this type

    of proposed project activity; and do not prevent the implementation of at least one of the alternatives.

    Sub-step 3a. Identify barriers that would prevent the implementation of the proposed CDM project

    activity:

    The following barriers would prevent the implementation of the proposed project activity:

    - Barrier 1 (research effort): to shift from an ordinary Portland cement to a blended cement,substantial research effort in the process and quality to enable the blend should be developed.

    - Barrier 2 (market acceptance): the perception that high additive blended cement is of inferior

    quality could happened in the early stages of the project, requiring market clarifying work, aswell as technical seminar to train masons to use correctly the blended cement.

    - Barrier 3 (first of its kind). when blended cement is produced and offered to the public at firsttime, public acceptance to a new type of cement is more difficult than persuade to use a higher

    blending in a public used to that type.

    - Barrier 4 (technological transfer). The use of new additives of different fineness and mineralogycould lead to necessity of change in the process and also of the equipments. Intimate and uniform

    blends of two or more fine materials are difficult to achieve. The manufacturer should therefore

    ensure that adequate equipment and controls are provided and that the blending process is

    adequate. The purchaser may also assure himself of the adequacy of the blending operation8.

    - Barrier 5 (operational). In a plant that uses to produce only one type of product, an increase in the

    product type could lead to change in the control of the process, to ensure not mixing theadditives, during pre-treatment, transport, production, storage and package.

    - Barrier 6 (lack of additive). Different type of additive should be available to be used in theblended cement production.

    Sub-step 3 b. Show that the identified barriers would not prevent the implementation of at least one of

    the alternatives (except the proposed project activity):

    Table 5 shows how barriers affect each one of the alternative scenarios identified in Step 1.

    Table 5 - Effect of Barriers in Each Alternative Scenario

    Alternative 1

    Proposed project

    activity without CDM

    Alternative 2

    Continuation of the

    current situation

    Alternative 3

    Use of other additives

    Barrier 1

    Research effortPrevents implementation

    Does not prevent

    implementationPrevents implementation

    8 Jamaican Standard Specifications for Blended Hydraulic Cements (Final Draft). Bureau of Standards Jamaica.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    19/73

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    20/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 20

    At first, CCCL tried to use the pozzolan in the clinker production. However this resulted in a high

    corrosion of the kiln. In addition, when the shale was replaced with pozzolan, the calibration of thechemical analyzer was not adjusted to the new material, natural pozzolan, hence results were misleading.

    Other physical analyses (such as granulometry, petrography) which would help in determining its

    suitability were no conclusive10

    .

    After the above results, tests were shifted to add the natural pozzolan to the produced clinker in the

    cement mill. Numerous trials & experiments with varying percentage of natural pozzolan addition and

    clinker to examine the impact on each other as well as their combined final impact on the strength

    properties ofCarib Plus manufactured. CCCL also carried out numerous trials with varying fineness of

    Carib Plus with numerous permutations and combinations of different pozzolan percentage additions and

    different clinker qualities.

    The quality is influenced by the grinding system selected. Much attention is put on the physical

    characteristics of the fly ash: bulk weight, specific weight, particle distribution, particle shape, degree of

    agglomeration and colour11.

    The cement produced in these initial trial runs was subjected to the laboratory physical tests required in

    ASTM C 595for blended hydraulic cements, such as the compression strength tests (1-day, 7-days, 28-

    days). As the preparation of motor cubes required a constant flow approach, a new flow table was

    purchased.

    Research and Development on Pozzolan Portland cement (Carib Plus) use

    Also, in the testing phase the product was provided to block manufacturers for trial use in making their

    blocks. This phase lasted about four (4) months and required close liaison with the targetted.

    The trials also included several controlled concrete trials to prove that the Carib Plus was compatible

    with the local aggregates.

    Samples of the new cement were also sent to Concrete Technologies Laboratory, U.S.A. for various

    analyses, including Alkali Suplhur Ratio (ASR).

    The cement is approved by the Jamaica Bureau of standards and meets the ASTM C 595 designation. A

    Jamaican blended cement standard is being developed.

    Barrier 2 (market acceptance) and Barrier 3 (first of its kind)

    As mentioned earlier, CCCL is the sole cement manufacture in Jamaica and until 2005 was also the sole

    seller of cement in entire Jamaica. In this way, Jamaica consumers have been exposed only to OPC over

    the years. The market acceptability ofCarib Plus with a higher additive percent is one of the major

    barriers due to prevailing practice. The customer resistance was found to be very high due to their lowawareness levels. CCCL had to overcome this barrier and to inform and clarify the market about the

    quality of the high additive blended cement.

    Carib Cement introduced the new blended pozzolanic cement to the Jamaican marketplace in 2005.

    10 Report ofIndependent Investigation into the production and distribution of non-conforming cement by CCCL.

    Ministry of Commerce, Science and Technology. June 2, 2006.

