caribbean cement_pdd 2007 12 21
TRANSCRIPT
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
1/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 1
CLEAN DEVELOPMENT MECHANISM
PROJECT DESIGN DOCUMENT FORM (CDM-PDD)Version 03 - in effect as of: 28 July 2006
CONTENTS
A. General description of project activity
B. Application of a baseline and monitoring methodology
C. Duration of the project activity / crediting period
D. Environmental impacts
E. Stakeholders comments
Annexes
Annex 1: Contact information on participants in the project activity
Annex 2: Information regarding public funding
Annex 3: Baseline information
Annex 4: Monitoring plan
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
2/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 2
SECTION A. General description of project activity
A.1 Title of the project activity:
Title: Blend increasing in the cement production of Caribbean Cement Company Ltd.
Version number of the document: 01
Date of the document: 19/December/2007
A.2. Description of the project activity:
Project Activity
Caribbean Cement Company Ltd (hereinafter referred as CCCL) (Figure 1) is the sole manufacturer of
cement in Jamaica, operating a dual process cement manufacturing plant, utilizing both the wet and dry
process technologies to produce the Ordinary Portland Cement (OPC).
Concerned about the sustainable development of the country, CCCL has embarked in an Expansion and
Modernization Programme, to expand the production capacity to meet market demand increase (domestic
market is conservatively forecast to grow by approximately 4% per annum), and in the same time, reduce
environmental impact, improving gaseous emissions control, implementing more energy efficient
technologies to reduce electricity and fossil fuel consumption, bringing the plant in line with the best
industry technologies and standards.
The purpose of the project activity involves the use of pozzolan, an alternative raw material, as
substitute of clinker. Pozzolan is derived from material present in volcanic ash and is indigenous to the
region where the plant is located, because of the presence of active volcanoes in some of the neighbouring
islands. Pozzolan was found in a footprint of the existing gypsum quarry, so will not result in new area
degradation.
The company now supplies a local market in the region of 1 million tonnes of cement. In February
2005, the company initiated a
conversion of the local market from a
predominantly OPC - Type 1, to a
blended cement - Type 1P market. The
average clinker content in cement has
reduced by approximately 15%. Thisresults in a reduction in the specific
energy and power consumptions to
produce cement. It also results in a
proportional reduction in the emission
of carbon dioxide, which is produced in
the production of clinker.
Greenhouse gases emissions are
reduced as a result of the decrease on
emissions during the calcinations of
limestone and due to the reduction of Fi ure 1 Caribbean Cement Com an Ltd. Plant
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
3/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 3
fossil fuels consumption in the kiln.
The manufacture of blended cements with high contents of pozzolan and relatively high strengths maycause difficult problems, which may increase when the grindability of the components is very different
and the moisture content of the pozzolan is high.1.
Initially, several search and development were done to assure the blended cement quality, inclusive
working together to the Bureau Jamaica Standard, to develop the technical standard for the pozzolan
blended cement as this is the first time blended cement is produced in Jamaica. Although new to Jamaica,
the Pozzolan process is currently used by many cement manufacturers worldwide, particularly those in
Europe. Due to poor awareness levels on use and preparation of Carib Plus for building and other benefits,
the product acceptability levels of Carib Plus with higher additive % were very low in the beginning.
In 2010 is planned the substitution of Kiln #3 that operates in wet process by a new Kiln #5 that will
operates in dry process, which is more efficient. Cement Mill #4 will be upgraded and Cement Mill #3
will be replaced by Mill #5. Although theses substitutions will result in energy saving in the clinker andcement process, CO2 emission reductions resulting from these savings will not be claimed in this project
activity, as stated by methodology ACM0005.
Cement Production Process
Cement is made by heating limestone with small quantities of other materials, such as clay, to 1,450C
in a kiln. The resulting hard substance, called clinker, is then ground into a powder, in cement mills, with
a small amount of gypsum to make the Ordinary Portland Cement (OPC), the first produced type of
cement. Other materials can be used in substitution of clinker in the grinding phase of the fabrication,
producing the so-called blended cement. Pozzolan is one of these alternative materials, resulting in the
production of the Blended Type 1 Cement, known as Carib Cement Plus.
Pozzolan will be used in the project activity as clinker substitute. It is used in the grinding phase of
cement production chain, i.e. pozzolan replaces clinker in the cement mills avoiding, then, clinkerproduction in the kilns.
It is important to highlight that the cement industry plays a significant role in Climate Change2. First
because the cement manufacture is an energy intensive process, demanding large amounts of fuel and
electricity in the whole process chain. In addition, the chemical process of producing clinker (calcination
of limestone) produces non-renewable CO2. These two factors results in that the cement industry is
responsible for a significant portion of global man-made CO2 emissions. It is estimated that 50% of the
cement industry GHG emissions derive from the chemical process, and 40% from burning fuel. The
remainder is split between electricity and transport uses.
Company History
CCCL was incorporated in 1947, and the first bag of cement was delivered in 1952. The company has
transitioned from private ownership in the 1950s, to the state acquiring controlling interest in the 1970s,to Scancem and later to Cemex operating the plant under management contracts in the 1990s, and finally,
to the divestment of the Governments interest to Trinidad Cement Limited in 1999.
CCCL is the sole manufacturer of cement in Jamaica and was the sole supplier until as recently as 1999.
The size of the cement market has grown substantially over the last 10 years: demand has increased by
1 Baragano Coronas, J. R.; Rey y Vazquez de la Torre, P.; Difficulties in the manufacture of cements with grinding
additives; Spain, 1986 in Portland Cement Association: www.cement.org
2World Business Council for Sustainability Development. Cement Sustainability Initiative Progress Report. June
2005.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
4/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 4
52% or 5.1% per annum. The domestic market is conservatively forecast to grow by approximately 4%
per annum from 862,289 tonnes in 2004 to 1,291,167 tonnes in 2010.CCCL presently holds the dominant share of the domestic market and is developing and implementing
strategies to meet this increasing demand and to provide even better service to the construction industry.
The modernization and expansion of the existing plant is necessary in order to meet the growing demand
for cement in Jamaica as well as the need to reduce fuel consumption, improve production efficiencies
and environmental performance.
Concurrent with the developments in Jamaica and the wider business world, the company has gone
through several changes. In addition to the changes in ownership and leadership, the company has had
three major plant expansions to meet increasing consumption.
The company has embarked on an Expansion and Modernization Programme, which involves the
retiring of obsolete technology and expensive operating units. Caribbean Cement Company Ltd. willinstall and commission new plants to increase capacity, continue to meet market demand, reduce
operating costs and improve environmental performance.
The project activity contributes to sustainable development in the following manners:
- The project activity helps mitigating Climate Change because of the significant reductions ofdirect and indirect greenhouse gases emissions.
- Project activity contributes to the reduction of energy consumption in the cement manufacturechain and consequently to the conservation of energy resources. The increase in the use of
pozzolan in place of clinker reduces energy demand in cement manufacture and mining of
limestone. Both import of grid energy and fossil fuel consumption are reduced. This is an
improvement in the usage of a commodity that is supplied by the power utility in the case of grid
energy, and supplied internally in the case of fossil fuel;- The reduction of fossil fuel consumption also results in the reduction of local air pollution;
- Energy consumption is reduced also during cement milling process because of the fact thatpozzolan is easier to grind than clinker;
- The reduced use of clinker helps in the conservation of non-renewable reserves of limestone.
- The substitution on part of limestone mining to pozzolan mining, reduces noise and vibrationpollution as the limestone mining requires the blasting of dynamite, and pozzolan mining does
not.
- The limestone quarry is located riverside, causing water pollution from the mining activities. Onthe other hand the pozzolan quarry is located far from waterfront, decreasing water pollution
There is only one registered CDM project in Jamaica. The acceptation of the CCCL project will attract
new players in the country. In entire Caribbean, composed by 13 independent countries and 11 territories
there are only 2 (two) CDM registered projects. Both of Wind Farm, one in Dominican Republic and one
in Jamaica. The CCCL project if registered as CDM, could stimulate other countries in the Caribbean
region and the Central America to manufacture blended cements, or improve the share of additives,
leading to benefits explained above.
