Calvert Cliffs Unit 3 Update
Susan Gray, Power Plant Research ProgramPresentation to PPRAC
September 27, 2010
Image or Graphic
2
Calvert Cliffs Unit 3 Update
• UniStar - Constellation joint venture with EdF
• Applications– State permit – Certificate of Public
Convenience and Necessity (Maryland PSC)• Case 9127 – CPCN issued June 2009• Case 9218 – CPCN issued August 2010
– Federal permit – Combined Construction and Operating License (NRC/USACE); PPRP – State lead for NRC review; Maryland participating as an “Interested State.”
3
Calvert Cliffs Unit 3 Update
Artist’s rendering
Existing2 Units
CC3HybridCoolingTower
NewUniStarUnit(CC3)
CC3SwitchYard
BargeSlip
ExistingIntakeStructure
NewIntake
If constructed, CCU3 would be one of the largest nuclearplants in the world. Benefits would include~350 new jobs and ~$20M annual property tax payments.
4
Calvert Cliffs Unit 3 Update
• Critical Area• Forest• Streams & Wetlands• Habitats
– Oyster– Bald Eagle– Threatened/Endangered Species
• Tiger Beetle• Showy Goldenrod
• Archaeological/Historical/Cultural
• Water• Air• Traffic
Case 9127 - Impacts
~ 100 recommendedCPCN conditions
5
Calvert Cliffs Unit 3 Update
Other Case 9127 CPCN Conditions:• Site Redress Plan• Significant reduction or elimination of ground
water use from CCNPP 1 & 2 from CCU3 Desalination Plant (excess capacity)
• Analyze alternatives for the unanticipated event of the unavailability of the desalination plant
• CPCN reopened if Nuclear Regulatory Commission (NRC) conditions conflict with CPCN conditions– Draft EIS issued 04/2010: Consistent with CPCN Case
9217; did not address changes stemming from Case 9218. PPRP submitted comments to NRC 07/2010 (no major issues).
6
Calvert Cliffs Unit 3 Update
Artist’s rendering
Case 9127 CCU3 Air Permit
Apply Best AvailableControl Technology:
Cooling Towers(minimize salt drift by drift eliminators & limitson total dissolved solids)
Emergency andStation BlackoutDiesel Generators(minimize emissionsby use of low-sulfurdiesel fuel & limitson operation)
7
Calvert Cliffs Unit 3 Update
Case 9218 Changes to the Air Permit:• minor changes to the layout or stack
design of the air emissions• add two types of new air emission
sources – two emergency fire water pumps and two sponge media blasting units
8
Calvert Cliffs Unit 3 Update
USACE & MDE Ongoing Evaluations:Streams & Wetlands
~12 acres wetlands, 30 acres of wetland buffersand 8,000 linear feet of stream beds impacts willbe mitigated by in-kind creation, restoration orenhancement elsewhere on the property.
9
Calvert Cliffs Unit 3 Update
• CPCN/CAC Approvals – done• USACE/MDE Review on Tidal & Nontidal
Wetlands – in sync with NRC schedule• NRC process
– Design Certification– Final EIS (02/2011)– Final SER (07/2012)– COL w/ITAAC
NRC jurisdiction:Nuclear Waste Disposal
Radiological Emergency PlanningDecommissioningRisk Assessment
Design Safety AnalysisSite Specific Safety and Security Analyses