    11 Stoltenberg-Hanson, E. (Norcem Cement); Fly ash cement:Production methods, materials properties and

    energy savings; Norway, 1986 in Portland Cement Association: www.cement.org

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    21/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 21

    As per regulatory norms cement cannot be manufactured, stored or sold in Jamaica without it being

    tested and certified by BSJ, Carib Plus too had to be manufactured under strict quality control and meetinternational standards. Although of this quality assurance of product alone could not overcome the

    market acceptability barrier.

    Challenges Faced

    There were several challenges that were faced in the introduction of this product to the market. These

    were identified and actions put in place to minimize the effects, as described in the table below:

    Challenge Mitigating Action

    Product not well known. Market was not

    familiar with blended cements. Further, there is

    a wrong impression in the market that higher

    addition on blended material degrades the

    properties of the cement.

    Extensive education programme which

    consisted of seminars and product advertising

    Lower early strengths, which was not

    acceptable for market segments such as the

    blockmaking sector.

    Technical assistance provided to blockmakers

    to maximize efficiency of operations and to

    show them how Carib Plus could work for

    them

    Lower price could be construed as representing

    a lower quality product.

    Extensive awareness programmes and constant

    dialogue to show that the product was not

    inferior. Also, product was manufactured to

    mimic the characteristics of Carib OPC as

    close as possible so that minimum differenceswould be detected by the market.

    Lighter colour of cement which represents a

    weaker cement in the eyes of the Jamaican

    public.

    Awareness programme implemented through

    seminars to communicate that the colour of

    cement has no impact on strength.

    Introducing a product that was in fact not

    similar to a product that the market had been

    requesting that of a rapid hardening cement.

    Technical consultation with those players who

    wanted a rapid hardening product to show that

    Carib Plus could achieve desired early

    strengths with better practice (better curing, use

    of additives, better mix design, etc.)

    The masons and builders require special training and guidance in order to use Carib Plus as building

    materials. The training and guidance include measures to be adopted to ensure equal durability andworkability of OPC and Carib Plus.

    The reduction in greenhouse gas emissions in the production of blended cement was highlighted as a

    benefit to potential users.

    Launch of Carib Cement Plus

    The strategy of the launch ofCarib Plus, the pozzolan Portland cement, in an effort to maximize the

    acceptance in the marketplace was to promote it as a product that had characteristics similar to that of

    Carib Cement OPC, but with additional properties. These characteristics are:

    1. Greater suitability for use in marine environments;

    2. Lower heat of hydration thus better suited for large pours;

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    22/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 22

    3. Higher sulphate resistance;

    4. Higher later strengths;5. A more environmentally friendly product;

    6. More economically priced than ordinary Portland cement (OPC) as the company was passingon some of the savings realized in the production process to the consumers.

    CCCL took up extensive marketing, promotional activities and has dedicated its good manpower in

    order to promote Carib Plus with higher additive percent in the consumer market launching a multi

    fold activity. The launch was implemented in 2 phases as follows:

    Stage 1 of Launch

    The Carib Plus produced during the tests in 2004 was introduced to the market in the form of bulk

    cement that was offered to ready mix operators. The acceptance by this segment of the market was a

    slow one due to the segment comprising the more sophisticated Jamaican cement users who wereconcerned about the quality of a product with which they were not familiar. However, the cement was

    found by them to be satisfactory in their applications and in conjunction with educational seminars

    that were held by CCCL this market segment was able to adjust its processes to utilize this more

    economical product.

    Stage 2 of Launch

    The second stage of the introduction of the product to the market was the launch of Carib Plus

    (pozzolan Portland cement) in 42.5 Kg bags and 1.5 tonne jumbo bags. This was a more challenging

    phase as Carib Plus was replacing a product that had been tried, tested and proven in the Jamaican

    market for over 50 years. However, a key introductory strategy was to ensure that Carib Plus did not

    totally replace the OPC, so that consumers still had a choice in the product they bought.

    The introductory price of the product in bags was also slightly below that of OPC and the rationale

    for this was that CCCL was passing on some of the savings in the production that were realized from

    a more efficient manufacturing process.

    These market acceptability, customer resistance and first of its kind barriers due to current prevailing

    practice in Jamaica, would have led to not implement the project activity, with CCCL continuing to

    produce only the Ordinary Portland Cement.

    Barrier 4 (Technological)

    The production of the blended cement resulted in very high material wear of (a) the separator parts suchas the auxiliary blades and hopper distribution table, and (b) the elevators

    Effort had to be expended in doing regular patching on the elevators using salvaged auxiliary blades

    (made of a hardwearing alloy) to prolong useful life, as well as on doing frequent changeovers of

    auxiliary blades and hopper distribution table.