Additionally, the incomes from the CDM will indirectly support and stimulate Caribbean Cement
Company Ltd. in keeping and improving its social and environmental programs already developed with
the local community and employees at several locations. Information is available at the company website:
http://www.caribcement.com/community/
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
5/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 5
A.3. Project participants:
>>
Table 1 - Parties involved in the project activity
Name of Party involved (*)
((host) indicates host
Party)
Private and/or public entity(ies)
project participants (*)
(as applicable)
Kindly indicate if the Party
involved wishes to be considered
as project participant (Yes/No)
Jamaica (host)
Caribbean Cement Company
Limited
(private entity)
BrazilEcoinvest Carbon SA
(private entity)
NO
(*) In accordance with the CDM modalities and procedures, at the time of making the CDM-PDD public at the stage
of validation, a Party involved may or may not have provided its approval. At the time of requesting registration, the
approval by the Party(ies) involved is required.
Note: When the PDD is filled in support of a proposed new methodology (forms CDM-NBM and CDM-NMM), at
least the host Party(ies) and any known project participant (e.g. those proposing a new methodology) shall be
identified.
A.4. Technical description of the project activity:
A.4.1. Location of the project activity:
>>
A.4.1.1. Host Party(ies):
>>Jamaica
A.4.1.2. Region/State/Province etc.:
>>Saint Andrew
A.4.1.3. City/Town/Community etc:
>>Kingston, Kingston Harbour
A.4.1.4. Detail of physical location, including information allowing the
unique identification of this project activity (maximum one page):
The project activity encompasses the cement manufacturing plant located in Kingston, Jamaica.
Kingston is the capital of Jamaica, with 652,000 inhabitants, and is located on the southeastern coast of
the island country.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
6/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 6
Project boundary encompasses the cement manufacturing plant and new additive (pozzolan) source
located 12km away from cement plant, , as well as the pozzolan transportation route.The CCCCL facility is located on the south coast of Jamaica, in Kingston Harbour. It lies within the
Kingston Metropolitan Area (KMA), with the Liguanea Plains, Kingston, Long Mountain to the west.
The Blue Mountains, to the north, Harbour View and St Thomas to the east and Kinsgton Harbour, the
Palisades and the Norman Manley International Airport to the south.
Figure 2: Map showing the location of the city of Kingston in Jamaica, and CCCL plant.
(References: 1. Wikipedia, 2. CCCL internal document, 3. Google Maps 2007)
Address and Geographical Coordinates:CCCL Plant: PO Box 448, Rockfort, Kingston 2.
17o 5748 N, 76o 4352 W.
Pozzolan Quarry: Bito/Jacksonville District, Saint Andrew Parishi
17o
5656.8 N, 76o
3929.8 W.
In Jamaican JAD69 coordinates: 286200E, 144400N
A.4.2. Category(ies) of project activity:
>>
The project activity pertains to Sectoral Scope 4 (Manufacturing industries).
2
3
1
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
7/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 7
A.4.3. Technology to be employed by the project activity:
>>
Pozzolan Blended Cement
Since the beginning of the Christian era, the Italians have successfully employed pozzolan cement,
made by grinding 2 to 4 parts of a pozzolan with 1 part of hydrate lime. A pozzolan is a material which is
not cementitious in itself but which becomes so upon admixture with lime. The early strength of a
pozzolan cement is lower than that of Ordinary Portland cement, but within a year the strengths are equal.
The advantage of this cement is that it resists the corrosive action of saline solutions and seawater much
better than does Ordinary Portland cement. (ref3).
Greater Resistance to Alkali Attack and greater resistance to Chloride Penetration: This property makes
Carib Cement Plus ideal for the tropical market and suitable for structures erected near the sea. Concrete
made with Carib Cement Plus offers greater protection to reinforced steel from Chloride attack.
Clinker Production Process
CCCL operates a dual process cement manufacturing plant, utilizing both the wet and dry process
technologies. The dry process, using preheaters and precalciners, is both economically and
environmentally preferable to the wet process because the energy consumption (3,200 kJ/kg) is
approximately half of that for the wet process.
One of the line, Kiln No.3, is a wet process plant. This kiln line consists of: two wet raw mills, Raw
Mills 2 and 3; slurry basins; slurry pumps; the rotary kiln; an ID fan; and a fabric filter to clean the kiln
exhaust gases (Figure 3).
The other line, Kiln No.4, is a dry process line and consists of: a preheater tower; the rotary kiln;preheater ID fan; dry process vertical roller mill; electrostatic precipitator (EP) to clean the exhaust gases;
and an EP fan (Figure 4).
A new line, Kiln No.5 will be constructed in the plant footprint decommissioning the Kiln No.3. This
shift is planned to finish in 2010. The new line system consists in a vertical roller mill, preheater vessels,
calciner, kiln, and clinker cooler will all use the most recent technology, thus significantly lowering
operating costs and providing the best environmental performance.
Wet process
The critical manufacturing step, called pyroprocessing, takes place in the cement kiln. The prepared
raw feed is pumped into the kiln where it is exposed to gas temperatures starting at 260C at the elevated
feed end to over 1,870C near the product discharge end. After tumbling slowly through the kiln,exothermic chemical changes in the burning zone transform the raw materials to cement clinker, a product
physically resembling grey gravel.
The production of clinker in a wet kiln requires that the solid material be heated to approximately
1,400C to 1,482C, while the gaseous material reaches a temperature of greater than 1,870C. Tricalcium
silicate is the major strength-producing constituent of cement, and its formation begins in the burning
zone at material temperatures above 1,400C. Other clinker compounds important for the performance of
Portland cement are formed by reactions that take place in the burning zone.
3 Austin, G.T.; Shreves Chemical Process Industries, 5 th edition, McGraw-Hill (1984)
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
8/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 8
Exhaust gases from the kiln are routed to the air pollution control system and then discharged to the
atmosphere through a stack.
Figure 3 - Representation of the wet process (Ref: WBCSD, 20064
)
Dry Process
Initially, the crushed raw materials (raw meal feed i.e., limestone, clay, ash, sand, and/or iron ore) enter
the raw mill to be dried and ground. A fan draws hot combustion gas from the top of the preheater tower
into the raw mill to evaporate moisture from the raw meal, as it is ground. The prepared raw meal feed is
transported to a blending silo where it is held pending introduction into the pyroprocess.
The dry process, by re-use of the hot gases for drying raw materials and with the use of the vertical
tower for calcining the raw material is very energy efficient. The rapid heating of the raw materials is the
key to the efficiency of the preheater tower. The entrainment of the raw material in the air stream and
collection of the solids through the cyclones transfers heat to the raw materials rapidly and efficiently.
The addition of fuel in the precalciner also prepares the raw material for final chemical transformation inthe rotary kiln.
4WBCSD, 2006. Formation and Release of POPs in the Cement Industry Second edition, World Business
Council for Sustainable Development http://www.wbcsdcement.org/.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
9/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 9
Figure 4 - Representation of the dry process (Ref: WBCSD, 20064)
Raw materials for both production lines are supplied by limestone and shale quarries operated by
CCCL. Together, the limestone and two types of shale supply the necessary chemical components for kiln
feed that will produce high quality clinker and cement chemistry while providing good performance in
the kilns. These three raw materials are stored in a longitudinal storage and reclaiming facility known as a
Reclaimer. Raw materials enter the storage hall on one of two conveyor belts, one for limestone, the other
for the two shales. Each has a movable, overhead tripper that stacks the raw materials into one of four
bays. A single, portal reclaimer withdraws the raw materials and deposits them on the reclaim belt. From
the reclaim belt, the raw materials may be directed onto a series of belt conveyors that transports them to
raw mill feed bins, and from there into either wet raw mills 2 and 3 or dry raw mill 4. Raw mill product
from the wet raw mills is stored in slurry basins where it is blended and stored for use in kiln system 3.
Raw mill product from Raw Mill No.4 is pneumatically conveyed to a 1200-ton capacity blending silo,
and then to a 3500-ton capacity kiln feed storage silo for subsequent use in the Kiln No.4 system.
In order to achieve the objectives of energy conservation, the clinker produced in rotary kiln is cooled
in a counter current air cooler. Typically, it is also stored for few days before it is ground in cement
grinding mills along with appropriate quantity of gypsum and other additive materials for production of
finely pulverized cement with desired fineness.
Cement Milling
The Ball / Tube millss are used for clinker grinding in cement plants. Cement mills 3 and 4 are used in
open circuit and closed circuit modes respectively.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
10/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 10
Mill 3 will be decommissioned and substituted by new Mill 5, with a more energy efficient technology.
This shift is planned to finish in 2010.
Energy
The company currently uses Bunker C, Coal and Petroleum Coke to fuel the Clinker Manufacturing
Process. Electrical power is provided by the Jamaica Public Service Company Limited, which is the
national grid supplier.
Table 2 Kiln and Mil description
Line 3 (wet) Line 4 (dry) Line 5 (dry)
Kiln Supplier Allis Chalmers Allis Chalmers F.L. Smidth
Maximum Production Capacity
(tones/day)705 1250 2800
Diameter (meters) 4 4.26 4.55
Length (meters) 120 60 54
Mill Supplier F.L. Smidth Allis Chalmers Loesche
Power (HP) 2,000 4,500 4,224
Maximum Production Capacity
(tones/h)40 for OPC 100 for OPC 110 for Carib Plus
A.4.4 Estimated amount of emission reductions over the chosen crediting period:
>>
The chosen crediting period for this project is the non-renewable crediting period of 10 years. The
estimated amount of emission reductions of the project can be seen at Table 3.
Table 3 Estimated emission reductions for the crediting period
YearsAnnual estimation of
emission reductions intonnes of CO2
2008 (from July 1st
) 153.490
2009 187.175
2010 217.262
2011 228.712
2012 237.569
2013 242.433
2014 239.114
2015 235.728
2016 232.275
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
11/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 11
2017 228.753
2018 (until June 30th ) 112.580
Total Estimated Reductions(tonnes of CO2e)
2.315.089
Total number of crediting years 10
Annual average over thecrediting period of estimatedreductions (tonnes of CO2e)
231,509
A.4.5. Public funding of the project activity:>>
There were no public funding the project activity.
SECTION B. Application of a baseline and monitoring methodology
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
project activity:
>>
Main Methodology: ACM 0005 Consolidated Baseline Methodology fro Increasing the Blend in Cement
Production, version 04, EB35
Methodological Tool: Tool to calculate the emission factor for an electricity system , version 01,
EB35
Tool for the demonstration and assessment of additionality, version 04
B.2 Justification of the choice of the methodology and why it is applicable to the project
activity:
>>
Methodology for the Blended Cement
ACM0005 is applicable to projects that increase the share of additives (i.e. reduce the share of clinker) in
the production of cement types beyond current practices in the country. Additives are defined as materials
blended with clinker to produce blended cement types and include fly ash, gypsum, slag, etc.
In the case of Caribbean Cements project, the increase in the share of additives and respective reduction
in the share of clinker in the production of cement occurs due to the use of pozzolan beyond current
practices in the country.
The methodology is applicable to this project activity because it meets the applicability conditions:
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
12/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 12
- There is no shortage of additives related to the lack of blending materials. Project participantsshould demonstrate that there is no alternative allocation or use for the additional amount of
additives used in the project activity.
Pozzolan use in CCCL has natural source and is derived from material present in volcanic ash
that is indigenous to the region where the plant is located, because of the presence of active
volcanoes in some of the neighboring islands. Pozzolan was found in the gypsum quarry owned
by Jamaica Gypsum and Quarries Limited (JGQ), a CCCL subsidiary company, which supplies
the company with the gypsum used in the manufacture of its cement Therefore, the shortage of
pozzolan is unlikely and the alternative allocation for it would be maintain the pozzolan at place,
without quarrying.
- ACM0005 is applicable to domestically sold output of the project activity plant and excludesexport of blended cement.
The production of the blended cement in the project activity is sold domestically; therefore no
export of blended cement is included. In the event that some part of the production is exported in
the future, then, this amount shall be discounted from emissions reductions calculations.
Until now, only the Ordinary Portland Cement, Type 1 is exported.
- Adequate data are available on cement types in the market.
According to ACM0005, blended cement type (BC) is defined as distinct products with
different uses, additives and additive to clinker ratios. In this project activity blended cement type
is Portland Pozzolan cement.
Until half of 2006, CCCL was the sole cement seller in Jamaica, producing only Ordinary
Portland Cement (OPC). In this way, the Bureau of Standards Jamaica (BSJ) has standard only
for OPC. When CCCL planned to start producing blended cement, CCCL uses the United States
standard American Society for Testing and Materials (ASTM) C-595 for blended Portland
cements as reference. CCCL pozzolan cement was approved by BSJ.
For Ordinary Portland Cement and rapid-hardening, BSJ has the standard JS32 Part 1: 1999
A Jamaican Standard Specification for Blended Hydraulic Cements is being developed, has
already been approved by the Standards Council 5, 6, resulting in a draft standard 7.
The draft standard made available by BSJ to CCCL, classifies the blended cement in 4 (four)
types as follows:Table 4 Blended Cement Type in Jamaica
Description Additive Range (%)Portland Blast Furnace Slag Cement 25 70
Portland Pozzolan Cement 15 - 40
Slag Modified Portland Cement Less than 25
Pozzolan Modified Portland Cement. Less than 15
5 Bureau of Standards Jamaica. Standards Development Work Pogramme. April 2006 September 2006
6 Ministry of Industry, Technology, Energy and Commerce. Performance of the Bureau of Standards, Jamaica
(BSJ) for Financial Year 2005/2006 and Focus for Financial Year 2006/2007.June 20, 2006.
7 Jamaican Standard Specifications for Blended Hydraulic Cements (Final Draft). Bureau of Standards Jamaica.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
13/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 13
Reference: Jamaican Standard Specifications for Blended Hydraulic Cements. Bureau ofStandards Jamaica (Final Draft)
For the purposes of this standard, the following definitions and terminology shall apply
PORTLAND CEMENT CLINKER
A clinker consisting predominantly of crystalline hydraulic calcium silicates
PORTLAND CEMENT
A hydraulic cement made by pulverizing Portland cement clinker, and which usually contains
calcium sulphate.
SLAG MODIFIED PORTLAND CEMENT
An intimate and uniform blend of Portland cement and finely ground granulated blast furnace
slag in which the slag constituent is kept within certain limits.
PORTLAND BLAST FURNACE SLAG CEMENT
A hydraulic cement consisting of an intimately interground mixture of Portland cement or
portland cement clinker and granulated blast furnace slag with the proportion of the slag
constituent restricted within certain specified limits.
POZZOLAN
A siliceous or siliceous and aluminous material which in itself possesses little or no cementitious
property but which, in a finely divided form, will react chemically with calcium hydroxide in the
presence of moisture at ordinary temperatures to produce compounds possessing cementitiousproperties.
POZZOLAN MODIFIED PORTLAND CEMENT
An intimate and uniform blend of Portland cement or Portland blast furnace slag cement and a
finely ground pozzolan in which the pozzolan constituent is kept within certain limits.
PORTLAND POZZOLAN CEMENT
A hydraulic cement consisting of an intimate and uniform blend of Portland cement or Portland
blast furnace slag cement and a fine pozzolan in which the proportion of the pozzolan constituent
is kept within specified limits
B.3. Description of the sources and gases included in the project boundary
The project boundary includes the cement production plant, any onsite power generation, and the power
generation in the grid. Three emission sources are considered:
- Direct emissions at the cement plant due to fuel combustion for firing the kiln and on-sitegeneration of electricity.
- Direct emissions due to calcination of limestone.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
14/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 14
- Indirect emissions from fossil fuel combustion in power plants in the grid due to electricity use at
the cement plant for: crushing and grinding the raw materials used for clinker production; drivingthe kiln and kiln fans; finish grinding of cement; and processing of additives.
Figure 5 Project Activity Boundary
Any transport related emissions for the delivery of additional additives will be included in the emissions
related to the project activity as leakage.
Emissions reductions from transport of raw materials for clinker production are not taken into account as
a conservative simplification.
Only CO2 is considered in the calculations because changes in CH4 and N2O emissions from combustion
processes and calcination are considered to be negligible and excluded because the differences in the
baseline and project activity are not substantial. This assumption is conservative and in accordance with
ACM0005.
Source Gas Included? Justification/Explanation
el Calcination of CO2 Yes Main source of emissions.
RAW MATERIAL
SUPPLY
Quarrying,Transport
RAW MATERIAL
SUPPLY
Quarrying,Transport
FUELS
PREPARATION
Crushing,Grinding, Drying
FUELS
PREPARATION
Crushing,Grinding, Drying
PYRO-
PROCESSING
Calcinations,Clinkering, Cooling
PYRO-
PROCESSING
Calcinations,Clinkering, Cooling
CEMENT
GRINDING
Clinker
Electricity from Grid
Bagging &Transport
TRANSPORT
PREPARATION
(Drying, Crushing)
FUEL
FIRING
ADDITIVES
QUARRYING
PREPARATION
Crushing, drying,grinding,
homogenizing
PREPARATION
Crushing, drying,grinding,
homogenizing
Project Boundary
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
15/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 15
CH4 No Excluded. This is conservative.limestone
N2O No Excluded. This is conservative.