    Alternative high abrasion materials had to be sourced and this was obtained from WEAR CONCEPTS

    (Wearcon), imported from USA, Missouri. Previously, CCCL had to changeover the auxiliary blades and

    hopper distribution table used in the making of the pozzolan cement about every 6 to 8 weeks. After the

    change to the Wearcon materials, higher wear resistance of the mill and separator was obtained,

    decreasing dramatically the need for frequent changeovers. With the Wearcon materials, changes in

    hopper distribution table were required every 12 months on average and changes in the auxiliary blades

    were required about every 4 to 5 months a significant improvement from the previous situation.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    23/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 23

    Table 6 - Downtime before and after installation of high abrasion materialInstallation completed in February 2007. (Data extracted from Pareto Charts available on-site)

    Month/Year Downtime duration, hrs Frequency

    December/2006 21.95 4

    January/2007 17.8 5

    February/2007 7.3 3

    March/2007 - -

    April/2007 - -

    Barrier 5 (Operational)

    As new raw material and final product were included: (i) adaptations in the process needed to be

    implemented and (ii) more stringent quality assurance and quality control procedures needed to bedeveloped and implemented.

    To be able to successfully commence routine production of blended cement, the company had to

    conduct initial trial production runs and internal checks on the batches of pozzolan cement produced. For

    these initial trial runs, one of the cement silos had to serve as a dedicated Carib Plus cement silo, and

    hence could not be used for storage of the OPC. The unavailability of this silo required careful planning

    for storage of the OPC and vigilance in ensuring the right silo(s) was selected for packing or loading.

    Process changes were required in the cement mill no. 4 so as to properly balance the mill circuit. For

    example, the correct settings for airflow and for the separator had to be determined for the production of

    the Carib Plus.

    Limestone and pozzolan bin are side by side. Natural pozzolan stockpile must be controlled carefully to

    not mix with the limestone stockpile. In the beginning of the Carib Plus production, pozzolancontamination occurs in the limestone, causing equipment failure and cement quality problems. Also

    greater vigilance is needed to ensure correct material is transported.

    For the production and dispatching of the Carib Plus, the existing silos have to be shared between

    storage ofCarib Plus and OPC. Thus, there is some loss in flexibility in which silos can be assigned for

    OPC storage and dispatch.

    Barrier 6 (Lack of Additive)

    There is no thermal plant in Jamaica operating with coal to supply fly ash to CCCL, all of them operates

    with liquid or gas fuel12

    . Blast furnace slag is also unavailable in a quantity to supply CCCL needs.

    Initially the pozzolan was imported via ships and this presented many logistical challenges including

    maintenance of adequate inventory. Subsequently, reserves of pozzolanic material were discovered at theCCCL Bull Bay quarry, and after extensive effort in proving the pozzolan reserves, these reserves were

    deemed to be of adequate quality, and so the importation ceased.

    Outcome of Step 3:

    All barriers listed above are processes that CCCL would not need to overcome if there is no purpose in

    launching a new product, the Carib Plus cement, using a new additive, the pozzolan.

    12 Jamaica Public Service Company. Website: http://www.jpsco.com, accessed in 27 June 2007

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    24/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 24

    The barrier analysis shows that:

    (i) Alternative 3 and 1 are strongly prevented by identified barriers and for this reason are veryunlikely scenarios. These alternatives are eliminated from further consideration.

    (ii) Alternatives 2 is not prevented by the barriers, remaining as the most plausible baselinescenario.

    Step 4. Common practice analysis

    Sub-step 4a. Analyze other activities similar to the proposed project activity:

    CCCL is the sole cement manufacture in Jamaica, and is the largest supplier of the market. All other

    cement sellers in Jamaica import from other countries. Other cement companies in the Caribbean Regionbesides TCL group companies, are multinational large companies as CEMEX, Holcim, Lafarge, and

    could not be compared as similar activities because they do not have comparable investment climate,

    access to technology, access to financing, etc.

    Therefore, the CCCL project activity is not a common practice in the region.

    Sub-step 4b. Discuss any similar options that are occurring:

    Not applicable, because there is no similar project activities in Jamaica neither in Caribbean region.

    B.6. Emission reductions:

    B.6.1. Explanation of methodological choices:

    >>

    Step 1 Emission Reductions

    Emissions reductions in year y of the project activity are calculated from equation 4, described below.

    yyyyBCyBCy LBCPEBEER += 11000,, tCO2 (4)

    ERy Emissions reductions in year y due to project activity 1000 tonnes/CO2

    BEBC,y Baseline emissions of CO2 per tonne of BC in year y of the projectactivity. Calculated from equation (1).

    tCO2/t(BC)

    PEBC,y Project emissions of CO2 per tonne of BC in year y of the projectactivity. Calculated from equation (5).

    tCO2/t(BC)

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    25/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 25

    BCy Production of blended cement in year y of the project activity.

    Monitored by project proponents.

    1000tonnes (BC)

    Ly Leakage due to transport of additives. Calculated from equation(2.1).

    tCO2

    y Proportion of additives that are not surplus. Calculated fromequation (3).