CO2 Yes
Main source of emissions. Fuel firing in the clinker
production kiln and fuel consumption in the additive
transport.
CH4 NoExcluded. Emissions are considered negligible. This is
conservative.
Fossil Fuel
combustion
N2O NoExcluded. Emissions are considered negligible. This is
conservative.
CO2 YesMay be an important emission source in cement
production process as well as additives transport.
CH4 No Excluded. This is conservative.
Grid Electricity
Consumption
N2O No Excluded. This is conservative.
CO2 Yes Main source of emissions.
CH4 No Excluded. This is conservative.Calcination of
limestoneN2O No Excluded. This is conservative.
CO2 Yes
Main source of emissions. Fuel firing in the clinker
production kiln and fuel consumption in the additive
transport.
CH4 NoExcluded. Emissions are considered negligible. This is
conservative.
Fossil Fuel
combustion
N2O NoExcluded. Emissions are considered negligible. This is
conservative.
CO2 YesMay be an important emission source in cement
production process as well as additives transport.
CH4 No Excluded. This is conservative.
Proje
ctActivity
Grid Electricity
Consumption
N2O No Excluded. This is conservative.
B.4. Description of how the baseline scenario is identified and description of the identified
baseline scenario:
Identification of the baseline scenario
The baseline scenario is the most plausible scenario among all realistic and credible alternative
production scenarios for the relevant cement type that are consistent with current rules and regulations.
Project proponents identify the baseline scenario in Section B.5 through the use of Step 3 Barrier
Analysis of the latest approved version of the Tool for the determination and assessment of
additionality.
Alternative project activities that would take place are as follow:
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
16/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 16
- Alternative 1: the proposed project activity undertaken without being registered as CDM project
activity. Production of pozzolan blended cement Carib Plus;- Alternative 2: continuation of the current situation. In this scenario CCCL continues to produce
only Ordinary Portland cement, and does not use pozzolan or any other additives ;
- Alternative 3: use of other additives different from natural pozzolan. In this scenario CCCL usesother additives, such as blast furnace slag, fly ash from thermal power plants, in the production of
blended cement above the benchmark level.
Section B.5 describes the barriers that alternatives 1 and 3 faces preventing the implementation, resulting
that Alternative 2 is the most plausible baseline scenario Please, refer to Section B.5 for detailed barrier
analysis.
Definition of BBlend,y from benchmark analysis
The baseline benchmark of share of clinker per tonne of BC, BBlend,y, is defined as the lowest value among
the following:
(i) The average (weighted by production) mass percentage of clinker for the 5 highest blendcements brands for the relevant cement type in the region; If region comprises of less than 5
blend cement brands, the national market should be used as the default region; or
(ii) The production weighted average mass percentage of clinker in the top 20% (in terms ofshare of additives) of the total production of the blended cement type in the region. If 20%
falls on part of a plant, that plant is included in the calculations; or(iii) The mass percentage of clinker in the relevant cement type produced in the proposed project
activity plant before the implementation of the CDM project activity, if applicable (for
Greenfield project activity this option may be excluded).
CCCL is the sole cement manufacture as well as the sole seller in Jamaica until half of 2006. Therefore,
option iii) is used to calculate benchmark share of clinker. The lowest percentage of clinker used over the
3 most recent years before project implementation is selected and an increasing trend of 2% in the blend
is incorporated, as indicated in ACM0005 up to the limit of the regulatory/product norm in the national
market. Jamaican
According to the Draft Standard for blended cement defined by the Bureau of Standards Jamaica, the
limit for Portland Pozzolan Cement (Carib Plus) is 40% of pozzolan.
Project activity started in the beginning of 2005, after decision of the Group Budget Meeting in
December 2004. Therefore years 2002, 2003 and 2004 are used to define the baseline share of clinker.
According to ACM0005, at the renewal of the crediting period, the benchmark shall be recalculated. The
basis (between the 3 options) of the benchmark may change from the option selected during the first
crediting period.
Detailed information and calculation can be found in Section B.6.1.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
17/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 17
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered CDM project activity (assessmentand demonstration of additionality): >>
The additionality of the project activity is demonstrated and assessed using the Tool for the
demonstration and assessment of additionality Version 4.
Step 3 of the Tool is used to identify the most plausible scenario among all realistic and credible
alternatives(s) to the project activity, i.e. the baseline scenario.
Step 1. Identification of alternatives to the project activity consistent with current laws and
regulations
Sub-step 1a. Define alternatives to the project activity:
Realistic and credible alternatives are production scenarios for the relevant cement type that are consistent
with current rules and regulations available to the project participants or similar project developers. They
include the proposed project activity, the existing practice of cement production and practices in other
manufacturing plants in the region using similar input/raw materials and facing similar economic, market
and technical circumstances:
- Alternative 1: the proposed project activity undertaken without being registered as a CDM projectactivity. In this scenario CCCL uses natural pozzolan in the production of blended cement above
the benchmark level, as in the project activity;- Alternative 2: continuation of the current situation. In this scenario CCCL does not change its
production pattern, thus continuing to produce only the Ordinary Portland cement;
- Alternative 3: use of other additives different from natural pozzolan. In this scenario CCCL usesother additives, such as blast furnace slag, fly ash from thermal power plants, in the production of
blended cement above the benchmark level.
Sub-step 1b. Consistency with mandatory laws and regulations:
As there is no modification in equipments or implementation of new facilities in neither case, all the
alternatives are in compliance with all applicable legal and regulatory requirements.
Step 2. Investment analysis
Investment analysis is not undertaken.
Step 3. Barrier analysis
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
18/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 18
As showed below, the proposed project activity faces barriers that prevent the implementation of this type
of proposed project activity; and do not prevent the implementation of at least one of the alternatives.
Sub-step 3a. Identify barriers that would prevent the implementation of the proposed CDM project
activity:
The following barriers would prevent the implementation of the proposed project activity:
- Barrier 1 (research effort): to shift from an ordinary Portland cement to a blended cement,substantial research effort in the process and quality to enable the blend should be developed.
- Barrier 2 (market acceptance): the perception that high additive blended cement is of inferior
quality could happened in the early stages of the project, requiring market clarifying work, aswell as technical seminar to train masons to use correctly the blended cement.
- Barrier 3 (first of its kind). when blended cement is produced and offered to the public at firsttime, public acceptance to a new type of cement is more difficult than persuade to use a higher
blending in a public used to that type.
- Barrier 4 (technological transfer). The use of new additives of different fineness and mineralogycould lead to necessity of change in the process and also of the equipments. Intimate and uniform
blends of two or more fine materials are difficult to achieve. The manufacturer should therefore
ensure that adequate equipment and controls are provided and that the blending process is
adequate. The purchaser may also assure himself of the adequacy of the blending operation8.
- Barrier 5 (operational). In a plant that uses to produce only one type of product, an increase in the
product type could lead to change in the control of the process, to ensure not mixing theadditives, during pre-treatment, transport, production, storage and package.
- Barrier 6 (lack of additive). Different type of additive should be available to be used in theblended cement production.
Sub-step 3 b. Show that the identified barriers would not prevent the implementation of at least one of
the alternatives (except the proposed project activity):
Table 5 shows how barriers affect each one of the alternative scenarios identified in Step 1.
Table 5 - Effect of Barriers in Each Alternative Scenario
Alternative 1
Proposed project
activity without CDM
Alternative 2
Continuation of the
current situation
Alternative 3
Use of other additives
Barrier 1
Research effortPrevents implementation
Does not prevent
implementationPrevents implementation
8 Jamaican Standard Specifications for Blended Hydraulic Cements (Final Draft). Bureau of Standards Jamaica.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
19/73
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
20/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 20
At first, CCCL tried to use the pozzolan in the clinker production. However this resulted in a high
corrosion of the kiln. In addition, when the shale was replaced with pozzolan, the calibration of thechemical analyzer was not adjusted to the new material, natural pozzolan, hence results were misleading.
Other physical analyses (such as granulometry, petrography) which would help in determining its
suitability were no conclusive10
.
After the above results, tests were shifted to add the natural pozzolan to the produced clinker in the
cement mill. Numerous trials & experiments with varying percentage of natural pozzolan addition and
clinker to examine the impact on each other as well as their combined final impact on the strength
properties ofCarib Plus manufactured. CCCL also carried out numerous trials with varying fineness of
Carib Plus with numerous permutations and combinations of different pozzolan percentage additions and
different clinker qualities.
The quality is influenced by the grinding system selected. Much attention is put on the physical
characteristics of the fly ash: bulk weight, specific weight, particle distribution, particle shape, degree of
agglomeration and colour11.
The cement produced in these initial trial runs was subjected to the laboratory physical tests required in
ASTM C 595for blended hydraulic cements, such as the compression strength tests (1-day, 7-days, 28-
days). As the preparation of motor cubes required a constant flow approach, a new flow table was
purchased.
Research and Development on Pozzolan Portland cement (Carib Plus) use
Also, in the testing phase the product was provided to block manufacturers for trial use in making their
blocks. This phase lasted about four (4) months and required close liaison with the targetted.
The trials also included several controlled concrete trials to prove that the Carib Plus was compatible
with the local aggregates.
Samples of the new cement were also sent to Concrete Technologies Laboratory, U.S.A. for various
analyses, including Alkali Suplhur Ratio (ASR).
The cement is approved by the Jamaica Bureau of standards and meets the ASTM C 595 designation. A
Jamaican blended cement standard is being developed.
Barrier 2 (market acceptance) and Barrier 3 (first of its kind)
As mentioned earlier, CCCL is the sole cement manufacture in Jamaica and until 2005 was also the sole
seller of cement in entire Jamaica. In this way, Jamaica consumers have been exposed only to OPC over
the years. The market acceptability ofCarib Plus with a higher additive percent is one of the major
barriers due to prevailing practice. The customer resistance was found to be very high due to their lowawareness levels. CCCL had to overcome this barrier and to inform and clarify the market about the
quality of the high additive blended cement.
Carib Cement introduced the new blended pozzolanic cement to the Jamaican marketplace in 2005.
10 Report ofIndependent Investigation into the production and distribution of non-conforming cement by CCCL.
Ministry of Commerce, Science and Technology. June 2, 2006.
11 Stoltenberg-Hanson, E. (Norcem Cement); Fly ash cement:Production methods, materials properties and
energy savings; Norway, 1986 in Portland Cement Association: www.cement.org
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
21/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 21
As per regulatory norms cement cannot be manufactured, stored or sold in Jamaica without it being
tested and certified by BSJ, Carib Plus too had to be manufactured under strict quality control and meetinternational standards. Although of this quality assurance of product alone could not overcome the
market acceptability barrier.
Challenges Faced
There were several challenges that were faced in the introduction of this product to the market. These
were identified and actions put in place to minimize the effects, as described in the table below:
Challenge Mitigating Action
Product not well known. Market was not
familiar with blended cements. Further, there is
a wrong impression in the market that higher
addition on blended material degrades the
properties of the cement.
Extensive education programme which
consisted of seminars and product advertising
Lower early strengths, which was not
acceptable for market segments such as the
blockmaking sector.
Technical assistance provided to blockmakers
to maximize efficiency of operations and to
show them how Carib Plus could work for
them
Lower price could be construed as representing
a lower quality product.
Extensive awareness programmes and constant
dialogue to show that the product was not
inferior. Also, product was manufactured to
mimic the characteristics of Carib OPC as
close as possible so that minimum differenceswould be detected by the market.
Lighter colour of cement which represents a
weaker cement in the eyes of the Jamaican
public.
Awareness programme implemented through
seminars to communicate that the colour of
cement has no impact on strength.
Introducing a product that was in fact not
similar to a product that the market had been
requesting that of a rapid hardening cement.
Technical consultation with those players who
wanted a rapid hardening product to show that
Carib Plus could achieve desired early
strengths with better practice (better curing, use
of additives, better mix design, etc.)
The masons and builders require special training and guidance in order to use Carib Plus as building
materials. The training and guidance include measures to be adopted to ensure equal durability andworkability of OPC and Carib Plus.
The reduction in greenhouse gas emissions in the production of blended cement was highlighted as a
benefit to potential users.
Launch of Carib Cement Plus
The strategy of the launch ofCarib Plus, the pozzolan Portland cement, in an effort to maximize the
acceptance in the marketplace was to promote it as a product that had characteristics similar to that of
Carib Cement OPC, but with additional properties. These characteristics are:
1. Greater suitability for use in marine environments;
2. Lower heat of hydration thus better suited for large pours;
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
22/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 22
3. Higher sulphate resistance;
4. Higher later strengths;5. A more environmentally friendly product;
6. More economically priced than ordinary Portland cement (OPC) as the company was passingon some of the savings realized in the production process to the consumers.
CCCL took up extensive marketing, promotional activities and has dedicated its good manpower in
order to promote Carib Plus with higher additive percent in the consumer market launching a multi
fold activity. The launch was implemented in 2 phases as follows:
Stage 1 of Launch
The Carib Plus produced during the tests in 2004 was introduced to the market in the form of bulk
cement that was offered to ready mix operators. The acceptance by this segment of the market was a
slow one due to the segment comprising the more sophisticated Jamaican cement users who wereconcerned about the quality of a product with which they were not familiar. However, the cement was
found by them to be satisfactory in their applications and in conjunction with educational seminars
that were held by CCCL this market segment was able to adjust its processes to utilize this more
economical product.
Stage 2 of Launch
The second stage of the introduction of the product to the market was the launch of Carib Plus
(pozzolan Portland cement) in 42.5 Kg bags and 1.5 tonne jumbo bags. This was a more challenging
phase as Carib Plus was replacing a product that had been tried, tested and proven in the Jamaican
market for over 50 years. However, a key introductory strategy was to ensure that Carib Plus did not
totally replace the OPC, so that consumers still had a choice in the product they bought.
The introductory price of the product in bags was also slightly below that of OPC and the rationale
for this was that CCCL was passing on some of the savings in the production that were realized from
a more efficient manufacturing process.
These market acceptability, customer resistance and first of its kind barriers due to current prevailing
practice in Jamaica, would have led to not implement the project activity, with CCCL continuing to
produce only the Ordinary Portland Cement.
Barrier 4 (Technological)
The production of the blended cement resulted in very high material wear of (a) the separator parts suchas the auxiliary blades and hopper distribution table, and (b) the elevators
Effort had to be expended in doing regular patching on the elevators using salvaged auxiliary blades
(made of a hardwearing alloy) to prolong useful life, as well as on doing frequent changeovers of
auxiliary blades and hopper distribution table.
Alternative high abrasion materials had to be sourced and this was obtained from WEAR CONCEPTS
(Wearcon), imported from USA, Missouri. Previously, CCCL had to changeover the auxiliary blades and
hopper distribution table used in the making of the pozzolan cement about every 6 to 8 weeks. After the
change to the Wearcon materials, higher wear resistance of the mill and separator was obtained,
decreasing dramatically the need for frequent changeovers. With the Wearcon materials, changes in
hopper distribution table were required every 12 months on average and changes in the auxiliary blades
were required about every 4 to 5 months a significant improvement from the previous situation.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
23/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 23
Table 6 - Downtime before and after installation of high abrasion materialInstallation completed in February 2007. (Data extracted from Pareto Charts available on-site)
Month/Year Downtime duration, hrs Frequency
December/2006 21.95 4
January/2007 17.8 5
February/2007 7.3 3
March/2007 - -
April/2007 - -
Barrier 5 (Operational)
As new raw material and final product were included: (i) adaptations in the process needed to be
implemented and (ii) more stringent quality assurance and quality control procedures needed to bedeveloped and implemented.
To be able to successfully commence routine production of blended cement, the company had to
conduct initial trial production runs and internal checks on the batches of pozzolan cement produced. For
these initial trial runs, one of the cement silos had to serve as a dedicated Carib Plus cement silo, and
hence could not be used for storage of the OPC. The unavailability of this silo required careful planning
for storage of the OPC and vigilance in ensuring the right silo(s) was selected for packing or loading.
Process changes were required in the cement mill no. 4 so as to properly balance the mill circuit. For
example, the correct settings for airflow and for the separator had to be determined for the production of
the Carib Plus.
Limestone and pozzolan bin are side by side. Natural pozzolan stockpile must be controlled carefully to
not mix with the limestone stockpile. In the beginning of the Carib Plus production, pozzolancontamination occurs in the limestone, causing equipment failure and cement quality problems. Also
greater vigilance is needed to ensure correct material is transported.
For the production and dispatching of the Carib Plus, the existing silos have to be shared between
storage ofCarib Plus and OPC. Thus, there is some loss in flexibility in which silos can be assigned for
OPC storage and dispatch.