    Non-dimensional

    Step 2 Baseline emissions

    Baseline emissions per tonne of blended cement produced are calculated from equation 1, described

    below:

    BCADDeleyBlendclinyBC BEBBEBE __,ker, += tCO2/t(BC) (1)

    BEBC,y Baseline emissions per tonne of blended cement type. tCO2/t(BC)

    BEclinker Baseline emissions per tonne of clinker in the project activity

    plant. Calculated from equation (1.1).

    tCO2/t(clinker)

    BBlend,y Baseline benchmark of share of clinker per tonne of BC updated

    for year y. Defined from Benchmark Analysis.

    t(clinker)/t(BC)

    BEele_ADD_BC

    Baseline electricity emissions for BC grinding and preparation of

    additives. Calculated from equation (1.2).

    tCO2/t(BC)

    Equations (1.1), (1.1.1), (1.1.2), (1.1.3) and (1.1.4)

    CLNKsgeleCLNKgridelefuelfossilcalcinclin BEBEBEBEBE _____ker +++= tCO2/t(clinker) (1.1)

    BEcalcin Baseline emissions per tonne of clinker due to calcinations of calcium

    carbonate and magnesium carbonate. Calculated from equation (1.1.1)

    below:

    tCO2/t(clinker

    )

    ( ) ( )

    BSL

    calcinCLNK

    InMgOOutMgOInCaOOutCaOBE

    += 1000

    092.1785.0tCO2/t(clinker) (1.1.1)

    BEfossil_fuel Baseline emissions per tonne of clinker due to combustion of fossil fuels

    for clinker production. Calculated from equation (1.1.2) below:

    tCO2/t(clinker

    )

    ( )

    BSL

    iBSLi

    fuelfossilCLNK

    EFFFFBE

    =

    1000

    _

    _ tCO2/t(clinker) (1.1.2)

    BEele_grid_CLNK Baseline grid electricity emissions for clinker production per tonne of

    clinker. Calculated from equation (1.1.3) below:

    tCO2/t(clinker

    )

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    26/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 26

    BSL

    BSLgridCLNKgrid

    CLNKgrideleCLNK

    EFBELE

    BE

    = 1000

    __

    __ tCO2/t(clinker) (1.1.3)

    BEele_sg_CLNK Baseline emissions from self generated electricity for clinker production

    per tonne of clinker. Calculated from equation (1.1.4) below:

    tCO2/t(clinker

    )

    BSL

    BSLsgCLNKsg

    CLNKsgeleCLNK

    EFBELEBE

    =

    1000

    __

    __ tCO2/t(clinker) (1.1.4)

    Equations (1.2), (1.2.1), (1.2.2), (1.2.3) and (1.2.4)

    ADDsgeleADDgrideleBCsgeleBCgrideleBCADDele BEBEBEBEBE __________ +++= tCO2/t(BC) (1.2)

    BEele_grid_BC Baseline grid electricity emissions for grinding BC. Calculated from

    equation (1.2.1) below:

    tCO2/t(BC)

    BSL

    BSLgridBCgrid

    BCgrideleBC

    EFBELEBE

    =

    1000

    __

    __ tCO2/t(BC) (1.2.1)

    BEele_sg_BC Baseline self generated electricity emissions for grinding BC. Calculated

    from equation (1.2.2) below:

    tCO2/t(BC)

    BSL

    BSLsgBCsg

    BCsgeleBC

    EFBELEBE

    =

    1000

    __

    __ tCO2/t(BC) (1.2.2)

    BEele_grid_ADD Baseline grid electricity emissions for preparation of additives. Calculated

    from equation (1.2.3) below:

    tCO2/t(BC)

    BSL

    BSLgridADDgrid

    ADDgrideleBC

    EFBELEBE

    =

    1000

    __

    __ tCO2/t(BC) (1.2.3)

    BEele_sg_ADD Baseline self generated electricity emissions for preparation of additives.

    Calculated from equation (1.2.4) below:

    tCO2/t(BC)

    BSL

    BSLsgADDsg

    ADDsgeleBC

    EFBELEBE

    =

    1000

    __

    __ tCO2/t(BC) (1.2.4)

    Definition of BEclinker:

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    27/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 27

    BEclinker is primarily defined from equation (1.1). However, considering that ACM0005 is restricted to

    increase in percentage of blend only and not to efficiency improvements or fuel switching, themethodology states that in each year of the crediting period BEclinker needs to verified and redefined as

    described below:

    If project emissions per tonne of clinker are less than baseline emissions in year y of the crediting

    period: PEclinker,y < BEclinker, BEclinkershall be substituted by the PEclinker,y in year y.

    If project emissions per tonne of clinker are equal to baseline emissions in year y of the crediting

    period: PEclinker,y = BEclinker, BEclinkershall be maintained as calculated by equation (1.1).

    If project emissions per tonne of clinker are greater than baseline emissions in year y of the crediting

    period: PEclinker,y > BEclinker, BEclinker shall be maintained as calculated by equation (1.1). In this case,

    there is a possibility that project activity emissions exceed the baseline emissions and the project does

    not get new credits for emissions reduction till the net balance for the project is positive.

    PEclinker,y is calculated from equation (5.1).

    Step 3 Project Activity Emissions

    Project activity emissions per tonne of blended cement produced are calculated from equation 5,

    described below:

    yBCADDeleyblendyclinyBC PEPPEPE ,__,ker,, += tCO2/t(BC) (5)

    PEBC,y Project emissions per tonne of blended cement type, in year y of

    the crediting period.

    tCO2/t(BC)

    PEclinker,y Project emissions per tonne of clinker, in year y of the crediting

    period. Calculated from equation (5.1) in the following pages.

    tCO2/t(clinker)

    PBlend,y Project share of clinker per tonne of BC in year y. Monitored by

    project proponents, during the crediting period, in the project site.

    t(clinker)/t(BC)

    y

    y

    yblendBC

    CLNKP =, tCO2/t(clinker)

    PEele_ADD_BC,y Project electricity emissions for BC grinding and preparation of

    additives, in year y of the crediting period. Calculated from

    equation (5.2) in the following pages.

    tCO2/t(BC)

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    28/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 28

    Equations (5.1), (5.1.1), (5.1.2), (5.1.3) and (5.1.4)

    yCLNKsgeleyCLNKgrideleyfuelfossilycalcinyclin PEPEPEPEPE ,__,__,_,ker, +++= tCO2/t(clinker) (5.1)

    PEcalcin,y Project emissions per tonne of clinker due to calcination of calcium

    carbonate and magnesium carbonate. Calculated from equation (5.1.1)

    below:

    tCO2/t(clinker

    )

    y

    yyyy

    ycalcinCLNK

    InMgOOutMgOInCaOOutCaOPE

    +=

    1000

    092.1785.0, tCO2/t(clinker)

    (5.1.1)

    PEfossil_fuel,y Project emissions per tonne of clinker due to combustion of fossil fuelsfor clinker production. Calculated from equation (5.1.2) below: tCO2/t(clinker)

    ( )

    y

    iyi

    yfuelfossilCLNK

    EFFFFPE

    =

    1000

    _

    ,_ tCO2/t(clinker) (5.1.2)

    PEele_grid_CLNK,y Project emissions from grid electricity for clinker production per tonne

    of clinker. Calculated from equation (5.1.3) below:

    tCO2/t(clinker

    )

    y

    ygridyCLNKgrid

    yCLNKgridele

    CLNK

    EFPELEPE

    =

    1000

    _,_

    ,__ tCO2/t(clinker) (5.1.3)

    PEele_sg_CLNK,y Project emissions from self generated electricity for clinker production

    per tonne of clinker. Calculated from equation (5.1.4) below:

    tCO2/t(clinker

    )

    y

    ysgyCLNKsg

    yCLNKsgeleCLNK

    EFPELEPE

    =

    1000

    _,_

    ,__ tCO2/t(clinker) (5.1.4)

    Equations (5.2), (5.2.1), (5.2.2), (5.2.3) and (5.2.4)

    yADDsgeleyADDgrideleyBCsgeleyBCgrideleyBCADDele PEPEPEPEPE ,__,__,__,__,__ +++= tCO2/t(BC)

    (5.2)

    PEele_grid_BC,y Project grid electricity emissions for BC grinding. Calculated from

    equation (5.2.1) below:

    tCO2/t(BC)

    y

    ygridyBCgrid

    yBCgrideleBC

    EFPELEPE

    _,_

    ,__

    = tCO2/t(BC) (5.2.1)

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    29/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 29

    PEele_sg_BC,y Project self generated electricity emissions for BC grinding. Calculated

    from equation (5.2.2) below:

    tCO2/t(BC)

    y

    ysgyBCsg

    yBCsgeleBC

    EFPELEPE

    _,_

    ,__

    = tCO2/t(BC) (5.2.2)

    PEele_grid_ADD,y Project grid electricity emissions for additive preparation. Calculated from

    equation (5.2.3) below:

    tCO2/t(BC)

    y

    ygridyADDgrid

    yADDgrideleBC

    EFPELEPE

    _,_

    ,__

    = tCO2/t(BC) (5.2.3)

    PEele_sg_ADD,y Project self generated electricity emissions for additive preparation.

    Calculated from equation (5.2.4) below:

    tCO2/t(BC)

    y

    ysgyADDsg

    yADDsgeleBC

    EFPELEPE

    _,_

    ,__

    = tCO2/t(BC) (5.2.4)

    According to ACM0005, version 3, if additional additives used in the project activity needs drying, fuel

    combustion used in the drying process shall be accounted as an emission source. Therefore, emissions

    resulting for drying additional additives are accounted as project emissions.