Barrier 6 (Lack of Additive)
There is no thermal plant in Jamaica operating with coal to supply fly ash to CCCL, all of them operates
with liquid or gas fuel12
. Blast furnace slag is also unavailable in a quantity to supply CCCL needs.
Initially the pozzolan was imported via ships and this presented many logistical challenges including
maintenance of adequate inventory. Subsequently, reserves of pozzolanic material were discovered at theCCCL Bull Bay quarry, and after extensive effort in proving the pozzolan reserves, these reserves were
deemed to be of adequate quality, and so the importation ceased.
Outcome of Step 3:
All barriers listed above are processes that CCCL would not need to overcome if there is no purpose in
launching a new product, the Carib Plus cement, using a new additive, the pozzolan.
12 Jamaica Public Service Company. Website: http://www.jpsco.com, accessed in 27 June 2007
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
24/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 24
The barrier analysis shows that:
(i) Alternative 3 and 1 are strongly prevented by identified barriers and for this reason are veryunlikely scenarios. These alternatives are eliminated from further consideration.
(ii) Alternatives 2 is not prevented by the barriers, remaining as the most plausible baselinescenario.
Step 4. Common practice analysis
Sub-step 4a. Analyze other activities similar to the proposed project activity:
CCCL is the sole cement manufacture in Jamaica, and is the largest supplier of the market. All other
cement sellers in Jamaica import from other countries. Other cement companies in the Caribbean Regionbesides TCL group companies, are multinational large companies as CEMEX, Holcim, Lafarge, and
could not be compared as similar activities because they do not have comparable investment climate,
access to technology, access to financing, etc.
Therefore, the CCCL project activity is not a common practice in the region.
Sub-step 4b. Discuss any similar options that are occurring:
Not applicable, because there is no similar project activities in Jamaica neither in Caribbean region.
B.6. Emission reductions:
B.6.1. Explanation of methodological choices:
>>
Step 1 Emission Reductions
Emissions reductions in year y of the project activity are calculated from equation 4, described below.
yyyyBCyBCy LBCPEBEER += 11000,, tCO2 (4)
ERy Emissions reductions in year y due to project activity 1000 tonnes/CO2
BEBC,y Baseline emissions of CO2 per tonne of BC in year y of the projectactivity. Calculated from equation (1).
tCO2/t(BC)
PEBC,y Project emissions of CO2 per tonne of BC in year y of the projectactivity. Calculated from equation (5).
tCO2/t(BC)
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
25/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 25
BCy Production of blended cement in year y of the project activity.
Monitored by project proponents.
1000tonnes (BC)
Ly Leakage due to transport of additives. Calculated from equation(2.1).
tCO2
y Proportion of additives that are not surplus. Calculated fromequation (3).
Non-dimensional
Step 2 Baseline emissions
Baseline emissions per tonne of blended cement produced are calculated from equation 1, described
below:
BCADDeleyBlendclinyBC BEBBEBE __,ker, += tCO2/t(BC) (1)
BEBC,y Baseline emissions per tonne of blended cement type. tCO2/t(BC)
BEclinker Baseline emissions per tonne of clinker in the project activity
plant. Calculated from equation (1.1).
tCO2/t(clinker)
BBlend,y Baseline benchmark of share of clinker per tonne of BC updated
for year y. Defined from Benchmark Analysis.
t(clinker)/t(BC)
BEele_ADD_BC
Baseline electricity emissions for BC grinding and preparation of
additives. Calculated from equation (1.2).
tCO2/t(BC)
Equations (1.1), (1.1.1), (1.1.2), (1.1.3) and (1.1.4)
CLNKsgeleCLNKgridelefuelfossilcalcinclin BEBEBEBEBE _____ker +++= tCO2/t(clinker) (1.1)
BEcalcin Baseline emissions per tonne of clinker due to calcinations of calcium
carbonate and magnesium carbonate. Calculated from equation (1.1.1)
below:
tCO2/t(clinker
)
( ) ( )
BSL
calcinCLNK
InMgOOutMgOInCaOOutCaOBE
+= 1000
092.1785.0tCO2/t(clinker) (1.1.1)
BEfossil_fuel Baseline emissions per tonne of clinker due to combustion of fossil fuels
for clinker production. Calculated from equation (1.1.2) below:
tCO2/t(clinker
)
( )
BSL
iBSLi
fuelfossilCLNK
EFFFFBE
=
1000
_
_ tCO2/t(clinker) (1.1.2)
BEele_grid_CLNK Baseline grid electricity emissions for clinker production per tonne of
clinker. Calculated from equation (1.1.3) below:
tCO2/t(clinker
)
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
26/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 26
BSL
BSLgridCLNKgrid
CLNKgrideleCLNK
EFBELE
BE
= 1000
__
__ tCO2/t(clinker) (1.1.3)
BEele_sg_CLNK Baseline emissions from self generated electricity for clinker production
per tonne of clinker. Calculated from equation (1.1.4) below:
tCO2/t(clinker
)
BSL
BSLsgCLNKsg
CLNKsgeleCLNK
EFBELEBE
=
1000
__
__ tCO2/t(clinker) (1.1.4)
Equations (1.2), (1.2.1), (1.2.2), (1.2.3) and (1.2.4)
ADDsgeleADDgrideleBCsgeleBCgrideleBCADDele BEBEBEBEBE __________ +++= tCO2/t(BC) (1.2)
BEele_grid_BC Baseline grid electricity emissions for grinding BC. Calculated from
equation (1.2.1) below:
tCO2/t(BC)
BSL
BSLgridBCgrid
BCgrideleBC
EFBELEBE
=
1000
__
__ tCO2/t(BC) (1.2.1)
BEele_sg_BC Baseline self generated electricity emissions for grinding BC. Calculated
from equation (1.2.2) below:
tCO2/t(BC)
BSL
BSLsgBCsg
BCsgeleBC
EFBELEBE
=
1000
__
__ tCO2/t(BC) (1.2.2)
BEele_grid_ADD Baseline grid electricity emissions for preparation of additives. Calculated
from equation (1.2.3) below:
tCO2/t(BC)
BSL
BSLgridADDgrid
ADDgrideleBC
EFBELEBE
=
1000
__
__ tCO2/t(BC) (1.2.3)
BEele_sg_ADD Baseline self generated electricity emissions for preparation of additives.
Calculated from equation (1.2.4) below:
tCO2/t(BC)
BSL
BSLsgADDsg
ADDsgeleBC
EFBELEBE
=
1000
__
__ tCO2/t(BC) (1.2.4)
Definition of BEclinker:
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
27/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 27
BEclinker is primarily defined from equation (1.1). However, considering that ACM0005 is restricted to
increase in percentage of blend only and not to efficiency improvements or fuel switching, themethodology states that in each year of the crediting period BEclinker needs to verified and redefined as
described below:
If project emissions per tonne of clinker are less than baseline emissions in year y of the crediting
period: PEclinker,y < BEclinker, BEclinkershall be substituted by the PEclinker,y in year y.
If project emissions per tonne of clinker are equal to baseline emissions in year y of the crediting
period: PEclinker,y = BEclinker, BEclinkershall be maintained as calculated by equation (1.1).
If project emissions per tonne of clinker are greater than baseline emissions in year y of the crediting
period: PEclinker,y > BEclinker, BEclinker shall be maintained as calculated by equation (1.1). In this case,
there is a possibility that project activity emissions exceed the baseline emissions and the project does
not get new credits for emissions reduction till the net balance for the project is positive.
PEclinker,y is calculated from equation (5.1).