    Step 4 Leakage

    Leakage 1: Emissions due to fuel use for the transport of raw materials and fuels from offsite locations to

    the project plant are likely to decrease due to the implementation of the project. Following ACM0005, in

    order to keep emissions reductions conservative, this change is not included.

    Leakage 2: Emissions due to fuel use for the transport of additives from offsite locations to the project

    plant are likely to increase. These emissions are accounted as leakage, as per equations (2.1) and (2)

    below:

    Equations (2.1) and (2)

    yyblendyblendtransaddy BCPALL = ,,_ tCO2 (2.1)

    y

    gridADDconveyor

    add

    sourceaddcons

    transaddADD

    EFELE

    Q

    TEFDTFL

    +

    =

    __

    _1000

    tCO2/t(additive) (2)

    Ly Leakage emissions for transport of additives. tCO2

    Ablend,y Baseline benchmark share of additives per tonne of BC updated for t(slag)/t)BC)

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    30/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 30

    year y.

    Pblend,y Share of additives per tonne of BC updated for year y.*

    t(additive)/t(BC

    )

    Ladd_trans Transport related emissions per tonne of additives. Calculated from

    equation (2).

    tCO2/t(additive)

    TFcons Fuel consumption for the vehicle per kilometre. Monitored by project

    proponents, in year y of the crediting period, in the project site.

    kg(fuel)/km

    Dadd_source Distance between the source of additive and the project activity plant.

    Monitored by project proponents, in year y of the crediting period, in

    the project site.

    km

    ELEconveyor_ADD Annual electricity consumption for conveyor system for additives.Monitored by project proponents, in year y of the crediting period, in

    the project site.

    MWh

    Qadd Quantity of additive carried in one trip per vehicle. Monitored by

    project proponents, in year y of the crediting period, in the project

    site.

    t(slag)

    TEF Emission factor for transport fuel. Calculated from equation (7). tCO2/t(fuel)

    EFgrid Grid electricity emission factor. Calculated according to methodology

    ACM0002.

    tCO2/MWh

    - Note: The revised methodology ACM0005-Version 2 redefines Pblend,y from share of clinker per tonneof BC to share of additives per tonne of BC. This is maintained in ACM0005-Version3. Notwithstanding,

    this new definition can be used only for leakage calculation, see ACM0005-Page 7-Equation 2.1. For

    project emissions calculations, the old definition needs to be maintained, see ACM0005-Version 3-

    Equation 5.

    Leakage 3: The methodology defines that another possible leakage is due to the diversion of additives

    from existing uses. As the slag used is surplus, it is expected that this source of leakage will not affect

    calculations. Notwithstanding, y is calculated from equation (3) below:

    yyearinusedadditivesadditionaltotal

    surplusnotyyearinadditivesoftonnesxy = (3)

    Only domestically sold output is considered and any export of cement produced by the project activity is

    excluded in the calculation of emission reductions. Actually, part of the Carib Plus cement is exported.

    Step 5 Fuel and electricity emission factors

    For the calculation of emissions from grid electricity (EFgrid) the approved methodology tool Tool to

    calculate the emission factor for an electricity system ver.01 is applied.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    31/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 31

    There is no self-generated electricity.

    Electricity Emission Factor for grid electricity

    According to the tool, the grid CO2 emission is is calculated as a combined margin ( CM), consisting of

    the combination of operating margin (OM) and build margin (BM) factors.

    To determine the grid emission factor, according to the tool, should apply the following six steps:

    STEP 1. Identify the relevant electric power system.

    STEP 2. Select an operating margin (OM) method.

    STEP 3. Calculate the operating margin emission factor according to the selected method.

    STEP 4. Identify the cohort of power units to be included in the build margin (BM).STEP 5. Calculate the build margin emission factor.

    STEP 6. Calculate the combined margin (CM) emissions factor.

    Step 1. Identify the relevant electric power system

    The tools states that:

    For the purpose of determining the electricity emission factors, a project electricity system is

    defined by the spatial extent of the power plants that are physically connected through

    transmission and distribution lines to the project activity (e.g. the renewable power plant location

    or the consumers where electricity is being saved) and that can be dispatched without significant

    transmission constraints

    Similarly, a connected electricity system, e.g. national or international, is defined as an

    electricity system that is connected by transmission lines to the project electricity system. Power

    plants within the connected electricity system can be dispatched without significant transmission

    constraints but transmission to the project electricity system has significant transmission

    constraint.

    If the DNA of the host country has published a delineation of the project electricity system and

    connected electricity systems, these delineations should be used. If such delineations are not

    available, project participants should define the project electricity system and any connected

    electricity system and justify and document their assumptions in the CDM-PDD.

    The Jamaican DNA has not defined nor publicized a delineation of the system. The spatial extent for the

    CCCL project activity is defined as the national grid.

    CCCL purchases electricity from the Jamaica Public Service Company (JPSCo) that is involved with

    the generation, purchase and distribution of electricity in whole Jamaica.

    As the electric system is the national grid, and there are no subsystem, there are no electricity imports

    nor exports between subsystems. Moreover, as Jamaica is an island country, there will be no

    imports/exports between countries to be considered.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    32/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 32

    Grid Emission factor (EFgrid) is calculated as a combined margin (EFgrid,CM,y), consisting of the

    combination of operating margin (EFgrid,OM,y) and build margin (EFgrid,BM,y) factors according to thefollowing three steps.

    Power plant capacity additions registered as CDM project activities should be excluded from all

    calculations.

    Step 2. Select an operating margin (OM) method

    The calculation of the operating margin emission factor (EFgrid,OM,y

    ) is based on one of the following

    methods:

    (a) Simple OM, or

    (b) Simple adjusted OM, or(c) Dispatch data analysis OM, or

    (d) Average OM.

    Any of the four methods can be used, however, the simple OM method (option a) can only be used if low-

    cost/must-run13

    resources

    constitute less than 50% of total grid generation in: 1) average of the five most

    recent years, or 2) based on long-term averages for hydroelectricity production.

    For the proposed project activity, option (a), simple OM, has been chosen. Historically Jamaica electricity

    is generated from fossil fuel, mainly natural gas and diesel oil. In 2005 more than 95% of Jamaican

    generation was based on fossil fuels, demonstrating that this option could be used, see also the data

    provided in Annex 3.

    Ex-ante data vintage option is chosen. A 3-year generation-weighted average, based on the most recentdata available at the time of submission of the CDM-PDD to the DOE for validation.

    Step 3. Calculate the operating margin emission factor according to the selected method

    (a) Simple OMThe simple OM emission factor is calculated as the generation-weighted average CO

    2emissions per unit

    net electricity generation (tCO2/MWh) of all generating power plants serving the system, not including

    low-cost / must-run power plants / units. It may be calculated:

    Based on data on fuel consumption and net electricity generation of each power plant / unit

    (Option

    A), or

    Based on data on net electricity generation, the average efficiency of each power unit and the fuel

    type(s) used in each power unit (Option B), or

    Based on data on the total net electricity generation of all power plants serving the system and the

    fuel types and total fuel consumption of the project electricity system (option C)

    Option A should be preferred and must be used if fuel consumption data is available for each power

    plant / unit. In other cases, option B or option C can be used. For the purpose of calculating the

    13 Low-cost/must-run resources are defined as power plants with low marginal generation costs or power plants that

    are dispatched independently of the daily or seasonal load of the grid. They typically include hydro, geothermal,

    wind, low-cost biomass, nuclear and solar generation. If coal is obviously used as must-run, it should also be

    included in this list, i.e. excluded from the set of plants.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    33/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 33

    simple OM, Option C should only be used if the necessary data for option A and option B is not

    available and can only be used if only nuclear and renewable power generation are considered as low-cost / must-run power sources and if the quantity of electricity supplied to the grid by these sources is

    known.

    For the CCCL project, Option B2 will be used, as there is no data on fuel consumption for each

    power plant.

    Where:

    EFgrid,OMsimple,y Simple operating margin CO2 emission factor in year y (tCO2/MWh)EG

    m,yNet quantity of electricity generated and delivered to the grid by power unit m in

    year y (MWh)

    EFEL,m,y

    CO2emission factor of power unit m in year y (tCO

    2/MWh)

    m All power units serving the grid in year y except low-cost / must-run power units

    y Either the three most recent years for which data is available at the time of

    submission of the CDM-PDD to the DOE for validation (ex ante option) or the

    applicable year during monitoring (ex post option), following the guidance on data

    vintage in step 2

    Option B2. If for a power unit m only data on electricity generation and the fuel types used isavailable, the emission factor should be determined based on the CO

    2emission factor of the fuel

    type used and the efficiency of the power unit, as follows:

    Where:

    EFEL,m,y

    CO2emission factor of power unit m in year y (tCO

    2/MWh)

    EFCO2,m,i,y

    Average CO2emission factor of fuel type i used in power unit m in year y (tCO

    2/GJ)

    m,y Average net energy conversion efficiency of power unit m in year y (%)y Either the three most recent years for which data is available at the time of submission of

    the CDM-PDD to the DOE for validation (ex ante option) or the applicable year during

    monitoring (ex post option), following the guidance on data vintage in step 2

    The data and details of the calculations are provided in Annex 3.