Step 3 Project Activity Emissions
Project activity emissions per tonne of blended cement produced are calculated from equation 5,
described below:
yBCADDeleyblendyclinyBC PEPPEPE ,__,ker,, += tCO2/t(BC) (5)
PEBC,y Project emissions per tonne of blended cement type, in year y of
the crediting period.
tCO2/t(BC)
PEclinker,y Project emissions per tonne of clinker, in year y of the crediting
period. Calculated from equation (5.1) in the following pages.
tCO2/t(clinker)
PBlend,y Project share of clinker per tonne of BC in year y. Monitored by
project proponents, during the crediting period, in the project site.
t(clinker)/t(BC)
y
y
yblendBC
CLNKP =, tCO2/t(clinker)
PEele_ADD_BC,y Project electricity emissions for BC grinding and preparation of
additives, in year y of the crediting period. Calculated from
equation (5.2) in the following pages.
tCO2/t(BC)
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
28/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 28
Equations (5.1), (5.1.1), (5.1.2), (5.1.3) and (5.1.4)
yCLNKsgeleyCLNKgrideleyfuelfossilycalcinyclin PEPEPEPEPE ,__,__,_,ker, +++= tCO2/t(clinker) (5.1)
PEcalcin,y Project emissions per tonne of clinker due to calcination of calcium
carbonate and magnesium carbonate. Calculated from equation (5.1.1)
below:
tCO2/t(clinker
)
y
yyyy
ycalcinCLNK
InMgOOutMgOInCaOOutCaOPE
+=
1000
092.1785.0, tCO2/t(clinker)
(5.1.1)
PEfossil_fuel,y Project emissions per tonne of clinker due to combustion of fossil fuelsfor clinker production. Calculated from equation (5.1.2) below: tCO2/t(clinker)
( )
y
iyi
yfuelfossilCLNK
EFFFFPE
=
1000
_
,_ tCO2/t(clinker) (5.1.2)
PEele_grid_CLNK,y Project emissions from grid electricity for clinker production per tonne
of clinker. Calculated from equation (5.1.3) below:
tCO2/t(clinker
)
y
ygridyCLNKgrid
yCLNKgridele
CLNK
EFPELEPE
=
1000
_,_
,__ tCO2/t(clinker) (5.1.3)
PEele_sg_CLNK,y Project emissions from self generated electricity for clinker production
per tonne of clinker. Calculated from equation (5.1.4) below:
tCO2/t(clinker
)
y
ysgyCLNKsg
yCLNKsgeleCLNK
EFPELEPE
=
1000
_,_
,__ tCO2/t(clinker) (5.1.4)
Equations (5.2), (5.2.1), (5.2.2), (5.2.3) and (5.2.4)
yADDsgeleyADDgrideleyBCsgeleyBCgrideleyBCADDele PEPEPEPEPE ,__,__,__,__,__ +++= tCO2/t(BC)
(5.2)
PEele_grid_BC,y Project grid electricity emissions for BC grinding. Calculated from
equation (5.2.1) below:
tCO2/t(BC)
y
ygridyBCgrid
yBCgrideleBC
EFPELEPE
_,_
,__
= tCO2/t(BC) (5.2.1)
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
29/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 29
PEele_sg_BC,y Project self generated electricity emissions for BC grinding. Calculated
from equation (5.2.2) below:
tCO2/t(BC)
y
ysgyBCsg
yBCsgeleBC
EFPELEPE
_,_
,__
= tCO2/t(BC) (5.2.2)
PEele_grid_ADD,y Project grid electricity emissions for additive preparation. Calculated from
equation (5.2.3) below:
tCO2/t(BC)
y
ygridyADDgrid
yADDgrideleBC
EFPELEPE
_,_
,__
= tCO2/t(BC) (5.2.3)
PEele_sg_ADD,y Project self generated electricity emissions for additive preparation.
Calculated from equation (5.2.4) below:
tCO2/t(BC)
y
ysgyADDsg
yADDsgeleBC
EFPELEPE
_,_
,__
= tCO2/t(BC) (5.2.4)
According to ACM0005, version 3, if additional additives used in the project activity needs drying, fuel
combustion used in the drying process shall be accounted as an emission source. Therefore, emissions
resulting for drying additional additives are accounted as project emissions.
Step 4 Leakage
Leakage 1: Emissions due to fuel use for the transport of raw materials and fuels from offsite locations to
the project plant are likely to decrease due to the implementation of the project. Following ACM0005, in
order to keep emissions reductions conservative, this change is not included.
Leakage 2: Emissions due to fuel use for the transport of additives from offsite locations to the project
plant are likely to increase. These emissions are accounted as leakage, as per equations (2.1) and (2)
below:
Equations (2.1) and (2)
yyblendyblendtransaddy BCPALL = ,,_ tCO2 (2.1)
y
gridADDconveyor
add
sourceaddcons
transaddADD
EFELE
Q
TEFDTFL
+
=
__
_1000
tCO2/t(additive) (2)
Ly Leakage emissions for transport of additives. tCO2
Ablend,y Baseline benchmark share of additives per tonne of BC updated for t(slag)/t)BC)
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
30/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 30
year y.
Pblend,y Share of additives per tonne of BC updated for year y.*
t(additive)/t(BC
)
Ladd_trans Transport related emissions per tonne of additives. Calculated from
equation (2).
tCO2/t(additive)
TFcons Fuel consumption for the vehicle per kilometre. Monitored by project
proponents, in year y of the crediting period, in the project site.
kg(fuel)/km
Dadd_source Distance between the source of additive and the project activity plant.
Monitored by project proponents, in year y of the crediting period, in
the project site.
km
ELEconveyor_ADD Annual electricity consumption for conveyor system for additives.Monitored by project proponents, in year y of the crediting period, in
the project site.
MWh
Qadd Quantity of additive carried in one trip per vehicle. Monitored by
project proponents, in year y of the crediting period, in the project
site.
t(slag)
TEF Emission factor for transport fuel. Calculated from equation (7). tCO2/t(fuel)
EFgrid Grid electricity emission factor. Calculated according to methodology
ACM0002.
tCO2/MWh
- Note: The revised methodology ACM0005-Version 2 redefines Pblend,y from share of clinker per tonneof BC to share of additives per tonne of BC. This is maintained in ACM0005-Version3. Notwithstanding,
this new definition can be used only for leakage calculation, see ACM0005-Page 7-Equation 2.1. For
project emissions calculations, the old definition needs to be maintained, see ACM0005-Version 3-
Equation 5.
Leakage 3: The methodology defines that another possible leakage is due to the diversion of additives
from existing uses. As the slag used is surplus, it is expected that this source of leakage will not affect
calculations. Notwithstanding, y is calculated from equation (3) below:
yyearinusedadditivesadditionaltotal
surplusnotyyearinadditivesoftonnesxy = (3)
Only domestically sold output is considered and any export of cement produced by the project activity is
excluded in the calculation of emission reductions. Actually, part of the Carib Plus cement is exported.
Step 5 Fuel and electricity emission factors
For the calculation of emissions from grid electricity (EFgrid) the approved methodology tool Tool to
calculate the emission factor for an electricity system ver.01 is applied.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
31/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 31
There is no self-generated electricity.
Electricity Emission Factor for grid electricity
According to the tool, the grid CO2 emission is is calculated as a combined margin ( CM), consisting of
the combination of operating margin (OM) and build margin (BM) factors.
To determine the grid emission factor, according to the tool, should apply the following six steps:
STEP 1. Identify the relevant electric power system.
STEP 2. Select an operating margin (OM) method.
STEP 3. Calculate the operating margin emission factor according to the selected method.
STEP 4. Identify the cohort of power units to be included in the build margin (BM).STEP 5. Calculate the build margin emission factor.
STEP 6. Calculate the combined margin (CM) emissions factor.
Step 1. Identify the relevant electric power system
The tools states that:
For the purpose of determining the electricity emission factors, a project electricity system is
defined by the spatial extent of the power plants that are physically connected through
transmission and distribution lines to the project activity (e.g. the renewable power plant location
or the consumers where electricity is being saved) and that can be dispatched without significant
transmission constraints
Similarly, a connected electricity system, e.g. national or international, is defined as an
electricity system that is connected by transmission lines to the project electricity system. Power
plants within the connected electricity system can be dispatched without significant transmission
constraints but transmission to the project electricity system has significant transmission
constraint.
If the DNA of the host country has published a delineation of the project electricity system and
connected electricity systems, these delineations should be used. If such delineations are not
available, project participants should define the project electricity system and any connected
electricity system and justify and document their assumptions in the CDM-PDD.
The Jamaican DNA has not defined nor publicized a delineation of the system. The spatial extent for the
CCCL project activity is defined as the national grid.
CCCL purchases electricity from the Jamaica Public Service Company (JPSCo) that is involved with
the generation, purchase and distribution of electricity in whole Jamaica.
As the electric system is the national grid, and there are no subsystem, there are no electricity imports
nor exports between subsystems. Moreover, as Jamaica is an island country, there will be no
imports/exports between countries to be considered.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
32/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 32
Grid Emission factor (EFgrid) is calculated as a combined margin (EFgrid,CM,y), consisting of the
combination of operating margin (EFgrid,OM,y) and build margin (EFgrid,BM,y) factors according to thefollowing three steps.
Power plant capacity additions registered as CDM project activities should be excluded from all
calculations.
Step 2. Select an operating margin (OM) method
The calculation of the operating margin emission factor (EFgrid,OM,y
) is based on one of the following
methods:
(a) Simple OM, or
(b) Simple adjusted OM, or(c) Dispatch data analysis OM, or
(d) Average OM.