    Step 4. Identify the cohort of power units to be included in the build margin

    The sample group of power units m used to calculate the build margin consists of either:

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    34/73

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    35/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 35

    Step 6. Calculate the combined margin emissions factorThis has been calculated as the weighted average of the emissions factor of the OM and the BM. The

    formula that has been used to calculate this weighted average emission factor is as follows:

    BMyBMgridOMyOMgridyCMgrid wEFwEFEF += ,,,,,, Equation 6

    Where:

    EFgrid,BM,y

    Build margin CO2emission factor in year y (tCO

    2/MWh)

    EFgrid,OM,y

    Operating margin CO2emission factor in year y (tCO

    2/MWh)

    wOM

    Weighting of operating margin emissions factor (%)

    wBM

    Weighting of build margin emissions factor (%)

    The emissions factors of the OM and BM in Jamaica have been weighed equally, each 50% as per the

    tools as the project activity is not a wind or solar source power.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    36/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 36

    B.6.2. Data and parameters that are available at validation:

    Parameters related to the self-generated electricity is not included because there is no self-generation. All

    electricity need is supplied by the grid.

    BEcalcin (emissions from calcinations of limestone)

    Data / Parameter: InCaOBSL

    Data unit: %

    Description: CaO content of the raw material in baseline year

    Source of data used: Plant records

    Value applied: Year 2004: 42.32Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Calculated from measured data as part of normal operations.

    One year before project start

    Any comment: None

    ata / Parameter: OutCaOBSL

    Data unit: %

    Description: CaO content of the in baseline year

    Source of data used: Plant records

    Value applied: 65.10

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Calculated from measured data as part of normal operations.

    One year before project start.

    Any comment: None

    Data / Parameter: InMgOBSL

    Data unit: %

    Description: MgO content of the raw in baseline year

    Source of data used: Plant records

    Value applied: 0.71

    Justification of the

    choice of data or

    description of

    Calculated from measured data as part of normal operations.

    One year before project start.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    37/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 37

    measurement methods

    and procedures actuallyapplied :

    Any comment: None

    Data / Parameter: OutMgOBSL

    Data unit: %

    Description: MgO content of the clinker in baseline year

    Source of data used: 1.09

    Value applied: Plant records

    Justification of the

    choice of data ordescription of

    measurement methods

    and procedures actually

    applied :

    Calculated from measured data as part of normal operations.

    One year before project start.

    Any comment: None

    Data / Parameter: Quantity of clinker raw material in the baseline

    Data unit: Kilo tonnes

    Description: Quantity of raw material used in the production of clinker.

    Source of data used: Plant records

    Value applied: 999.402

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Calculated from measured data as part of normal operations.

    One year before project start (2004).

    Any comment: None

    Data / Parameter: CLNKBSLData unit: Kilo tonnes

    Description: Annual production of clinker in the baseline scenario

    Source of data used: Plant records

    Value applied: Year 2002: 532

    Year 2003: 601

    Year 2004: 606

    Justification of the

    choice of data or

    description of

    Measured as part of normal operations.

    Monitored 3 years before project start

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    38/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 38

    measurement methods

    and procedures actuallyapplied :

    Any comment: None

    Data / Parameter: BCBSL

    Data unit: Kilo tonnes

    Description: Annual production of blended cement in the baseline years

    Source of data used: Plant records

    Value applied: 2002: 614

    2003: 601

    2004: 808Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Monitored by project proponents, for three years previously to project

    implementation.

    Any comment: The production presented here is for the ordinary Portland cement, as there were

    no blended cement productions before the project activity.

    - Note: The above parameter BCBSL is not included in the monitoring plan in ACM0005 ver03,

    however it is necessary to include as is used to calculate baseline emissions. Refer to equations 1.2.1 o

    1.2.4, page 6 of the methodology.

    - Note: The revised methodology ACM0005-Version 2 requires that Bblend,y (ID#29) is replaced by

    Ablend,y (ID#29) in table for Data to monitor emissions from the project activity. This is maintained in

    ACM0005-Version 3. However, Bblend,y cannot be eliminated from monitoring because this parameter is

    necessary for baseline emissions calculations, see ACM0005-Version 3-Page 5-Equation 1.

    BEfossil_fuel (emissions due to combustion of fossil fuels for clinker production)

    Data / Parameter: FF1_BSL

    Data unit: .tonnes

    Description: Consumption of fossil fuel, Bunker C, for clinker production in the baseline.

    Source of data used: Plant records

    Value applied: 17,334

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Measured as part of normal operations.

    The overall consumption in the year before project activity is taken.

  • 7/28/2019 Caribbean Cement_pdd 2007 12 21

    39/73

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 39

    Any comment: None

    Data / Parameter: FF2_BSL

    Data unit: .tonnes

    Description: Consumption of fossil fuel, Coal, for clinker production in the baseline.

    Source of data used: Plant records

    Value applied: 90,860

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actuallyapplied :

    Measured as part of normal operations.

    The overall consumption in the year before project activity is taken.

    Any comment: None

    Data / Parameter: EFF1

    Data unit: tCO2/tonne of fuel

    Description: Emission Factor of the fossil fuel, Bunker C, used for clinker production

    Source of data used: IPCC 2006

    Value applied: 3.14

    Justification of thechoice of d