Any of the four methods can be used, however, the simple OM method (option a) can only be used if low-
cost/must-run13
resources
constitute less than 50% of total grid generation in: 1) average of the five most
recent years, or 2) based on long-term averages for hydroelectricity production.
For the proposed project activity, option (a), simple OM, has been chosen. Historically Jamaica electricity
is generated from fossil fuel, mainly natural gas and diesel oil. In 2005 more than 95% of Jamaican
generation was based on fossil fuels, demonstrating that this option could be used, see also the data
provided in Annex 3.
Ex-ante data vintage option is chosen. A 3-year generation-weighted average, based on the most recentdata available at the time of submission of the CDM-PDD to the DOE for validation.
Step 3. Calculate the operating margin emission factor according to the selected method
(a) Simple OMThe simple OM emission factor is calculated as the generation-weighted average CO
2emissions per unit
net electricity generation (tCO2/MWh) of all generating power plants serving the system, not including
low-cost / must-run power plants / units. It may be calculated:
Based on data on fuel consumption and net electricity generation of each power plant / unit
(Option
A), or
Based on data on net electricity generation, the average efficiency of each power unit and the fuel
type(s) used in each power unit (Option B), or
Based on data on the total net electricity generation of all power plants serving the system and the
fuel types and total fuel consumption of the project electricity system (option C)
Option A should be preferred and must be used if fuel consumption data is available for each power
plant / unit. In other cases, option B or option C can be used. For the purpose of calculating the
13 Low-cost/must-run resources are defined as power plants with low marginal generation costs or power plants that
are dispatched independently of the daily or seasonal load of the grid. They typically include hydro, geothermal,
wind, low-cost biomass, nuclear and solar generation. If coal is obviously used as must-run, it should also be
included in this list, i.e. excluded from the set of plants.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
33/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 33
simple OM, Option C should only be used if the necessary data for option A and option B is not
available and can only be used if only nuclear and renewable power generation are considered as low-cost / must-run power sources and if the quantity of electricity supplied to the grid by these sources is
known.
For the CCCL project, Option B2 will be used, as there is no data on fuel consumption for each
power plant.
Where:
EFgrid,OMsimple,y Simple operating margin CO2 emission factor in year y (tCO2/MWh)EG
m,yNet quantity of electricity generated and delivered to the grid by power unit m in
year y (MWh)
EFEL,m,y
CO2emission factor of power unit m in year y (tCO
2/MWh)
m All power units serving the grid in year y except low-cost / must-run power units
y Either the three most recent years for which data is available at the time of
submission of the CDM-PDD to the DOE for validation (ex ante option) or the
applicable year during monitoring (ex post option), following the guidance on data
vintage in step 2
Option B2. If for a power unit m only data on electricity generation and the fuel types used isavailable, the emission factor should be determined based on the CO
2emission factor of the fuel
type used and the efficiency of the power unit, as follows:
Where:
EFEL,m,y
CO2emission factor of power unit m in year y (tCO
2/MWh)
EFCO2,m,i,y
Average CO2emission factor of fuel type i used in power unit m in year y (tCO
2/GJ)
m,y Average net energy conversion efficiency of power unit m in year y (%)y Either the three most recent years for which data is available at the time of submission of
the CDM-PDD to the DOE for validation (ex ante option) or the applicable year during
monitoring (ex post option), following the guidance on data vintage in step 2
The data and details of the calculations are provided in Annex 3.
Step 4. Identify the cohort of power units to be included in the build margin
The sample group of power units m used to calculate the build margin consists of either:
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
34/73
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
35/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 35
Step 6. Calculate the combined margin emissions factorThis has been calculated as the weighted average of the emissions factor of the OM and the BM. The
formula that has been used to calculate this weighted average emission factor is as follows:
BMyBMgridOMyOMgridyCMgrid wEFwEFEF += ,,,,,, Equation 6
Where:
EFgrid,BM,y
Build margin CO2emission factor in year y (tCO
2/MWh)
EFgrid,OM,y
Operating margin CO2emission factor in year y (tCO
2/MWh)
wOM
Weighting of operating margin emissions factor (%)
wBM
Weighting of build margin emissions factor (%)
The emissions factors of the OM and BM in Jamaica have been weighed equally, each 50% as per the
tools as the project activity is not a wind or solar source power.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
36/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 36
B.6.2. Data and parameters that are available at validation:
Parameters related to the self-generated electricity is not included because there is no self-generation. All
electricity need is supplied by the grid.
BEcalcin (emissions from calcinations of limestone)
Data / Parameter: InCaOBSL
Data unit: %
Description: CaO content of the raw material in baseline year
Source of data used: Plant records
Value applied: Year 2004: 42.32Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Calculated from measured data as part of normal operations.
One year before project start
Any comment: None
ata / Parameter: OutCaOBSL
Data unit: %
Description: CaO content of the in baseline year
Source of data used: Plant records
Value applied: 65.10
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Calculated from measured data as part of normal operations.
One year before project start.
Any comment: None
Data / Parameter: InMgOBSL
Data unit: %
Description: MgO content of the raw in baseline year
Source of data used: Plant records
Value applied: 0.71
Justification of the
choice of data or
description of
Calculated from measured data as part of normal operations.
One year before project start.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
37/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 37
measurement methods
and procedures actuallyapplied :
Any comment: None
Data / Parameter: OutMgOBSL
Data unit: %
Description: MgO content of the clinker in baseline year
Source of data used: 1.09
Value applied: Plant records
Justification of the
choice of data ordescription of
measurement methods
and procedures actually
applied :
Calculated from measured data as part of normal operations.
One year before project start.
Any comment: None
Data / Parameter: Quantity of clinker raw material in the baseline
Data unit: Kilo tonnes
Description: Quantity of raw material used in the production of clinker.
Source of data used: Plant records
Value applied: 999.402
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Calculated from measured data as part of normal operations.
One year before project start (2004).
Any comment: None
Data / Parameter: CLNKBSLData unit: Kilo tonnes
Description: Annual production of clinker in the baseline scenario
Source of data used: Plant records
Value applied: Year 2002: 532
Year 2003: 601
Year 2004: 606
Justification of the
choice of data or
description of
Measured as part of normal operations.
Monitored 3 years before project start
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
38/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 38
measurement methods
and procedures actuallyapplied :
Any comment: None
Data / Parameter: BCBSL
Data unit: Kilo tonnes
Description: Annual production of blended cement in the baseline years
Source of data used: Plant records
Value applied: 2002: 614
2003: 601
2004: 808Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Monitored by project proponents, for three years previously to project
implementation.
Any comment: The production presented here is for the ordinary Portland cement, as there were
no blended cement productions before the project activity.
- Note: The above parameter BCBSL is not included in the monitoring plan in ACM0005 ver03,
however it is necessary to include as is used to calculate baseline emissions. Refer to equations 1.2.1 o
1.2.4, page 6 of the methodology.
- Note: The revised methodology ACM0005-Version 2 requires that Bblend,y (ID#29) is replaced by
Ablend,y (ID#29) in table for Data to monitor emissions from the project activity. This is maintained in
ACM0005-Version 3. However, Bblend,y cannot be eliminated from monitoring because this parameter is
necessary for baseline emissions calculations, see ACM0005-Version 3-Page 5-Equation 1.
BEfossil_fuel (emissions due to combustion of fossil fuels for clinker production)
Data / Parameter: FF1_BSL
Data unit: .tonnes
Description: Consumption of fossil fuel, Bunker C, for clinker production in the baseline.
Source of data used: Plant records
Value applied: 17,334
Justification of the
choice of data or
description of
measurement methods
and procedures actually
applied :
Measured as part of normal operations.
The overall consumption in the year before project activity is taken.
-
7/28/2019 Caribbean Cement_pdd 2007 12 21
39/73
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM Executive Board
page 39
Any comment: None
Data / Parameter: FF2_BSL
Data unit: .tonnes
Description: Consumption of fossil fuel, Coal, for clinker production in the baseline.
Source of data used: Plant records
Value applied: 90,860
Justification of the
choice of data or
description of
measurement methods
and procedures actuallyapplied :
Measured as part of normal operations.
The overall consumption in the year before project activity is taken.
Any comment: None
Data / Parameter: EFF1
Data unit: tCO2/tonne of fuel
Description: Emission Factor of the fossil fuel, Bunker C, used for clinker production
Source of data used: IPCC 2006
Value applied: 3.14
Justification of thechoice of d